State College Area School District...Building Veneer Installation of the exterior veneer systems...

9
State College Area School District September 12, 2018

Transcript of State College Area School District...Building Veneer Installation of the exterior veneer systems...

Page 1: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

State College Area School District

September 12, 2018

Page 2: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

Unit D – 2nd Floor Steel & Deck

Roof joists and decking are being set in Unit D.

Page 3: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

Unit C & D – Masonry Walls

Masonry walls have continued to go up in Units C & D – 1st and 2nd floors.

Unit D

Unit C: Multi-Purpose Room (C132)

Unit C: LGI Room (C130)

Page 4: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

Unit C – 2nd Floor Steel & Deck

Roof decking is being placed in Unit C 2nd floor. Roofing is scheduled to start the week of September 10, 2018.

The classrooms have all received roof joists and decking.

The Large Group Instruction Room has taken shape with the

stair steel and high roof steel installation

underway.

Page 5: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

Site – Utility Installation

Lobar subcontractor installed the new underground storm water

line down Highland Alley to CorlStreet.

On August 16, 2018, the Columbia Gas contractor

installed the new gas line down Highland Alley to Corl Street.

West Penn set the new transformer on August 20, 2018.

Page 6: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

Building Veneer

Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board –pictured left and above.

Interior brick veneer installation has begun in Stair 1B (D103) – pictured below.

Page 7: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

MEP Progress – HVAC & Plumbing

Silvertip installed roof drain piping in Unit D 2nd floor.

Midline extended ductwork into Unit D 1st floor.

The Exterior Mechanical Yard has progressed with the CMU walls and transformer installation.

Unit C 1st floor corridor above-ceiling rough-ins.

Page 8: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

MEP Progress - Electrical

Pictured above, Farfieldhas begun installing above-ceiling rough-ins in Unit D

2nd floor classrooms.

Farfield has mounted panel boxes in Unit C first and second floor electrical rooms. Cabling is continuing to be pulled for both floors.

Pictured above, Farfield is terminating feeder cables in the new building switchgear.

Page 9: State College Area School District...Building Veneer Installation of the exterior veneer systems began at the end of August with the metal stud framing, insulation, and wall board

Overall Progress

Upcoming Work• Roofing installation in Unit C• Complete CMU walls in Units C & D• Continue MEP Rough Ins• Multi-Purpose Room – Complete

under slab rough-ins and place concrete slab on grade

Project StatsSafety = 192 Days with Zero Recordable Accidents

ScheduleOn schedule for Move-In to Phase 1 -January 2019 and Project Completion -August 2019