STATE HIGH RENEWAL PROJECT “KICK-OFF” MEETING
July 14, 2014
Crabtree, Rohrbaugh & Associates, Architects
Agenda
Opening Remarks
Overview/Purpose
Design Team Introductions
Schematic Design ConceptsSite PlanBuilding
General Timeline
Your Thoughts/Questions
State High Renewal – Schematic Design Concepts
Site Improvement Goals
•Access Management and Circulation•Vehicular and Pedestrian
•Sufficient Parking at Appropriate Locations•Short-Term/Visitor•Event
•Improved Storm Water Management•Minimize Impervious Footprint
•Enhanced ADA Accessibility •Maintain Physical Education and Athletic Facilities
State High Renewal – Schematic Design Concepts
Overall Campus
Concept for Future Community Field Improvements (Not Part of the Renewal)
Concept for Future Community Field Improvements (Not Part of the Renewal)New Athletic Field
(Grass, Included in Renewal)
New Athletic Field (Grass, Included in Renewal)
State High Renewal – Schematic Design Concepts
4-Way, Signalized Intersection
4-Way, Signalized Intersection 4-Way,
Signalized Intersection
4-Way, Signalized Intersection
Drop-off and ADA parking
Drop-off and ADA parking
Main Parking North (Band Practice)
Main Parking North (Band Practice)
Main Parking South (Track)Main Parking South (Track)
Bus Staging for Dismissal and Event Parking
Bus Staging for Dismissal and Event Parking
Drop-off Loop & Visitor Parking
Drop-off Loop & Visitor Parking
Primary SWM Area (South)
Primary SWM Area (South)
Primary SWM Area (North)
Primary SWM Area (North)
Separate Bus AccessSeparate Bus Access
Architectural Massing Study Views
State High Renewal – Schematic Design Concepts
Massing Study - Aerial View Looking North
State High Renewal – Schematic Design Concepts
Massing Study - Aerial View Looking South
State High Renewal – Schematic Design Concepts
Massing Study – Looking West (above O’Bryan Ln.)
State High Renewal – Schematic Design Concepts
Massing Study – Looking South
State High Renewal – Schematic Design Concepts
Massing Study – Looking Southeast
State High Renewal – Schematic Design Concepts
Massing Study – Looking Southeast (above Welch)
State High Renewal – Schematic Design Concepts
Massing Study - Main Entry View
State High Renewal – Schematic Design Concepts
State High Renewal – General Timeline
• Overall Goal – Construction Start Summer 2015•Approximate 30 month duration – in Phases
•Municipal and State Approvals •Concurrent with Construction Documents and District Process•Municipal
•Land Development Plans (Preliminary & Final)•Conditional Use for Parking Reduction (with Prelim. LD)•Zoning (Building Height and other Variances)•Traffic Study
•State•NPDES (Storm Water)•PennDOT for Traffic Signal Permits
State High Renewal – General Timeline