Stephen Norum LCLS Oct. 12, 2006 1 LCLS Machine Protection System Outline Overview of interim MPS...
-
Upload
vivian-wheeler -
Category
Documents
-
view
217 -
download
0
description
Transcript of Stephen Norum LCLS Oct. 12, 2006 1 LCLS Machine Protection System Outline Overview of interim MPS...
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20061
LCLS Machine Protection System
OutlineOverview of interim MPSUpdate on the interim MPS progressBurst and single shot modesInterim MPS scheduleFull MPS
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20062
Overview of Interim MPS
Using existing infrastructure (1553 MPS)Adding new signals and devicesInterim MPS will be used for gating beam
Single Shot ModeBurst Mode
MPS algorithm is responsible for both LCLS and CID beamPockels cell and MPS mechanical shutter limit laser rate on cathode
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20063
1553 MPS
MPS device faults are input to Latching Digital Input Modules (LDIMs)Algorithms running in local processors (APs) determine the max allowed rate based on these faultsThe supervisor (SP00) chooses the lowest rate from the APs for the beam’s max allowed rate
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20064
Status
LDIM Assignments and MPS DatabaseLDIM channels have been assignedVMS database has been built from these assignments
AlgorithmAlgorithm processor code is near completion and is being reviewed
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20065
Interim MPS Devices
Vacuum valves/statusBeam stoppersMagnet power suppliesProfile monitorsStandalone toroid, toroid comparatorsFlow switches and temperature monitorsJoule meterTone interrupt unit (TIU)Protection Ion Chambers (PICs)
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20066
Interesting Additions
MPS responsible for both CID and LCLS beamBAS II stoppers are used to isolate LCLSWhile BAS II stoppers are in
TIU is ignored as there are no devices between BX01 and TD11Algorithm rate limits LCLS beam only
While BAS II stoppers are outTIU works regularly—will zero rate all beams on any TIU faultAlgorithm rate limits both CID and LCLS beam
Algorithm switches modes automatically
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20067
Interesting Additions
Burst and Single Shot ModesRequired for profile monitor acquisitionBurst mode—create a specified number of pulses at a requested rateSingle shot—create a single pulseBoth modes are preceded and followed by no beam
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 20068
Burst Mode
ImplementationEPICS IOC obtains three pieces of information
Number of pulses in burstBurst Mode—a request to go enter burst modeBurst Request—the request to allow beam
An event receiver (EVR) provides timing data to IOCIOC uses the timing data to count pulsesWhen number of requested pulses have been created, the IOC drops the burst requestTiming is handled by IOC, rate limiting logic is handled by MPS algorithm
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200610
Burst Mode Logic
Burst Mode Burst Request Rate (Hz)
0 0 –
0 1 –
1 0 0
1 1 Burst Rate
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200611
Single Shot Mode
Implementation similar to Burst Mode“Counting” is done in hardwareA hardware flip-flop is set when single shot mode is requestedWhen the single shot request is made, a pulse is createdThe trigger for this pulse clears the flip-flop, ensuring only one pulse is created
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200612
Interim MPS Schedule
Creation Installation Testing CertificationSoftware SLC Database
- Device List Complete Complete Oct 13 N/A - LDIM Assignment Complete Complete Oct 13 N/A - Electrical Interconnect Complete Complete Complete N/AMPS Algorithm Oct 23 Oct 24 Dec 07 Oct 23IOC - Burst mode Nov 15 Nov 23 Nov 22 Nov 22 - Single shot Oct 11 Oct 13 Oct 11 N/A - Digital IO Database Oct 18 Oct 20 Oct 20 N/A
Date of Completion (2006)
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200613
Interim MPS ScheduleProcurement Installation Testing Certification
Hardware Linac PLIC - PLIC Processor Nov 01 Nov 03 Nov 06 N/APIC - Power supply Complete Complete Complete Complete - PICP Complete Complete Complete Complete - PICs Complete Dec 06 Nov 01 N/AUtilities - Gas Complete Dec 06 Dec 07 N/AIOC - VME Crate Complete Oct 18 Oct 16 N/A - EVR Complete Oct 18 Nov 22 N/A - Transition Module Complete Oct 18 Oct 16 N/A - Terminal Block Complete Oct 18 Oct 16 N/A - IOC Cable Complete Oct 18 Oct 16 N/A - IP Carrier Complete Oct 18 Oct 16 N/A - IP 445 Complete Oct 18 Oct 16 N/A - IP 440 Complete Oct 18 Oct 16 N/AMPS Electronics Oct 11 Oct 13 Oct 11 Oct 11Shutter - Shutter Controller Complete Nov 15 Complete N/APockels Cell - Pockels Cell AND Gate Oct 25 Nov 03 Nov 01 N/AFaston Complete Complete Complete N/A24V Power Supply Complete Oct 13 Oct 11 Oct 11LDIM Complete Complete Complete N/A
Date of Completion (2006)
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200614
Full MPS Requirements
Strict timing requirement—respond to MPS faults before next 120 Hz pulse (8.3 ms)Multiple rate limits determined by fault locationAutomatic Recovery—if requested, raise beam to before-fault rate after a fault is correctedFault logic based on how quickly an integrated loss threshold is exceeded
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200615
Simplified MPS Device Layout
(Note: Only PICs and PLICs shown. Many more devices are input to the MPS)
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200616
Full LCLS MPS
New hardware developed by MRFModified VME-EVR-200 (VME-EVR-235)Larger FPGA (XC2VP20)2× logic cells, 1.5× IO, 2× PPC coresAdditional SFP transceiver and clock circuit10/100 MAC/PHYMMC Slot for Atmel Flash Card128 MB SDRAM
Board has been ordered
Stephen Norum
LCLS MPS [email protected]
Oct. 12, 200619
Full LCLS MPS
MPS hardware provides a high-speed communication path back to EVG (2.5 Gbps)The MPS’s mitigation path is independent of the EVG and MPG, allowing the MPS to quickly respond to faultsDesign overview has been presented to small groupConceptual design review scheduled for November 9th