Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis...

24
Steven Farrah Senior Thesis Presentation Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management 4/12/2010

Transcript of Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis...

Page 1: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Steven FarrahSenior Thesis PresentationSenior Thesis PresentationVoorhees Replacement FacilityVoorhees, NJ

Steven Farrah Construction Management 4/12/2010

Page 2: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project OverviewII LEED/S t i bilit St dII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Page 3: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Project Overview Project Team

Virtua HealthFunction: Hospitalj

II. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

Virtua Health

owner

HGA

Architect/Engineers

Hammes Company

Program Manager

Turner Construction

CM@ Risk

CSRI Safety Services

Owners Safety Rep

Size: 675,000 SF

Height: 8 Stories

Delivery Method: CM @ Risk w/GMP ContractVI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Cives Steel

Structural Steel

E.J. Deseta (Bed Tower)

Advantage (Ancillary)

HVAC

Palmieri (Bed Tower)

Scalfo (Ancillary)

Electrical

Subcontractors

Cost: 323 Million Construction Costs

Construction Schedule: March 2008 – March 2011

Page 4: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Project Location Project Location

Point AjII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

Point A(Current Hospital)

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Point B(Replacement

Hospital)

Page 5: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Background/Goals

GOALSjII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Voorhees Replacement FacilityIs Not Currently Pursuing a LEED Rating

1. Evaluate the Designed Voorhees ReplacementFacility to Determine What LEED Points areCurrently Being Achieved.

2. Conduct a Point-by-Point Cost Analysis of Points Not Being Obtained By the Current Design.

CertificationCertified

Points Required40 - 49VI. Acknowledgements

VII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

3. Determine the Cost to Reach Each LEED Certification in the Voorhees Replacement Facility

SilverGoldPlatinum

50 - 5960 - 7980 - 110

Page 6: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Sustainable Sites

Points Used in Each LEED Rating

e B

uildin

g

fie

d

r

LEED RatingPoints Included In Base Building

Points Obtained at a

Cost

Additional Cost of Points

Section Total Points

Sustainable Sites

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Possible Points: 26

Prereq 1 Prerequisite

Credit 1 Site Selection 1

Credit 2 5

Credit 3 1

Credit 4.1 6

Credit 4.2 1

Credit 4.3 3

Credit 4.4 2

Alternative Transportation—Public Transportation Ac

Alternative Transportation—Bicycle Storage and Cha

Alternative Transportation—Low-Emitting and Fuel-E

Alternative Transportation—Parking Capacity

Ba

se

Ce

rtif

Silve

r

Go

ld

Sustainable Sites

Construction Activity Pollution Pre

Development Density and Community Connectivity

Brownfield Redevelopment

Cost PointsBase Building 9 - -$ 9

Certified 9 6 14,663.00$ 15Silver 9 6 14,663.00$ 15Gold 9 7 1,483,200.00$ 16

Platinum - - - -

• Site Selection

B ilding FootprintVI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Credit 4.4 2

Credit 5.1 1

Credit 5.2 1

Credit 6.1 1

Credit 6.2 1

Credit 7.1 1

Credit 7.2 1

Credit 8 1

Heat Island Effect—Roof

Light Pollution Reduction

lte at ve a spo tat o a g Capac ty

Site Development—Protect or Restore Habitat

Site Development—Maximize Open S

Stormwater Design—Quantity Cont

Stormwater Design—Quality Contro

Heat Island Effect—Non-roof

• Building Footprint

• Parking Footprint

Page 7: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Water Efficiency

din

g

Points Included Points

Additional Cost Section

Water Efficiencyj

II. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Possible Points: 10

Prereq 1 Prerequisite

Credit 1 2 to 4

Reduce by 50% 2

4

Credit 2 2

Water Efficient Landscaping

No Potable Water Use or Irrigation

Innovative Wastewater Technologi

Points Used in Each LEED Rating

Ba

se

Bu

il

Ce

rtif

ied

Silve

r

Go

ld

Water Efficiency

Water Use Reduction—20% Reducti

LEED RatingPoints Included In Base Building

Obtained at a Cost

Additional Cost of Points

Total Points

Base Building 0 - -$ 0Certified 0 4 85,225.00$ 4

Silver 0 4 85,225.00$ 4Gold 0 4 85,225.00$ 4

Platinum - - - -

• Water Efficient FixturesVI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Credit 3 2 to 4

Reduce by 30% 2

Reduce by 35% 3

Reduce by 40% 4

Water Use Reduction

• Rainwater/Grey Water Collection Systems

• Use Plants Native to Area

Page 8: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Energy & Atmosphere

LEED RatingPoints Included In Base Building

Points Obtained at a

Cost

Additional Cost of Points

Section Total Points

Base Building 7 - -$ 7

Energy & Atmosphere

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Base Building 7 - -$ 7Certified 7 0 -$ 7

Silver 7 5 285,457.00$ 12Gold 7 9 6,195,757.00$ 16

Platinum - - - -

• Energy Modeling

• Renewable EnergyVI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

• Renewable Energy

• Commissioning

Page 9: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Materials & Resources

Points Used in Each LEED Rating

ase B

uild

ing

ert

ifie

d

lve

r

old

LEED RatingPoints Included In Base Building

Points Obtained at a

Cost

Additional Cost of Points

Section Total Points

B B ildi 1 $ 1

Materials & Resources

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Possible Points: 14

Prereq 1 Prerequisite

Credit 1.1 1 to 3

Reuse 55% 1

Reuse 75% 2

Reuse 95% 3

Credit 1.2 1

Credit 2 1 to 2

1

2

Credit 3 Materials Reuse 1 to 2

Reuse 5% 1

Building Reuse—Maintain Existing Walls, Floors, and R

Construction Waste Management

50% Recycled or Salvaged

75% Recycled or Salvaged

Building Reuse—Maintain 50% of Interior Non-Structu

B Ce

Sil

GoMaterials and Resources

Storage and Collection of Recyclabl

Base Building 1 - -$ 1Certified 1 0 -$ 1

Silver 1 4 432,000.00$ 5Gold 1 6 972,000.00$ 7

Platinum - - - -

• Construction Waste Management/Recycling

• Recycled ContentVI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Reuse 10% 2

Credit 4 Recycled Content 1 to 2

10% of Content 1

20% of Content 2

Credit 5 Regional Materials 1 to 2

10% of Materials 1

20% of Materials 2

Credit 6 1

Credit 7 Certified Wood 1

Rapidly Renewable Materials

• Recycled Content

•Regional Materials

Page 10: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Indoor Air Quality

Points Used in Each LEED Rating

se

Build

ing

tifi

ed

ve

r

d

LEED RatingPoints Included In Base Building

Points Obtained at a

Cost

Additional Cost of Points

Section Total Points

B B ildi 12 $ 12

Indoor Air Quality

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Possible Points: 15

Prereq 1 Prerequisite

Prereq 2 Prerequisite

Credit 1 1

Credit 2 1

Credit 3.1 1

Credit 3.2 1

Credit 4.1 1

Credit 4.2 1

Credit 4.3 1

Environmental Tobacco Smoke (ETS) Control

Low-Emitting Materials—Flooring Sy

Outdoor Air Delivery Monitoring

Construction IAQ Management Plan—During Construc

Construction IAQ Management Plan—Before Occupan

Low-Emitting Materials—Adhesives and Sealants

Low-Emitting Materials—Paints and Coatings

Ba

s

Ce

rt

Silv

Go

ld

Indoor Environmental Qualit

Minimum Indoor Air Quality Perform

Increased Ventilation

Base Building 12 - -$ 12Certified 12 0 -$ 12

Silver 12 0 -$ 12Gold 12 0 -$ 12

Platinum - - - -

• Outside Air / Ventilation

• Indoor Air Quality Plan VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Credit 4.4 1

Credit 5 1

Credit 6.1 1

Credit 6.2 1

Credit 7.1 1

Credit 7.2 1

Credit 8.1 1

Credit 8.2 1

Low-Emitting Materials—Composite Wood and Agrifib

Indoor Chemical and Pollutant Source Control

Controllability of Systems—Thermal Comfort

Daylight and Views—Daylight

Daylight and Views—Views

Thermal Comfort—Design

Thermal Comfort—Verification

Controllability of Systems—Lighting • Low-Emitting Materials

• Controllability of Lighting & Thermal Comfort

Page 11: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

LEED/Sustainability StudyI. Sustainable Sites

LEED/Sustainability Study Conclusions

Soft Cost Estimates

Cost Decription% of Construction

CostTotal Construction

CostCost to Project• The current design of the Voorhees Replacement j

II. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. Water EfficiencyIII. Energy & AtmosphereIV. Materials & ResourcesV. Indoor Air QualityVI. Conclusions

Design Costs 0.50% $323,000,000 $1,615,000

Documentation & Application Fees

0.50% $323,000,000 $1,615,000

Energy Modeling 0.10% $323,000,000 $323,000

Total $3,553,000

TOTALS

LEED RatingTotal Additional

Cost% Construction Cost Increase Point Range Point Total

The current design of the Voorhees Replacement Facility is achieving 30 LEED points

• Start Early

• A LEED rating can be obtained at little cost to the project if the owner sets the standard early.

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Cost Cost Increase

Base Building $ - - - 30

Certified $ 3,652,888.00 1.118% 40-49 42

Silver $ 4,370,345.00 1.335% 50-59 51

Gold $ 12,289,182.00 3.665% 60-79 60

Platinum - - 80-110 -

Page 12: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Patient Room LED LightingI. Lighting Breadth

Patient Room LED Lighting Background/Goals

GOALSjII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

g gII. Mechanical BreadthIII. Cost AnalysisIV. Conclusions

1. Redesign a Typical Patient Room to Utilize LED Lighting In Place of Fluorescent Lighting

2. Determine Effect of Lighting Change on the Mechanical System

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

3. Evaluate the Life Cycle of the LED Lit Room

(http://www.ptrenergy.com/images/chart.jpg)

Page 13: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Patient Room LED LightingI. Lighting Breadth

Patient Room LED Lighting Lighting Breadth

Required Lighting Levels•Reading – 30 Footcandlesj

II. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

g gII. Mechanical BreadthIII. Cost AnalysisIV. Conclusions

Ligh

ting

vel L

ight

ing

g•Exam Level – 50 Footcandles

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Exam

Lev

el

Rea

ding

Le v

Cree LR24 Halo 6” LED Downlight

Page 14: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Patient Room LED LightingI. Lighting Breadth

Patient Room LED Lighting Lighting Breadth

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

g gII. Mechanical BreadthIII. Cost AnalysisIV. Conclusions

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Page 15: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Patient Room LED LightingI. Lighting Breadth

Patient Room LED Lighting Mechanical Breadth

Total Fluorescent Room Wattage – 212WTotal LED Room Wattage - 142W Total CFM Reduction For All Patient Rooms = 109,200

Mechanical Equipmentj

II. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

g gII. Mechanical BreadthIII. Cost AnalysisIV. Conclusions

Reduction in BTUs/hr Per Room = 364 BTUs/hr

Total Reduction in BTUs/hr = (364 BTUs/hr-room)x(300 patient rooms) = 109,200 BTUs/hr

g Total CFM Reduction For All Patient Rooms 109,200 BTUs/hr / 20° / 1.1 = 4964 CFM

There Is No Mechanical Equipment Cost Savings Due to Equipment Downsizing

Electricity SavingsChange in Load on Chillers = (109 200 BTUs/hr) / VI. Acknowledgements

VII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Change in Load on Chillers (109,200 BTUs/hr) / (12,000BTUs/Ton) = 9.1 Tons

Cost Savings/Year = (0.6kW/Ton)x(9.1Tons)x(2000hrs)x ($0.1307/kWhr) = $1,427.00/Year

Page 16: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Patient Room LED LightingI. Lighting Breadth

Patient Room LED Lighting Cost Analysis

$‐

LED vs Fluorescent Cumulative Cash Flow

LED vs Fluorescent Life Cycle AnalysisVoorhees Replacement Facility

Average Number of Hours of Use Per Day 12Price of Electricity (Dollars/per kWH) 0.1307

Existing Fluorescent Lighting LED Replacement LightingjII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

g gII. Mechanical BreadthIII. Cost AnalysisIV. Conclusions

$(300,000)

$(250,000)

$(200,000)

$(150,000)

$(100,000)

$(50,000)0 5 10 15 20 25

Total Luminaire Cost $ 78,000 $ 130,500 $ 302,400 $ 131,700

Total Controls Cost N/A N/A $ 90,000

Total Initial Cost $ 208,500 $ 524,100

Total Annual Energy Costs $ 36,065 $ 18,520

Average Annual Lamp Maintenance Cost

$ 5,518 $ 35,478

Luminaire Description DF 11 MF 13 HALO CREE

Energy Savings from LED per year

$ 17,546

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

$(500,000)

$(450,000)

$(400,000)

$(350,000)Maintenance Cost

Extra Average Maintenance Cost for LED $ (29,959)

Total savings per year $ (10,986)

Mechanical Savings per year

$ 1,427

Page 17: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Patient Room LED LightingI. Lighting Breadth

Patient Room LED Lighting Conclusions

$‐

LED vs Fluorescent Cumulative Cash Flow

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

g gII. Mechanical BreadthIII. Cost AnalysisIV. Conclusions

• Rooms can be designed using LED downlighting

• Rooms designed using LED lighting may see a reduction in mechanical energy costs.

• LED lighting presents too much of an initial investment and replacement cost to produce a cost savings over

$(300,000)

$(250,000)

$(200,000)

$(150,000)

$(100,000)

$(50,000)0 5 10 15 20 25

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

and replacement cost to produce a cost savings over time.

$(500,000)

$(450,000)

$(400,000)

$(350,000)

Page 18: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Bed Tower Schedule AnalysisI. Overview

Bed Tower Schedule Analysis Background/Goals

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. ScheduleIII. Conclusions GOALS

1. Create a Short Interval Schedule for the Fit-Out of the Bed Tower to Accelerate the Project Schedule.

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Page 19: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Bed Tower Schedule AnalysisI. Overview

Bed Tower Schedule Analysis Overview

Patient Room Pairing 1. Rough-in in wall plumbing2. Rough-in in wall duct drops3 R h i i ll di l

15. Install millwork16. Install plumbing/bathroom fixtures17 I t ll t VCT fl i d b

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. ScheduleIII. Conclusions

3. Rough-in in wall medical gas4. Rough-in in wall electrical5. Rough-in in wall low-voltage wiring6. Insulate, drywall and tape partitions7. Frame drywall ceilings8. Electrical work in drywall ceilings9. Ductwork in drywall ceilings10. Drywall and tape drywall ceilings11 Prime and paint 1 coat walls and

17. Install carpet, VCT flooring and base18. Install grilles and diffusers19. 2nd and final coat of paint20. Install doors, hardware and interior

glazing21. Drop in acoustical ceiling tile into grid22. Cut in sprinkler heads

(ACT and drywall)23 Finish and install low voltage devicesVI. Acknowledgements

VII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

11. Prime and paint 1 coat walls and drywall ceilings

12. Install acoustical ceiling tile grid13. Drop in and install light fixtures14. Install all ceramic tile floors and

partial walls

23. Finish and install low voltage devices24. Finish and install medical gas trim

plates and labels25. Finish and install electrical devices

and trim plates

Page 20: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Bed Tower Schedule AnalysisI. Overview

Bed Tower Schedule Analysis Analysis

Short Interval Schedule Start Short Interval Schedule Finish

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. ScheduleIII. Conclusions

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Page 21: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Bed Tower Schedule AnalysisI. Overview

Bed Tower Schedule Analysis Conclusions

Original Bed Tower Fit-Out General Conditions/jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

II. ScheduleIII. Conclusions

O g a ed o e OuCompletion Date: December 23rd, 2010

Short Interval Schedule BedTower Fit-Out Completion Date: November 2nd, 2010

Schedule Reduction: 35 Work Days

General Conditions/Requirements Cost/Month: $301,950.00/Month

General Conditions Savings = ($301,950.00/calendar month) x(1.75 calendar months) = $528,412.00VI. Acknowledgements

VII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Schedule Reduction: 35 Work Days1.75 Calendar Months

Page 22: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Conclusions Conclusions

LEED/Sustainability Study Patient Room LED Lighting• Rooms can be designed using LED downlighting• The current design of the Voorhees Replacement Facility is

l d hi i 30 LEED i t

I. Patient Room LED Lighting

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements Bed Tower Schedule Analysis

g g g g• Rooms designed using LED lighting may see a reduction in mechanical energy costs.• LED lighting presents too much of an initial investment and replacement cost to produce a cost savings over time.

already achieving 30 LEED points• Start Early• A LEED rating can be obtained at little cost to the project if the owner sets the standard early.

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

• Schedule Reduction: 35 Work Days or 1.75 Calendar Months

• General Conditions Savings = ($301,950.00/calendar month)x(1.75 calendar months) = $528,412.00

Page 23: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Presentation OutlineI. Project Overview

Acknowledgements Acknowledgements

Penn State Architectural Engineering Faculty

HGA Architects & EngineersMike Torine

Haines &KibblehouseTom Spenillo

E.J. Deseta CompanyS B kHGA Architects & Engineers

Mike TorineWayne JohnsonRD RuffinChad O’DonnellPaul GruettnerPat Hunt

jII. LEED/Sustainability StudyIII. Patient Room LED Lighting

I. Lighting BreadthII. Mechanical Breadth

IV. Bed Tower Schedule AnalysisV. ConclusionsVI. Acknowledgements

Engineering FacultyChris MagentProfessor ParfittProfessor HollandCorey Wilkinson

Turner ConstructionBill S anson

Mike TorineWayne JohnsonRD RuffinChad O’DonnellPaul GruettnerPat HuntJim KoehlerMichael Woodson

Tom SpenilloHamada Inc.Joe BruskiThomas Building GroupMichael GejerHispanic Ventures

Sean BrooksMajek Fire ProtectionGeorge DoughertyFalasca MechanicalWally CopestickJohnson ControlsK l B

Pat HuntJim KoehlerMichael Woodson

VI. AcknowledgementsVII. Questions & Answers

Steven Farrah Construction Management 4/12/2010

Bill SwansonJoel MinerJeremy KlingerChris McCrae

Michael Woodson Hispanic VenturesLen SpatoccoSwisslogTranslogicJeff Mazur

Kyle BonnerPalmieri ElectricSharon Ashbridge

Page 24: Steven Farrah Senior Thesis Presentation · 2010. 4. 14. · Steven Farrah Senior Thesis Presentation Voorhees Replacement Facility Voorhees, NJ Steven Farrah Construction Management

Questions & AnswersQuestions & Answers

Steven Farrah Construction Management 4/12/2010