Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014...

12
Knutsford to Bowdon Improvement Start of works exhibition November 2014 Welcome An executive agency of the Department for Transport HA Media Services Team, Manchester N140540

Transcript of Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014...

Page 1: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition

November 2014

Welcome

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 2: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Schemeplan

TattonDale

M6

M56M56

A56

A56

A50

A50

A50

A556

A5034

A5033

A556

A556

Junction 8

Junction 7

Junction 19

Tatton ParkTatton Park

MereHall

MereHall

Knutsford ServicesKnutsford Services

Mere

Bucklow Hill

Rostherne

Bowdon

Knutsford

HooGreen

OverTabley

BoothBank

RostherneMere

The

Mer

e

Cicely Mill Lane

Rostherne Lane

Bucklow Hill Lane

Moss Lane

Millington LaneCherry Tree Lane

Millington Hall Lane

Chapel Lane

© C

row

n c

op

yrig

ht

an

d d

ata

ba

se

rig

hts

20

14

Ord

na

nc

e S

urv

ey 1

00

03

06

49

Bentley Hurst Lane

N140519

Diagrammatic

TattonDaleD

M6

M56M56

A56

A56

A50

A50

A50

A556

A5034

A5033

A556

A556

Junction 8

Junction 7

Junction 19

krrPaParraTatton tt nttaTatton Paatton PaTatton PTatton PTT tton Parktton Parkkkaaatto aaaa kkoo rrPPPPnn kn Pn

ereererMMereaHa

scessceServSe Se SrdrdforordKnutsfo sceccd Sedoots sKnutsK serviceKnutsfordd

Mere

BucklowBu Hill

thernetheRRosthR

wdonwdonwdonwdonBowwwd

Knuutsford

HooHoGreen

OverOv rTableyleab y

BoothBankB k

The

Mer

Mer

eer

e

Cicely Mill Lane

Rostherne Lane

Bucklow Hill Lane

ss Lane

Millington LaneCherry Tree Lane

Millington Hall Lane

Chapel Lane

© C

row

n c

op

yrig

ht

an

d d

ata

ba

se

rig

hts

20

14

Ord

na

nc

e S

urv

ey 1

00

03

06

hts

20

Bentley Hurst Lane

N14051940

stherneRostMereM

Cher

A5

B

RRRR

y Mill

Rosthern

64

90

00

Su

rv

on

S

TatTTaaTTTT

© C

row

for

50

Moss Lane

A5

Hurs

A5033

ww

TattonDale

TattonDale

M6

M56M56

A56

A56

A50

A50

A50

A556

A5034

A5033

A556

A556

Junction 8

Junction 7

Junction 19

Tatton ParkTatton ParkTatton ParkTatton Park

MereMereHallHall

MereHall

MereHall

Knutsford ServicesKnutsford ServicesKnutsford ServicesKnutsford Services

MereMere

Bucklow HillBucklow Hill

RostherneRostherne

BowdonBowdon

KnutsfordKnutsford

HooGreenHoo

Green

OverTableyOver

Tabley

BoothBankBoothBank

RostherneMere

The

Mer

e

Cicely Mill Lane

Rostherne Lane

Bucklow Hill Lane

Moss Lane

Millington LaneCherry Tree Lane

Millington Hall Lane

Chapel Lane

© C

row

n c

op

yrig

ht and

data

ba

se

rig

hts

2014

Ord

nance S

urv

ey 1

000306

49

© C

row

n c

op

yrig

ht and

data

base r

ights

2014 O

rdnance S

urv

ey 1

00030649

Bentley Hurst Lane

N140519N140519

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 3: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

The scheme

The A556 links north Cheshire and Greater

Manchester with the West Midlands. The scheme

will improve a 4.7 mile (7.6 Km) section connecting

M6 Junction 19 near Knutsford with the M56

Junction 7 near Bowdon, which passes through

Over Tabley, Mere and Bucklow Hill. This section

forms part of the strategic road network, but is the

only non-motorway link between Manchester and

Birmingham. Its improvement will bring significant

benefits to strategic traffic between the M6, south

Manchester and Manchester International Airport.

The A556 currently suffers from congestion,

unreliable journey times and a poor safety record.

The road has been identified as one of the most

congested roads in England. The existing road is

mainly single carriageway with two lanes in each

direction, however there are small stretches of

dual carriageway. It has numerous junctions,

private accesses and field entrances onto the

trunk road.

Key scheme objectives

Improve the local environment in Bucklow Hill

and Mere

Improve road safety and journey time

reliability

Reduce conflicts between long distance and

local traffic

Minimise the environmental impacts of the

scheme, during construction and once open

to traffic

The proposals

The scheme will improve the route to a consistent

standard of modern dual carriageway to achieve

these objectives. The main aspects of the design

include:

Construction of a new section of the A556

from M6 Junction 19 to north of Bucklow Hill,

to bypass Over Tabley, Mere and Bucklow

Hill (the ‘offline’ works)

Improvement of the existing A556 north of the

new bypass, to the M56 (the ‘online’ works)

Improvement of the layout of M56 Junction 7

at Bowdon

Creation of junctions allowing local traffic

access to the new A556

Narrowing of the bypassed section of the

A556 (the ‘de-trunking’ works) and changes

to side road connections

Measures to mitigate environmental impacts

of the scheme and improve the local

environment

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 4: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Spring Summer Autumn WinterAutumn Winter Spring Summer Autumn Winter Spring Summer Autumn Winter

Timeline

2014 2015 2016 2017

MobilisationMobilisationMobilisation

Enabling works and environmental mitigationEnabling works and environmental mitigationEnabling works and environmental mitigation

StructuresStructuresStructures

Utilities diversionsUtilities diversionsUtilities diversions

Earthworks season 1Earthworks season 1Earthworks season 1

Side road realignmentsSide road realignmentsSide road realignments

Earthworks season 2Earthworks season 2Earthworks season 2

Roadworks and pavementsRoadworks and pavementsRoadworks and pavements

Finishing worksFinishing worksFinishing works

DetrunkingworksDetrunkingworksDetrunkingworks

New A556 open to trafficNew A556 open to trafficNew A556 open to traffic

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 5: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Mainline works

New junction at M56 junction 7

General scheme features:

Junctions – the existing A556 has numerous

direct accesses and junctions which

contribute to accidents. The new road will

have junctions which are different levels and

roundabouts which will be safer.

Technology – variable driver information signs

will be provided to warn of incidents on the

new road and surrounding network.

As an interim measure there will be a speed

limit of 60mph on the new road to mitigate air

quality impacts. As soon as air quality

improves the speed limit will be increased to

70mph.

New vehicle checkpoint facility will be

provided for the DVSA (formerly VOSA) on

Bowdon roundabout to replace existing

facility near Cheshire Lounge.

Provision of a re-modelled M56 junction 7

providing free flow link between the M56 and

the A556

Some facts and figures:

18 miles of new drainage

1 million square cubic meters of earth

to move

laying 130,000 tonnes of tarmac

erecting 19 miles of fencing

up to 300 people employed on the

construction site.

The new dual carriageway will consist of 2 lanes in each direction separated by a concrete safety barrier in the central reservation.

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 6: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Construction methods

Construction methods will follow latest best

practice and will be designed to have as little

impact on the local residents, the environment and

local infrastructure as possible. This will include:

using silenced and low emission plant /

machinery

minimising transportation / HGV journeys

screening temporary working lights to

minimise light pollution to the surrounding

areas

road-cleaning

prohibiting fires and providing noise

screening where appropriate and feasible.

Working hours

general site hours will be 7.30am to 6.00pm

Monday to Friday and 8.00am to 1.00pm on

Saturday

out of hours working will be 1.00pm and

6.00pm on Saturday and 7.30am to 6.00pm

on Sunday

night time working will be between 9.00pm

and 5.00am

We anticipate some out of hours and night time

working during the project, but we will endeavour

to keep these to a minimum and will communicate

with the local community through:

the Highways Agency’s website

social media

key liaison group meetings

direct information to local councils /

councillors

letters to affected residents and businesses

regular public newsletter

Throughout the works, our primary objective will

be the health and safety of the public and our

workforce. Our aim is to deliver the scheme

efficiently, with the minimum of disruption whilst

achieving excellent health and safety standards.

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 7: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

TattonDale

M6

M56

M56

A56

A56

A50

A50

A50

A556

A5034

A5033

A556

A556

Junction 8

Junction 7

Junction 19

Tatton ParkTatton Park

MereHallMereHall

KnutsfordServices

KnutsfordServices

Mere

BucklowHill

Rostherne

Bowdon

Knutsford

HooGreen

OverTabley

BoothBank

RostherneMere

The Mere

Cicely Mill Lane

Rostherne Lane

Moss Lane

Millington Lane

Cherry Tree Lane

Millington Hall Lane

Chapel Lane

© Crown copyright and database rights 2014 Ordnance Survey 100030649

Diagrammatic

Bentley Hurst Lane

Old Hall LaneNon motorised user

underpass and retaining walls

Tabley junctionoverbridge

Millington Laneoverbridge

Chester Road bridge(Refurbishment workto existing structure)

Bucklow Manorretaining wall

A50 overbridge

Bentley HurstLane overbridge

Chapel Laneoverbridge

Green/Accomodationoverbridge

Yarwood Heath LaneBridge (Refurbishment

work to existingstructure)

M56 on-slipretaining wall

Yarwood Heath FarmAccess Bridge

(Refurbishment workto existing structure)

Bowdon RoundaboutLink overbridge

Structures

The scheme incorporates 7 new over bridges, 1 pedestrian underpass and refurbishment works to 2 existing bridges.

One of the bridges which is approximately 500m south of the A50 adjacent to Belt Wood is a “green

bridge”, which will provide a safe crossing point for wildlife and reconnect valuable ecological habitats

severed by the new road, and will also carry an agricultural accommodation track.

The ‘green bridge’ is the Agency’s first of this type of structure.

Plan of new structures to be built.

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 8: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Closures or restrictions will be well advertised in

advance on our website, social media and

through local media outlets where possible.

Diversion routes will also be published and local

access will be maintained.

Traffic management will be varied in scale, timing

and detail and includes:

provision of suitable access arrangements in

and out of the site;

overnight lane closures of the motorway and

local roads to undertake bridge works; and

overnight closure of the A556 to complete the

tie ins between the online and off line works.

Traffic management arrangements and provisions

will be planned to take into account local Tatton

Park and Cheshire Show events.

Air quality and dust management

Air quality around the construction site will be

monitored whilst work is ongoing to ensure the

project will not have a negative effect on the local

environment.

Noise impact

Noise levels will be monitored to ensure that the

effect on local people is minimised. Silenced

plant and equipment will be used to mitigate noise

levels and appropriate maintenance regimes will

be in place. Screening will be used where

possible.

Traffic management during construction

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 9: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

The project will be carried out in a manner which

will minimise the impact of construction on the

surrounding environment.

An environmental assessment covering a range of

topics, including noise, air quality, ecology,

cultural heritage, materials use and impacts on the

landscape has been undertaken. The assessment

identifies the key environmental issues. Following

this assessment a number of mitigation measures

have been incorporated into the design and

construction methods, to avoid adverse impacts

on the environment.

A number of native species will need to be

relocated to accommodate the scheme.

These include the provision of:

6 bat hop overs to prevent low flying bats

from being struck by vehicles

20 new ponds for great crested newts

approximately 50 hectares of new habitat

woodland

3 mammal tunnels to ensure safe passage for

animals under the road

construction of the first green bridge on a

project of this scale to provide connectivity

between habitats.

Reusing the excavated material in the construction

of the new road will reduce HGV movements on

local roads.

An extensive archaeology survey will be

undertaken prior to the works to record for

preservation, any features uncovered.

The new alignment of the A556 will take traffic

away from the communities of Bucklow Hill, Mere

and Over Tabley. This reduction in traffic will

provide an improvement in air quality for the

surrounding villages.

Environmental mitigation

Impression of the new ‘green bridge

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 10: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Works will be undertaken to de-trunk the existing A556. The de-trunked Chester Road will be reduced

to a single carriageway after the opening of the new route. The existing southbound carriageway will

become two lanes, one in each direction and the existing northbound lanes will be used to provide a

shared pathway for pedestrians, cyclists and equestrians.

The redundant outside lane will be replaced with a mounded grass bund. The existing A556 will be

renamed and re-classified to discourage its use by non-local traffic.

There are two existing traffic light junctions within the section of Chester Road to be de-trunked.

Works to these junctions are as follows:

Mere Crossroads – will be re-aligned and the A50 will become the main through route.

Bucklow Hill Junction – will be modified to accommodate the new flow of vehicular traffic utilising

the left turn at Bucklow Hill onto the A5034.

Detrunking

Footway/cycleway/bridleway Single carriageway roadBund

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 11: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

The team

Client/Employer

Contractor

Contractor’s Designer

Employer’s Agents

Employer’s Valuation andProperty Adviser

Local Highways Authority

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540

Page 12: Start of works exhibition November 2014 Welcome€¦ · Start of works exhibition – November 2014 Mainline works New junction at M56 junction 7 General scheme features: Junctions

Knutsford to BowdonImprovement

Start of works exhibition – November 2014

Contact us

Visit the scheme web page atwww.highways.gov.uk/roads/road-project/a556-knutsford-to-bowdon-improvement

Find us on Twitter: www.twitter.com/HA@HAnews_nwest

Call us on: 0161 930 5998

Write to us at:A556 Knutsford to Bowdon Project TeamMajor ProjectsHighways AgencyPiccadilly GateStore StreetManchesterM1 2WD

Email us: [email protected]

If you want to contact us or find out more about this project, you can:

An executive agency of the Department for Transport

HA Media Services Team, Manchester N140540