Status report of my home vihanga as on 22.02.2014
-
Upload
manjumyhome -
Category
Real Estate
-
view
2.048 -
download
0
description
Transcript of Status report of my home vihanga as on 22.02.2014
Project Progress – 22nd Feb 2014
BLOCK-1 REINFORCEMENT FIXING & SHUTTERING IN PROGRESS BASEMENT-2 SLAB COLUMNS IN PROGRESS
BLOCK-1 BASEMENT-1 ROOF SLAB TOPVIEW SOUTH SIDE
BLOCK-1 BASEMENT-2 ROOF SLAB TOPVIEW NORTH SIDE
BLOCK-2 BASEMENT-2 SLAB SOUTH SIDE TOP VIEW
BLOCK-2 NORTHSIDE VIEW REINFORCEMENT FIXING IN PROGRESS FOR SLAB
BLOCK-3 STUB COLUMNS IN PROGRESS
BLOCK-3 TIE BEAMS PCCGROUND PREPARATION IN PROGRESS
BLOCK-4 PCC & FOOTINGS IN PROGRESS
BLOCK 19&20 SOUTH SIDE TIE BEAMS IN PROGRESS FOR GRADE SLAB
BLOCK -19 PCC DONE FOR TIE BEAMS SHUTTERING IN PROGRESS
BLOCK -20 PCC DONE FOR FOOTINGS IN PROGRESS
17 &18 BLOCKS IN PROGRESS
BLOCK 5 & 6 IN PROGRESS
BLOCK 15 & 16 IN PROGRESS
BLOCK 7 &8 IN PROGRESS
BLOCK 13&14 IN PROGRESS
BLOCK 9 &10 IN PROGRESS
BLOCK 11 &12 WORK IN PROGRESS