Steel Mill Industrial Training

51
INDUSTRIAL TRAINING AT AJAOKUTA STEEL MILL NIGERIA TRAINING REPORT ON ACTIVITIES BETWEEN 12TH JULY AND 9TH OF AUGUST SUBMITTED BY: OSUDE BENEDICT

description

A report of my industrial training in The ajaokuta steel mill of Nigeria

Transcript of Steel Mill Industrial Training

Page 1: Steel Mill Industrial Training

INDUSTRIAL TRAINING

AT

AJAOKUTA STEEL MILL

NIGERIA

TRAINING REPORT ON ACTIVITIES BETWEEN

12TH JULY AND 9TH OF AUGUST

SUBMITTED BY:

OSUDE BENEDICT

SUBMITTED TO:

METIN BILIN

Page 2: Steel Mill Industrial Training

2

ABSTRACT

The Ajaokuta Steel Company is one of the steel mills, located I the western part of Nigeria and it was established 1979 and charged with the task of constructing and operating an integrated iron and steel plant. Ajaokuta Steel plant was planned to be built in three stages. The first stage of 1.3 million tonnes to produce long steel products was followed by immediate expansion to 3.6 million tonnes for the production of 1.3 million tons of flat products in addition to the long products. The third stage is the expansion of the complex to produce 5.2 million tons of various types of finished and semi-finished steel products including heavy plates and heavy sections. The plant is designed such that it can be expanded up to 10 million tonnes eventually subject to demand. The steel complex is almost completed.

Page 3: Steel Mill Industrial Training

3

ACKNOWLEDGEMENT

First and foremost a special thanks to almighty God for his abundant blessings all through the training.

To the national metallurgical center, Jos. A special thanks to you to for accepting my application for an internship in the steel.

To my supervisor and my very own personal assistant who helped me through all the difficulties while getting accustomed the mill.

To the rest of the steel mill, a gracious thanks to you all. It wasn’t easy but it was worth the experience.

God bless you all.

Page 4: Steel Mill Industrial Training

4

TABLE OF CONTENT

ABSTRACT………………………………………………………………2

ACKNOWLEDGEMENT……………………………………………….…….3

CHAPTER 1

INTRODUCTION………………………………………………………...…….5

BACKGROUND TO THE NIGERIAN STEEL INDUSTRY………………….5

CHAPTER 2

COMPANY OVERVIEW AND TRAINING DESCRIPTION…………….…12

CHAPTER 3

IRON AND STEEL MANUFACTURING PROCESSES…………………….15

INTRODUCTION TO STEEL PRODUCTION ……………………….…….15

PIG-IRON PRODUCTION…………………………………………………..16

OTHER METHODS OF IRON REFINING…………………..………………18

OPEN HEARTH PROCESS………………………………………..…………19

BASIC OXYGEN PROCESS…………………………………………………21

ELECTRIC-FURNACE STEEL………………………………………………21

FINISHING PROCESSES…………………………………………………….22

PIPE……………………………………………………………………………22

RED-INGOT…………………………………………………………….……..23

TIN PLATE………………………………………………………………...….25

WROUGHT IRON…………………………………………………………....25

CLASSIFICATIONS OF STEEL……………………………………………..27

Carbon Steels…………………………………………………….……………27

Alloy Steels……………………………………………………………………27

Page 5: Steel Mill Industrial Training

5

High-Strength Low-Alloy Steels………………………………………………27

Stainless Steels………………………………………………………………....27

Tool Steels……………………………………………………………………..28

STRUCTURE OF STEEL………………………………………..……………28

HEAT TREATMENT OF STEEL………………………………………….....29

CHAPTER 4

STEEL MILL SAFETY REGULATIONS……………………….……………30

Health and Safety Hazards…………………………………………..…………30

Other health hazards…………………………………………….……………..33..

Page 6: Steel Mill Industrial Training

6

CHAPTER 1

INTRODUCTION

1.1 BACKGROUND TO THE NIGERIAN STEEL INDUSTRY

Planning for the Nigerian Steel Industry started around 1958 as earlier stated. The starting point was the search for appropriate local inputs, the characteristics of which determined the particular technologies that would be adopted. Iron ore was located at Agbaja, Itakpe and Udi; suitable Limestone at Jakura, Mfamosin and other parts of the country. Coal deposits were always there at Enugu while potential coke-able coal was struck at Lafia.

Market surveys were commissioned and the construction of the Kainji Hydro-electric Dam promised an abundant source of electrical energy. Between 1961 and 1965 many firms from the industrialized nations of the West submitted proposals for the construction of an integrated Steel Plant in Nigeria. The view, then, was that the available raw materials could not be used in conventional Iron and Steel making technologies. The “Strategic Udy Process”, a direct reduction (DR) process still in the pilot plant stage in the USA, was then considered by Nigeria. The idea was accepted and a joint venture company, the Nigerian Steel Associates was formed with Westinghouse and Koppers as the foreign Partners. This programme failed because it did not prove capable of meeting commercial scale requirements.

In 1967 a UNIDO survey identified Nigeria as a potential steel Market. This led to the signing of a bilateral agreement between the defunct Soviet Union and Nigeria, and, the arrival of Soviet steel experts in Nigeria to conduct a feasibility study. The experts recommended the Blast Furnace/Basic Oxygen Furnace (BF/BOF) process of 570,000 tonnes per annum capacity of rolled products. They also confirmed the availability of raw materials and recommended further geological surveys. In 1970 a contract was awarded to TiajPromExport (TPE) of defunct USSR to conduct a study to identify sources of feedstock, quality and quantity of materials for the proposed integrated iron and steel plant. By this time the second National Development Plan (1970 – 1975) had envisaged the construction of a 750,000 tonnes per year capacity Plant.

Apart from Government Ventures there were a few private initiatives in the lesser capital-intensive steel industry of rolling mills coming up.

Page 7: Steel Mill Industrial Training

7

The Nigerian Steel Development Authority

In April 1971, the Nigerian Steel Development Authority (NSDA) was established by a Military Decree (No.9 of April 14). Thus, the first formal body to be charged with the supervision of the steel programme in Nigeria was born. NSDA was charged with;

o Planning, construction and operation of Steel Plants.

o Carrying out geological surveys, market surveys, metallurgical research

and training.

The Authority was to examine various process routes including natural gas-based direct reduction processes that require high-grade iron ores, which were not available in Nigeria. In 1973, the presence of good grade ore (though not of high-grade quality) was confirmed at Itakpe that led to the NSDA commissioning TPE to prepare a Preliminary Project Report (PPR) for the proposed BF/BOF Plant. The PPR was submitted in 1974, scrutinized and finally accepted in 1975. With the source of Iron Ore confirmed it was proposed that coking coal would be imported and blended appropriately with local coals. A three-phased development program (1st phase to produce 1.3 million tonnes, which will be expanded to 2.6 million tonnes incorporating the flat sheet production in the 2nd phase, and the third phase to increase capacity to 5.2 million tonnes) was accepted.

The initial product mix proposal suggested 50% long products and 50% flat products. This was based on the product demand profile revealed by market surveys. The Government decided that Ajaokuta Steel Plant should produce only long products in the first stage of 1.3 million tonnes per year, and flat products in the 2.6 million tonnes expansion which was planned to dove-tail the first phase completion and this is to be followed by a third phase of 5.2 million tonnes per annum. This decision was advised by the need to take advantage of economy of scale since flat-product mills of capacity below 1 million tonnes were considered uneconomical. An additional consideration was to use the relatively simpler technology of long-products rolling to rain up an otherwise virgin and inexperienced Nigerian Workforce of the time.

Page 8: Steel Mill Industrial Training

8

The NSDA was dissolved by the federal Government in 1979 and this metamorphosed in to several organizations, thus:

o Ajaokuta Steel Project, Ajaokuta

o The Delta Steel Company, Ovwian - Aladja

o Jos Steel Rolling Company, Jos

o Katsina Steel Rolling Company, Katsina

o Oshogbo Steel Rolling Company, Oshogbo

o National Iron Ore Mining Company, Itakpe.

o National Steel Raw Materials Exploration Agency, Kaduna.

o National Metallurgical Development Center, Jos.

o Metallurgical Training Institute, Onitsha.

The last three establishments are to be fully funded by the Government, through the Ministry. The rest of the organizations are supposed to be companies that should be self-funding, because at one time or the other, they had been incorporated as limited liability companies.

S/No Plant Location

Type of

Plant

Iron-making

Process and

capacity

(per year)

Casting

Process

Rolling

Capacity

(per year)

Product Mix

i. Ajaokuta Steel Co. Ltd.

Ajaokuta

Inter-grated

(Public)

Blast furnace, capacity 1.35m.ton

3 no.

4-strand for blooms

540,000 tons long products

Bars, rods, light sections

ii. Alliance Steel Co., Ibadan

Rolling mill

- - 20,000 tons long products

Bars

iii. Allied Steel Co., Onitsha

Rolling mill

- - 20,000 tons long products

Bars

Page 9: Steel Mill Industrial Training

9

iv. Asiastic Manarin Ind., Ikeja

Rolling mill

- - 60,000 tons long products

Bars; sections

v. Continental Iron & Steel Co., Ikeja

Mini mill - - 150,000 tons long products

Bars; sections

vi. Delta Steel Co., Ovwien/Aladja,

Inter-grated

(Public)

2 Midrex 600 series Direct Reduction furnaces; capacity1.02 m.t

3no.

6-strand for billets

320,000 tons long products

Bars; rods; sections

vii. Federated Steel Industry, Otta

Mini mill - - 140,000 tons long products

Bars; sections

viii. General Steel Mill, Asaba

Mini-mill - - 50,000 tons long products

Bars

ix. Jos Steel Rolling Company, Jos

Rolling mill

(Public)

- - 210,000 tons long products

Bars, rods

x. Katsina Steel Rolling Co. Katsina

Rolling mill

(Public)

- - 210,000 tons long products

Bars, rods

xi. Kew Metal Industries, Ikorodu

Mini-mill - - 20,000 tons long products

Bars; sections

xii. Kwara Rolling - - 40,000 tons Bars

Page 10: Steel Mill Industrial Training

10

Commercial, Metal and Chemical Industries, Ilorin

mill long products

xiii Mayor Eng. Co., Ikorodu

Rolling mill

- - 220,000 tons long products

Bars. sections

xiv Metcombe Steel Co., Owerri

Rolling mill

- - 10,000 tons long products

Bars; sections

xv. Nigerian Spanish Eng. Co., Kano

Mini mill - - 100,000 tons long products

Bars

xvi. Nigersteel Co., Enugu

Mini mill - - 40,000 tons long products

Bars; sections

xvii. Oshogbo Steel Co., Oshogbo

Rolling mill

(Public)

- - 210,000 tons long products

Bars; rods

xviii. Qua Steel Products, Eket

Rolling mill

- - 60,000 tons long products

Bars, sections

xix. Selsametal, Otta

Rolling mill

- - 100,000 tons long products

Bars

xx. Union Steel Co., Ilorin

Rolling mill

- - 20,000 tons long products

Bars

xxi. Universal Mini mill - - 80,000 tons Bars,

Page 11: Steel Mill Industrial Training

11

Steel Co., Ikeja

long products

sections

xxii. Baoyao Futurelex, Abuja

Rolling mill

- - 20,000 tons long products

Bars

CHAPTER 2

COMPANY OVERVIEW AND TRAINING DESCRIPTION

Page 12: Steel Mill Industrial Training

12

Ariel view of the Ajaokuta steel mill

The Ajaokuta Steel Company is one of the steel mills that were born when the NSDA was dissolved. This mill is located at the western part of Nigeria and it was established 1979. The Ajaokuta Steel plant is built in three stages. The first stage of 1.3 million tonnes to produce long steel products was followed by immediate expansion to 3.6 million tonnes for the production of 1.3 million tons of flat products in addition to the long products. The third stage is the expansion of the complex to produce 5.2 million tons of various types of finished and semi-finished steel products including heavy plates and heavy sections. The plant is designed such that it can be expanded up to 10 million tonnes eventually subject to demand. The Ajaokuta steel mill was tasked with producing services such as;

(i) Cast iron (different categories),

(ii) Rods and bars (both high tensile and mild steel varieties),

(iii) Wires (in all its ramifications),

(iv) Structural steels (light, medium and heavy structural),

(v) Flat sheet steels (plain, and galvanized, and also the entire spectrum classified as flats),

(vi) Stainless and other special alloy steels,

(vii) Rails and pipes,

(viii) Plates (various sizes in width and thickness).

Page 13: Steel Mill Industrial Training

13

INTERIOR VIEW OF THE STEEL MILL

The site of the Ajaokuta mill is like a small community (it is very gigantic). The first day on site was very interesting and I was excited, I was given a tour of the facility by my supervisor who is a senior staff of the company. I was to

Page 14: Steel Mill Industrial Training

14

accompany him while he was making his morning trip around the facility upon an electrical mobile. He put me through a rough sketch of the facility and a bit of history the rest of the day ended on a better note since I was the new guy people were quite eager to help.

The company rule is that even if you are a working employee newly employee to the facility you won’t operate any machinery or participate in the processing of steel. You will go through six months of just observation and tutoring, it’s more like a safety measure since every part of the facility is as dangerous as the other. Every part of the main processing unit is hot!!!

The rest of my first month I was tagged with junior staffs that was tasked who in turn is a newly employed staff and is presently at the last quarter of his training period. I spent a great deal of the rest of my internship with him, and I was to write a report on my weekly activities and submit to my supervisor at the end of every week.

CHAPTER 3

IRON AND STEEL MANUFACTURING PROCESSES.

Page 15: Steel Mill Industrial Training

15

3.1 INTRODUCTION TO STEEL PRODUCTION

Steel Production

Molten pig iron is poured into a basic oxygen furnace (BOF) for conversion to steel. Steel is a form of iron produced from iron ore, coke, and limestone in a blast furnace. Excess carbon and other impurities are removed to make strong steel.

Iron and Steel Manufacture, technology related to the production of iron and its alloys, particularly those containing a small percentage of carbon. The differences between the various types of iron and steel are sometimes confusing because of the nomenclature used. Steel in general is an alloy of iron and carbon, often with an admixture of other elements. Some alloys that are commercially called irons contain more carbon than commercial steels. Open-hearth iron and wrought iron contain only a few hundredths of 1% of carbon. Steels of various types contain from 0.04 % to 2.25 % of carbon. Cast iron, malleable cast iron, and pig iron contain amounts of carbon varying from 2-4 %. A special form of malleable iron, containing virtually no carbon, is known as white-heart malleable iron. A special group of iron alloys, known as ferroalloys, is used in the manufacture of iron and steel alloys; they contain from 20 to 80 % of an alloying element, such as manganese, silicon, or chromium.

Page 16: Steel Mill Industrial Training

16

3.1.1 PIG-IRON PRODUCTION

Blast Furnace

In order to turn crude iron ore into usable pig iron, its impurities must be removed. A blast furnace accomplishes this by forcing extremely hot air through a mixture of ore, coke, and limestone, called the charge. Carts called skips dump the charge into the top of the furnace, where it filters down through bell-shaped containers called hoppers. Once in the furnace, the charge is subjected to air blasts that may be as hot as 870° C (1600° F). (The furnace must be lined with a layer of firebrick, called the refractory, in order to sustain these temperatures.) Melted metal collects in the bottom of the furnace. The waste metal, called slag, floats on top of the molten pig iron. Both of these substances are drained, or tapped, periodically for further processing.

The basic materials used for the manufacture of pig iron are iron ore, coke, and limestone. The coke is burned as a fuel to heat the furnace; as it burns, the coke gives off carbon monoxide, which combines with the iron oxides in the ore, reducing them to metallic iron. This is the basic chemical reaction in the blast furnace; it has the equation: Fe2O3 + 3CO = 3CO2 + 2Fe. The limestone in the furnace charge is used as an additional source of carbon monoxide and as a

Page 17: Steel Mill Industrial Training

17

“flux” to combine with the infusible silica present in the ore to form fusible calcium silicate. Without the limestone, iron silicate would be formed, with a resulting loss of metallic iron. Calcium silicate plus other impurities form a slag that floats on top of the molten metal at the bottom of the furnace. Ordinary pig iron as produced by blast furnaces contains iron, about 92 %; carbon, 3 or 4 %; silicon, 0.5 - 3 %; manganese, 0.25 - 2.5%; phosphorus, 0.04 - 2 %; and a trace of sulphur.

A typical blast furnace consists of a cylindrical steel shell lined with a refractory, which is any non-metallic substance such as firebrick. The shell is tapered at the top and at the bottom and is widest at a point about one-quarter of the distance from the bottom. The lower portion of the furnace, called the bosh, is equipped with several tubular openings or tuyeres through which the air blast is forced. Near the bottom of the bosh is a hole through which the molten pig iron flows when the furnace is tapped, and above this hole, but below the tuyeres, is another hole for draining the slag. The top of the furnace, which is about 27 m (about 90 ft.) in height, contains vents for the escaping gases, and a pair of round hoppers closed with bell-shaped valves through which the charge is introduced into the furnace. The materials are brought up to the hoppers in small dump cars or skips that are hauled up an inclined external skip hoist.

Blast furnaces operate continuously. The raw material to be fed into the furnace is divided into a number of small charges that are introduced into the furnace at 10- to 15-min intervals. Slag is drawn off from the top of the melt about once every 2 hrs. and the iron itself is drawn off or tapped about five times a day.

The air used to supply the blast in a blast furnace is preheated to temperatures between approximately 540° and 870° C (approximately 1,000° and 1,600° F). The heating is performed in stoves, cylinders containing networks of firebrick. The bricks in the stoves are heated for several hours by burning blast-furnace gas, the waste gases from the top of the furnace. Then the flame is turned off and the air for the blast is blown through the stove. The weight of air used in the operation of a blast furnace exceeds the total weight of the other raw materials employed.

An important development in blast furnace technology, the pressurizing of furnaces, was introduced after World War II. By “throttling” the flow of gas from the furnace vents, the pressure within the furnace may be built up to 1.7 atm or more. The pressurizing technique makes possible better combustion of

Page 18: Steel Mill Industrial Training

18

the coke and higher output of pig iron. The output of many blast furnaces can be increased 25 %by pressurizing. Experimental installations have also shown that the output of blast furnaces can be increased by enriching the air blast with oxygen.

The process of tapping consists of knocking out a clay plug from the iron hole near the bottom of the bosh and allowing the molten metal to flow into a clay-lined runner and then into a large, brick-lined metal container, which may be either a ladle or a rail car capable of holding as much as 100 tons of metal. Any slag that may flow from the furnace with the metal is skimmed off before it reaches the container. The container of molten pig iron is then transported to the steelmaking shop.

Modern-day blast furnaces are operated in conjunction with basic oxygen furnaces and sometimes the older open-hearth furnaces as part of a single steel-producing plant. In such plants the molten pig iron is used to charge the steel furnaces. The molten metal from several blast furnaces may be mixed in a large ladle before it is converted to steel, to minimize any irregularities in the composition of the individual melts.

3.2 OTHER METHODS OF IRON REFINING

Although almost all the iron and steel manufactured in the world is made from pig iron produced by the blast-furnace process, other methods of iron refining are possible and have been practiced to a limited extent. One such method is the so-called direct method of making iron and steel from ore, without making pig iron. In this process iron ore and coke are mixed in a revolving kiln and heated to a temperature of about 950° C (about 1,740° F). Carbon monoxide is given off from the heated coke just as in the blast furnace and reduces the oxides of the ore to metallic iron. The secondary reactions that occur in a blast furnace, however, do not occur, and the kiln produces so-called sponge iron of much higher purity than pig iron. Virtually pure iron is also produced by means of electrolysis (see Electrochemistry), by passing an electric current through a solution of ferrous chloride. Neither the direct nor the electrolytic processes have yet achieved any great commercial significance.

3.2.1 OPEN-HEARTH PROCESS

Page 19: Steel Mill Industrial Training

19

Steel Production at a Krupp Plant

Based in Germany, the Krupp Corporation is a leading manufacturer of iron and steel in Europe. This Krupp plant worker makes sure that the raw materials used to make steel are added to the process in the correct quantities and at the correct times. Extremely hot temperatures generate the chemical reactions necessary to turn crude iron ore into iron, or with further refinements, steel.

Essentially the production of steel from pig iron by any process consists of burning out the excess carbon and other impurities present in the iron. One difficulty in the manufacture of steel is its high melting point, about 1,370° C (about 2,500° F), which prevents the use of ordinary fuels and furnaces. To overcome this difficulty the open-hearth furnace was developed; this furnace can be operated at a high temperature by regenerative preheating of the fuel gas and air used for combustion in the furnace. In regenerative preheating, the exhaust gases from the furnace are drawn through one of a series of chambers containing a mass of brickwork and give up most of their heat to the bricks. Then the flow through the furnace is reversed and the fuel and air pass through the heated chambers and are warmed by the bricks. Through this method open-hearth furnaces can reach temperatures as high as 1,650° C (approximately 3,000° F).

The furnace itself consists typically of a flat, rectangular brick hearth about 6 m by 10 m (about 20 ft. by 33 ft.), which is roofed over at a height of about 2.5 m

Page 20: Steel Mill Industrial Training

20

(about 8 ft.). In front of the hearth a series of doors opens out onto a working floor in front of the hearth. The entire hearth and working floor are one story above ground level, and the space under the hearth is taken up by the heat-regenerating chambers of the furnace. A furnace of this size produces about 100 metric tons of steel every 11 hr.

The furnace is charged with a mixture of pig iron (either molten or cold), scrap steel, and iron ore that provides additional oxygen. Limestone is added for flux and fluorspar to make the slag more fluid. The proportions of the charge vary within wide limits, but a typical charge might consist of 56,750 kg (125,000 lb.) of scrap steel, 11,350 kg (25,000 lb.) of cold pig iron, 45,400 kg (100,000 lb.) of molten pig iron, 11,800 kg (26,000 lb.) of limestone, 900 kg (2,000 lb.) of iron ore, and 230 kg (500 lb.) of fluorspar. After the furnace has been charged, the furnace is lighted and the flames play back and forth over the hearth as their direction is reversed by the operator to provide heat regeneration.

Chemically the action of the open-hearth furnace consists of lowering the carbon content of the charge by oxidization and of removing such impurities as silicon, phosphorus, manganese, and sulphur, which combine with the limestone to form slag. These reactions take place while the metal in the furnace is at melting heat, and the furnace is held between 1,540° and 1,650° C (2,800° and 3,000° F) for many hours until the molten metal has the desired carbon content. Experienced open-hearth operators can often judge the carbon content of the metal by its appearance, but the melt is usually tested by withdrawing a small amount of metal from the furnace, cooling it, and subjecting it to physical examination or chemical analysis. When the carbon content of the melt reaches the desired level, the furnace is tapped through a hole at the rear. The molten steel then flows through a short trough to a large ladle set below the furnace at ground level. From the ladle the steel is poured into cast-iron moulds that form ingots usually about 1.5 m (about 5 ft.) long and 48 cm (19 in) square. These ingots, the raw material for all forms of fabricated steel, weigh approximately 2.25 metric tons in this size. Recently, methods have been put into practice for the continuous processing of steel without first having to go through the process of casting ingots.

3.2.2 BASIC OXYGEN PROCESS

Page 21: Steel Mill Industrial Training

21

The oldest process for making steel in large quantities, the Bessemer process, made use of a tall, pear-shaped furnace, called a Bessemer converter that could be tilted sideways for charging and pouring. Great quantities of air were blown through the molten metal; its oxygen united chemically with the impurities and carried them off.

In the basic oxygen process, steel is also refined in a pear-shaped furnace that tilts sideways for charging and pouring. Air, however, has been replaced by a high-pressure stream of nearly pure oxygen. After the furnace has been charged and turned upright, an oxygen lance is lowered into it. The water-cooled tip of the lance is usually about 2 m (about 6 ft.) above the charge although this distance can be varied according to requirements. Thousands of cubic meters of oxygen are blown into the furnace at supersonic speed. The oxygen combines with carbon and other unwanted elements and starts a high-temperature churning reaction that rapidly burns out impurities from the pig iron and converts it into steel. The refining process takes 50 min or less; approximately 275 metric tons of steel can be made in an hour.

3.3.3 ELECTRIC-FURNACE STEEL

In some furnaces, electricity instead of fire supplies the heat for the smelting and refining of steel. Because refining conditions in such a furnace can be regulated more strictly than in open-hearth or basic oxygen furnaces, electric furnaces are particularly valuable for producing stainless steels and other highly alloyed steels that must be made to exacting specifications. Refining takes place in a tightly closed chamber, where temperatures and other conditions are kept under rigid control by automatic devices. During the early stages of this refining process, high-purity oxygen is injected through a lance, raising the temperature of the furnace and decreasing the time needed to produce the finished steel. The quantity of oxygen entering the furnace can always be closely controlled, thus keeping down undesirable oxidizing reactions.

Most often the charge consists almost entirely of scrap. Before it is ready to be used, the scrap must first be analysed and sorted, because its alloy content will affect the composition of the refined metal. Other materials, such as small quantities of iron ore and dry lime, are added in order to help remove carbon

Page 22: Steel Mill Industrial Training

22

and other impurities that are present. The additional alloying element goes either into the charge or, later, into the refined steel as it is poured into the ladle.

After the furnace is charged, electrodes are lowered close to the surface of the metal. The current enters through one of the electrodes, arcs to the metallic charge, flows through the metal, and then arcs back to the next electrode. Heat is generated by the overcoming of resistance to the flow of current through the charge. This heat, together with that coming from the intensely hot arc itself, quickly melts the metal. In another type of electric furnace, heat is generated in a coil. See Electric Furnace.

3.4 FINISHING PROCESSES

Steel Shaping: Hot Rolling and Continuous Casting

Continuous casting (right, red arrows) is a method of working steel that conveys steel from its molten state to blooms, ingots, or slabs. The white-hot metal is poured into open-ended moulds and continues on through rollers cooled by water. A series of guide rollers further shapes the steel into the desired form. However, hot rolling (left, blue arrows) is still the primary means of milling steel. This process begins with pre-shaped steel slabs, which are reheated in a soaking pit. The steel passes through a series of mills: the blooming mill, the roughing mill, and the finishing mill, which make it progressively thinner. Finally, the steel is wound into coils and transported elsewhere for further processing.

Page 23: Steel Mill Industrial Training

23

Steel is marketed in a wide variety of sizes and shapes, such as rods, pipes, railroad rails, tees, channels, and I-beams. These shapes are produced at steel mills by rolling and otherwise forming heated ingots to the required shape. The working of steel also improves the quality of the steel by refining its crystalline structure and making the metal tougher.

The basic process of working steel is known as hot rolling. In hot rolling the cast ingot is first heated to bright-red heat in a furnace called a soaking pit and is then passed between a series of pairs of metal rollers that squeeze it to the desired size and shape. The distance between the rollers diminishes for each successive pair as the steel is elongated and reduced in thickness.

A Hot Ingot

3.4.1 A RED-INGOT

An ingot, red-hot and malleable from the high temperature of the soaking pit, is lifted out of the furnace for further processing. As the steel is worked and reheated, it becomes stronger.

The first pair of rollers through which the ingot passes is commonly called the blooming mill, and the square billets of steel that the ingot produces are known as blooms. From the blooming mill, the steel is passed on to roughing mills and finally to finishing mills that reduce it to the correct cross section. The rollers of mills used to produce railroad rails and such structural shapes as I-beams, H-beams, and angles are grooved to give the required shape.

Modern manufacturing requires a large amount of thin sheet steel. Continuous mills roll steel strips and sheets in widths of up to 2.4 m (8 ft.). Such mills process thin sheet steel rapidly, before it cools and becomes unworkable. A slab of hot steel over 11 cm (about 4.5 in) thick is fed through a series of rollers which reduce it progressively in thickness to 0.127 cm (0.05 in) and increase its

Page 24: Steel Mill Industrial Training

24

length from 4 m (13 ft.) to 370 m (1,210 ft.). Continuous mills are equipped with a number of accessory devices including edging rollers, descaling devices, and devices for coiling the sheet automatically when it reaches the end of the mill. The edging rollers are sets of vertical rolls set opposite each other at either side of the sheet to ensure that the width of the sheet is maintained. Descaling apparatus removes the scale that forms on the surface of the sheet by knocking it off mechanically, loosening it by means of an air blast, or bending the sheet sharply at some point in its travel. The completed coils of sheet are dropped on a conveyor and carried away to be annealed and cut into individual sheets. A more efficient way to produce thin sheet steel is to feed thinner slabs through the rollers. Using conventional casting methods, ingots must still be passed through a blooming mill in order to produce slabs thin enough to enter a continuous mill.

By devising a continuous casting system that produces an endless steel slab less than 5 cm (2 in) thick, German engineers have eliminated any need for blooming and roughing mills. In 1989, a steel mill in Indiana became the first outside Europe to adopt this new system.

Cheaper grades of pipe are shaped by bending a flat strip, or skelp, of hot steel into cylindrical form and welding the edges to complete the pipe. For the smaller sizes of pipe, the edges of the skelp are usually overlapped and passed between a pair of rollers curved to correspond with the outside diameter of the pipe. The pressure on the rollers is great enough to weld the edges together. Seamless pipe or tubing is made from solid rods by passing them between a pair of inclined rollers that have a pointed metal bar, or mandrel, set between them in such a way that it pierces the rods and forms the inside diameter of the pipe at the same time that the rollers are forming the outside diameter.

3.4.2 TIN PLATE

By far the most important coated product of the steel mill is tin plate for the manufacture of containers. The “tin” can is actually more than 99 % steel. In

Page 25: Steel Mill Industrial Training

25

some mills steel sheets that have been hot-rolled and then cold-rolled are coated by passing them through a bath of molten tin. The most common method of coating is by the electrolytic process. Sheet steel is slowly unrolled from its coil and passed through a chemical solution. Meanwhile, a current of electricity is passing through a piece of pure tin into the same solution, causing the tin to dissolve slowly and to be deposited on the steel. In electrolytic processing, less than half a kilogram of tin will coat more than 18.6 sq. m (more than 200 sq. ft.) of steel. For the product known as thin tin, sheet and strip are given a second cold rolling before being coated with tin, a treatment that makes the steel plate extra tough as well as extra thin. Cans made of thin tin are about as strong as ordinary tin cans, yet they contain less steel, with a resultant saving in weight and cost. Lightweight packaging containers are also being made of tin-plated steel foil that has been laminated to paper or cardboard.

Other processes of steel fabrication include forging, founding, and drawing the steel through dies

3.4.3 WROUGHT IRON

The process of making the tough, malleable alloy known as wrought iron differs markedly from other forms of steel making. Because this process, known as puddling, required a great deal of hand labour, production of wrought iron in tonnage quantities was impossible. The development of new processes using Bessemer converters and open-hearth furnaces allowed the production of larger quantities of wrought iron.

Wrought iron is no longer produced commercially, however, because it can be effectively replaced in nearly all applications by low-carbon steel, which is less expensive to produce and is typically of more uniform quality than wrought iron.

The puddling furnace used in the older process has a low, arched roof and a depressed hearth on which the crude metal lies, separated by a wall from the combustion chamber in which bituminous coal is burned. The flame in the combustion chamber surmounts the wall, strikes the arched roof, and “reverberates” upon the contents of the hearth. After the furnace is lit and has become moderately heated, the puddler, or furnace operator, “fettles” it by plastering the hearth and walls with a paste of iron oxide, usually hematite ore. The furnace is then charged with about 270 kg (about 600 lb.) of pig iron and

Page 26: Steel Mill Industrial Training

26

the door is closed. After about 30 min the iron is melted and the puddler adds more iron oxide or mill scale to the charge, working the oxide into the iron with a bent iron bar called a raddle. The silicon and most of the manganese in the iron are oxidized and some sulphur and phosphorus are eliminated. The temperature of the furnace is then raised slightly, and the carbon starts to burn out as carbon-oxide gases. As the gas is evolved the slag puffs up and the level of the charge rises. As the carbon is burned away the melting temperature of the alloy increases and the charge becomes more and more pasty, and finally the bath drops to its former level. As the iron increases in purity, the puddler stirs the charge with the raddle to ensure uniform composition and proper cohesion of the particles. The resulting pasty, sponge like mass is separated into lumps, called balls, of about 80 to 90 kg (about 180 to 200 lb.) each. The balls are withdrawn from the furnace with tongs and are placed directly in a squeezer, a machine in which the greater part of the intermingled siliceous slag is expelled from the ball and the grains of pure iron are thoroughly welded together. The iron is then cut into flat pieces that are piled on one another, heated to welding temperature, and then rolled into a single piece. This rolling process is sometimes repeated to improve the quality of the product.

The modern technique of making wrought iron uses molten iron from a Bessemer converter and molten slag, which is usually prepared by melting iron ore, mill scale, and sand in an open-hearth furnace. The molten slag is maintained in a ladle at a temperature several hundred degrees below the temperature of the molten iron. When the molten iron, which carries a large amount of gas in solution, is poured into the ladle containing the molten slag, the metal solidifies almost instantly, releasing the dissolved gas. The force exerted by the gas shatters the metal into minute particles that are heavier than the slag and that accumulate in the bottom of the ladle, agglomerating into a spongy mass similar to the balls produced in a puddling furnace. After the slag has been poured off the top of the ladle, the ball of iron is removed and squeezed and rolled like the product of the puddling furnace.

3.5 CLASSIFICATIONS OF STEEL

Steels are grouped into five main classifications.

Page 27: Steel Mill Industrial Training

27

3.5.1 Carbon Steels

More than 90 % of all steels are carbon steels. They contain varying amounts of carbon and not more than 1.65 % manganese, 0.60 % silicon, and 0.60 % copper. Machines, automobile bodies, most structural steel for buildings, ship hulls, bedsprings, and bobby pins are among the products made of carbon steels.

3.5.2 Alloy Steels

These steels have a specified composition, containing certain percentages of vanadium, molybdenum, or other elements, as well as larger amounts of manganese, silicon, and copper than do the regular carbon steels. Automobile gears and axles, roller skates, and carving knives are some of the many things that are made of alloy steels.

3.5.3 High-Strength Low-Alloy Steels

Called HSLA steels, they are the newest of the five chief families of steels. They cost less than the regular alloy steels because they contain only small amounts of the expensive alloying elements. They have been specially processed, however, to have much more strength than carbon steels of the same weight. For example, freight cars made of HSLA steels can carry larger loads because their walls are thinner than would be necessary with carbon steel of equal strength; also, because an HSLA freight car is lighter in weight than the ordinary car, it is less of a load for the locomotive to pull. Numerous buildings are now being constructed with frameworks of HSLA steels. Girders can be made thinner without sacrificing their strength, and additional space is left for offices and apartments.

3.5.4 Stainless Steels

Stainless steels contain chromium, nickel, and other alloying elements that keep them bright and rust resistant in spite of moisture or the action of corrosive acids and gases. Some stainless steels are very hard; some have unusual strength and will retain that strength for long periods at extremely high and low temperatures. Because of their shining surfaces architects often use them for decorative purposes. Stainless steels are used for the pipes and tanks of petroleum refineries and chemical plants, for jet planes, and for space capsules. Surgical instruments and equipment are made from these steels, and they are also used to patch or replace broken bones because the steels can withstand the

Page 28: Steel Mill Industrial Training

28

action of body fluids. In kitchens and in plants where food is prepared, handling equipment is often made of stainless steel because it does not taint the food and can be easily cleaned.

3.5.5 Tool Steels

These steels are fabricated into many types of tools or into the cutting and shaping parts of power-driven machinery for various manufacturing operations. They contain tungsten, molybdenum, and other alloying elements that give them extra strength, hardness, and resistance to wear.

3.6 STRUCTURE OF STEEL

The physical properties of various types of steel and of any given steel alloy at varying temperatures depend primarily on the amount of carbon present and on how it is distributed in the iron. Before heat treatment most steels are a mixture of three substances: ferrite, pearlite, and cementite. Ferrite is iron containing small amounts of carbon and other elements in solution and is soft and ductile. Cementite, a compound of iron containing about 7 % carbon, is extremely brittle and hard. Pearlite is an intimate mixture of ferrite and cementite having a specific composition and characteristic structure, and physical characteristics intermediate between its two constituents. The toughness and hardness of steel that is not heat treated depend on the proportions of these three ingredients. As the carbon content of a steel increases, the amount of ferrite present decreases and the amount of pearlite increases until, when the steel has 0.8 % of carbon, it is entirely composed of pearlite. Steel with still more carbon is a mixture of pearlite and cementite. Raising the temperature of steel changes ferrite and pearlite to an allotropic form of iron-carbon alloy known as austenite, which has the property of dissolving all the free carbon present in the metal. If the steel is cooled slowly the austenite reverts to ferrite and pearlite, but if cooling is sudden, the austenite is “frozen” or changes to martensite, which is an extremely hard allotropic modification that resembles ferrite but contains carbon in solid solution.

3.7 HEAT TREATMENT OF STEEL

The basic process of hardening steel by heat treatment consists of heating the metal to a temperature at which austenite is formed, usually about 760° to 870° C (about 1,400° to 1,600° F) and then cooling, or quenching, it rapidly in water or oil. Such hardening treatments, which form martensite, set up large internal

Page 29: Steel Mill Industrial Training

29

strains in the metal, and these are relieved by tempering, or annealing, which consists of reheating the steel to a lower temperature. Tempering results in a decrease in hardness and strength and an increase in ductility and toughness.

The primary purpose of the heat-treating process is to control the amount, size, shape, and distribution of the cementite particles in the ferrite, which in turn determines the physical properties of the steel.

Many variations of the basic process are practiced. Metallurgists have discovered that the change from austenite to martensite occurs during the latter part of the cooling period and that this change is accompanied by a change in volume that may crack the metal if the cooling is too swift. Three comparatively new processes have been developed to avoid cracking. In time-quenching the steel is withdrawn from the quenching bath when it has reached the temperature at which the martensite begins to form, and is then cooled slowly in air. In martempering the steel is withdrawn from the quench at the same point, and is then placed in a constant-temperature bath until it attains a uniform temperature throughout its cross section. The steel is then allowed to cool in air through the temperature range of martensite formation, which for most steels is the range from about 288° C (about 550° F) to room temperature. In austempering the steel is quenched in a bath of metal or salt maintained at the constant temperature at which the desired structural change occurs and is held in this bath until the change is complete before being subjected to the final cooling.

Other methods of heat treating steel to harden it are used. In case hardening, a finished piece of steel is given an extremely hard surface by heating it with carbon or nitrogen compounds. These compounds react with the steel, either raising the carbon content or forming nitrides in its surface layer. In carburizing, the piece is heated in charcoal or coke, or in carbonaceous gases such as methane or carbon monoxide. Cyaniding consists of hardening in a bath of molten cyanide salt to form both carbides and nitrides. In nitriding, steels of special composition are hardened by heating them in ammonia gas to form alloy nitrides.

CHAPTER 4

Page 30: Steel Mill Industrial Training

30

STEEL MILL SAFETY REGULATIONS.

4.1 Health and Safety Hazards

For construction crews working in steel plants, there are many hazards. The following points summarize the main hazard areas.

1) Pinch points and moving equipment. o Transportation equipment

Bulk material handling and transport is a major activity for a steel mill. There are railroad systems with tracks all over the plant, hot metal cars, transfer cars, buggies, charging cars, hopper cars, scrapers, coil carriers, slab carriers, and many others.

o Overhead cranesOverhead cranes form an integral part of operating and maintenance practice throughout a steel mill. Many hazards are associated with their use, including overhead loads, hot metal splash, equipment failure, communication breakdown, and the fact that crane operators may not be aware of construction workers in unexpected locations.

o Operating equipmentProduction equipment may operate on a timed basis, it may be remote-controlled, or operators may not expect non-operating personnel on site. Construction personnel must learn plant safety practices, alarms, access requirements and limitations, and emergency procedures for whichever section of the mill they must enter. They must follow these procedures.

2) Explosion and burn hazardsSpatters or spills of molten material are an obvious source of burns and fires. Contact between molten metal or slag and moisture will result in violent explosions and spattering of molten material. A network of piping transports fuel gases and oxygen around the plant – all of which have a potential for explosion and fire. Sparks and fires around oxygen lines are especially hazardous. One area of a steel mill with a high fire hazard is the coke oven by-product plant, which shares many characteristics with oil refineries.

3) Health and hygiene hazardsPlant operating practices and precautions must be followed at all times. The contents of all storage and piping systems should be determined. MSDSs should be obtained and reviewed in advance. Information should be readily available from the client/mill operators. The table on the next page relates various locations in a steel mill to the health hazards they pose.

Page 31: Steel Mill Industrial Training

31

o Chemical HazardsThe following is a list of the major chemical hazards present in steel mills identified in the table and their effects. It is not intended to be comprehensive. Chemicals and chemical processes may vary from plant to plant.

Acids• pickling and tinning lines and acid regeneration plants (hydrochloric) • Hydrochloric acid or sulphuric acid• Highly corrosive, can be dangerously reactive in high concentrations

Ammonia• Very irritating to the eyes, nose and throat• High exposure can cause choking and breathing difficulties• Coke oven by-products plant.

Asbestos• can be present in blast furnace and stoves, by-products plant, steam, generation (either central or waste heat boilers)• Asbestosis, mesothelioma, lung cancer

By-product plant light oil• containing chemicals such as benzene and naphthalene and minor amounts of toluene and xylene• Coke oven by-products• Acute effects - typical solvent effects, central nervous system depression• Chronic effects - carcinogens (cancer-causing agents); some cause liver and kidney damage.

Carbon monoxide (CO)• Odourless, colourless, poisonous gas• makes up a large part of fuel gases (22-30% of blast furnace gas, 5-10% of coke oven gas)• Many hazardous locations, especially around blast furnaces – also coke ovens and steelmaking• can leak out from tops of blast furnaces, around hot stoves, pipelines; can occur due to sudden shutdown of blowing engines, boiler rooms, ventilation fans, and from insufficient gas removal during electrostatic precipitator cleaning.

Coal tar pitch volatiles• Coke oven by-products plant• Skin irritant, cancer of the lung, skin, and scrotum• Photosensitive dermatitis.

Coke oven emissions• In the vicinity of the coke oven batteries• A “designated substance” in Ontario, carcinogenic• There must be a control/monitoring program.

Coke oven gas• High in carbon monoxide and may contain trace amounts of carcinogens

Page 32: Steel Mill Industrial Training

32

• Contents can include benzene (0.4%), H2S, and hydrogen cyanide. Dusts

• Iron oxide: (found in sinter plant, before blast furnace, and around steelmaking) in addition to being irritating to eyes, this causes ciderosis, which is a specifically named type of pneumoconiosis or obstructive lung disease; i.e., dust build-up, not fibrosis• Coal: - Irritant to the eyes, etc.- Pulmonary fibrosis, pneumoconiosis• Coke: - There is some suspicion that coke is a carcinogen• Silica: - Silicosis- Refractory brick lined furnaces and ladles- may occur as dust at sinter plant,Primarily during furnace repair• iron chloride- around hydrochloric acid regeneration•dust: plant- Respiratory tract irritant to some people.

Hydrogen Sulphide (H2S)• Around coke oven batteries• Toxic gas (500-700 ppm can be instantly fatal)• Rotten egg smell at very low concentrations - below 100 ppm• Explosive at high concentrations.

Sodium hydroxide (NaOH)- cleaning lines (tinning)- Corrosive.

Sulphur dioxide (SO2)• Blast furnace slag pits• gas irritating to eyes, nose, and throat• Overexposure can cause choking and breathing difficulties• Delayed reaction to overexposure can be fluid build-up in the lungs.

4.2 Other Health Hazardso Heat

Heat is generated and used all over a steel plant. Care must be taken to control overexposure. This can come in the form of extreme radiant heat in many locations where there are hot or molten materials. Care must be exercised in these places. There are also many locations where strenuous work may have to

Page 33: Steel Mill Industrial Training

33

be done in hot locations. Heat stroke can be a constant risk, especially during warm weather. See the chapter on Heat Stress in this manual.

o NoiseNoise is a hazard at many locations in a steel mill. Hearing protection is often required and warning signs are posted. High noise levels exist, for example, around the tuyeres in the blast furnaces or any rolling mills. For guidelines on noise exposure and hearing protection, refer to the chapter on Personal Protective Equipment in this manual.

o GeneralBefore work begins, crews should receive training in the hazards existing in the work area and obtain and review the material safety data sheets for any hazardous materials to which they may be exposed. These should be readily available from the client or owner and, in fact, should be obtained at the time of bidding to facilitate job planning. Any protective equipment used should at least equal that worn by the client's workers in the area.

o Piping systemsThe contents of piping systems, storage bins, and tanks should be known and identified. Know the system of identification and warning used by the owner. These may vary from one plant to another.

o Confined spacesSpecial attention must always be paid to confined space entry. Always comply with the Construction Regulation (Ontario Regulation 213/91) as a minimum. The steel mill will usually have an entry permit system and requirements for entry and work in confined spaces. Welding in any confined space must be done with precautions. Pay special attention in cases where welding is being done on stainless steel, since the chromium released is a possible cause of lung cancer.

4.3 Emergency Procedures

The steel mill has an emergency procedure in place. All workers are expected to know the warning alarm signals and follow the procedures.

Page 34: Steel Mill Industrial Training

34

REFERENCE Health Hazard Manual The Metallurgical Centre, Jos

Guidelines in a Steel mill.Samuel M. Allen

Microsoft ® Encarta ® 2009. © 1993-2008 Microsoft Corporation. All rights reserved.