State Route 58 - Caltrans - California Department of ... Route 58 Hinkley Expressway Project Project...

1
State Route 58 Hinkley Expressway Project Project Overview Batch Plant Locaon: For more informaon about this project, please go to cal- trans8.info for news release/commuter alerts. Follow us on Twier at www.twier.com/caltrans8. California Department of Transportaon San Bernardino County, California District 8 — SBD — SR58 — Post Mile 22.2 to 31.1 March 2016 The California Department of Transportaon (Caltrans) project to widen a poron of State Route 58 from a two-lane convenonal high- way to a four-lane expressway, is now in the construcon phase. The improvements to State Route 58 extend from approximately 2.8 miles west of Hidden River Road to approxi- mately 0.7 miles east of Lenwood Road, in and around the unincorporated Community of Hin- kley, in San Bernardino County. The express- way would include: 12-foot standard trav- eled way lanes; 10-foot standard shoulder widths; and a 78-foot-wide median. Two interchanges will be constructed; one at Hinkley Road and the other at Lenwood Road. This realigned roadway would be con- structed on a fill secon (elevated secons of a roadway). Start Concrete Paving New Hwy 58 - April 2016 New Batch Plant - April 2016 Complete import of fill - April 2016 Open Hinkley Road - Mid-July 2016 Open Lenwood Road - February 2017 Open New Hwy 58 Expressway - November 2016 Permanent Closure of Existing Hwy 58 to Through Traffic (W/o Valley View Rd) - November 2016 Start Asphalt Overlay on Existing Hwy 58 - November 2016 Finish Asphalt Overlay on Existing Hwy 58 - December 2016 Open Lenwood WB Exit Ramp - February 2017 Planned Construction Duration - Early 2017 Public Information Officer Philip Havins (909) 383-6799 [email protected] Resident Engineer Shaine Shahidi Project Manager Jim Robinson http://www.dot.ca.gov/dist8/Project-SR-58-Hinkley.html Project Construcon Schedule * Project Contacts *Please note that the above dates are initial estimates and subject to change through out the duration of construction. Project schedule updates will be available from Caltrans project contacts. NTS

Transcript of State Route 58 - Caltrans - California Department of ... Route 58 Hinkley Expressway Project Project...

Page 1: State Route 58 - Caltrans - California Department of ... Route 58 Hinkley Expressway Project Project Overview Batch Plant Location: For more information about this project, please

State Route 58 Hinkley Expressway Project

Project Overview

Batch Plant Location:

For more information about this project, please go to cal-trans8.info for news release/commuter alerts.

Follow us on Twitter at www.twitter.com/caltrans8.

California Department of Transportation San Bernardino County, California District 8 — SBD — SR58 — Post Mile 22.2 to 31.1 March 2016

The California Department of Transportation (Caltrans) project to widen a portion of State Route 58 from a two-lane conventional high-way to a four-lane expressway, is now in the construction phase. The improvements to State Route 58 extend from approximately 2.8 miles west of Hidden River Road to approxi-mately 0.7 miles east of Lenwood Road, in and around the unincorporated Community of Hin-kley, in San Bernardino County. The express-way would include: 12-foot standard trav-eled way lanes; 10-foot standard shoulder widths; and a 78-foot-wide median.

Two interchanges will be constructed; one at Hinkley Road and the other at Lenwood Road. This realigned roadway would be con-structed on a fill section (elevated sections of a roadway).

Start Concrete Paving New Hwy 58 - April 2016

New Batch Plant - April 2016

Complete import of fill - April 2016

Open Hinkley Road - Mid-July 2016

Open Lenwood Road - February 2017

Open New Hwy 58 Expressway - November 2016

Permanent Closure of Existing Hwy 58 to Through Traffic (W/o Valley View Rd) - November 2016

Start Asphalt Overlay on Existing Hwy 58 - November 2016

Finish Asphalt Overlay on Existing Hwy 58 - December 2016

Open Lenwood WB Exit Ramp - February 2017

Planned Construction Duration - Early 2017

Public Information Officer

Philip Havins

(909) 383-6799

[email protected]

Resident Engineer

Shaine Shahidi

Project Manager

Jim Robinson

http://www.dot.ca.gov/dist8/Project-SR-58-Hinkley.html

Project Construction Schedule*

Project Contacts

*Please note that the above dates are initial estimates and subject to change through out the duration of construction. Project schedule

updates will be available from Caltrans project contacts.