Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing...
-
Upload
malcolm-cannon -
Category
Documents
-
view
213 -
download
0
Transcript of Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing...
![Page 1: Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing up in west and east bores COT Loose cables SVX](https://reader036.fdocuments.in/reader036/viewer/2022082816/56649ccf5503460f9499b7af/html5/thumbnails/1.jpg)
1Steve Hahn, CDF Meeting - October 7, 2004
CDF Operations SummaryCDF Operations Summary
• Shutdown progress Work finishing up in west and east bores
• COT Loose cables
• SVX Separation of SVX & COT volumes working as expected Problems seen initially due to miscalculation of dewpoint
CPR/CCR Run 2B upgrade finishing inside SW arch• Aggressive schedule of an arch each two weeks (end of 1st week for
SW)—actually, squeezing to even less iFIX progress
• Long wait for security committee to approve new Windows XP PCs• 3/10 PCs replaced last week, one per day, with minimal problems
VNODE1 & VNODE2 remarkably faster Waiting for new ORACLE client to resurrect ICICLE
• COT PC replaced this week, two more in queue
CDF
![Page 2: Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing up in west and east bores COT Loose cables SVX](https://reader036.fdocuments.in/reader036/viewer/2022082816/56649ccf5503460f9499b7af/html5/thumbnails/2.jpg)
2Steve Hahn, CDF Meeting - October 7, 2004
CDF Operations SummaryCDF Operations Summary
Electronicsproblem
Electronicsproblem Light OK
SW SE
Note 25% more light in SW arch
due to 50 cm less fiber
![Page 3: Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing up in west and east bores COT Loose cables SVX](https://reader036.fdocuments.in/reader036/viewer/2022082816/56649ccf5503460f9499b7af/html5/thumbnails/3.jpg)
3Steve Hahn, CDF Meeting - October 7, 2004
CDF Operations SummaryCDF Operations SummaryCDF
Light OK
SW SE
![Page 4: Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing up in west and east bores COT Loose cables SVX](https://reader036.fdocuments.in/reader036/viewer/2022082816/56649ccf5503460f9499b7af/html5/thumbnails/4.jpg)
4Steve Hahn, CDF Meeting - October 7, 2004
CDF Operations SummaryCDF Operations SummaryCDF
SW SE
CP2
![Page 5: Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing up in west and east bores COT Loose cables SVX](https://reader036.fdocuments.in/reader036/viewer/2022082816/56649ccf5503460f9499b7af/html5/thumbnails/5.jpg)
5Steve Hahn, CDF Meeting - October 7, 2004
CDF Operations SummaryCDF Operations Summary
• Schedule COT baggies up tonight; silicon cooldown starts tomorrow Move SW arch in Friday 0630; move out NW arch
• Problems with many blown Café card fuses (spares low) PMT HV and signal cables plugged and unplugged on SE arch No none incidents on SW arch, but suspect same problem Need to test more frequently to catch these problems earlier
While old CPR/CCR chambers stripped Monday, Tuesday:• Fileserver moved back all Monday—no DAQ• CSL upgraded• Motor generator maintenance starting Tuesday; short
shutdowns on 3/4 MGs for brush replacements Friday, October 15
• Close west endplug, start prep for west low quad support• Start flammable gas to muon chambers
CDF
![Page 6: Steve Hahn, CDF Meeting - October 7, 20041 CDF Operations Summary Shutdown progress Work finishing up in west and east bores COT Loose cables SVX](https://reader036.fdocuments.in/reader036/viewer/2022082816/56649ccf5503460f9499b7af/html5/thumbnails/6.jpg)
6Steve Hahn, CDF Meeting - October 7, 2004
CDF Operations SummaryCDF Operations Summary
• Schedule (continued) Monday, October 18: Start west low quad support
installation; west muon wall closed October 19–22: Close east endplug Friday, October 22: Close NW arch & north muon wall; move
support and forklift to east side Monday October 25: Open north muon wall & NE arch October 26–28: Finish east low quad support installation November 5 or 8: Close NE arch; CPR/CCR work done November 8–15
• Solenoid checkout• COT Ar/CO2 field on tests with no beam
November 22: Shutdown done
CDF