STATE TRANSPORTATION IMPROVEMENT PROGRAM 14.pdfeb-5758 i-5508 eb-5735 eb-5759 u-5604 i-4729 eb-5757...
Transcript of STATE TRANSPORTATION IMPROVEMENT PROGRAM 14.pdfeb-5758 i-5508 eb-5735 eb-5759 u-5604 i-4729 eb-5757...
14
Division 14CherokeeClayGrahamHaywoodHendersonJacksonMaconPolkSwainTransylvania
STATE TRANSPORTATION IMPROVEMENT PROGRAM
JACKSON TRANSYLVANIA
MACONCHEROKEE
CLAY
HENDERSON
POLK
GRAHAM
HAYWOOD
SWAIN
64
19
176
23
23
64
64
129
19
64
276
441
26
40 209
294106
225281
108
28
107
280143
215
Waynesville
Hendersonville
AV-5775
B-5911
B-5918
B-4823B-4822
B-5915
B-5550 B-5403
B-5923
B-5898
B-5904
B-5920
B-5909
B-5900
B-5903 B-5409
B-5917
B-5913
B-5901B-5906
B-5907
B-5899
B-5921
B-5905
B-5902
B-4159
B-5404
B-5410
B-4775
B-5919
B-5908
B-3868B-5914B-5912
B-4792 B-5916
W-5506
B-5896
K-5002
U-5105
U-5840
I-5758
EB-5758
I-5508
EB-5735
EB-5759
U-5604
I-4729
EB-5757
U-5866
R-5527B
R-5527A
R-5715
EB-5756
U-5104R-5605
R-4047
R-5734
U-5783
U-5839
R-5735
R-5206
EB-5737
U-4412
R-5600
I-5757
R-4416
I-5759
I-5810
I-4400C
A-0011C
R-4753R-5748
R-5742
R-2588BR-5744
I-5776
A-0009B
I-5834
R-2409C
I-5756
I-5835
I-5868
R-5747
R-3622B R-5115
DRAFT STIPFY 2015-2025STI ProjectsDIVISION 14
0 10 205Miles
BRIDGES FUNDED THROUGH STI
STATEWIDE AVIATION
REGIONAL AVIATION
DIVISION AVIATION
DIVISION FERRYREGIONAL RAILDIVISION RAILREGIONAL TRANSITDIVISION TRANSITSAFETYTRANSITION *TRANSITION *INTERSTATE MAINTENANCESTATEWIDE HIGHWAYREGIONAL HIGHWAYDIVISON HIGHWAYDIVISION BIKE/PEDESTRIANINTERSTATE ROUTEUS ROUTENC ROUTESECONDARY ROADPROJECTED ROUTEMUNICIPAL BOUNDARIESMILITARY BASENCDOT DIVISION BOUNDARYCOUNTY BOUNDARYWATER FEATURES
* Note: Reflects 108 of the Major Transition ProjectsNote: FY 2015 projects represent major projects not
let as of November 2014
COUNTY
FUTURE YEARS
F
NHPB - National Highway Performance Program (Bridge)NHPIM - National Highway Performance Program (Interstate Maintenance)O - OthersRR - Rail-Highway SafetyS (M) - State MatchSRTS - Safe Routes to School
FLPI - Federal Lands Program (Indian Reservation Roads) STP - Surface Transportation ProgramHFB - Highway Fund Bridge Replacement Program STPDA - Surface Transportation Program - Direct AttributableHP - Federal-Aid High Priority STPEB - Surface Transportation Program, Enhancements (Bike)
STPON - Surface Transportation Program Bridge (On System Bridge)STPOFF -Surface Transportation Program (Off System Bridge) PE - Preliminary EngineeringT - State Highway Trust Funds
NHP - National Highway Performance Program TAP - Transportation Alternatives Program RG - Right of Way (GARVEE)
SW - StatewideTRN -Transition Project
S - StructureU - Utilities
I - ImplementationL - LandscapingM - MitigationO - OperationsP - Paving
WAKE
NUMBERLENGTH (MILES)
DIVISION 00
R-0000
IDROUTE/CITY
US or NC RoutesON NEW LOCATION. I - InterstateWITH A BYPASS OF HOMETOWN ROUTE/CITY
Project termini and a general
SW
M1500
A
NHP
4000
FUNDING CATEGORY (1)
used for each project phase.
FUNDING SOURCE (2)
U
B3000R
FY 2017
C
(3) WORK TYPE (ACTIVITY)
A - Acquisition
with proposed work type or activity beginning in the initial scheduled year. (Estimates are in thousand of
For other work types or activities see Work Type (Activity) box below.
dollars.)
of a project segment indicates (Cash-Flow Funding) COMMITMENTSFUTURE
SW CBSW
One or two letter
HIGHWAY PROGRAM
UNFUNDED
NC 3 TO SR 1003SR 1003 TO NC 96
ASW
UNFUNDED
20000CRC 5000C 5000 BC B
WIDEN TO A FOUR-LANE FACILITY
A
NC 00 R7.3 R25063,450I-40 TO NC 96 EAST OF HOMETOWN.
B
FY 2025 FY 2018
700
FY 2019
DEVELOPMENTAL PROGRAMSTATE TRANSPORTATION IMPROVEMENT PROGRAM
FY 2020FY 2015 FY 2016
M
TOTAL PROJECT
COST (THOU)
NHPNHP
FUN
DS
A
PRIOR YEARS COST
(THOU)
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
U 5000NHP
C10000
FY 2021
C
FY 2023 FY 2024
FY 2022
5000
9000
APD - Appalachian Development
NHPNHP
LOCATION / DESCRIPTION NHP
NHP
I-40 TO NC 3
Preliminary engineering, Right of Way, Mitigation, Utilities or Construction. break.
work description.
way, utility, mitigation and construction cost estimates
See Highway Funding Key
any project breaks.Category for the project andIdentifies the "STI" Funding
by funding category in current dollars. Cost may include one or more funding types. Multi-year funding
for an explanation of funding categories
Phases of implementation: ESTIMATED COST Preliminary engineering, right of
(1) FUNDING CATEGORY
PROJECT BREAKS
designation for project
LOCATION / DESCRIPTION
SR - Secondary Road
IDENTIFICATION NUMBER Assigned to each project at conception and remains with
BVarious - multiple routesNEW ROUTE or City
WORK TYPE (ACTIVITY) (3)
BOND (R) - Revenue Bond
HRRR - High Risk Rural Roads
L - LocalHSIP - Highway Safety Improvement Program
project until completion.
DIV - DivisionEX - Exempt
REG - RegionalHF - State Dollars (Non-STI)
F - Feasibility StudyCG - Construction (GARVEE)C - Construction
G - Grading and Structures
R - Right of Way
(2) FUNDING KEY FOR HIGHWAY FUNDING SOURCES
ER - Emergency Relief Funds
CMAQ - Congestion MitigationDP - Discretionary or Demonstration
FED - Federal Rail Funds
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS
R-5735 11360END OF 4-LANE DIVIDED SECTION TO SR 1556 (MARTINS CREEK ROAD). IMPROVE ROADWAY.
1.2
DIV
T R 1300 T U 160 T C 9900
CHEROKEE US 19/US 74/US 64/US 129
SECTIONS A, B, AND BA - DIVISION PROJECTS; PLANNING/DESIGN IN PROGRESS
R-3622 20534 12719US 64/US 74 AT RANGER TO TENNESSEE STATE LINE. UPGRADE EXISTING ROADWAY.
13.5
TRN
T 7700C B T 115C BA
AA REPLACE BRIDGE NO. 50 - COMPLETEAB SR 1309 TO SR 1130 (SUNNY POINT ROAD) - EXCLUDING BRIDGE REPLACEMENT - COMPLETEB SR 1130 (SUNNY POINT ROAD) TO SR 1312 (BEAR PAW ROAD). - RIGHT OF WAY IN PROGRESSTRNBA SR 1130 (SUNNY POINT ROAD) TO SR 1312 (BEAR PAW ROAD). - CLEARING AND GRUBBING ONLYTRN
CHEROKEE NC 294
R-5527 11275 11275CONSTRUCT ACCESS ROAD AND BRIDGE OFF US 19/74/129 NEAR MURPHY.
0.8TRN A CONSTRUCT BRIDGE. - UNDER CONSTRUCTIONTRN
B CONSTRUCT ROADWAY. - UNDER CONSTRUCTIONTRN
CHEROKEE NEW LOCATION
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
PROGRAMMED FOR PLANNING AND ENVIRONMENTAL STUDY ONLY
A-0009* 883443 83818CORRIDOR "K", US 19/US 74/US 129 AT ANDREWS TO NC 28 EAST OF ALMOND. FOUR LANE DIVIDED FACILITY, PRIMARILY ON NEW LOCATION.
27.1 APD 14300R A APD 925U A APD 366000C A APD R 14900 B APD U 2300 B APD M 2500 B APD 39000C B C 19500 B C 19500 BAPD R 14500 C APD M 22200 C APD 41000G CA G 20500 CA G 20500 CAAPD 91500C CB C 45750 CB C 45750 CBAPD 19000P CC
A US 19 BUSINESS IN ANDREWS TO US 129B US 129 TO NC 143 AT SR 1223 (BEECH CREEK) - DESIGN-BUILD CONTRACTDIVC NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH - RIGHT OF WAY ONLYEXCA NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH. GRADING AND STRUCTURES ( EXCEPT TUNNELS). - DESIGN-BUILD CONTRACTEXCB TUNNELS AT APPALACHIAN TRAIL - DESIGN-BUILD CONTRACTEXCC NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH. PAVING.DA SR 1121 (WATTIA ROAD) AT ALMONDS TO EXISTING US 19/NC 28 - COMPLETEDB EAST OF CALFPEN GAP IN GRAHAM COUNTY TO SR 1121 (WATTIA ROAD) AT ALMONDS IN SWAIN COUNTY - COMPLETEDC WEST OF SR 1231 (TOBACCO BRANCH ROAD) TO CALFPEN GAP - COMPLETEDD NC 28 AT STECOAH TO WEST OF SR 1231 (TOBACCO BRANCH ROAD) - COMPLETE
CHEROKEEGRAHAMSWAIN
FUTURE US 74
FEDERAL BRIDGE PROJECTSB-4462 812 162REPLACE BRIDGE NO. 148 OVER
PERSIMMON CREEK.
HF
HFB R 50 HFB C 600
CHEROKEE SR 1127(BELL HILL ROAD)
B-4069 2098 3REPLACE BRIDGE NO. 159 OVER HANGING DOG CREEK.
HF
HFB R 295 HFB C 1800
CHEROKEE SR 1326(JOE BROWN HIGHWAY)
14-7 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
B-5925 2860REPLACE BRIDGE NO. 223 OVER HIWASSEE RIVER.
HF
HFB 260R HFB 2600C
CHEROKEE SR 1548(OLD HIGHWAY 64)
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-8 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
RURAL PROJECTSA-0011 103468 30268NC 69, GEORGIA STATE LINE TO US 64.
WIDEN TO FOUR LANES DIVIDED. US 64, NC 69 TO EAST OF NC 175. WIDEN TO MULTI-LANES.
4.5 APD R 14700 C APD 29000C C APD 14800R D APD 14700C D
A GEORGIA STATE LINE TO US 64 (HAYESVILLE BYPASS). UPGRADE EXISTING TWO-LANES - COMPLETEBA NC 69 IN HAYESVILLE TO EAST OF THE HIWASSEE RIVER - COMPLETEBB EAST OF THE HIWASSEE RIVER TO EAST OF NC 175 - COMPLETEC GEORGIA STATE LINE TO US 64 (HAYESVILLE BYPASS). WIDEN TO FOUR-LANESDIVD EAST OF THE HIWASSEE RIVER TO EAST OF NC 175. WIDEN TO FOUR-LANES.
CLAY US 64/NC 69
DIVISION PROJECT
R-4416 5675 675CHUNKY GAL GAP WESTWARD FOR TWO MILES. CONSTRUCT TRUCK CLIMBING LANE.
2TRN
STP 5000C CLAY US 64
R-5742 4900GEORGIA STATE LINE TO US 64. UPGRADE ROADWAY.
4.1
DIV
T R 100 T C 4800
CLAY NC 175
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
FEDERAL BRIDGE PROJECTS
UNDER CONSTRUCTION
B-4733 4072 4072REPLACE BRIDGE NO. 11 OVER CHATUGE LAKE.REG
CLAY NC 175
14-9 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
B-5918 320REPLACE BRIDGE NO. 60 OVER LEFT FORK EAGLE CREEK.
DIV
STPOFF 20R STPOFF 300C
CLAY SR 1169(LEFORD ROAD)
UNDER CONSTRUCTION
B-4734 1366 1366REPLACE BRIDGE NO. 9 OVER TUSQUITEE CREEK.
DIV
CLAY SR 1300(JULIA BUCKNER ROAD)
B-5911 370REPLACE BRIDGE NO. 41 OVER SWEETWATER CREEK.
DIV
STPOFF 20R STPOFF 350C
CLAY SR 1302(LOWER SWEETWATER)
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTSW-5119 1950 50GEORGIA STATE LINE TO US 64. INSTALL
PAVED SHOULDERS AND REALIGN CURVE.4
REG
HSIP 100R HSIP C 900 C 900
CLAY NC 175
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-10 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
RURAL PROJECTS
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
PROGRAMMED FOR PLANNING AND ENVIRONMENTAL STUDY ONLY
A-0009* 883443 83818CORRIDOR "K", US 19/US 74/US 129 AT ANDREWS TO NC 28 EAST OF ALMOND. FOUR LANE DIVIDED FACILITY, PRIMARILY ON NEW LOCATION.
27.1 APD 14300R A APD 925U A APD 366000C A APD R 14900 B APD U 2300 B APD M 2500 B APD 39000C B C 19500 B C 19500 BAPD R 14500 C APD M 22200 C APD 41000G CA G 20500 CA G 20500 CAAPD 91500C CB C 45750 CB C 45750 CBAPD 19000P CC
A US 19 BUSINESS IN ANDREWS TO US 129B US 129 TO NC 143 AT SR 1223 (BEECH CREEK) - DESIGN-BUILD CONTRACTDIVC NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH - RIGHT OF WAY ONLYEXCA NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH. GRADING AND STRUCTURES ( EXCEPT TUNNELS). - DESIGN-BUILD CONTRACTEXCB TUNNELS AT APPALACHIAN TRAIL - DESIGN-BUILD CONTRACTEXCC NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH. PAVING.DA SR 1121 (WATTIA ROAD) AT ALMONDS TO EXISTING US 19/NC 28 - COMPLETEDB EAST OF CALFPEN GAP IN GRAHAM COUNTY TO SR 1121 (WATTIA ROAD) AT ALMONDS IN SWAIN COUNTY - COMPLETEDC WEST OF SR 1231 (TOBACCO BRANCH ROAD) TO CALFPEN GAP - COMPLETEDD NC 28 AT STECOAH TO WEST OF SR 1231 (TOBACCO BRANCH ROAD) - COMPLETE
CHEROKEEGRAHAMSWAIN
FUTURE US 74
14-11 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025URBAN PROJECTS
U-5866 3970US 129 (RODNEY ORR BYPASS) TO ROBINSVILLE HIGH SCHOOL AND MIDDLE SCHOOL. CONSTRUCT NEW ROUTE INCLUDING BRIDGE OVER CHEOAH RIVER.
0.3
DIV
T R 150 T U 20 T 3800C
GRAHAM NEW ROUTE
FEDERAL BRIDGE PROJECTSB-5923 260REPLACE BRIDGE NO. 119 OVER MILL
CREEK.
DIV
STPOFF R 10 STPOFF C 250
GRAHAM SR 1105(MILL CREEK ROAD)
UNDER CONSTRUCTION
B-3457 782 782REPLACE BRIDGE NO. 68 OVER PANTHER CREEK.
DIV
GRAHAM SR 1232(PANTHER CREEK ROAD)
BRIDGE PURCHASE ORDER CONTRACT (DPOC)
B-3458 826 201REPLACE BRIDGE NO. 114 OVER STECOAH CREEK.
DIV
T 625C GRAHAM SR 1237(JENKINS ROAD)
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-12 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
INTERSTATE PROJECTSI-5834 30470.4 MILE EAST OF SR 1366 (ORCHARD COVE
ROAD) TO 0.4 MILE EAST OF SR 1535 (THOMPSON COVE ROAD). PAVEMENT REHABILITATION.
5SW
NHPIM C 3047 HAYWOOD I-40
I-5776 6000.4 MILE EAST OF SR 1366 (ORCHARD COVE ROAD) TO SR 1535 (THOMPSON COVE). PAVEMENT REHABILITIATION.
5SW
NHPIM C 600 HAYWOOD I-40
I-5757 2000.2 MILE EAST OF SR 1513 (HYDER MOUNTAIN ROAD) TO SR 1535 (THOMPSON COVE ROAD). PAVEMENT REHABILITATION.
2SW
NHPIM C 200 HAYWOOD I-40
I-5756 4000.4 MILE EAST OF SR 1366 (ORCHARD COVE ROAD) TO 0.2 MILE EAST OF SR 1513 (HYDER MOUNTAIN ROAD). PAVEMENT REHABILITATION.
3SW
NHPIM C 400 HAYWOOD I-40
"O" FUNDS ARE STATE BRIDGE FUNDS.
I-5512 6000REHABILITATE TUNNELS 15, 17, AND 104.
SW
NHPIM 2500C O 3500C
HAYWOOD I-40
RIGHT OF WAY IN PROGRESS
I-5508 6551 251I-40 NEAR MILEPOST 7. SLOPE STABILIZATION, ROCK BOLTING, AND ROCKFALL BARRIER FENCE AND MESH.TRN
NHPIM 6300C HAYWOOD I-40
UNDER CONSTRUCTION
I-5402 1439 1439MILE POST 35 TO MILE POST 36. ADDRESS SLOPE INSTABILITY THROUGH REPAIRS AND STREAM RESTORATION.
HAYWOOD I-40
UNDER CONSTRUCTION
I-5323 4473 4473MILE MARKER 34 TO MILE MARKER 36. PAVEMENT REHABILITATION.
2HAYWOOD I-40
UNDER CONSTRUCTION
I-5322 9864 9864MILE MARKER 15 TO MILE MARKER 20. PAVEMENT REHABILITATION.
5HAYWOOD I-40
14-13 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025INTERSTATE PROJECTS
COMPLETE - GARVEE BOND FUNDING $12.87 MILLION; PAYBACK FY 2008 - FY 2019
I-4910 24728 17673TENNESSEE STATE LINE (MILE MARKER 0.0) TO EXIT 15 (MILE MARKER 14.8). PAVEMENT REHABILITATION.
14.8TRN
NHP 1411CG CG 1411 CG 1411 CG 1411 CG 1411 HAYWOOD I-40
I-5868 4200SR 1535 (THOMPSON COVE RD) TO BUNCOMBE COUNTY LINE. PAVEMENT REHABILITATION.
8.5SW
NHPIM C 4200 HAYWOOD I-40
I-5810 23000.2 MILE EAST OF SR 1338 (WHITEOAK ROAD) TO 0.7 MILE EAST OF US 276. PAVEMENT REHABILITATION.
6.3SW
NHPIM C 2300 HAYWOOD I-40
COMPLETE - GARVEE BOND FUNDING $8.37 MILLION; PAYBACK FY 2007 - FY 2018
I-5004 12404 8732US 74 (MILE MARKER 27) TO BUNCOMBE COUNTY LINE. PAVEMENT REHABILITATION.
7TRN
NHP 918CG CG 918 CG 918 CG 918 HAYWOOD I-40
RURAL PROJECTSR-5747 8800SR 1304 (FIE TOP ROAD) AT GHOST TOWN
USA TO JENKINS CREEK ROAD. UPGRADE ROADWAY.
9.4
DIV
T 100R T 5800C C 2900
HAYWOODJACKSON
US 19
UNDER CONSTRUCTION - SECTION 115 FUNDS, 2004 APPROPRIATIONS ACT USED FOR PRELIMINARY ENGINEERING
R-4904 921 9213 MILES EAST OF US 23 BUSINESS. REPAIR SLOPE FAILURES AND RESURFACE.TRN
HAYWOOD US 276
UNDER CONSTRUCTION - INCLUDES R-2210 B
R-4047 31261 19287US 23 BUSINESS TO NORTH OF SR 1523 (OLD CLYDE ROAD) AT LAKE JUNALUSKA. WIDEN TO A MULTI-LANE FACILITY AND REPLACE RAILROAD STRUCTURE R-32. (INCLUDES R-2210B).
0.3TRN
STP 5987C C 5987 HAYWOOD NC 209
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
URBAN PROJECTSU-5839 17750US 23/74 TO US 23 BUSINESS (MAIN
STREET). UPGRADE CORRIDOR.1.1
DIV
T R 6200 T U 750 T 10800C
HAYWOOD US 276 (RUSSAVENUE)
UNDER CONSTRUCTION
U-4412 22023 22023US 276 TO US 23 BUSINESS IN WAYNESVILLE. UPGRADE TWO LANES AND CONSTRUCT RAILROAD GRADE SEPARATION.
1.5HAYWOOD SR 1184 (HOWELLMILL ROAD)
U-5100 36950STP-DA IN THE FRENCH BROAD RIVER METROPOLITAN PLANNING ORGANIZATION.
DIV
STPDA C 500 C 1060 C 3500 C 3500 C 3500 3500C3500C3500C C 3500 C 3500L C 125 C 265 C 875 C 875 C 875 875C875C875C C 875 C 875
BUNCOMBEHAYWOODHENDERSON
VARIOUS
U-5548 550REALIGNMENT OF BROWN AVENUE FROM BOYD AVENUE TO APPROXIMATELY 1200 FEET SOUTH OF THE INTERSECTION. PROJECT INCLUDES CONSTRUCTION OF NEW ROADWAY (SCHOOL STREET), RAISED CROSSWALK, PAINTED CROSSWALKS, REFUGE ISLAND, BULBOUT AND SIGNAGE.
DIV
STPDA PE 40 L PE 10 STPDA C 400 L C 100
HAYWOOD BROWN AVENUE
14-14 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
B-5541 7700REPLACE BRIDGE NO. 236 OVER SR 1513.
HF
HFB 700R HFB C 7000
HAYWOOD I-40
B-3186 5900REPLACE BRIDGE NO. 155 AND BRIDGE NO. 158 OVER RICHLAND CREEK.
SW
NHPB R 800 NHPB 5100C
HAYWOOD US 23/US 74(NORTHBOUND LANE)
B-5898 3250REPLACE BRIDGE NO. 168 OVER US 19 AND US 23.
SW
NHPB R 150 NHPB 3100C
HAYWOOD US 23US 74
B-5408 770REPLACE BRIDGE NO. 386 OVER ALLENS CREEK.
HF
HFB R 70 HFB C 700
HAYWOOD SR 1148(WIGGINS ROAD)
B-5920 640REPLACE BRIDGE NO. 246 OVER WEST FORK PIGEON CREEK.
DIV
STPOFF 30R STPOFF 610C
HAYWOOD SR 1216(REECE ROAD)
B-5924 295REPLACE BRIDGE NO. 192 OVER WESLEY CREEK.
HF
HFB 25R HFB 270C
HAYWOOD SR 1336(WESLEY CREEK ROAD)
UNDER CONSTRUCTION
B-4762 1015 1015REPLACE BRIDGE NO. 72 OVER JONATHAN CREEK.
DIV
HAYWOOD SR 1407(MEDLEY DRIVE)
UNDER CONSTRUCTION
B-4763 1630 1630REPLACE BRIDGE NO. 35 OVER BALD CREEK.
DIV
HAYWOOD SR 1503(UPPER CRABTREEROAD)
B-5904 261REPLACE BRIDGE NO. 241 OVER BEAVERDAM CREEK.
DIV
STPOFF R 10 STPOFF M 1 STPOFF 250C
HAYWOOD SR 1619(WILSON COVE ROAD)
B-5900 261REPLACE BRIDGE NO. 382 OVER DUTCH COVE CREEK.
DIV
STPOFF R 10 STPOFF M 1 STPOFF 250C
HAYWOOD SR 1835(WINDING STAIRS)
B-5909 280REPLACE BRIDGE NO. 375 OVER DUTCH COVE CREEK.
DIV
STPOFF 10R STPOFF 270C
HAYWOOD SR 1856(JENKINS ROAD)
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-15 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025MUNICIPAL BRIDGE PROJECTS
PROGRAMMED FOR PLANNING AND ENVIRONMENTAL STUDY ONLY BY THE TOWN OF WAYNESVILLE - MUNICIPAL BRIDGE
B-5013 REPLACE BRIDGE NO. 262 OVER RICHLAND CREEK.
HAYWOOD WAYNESVILLE(DEPOT STREET)
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
UNDER CONSTRUCTION
W-5315 5832 5832EXIT 98 IN HAYWOOD COUNTY TO 0.1 MILE WEST OF THE JACKSON-HAYWOOD COUNTY LINE. REMOVE CONCRETE ISLAND, REPAVE WITH ASPHALT, DRAINAGE MODIFICATIONS, AND INSTALL GUARDRAIL.
4.8
TRN
HAYWOODJACKSON
US 74
UNDER CONSTRUCTION
SF-4914A 43 43SR 1004 (NEWFOUND ROAD) NEAR SR 1612 (MP 2.14-2.62) NEAR CANTON. INSTALL GUARDRAIL.
HAYWOOD SR 1004(NEWFOUND ROAD)
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
CONGESTION MITIGATION PROJECTSC-5612 100PROJECTS TO IMPROVE CONGESTION AND
AIR QUALITY IN THE LAND OF SKY RPO AND SOUTHWESTERN RPO.EX
CMAQ C 50 C 50 HAYWOODSWAIN
VARIOUS
IN PROGRESS
C-5564 172 52LAND OF SKY RPO TO WORK WITH REGIONAL CLEAN AIR CAMPAIGN AND CLEAN VEHICLE COALITION TO IMPLEMENT AN EDUCATIONAL AND OUTREACH PROGRAM IN COMMUNITIES ADJACENT TO GREAT SMOKY MOUNTAINS NATIONAL PARK.
EX
CMAQ 65I I 30 L 17I I 8
BUNCOMBEHAYWOODMADISONTRANSYLVANIA
VARIOUS
C-5151 242GREAT SMOKIES NATIONAL PARK. CONSTRUCT A MIXED-USE PATHWAY.
EX
CMAQ 177C L 65C
HAYWOODSWAIN
EASTERN BANDOF CHEROKEEINDIANS (EBCI)
14-16 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025CONGESTION MITIGATION PROJECTS
IN PROGRESS
C-5202 308 119TRANSPORTATION CHOICES. INCREASE EDUCATION EFFORTS THAT INFORM VISITORS ABOUT THE ROLE THEIR TRANSPORTATION CHOICES HAVE IN RELATION TO AIR POLLUTION ISSUES IN GSMNP.EX
CMAQ 91I I 60 L 23I I 15
HAYWOODSWAIN
GREAT SMOKYMOUNTAINSNATIONAL PARK(GSMNP)
ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
ROADSIDE ENVIRONMENTAL PROJECTS (REST AREA)
UNDER CONSTRUCTION - INCLUDES WORK PREVIOUSLY IN PROJECT K-3803B
K-5002 7892 5142US 23/US 74, ADD NEW SOUTHBOUND REST AREA ON NEW LOCATION AS A COMPANION TO EXISTING NORTHBOUND REST AREA. CONNECT NEW REST AREA TO MUNICIPAL WATER AND SEWER SYSTEM. RENOVATE EXISTING NORTHBOUND REST AREA TO INCLUDE ADA COMPLIANT FAMILY RESTROOM, UPGRADE FIXTURES AND FINISHES AND CONNECT TO MUNICIPAL SEWER SYSTEM.
TRN
NHP 2750C HAYWOOD US 23/US 74
UNDER CONSTRUCTION
S-5105 261 261GRAVEYARD FIELDS OVERLOOK AT BLUE RIDGE PARKWAY MILE POST 418. EXPAND PARKING LOT, CONSTRUCT A THREE-UNIT CONVENIENCE STATION, INSTALL NEW INTERPRETIVE EDUCATIONAL SIGNS AND MAKE TRAIL IMPROVEMENTS.
HAYWOOD BLUE RIDGEPARKWAY
INTERSTATE PROJECTSI-5759 2001 MILE EAST OF SR 1793 (TRACY GROVE
ROAD) TO 0.2 MILE EAST OF US 25. PAVEMENT REHABILITATION.
1.8SW
NHPIM C 200 HENDERSON I-26
I-5835 6000SR 1525 (DANA ROAD) TO 0.1 MILE EAST OF POLK COUNTY LINE. PAVEMENT REHABILITATION.
7.4
SW
NHPIM C 6000 HENDERSONPOLK
I-26 / US 74
14-17 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025INTERSTATE PROJECTS
PLANNING/DESIGN IN PROGRESS
I-4400 114941 2044US 25 (EXIT 54) TO NC 280 (EXIT 40). WIDEN TO ADD ADDITIONAL LANES.
13.6 NHP 1000R A NHP 1260M A NHP 38768C A NHP 1000R B NHP 38769C B NHP R 1000 C NHP C 31100 C
A US 25 (EXIT 54) TO US 64 (EXIT 49)B US 64 (EXIT 49) TO US 25 BUSINESS (EXIT 44)C US 25 BUSINESS (EXIT 44) TO NC 280 (EXIT 40)REG
BUNCOMBEHENDERSON
I-26
PLANNING/DESIGN IN PROGRESS
I-4700 153570 1170NC 280 (EXIT 40) TO I-40 AT ASHEVILLE. ADD ADDITIONAL LANES.
8.6 NHP R 1000 A NHP C 52600 A NHP R 1000 B NHP C 48900 B 48900C B
A NC 280 (EXIT 40) TO NC 146 - LONG SHOALS ROAD (EXIT 37)SWB NC 146 - LONG SHOALS ROAD (EXIT 37) TO I-40SW
BUNCOMBEHENDERSON
I-26
GARVEE BOND FUNDING $7.92 MILLION; CONSTRUCTION - PAYBACK FY 2008 - FY 2019; INCLUDES PROJECT I-4920
I-5005 29541 25201MILE MARKER 37.1 IN BUNCOMBE COUNTY TO SR 1783 (MILE MARKER 53.3) IN HENDERSON COUNTY. PAVEMENT REHABILITATION.
16.2 NHP 868CG A CG 868 A CG 868 A CG 868 A CG 868 A
A MILEPOST 37.1 IN BUNCOMBE COUNTY TO MILEPOST 50.3 (CONCRETE SECTION) - COMPLETETRNB MILEPOST 50.3 TO SR 1783 (MILEPOST 53.3 - ASPHALT SECTION) - COMPLETE
BUNCOMBEHENDERSON
I-26
UNDER CONSTRUCTION
I-5501 6624 6624I-26/NC 280 INTERCHANGE. RETROFIT EXISTING INTERCHANGE TO A DIVERGING DIAMOND CONFIGURATION.TRN
BUNCOMBEHENDERSON
I-26
I-5758 5000BUNCOMBE COUNTY LINE TO 1 MILE EAST OF SR 1534 (SOUTH NAPLES ROAD). PAVEMENT REHABILITATION.
4.9SW
NHPIM C 5000 HENDERSON I-26 / US 74
RURAL PROJECTSR-2588 85900US 25 IN HENDERSONVILLE TO NC 280
SOUTH OF MILLS RIVER. WIDEN TO MULTI-LANES.
7.2 STP 15200R A STP 1800U A STP 18800C A STP 4500R B STP 500U B STP 33825C B C 11275 B
A US 25 TO SR 1381 (MOUNTAIN ROAD).B SR 1381 (MOUNTAIN ROAD) TO NC 280 SOUTH OF MILLS RIVER.REG
HENDERSON NC 191
R-5207 26291 25341US 25 IN FLETCHER TO US 64. UPGRADE ROADWAY.
7.6 T 100R C T 850C C
A US 64 TO HENDERSON COUNTY BRIDGE NO. 20 - UNDER CONSTRUCTIONTRNB HENDERSON COUNTY BRIDGE NO. 20 TO SR 1539 (JACKSON ROAD) - UNDER CONSTRUCTIONTRNC SR 1539 (JACKSON ROAD) TO US 25 IN FLETCHERTRN
HENDERSON SR 1006 (HOWARDGAP ROAD)
R-5748 10300US 25 BUSINESS (CHURCH STREET) TO SR 1123 (LITTLE RIVER ROAD). UPGRADE ROADWAY.
4
DIV
T 100R T 7650C C 2550
HENDERSON SR 1127(KANUGA ROAD)
UNDER CONSTRUCTION
R-4430 49359 49359US 176 TO SR 1006 (HOWARD GAP ROAD). WIDEN AND IMPROVE ROADWAY.
2.7HENDERSON SR 1783(UPWARD ROAD)
14-18 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS
R-5524 2221 2181CONSTRUCT IMPROVEMENTS TO OLD FANNING BRIDGE ROAD AND CONSTRUCT NEW ACCESS ROAD INTO FERNCLIFF INDUSTRIAL PARK.
T 40R C
A INSTALL TRAFFIC SIGNAL. - UNDER CONSTRUCTIONB NC 280 TO SR 1419 (OLD FANNING BRIDGE ROAD). RESURFACE AND ADD BIKE LANES. - UNDER CONSTRUCTIONC CONSTRUCT ROUNDABOUT. - UNDER CONSTRUCTIONTRND CONSTRUCT NEW ACCESS ROAD INTO FERNCLIFF INDUSTRIAL PARK. - UNDER CONSTRUCTION
BUNCOMBEHENDERSON
SR 2277/SR 3526(OLD FANNINGBRIDGE ROAD)
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
R-5744 156200NC 191 (BREVARD ROAD) TO US 64. CONSTRUCT NEW 4-LANE EXPRESSWAY.
4.6
DIV
T 8767R R 8767 R 8766T U 900 T 129000C
HENDERSON BALFOUR PARKWAY
URBAN PROJECTSU-5783 7270SR 1180 (BLYTHE STREET) TO SR 1173
(WHITE PINE DRIVE)/SR 1186 (DANIEL DRIVE). WIDEN ROADWAY.
1
REG
T R 1850 T U 220 T 5200C
HENDERSON US 64
U-5840 2300US 25 TO MILLS GAP ROAD. WIDEN ROADWAY.
0.9
DIV
T R 100 T 2200C
HENDERSON SR 1545 (OLDAIRPORT ROAD)
U-5100 36950STP-DA IN THE FRENCH BROAD RIVER METROPOLITAN PLANNING ORGANIZATION.
DIV
STPDA C 500 C 1060 C 3500 C 3500 C 3500 3500C3500C3500C C 3500 C 3500L C 125 C 265 C 875 C 875 C 875 875C875C875C C 875 C 875
BUNCOMBEHAYWOODHENDERSON
VARIOUS
U-3403 49300NC 191 (BREVARD ROAD - OLD HAYWOOD ROAD), NC 280 TO NC 112 (SARDIS ROAD). WIDEN TO MULTI-LANES.
9.1 STP 9000R A STP 17700C A STP 5100R B STP 600U B STP C 16900 B
A NC 280 (BOYLSTON HIGHWAY) TO NC 146.B NC 146 TO NORTH OF BLUE RIDGE PARYWAY.REGC NORTH OF BLUE RIDGE PARKWAY TO NC 112 (SARDIS ROAD) - COMPLETE
BUNCOMBEHENDERSON
ASHEVILLE
U-5192 2090CONSTRUCT TRANSIT CENTER IN HENDERSONVILLE.
DIV
STPDA 1672C L 418C
HENDERSON HENDERSONVILLE
DIVISION PROJECT
U-5105 1900 200NC 225/SR 1164 (ERKWOOD DRIVE)/SR 1779(SHEPHERD STREET) IN HENDERSONVILLE. IMPROVE INTERSECTION.
TRN
STP 200R STP C 1500
HENDERSON HENDERSONVILLE
FEASIBILITY STUDIES
FEASIBILITY STUDY IN PROGRESS
FS-1214B US 64 TO NC 191 (BREVARD ROAD). CONSTRUCT NEW ROUTE.
4.6HENDERSON BALFOUR PARKWAY
14-19 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
B-5901 2206REPLACE BRIDGE NO. 121 OVER FRENCH BROAD RIVER OVERFLOW.
REG
NHPB R 100 NHPB M 6 NHPB 2100C
HENDERSON NC 191
B-5913 1050REPLACE BRIDGE NO. 100 OVER ROCK CREEK.
DIV
STPOFF 50R STPOFF 1000C
HENDERSON SR 1108(ROCK CREEK ROADEAST)
B-5907 260REPLACE BRIDGE NO. 208 OVER CABIN CREEK.
DIV
STPOFF R 10 STPOFF C 250
HENDERSON SR 1109(CABIN CREEK ROAD)
UNDER CONSTRUCTION
B-4147 2348 2348REPLACE BRIDGE NO. 75 OVER RIGHT PRONG MUD CREEK, AND BRIDGE NO. 76 OVER LEFT PRONG MUD CREEK.DIV
HENDERSON SR 1123(LITTLE RIVER ROAD)
B-5917 400REPLACE BRIDGE NO. 89 OVER BIG WILLOW CREEK.
DIV
STPOFF 20R STPOFF 380C
HENDERSON SR 1210(BIG WILLOW ROAD)
B-5903 340REPLACE BRIDGE NO. 15 OVER BOYLSTON CREEK.
DIV
STPOFF R 20 STPOFF 320C
HENDERSON SR 1323(BRICKYARD ROAD)
B-5906 270REPLACE BRIDGE NO. 182 OVER SWEET WATER BRANCH CREEK.
DIV
STPOFF 10R STPOFF 260C
HENDERSON SR 1328(GASH ROAD)
UNDER CONSTRUCTION
B-4547 1059 1059REPLACE BRIDGE NO. 45 OVER DEVILS FORK CREEK.
DIV
HENDERSON SR 1525(DANA ROAD)
UNDER CONSTRUCTION
B-4988 626 626REPLACE BRIDGE NO. 309 OVER FEATHERSTONE CREEK.
DIV
HENDERSON SR 1528(LOCUST GROVE ROAD)
B-5922 1650REPLACE BRIDGE NO. 237 OVER SOUTHERN RAILROAD.
HF
HFB 150R HFB 1500C
HENDERSON SR 1545(OLD ASHEVILLE)
UNDER CONSTRUCTION
B-4987 655 655REPLACE BRIDGE NO. 35 OVER CLEAR CREEK.
DIV
HENDERSON SR 1572(APPLE VALLEYROAD)
UNDER CONSTRUCTION (COMBINED WITH B-4765)
B-5149 559 559REPLACE BRIDGE NO. 38 OVER CLEAR CREEK.
DIV
HENDERSON SR 1574(FRUITLAND ROAD)
UNDER CONSTRUCTION (COMBINED WITH B-5149)
B-4765 2517 2517REPLACE BRIDGE NO. 113 OVER KYLES CREEK.
DIV
HENDERSON SR 1574(HAYWOOD AVENUE)
UNDER CONSTRUCTION
B-3346 1438 1438REPLACE BRIDGE NO. 42 OVER SACONON CREEK.
DIV
HENDERSON SR 1734(STEPP MILL ROAD)
14-20 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
B-5897 255REPLACE BRIDGE NO. 62 OVER KING CREEK.
HF
HFB R 25 HFB 230C
HENDERSON SR 1812(BLUE RIDGE ROAD)
B-5409 660REPLACE BRIDGE NO. 58 OVER DEVILS FORK CREEK.
DIV
STPOFF R 60 STPOFF C 600
HENDERSON SR 1893MID ALLEN ROAD)
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MUNICIPAL BRIDGE PROJECTSB-5929 1040REPLACE BRIDGE NO. 350 OVER DEVILS
FORK CREEK.
DIV
L 30PE STPOFF 120PE L R 10 STPOFF R 40 L C 168 STPOFF C 672
HENDERSON OLD DANA ROAD
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTSW-5506 4820 190SR 1381 (MOUNTAIN ROAD) TO NORTH OF
SR 1365 (NORTH RUGBY ROAD). CONSTRUCT A CONTINUOUS THREE-LANE SECTION, EXTEND RIGHT TURN LANE INTO SCHOOL, REVISE AND INSTALL GUARDRAIL AND CONSTRUCT PAVED SHOULDERS.
REG
HSIP 155R HSIP C 1975 STP C 2500
HENDERSON NC 191
UNDER CONSTRUCTION
SF-4914C 77 77SR 1328 (TURNPIKE/GASH ROAD) TO SR 1317 (BRANNON/MAPLE SWAMP ROAD). INSTALL GUARDRAIL ALONG STEEP FILL SECTIONS.
HENDERSON SR 1316(RAY HILL ROAD)
14-21 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025HAZARD ELIMINATION PROJECTS
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
ROADSIDE ENVIRONMENTAL PROJECTS (SCENIC)
IN PROGRESS
S-5101 46 46PACOLET RIVER BYWAY. COMPREHENSIVE BASELINE ASSESSMENT AND STRATEGIC PLAN FOR BYWAY IN NORTH PACOLET WATERSHED.
HENDERSONPOLK
VARIOUS
RURAL PROJECTSR-5747 8800SR 1304 (FIE TOP ROAD) AT GHOST TOWN
USA TO JENKINS CREEK ROAD. UPGRADE ROADWAY.
9.4
DIV
T 100R T 5800C C 2900
HAYWOODJACKSON
US 19
DIVISION PROJECT - PLANNING/DESIGN IN PROGRESS
R-2409 22931 12581NC 107 AT CASHIERS TO US 178 AT ROSMAN. SAFETY IMPROVEMENTS AND CLIMBING LANES AT SELECTED LOCATIONS.
HP 4350C C STP 1000R D STP 5000C D
A CASHIERS TO JACKSON-TRANSYLVANIA COUNTY LINE - COMPLETEB 1.1 MILES EAST OF CASHIERS TO 1.6 MILES EAST OF CASHIERS - COMPLETEC WEST OF NC 281 N NEAR LAKE TOXAWAY TO INDIAN CREEK. WIDENING AND REALIGNMENT. - RIGHT OF WAY IN PROGRESSTRND INDIAN CREEK TO FLAT CREEK VALLEY ROAD. WIDENING AND REALIGNMENT
JACKSONTRANSYLVANIA
US 64
14-22 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS
FEASIBILITY STUDY IN PROGRESS
FS-1214C NC 281 TO APPROXIMATELY 1 MILE NORTH OF SR 1157 (PINE CREEK ROAD). WIDEN PAVEMENT TO 24 FEET WITH 5 FEET PAVED SHOULDERS.
7.1JACKSON NC 107
R-5715 12000SR 1449 (COPE CREEK ROAD) TO SR 1783 (COUNCIL CIRCLE). UPGRADE ROADWAY.
1
REG
T R 5800 T U 700 T 5500C
JACKSON NC 107 (E MAIN ST),US 23 BUS. (W MAIN ST)US 23 BUS(ASHEVILLE HW)
R-5600 21275NC 116 TO US 23 BUSINESS. UPGRADE TO MEDIAN DIVIDED FACILITY.
1.9
REG
STP R 7300 STP U 875 STP 13100C
JACKSON NC 107
PLANNING/DESIGN IN PROGRESS
R-4753 19680 813SR 1002 TO NC 281. UPGRADE EXISTING ROADWAY.
4.1
DIV
STP 5000R STP 267M STP C 6800 C 6800
JACKSON NC 107
RIGHT OF WAY IN PROGRESS
R-5206 3857 1576SR 1710 TO US 23/US 74. SAFETY IMPROVEMENTS AND WIDENING TO 10 FEET LANES.
1.9
TRN
T 10C T 71M T 2200C
A SR 1710 TO US 23/US 74. - CLEARING AND GRUBBING ONLYTRN
JACKSON SR 1449 (COPECREEK ROAD)
UNDER CONSTRUCTION
R-5000 26857 26857NC 116 TO NC 107 IN WEBSTER. CONSTRUCT CONNECTOR ON NEW LOCATION.
0.7JACKSON NEW ROUTE
R-5500 5672INDIAN RESERVATION ROAD (IRR) PROGRAM. ROAD AND BRIDGE IMPROVEMENTS TO BE CONSTRUCTED BY EASTERN BAND OF CHEROKEE INDIANS.EX
FLPI 5672C JACKSONSWAIN
VARIOUS
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
FEDERAL BRIDGE PROJECTSB-5905 5820 150REPLACE BRIDGE NO. 27 OVER SCOTT
CREEK AND SOUTHERN RAILROAD.REG
STPON R 270 STPON C 5400
JACKSON US 23 BUSINESS
UNDER CONSTRUCTION
B-4554 8000 8000REPLACE BRIDGE NO. 145 OVER SR 1705, SOUTHERN RAILROAD, AND SCOTT CREEK.SW
JACKSON US 23/US 74
UNDER CONSTRUCTION
B-3480 6274 6274REPLACE BRIDGE NO. 39 OVER EAST FORK TUCKASEGEE RIVER.REG
JACKSON NC 107
B-5910 2130 150REPLACE BRIDGE NO. 32 OVER SAVANNAH CREEK.
HF
HFB 180R HFB 1800C
JACKSON NC 116
14-23 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
RIGHT OF WAY IN PROGRESS
B-4159 6686 886REPLACE BRIDGE NO. 108 OVER TUCKASEGEE RIVER.
DIV
STPON 5800C JACKSON SR 1002(ROGER ROAD)
B-5899 420REPLACE BRIDGE NO. 1 OVER HORSE PASTURE RIVER.
DIV
STPOFF R 20 STPOFF 400C
JACKSON SR 1119(SAPPHIRE POSTOFFICE ROAD)
B-5921 420REPLACE BRIDGE NO. 8 CEDAR CREEK.
DIV
STPOFF R 20 STPOFF C 400
JACKSON SR 1120(CEDAR CREEKROAD)
B-5404 950 200REPLACE BRIDGE NO. 136 OVER PINE CREEK.
DIV
STPOFF 50R STPOFF C 700
JACKSON SR 1163(BIG PINE CREEK)
B-5410 985 150REPLACE BRIDGE NO. 221 OVER LITTLE SAVANNAH CREEK.
DIV
STPOFF 35R STPOFF C 800
JACKSON SR 1367(LITTLE SAVANNAHROAD)
UNDER CONSTRUCTION
B-4162 2111 2111REPLACE BRIDGE NO. 320 OVER SOUTHERN RAILWAY.
DIV
JACKSON SR 1432(SKYLINE DRIVE)
B-5902 260REPLACE BRIDGE NO. 99 OVER FISHER CREEK.
DIV
STPOFF R 10 STPOFF 250C
JACKSON SR 1447(DILLS BRANCHROAD)
UNDER CONSTRUCTION
B-3861 1987 1987REPLACE BRIDGE NO. 107 OVER TUCKASEGEE RIVER.
DIV
JACKSON SR 1731(WEYEHUTTA ROAD)
UNDER CONSTRUCTION BY FEDERAL HIGHWAY ADMINISTRATION - FEDERAL LANDS ACCESS PROGRAM (FLAP) PROJECT
B-4472 2955 2955REPLACE BRIDGE NO. 80 OVER CANEY CREEK. NANTAHALA NATIONAL FOREST, FEDERAL AID NUMBER NC FLAP DOT BR80(1).
DIV
JACKSON SR 1737FH 102(CANEY FORK ROAD)
B-5159 1551 213REPLACE BRIDGE NO. 101 OVER CANEY CREEK.
HF
HFB R 135 HFB M 3 HFB C 1200
JACKSON SR 1740(MOSES CREEKROAD)
14-24 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
UNDER CONSTRUCTION
W-5315 5832 5832EXIT 98 IN HAYWOOD COUNTY TO 0.1 MILE WEST OF THE JACKSON-HAYWOOD COUNTY LINE. REMOVE CONCRETE ISLAND, REPAVE WITH ASPHALT, DRAINAGE MODIFICATIONS, AND INSTALL GUARDRAIL.
4.8
TRN
HAYWOODJACKSON
US 74
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-25 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
RURAL PROJECTSR-5734 6290US 64 TO SR 1652 (WIDE HORIZON DRIVE)/SR
1152 (BELDEN CIRCLE). IMPLEMENT ACCESS MANAGEMENT STRATEGIES.
0.8
DIV
T R 530 T U 60 T 5700C
MACON US 23/US 441
RIGHT OF WAY IN PROGRESS
R-5115 1448 623US 23/US 441 IN FRANKLIN TO NC 106 IN HIGHLANDS. CONSTRUCT TRUCK INFORMATION STATIONS AND TRUCK TURN-AROUNDS.
19TRN
T 825C MACON US 64/NC 28
R-2408 25918 25918SR 1729 (DEPOT STREET EXTENSION) TO SR 1378 (BENNETT ROAD). UPGRADE AND MAKE SAFETY IMPROVEMENTS.
3.5
A US 441 BUSINESS TO NC 28 - COMPLETEB NORTH OF SR 1323 (RIVERVIEW STREET) TO SOUTH OF SR 1378 (BENNETT ROAD) - UNDER CONSTRUCTION
MACON NC 28 ANDSR 1323
UNDER CONSTRUCTION
R-4748 19440 19440SR 1660 (SILER ROAD) TO SR 1662 (WILEY BROWN ROAD) SOUTH OF US 441 IN FRANKLIN. TWO LANE ROADWAY ON NEW LOCATION.
0.7MACON NEW ROUTE
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-26 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025URBAN PROJECTS
U-5604 7300US 23/US 64/US 441 TO PORTER STREET. INTERSECTION IMPROVEMENTS AT WOMAK STREET, MAPLE STREET, PORTER STREET, AND DEPOT STREET IN FRANKLIN.
1.4
REG
STP R 1600 STP 5700C
MACON US 441 BUSINESS
FEASIBILITY STUDIES
FEASIBILITY STUDY IN PROGRESS
FS-1214A SR 1649 (PRENTISS BRIDGE ROAD) TO US 64. UPGRADE ROADWAY WITH ACCESS MANAGEMENT FEATURES.
3.2MACON US 23US 441
FEDERAL BRIDGE PROJECTSB-5125 2725 275REPLACE BRIDGE NO. 22 OVER LITTLE
TENNESSEE RIVER.HF
HFB 400R HFB C 2050
MACON US 441 BUSINESS
DIVISION PURCHASE ORDER CONTRACT (DPOC)
B-4775 572 72REPLACE BRIDGE NO. 17 OVER WAYAH CREEK.
DIV
STPOFF R 50 STPOFF C 450
MACON SR 1309(CRANFORD ROAD)
B-5912 260REPLACE BRIDGE NO. 181 OVER TELLICO CREEK.
DIV
STPOFF 10R STPOFF 250C
MACON SR 1369(BYRD ROAD)
B-5914 260REPLACE BRIDGE NO. 180 OVER SUGAR COVE CREEK.
DIV
STPOFF 10R STPOFF 250C
MACON SR 1369(BYRD ROAD)
B-5908 360REPLACE BRIDGE NO. 127 OVER BURNINGTOWN CREEK.
DIV
STPOFF 20R STPOFF 340C
MACON SR 1387(OLIVE HILL ROAD)
RIGHT OF WAY IN PROGRESS
B-3868 3686 736REPLACE BRIDGE NO. 172 OVER LITTLE TENNESSEE RIVER AND CONSTRUCT IMPROVEMENTS TO NC 28.DIV
STPOFF C 2950 MACON SR 1456
B-5406 1140 150REPLACE BRIDGE NO. 67 OVER RABBIT CREEK.
HF
HFB R 90 HFB C 900
MACON SR 1513(CAT CREEK ROAD)
B-5919 420REPLACE BRIDGE NO. 43 OVER MIDDLE CREEK.
DIV
STPOFF 20R STPOFF 400C
MACON SR 1635(MIDDLE CREEKROAD)
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-27 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
ROADSIDE ENVIRONMENTAL PROJECTS (REST AREA)K-5103 285 35US 23/US 441, RENOVATION OF REST AREA-
BUILDING AND GROUNDS. INCLUDE ADA COMPLIANT FAMILY RESTROOM AND UPGRADE OF FIXTURES AND FINISHES.
TRN
NHP 250C MACON US 23/US 441
14-28 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ROADSIDE ENVIRONMENTAL PROJECTS (REST AREA)
UNDER CONSTRUCTION
S-5102 256 256US 64. MOUNTAIN WATERS SCENIC BYWAY-DRY FALLS. RESTORATION AND IMPROVEMENTS IN THE CULLASAJA GORGE.
MACON US 64
INTERSTATE PROJECTSI-4729 19000US 74/NC 108 INTERCHANGE (EXIT 36).
REVISE INTERCHANGE AND CONSTRUCT IMPROVEMENTS TO NC 108.DIV
T R 1400 T 17600C
POLK I-26
I-5835 6000SR 1525 (DANA ROAD) TO 0.1 MILE EAST OF POLK COUNTY LINE. PAVEMENT REHABILITATION.
7.4
SW
NHPIM C 6000 HENDERSONPOLK
I-26 / US 74
RURAL PROJECTS
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
FEDERAL BRIDGE PROJECTS
DIVISION PURCHASE ORDER CONTRACT (DPOC)
B-4792 759 69REPLACE BRIDGE NO. 4 OVER FORK CREEK (SMALL BRANCH OF PACOLET RIVER).
DIV
STPOFF 40R STPOFF C 650
POLK SR 1102(PEARSON FALLS)
B-5896 260REPLACE BRIDGE NO. 143 OVER PANTHER CREEK.
DIV
STPOFF R 10 STPOFF 250C
POLK SR 1138(SILVER CREEKROAD)
B-5407 1800 150REPLACE BRIDGE NO. 34 OVER WALNUT CREEK.
HF
HFB R 150 HFB C 1500
POLK SR 1311(ROCK SPRINGSROAD)
B-5916 300REPLACE BRIDGE NO. 22 OVER WOLFE CREEK.
DIV
STPOFF 10R STPOFF 290C
POLK SR 1501(HUNTING COUNTRY)
UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
B-4241 623 623REPLACE BRIDGE NO. 24 OVER HOOPER CREEK.
DIV
POLK SR 1520(LANDRUM ROAD)
14-29 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
UNDER CONSTRUCTION
SF-4914D 106 106SR 1150 TO BRIDGE #202. INSTALL GUARDRAIL ALONG STEEP FILL SECTIONS.
POLK SR 1151(GREEN RIVERCOVE ROAD)
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-30 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
ROADSIDE ENVIRONMENTAL PROJECTS (SCENIC)
IN PROGRESS
S-5101 46 46PACOLET RIVER BYWAY. COMPREHENSIVE BASELINE ASSESSMENT AND STRATEGIC PLAN FOR BYWAY IN NORTH PACOLET WATERSHED.
HENDERSONPOLK
VARIOUS
RURAL PROJECTS
UNDER CONSTRUCTION - FEDERAL LANDS ACCESS PROGRAM (FLAP) PROJECT
R-5529 71 71CONSTRUCT HELIPAD ADJACENT TO NC 28 NEAR TSALI FOREST SERVICE RECREATIONAL AREA. FEDERAL AID NUMBER NC FLAP SWN HPAD(1)
EXSWAIN NC 28
R-5500 5672INDIAN RESERVATION ROAD (IRR) PROGRAM. ROAD AND BRIDGE IMPROVEMENTS TO BE CONSTRUCTED BY EASTERN BAND OF CHEROKEE INDIANS.EX
FLPI 5672C JACKSONSWAIN
VARIOUS
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-31 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS
PROGRAMMED FOR PLANNING AND ENVIRONMENTAL STUDY ONLY
A-0009* 883443 83818CORRIDOR "K", US 19/US 74/US 129 AT ANDREWS TO NC 28 EAST OF ALMOND. FOUR LANE DIVIDED FACILITY, PRIMARILY ON NEW LOCATION.
27.1 APD 14300R A APD 925U A APD 366000C A APD R 14900 B APD U 2300 B APD M 2500 B APD 39000C B C 19500 B C 19500 BAPD R 14500 C APD M 22200 C APD 41000G CA G 20500 CA G 20500 CAAPD 91500C CB C 45750 CB C 45750 CBAPD 19000P CC
A US 19 BUSINESS IN ANDREWS TO US 129B US 129 TO NC 143 AT SR 1223 (BEECH CREEK) - DESIGN-BUILD CONTRACTDIVC NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH - RIGHT OF WAY ONLYEXCA NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH. GRADING AND STRUCTURES ( EXCEPT TUNNELS). - DESIGN-BUILD CONTRACTEXCB TUNNELS AT APPALACHIAN TRAIL - DESIGN-BUILD CONTRACTEXCC NC 143 AT SR 1223 (BEECH CREEK) TO NC 28 AT STECOAH. PAVING.DA SR 1121 (WATTIA ROAD) AT ALMONDS TO EXISTING US 19/NC 28 - COMPLETEDB EAST OF CALFPEN GAP IN GRAHAM COUNTY TO SR 1121 (WATTIA ROAD) AT ALMONDS IN SWAIN COUNTY - COMPLETEDC WEST OF SR 1231 (TOBACCO BRANCH ROAD) TO CALFPEN GAP - COMPLETEDD NC 28 AT STECOAH TO WEST OF SR 1231 (TOBACCO BRANCH ROAD) - COMPLETE
CHEROKEEGRAHAMSWAIN
FUTURE US 74
FEDERAL BRIDGE PROJECTS
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-32 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025HAZARD ELIMINATION PROJECTS
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
CONGESTION MITIGATION PROJECTSC-5612 100PROJECTS TO IMPROVE CONGESTION AND
AIR QUALITY IN THE LAND OF SKY RPO AND SOUTHWESTERN RPO.EX
CMAQ C 50 C 50 HAYWOODSWAIN
VARIOUS
C-5151 242GREAT SMOKIES NATIONAL PARK. CONSTRUCT A MIXED-USE PATHWAY.
EX
CMAQ 177C L 65C
HAYWOODSWAIN
EASTERN BANDOF CHEROKEEINDIANS (EBCI)
C-5203 241BIG COVE MIXED USE PATH, CHEROKEE CENTRAL SCHOOL NORTHWARD ON BOTH SIDES OF THE OCONALUFTEE RIVER TO THE EXISTING BIG COVE ROAD MIXED USE TRAIL. CONSTRUCT PEDESTRIAN AND BIKE PATH, PHASES 3 AND 4.
EX
CMAQ 39PE L 10PE CMAQ 77R L 19R CMAQ 77C L 19C
SWAIN EASTERN BANDOF CHEROKEEINDIANS (EBCI)
IN PROGRESS
C-5202 308 119TRANSPORTATION CHOICES. INCREASE EDUCATION EFFORTS THAT INFORM VISITORS ABOUT THE ROLE THEIR TRANSPORTATION CHOICES HAVE IN RELATION TO AIR POLLUTION ISSUES IN GSMNP.EX
CMAQ 91I I 60 L 23I I 15
HAYWOODSWAIN
GREAT SMOKYMOUNTAINSNATIONAL PARK(GSMNP)
14-33 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
RURAL PROJECTS
FEASIBILITY STUDY REEVALUATION IN PROGRESS
R-2702 27000TWO LANES ON MULTI-LANE RIGHT OF WAY. 4.8 STP 7100R STP 19900C
TRANSYLVANIA US 64BREVARD BYPASS
DIVISION PROJECT - PLANNING/DESIGN IN PROGRESS
R-2409 22931 12581NC 107 AT CASHIERS TO US 178 AT ROSMAN. SAFETY IMPROVEMENTS AND CLIMBING LANES AT SELECTED LOCATIONS.
HP 4350C C STP 1000R D STP 5000C D
A CASHIERS TO JACKSON-TRANSYLVANIA COUNTY LINE - COMPLETEB 1.1 MILES EAST OF CASHIERS TO 1.6 MILES EAST OF CASHIERS - COMPLETEC WEST OF NC 281 N NEAR LAKE TOXAWAY TO INDIAN CREEK. WIDENING AND REALIGNMENT. - RIGHT OF WAY IN PROGRESSTRND INDIAN CREEK TO FLAT CREEK VALLEY ROAD. WIDENING AND REALIGNMENT
JACKSONTRANSYLVANIA
US 64
SCHEDULED FOR FEASIBILITY STUDY
FS-1514A SR 1504 (OLD US 64) TO US 276. UPGRADE ROADWAY.
3.7TRANSYLVANIA SR 1540(WILSON ROAD)
R-5743 26050US 64/US 276 TO US 64. CONSTRUCT NEW ROUTE
2.7
DIV
T 6300R T 750U T 14250C C 4750
TRANSYLVANIA NEW ROUTE
IN PROGRESS - PURCHASE ORDER CONTRACT (POC)
R-4048 2519 2519GUARDRAIL INSTALLATION AND SAFETY IMPROVEMENTS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
14-34 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS
R-5605 10700US 64 TO US 276/US 64 IN PISGAH FOREST. 0.8
DIV
T R 100 T U 100 T C 10500
TRANSYLVANIA DAVIDSON RIVERVILLAGECONNECTOR
URBAN PROJECTS
RIGHT OF WAY IN PROGRESS - DIVISION PROJECT
U-5104 4071 2071SR 1348 (PROBART STREET) TO US 64 IN BREVARD. WIDEN ROADWAY.
0.6TRN
STP 2000C TRANSYLVANIA US 64 BUSINESS
FEDERAL BRIDGE PROJECTS
UNDER CONSTRUCTION
B-5010 1506 1506REPLACE BRIDGE NO. 27 OVER ROCKY CREEK WITH CULVERT.REG
TRANSYLVANIA US 64
UNDER CONSTRUCTION AS DESIGN-BUILD PROJECT - FEDERAL LANDS ACCESS PROGRAM (FLAP) PROJECT
B-5555 895 895REPLACE BRIDGE NO. 46 OVER NORTH FORK FRENCH BROAD RIVER. FEDERAL AID NUMBER: NC FLAP DOT 215(2).EX
TRANSYLVANIA NC 215
UNDER CONSTRUCTION AS DESIGN-BUILD PROJECT - FEDERAL LANDS ACCESS PROGRAM (FLAP) PROJECT
B-5554 746 746REPLACE BRIDGE NO. 73 OVER NORTH FORK FRENCH BROAD RIVER. FEDERAL AID NUMBER: NC FLAP DOT 215(1).EX
TRANSYLVANIA NC 215
UNDER CONSTRUCTION
B-4288 1090 1090REPLACE BRIDGE NO. 85 OVER EAST FORK FRENCH BROAD RIVER.
DIV
TRANSYLVANIA SR 1107(EAST FORK ROAD)
B-4822 1030 185REPLACE BRIDGE NO. 13 OVER NICHOLSON CREEK.
DIV
STPOFF 45R STPOFF C 800
TRANSYLVANIA SR 1119(SUGAR LOAF ROAD)
B-5405 645 150REPLACE BRIDGE NO. 139 OVER EAST BRANCH TOXAWAY CREEK.
HF
HFB R 45 HFB C 450
TRANSYLVANIA SR 1139(OLD TOXAWAY ROAD)
B-5915 270REPLACE BRIDGE NO. 29 OVER FLAT CREEK.
DIV
STPOFF 10R STPOFF 260C
TRANSYLVANIA SR 1316(OAK GROVECHURCH ROAD)
UNDER CONSTRUCTION
B-4289 1558 1558REPLACE BRIDGE NO. 93 OVER NORTH FORK FRENCH BROAD RIVER.
DIV
TRANSYLVANIA SR 1324(TENNESSEE GAP ROAD)
UNDER CONSTRUCTION
B-4291 2090 2090REPLACE BRIDGE NO. 193 OVER DAVIDSON RIVER.
DIV
TRANSYLVANIA SR 1504(OLD US 64)
B-5403 1140 200REPLACE BRIDGE NO. 196 OVER CRAB CREEK.
DIV
STPOFF 40R STPOFF C 900
TRANSYLVANIA SR 1532(ISLAND COVE ROAD)
B-4823 595 150REPLACE BRIDGE NO. 12 OVER HOGSED CREEK.
DIV
STPOFF R 45 STPOFF C 400
TRANSYLVANIA SR 1538(SEA OFF MOUNTAINROAD)
14-35 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS
PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)
BD-5114 17255 15255DIVISION 14 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.
DIV
STPOFF 200R STPOFF 1800C
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
MUNICIPAL BRIDGE PROJECTS
PLANNING/DESIGN BY CITY OF BREVARD
B-5550 883 83RAILROAD AVENUE OVER KINGS CREEK. REPLACE BRIDGE NO. 102.
DIV
STPON 120R L 30R STPON C 520 L C 130
TRANSYLVANIA BREVARD
MITIGATION PROJECTS
IN PROGRESS
EE-4914 18871 18871ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 14 PROJECT MITIGATION.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
HAZARD ELIMINATION PROJECTS
IN PRGRESS - DIVISION PURCHASE ORDER CONTRACT (DPOC)
W-5214 3128 3128DIVISION 14 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.
CHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONPOLKSWAINTRANSYLVANIA
VARIOUS
CONGESTION MITIGATION PROJECTS
IN PROGRESS
C-5564 172 52LAND OF SKY RPO TO WORK WITH REGIONAL CLEAN AIR CAMPAIGN AND CLEAN VEHICLE COALITION TO IMPLEMENT AN EDUCATIONAL AND OUTREACH PROGRAM IN COMMUNITIES ADJACENT TO GREAT SMOKY MOUNTAINS NATIONAL PARK.
EX
CMAQ 65I I 30 L 17I I 8
BUNCOMBEHAYWOODMADISONTRANSYLVANIA
VARIOUS
14-36 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)
UNDER CONSTRUCTION
E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.
ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY
VARIOUS
14-37 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
COUNTY ID
FUTURE YEARS
F
RR - Rail-Highway SafetyRTAP - Rural Transit Assistance ProgramS - State I - ImpementationS (M) - State Match O - OperationsSMAP - Operating Assistance and State Maintenance Oc - OPS Funded CapitalSRTS - Safe Routes to School PE - Preliminary EngineeringSTAT - State PL - Planning / DesignSTHSR - Stimulus High Speed Rail R - Right-of-WaySTPDA - Surface Transportation Program - Direct AttributableSTPE - Surface Transportation Program, EnhancementsSTPEB - Surface Transportation Program, Enhancements (Bike)T - State Highway Trust FundsT2001 - State Rail FundsTAP - Transportation Alternatives ProgramTIGER DISC - TIGER Discretionary Grants
HP - Federal-Aid High PriorityJARC - Job Assistance and Reverse Commute (3037)
(1) FUNDING CATEGORY
DURHAM AREA
SR - Secondary Road
TRANSIT PARTNERROUTE / CITY /
NUMBER
TA-4738
LOCATION / DESCRIPTION
PASSENGER AMENITIES - BUS STOP TRANSIT AUTHORITY
DIV
SHELTERS, BENCHES, SHOP EQUIPMENTSPARE PARTS, ENGINES, SERVICE VEHICLES, ETC.
CP
BUS STOP SHELTER AND BENCHES LOCATED AT HOLLOWAY STREET
ESTIMATED COST Preliminary engineering, right of
C10000
dollars.)
of a project segment indicates (Cash-Flow Funding)Mitigation, Utilities or Construction.
way, utility, mitigation and construction cost estimates
(2) FUNDING SOURCES KEY
O - OtherL - Local
initial scheduled year. (Estimates are in thousand of
For other work types or activities see Work Type (Activity) box below.
work description. CPProject termini and a general
conception and remains with
9000
PROJECT BREAKS
CP
Various - multiple routes
A
5000
FY 2022
C
CP 3000CP
BCP 5000 B
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FY 2023 FY 2024FY 2021
STATE TRANSPORTATION IMPROVEMENT PROGRAM
FY 2020
TOTAL PROJECT
COST (THOU)
FUZFUZ
FUN
DS
A
PRIOR YEARS COST
(THOU)
ACP 700
FY 2015 FY 2016
4000CP
FY 2025
5000
BB
CP CP 5000B
UNFUNDED
NON HIGHWAY PROGRAM
ADIV
FY 2017 FY 2018
BSHOP EQUIPMENT, SPARE PARTS, ENGINES, SERVICE VEHICLES, ETC.
WORK TYPE (ACTIVITY) (3)Phases of implementation:
DIV C
20000
COMMITMENTSFUTURE
by funding category in current dollars. Cost may include one or more funding types. Multi-year funding
Preliminary engineering, Right of Way, UNFUNDED
BUS STOP SHELTER AND BENCHES LOCATED AT GREGSON AVENUE
with proposed work type or activity beginning in the
break.
One or two letter
CP
A
for an explanation of funding categories
FUNDING CATEGORY (1)
DIV
DIVISION 00
DEVELOPMENTAL PROGRAM
DURHAM
FY 2019
TRANSIT PARTNERROUTE / CITY /
NEW ROUTE or CityTRANSIT PARTNER
IDENTIFICATION NUMBER Assigned to each project at
US or NC RoutesI - Interstate
project until completion.
C - City
FEPD - Elderly and Persons with Disablity (5310)
FMOD - Fixed Guideway Modifications
designation for project
any project breaks.Category for the project and
LOCATION / DESCRIPTION
used for each project phase.
FUNDING SOURCE (2)
Identifies the "STI" Funding
See Highway Funding Key
FSPR - State Planning and Research
FNF - New Freedom ProgramFNS - New Starts - Capital (5309)
FMPL - Metropolitan Planning (5303)
FED - Federal Rail Funds
FLAP - Federal Lands Access Program
FUZ - Urbanized Area Formula Program (5307)
CMAQ - Congestion Mitigation
FF - Federal Ferry
FNU - Non Urbanized Area Formula Program (5311)
(3) WORK TYPE (ACTIVITY)
C - ConstructionAD - Administrative
CP - Capital
A - AcquisitionHF - State Dollars (Non-STI)REG - RegionalSW - Statewide
DIV - Division
DP - Discretionary or DemonstrationFBUS - Capital Program - Bus Earmark (5309)
NON HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025BICYCLE AND PEDESTRIAN PROJECTS
EB-5735 225SR 1649 (BULLDOG DRIVE) TO SR 1680 (MURPHY MIDDLE SCHOOL DRIVE). CONSTRUCT SIDEWALK.
0.2
DIV
TAP 16PE L 4PE L 15R TAP C 152 L C 38
CHEROKEE CAMPUS OF MURPHYMIDDLE SCHOOL
PUBLIC TRANSPORTATION PROJECTSTA-6178 328 122CAPITALHF
FNU 206CP CHEROKEE CHEROKEE COUNTY
TK-6118 2505 725ADMINISTRATION
HF
FNU 356O O 178 O 178 O 178 O 178 O 178 178O178O178O FNU
CHEROKEE CHEROKEE COUNTY
TM-6145 28OPERATING
HF
JARC 14O L 14O
CHEROKEE CHEROKEE COUNTY
TQ-6807 138OPERATING
HF
FEPD 69O L 69O
CHEROKEE CHEROKEE COUNTY
TA-6529 71CAPITAL
HF
FEPD 71CP CHEROKEE EASTERN BAND OFCHEROKEE INDIANS
TA-6163 338 127CAPITAL
HF
FNU 211CP CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TK-6127 1644 484ADMINISTRATION
HF
FNU 232O O 116 O 116 O 116 O 116 O 116 116O116O116O FNU
CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TM-6135 190OPERATING ASSISTANCE
HF
JARC 95O L 95O
CHEROKEE EASTERN BAND OFCHEROKEE INDIANS
TM-6153 110OPERATING
HF
JARC 55O L 55O
CHEROKEE EASTERN BAND OFCHEROKEE INDIANS
TN-6118 131MOBILITY MANAGEMENT
HF
FNF 105CP L 13CP S 13CP
CHEROKEE EASTERN BAND OFCHEROKEE INDIANS
TQ-6805 222OPERATING
HF
FEPD 111O L 111O
CHEROKEE EASTERN BAND OFCHEROKEE INDIANS
TQ-8005 52CAPITAL - MOBILITY MANAGEMENT
HF
FNF 46CP L 6CP
CHEROKEE EASTERN BAND OFCHEROKEE INDIANS
PUBLIC TRANSPORTATION PROJECTSTA-6162 1788 1574CAPITALHF
FNU 214CP CLAY CLAY COUNTY
TK-6120 2467 699ADMINISTRATION
HF
FNU 360O O 176 O 176 O 176 O 176 O 176 176O176O176O FNU
CLAY CLAY COUNTY
14-41 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
NON HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS
TQ-6178 72MOBILITY MANAGEMENT
HF
FEPD 58CP L 7CP S 7CP
CLAY CLAY COUNTY
PUBLIC TRANSPORTATION PROJECTSTA-6163 338 127CAPITAL
HF
FNU 211CP CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TK-6127 1644 484ADMINISTRATION
HF
FNU 232O O 116 O 116 O 116 O 116 O 116 116O116O116O FNU
CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TK-6130 888 592ADMINISTRATIONHF
FNU 296AD GRAHAM GRAHAM COUNTY
TQ-8001 42CAPITAL - MOBILITY MANAGEMENT
HF
FEPD 34CP L 4CP S 4CP
GRAHAM GRAHAM COUNTY
TQ-6801 202OPERATINGHF
FEPD 202O GRAHAM GRAHAM COUNTY
BICYCLE AND PEDESTRIAN PROJECTSU-5535 4013FRENCH BROAD RIVER MPO
TRANSPORTATION ALTERNATIVES (TA) PROGRAM.
DIV
TAP C 597 C 290 C 290 C 290 C 290 290C290C290C C 290 C 290L C 149 C 73 C 73 C 73 C 73 73C73C73C C 73 C 73
BUNCOMBEHAYWOODHENDERSONMADISONTRANSYLVANIA
VARIOUS
EB-5757 150US 23 BUSINESS (SOUTH MAIN STREET) TO BELLE MEADE DRIVE. REDUCE ROADWAY LANES TO THREE AND CONSTRUCT BIKE LANES.
0.3
DIV
TAP 40PE L 10PE TAP 80C L 20C
HAYWOOD BROWN AVENUE
PUBLIC TRANSPORTATION PROJECTSTA-6531 41CAPITAL
HF
FEPD 33CP L 4CP S 4CP
HAYWOOD MOUNTAIN PROJECTS, INC.
TA-6132 728 282CAPITALHF
FNU 446CP HAYWOOD MOUNTAIN PROJECTS, INC.
TK-6149 3291 937ADMINISTRATION
HF
FNU 490O O 233 O 233 O 233 O 233 O 233 233O233O233O FNU
HAYWOOD MOUNTAIN PROJECTS, INC.
TM-5314 805316 OPERATING FOR EMPLOYMENT TRIPS TO BUNCOMBE COUNTY
HF
JARC 40O L 40O
HAYWOOD MOUNTAIN PROJECTS, INC.
TQ-6182 270OPERATING ASSISTANCE
HF
FEPD 135O L 135O
HAYWOOD MOUNTAIN PROJECTS, INC.
14-42 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
NON HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS
TQ-6183 127MOBILITY MANAGEMENT
HF
FEPD 101CP L 13CP S 13CP
HAYWOOD MOUNTAIN PROJECTS, INC.
TM-5320 534FY 2011 FTA SECTION 5316 JARC (STATEWIDE ALLOCATION) OPERATING ASSISTANCE FOR JARC PROJECTS IN ASHEVILLE URBANIZED AREA INCLUDING MOUNTAIN MOBILITY (BUNCOMBE), MOUNTAIN PROJECTS (HAYWOOD AND ASHEVILLE TRANSIT)
HF
JARC 267O L 267O
BUNCOMBEHAYWOOD
ASHEVILLE REDEFINESTRANSIT
BICYCLE AND PEDESTRIAN PROJECTSU-5535 4013FRENCH BROAD RIVER MPO
TRANSPORTATION ALTERNATIVES (TA) PROGRAM.
DIV
TAP C 597 C 290 C 290 C 290 C 290 290C290C290C C 290 C 290L C 149 C 73 C 73 C 73 C 73 73C73C73C C 73 C 73
BUNCOMBEHAYWOODHENDERSONMADISONTRANSYLVANIA
VARIOUS
EB-5537 1300 100OKLAWAHA GREENWAY, PATTON PARK TO BALFOUR ROAD/BERKLEY MILLS IN HENDERSONVILLE. CONSTRUCT GREENWAY.
TRN
STPEB 1200C HENDERSON HENDERSONVILLE
PUBLIC TRANSPORTATION PROJECTSTA-6558 106CAPITAL
HF
FNU 84CP L 11CP S 11CP
HENDERSON APPLE COUNTRY TRANSIT
TA-6533 93CAPITAL
HF
FEPD 75CP L 9CP S 9CP
HENDERSON APPLE COUNTRY TRANSIT
TQ-6185 282Operating ASSISTANCEHF
FEPD 282O HENDERSON APPLE COUNTRY TRANSIT
TG-4951 6428 1621ROUTINE CAPITAL - COST OF CONTRACTING
HF
FUZ 610Oc Oc 305 Oc 305 Oc 305 Oc 305 Oc 305 480Oc480Oc480Oc SMAP 352O O 176 O 176 O 176 O 176 O 176
HENDERSON APPLE COUNTRY TRANSIT,
TG-6143 514 124ROUTINE CAPITAL - BUS STOP SHELTERS, BENCHES, SHOP EQUIPMENT, SPARE PARTS, ENGINES, FAREBOX, SERVICE VEHICLES, ETC
HF
FNU FUZ 78CP CP 39 CP 39 CP 39 CP 39 CP 39 39CP39CP39CP
HENDERSON APPLE COUNTRY TRANSIT,
TK-5176 2016 533ADMINISTRATION
HF
FNU 322O O 108 O 108 O 108 O 135 O 135 135O135O135O FNU L 61O O 20 O 20 O 20 S 20O O 7 O 7 O 7
HENDERSON APPLE COUNTRY TRANSIT,
TO-6106 672 112OPERATING ASSISTANCEHF
FNU 112O O 56 O 56 O 56 O 56 O 56 56O56O56O HENDERSON APPLE COUNTRY TRANSIT,
TS-5101 50 21SAFETY & SECURITY - MIN. 1% SET ASIDEHF
FUZ 6CP CP 3 CP 3 CP 3 CP 3 CP 2 3CP3CP3CP HENDERSON APPLE COUNTRY TRANSIT,
TD-5265 321 246CITY OF HENDERSONVILLE - - US 64 PEDESTRIAN ACCESS TO BUS STOPS IMPROVEMENTS (SIDEWALKS AND CROSSWALKS) FOR FY 2013-2016
HF
FNF 75CP HENDERSON ASHEVILLE REDEFINES TRA
TM-5138 434 204BUNCOMBE COUNTY - BLACK MOUNTAIN TRAILBLAZER SERVICE JOB ACCESS REVERSE COMMUTE OPERATING ASSISTANCEHF
JARC 115O L 115O
BUNCOMBEHENDERSON
ASHEVILLE REDEFINESTRANSIT
14-43 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
NON HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS
TA-6163 338 127CAPITAL
HF
FNU 211CP CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TK-6127 1644 484ADMINISTRATION
HF
FNU 232O O 116 O 116 O 116 O 116 O 116 116O116O116O FNU
CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TA-6266 335 58CAPITALHF
FNU 277CP JACKSON JACKSON COUNTY
TK-6137 2632 752ADMINISTRATION
HF
FNU 376O O 188 O 188 O 188 O 188 O 188 188O188O188O FNU
JACKSON JACKSON COUNTY
TQ-6179 276OPERATING ASSISTANCE
HF
FEPD 138O L 138O
JACKSON JACKSON COUNTY
TQ-7180 77MOBILITY MANAGEMENT
HF
FEPD 61CP L 8CP S 8CP
JACKSON JACKSON COUNTY
TA-6192 457 177REPLACEMENT VAN
HF
FNU 280CP JACKSON TRANSPORTATION ADMIN.OF CLEVELAND COUNTY
BICYCLE AND PEDESTRIAN PROJECTSEB-5756 294US 441 BUSINESS (EAST MAIN STREET) TO
SR 1667 (WAYAH STREET). CONSTRUCT MISSING SECTIONS OF SIDEWALK ALONG WEST SIDE AND CONSTRUCT NEW SIDEWALK ALONG EAST SIDE.
0.6
DIV
TAP 14PE L 4PE TAP 221C L 55C
MACON SR 1729(DEPOT STREET)
PUBLIC TRANSPORTATION PROJECTSTA-6198 39 28CAPITALHF
FNU 11CP MACON MACON COUNTY
TA-6530 7CAPITAL
HF
FEPD 5CP L 1CP S 1CP
MACON MACON COUNTY
TK-6142 2815 907ADMINISTRATION
HF
FNU 380O O 191 O 191 O 191 O 191 O 191 191O191O191O FNU
MACON MACON COUNTY
TN-6123 40SECTION 5317 OPERATINGHF
FNF 40O MACON MACON COUNTY
TQ-8006 9MACON COUNTY 5317 CAPITAL
HF
FNF 7CP L 2CP
MACON MACON COUNTY
TQ-6781 356OPERATING ASSISTANCE
HF
FEPD 178O L 178O
MACON MACON COUNTY
14-44 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
NON HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025BICYCLE AND PEDESTRIAN PROJECTS
EB-5759 250WALKER ROAD TO WHEELER ROAD. CONSTRUCT SIDEWALK.
0.4
DIV
TAP 20PE L 5PE L 75R TAP C 120 L C 30
POLK PENIEL ROAD
PUBLIC TRANSPORTATION PROJECTSTA-6208 595 197CAPITAL
HF
FNU 318CP L 40CP S 40CP
POLK POLK COUNTYTRANSPORTATION
TK-6155 2679 736ADMINISTRATION
HF
FNU 471O O 184 O 184 O 184 O 184 O 184 184O184O184O FNU
POLK POLK COUNTYTRANSPORTATION
BICYCLE AND PEDESTRIAN PROJECTSEB-5737 448DOWNTOWN BRYSON CITY TO SWAIN
COUNTY HIGH SCHOOL. CONSTRUCT MULTI-USE PATH.
1.3
DIV
TAP 22PE L 6PE L 7R TAP 330C L 83C
SWAIN SR 1364 (FONTANADRIVE)
EB-5758 100US 441 END OF SIDEWALK TO ACQUONI ROAD END OF SIDEWALK. CONSTRUCT SIDEWALK, CURB CUTS, AND PEDESTRIAN SIGNALS.
0.1
DIV
TAP 5PE L 1PE TAP C 75 L C 19
SWAIN SR 1378(ACQUONI ROAD)
PUBLIC TRANSPORTATION PROJECTSTA-6163 338 127CAPITAL
HF
FNU 211CP CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TK-6127 1644 484ADMINISTRATION
HF
FNU 232O O 116 O 116 O 116 O 116 O 116 116O116O116O FNU
CHEROKEEGRAHAMJACKSONSWAIN
EASTERN BAND OFCHEROKEE INDIANS
TA-6532 5CAPITAL
HF
FEPD 3CP L 1CP S 1CP
SWAIN SWAIN COUNTY FOCALPOINT ON AGING, INC.
TA-6545 2400CAPITAL
HF
FNU 1920CP L 240CP S 240CP
SWAIN SWAIN COUNTY FOCALPOINT ON AGING, INC.
TA-6557 2400CAPITAL
HF
FNU 1920CP L 240CP S 240CP
SWAIN SWAIN COUNTY FOCALPOINT ON AGING, INC.
TK-6165 1784 514ADMINISTRATION
HF
FNU 204O O 102 O 102 O 102 O 127 O 127 127O127O127O FNU L 38O O 19 O 19 O 19 S 12O O 6 O 6 O 6
SWAIN SWAIN COUNTY FOCALPOINT ON AGING, INC.
14-45 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project
NON HIGHWAY PROGRAMDIVISION 14
ROUTE/CITYCOUNTYID
LOCATION / DESCRIPTION (THOU) (THOU)NUMBER
PRIORYEARSCOST
TOTALPROJCOST
LENGTH
TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS
FUNDS FY 2016
UNFUNDED
FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020
STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM
FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS
TQ-6184 59MOBILITY MANAGEMENT
HF
FEPD 47CP L 6CP S 6CP
SWAIN SWAIN COUNTY FOCALPOINT ON AGING, INC.
TQ-6804 60OPERATING
HF
FEPD 30O L 30O
SWAIN SWAIN COUNTY FOCALPOINT ON AGING, INC.
BICYCLE AND PEDESTRIAN PROJECTSU-5535 4013FRENCH BROAD RIVER MPO
TRANSPORTATION ALTERNATIVES (TA) PROGRAM.
DIV
TAP C 597 C 290 C 290 C 290 C 290 290C290C290C C 290 C 290L C 149 C 73 C 73 C 73 C 73 73C73C73C C 73 C 73
BUNCOMBEHAYWOODHENDERSONMADISONTRANSYLVANIA
VARIOUS
PUBLIC TRANSPORTATION PROJECTSTA-6272 118 62CAPITAL
HF
FNU 44CP L 6CP S 6CP
TRANSYLVANIA TRANSYLVANIA COUNTY
TK-6167 2324 680ADMINISTRATION
HF
FNU 284O O 143 O 143 O 143 O 161 O 161 161O161O161O FNU L 54O O 9 O 9 O 9 S 18O O 9 O 9 O 9
TRANSYLVANIA TRANSYLVANIA COUNTY
14-46 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES
AVAILABLE
DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project