Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which...

43
Hon Mark McGowan MLA Minister for tlw Environment; Racing <m cl Gaming 197 St G!.'or"w's Tcrraw, Perth 1'\IESTERN AUSTRALiA ilOOO Tdepbone: (+6'1 B) 9222 9 l J'l ( +61 8) CJ222 9410 f::mni!; o \Vebsill': WWIV.mini:;ters.lv<l.go\·,;lu/mcgowan/ Statement No. STATEMENT THAT A PROPOSAL MAY BE IMPLEMENTED (PURSUANT TO THE PROVISIONS OF THE ENVIRONMENTAL PROTECTION ACT, 1986) BLUEW ATERS POWER STATION- PHASE I! Proposal: Proponent: Proponent Address: Assessment Number: SHIRE OF COLLIE The construction and operation of a sub-critical coal-fired base-load power generating facility with a nominal generating capacity of 200 megawatts adjacent to the Bluewaters I Power Station on a site located approximately four kilometers north-east of Collie, as documented in schedule 1 of this statement. Griffin Power Pty Ltd 15' 11 Floor, 28 The Esplanade, PERTH WA 6000 1525 Report of the Environmental Protection Authority: Bulletin 1 l 77 The proposal refeJTed to above may be implemented by the proponent subject to the · following conditions and procedures: 1 Implementation 1-1 The proponent shall implement the proposal as documented in schedule 1 of this statement subject to the conditions of this statement. 2 Proponent Commitments 2-1 The proponent shall implement the envi1:mm1ental management commitments documented in schedule 2 of this statement. Published on 2 4 MAY 2006

Transcript of Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which...

Page 1: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Hon Mark McGowan MLA Minister for tlw Environment;

Racing <m cl Gaming

197 St G!.'or"w's Tcrraw, Perth 1'\IESTERN AUSTRALiA ilOOO Tdepbone: (+6'1 B) 9222 9 l J'l F<~csimik: ( +61 8) CJ222 9410

f::mni!; nt<Jrl-mcg<>w,ln®dj.~Ch'il.g<w.au o \Vebsill': WWIV.mini:;ters.lv<l.go\·,;lu/mcgowan/

Statement No.

STATEMENT THAT A PROPOSAL MAY BE IMPLEMENTED (PURSUANT TO THE PROVISIONS OF THE

ENVIRONMENTAL PROTECTION ACT, 1986)

BLUEW ATERS POWER STATION- PHASE I!

Proposal:

Proponent:

Proponent Address:

Assessment Number:

SHIRE OF COLLIE

The construction and operation of a sub-critical coal-fired base-load power generating facility with a nominal generating capacity of 200 megawatts adjacent to the Bluewaters I Power Station on a site located approximately four kilometers north-east of Collie, as documented in schedule 1 of this statement.

Griffin Power Pty Ltd

15'11 Floor, 28 The Esplanade, PERTH WA 6000

1525

Report of the Environmental Protection Authority: Bulletin 1 l 77

The proposal refeJTed to above may be implemented by the proponent subject to the · following conditions and procedures:

1 Implementation

1-1 The proponent shall implement the proposal as documented in schedule 1 of this statement subject to the conditions of this statement.

2 Proponent Commitments

2-1 The proponent shall implement the envi1:mm1ental management commitments documented in schedule 2 of this statement.

Published on

2 4 MAY 2006

Page 2: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

3 Proponent Nomination and Contact Details

3-1 The proponent for the time being nominated by the Minister for the Environment under section 38(6) or (7) of the Environmental Protection Act, 1986 is responsible for the implementation of the proposal until such time as the Minister for the Environment has exercised the Minister's power under section 38(7) of the Act to revoke the nomination of that proponent and nominate another person as the proponent for the proposal.

3-2 If the proponent wishes to relinquish the nomination, the proponent shall apply for the transfer of proponent and provide a letter with a copy of this statement endorsed by the proposed replacement proponent that the proposal will be carried out in accordance with this statement. Contact details and appropriate documentation on the capability of the proposed replacement proponent to carry out the proposal shall also be provided.

3-3 The nominated proponent shall notify the Department of Environment of any change of contact name and address within 60 days of such change.

4 Commencement and Time Limit of Approval

4-1 The proponent shall substantially commence the proposal within five years of the date of this statement or the approval granted in this statement shall lapse and be void.

Note: The Minister for the Environment will determine any dispute as to whether the proposal has been substantially commenced.

4-2 The proponent shall make application for any extension of approval for the substantial commencement of the proposal beyond five years from the date of this statement to the Minister for the Environment, prior to the expiration of the five-year period referred to in condition 4-1.

The application shall demonstrate that:

1. the environmental factors of the proposal have not changed significantly;

2. new, significant, environmental issues have not arisen; and

3. all relevant government authorities have been consulted.

Note: The Minister for the Environment may consider the grant of an extension of the time limit of approval not exceeding five years for the substantial commencement of the proposal.

5 Compliance Audit and Performance Review

5-1 The proponent shall prepme an audit program and submit compliance reports to the Department of Environment which address:

Page 3: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

1. the status of implementation of the proposal as defined m schedule 1 of this statement;

2. evidence of compliance with the conditions and commitments; and

3. the perfom1ance of the environmental management plans and programs.

Note: Under sections 48(1) and 47(2) of the Environmental Protection Act 1986, the Chief Executive Officer of the Depmiment of Environment is empowered to monitor the compliance of the proponent with the statement and should directly receive the compliance documentation, including environmental mm1agement plans, related to the conditions, procedures and commitments contained in this statement.

5-2 The proponent shall submit a performance review report every five years after the sta1i of operations, to the requirements of the Minister for the Environment on advice of the Environmental Protection Authority, which addresses:

1. the major environmental issues associated with the project; the targets for those issues; the methodologies used to achieve these; and the key indicators of environmental performance measured against those targets;

2. the level of progress in the achievement of sound environmental performance, including industry benchmarking, and the use of best available technology where practicable;

3. significant improvements gained in enviromnental management, including the use of external peer reviews;

4. stakeholder and community consultation about environmental performance and the outcomes of that consultation, including a report of any on-going concerns being expressed; and

5. the proposed environmental targets over the next five years, including improvements in technology and management processes.

5-3 The proponent may submit a report prepared by an independent auditor to the Chief Executive Office of the Department of Environment on each condition or commitment of this statement which requires the preparation of a management plan, programme, strategy or system, stating whether the requirements of each condition or commitment have been fulfilled within the timeframe stated within each condition or commitment.

6 Greenhouse Gas Abatement

6-1 Prior to commencement of constmction, the proponent shall demonstrate that the plant has been· designed to achieve reductions in "greenhouse gas" emissions as far as practicable, to the requirements of the Minister for the Environment on advice of the · Environmental Protection Authority.

Page 4: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

6-2 Within six months following the commencement of construction, the proponent shall develop a Greenhouse Gas Abatement Program to:

• ensure that the plant is operated in a manner which achieves reductions m "greenhouse gas" emissions as far as practicable;

• provide for ongoing "greenhouse gas" emissions reductions over time;

• ensure that through the use of best practice (as defined in Environmental Protection Authority Guidauce Statement No. 55), the total net "greenhouse gas" emissions and/or "greenhouse gas" emissions per unit of product from the project are minimised; aud

• manage "greenhouse gas" em1sswns in accordance with the Framework Convention on Climate Change 199 2, and consistent with the National Greenhouse Strategy;

to'the requirements of the Minister for the Environment on advice of the Environmental Protection Authority.

This Program shall include:

l. calculation of the "greenhouse gas" em1ss1ons associated with the proposal, as advised by the Environmental Protection Authority;

Note: The current requirements of the Environmental Protection Authority are set out in: Minimising Greenhouse Gas Emissions, Guidance for the Assessment of Environmental Factors, No. 12 published by the Environmental Protection Authority (October 2002). This document may be updated or replaced from time to time.

2. specific measures to minimise the total net "greenhouse gas" emissions and/or the "greenhouse gas" emissions per unit of product associated with the proposal using a combination of"no regrets" and "beyond no regrets" measures;

3. the implementation and ongoing review of "greenhouse gas" offset strategies with such offsets to remain in place for the life of the proposal;

4. estimation of the "greenhouse gas" efficiency of the project (per unit of product aud/or other agreed perfom1ance indicators) aud comparison with the efficiencies of other comparable projects producing a similar product, both within Australia and overseas;

5. implementation of thermal efficiency design and operating goals consistent with the Australian Greenhouse Office Technical Efficiency guidelines in design and operational management;

6. actions for the monitoring, regular auditing and annual reporting of "greenhouse gas" emissions and emission reduction strategies; ·

Page 5: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

7. a target set by the proponent for the progressive reduction of total net "greenhouse gas" emissions and/or "greenhouse gas" emissions per unit of product and as a percentage of total emissions over time, and mmual reporting of progress made in achieving this target. Consideration should be given to the use of renewable energy sources such as solar, wind or hydro power;

8. a program to achieve reductions in "greenhouse gas" emissions, consistent with the target refened to in (7) above;

9. entry, whether on a project-specific basis, company-wide arrangement or within an industrial grouping, as appropriate, into the Commonwealth Govenm1ent's "Greenhouse Challenge" voluntary cooperative agreement program.

Components of the agreement program include: I. an inventory of emissions; 2. opportunities for abating "greenhouse gas" emissions in the org3!1isation; 3. a "greenhouse gas" mitigation action plan; 4. regular monitoring and reporting of perfonnance; and 5. independent performance verification.

10. Review of practices and available technology;

11. "Continuous improvement approach" so that advances in technology and potential operational improvements of plant performance are adopted; and,

12. research relating to options for geosequestration of carbon dioxide emissions.

Note: In (2) above, the following definitions apply:

I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral.

2. "beyond no regrets" measures are those which can be implemented by a proponent and which involve additional costs that are not expected to be recovered.

6-3 The proponent shall implement the Greenhouse Gas Abatement Program required by condition 6-2.

6-4 The proponent shall make the Greenhouse Gas Abatement Program required by condition 6-2 publicly available.

7 Stack Emissions and Ambient Air Quality Monitoring

7-1 Prior to commencement of construction, the proponent shall demonstrate that the plant has been designed to ensure that best available, practicable and efficient teclmologies are to be used to minimise total air emissions from the power station to meet emission li1hits consistent with cmTent industry standards and ambient air quality standards, to the requirements of the Minister for the Environment on advice of the Enviromnental Protection Authority.

Page 6: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

7-2 Within six months following the commencement of constmction, the proponent shall prepare a Stack Emissions Management and Ambient Air Quality Monitoring Plan, to the requirements of the Minister for the Environment on advice of the Environmental Protection Authority.

The objectives of the plan are:

• To ensure that air emissions from the ongoing operation of the power station are minimised; and

• To ensure that high quality data are available to model and verify ambient air quality, and to provide input to a future Air Quality Management Framework for Collie.

This Plan shall address:

I. ongoing management of air emissions during the operation of the power station;

2. monitoring of air emissions;

3. monitoring of ambient air quality; and

4. public reporting of air emissions, ambient air quality and any complaints about air etTIJSS!OnS;

and shall be developed in consultation with the following parties:

• Environmental Protection Authority; • Department of Health; • Industry stakeholders; and • Community stakeholders.

7-3 The proponent shall implement the Stack Emissions Management and Ambient Air Quality Monitoring Plan required by condition 7-2.

7-4 The proponent shall make the Stack Emissions Management and Ambient Air Quality Monitoring Plan required by condition 7-2 publicly available.

8 Saline Wastewater Discharge

8-1 The proponent shall not discharge saljne wastewater from the power station into the existing Collie Power Station saline wastewater pipeline other than in accordance with a Saline Water Discharge Quality Plan prepared to the requirements of the Minister for the Environment on advice of the Environmental Protection Authority.

This Plan shall address the following:

Page 7: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

1. Continuous on-line monitoring of flowrate, temperature, conductivity, and turbidity;

2. Appropriate additional monitoring, with adequate analytical limits of reporting, to control discharge levels of any process additives and other environmental

· contaminants necessary to:

protect the enviromnental values of ecosystem health, recreation and aesthetics, fishing and aquaculture, and industrial water supply;

protect a high level of ecological protection outside the zone of initial dilution for the marine outfall;

protect a low to moderate level of ecological protection inside the zone of initial dilution for the marine outfall;

meet the discharge licence for the pipeline into the marine enviromnent.

3. The concentration of oxidising biocides and antiscalants in the brine discharge necessary to:

protect the established environmental values;

protect the established levels of ecological protection; and

meet the discharge licence for the pipeline into the marine environment.

8-2 The proponent shall implement the Saline Water discharge Quality Plan required by condition 8-1.

8-3 In the event that monitoring identifies unacceptable impacts, the proponent shall as soon as practicable undertake modifications to the method of saline wastewater discharge to mitigate these impacts.

8-4 The proponent shall make the Saline Water Discharge Quality Plan required by condition 8-1 publicly available.

9 Decommissioning Plans

9-1 Within six months following the commencement of constmction, the proponent shall prepare a Preliminary Decommissioning Plan, which provides the framework to ensure that the site is left in an environmentally acceptable condition to the requirements of the Minister for the Environment on advice of the Environmental Protection Authority.

The Preliminary Decommissioning Plan shall address:

Page 8: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

I. the rationale for the siting and design of plant and infrastructure as relevant to environmental protection, and conceptual plans for the removal or, if appropriate, retention of plant and infrastructure;

2. the long-term management of ground and surface water systems affected by the power station, coal stockpiles, waste disposal areas a11d associated infrastructure; .

3. a conceptual rehabilitation plan for all disturbed areas and a description of a process to agree on the end land use(s) with all stakeholders;

4. a conceptual plan for a care and maintenance phase; and

5. management of potentially polluting materials to avoid the creation of contaminated areas.

9-2 At least 12 months prior to the anticipated date of decommissioning, or at a time agreed with the Environmental . Protection Authority, the proponent shall prepare a Final Decommissioning Plan designed to ensure that the site is left in an environmentally acceptable condition to the requirements of the Minister for the Environment on advice of the Environmental Protection Authority.

The Final Decommissioning Plan shall address:

I. the removal or, if appropriate, retention of plant and infrastructure in consultation with relevant stakeholders;

2. the long-term management of ground and surface water systems affected by the power station, coal stockpiles, waste disposal areas and associated infrastructure;

3. rehabilitation of all disturbed areas to a standard suitable for the agreed new land use(s); and

4. identification of contaminated areas, including proviSIOn of evidence of notification and proposed management measures to relevant statutory authorities.

9-3 The proponent shall implement the Final Decommissioning Plan required by condition 9-2 until such time as the Minister for the Environment determines, on advice of the Environmental Protection Authority, that the proponent's decommissioning responsibilities have been fulfilled.

9-4 The proponent shall make the Final Decommissioning Pla11 required by condition 9-2 ·publicly available.

Page 9: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Procedures

1 Where a condition states "to the requirements of the Minister for the Environment on advice of the Environmental Protection Authority", the Environmental Protection Authority will provide that advice to the Department of Environment for the preparation of written notice to the proponent.

2 The Environmental Protection Authority may seek advice from other agencies or organisations, as required, in order to provide its advice to the Department of Environment.

3 Where a condition lists advisory bodies, it is expected that the proponent will obtain the advice of those listed as part of its compliance reporting to the Department of Envirom11ent.

HON MARK McGOWAN MLA MINISTER FOR THE ENVIRONMENT; RACING AND GAMING

2 4 MAY2006

Page 10: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Notes

1 The Minister for the Environment will detennine any dispute between the proponent and the Environmental Protection Authority or the Department of Environment over the fulfilment of the requirements of the conditions.

2 The proponent is required to apply for a Works Approval, Licence and Registration for this project under the provisions of Part V of the Environmental Protection Act, 1986.

3 Within this statement, to "have in place" means to "prepare, document, implement and maintain for the duration of the proposal".

Page 11: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Schedule 1

Bluewaters Power Station Phase II (Assessment No. 1525)

The proposal is to construct and operate a 200 megawatt power station known as the. Bluewaters II Power Station adjacent to the proposed Bluewaters Power Station (i.e. Bluewaters I Power Station) on a site located approximately 4 kilometres north-east of Collie (Figure 1). It will be a sub-critical coal-fired base-load generation facility with a nominal generating capacity of up to 200 Megawatts. The Bluewaters I! Power Station will supplement the Bluewaters I Power Station and supply electricity via the South West Interconnected System (SWIS). Power from both power stations will be offered as an option for Western Power Corporation's Stage 2 Power Procurement Process (PPP) for the provision of an additional 300 Megawatts of base-load capacity.

The power station will comprise the following components:

• boiler and turbine power block;

• mechanical draft cooling tower;

• flue gas cleaning equipment;. and

• generator transformer switchyard.

The following components will be used by the Bluewaters II Power Station. These components will be substantially in place to suppmi the Bluewaters I Power Station:

• a 1 00 metre stack;

• ash and dust disposal plant;

• water treatment plant;

• transmission line connection to Westem Power Corporation switch yard;

• buildings for administration, stores, water, sewage treatment, and chemical storage;

• liquid fuel storage facilities (typically for start-up purposes);

• communications and control systems;

• water supplies;

• electrical supplies;

• drainage systems;

• roads and fencing; and '

• saline wastewater discharge through the existing Collie Power Station ocean outfall.

The plant layout is shown in Figure 2. A diagram which illustrates the input and output flows for the power station is shown in Figure 3.

The main characteristics of the proposal are summarised in Table 1 below.

Page 12: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Table 1 - Key Proposal Characteristics (Assessment No. 1525)

ELEMENT DESCRIPTION General .

. .. . .

I. Project Purpose: To produce electricity to supply to the SWJS grid or direct to customers 2. ·construction Period: Approximil.tely 30 months to commercial operation 3. Project Life: Approximately 30 years 4. Power Plant Type: Subcritical coal fired power station 5. Power Generating Capacity: Up to 200MW., 11ominaL 202.3MW design 6. Plant Them1al Efliciency: HHV 36.4%- LHV 38.6% 7. Pia m Operation: Base load operation 24 hours per day, 365 days per year 8. ShU!down Time: Plant maintenance shutdowns lllllY be scheduled annually 9. Maximum Facility Footprint: 350m x 150m area 10. Maximum Total Area: 15 hectares

Plant' Facilities .

11. Stacks: I J 2. Height of Stack: lOOm 13 Diameter ofStllck: 4.!3m 14. Cooling Towers: 1 set 15. Liquid Fuel Storage Tanks: 2 x 100,000 litres and! x !0,000 litres 16. Boiler: Balanced draft pulverised coal steam generator mulched to steam turbine capacity 17. Steam Turbine: Tandem compound reheat steam turbine with synchronous ulternator- 200MW,. 18. Wastewater collection: Pucka 'e treatment nlam

Utilities .

19. Water Supply: 3.25GLiyr sourccd from mine dcWlltering at Ewington I 20. Coal Supply: 0.7Mtpa viu conveyor owned and operated by Griffin Coal Mining Company 21. Transmission Line LCJ.wth: lOOm unto 3km de Jending on interconnection noint as re(luired bv Western Power

Emissions 22. Noise: Less than 60di3(A) ut l50m from the p·lant. Less than 29dB(A) llt nearest residence in Col!ie 23, Flue Dust: 47mg/Nn)~ at 7% 0 2 dry basis; 9gls; 227tpa 24. Nitrogen Oxides: 606mg/Nm) at 7% o~ dry basis; 121 gls; 3050tpa 25. Sulphur Oxides: !490mg/Nm3 at 7%01 dry basis; 296gls; 7470tpa 26. Greenhouse Gases: l,300,000tpu eo~ e 27. Carbon Monoxide: 500mg/Nm) at 7% 0 1 dry basis; 93gls; 2350tpa 28. Volutilc Orgunic Compounds: 32kg/yr 29. PA!:ls: 6.0kg/yr 30. Ar:scnic: 6.7kg!yr 31. Cadmium: 8.5kg/yr 32. Chromimn compounds: !.5kg/yr 33. Lead compounds: 3lkg/yr 34. Mercury: 31kg/yr 35. Fluorides: 17 ,OOOkglyr (instantaneous rate estimated to be less than 590rng/s) 36. POPs inc. Dioxins and Fun111s: Less than 0.5 grams per year

Waste .

37. Ash: I 75,000tpa disposed to the adjacent mine (Ewington l) 38. Scptage: Pack<~ged treatment plant 39. Saline Water: !.2GUyr

Workforce .

40. Construction: Approximately 150 personnel ut the peak of construction 41. Oncrations: Uo to 30 full time ooerations and maintenance ocrsonnel

Page 13: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Key Proposal Characteristics (Assessment No. 1525)- continued

Abbreviations

co,e dfl(A) gl> GUyr HI-IV inc. kg kg!)~'

LHV m mg!Nm1

carbon dioxide equivalents decibels A weighted grams per second gigalitrc; per year higher heating value including kilograms kilograms p~r year lower heating value metres milligrams per st:mdard <:ubic metre

Figures (attached)

Figure 1: Figure 2: Figure 3:

Regional location Plant layout Input - output flow diagram

mg/s Mqia MW MW, o, pa PA!·Is POPs SWI$

'"' %,

milligrams per second million tonnes per annum megawatts megawatts scm out oxygen per annum polyC>•clic aromatic hydrocarbons pcrsistcm organic pollutams South West Interconnected System tonnes per annum percent

Page 14: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

0

~ (l 3?5 75Dm

"""" MGAS4 Zo~ SO ·-'----------

Railway -- Watercoarse --- Transmision Une

• Building --Mine Areas - Coo!angatta Industrial Estate

- ~-- ... ··., __

Figure 1:

Ewington 1 Mine

,,_

Ewington 2 Mine

a

,::::=

0

0

11.

. -.,:_....,_

i

LOCALITY

Suuthcm On·a"

0

0

GRIFFIN ENERGY BLUEWATERS POWER STA PLANT LOCATION

Regional location (Source: Figure 3 from Griffin Energy Pty Ltd 2005a)

Page 15: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

N 6312050 N 6312050 E 427805 ---------------- --- ----- ---------------------------------------------------------------~

D@

0 5

8 ~

m 8

9

--------------- -------------------7! N6311850 ,

No Description E 428035 i · 1 Coal Transfer Point from mine 2 Plant Coal Conveyor 3 Coal Crusher House 4 Raw Water Reservoir 5 Raw/Fire Fighting Pump House 6 Compressor House 7 PreTreatment Plant Area 8 Filtered Water Tank 9 D.M. Water Plant 10 I .D. Cooling Tower 11 CW I ACW Pump House 12 Effluent Treatment Plant 13 Diesel Generator House 14 Fuel Oil Tank Farm Area 15 Warehouse I Laboratory I Workshop 16 Power Block ~ TG Ha!! 17 Boiler 18 E.S.P. 19 E.S.P. Cohtrol Room 20 Hydrobin 21 Ash Silos 22 Administration & Canteen Building N 6311655 23 Plant Parking Shed E 428035 24 Plant Security Office 25 Plant Main Gate 26 Side Gate for Ash I OH Tankers 27 Transformer Area 28 Main Control Room

6 1@1 [ill]

r------1

~ "'@0 ~ "' : _<:,_ __ _j

' I

Jv 0 25 SOm

""" MGA94 Zone SO

. N6311655

__ c_ __ Q? ___________ ~

~ GRIFFIN ENERGY - BLUEWATERS 1 + 2

PLANT

Figure 2: Plant layout (Source: Figure 4 from Griffin Energy Pty Ltd 2005a)

Page 16: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Bluewaters fl Power Station Input- Output diagram

r:·Q( iOH!I"'"JUJl"l

Coal

325 G i~Fil rtres 'vVB tor

HI.! · ,1\J JWl'Ll~:.;_; ·u;_. ,~i'iN.>.il ,;r.•;;_i!'1:1 1-'•1 • ~J<:~JI:Jr·:~

~r!OO M-eg(l '1/•/Qtt.

EduBVi{tte rs 11 P0\\10f

Stali~'.Jf:,

·1 .,31JO G:•Jd•'dt~! h.:::.·Jre. ti!lt:.-.'.::tlir:.:Hy l•.::!- c·k!·:::k~ei:'fy f}:'i dl 9·~ C1{10::H'~~nt !'tO..~Jr"f.:. !2(~1~:'i1!:.~1y r(ll lti1Elln::J! U!'IE•

i .2 {.; ~.3lirres ·:;Elt:'ie 'J.'3!er m ocean d'i$.:::7\arge 2JJGt~alitres •.<:.J<er Ios-: :i"l e1,aporatmn r) .S G •;.~alitres ',J~,o,:r'Br u~..:!·j 1:n p:·•()Ce-s:s

Discharge to Atmosphere z;:7 !J;);''H'l€1S Ou<iJ· ·:J~JSt

::, ,OGO l(lf)t)B:G 1\iJlrous ()o:ir.J.::.t-::o / 4:-'(1 ir.ITT8::; n):l>::I~S Of 8,J}oi11..Lt

2: :~fi) 1~nr~o:::r:; ·~.;.r.;o, Mcrt(N.•dc ·1 ,:3()) ,•})(! ionr..;:~~._G:~ rtx;n Dio:dr.io

::o ·i<o \.'olt:~tiiG ()rgJr•ITC- Cr.wllpOI)r~·-J:;. (i_(,l ·r::[! .P(dy\:::;··:::hc ton:)T1i?4il-:: Hyth::.u;;tJO"t.0n!5

(i.l ,Kg Ar;:-R:ri.t:: 8.5 h!J (::tn:iT!iJJrn

! 5 ;<g C"Cir(tTiUTl C·tiTq<()',n'ld::;. :)1 'i(~ te;d Cr.mpovn;:l:;.

~; 1 .Ko ~..1El~cvr~· ! "(.(!(lC: i\q Fh)Or~j'(l".;;

L0s.s l·ift'; (l !.: 9r~r.1 Pot~i~'li-Jnl Org8n ic. ·Pc1iul;r~nt-s ino:uding 010::-;'~ns ~1d Fur.; m

Figure 3: Input - output flow di~gram (Source: Figure 6 from Griffin Energy Pty Ltd 2005a)

Page 17: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Schedule 2

Proponent's Environmental Management Commitments

January 2006

BLUEWATERS POWER STATION- PHASE II

(Assessment No. 1525)

Griffin Power Pty Ltd

Page 18: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Proponent's Environmental Management Commitments- January 2006

BLUEWATERS POWER STATION- PHASE II, SHIRE OF COLLIE (Assessment No. 1525)

Note: The term "commitment" as used in this schedule includes the entire row of the table and its six separate parts as follows:

• a commitment number;

• a commitment topic;

• the objective of the commitment;

• the 'action' to be undertaken by the proponent;

• the timing requirements of the commitment; and

• the body/agency to provide technical advice to the Department of Environment.

Commitment No.

2

Topic

Biodiversity

Terrestrial Flora:

• Vegetation Communities

• Declared Rare Flora and Priority Flora

Objective

Minimise clearing to establish power station. Examine all environmental factors and implementation of mitigation

Action

Develop and implement an EMS for the proposal which meets ASINZS ISO 14001:1996.

Timing

Prior to commissioning and ongoing.

plans and activities_ I The EMS will cover all elements in the standard as a minimum as well as the action items listed in this table:

l.1

L2

Removal of vegetation will be minimised I 2.1 where possible through appropriate location of the power station and associated infrastructure. l11e project will maximise the use of existing cleared land.

Manage construction works to minimise

Develop and implement a construction phase I Prior to construction. EMP"

Develop and implement an operational phase I Prior to commissioning and EMP. ongoing

Preparation and implementation of a I Prior to construction. Vegetation and Flora Management Plan addressing identification of areas not to be disturbed, site clearance procedures to manage construction works so as to avoid disturbance to native vegetation, and weed management practices.

• Flora of Conservation I disturbance to significant vegetation ! 2.2 Significance communities and priority flora.

If any clearing of natiVE: vegetation is I Prior to construction. determined to be required, the area will be

Maintain the abundance, species diversity, geographic distribution and productivity of vegetation communities.

surveyed and mapped prior to the commencement of construction, and the significance of impacted vegetation will be detailed.

Advice

Various stakeholders as indicated below.

Various stak~holders as indicated below.

Vmious stakeholders as indicated below.

Page 19: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Commitment No. 3

4

Topic

Terrestrial Fauna:

• All Fauna

• Specially Protected (Threatened) Fauna

Surface· Water Quality

I

Objective Action Timing

Maintain the abundance, spec1es I 3.1 Preparation and implementation of a Fauna I Prior to construction. Management Plan to ensure off-site and diversity, geographic distribution · of

terrestrial fauna.

Protect Specially Protected (Threatened) Fauna, consistent with the provisions of the Wildlife Conservation Act.

To minimise erosion and impacts on local surface water or do\vnStream environments.

indirect fauna impacts are minimised.

This may include: • ensuring physical disturbance is kept

within designated areas, • establishment of procedures,

monitoring requirements, workforce training and responsibilities to minimise disturbance of signiflcant terrestrial fauna,

• regular liaison with local CALM office to maintain acceptable management practices,

o development and implementation of fire prevention and contingency measures.

4.1 Cooling water discharge will not be directed to the surface water·system.

Prior to construction.

4.2 The plant will be designed to ensur~ that I Prior to commissioning and contaminants are not released to the ongoing. environment.

4.3 Contamination of surface water will be minimised I Prior to construction. by methods such as:

o suitably designed drainage areas and settling basins;

• appropriate design of areas to contain hazardous material such as hydrocarbons;

• washdown water will be collected in drains and passed through sediment traps and oil separation systems prior to transfer to settling ponds.

4.4 Develop and implement construction phase Surface I Prior to construction. Water Management Plan as part of construction phase EMP.

4.5 DeVelop and implement operational phase Surface ! Prior to commissioning Water Management Plan as part of operational phase EMP.

4.6 Document the existing surface water quality in the ! Prior to construction. project area.

Advice

Water & Commission.

Water & Commission,

Water & Commission.

Water & Commission.

Water & Commission.

Water & Commission.

Rivers

Rivers

Rivers

Rivers

Rivers

Rivers

Page 20: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Commitment No. 5

6

7

Topic

Groundwatcr Quality

Water Suppl)'

Marine Water Quality

Objective Action

Maintain the quality of local and regional I 5.1 groundwater to ensure that existing and potential uses, including ecosystem maintenance, are protected.

Timing

The plant will be designed to ensure that I Prior to construction. contaminants are not released into the environment.

5.2 All potentially hazardous materials will be Prior to commissioOing and

5.3

5.4

6.1

6.2

stored in accordance with relevant legislation ongoing. and regulations. Develop and implement construction phase Prior to construction. Groundwater Management Plan as part of construction phase EMP. Develop· and implement operational phase ! Prior to commissioning Groundwater Management Plan as part of operational phase EMP.

Develop and implement an appropriate water ! Prior to construction supply and management strategy which will satisfy requirements during both the construction and operation phases of the project. Develop and implement construction phase ! Prior to construction. Water Management Plan as part of Construction EMP.

6.3 Develop find implement operational phase Water Management Plan as part of operational EMP.

Prior to ongoing

commissioning

Maintain marine ecological integrity and ! 7 .I biodiversity and ensure that any impacts

Cooperate with operator of Collie A disposal line to ensure that effluent water meets discharge licence conditions prior to introduction into line.

Prior to commissioning ongoing.

on locally significant marine commuriities are avoided.

7.2 Determine final details of the wastewater quality and quantity and conduct a detailed modelling assessment of the ocean outfall discharge (with the existing operator of Collie A) to demonstrate the dilution criteria that can be achieved with the additional saline water discharge. An assessment of the levels of other contaminants (such as biocides) discharged into the ocean will be included to ensure that they meet the ANZECC/ARMCANZ 2000 Water Qul).lity Guidelines at the edge of the mixing zone.

7.3 Design and implement a Saline Water Management Plan incorporating a saline wastewater monitoring programme and wastewater management contingency plan, as part of the Operations EMP.

Prior to commissioning

Prior to commissioning

and

and

Advice

Water & Commission.

Water & Commission.

Water & Commission.

Water & Commission.

Water & Commission.

Water & Commission.

Water & Commission.

Rivers

Rivers

Rivers

Rivers

Rivers

Rivers

Rivers

Operator of Collie A discharge line.

Operator of Collie A discharge line.

Operator of Collie A discharge line.

Page 21: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Commitment No. 8

9

Topic

Contamination

(Oil and chemical sp.ills)

Solid and Liquid Wastes

Objective Action

To minimise potential adverse effects, ! 8.1 risk and liability associated with management of oils and chemicals.

To minimise potential contamination to the receiving environment.

8.2

8.3

8.4

8.5

9.1

9.2

9.3

9.4

9.5

9.6

9.7

9.8

9.9

Timing Advice

During the construction phase, potentially I Prior to construction. l DOCEP contaminating materials and activities will be stored and managed in accordance with regulatory requi'rements and good practice. Containment of any spi\lages or leakage wi!l be a priority. The plant will be designed to ensure spillages Prior to commissioning and ! DOCEP of chemicals or hydrocarbons are contained ongoing. and collected. During operation of the plant, all potentially Ongoing contaminating or hazardous materials will be stored in accordance with relevant legislation and regulations Develop and implement construction phase I Prior to construction. Contamination Management (Spills) Plan as part of construction phase EMP. Develop and implement operational phase I Prior to commissioning Contamination Management (Spills) Plan as part of operational phase EMP.

During- both the construction and operation phases of the project, solid and liquid wastes wi!l be minimised through resource recovery, reuse and recycling programmes. All materials requiring disposal will be managed in accordance with the requirements of the relevant authorities and regulations. Waste hydrocarbons \vill be contained, collected and disposed off~site by an approved method. Domestic wastewater will be managed on site via a packaged treatmerit plant. Develop and implement a Flyash Management Plan as part of the operational phase EMP. Cooling water discharge will be directed to Western Power's saline Water Pipeline. Develop construction phase Waste Management Plan as part of the construction phase EMP. Implement construction phase Waste Management Plan. Develop and implement operational phase Waste Management Plan as part of the operational phase EMP.

Prior to construction and ongoing.

Prior to commissioning and ongoing.

Prior to construction

Prior to commissioning and ongoing Prior to commissioning and ongoing ·

Prior to commissioning

Prior to commissioning

Prior to construction

Prior to commissioning

DOCEP

DOCEP

DOCEP

Shire of Collie.

Shire of Collie.

CALM

Page 22: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Commitment No. 10

!I

12

Topic

Noise and Vibration:

• Construction Phase

o Operations Phase

Objective

To minimise noise emissions and comply with Noise Regulations during construction and operations.

Air Emissions: I To minimise environmental or human health effects or significantly impact on

• Construction Phase l amenity. (?articulate I Dust)

• Operations Phase (Particulate I Dust (PM w), Oxides of Sulphur (S02), Oxides of Nitrogen (NOx), VOCs, etc.)

Action

10.1

10.2

I 0.3

ILl

IL2

113

11.4

11.5

11.6

Greenhouse Gas Emissions To minimise atmospheric emissions l 12.1 where practicable and comply with relevant guidelines (eg EPA Guidance No. 12).

12.2

123

Appropriate noise abatement technology will be installed to ensure the power station meets relevant noise criteria. Develop and implement construction phase Noise Management Plan as part of the construction phase EMP. Develop and implement operational phase Noise Management Plan as part of the operational phase EMP, including periodic monitoring to ensure compliance with Noise Regulations.

Dust levels will be managed by minimising vegetation clearing, the use of dust suppression equipment and appropriate site management. Best practice management will be used in the design and construction of coal handling. Develop and implement construction phase Dust Management Plan as part of construction phase EMP. Develop and implement operational phase Dust Management Plan as part of operational phase EMP. Develop and implement an operational Emissions Monitoring and Management Plan. Use EPA Guidance Note Number 55 to assist design.

Timing

Prior to construction.

Prior to construction

Prior to commissioning and ongoing.

Prior to construction.

Prior to commissioning and ongoing. Prior to construction

Prior to commissioning and ongoing.

Prior to commissioning and ongoing. Design phase.

Share in the contribution of financial and in I Ongoing. kind support by the Griffin Group valued at Sl40,000pa to the Cooperative Research Centre for Coal in Sustainable Development (CCSD) for further investigation into clean coal technologies.

Initiate and develop other research and I Ongoing. development projects to the point where they can be included as offsets in the GHG program.

Establish and implement an internal GHG trading sYstem within the Griffin group of companies to maximise benefits from the Greenhouse Gas Emissions Management Plan.

Upon signing the commitment to the Greenhouse Challenge.

Advice

Shire of Collie

Shire of Collie

CCSD

CSIRO, AGO, OOE, CALM, WA Depart. of Aglicu!ture and other relevant stakeho!ders

Australian Greenhouse Office

Page 23: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Commitment Topic Objective Action Timing Advice No. 13 Recreational Activity Maintain recreational values for the local 13.1 VisUal and noise impact will be minimised Prior to construction and Shire of Collie.

community as far as practicable. through planning design and screening ongoing. Local community strategies (eg. noise bunds and natural barriers).

132 Access to adjoining bush will not be affected. Prior to constnJCtion and Shire of Collie. ongoing Loc~iJ community

13.3 Liaise with local community, produce and Prior to commissioning and Shire of Collie. implement landscape and access management ongoing Local community plan to reduce impact.

14 Visual Amenity To maintain visual amenity 14.1 Potential impacts on visual amenity will be Prior to constructiOn and Shire of Collie. minimised through planning design and ongoing. Local community screening strategies (eg. natural barriers).

14.2 Vegetation management and landscape Prior to construction and Shire of Collie. strategies will be developed as appropriate. ongoing. Local community

15 Aboriginal Culture and To minimise disturbance to areas of 15.1 Develop and implement Heritage and Culture Prior to construction. Local Indigenous Heritage Aboriginal and cultural significance. awareness program for employees. commwlity. DIA

Shire of Collie.

15.2 If sites of aboriginal significance are found During construction and Department ·of during construction, application for clearance ongoing Indigenous Affairs. under Section 18 of the Aboriginal Herirage Act 1972 will be sought from the Minister for Indigenous Affairs before disturbance .

.

16 Public Risk To ensure that the risk to public safety is 16.1 Develop and implement local community Prior to construction. Shire of Collie.

Abbreviations AGO Australian Greenhouse Office

as low as reasonably practicable liaison program. Local community. (ALARP) and to minimise the potential creation of hazardous working 16.2 Hazardous materials will be stored and During construction and DolR/ DOCEP environments. handled according to DoiR regulations. ongoing.

16.3 Develop and implement Hazardous Materials Prior to construction. DoiR I DOCEP Management Plan

CALM Department of Coriservation & Land Management CCSD Cooperative Research Centre for Coal in SusJainable Development DlA Department of Indigenous Affairs DOCEP Department of Consumer & Employment Protection DOIR Department of Industry & Resources OOE Office of Energy

Page 24: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

'(

(

Attachment 1- Change to Proposal (Statement 724).

Proposal: BLUEWATERS POWER STATION- PHASE IT

Proponent: Griffin Power Pty Ltd

Change: IN SCHEDULE 1, TABLE 1: KEY PROPOSAL CHARACTERISTICS (ASSESSMENT NO. 1525).

1. Modification of the location plan for the project as outlined 111 figure 1 of Ministerial Statement 724;

2. Clmification of "Maximum Facility Footprint" and "Maximum Total Area" in Table 1, Schedule 1 of statement 724; and

3. Clarification regmding "Infi"astmcture" a11d "Construction Laydown Envelope" meas which were not included in Table 1, Schedule 1 of statement 724.

Features-of original Proposal:

Element Quantities/Description Location Plan Refer Figure 1 Maximum Facility Footprint. 350 m x 150 m area. Maximum Total Area. 15 hectares.

Features of current Proposal: . Element. Quantities/Description Location Plan (relocation of Bluewaters Power Station to Refer new Figure 1 j 530n1 south east of site referred to in EP .A. Bulletin 1160) (attached).

-: _-Maximum-Faciilly Footprintc (ana of ]JOWer generati.t1g::: AppJQXimately2j.3 h<t_:::::~-unit) Maxi.tnum Total Area (total a1·ea of power station pla11t) Approxi.tnately 15 ha

-.. J. Atlclllaryinfrastructure 1 Approxnnately 23.6 ha

Construction Laydovl'n Envelope Approximately 18.7 ha

Figures (attached): Figure 1. Bluewaters I at"1d II Power Stations: Regional Location Figme 2. Bluewaters I a11d II Power Stations: Pla11t Layout Figme 3. Bluewaters I and II Power Stations: Pla11t Schematic Figme 4. Bluewaters I md II Power Stations: Ii1put-Output Diagra1n

Approval D~te: f /to/ o {

Page 25: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

-------- ,-; i. --"'

Drawn: CAD Resources.- www.cadr:esources.com.au- Te\: {08) 9246 3242- Fax:- (06) 9246 3202- Datr:1: Seph6o5- t:~o R!!f: g1927 _p02.d'g~c~-_::A:4_-~R:'~'~D:_ _____ :_ ______________ ...:. _______ _

N 6312050

E42IOUO- --------------------- ------------'----------!------------- N 6312050 . 0@ \ 11 : ------------------ -- -- .. -- ------~ " I ' ' I ' ' I ' ' I ' ' I ' ' I ' ' I ' ' I ' ' I ' i

@

\ '·

N 6311850 E 427805

' '-L_ __________ " ____________________ ,_f:.·. No .1 2 3 4 5 6 7 8 9 10

N 6311850 !· 1

Description E 428035 ·. !; [ Coal Transfer Point from mine , , Plant Coal Co"nveyor : \ Coal C~usher House 1 Raw Water Reservoir 1

R-aw/Fife Fighting Pump House · · ! C8mpressor House t

PreTreatment Plant Area : l Filtered Water Tank ·:-: D.M. Water Plant -' 1 1.0. Coortng Tower . \ CW /.ACW Pump House 1

Effluent Treatment Plant · 1

Diesel Generator House J

Fuel Oil Tank Farm Area ·, 1 Warehouse I laboratory f Workshop r

I

[TI

0

D ' I ' ' I ' '

~ 0 25 50m L_j_ _ ___j

Scalr.: MGA9~ Zone 50

11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Power Block- TG Hall Boiler E.S.P. E.S.P. Control Room Hydro bin

I , ~ ' N 6311655

i __ _ ,, __ __ _C}J -----------------------------~-----~----- r28430 Ash Silos Adm'mistration & Canteen Building Plant Parking Shed Plant Security Office Plant Main Gate Side Gate for Ash I Oil Tankers Transfmmer Area Main Control Room MCC Room

N 6311655

E 42t:IV60

L._----~--~-------·------

Figure :l BLUEVVATERS 1 + 2 PLANT SCHEMATIC

Page 26: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

,----_

3202 A4-R9V0

~

" 0

----------------1---~-

0

0

0

ngton 2 Mine

~ ~;:,

• D

0 0

Sr!rrlfl<:lfl

Uc":rll

LOCALITY

I

0

0 I

Figur<l 1 BLUEWATERS POWER STATION REGIONAL LOCATION

Page 27: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

z 0

·~ en a: w s: 0 tl.J-­f.l) ::::>" a:o W>-1--<(

N<(.J ID 5: J--. i-UJZ ::I;:><( .~...J:..J u..ma..

Page 28: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Figure 4: Bluewaters Power Station - Input and Output Flow Diagram

'(

-- ---- ----- - --------'''-'~--'---'--·"'-

(

Page 29: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Attachment 2 to Statement 724

Change to Proposal

Proposal: Bluewaters Power Station Phase II

Proponent: Griffin Power Pty Ltd.

Amendment of Schedule 1 -Key Proposal Characteristics

The changes to the proposal are listed below:

• Power generating capacity - an increase from 200 megawatts to 208 megawatts (i.e. 4% increase).

• Construction laydown areas - an increase in the size of the laydown area • Air emissions profile -changed due. to the use of an individual stack (instead

of a shared stack), increased generating capacity (4%), and the use of coal with a maximum sulphur content of 0.38%.

• Project layout- relocation of the wastewater treatment plant and re-alignment of the coal conveyor.

Features of previously approved Proposal:

Element Quantities/Description Power generating capacity up to 200 megawatts

Flue dust 47 mg/Nm3; 9g/s; 227 tpa Nitrogen oxides 606 mg/Nm3; 12lg/s; 3050 tpa Sulphur oxides 1490 mg/Nm3; 296 g/s; 7470 tpa

Carbon monoxide 500mg/m3; 93g/s; 2350 tpa Greenhouse gas 1300 000 tpa

Volatile Organic Compounds 32 kg/yr PAH 6.0 kg/yr

Arsenic 6.7 kg/yr Cadmium 8.5 kg/yr

Chromium compounds 1.5 kg/yr Lead compounds 31 kg/yr

Mercury 31 kg/yr Flourides 17 000 kg/yr

Ash 175 000 tpa

Page 30: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Features of changed Proposal:

Quantitiesillescri tion Power up to 208 megawatts

Sulphur oxides Carbon monoxide Greenhouse gas 1359 000

Volatile Organic Compounds 33.3 kg/yr PAH 6.2 k yr

Arsenic 6.8 kg/yr Cadmium 8.8 kg/yr

Chromium compoundS 1.6kg/ Lead corn ounds 32.2 kg/yr

Mercury 32.2 kg/yr Flourides

Ash 182 000

Figure 1. Layout map revised

Approved under delegation from Minister for the Environment:

Approval Date: 1 8 SEP 2007

Page 31: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

~ riQ.

= .... ~ ,... . ~

<-< c = ~

a ~

"0

~ .... r7J ~ Q..

01 Waste Water Pond Unit I 02 Waste Water Pond Unit 2 03 Water Storage Pond/Raw Water Reservoir 04 Water Treatment Plant 05 Workshops, Administration, Canteen,

Warehouse and Laboratory Building 06 Sewerage Treatment Plant 07a Car Park 07b Com1ruction Car Park (temporary) 08 Cooling Tower Unit I 09 Cooling Tower Unit 2 10 Western Power Sub Station (not pan of

Bluewarers Project) 11 Water Pre-treatment Plant for both UnitS 1 & 2 12 Coal Delivery Conveyor 13 Boiler 14 Eme rgency Coal Stockpile 15 Service Water Storage Tanks 16 Fu:e F ighting Pump Station 17 Chemical Storage Buildings I Rydrobin 18 Drainage System 19 MainGate 20 Security Office 21 Fuel Oil Tank Farm Area 22 Compressor House 23 Side Gate for Ash 24 Coal Transfer Point 25 AshSilo 26 ESP I Baghouse and Control Room 27 bie$el Generator 28 MCCRoom 29 208MW Turbine Generator I Power Plant 30 Transfonner Area 31 CW I ACW Pump House 32 Main Control Room for both UnitS 1 & 2 33 SCC (Submerged Chain Conveyor) Ponds 34 Waste Water Treannenr Plan~ 35 Drainage Outlet Works 36 Access Road

F ig u r e 2 BLUE W ATERS P R OJ E CT DETAILED SITE L AYO UT

Page 32: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

. ·--------··----

Attachment 3 to Statement 724

Change to Proposal

Proposal: The construction and operation of a sub-critical coal-fired base-load power generating facility (Bluewaters Power Station - Phase II) with a nominal generating capacity of 208 megawatts on a site located approximately four kilometres north-east of Collie.

Proponent: Griffin Power 2 Pty Ltd

Change: Increase to ancillary infrastructure area.

Amendment of Schedule 1 -Key Proposal Characteristics

Features of currently approved Proposal:

The Proposal Table 1

Element

Ancillary Infrastructure

Quantities/Description

Not defmed in Schedule I.

Amended to 23.6 ha in Attachment I.

Features of approved change to Proposal:

The Proposal Table 1

Element

Ancillary Infrastructure

Approved under delegation

Quantities/Description

Approximately 23.75 ha

from the Minister for the Environment:

Approval Date: ~~ . f _.1() (

Page 33: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Attachment 4 to Statement 724

Change to Proposal

Proposal: Bluewaters Power Station- Phase 11, Shire of Collie

Proponent: Griffin Power 2 Pty Ltd

Change: Addition of a second ash disposal site.

c t f omponen so ti curren :1y approve dP I roposa: Component Quantitiesffiescription Ash 182,000 tpa disposed to the adjacent

mine (Ewington I).

Components of approved change to Proposal: Component Ash

tpa ~ tonnes per annum

Approved under delegation from the Minister for Environment: Delegation under section 18 of the Environmental Protection Act 1986 Dated 24 November 2004

Quantities/Description 182,000 tpa maximum disposed to the adjacent mines, Ewington I and Ewington II.

S45C Approval Date: ____ _

Page 34: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Attachment 5 to Statement 724

Change to Proposal Proposal: Bluewaters Power Station – Phase II, Shire of Collie Proponent: Griffin Energy Pty Ltd Change: Increase greenhouse gas emissions to 1,562,000 tpa CO2e Key Characteristics Table: Element Description of approved proposal Description of approved changes to

proposal (bolded) General Project Purpose: To produce electricity to supply to

the SWIS grid or direct to customers To produce electricity to supply to the SWIS grid or direct to customers

Construction Period: Approximately 30 months to commercial operation

Approximately 30 months to commercial operation

Project Life: Approximately 30 years Approximately 30 years Power Plant Type: Subcritical coal fired power station Subcritical coal fired power station Power Generating Capacity:

Up to 208 megawatts Up to 208 megawatts

Plant Thermal Efficiency:

HHV 36.4% - LHV 38.6% HHV 36.4% - LHV 38.6%

Plant Operation: Base load operation 24 hours per day, 365 days per year

Base load operation 24 hours per day, 365 days per year

Shutdown Time: Plant maintenance shutdowns may be scheduled annually

Plant maintenance shutdowns may be scheduled annually

Maximum Facility Footprint (area of power generating unit):

Approximately 5.3ha Approximately 5.3ha

Maximum Total Area (total area of power station plant):

Approximately 15ha Approximately 15ha

Ancillary Infrastructure Approximately 23.75ha Approximately 23.75ha Construction Laydown Envelope

Approximately 18.7ha Approximately 18.7ha

Plant facilities Stacks: 1 1 Height of Stack: 100m 100m Diameter of Stack: 4.13m 4.13m Cooling Towers: 1 set 1 set Liquid Fuel Storage Tanks:

2 x 100,000 litres and 1 x 10,000 litres

2 x 100,000 litres and 1 x 10,000 litres

Boiler: Balanced draft pulverised coal steam generator matched to steam turbine capacity

Balanced draft pulverised coal steam generator matched to steam turbine capacity

Steam Turbine: Tandem compound reheat steam turbine with synchronous alternator – 200MWe

Tandem compound reheat steam turbine with synchronous alternator – 200MWe

Wastewater collection: Package treatment plant Package treatment plant Utilities Water Supply: 3.25GL/yr sourced from mine

dewatering at Ewington 1 3.25GL/yr sourced from mine dewatering at Ewington 1

Coal Supply: 0.7Mtpa via conveyor owned and operated by Griffin Coal Mining Company

[removed from table]

Page 35: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Element Description of approved proposal Description of approved changes to proposal (bolded)

Transmission Line Length:

100m up to 3km depending on interconnection point as required by Western Power

100m up to 3km depending on interconnection point as required by Western Power

Emissions Noise: Less than 60dB(A) at 150m from the

plant. Less than 29dB(A) at nearest residence in Collie

Less than 60dB(A) at 150m from the plant. Less than 29dB(A) at nearest residence in Collie

Flue Dust: 47mg/Nm3; 9.4g/s; 237tpa 47mg/Nm3; 9.4g/s; 237tpa Nitrogen Oxides: 500mg/Nm3; 112.1g/s; 2828tpa 500mg/Nm3; 112.1g/s; 2828tpa Sulphur Oxides: 229.9g/s; 5800tpa 229.9g/s; 5800tpa Greenhouse Gases: 1,359,000tpa CO2 e 1,562,000tpa CO2 e Carbon Monoxide: 500mg/m3; 97g/s; 2444tpa 500mg/m3; 97g/s; 2444tpa Volatile Organic Compounds:

33.3kg/yr 33.3kg/yr

PAHs: 6.0kg/yr 6.0kg/yr Arsenic: 6.8kg/yr 6.8kg/yr Cadmium: 8.8kg/yr 8.8kg/yr Chromium compounds: 1.6kg/yr 1.6kg/yr Lead compounds: 32.2kg/yr 32.2kg/yr Mercury: 32.2kg/yr 32.2kg/yr Fluorides: 17,680kg/yr 17,680kg/yr POPs inc. Dioxins and Furans:

Less than 0.5 grams per year Less than 0.5 grams per year

Waste Ash: 182,000tpa maximum disposed to the

adjacent mines, Ewington I and Ewington II

182,000tpa maximum disposed to the adjacent mines, Ewington I and Ewington II

Septage: Packaged treatment plant Packaged treatment plant Saline Water: 1.2GL/yr 1.2GL/yr Workforce Construction: Approximately 150 personnel at the

peak of construction Approximately 150 personnel at the peak of construction

Operations: Up to 30 full time operations and maintenance personnel

Up to 30 full time operations and maintenance personnel

Abbreviations CO2 e carbon dioxide equivalents dB(A) decibels A weighted g/s grams per second GL/yr gigalitres per year HHV higher heating value inc. including kg kilograms kg/yr kilograms per year

LHV lower heating value m metres mg/Nm3 milligrams per standard

cubic metre mg/s milligrams per second Mtpa million tonnes per annum MW megawatts MWe megawatts sent out

O2 oxygen pa per annum PAHs polycyclic aromatic

hydrocarbons POPs persistent organic pollutants SWIS South West Interconnected

System tpa tonnes per annum % percent

Dr Paul Vogel CHAIRMAN Environmental Protection Authority under delegated authority Approval date: 2 September 2009

Page 36: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Attachment 6 to Statement 724

Change to Proposal

Proposal: Bluewaters Power Station - Phase IT, Shire of Collie

Proponent: Griffin Energy Pty Ltd

Change: Increase power generating capacity from 208 megawatts to 212 megawatts

Ke Characteristics Table: Element Description o f approved proposal

General Project Ptuvose: lectricity to supply to To produce e

1---:=,.-------,- -=----,------:--- l- the SW IS gri d or direct to customers Construction Period: Approximate ly 30 months to

Power Generating Ca >acit : Plant Thermal Efficienc : Plant Operation:

commercial o >pcrntion ly 30 years al fired power station gawatts

IIIIV 36.4% - LHV 38.6%

eration 24 hours per day, Base load op 365 days per Plant maintet scheduled an Approximate

~car -Shutdown Time: 1ance shutdowns may be

nuall~ Maximum Facility Footprint (area of p_ower gener_at_i--:'n "'--u_n_itL:--t--- -­Maximum Total Area Approximate (total area of power

station P....:.la-=-n""t ':'-: ----+---,------:-f--'::A'-'-n'-'c.::..:i l.::..:la.:..:.r.L.::.I.::.::n.::.::fr-='a""stc:..n"-tc::..::t.:..:.m::..::·e=----J--=Appro xi mate

Construction Laydown Approximate Envelope Plant facilities Stacks: Hei ht of Stack: lOOm Diameter of Stack: 4.13m - --+-------

ly 5.3ha

ly 15ha

ly 23.75ha ly 18.7ha

--

---.. -

it res and 1 x 10,000 Cooli~lg To,_v-'-e-'-'rs __ : ---f---1---'s_e_t __ _ Liquid Fuel Storage 2 x 100,000 I Tanks: litres

-

-

ft pulverised coal steam Boiler: Balanced dra generator mat ea acit

Steam Turbine:

ched to steam turbine

ound reheat steam Tandem comp turbine with s ynclu·onous alternator -

f--::-::-,------ ---:-:--c---+-=2Q_QMW e Wastewater collection: Packa e treat ment plant

----'---""--

Utilities Water Supply: urced from mine

E'y-~to~-- _ -- --

-

Description of approved changes to proposal (bolded)

To produce electricity to supply to the SWIS grid or direct to customers Approximately 30 months to commercial operation Approximately 30 years -Subcritical coal fired power station Up to 212 megawatts

HI-IV 36.4% - LHV 38.6%

Base load operation 24 hours per day, 365 _days per ~car Plant maintenance shutdowns may be sched~tled annually Approximately 5.3ha

-Approximately 15ha

- -Approximately 23.75ha Approximately 18.7ha

-- --

1 -lOOm --4.13111 I set -2 x 100,000 litres and 1 x 10,000 litres Balanced draft pulverised coal steam generator matched to steam turbine capacity __ Tandem compound reheat steam turbine with synchronous alternator -200MWc Package treatment plant

- - -3.25GL/yr sourcecl from mine dewatering at Ewington 1

·-

Page 37: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

-Element Description of approved proposal Description of approved changes to

proposal (boldcd) Coal Supply: 0.7Mtpa via conveyor owned and [removed from tn ble]

operated by Griffin Coal Mining Company

Transmissioi1 Line lOOm up to 3km depending on lOOm up to 3km depending on Length: interconnection point as required by interconnection point as required by

Western Power \V esterq Power -- -

Emissions ·--

Noise: Less than 60d13(A) at 150m from the Less than 60dB(A) at 150m from the plant. Less than 29di3(A) at nearest plant. Less than 29dB(A) at nearest residence in Collie residence in Collie

t-=:-· - - - -- --47mg/Nm3

; 9.4g/s; 237tpa 47mg/Nm3; 9.4g/s; 237tpa Flue Dust:

Nitrogen Oxides: 500mg/Nm3; 112.lg/s; 2828~)a 500mg/Nnl; 112.1g/s; 2828tpa_

--- -Sulplnn:._Oxjdes: . 229.9g/s; 5800tpa 229.9g/s; 5800tpa_ Greenhouse Gases: 1,562,000tpa C02 e 1,562,000tpa C02 e Carbon Monoxide: 500mgh;13

; 97f!./s; 2444tpa 500mg/m3; 97g/s; 2444tpa

Volatile Organic 33.3kg/yr 33.3kg/yr Compounds: -PAI-ls: -- - - 6.0kg/yr 6.0kg/yr Arsenic: 6.8kg/yr 6.8kg/yr --- --Cadmium: 8.8kg/yr - 8.8kg/yr . -Chromium compounds: 1.6kg/yr

-1.6k_g/yr

Lead compounds: 32.2~g/yr 32.2kg/yr -

Mercury: 32.2kg/yr 32.2kg/yr Fluorides: 17,680kg/yr 17,680kg/yr --POPs inc. Dioxins and Less than 0.5 grams per year Less than 0.5 grams per year Furans: - -Waste -Ash: 182,000tpa maximum disposed to the 182,000tpa maximum disposed to the

adjacent mines, Ewington I and adjacent mines, Ewingtonl and EwingtonJl Ewington II

Septagc: Packaged treatment plant - Packaged treatment plant Saline Water: 1.2GL/yr 1.2GL!yr Workforce Construction: Approximately 150 personnel at the Approximately 150 personnel at the

peak of constructio!1 peak of construction Operations: Up to 30 full time operations and Up to 30 full time operations and

'---maintenance personnel maintenance personnel

Abbreviations LHV lower heating va lue ol oxygen co1c carbon dioxide equivalents Ill metres pa per annum dB(A) decibels A weighted mg!Nm3 milligrams per standard PAHs polycyclic aromatic gls grams per second GUyr gigalitrcs per year HHV higher heating value inc. including kg kilograms kglyr kilograms per year

Dr Paul Vogel CHAIRMAN

mgls Mtpa MW MW,

Environmental Protection Authority under delegated authority

cubic metre milligrams per second million tonnes per annum megawatts megawatts sent out

Approval date: _ _ ;L_5_·_3_~_I_tO __

hydrocarbons POPs persistent organic pollutants SW IS South West Interconneclcu

System tpa tonnes per annum % percent

Page 38: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Attachment 7 to Ministerial Statement 724

Change to Proposal Proposal: Bluewaters Power Station – Phase II Shire of Collie Proponent: Griffin Power Pty Ltd Change: Removal of reference to maximum sulphur oxides in emissions and plant

thermal efficiency. Key Characteristics Table: Element Description of approved

proposal Description of approved changes to proposal (bolded)

General Project Purpose: To produce electricity to supply

to the SWIS grid or direct to customers

To produce electricity to supply to the SWIS grid or direct to customers

Construction Period: Approximately 30 months to commercial operation

Approximately 30 months to commercial operation

Project Life: Approximately 30 years Approximately 30 years Power Plant Type: Subcritical coal fired power

station Subcritical coal fired power station

Power Generating Capacity: Up to 212 megawatts Up to 212 megawatts Plant Thermal Efficiency: HHV 36.4% - LHV 38.6% Removed as not

environmentally significant Plant Operation: Base load operation 24 hours

per day, 365 days per year Base load operation 24 hours per day, 365 days per year

Shutdown Time: Plant maintenance shutdowns may be scheduled annually

Plant maintenance shutdowns may be scheduled annually

Maximum Facility Footprint (area of power generating unit):

Approximately 5.3ha Approximately 5.3ha

Maximum Total Area (total area of power station plant):

Approximately 15ha Approximately 15ha

Ancillary Infrastructure Approximately 23.75ha Approximately 23.75ha Construction Laydown Envelope Approximately 18.7ha Approximately 18.7ha Plant facilities Stacks: 1 1 Height of Stack: 100m 100m Diameter of Stack: 4.13m 4.13m Cooling Towers: 1 set 1 set Liquid Fuel Storage Tanks: 2 x 100,000 litres and 1 x

10,000 litres 2 x 100,000 litres and 1 x 10,000 litres

Boiler: Balanced draft pulverised coal steam generator matched to steam turbine capacity

Balanced draft pulverised coal steam generator matched to steam turbine capacity

Steam Turbine: Tandem compound reheat steam turbine with synchronous alternator – 200MWe

Tandem compound reheat steam turbine with synchronous alternator – 200MWe

Wastewater collection: Package treatment plant Package treatment plant Utilities Water Supply: 3.25GL/yr sourced from mine

dewatering at Ewington 1 3.25GL/yr sourced from mine dewatering at Ewington 1

Page 39: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Element Description of approved proposal

Description of approved changes to proposal (bolded)

Transmission Line Length: 100m up to 3km depending on interconnection point as required by Western Power

100m up to 3km depending on interconnection point as required by Western Power

Emissions Noise: Less than 60dB(A) at 150m from

the plant. Less than 29dB(A) at nearest residence in Collie

Less than 60dB(A) at 150m from the plant. Less than 29dB(A) at nearest residence in Collie

Flue Dust: 47mg/Nm3; 9.4g/s; 237tpa 47mg/Nm3; 9.4g/s; 237tpa Nitrogen Oxides: 500mg/Nm3; 112.1g/s; 2828tpa 500mg/Nm3; 112.1g/s; 2828tpa Sulphur Oxides: 229.9g/s; 5800tpa Removed as emissions are

regulated under Part V of the Environmental Protection Act 1986

Greenhouse Gases: 1,562,000tpa CO2 e 1,562,000tpa CO2 e Carbon Monoxide: 500mg/m3; 97g/s; 2444tpa 500mg/m3; 97g/s; 2444tpa Volatile Organic Compounds: 33.3kg/yr 33.3kg/yr PAHs: 6.0kg/yr 6.0kg/yr Arsenic: 6.8kg/yr 6.8kg/yr Cadmium: 8.8kg/yr 8.8kg/yr Chromium compounds: 1.6kg/yr 1.6kg/yr Lead compounds: 32.2kg/yr 32.2kg/yr Mercury: 32.2kg/yr 32.2kg/yr Fluorides: 17,680kg/yr 17,680kg/yr POPs inc. Dioxins and Furans: Less than 0.5 grams per year Less than 0.5 grams per year Waste Ash: 182,000tpa maximum disposed

to the adjacent mines, Ewington I and Ewington II

182,000tpa maximum disposed to the adjacent mines, Ewington I and Ewington II

Septage: Packaged treatment plant Packaged treatment plant Saline Water: 1.2GL/yr 1.2GL/yr Workforce Construction: Approximately 150 personnel at

the peak of construction Approximately 150 personnel at the peak of construction

Operations: Up to 30 full time operations and maintenance personnel

Up to 30 full time operations and maintenance personnel

Abbreviations CO2 e carbon dioxide equivalents dB(A) decibels A weighted g/s grams per second GL/yr gigalitres per year HHV higher heating value inc. including kg kilograms kg/yr kilograms per year

LHV lower heating value m metres mg/Nm3 milligrams per standard cubic

metre mg/s milligrams per second Mtpa million tonnes per annum MW megawatts MWe megawatts sent out

O2 oxygen pa per annum PAHs polycyclic aromatic

hydrocarbons POPs persistent organic pollutants SWIS South West Interconnected

System tpa tonnes per annum % percent

Dr Paul Vogel CHAIRMAN Environmental Protection Authority under delegated authority Approval date: 7 January 2013

Page 40: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

NOTICE OF INTERIM IMPLEMENTATION CONDITIONS

section 46A Environmental Protection Act 1986

Proposal: Bluewaters Power Station Phase II Shire of Collie Proponent: Bluewaters Power 2 Pty Ltd Proponent Address: Level 8, 225 St Georges Terrace, Perth WA 6000 Statement to which this notice relates: Statement 724 dated 24 May 2006

and Statement 804 dated 27 August 2009

Pursuant to section 46A(1) of the Environmental Protection Act 1986, and in addition to the conditions and procedures of Statement 724 dated 24 May 2006, as amended by Statement 804 dated 27 August 2009, the implementation of the above proposal is subject to the Interim Implementation Conditions set out in this Notice. These Interim Implementation Conditions are to have effect until a further statement is published under section 45(5) as applied by section 46(8) of the Environmental Protection Act 1986. 1 Metal Emissions Monitoring 1-1 The proponent shall ensure that air emissions from the proposal are minimised

and ensure that high quality and accurate data is available to model and verify ambient air quality.

1-2 Within 4 weeks of the date of this statement the proponent shall prepare and submit a Metal Emissions Monitoring Plan to the CEO. The Metal Emissions Monitoring Plan shall:

(1) describe the procedure for sampling and analysis of stack emissions of

the following pollutants: Arsenic, Cadmium, Total Chromium, Chromium

III, Chromium VI, Mercury and particulates;

(2) describe the procedures for sampling and analysis of a composite coal

sample that represents the coal used during stack sampling in 1-2(1).

The following parameters should be measured: Arsenic, Cadmium, Total

Chromium, Chromium III, Chromium VI and Mercury.

Page 41: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

(3) detail how the data obtained in 1-2(1) and 1-2(2) will be validated through

the use of duplicate, blind, blank and reference samples.

(4) outline a method to determine the suitability and limitations of using the

CEMS particulate monitor as a surrogate for metal emissions, by

correlating data from the metal emissions sampling with data from the

CEMS particulate monitor.

(5) outline the format for reporting the data obtained.

1-3 After receiving notice in writing from the CEO that the Metal Emissions Monitoring Plan satisfies the requirements of condition 1-2, the proponent shall undertake the first round of metal emissions monitoring with 4 weeks of the written notice. Monitoring shall be repeated at monthly intervals and in accordance with the requirements of the Metal Emissions Monitoring Plan.

1-4 On completion of each monthly metal emissions monitoring the proponent shall report to the CEO on the following:

(1) completion of the metal emissions monitoring in accordance with the

Metal Emissions Monitoring Plan; and

(2) the results of the metal emissions monitoring. 1-5 The proponent shall provide the results of monitoring required by condition 1-3

to the CEO within four weeks of the monitoring and until such time when the CEO has confirmed by notice in writing that monitoring is no longer required.

[Signed 21 December 2015] HON ALBERT JACOB MLA MINISTER FOR ENVIRONMENT; HERITAGE

Page 42: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Attachment 9 to Ministerial Statement 724

Change to Proposal Proposal: Bluewaters Power Station – Phase II Shire of Collie Proponent: Bluewaters Power 2 Pty Ltd Change: Adjustment of annual pollutant loads emitted to air Key Characteristics Table: This table replaces the Key Proposal Characteristics

Table in Schedule 1 to Statement 724 Element Description of approved

proposal Description of recommended changes

General Project Purpose: To produce electricity to supply

to the SWIS grid or direct to customers

To produce electricity to supply to the SWIS grid or direct to customers

Construction Period: Approximately 30 months to commercial operation

Approximately 30 months to commercial operation

Project Life: Approximately 30 years Approximately 30 years Power Plant Type: Subcritical coal fired power

station Subcritical coal fired power station

Power Generating Capacity: Up to 208 megawatts Up to 212 megawatts Plant Operation: Base load operation 24 hours

per day, 365 days per year Base load operation 24 hours per day, 365 days per year

Shutdown Time: Plant maintenance shutdowns may be scheduled annually

Plant maintenance shutdowns may be scheduled annually

Maximum Facility Footprint (area of power generating unit):

Approximately 5.3ha Approximately 5.3ha

Maximum Total Area (total area of power station plant):

Approximately 15ha Approximately 15ha

Ancillary Infrastructure Approximately 23.75ha Approximately 23.75ha Construction Laydown Envelope Approximately 18.7ha Approximately 18.7ha Plant facilities Stacks: 1 1 Height of Stack: 100m 100m Diameter of Stack: 4.13m 4.13m Cooling Towers: 1 set 1 set Liquid Fuel Storage Tanks: 2 x 100,000 litres and 1 x

10,000 litres 2 x 100,000 litres and 1 x 10,000 litres

Boiler: Balanced draft pulverised coal steam generator matched to steam turbine capacity

Balanced draft pulverised coal steam generator matched to steam turbine capacity

Steam Turbine: Tandem compound reheat steam turbine with synchronous alternator – 200MWe

Tandem compound reheat steam turbine with synchronous alternator – 200MWe

Wastewater collection: Package treatment plant Package treatment plant Utilities Water Supply: 3.25GL/yr sourced from mine

dewatering at Ewington 1 3.25GL/yr sourced from mine dewatering at Ewington 1

Transmission Line Length: 100m up to 3km depending on interconnection point as required by Western Power

100m up to 3km depending on interconnection point as required by Western Power

Page 43: Statement No. STATEMENT THAT A PROPOSAL MAY BE …€¦ · I. "no regrets" measures are those which can be implemented by a proponent and which are effectively cost-neutral. 2. "beyond

Element Description of approved proposal

Description of recommended changes

Emissions Noise: Less than 60dB(A) at 150m from

the plant. Less than 29dB(A) at nearest residence in Collie

Less than 60dB(A) at 150m from the plant. Less than 29dB(A) at nearest residence in Collie

Flue Dust: 47mg/Nm3; 9.4g/s; 237tpa 47mg/Nm3; 9.4g/s; 237tpa

Nitrogen Oxides: 500mg/Nm3; 112.1g/s; 2828tpa 500mg/Nm3; 112.1g/s; 2828tpa Greenhouse Gases: 1,562,000tpa CO2 e 1,562,000tpa CO2 e Carbon Monoxide: 500mg/m3; 97g/s; 2444tpa 500mg/m3; 97g/s; 2444tpa Volatile Organic Compounds: 33.3kg/yr 33.3kg/yr PAHs: 6.2kg/yr 6.2kg/yr Average

levels** Limit

Arsenic: 6.8kg/yr 10.4kg/yr 27.5kg/yr Cadmium: 8.8kg/yr 4.56kg/yr 22.5kg/yr Total Chromium*: 1.6kg/yr 18kg/yr 50kg/yr Chromium VI: Not Specified 0.28kg/yr 0.75kg/yr Mercury: 32.2kg/yr 6.44kg/yr 22.5kg/yr Lead compounds: 32.2kg/yr 32.2kg/yr Fluorides: 17,680kg/yr 17,680kg/yr POPs inc. Dioxins and Furans: Less than 0.5 grams per year Less than 0.5 grams per year Waste Ash: 182,000tpa maximum disposed

to the adjacent mines, Ewington I and Ewington II

182,000tpa maximum disposed to the adjacent mines, Ewington I and Ewington II

Septage: Packaged treatment plant Packaged treatment plant Saline Water: 1.2GL/yr 1.2GL/yr Workforce Construction: Approximately 150 personnel at

the peak of construction Approximately 150 personnel at the peak of construction

Operations: Up to 30 full time operations and maintenance personnel

Up to 30 full time operations and maintenance personnel

Abbreviations CO2 e carbon dioxide equivalents dB(A) decibels A weighted g/s grams per second GL/yr gigalitres per year HHV higher heating value inc. including kg kilograms kg/yr kilograms per year

LHV lower heating value m metres mg/Nm3 milligrams per standard cubic

metre (at 7% O2 at STP) mg/s milligrams per second Mtpa million tonnes per annum MW megawatts MWe megawatts sent out

O2 oxygen pa per annum PAHs polycyclic aromatic

hydrocarbons POPs persistent organic pollutants SWIS South West Interconnected

System tpa tonnes per annum % percent

*Previously described as Chromium compounds **Based on the average result from 15 rounds of monitoring Dr Tom Hatton CHAIRMAN Environmental Protection Authority under delegated authority Approval date: 4 April 2018