Status of EURISOL
description
Transcript of Status of EURISOL
Status of EURISOL
Yorick BLUMENFELD
We acknowledge the financial support of the European Community under the FP6 “Research Infrastructure Action - Structuring the European Research Area” EURISOL DS Project Contract no. 515768 RIDS . The EC is not liable for any use that can be made of the information contained herein.
NuPECC recommends the construction of 2 ‘next generation’ RIB infrastructures in Europe, i.e. one ISOL and one in-flight facility. The in-flight machine would arise from a major upgrade of the current GSI facility: FAIR, while EURISOL would constitute the new ISOL facility
THE EUROPEAN PLAN
The EURISOL Road Map
• Vigorous scientific exploitation of current ISOL facilities : EXCYT, Louvain, REX/ISOLDE, SPIRAL
• Construction of intermediate generation facilities: SPIRAL2, HIE-ISOLDE, SPES
• Design and prototyping of the most specific and challenging parts of EURISOL in the framework of EURISOL_DS.
The EURISOL_DS in the 6th framework
• Detailed engineering oriented studies and technical prototyping work
• 20 participants from 13 countries• 21 contributors from Europe, Asia and North America• Total Cost : 33 M€• Contribution from EU : 9.16 M€• Continues to July 2009• 12 Tasks in 4 Topical Areas:
– Targets– Accelerators– Physics, beams and Safety– Beta Beams
User Requirements (Trento meeting; Jan 2006)
• Internal report 10-25-2007-001• Energy: Main LINAC up to 150A MeV for 132Sn; second LINAC up to
5A MeV and possibility for 0.1 to 0.7A MeV (astrophysics)+ low energy
• Energy variability: 0.5% (below 20A MeV) and 1A MeV (above 20A MeV)
• Energy definition : 0.1%• Time resolution : 0.5ns or better(?)• Time structure : 8.8 MHz (buncher-chopper) and retain also 88MHz• Beam sharing: 1 MMW target and 3 direct 100 kW targets of which
2 can be used simultaneously• Pure beams• Emittance : 2mm.mrad and 2mm2 beam spot
New baseline scheme with extended capabilities
• 2 injection lines for H,D, He and A/q=2 ions• SARAF scheme up to 60 MeV/q • IPNO scheme from 60 to 140 MeV/q• CEA scheme from 140 to 1000 MeV/u• cw beam splitting at 1 GeV (1 line 4 MW + 3 lines 100 kW)• Total length of the linac: ~240 m
H-,D-
H+,D+, 3He+
+
RFQ176 MHz
HWR176 MHz
3-SPOKE 352 MHz
Elliptical704 MHz
4 MWH-
100 kWH+, 3He2+
1.5 MeV
/u
60 MeV
/q
140 MeV
/q
1 GeV
/q
B stripper
foil stripper>200 MeV/q
D, A/q=2
=0.047=0.03=0.09=0.15
=0.65 =0.78
10 36 31 63 97
1 GeV Multiple Extraction•3 splitting stations•4 simultaneous users for cw proton beams:
•1 4 MW•3 0100 kW (continuously adjustable)
•Unique ability of EURISOL at present
EURISOL parallel cw Proton extraction
New Target ConceptMMW target for fission fragments
Double effusion line prototype(E. Bouquerel, L. Penescu)
Heat screen
Bellows
ISOLDE cold FEBIAD MK7Ion source
Cu body
2 pneumatic valves
RIB
1.4GeV protons
2xwater cooledtransfer lines2x20cm containers
Schematic lay-outTarget-ion sources
Pre-separators,beam gates
Ion cooling and bunching
High-resolution separators
Charge breeding:EBIS and ECR
q/m selection
Electrostaticdeflection
Post-acceleration andExperimental areas
Beam preparation lay-out:
Two complete beam preparation chains
Two parallel mass-purified beams for on-line experiments
Two charge breeders: EBIS (fast, low capacity, low
background, narrower charge state distribution, provides intensity also for light elements)
ECR (slow, high capacity, high background, access to intense beams including stable ones)
Modular (easy to expand) Robust (electrostatic deflectors
without moving parts)
SPIRAL-2 philosophy : Smoothest beam dynamics (regular FDO lattice, low number of -sections), Modular solution and simple cryostats, Separated vacuum (safety with FP), Warm focusing (easier for alignement), Possibility to insert diagnostics at each period, ease of tuning
Main technical requirements: Only 2-gap cavities (high q/A acceptance)
Max. accelerating fields 7.8 MV/m
Nominal operation for A/Q between 4 and 8
Design of the post-accelerator
Fragmentation of 132Sn (Preliminary results)
Fragmentation of 132Sn on BeD. Perez and D. Dragosavac
Kr isotopes
Inte
nsity
(pps
)a)
a)Yield for in-flight production of fission fragments at relativistic energy
Yields after acceleration Comparison between facilities
Radioactive ISOL beam yields2020
2016
2012present
Possible Locations?
The Site Investigation Panel (chaired by Alan Shotter) will investigate the implementation and cost of
EURISOL in these 3 hypotheses
Time scales
Project definition
Construction
Exploitation
2005 2007 2009 2012 2020
FAIR
Why a EURISOL User Group?
• To build up an identifiable User Community for EURISOL
• To continuously update the EURISOL Physics Case; while Task 10 will now mainly concentrate on instrumentation.
• To continue to furnish input to the EURISOL concept after the end of the DS
• To interact with the user communities of the current ISOL facilities.
Goals of this week
• Updating of the Physics Case• Putting EURISOL in perspective with the other
worldwide initiatives.• Examining the current technical solutions in the
light of the physics requirements (Thursday morning)
• Discussing the practical organization and future actions of the UG in the framework of the future of EURISOL (Wednesday, 14:30-16:00)