STATE CAPITAL OUTLAY PLANNING
CCC Chancellor’s OfficeCheryl Larry
Lan Yuan
San Mateo CCDJose Nunez
Karen Pinkham
CCFC 2016
AGENDA
Overview
Eligibility
Priority
Review/Approval
Effective Practices
2
Key Policies
Zero-Based Budgeting
>$656k
State-Supportable
No Augmentation
One Project per Campus
In a 2-Year Cycle
FUSION
Facilities Planning
Space Inventory
Building Assessment
Project Administration
3
Application Components
Facilities Master Plan
Five-Year Plan
Initial Project Proposal
Final Project Proposal
Space Inventory
Enrollment Projections
Space Inventory
Due October
Existing Capacity
Age of site/building
ASF summary by space type
Keep Current
4
Five-Year Capital Outlay Plan
Call Letter
Project Planning
Enrollment (Load)
Priority
Status
Category
Initial Project Proposal
Input from users
Prerequisite for FPP (except Cat. A)
Submitted 3 years prior to funding
Conceptual
5
Final Project Proposal
Submitted 2 years prior to funding
Formal proposal
SAM
JCAF 31, 32, & 33
Quantities and Unit Cost
Diagrams
New Quantities and Unit Cost
Rolled out for 2018-19 plan
Minimize data entries
JCAF 31 data populates in Q&UC
Q&UC auto populates JCAF 31
Reduce computations
Q&UC formulated costs
Escalation options
Enhance consistency
6
FUSION Plan Year 2019-20
• 2019-20, Space Inventory 16-17
Oct 2016*
• Enrollment Projections (2016)
Feb 2017• 2019-20 5YP• 2019-20 FPP• 2020-21 IPP• Local/Future
July 2017
*Energy Usage Calculators
Capacity Load
Laboratory and Lecture
OfficeLibrary and
AV/TV
Capacity(ASF in S.I. and 5YP)
ASF to WSCHASF to Staff FTE
ASF
Load (Enrollment Forecast)
WSCH Staff FTEDay Enrollment
to ASF
7
Category Criteria• Least cost solution:
• A1 Imminent danger to building occupants• A3 Seismic deficiency• A4 Immediate infrastructure failure
• Independent 3rd party report
Cat. A (Safety)
• Expands program/support space• Preponderance of space cannot be >105%
Cat. B Instructional & Cat. E Inst. Support (Growth)
• Program/support efficiency• No GSF growth except for code• Cannot create or sustain overbuilt status
Cat. C Instructional & Cat. F Inst. Support (Modernization)
• Growth or modernization, i.e.,• Performing Arts• Physical Education• Child Dev. Center
Cat. D
(Complete Campus)
Board’s Funding Priorities
Allocation
Cat. B50% of
remaining
Cat. C25%
Cat. D15%
Cat. E5%
Cat. F5%
Cat. A up to 50%
of total
8
Prioritizing Cat. B and E
Factors (up to 50 points each):
Enrollment Growth
Existing Inventory
ASF Change
Local Contribution
Prioritizing Cat. C and F
Factors:
Age of Building (up to 120 points)
Activation of Unused Space (30 points)
Local Contribution (up to 50 points)
9
Prioritizing Cat. D
Factors (up to 50 points each): Age of Site
Program Service Offerings Enrollment growth or code= 10 pts.
New degree/certificate= 20 pts.
Initial program offering on campus= 20 pts.
Project Design Solutions (3 options) Replace temporary building= 50 pts.
Structurally/functionally deficient building= 30 pts.
Addition/expansion= 20 pts.
Local Contribution
Approval TimelinePlan Year 2018-19
• June 2018
Budget Act
• Feb 2018
LAO Analysis
• Jan 2018
Gov’s Budget
• Summer/Fall 2017
DOF
• Spring 2017
Board’s Spending Plan
• Summer-Winter 2016
FPU
10
CCC System
Estimated Systemwide Needs= $28 billion
2016 Local Bonds= $10 billion for 16 districts
Prop. 51= $2 billion
$750 million 2017-18
$750 million 2018-19
$500 million 2019-20
Resources
Chancellor’s Office Website
http://extranet.cccco.edu/Divisions/FinanceFacilities/FacilitiesPlanning/ReferenceMaterials.aspx
FUSION Help Desk
Email [email protected]
Call 1-866-325-3222
FPU Specialist
11
Questions?
1
CCFC 23rd Annual Conference State Capital Outlay Planning
Facilities Master Planning / Project Sequencing / Onuma
November 15, 2016
Facilities Master Planning
District Strategic Plan
College Educational Master Plan (2000, 2005, 2014)
Facilities Assessment (Building Systems & Infrastructure) 2001
Energy Audit 2001, 2010
Facilities Master Plan
2001 TBp Architecture
2005 Steinberg Architecture
2011 HMC Architecture
2015 Amendment to the 2011 HMC Architecture
Funding
Local Bond Measures (C, A, H)
State (Capital Outlay, SMSR, Haz Mat)
Grants / Rebates (CCC/IOU, Prop 39, CPUC)
2
2015 Facilities Master Plan Amendment
Cañada CollegeFacilities Master Plan Map
3
College of San Mateo Facilities Master Plan Map
Skyline College Facilities Master Plan Map
4
Capital Improvement Program (CIP) Funding Local Bond / State Funding / Grants / Rebates
CIP 1
2001 Measure C $207M
State Funding $65M
Local / Grant / Rebates
CIP 2
2005 Measure A $568M
State Funding $35M
Local / Grant / Rebates
CIP 3
2015 Measure H $388M
State Funding $25M ($19M)
Local / Grant / Rebates
State Capital Outlay Projects Approved Capital Outlay Funding (FY17-18 FPPs) State Funds Local Match Total
CSM B9 Library/Learning Resources$11,709,000 $11,410,000 $23,119,000
SKY B2 Workforce & Economic Development $13,433,000 $12,981,000 $26,414,000
TOTAL $25,142,000 $24,391,000 $49,533,000
Pending Capital Outlay Funding (FY18-19 FPPs)
CAN B13 Multiple Disciplinary Instructional $7,134,000 $11,503,094 $18,637,190
SKY B5 Learning Resource Ctr Tech and Env Upgrade $12,345,000 $11,911,000 $24,256,000
TOTAL $19,479,000 $23,414,094 $42,893,190
Submitted Capital Outlay Funding (FY19-20 IPPs)
CSM B8 Demolition & New Kinesiology $35,118,000 $34,882,000 $70,000,000
CAN B3 Performing Arts Center Tech and EnvModernization
$11,039,000 $10,566,000 $ 21,605,000
TOTAL $46,157,000 $45,448,000 $91,605,000
5
Capital Improvement Program (CIP) CIP 1 & 2 Projects
2001 – 2005 CIP 1
CAN 9 New Construction (State $)
CAN 22 New Construction
CAN Facilities Maintenance Center (FMC) (State $)
CSM 18 Modernization (State $)
CSM 35 New Construction
CSM 36 New Construction
SKY 2 Modernization Phase II
SKY 3 Modernization (State $)
SKY 6/7A New Construction
SKY 7 Modernization (State $)
SKY 8 HHW
SKY 8 Seismic Upgrade & Modernization
SKY 19 Pac Heights Swing
SKY Facilities Maintenance Center (FMC) (State $)
DW Athletics
2005 – 2011 CIP 2
CAN 5/6 Modernization (State $)
CAN 16/18 Modernization
CAN Electrical Infrastructure Upgrade
CAN Gateways
CAN 12 Pony Espresso
CSM 2 & 4 Modernization
CSM Design Build: 5N, 10N, Site Work, Aquatics, Chiller, 12KV
CSM 12, 15, 17 & 34 Modernization
CSM North Gateway (State $)
SKY 19 Pac Heights Swing
SKY Design Build: 4N, 11N, Site Work
SKY Electrical Infrastructure Upgrade (State $)
CIP3 Phase 1 Projects (2014 – 2022)
CAN 1 Demo & New Kinesiology – DB Awarded (Blach Construction / ELS Architects)
CAN 23N Math & Science – RFP in Progress
CSM 3 Theater Modernization – CDs (TLCD Architects)
CSM 12 / 19 Demo & New Construction – Programming (Steinberg Architects)
CSM 17 Student Life / Faculty Office Tennant Improvement – DSA (Cody Anderson Wasney Architects)
CSM Solar PV Energy Storage – RFP Development
SKY 1 Social Science / Creative Arts (Demo & New Construction) and Boiler Plant Relocation – RFSOQ in Progress
SKY 12N Environmental – DB Awarded (XL Construction / Ratcliff Architects)
SKY Lot L Expansion – DSA (Carducci Landscape)
SKY 19 (PH) – Schematic Design in Progress (Group 4 Architects)
DW Network Upgrade – In Progress
DW Door Lock Upgrade (Mandated by BOT 10/28/15) – Phase 1 Completed, Phase 2 in Progress
DW Fire Alarm Panel Upgrade – AE Selected
6
CIP3 Phase 2 Projects (2018 - 2026)
CAN 3 Modernization (State $) IPP Pending
CAN 13 Modernization (State $) FPP Pending
CAN 16/18 Secondary Effects
CSM 1 Modernization
CSM 8 Demo & New Construction (State $) IPP Pending
CSM 9 Modernization (State $) FPP Approved
SKY 2 Modernization (State $) FPP Approved
SKY 5 Modernization (State $) FPP Pending
DW Roadways & Parking
Process of a Project Facilities Planning is based upon Educational Planning
Budget (Conceptual vs. Actual)
Delivery Method (DBB vs. DB)
Schedule Development & Execution
Academic vs. Construction Logistics
A&E Selection & Design Process (9-12 months)
Programming / Schematic Design / Design Development / Construction Documents
Contractor Procurement (DBB vs. DB)
Permitting (4-7 Months)
Construction (12-24 Months)
Furniture Fixtures and Equipment Installation (FF&E)
Commissioning
Occupancy
Close Out
7
Sequencing of Projects Case Study: Skyline College
6/2017-6/2019
Sequencing of Projects Case Study: Skyline College CIP 3
8
Onuma for Strategic Space SchedulingCase Study: Skyline College
Onuma for Strategic Space SchedulingCase Study: Skyline College
9
Onuma for Strategic Space SchedulingCase Study: Skyline College
Onuma for Strategic Space SchedulingCase Study: Skyline College
4-301 – traditionally used as meeting space
10
Onuma for Strategic Space SchedulingCase Study: Skyline College
Portables – 3A and 3DCurrently dedicated for Athletics Only
Onuma for Strategic Space SchedulingCase Study: Skyline College
Cosmetology Classroom – Currently Dedicated Could easily be used for General Lecture
11
Onuma for Strategic Space SchedulingCase Study: Skyline College
Opportunity to think differently –One lab has 36 stations, One has 40 stationsBoth have PC computers
Question & Answer
Karen Pinkham
Interim Facilities Manager
Cañada College
(650) 306-3325
José D. Nuñez, LEED® AP
Vice Chancellor
Facilities Planning, Maintenance & Operations
(650) 574-6512