Standard Water and Sewer Specifications PDF

356

Transcript of Standard Water and Sewer Specifications PDF

Page 1: Standard Water and Sewer Specifications PDF
Page 2: Standard Water and Sewer Specifications PDF
Page 3: Standard Water and Sewer Specifications PDF
Page 4: Standard Water and Sewer Specifications PDF
Page 5: Standard Water and Sewer Specifications PDF

TABLE OF CONTENTS STANDARD WATER & SEWER SPECIFICATIONS 

CITY OF CLARKSVILLE 

TECHNICAL SPECIFICATIONS 

02010  General Miscellaneous Specifications 02110  Clearing and Grubbing 02200  Erosion Prevention and Sediment Control 02221  Trenching, Bedding and Backfilling 02410  Cleanup and Restoration 02485  Lawn and Grass Landscaping 02575  Pavement Repair 02713  Water Distribution Systems 02715  Fire Service Water Meters 02722  Sanitary Sewer Systems 02725  Boring and Jacking 02726  Tunneling 02727  Horizontal Directional Drilling 02821  Chain Link Fences and Gates 03300  Cast‐In‐Place Concrete 11200  Sewer Valves 11311  Submersible Sewage Pump Stations 11330  Hydraulic Sewage Grinders 11410  Wet Well Mounted, Suction Lift Sewage Pump Stations With Duplex Pumps11411  Wet Well Mounted, Suction Lift Sewage Pump Stations With Series Pumps11420  Low Pressure Grinder Pump Stations 13310  Sewage System Field Instrumentation 16010 General Electrical Provisions 16030 Overcurrent Protective Device Coordination and ARC Flash Study 16109 Raceways and Conduit Systems 16119 Conductors‐ Controls and Instrumentation 16120 Conductors‐ 600 Volt and Below 16127 Medium Voltage Cable Terminations 16134 Panelboards 16137 Cable Trays 16162 Variable Frequency Drives 16190 Supporting Devices and Hangers 16216 Emergency Standby Engine Generator System 16252 Underground Ducts and Utility Structures 16260 Uninterruptible Power System (UPS) 16320 Pad‐ Mounted Transformers 

Page 6: Standard Water and Sewer Specifications PDF

16343 Medium Voltage Metal Enclosed Switches             16346 Medium Voltage Metal Clad Switchgear             16420 Circuit Breaker Distribution Switchboard              16443 Low Voltage Motor Control Center               16450 Grounding                     16460 Dry Type Transformers                 16505 Heat Tracing Cable                    16532 Wooden Poles                     16601 Lighting Protection                     APPENDIX  A  –  Opening Direction of Sewer Valves, Water Valves and Fire Hydrants  APPENDIX  B  –  Notice of Intent (NOI) Form  APPENDIX  C  –  Construction Stormwater Inspection Certification Form  APPENDIX  D  –  Notice of Termination (NOT) Form  APPENDIX  E  –  CGW Water Customer Data Sheet  APPENDIX  F  –  Clarksville Gas & Water Lift Station Final Inspection Checklist   

Page 7: Standard Water and Sewer Specifications PDF

GENERAL MISCELLANEOUS SPECIFICATIONS  02010‐1 

SECTION 02010  

GENERAL MISCELLANEOUS SPECIFICATIONS  

TABLE OF CONTENTS  PART 1 – GENERAL  There  are  some miscellaneous  guidelines  that  exist  for  performing  work  in  the  City  of  Clarksville. These are general in nature and are itemized below:  1. Design  of  utility‐related  projects  shall  comply  with  the  provisions  of  the  Subdivision 

Regulations prepared by the Clarksville‐Montgomery County Regional Planning Commission.  2. Changes to bid documents are acceptable only if they are made with the prior agreement of 

the City Engineer’s Office or their designated representative prior to submission of a bid and issued as a change in an Addendum. 

 3. Any item not specifically listed on the Bid Form shall be considered to be included in the price 

of other related items on the Bid Form, or otherwise considered incidental to the scope of the Contract. 

 4. All  survey  elevations  shall  be  referenced  to mean  sea  level  (msl).    Elevation  references  to 

temporary benchmarks not referenced to mean sea level shall be rejected.   5. A permit must be completed prior to beginning any water and/or sewer construction.  Permits 

are located at the City Engineer’s Office.  There is no fee associated with the permit.    6. Pre‐construction photographs and/or video shall be taken on projects performed for the City 

of Clarksville, with particular attention to improved areas, to aid in restoring landscaping and other features to their initial condition.  

 7. Where utilities are installed in new fill, a compaction letter sealed by a Geotechnical Engineer 

registered in the State of Tennessee shall be submitted to the owner prior to accepting said utilities.  An acceptable compaction letter shall state that field density testing indicates the fill has been compacted to at  least 95% of the maximum dry density according to the Standard Proctor.    Special  protection  such  as  use  of  ductile  iron  pipe  with  joint  restraint  may  be required.    In  special  instances  and  cases  where  compaction  letters  may  not  have  been requested  for  fill  slopes  the  Engineer  retains  the  right  to  request  additional  testing  and/or remedies for insuring the integrity of the installed utilities and surrounding property.  

 8. Where water and sewer services cross street curbs, the curbs shall be stamped with the letter 

“W” or “S” as appropriate.   The end of each service stub shall be marked with a 6‐foot  long 4x4 wooden post or metal  fence post embedded 2  feet  into  the ground.    The post  shall be marked with blue paint for water services and green paint for sewer services.   

Page 8: Standard Water and Sewer Specifications PDF

GENERAL MISCELLANEOUS SPECIFICATIONS  02010‐2 

 9. Tracer  wire  shall  be  installed  as  specified  in  the  applicable  water  and  sewer  specification 

section.  10. Upon completion of the  installation of the sanitary sewer and water  line  improvements and 

prior to acceptance by the City of Clarksville, the Contractor shall submit one (1) hardcopy and one (1) electronic copy on CD in AutoCad .dwg format of the record drawings.  A. All drawings shall be referenced to Tennessee State Plane Coordinates (NAD27). 

 B. The record drawings shall also include detailed valve locations showing a minimum of 

three measurements to permanent features. Also, water lines shall be adjusted to the as‐built locations by snapping the lines correctly to the adjusted valve location for each valve or valve cluster.  

C. The as‐built submission should also be accompanied by a text  file, which will  include points  in  State  plane  format  and  point  type  (Ex.  788870.372,  1568830.499,  Fire Hydrant).   At a minimum,  the  text  file  should  include all  valves, hydrants, manholes, wet wells, benchmarks, water and sewer service markers.  Additionally, manhole and wet well data should include as‐built rim elevations and invert elevations.  Benchmark data should include elevation and description.  

D. The City of Clarksville will not execute the Final Plat of the development until such time that the as‐built drawings and text files are received.  

E. A Certificate  of  Occupancy will  not  be  issued  by  Clarksville  Building  and  Codes  until such time that the as‐built drawings and text files are received. 

 11. All  lift  station  property,  including  the  dedicated  access  road,  shall  have  a  recorded  deed 

submitted with final plat to the City Engineer’s Office prior to final acceptance by the City.  

12. Prior  to  bacteriological  testing  and  acceptance  of  newly  installed  water  mains,  Contractor shall complete, sign and submit a “Disinfection, Flushing, and Pressure Testing Worksheet” to the City’s Inspector.  A copy of this sheet is available in Section 02713 of these specifications. 

 13. All electrical wiring shall be copper conductor.  Aluminum is not an acceptable substitute.  All 

control  and  instrument panels  shall  be  supported by galvanized  steel posts  set  in  concrete.  Wooden posts are not acceptable. 

 14. Utility work necessary for after normal business hours may be required to be performed by all 

contractors  and  subcontractors  working  on  or  adding  to  the  City’s  various  systems  at  the direction of  the City Engineer or his designated  representative. Work of  this nature may be necessary  to  limit  impact  to  the  utility  customers  and will  not  be  considered  for  additional payment.   

 

Page 9: Standard Water and Sewer Specifications PDF

GENERAL MISCELLANEOUS SPECIFICATIONS  02010‐3 

15. The  contractor  shall  be  responsible  for  handing  sewage  flows  during  construction  by furnishing adequate bypass pumping for the duration of the project. No bypassing of sewage shall  be  permitted.    Unless  specified  elsewhere,  all  costs  associated  with  handling  sewage flows shall be borne by the contractor.   

 16. WARRANTIES 

 A. The developer and/or Contractor shall warrant all utilities and related appurtenances 

for a one (1) year period (minimum) following testing and acceptance by the City.  The Contractor  agrees  that  he  will  obtain  from  the  manufacturers  or  equipment  and materials  furnished  under  this  Contract,  guarantees  against  defective materials  and workmanship, and  if  those guarantees  furnished by  the manufacturer do not extend for the term of one (1) year from and after the date upon which the final estimate is formally approved by the City or other established date as set forth hereinbefore, he shall  make  the  necessary  arrangements  and  assume  all  cost  for  extending  this guarantee for the required period. 

 B. The Contractor shall promptly make such repairs or replacement as may be required 

under the above specified guarantee, and, when the repairs or replacements  involve one  or  more  items  of  installed  equipment,  shall  provide  the  services  of  qualified factory‐trained servicemen in the employ of the equipment manufacturers to perform or supervise the repairs or replacements. 

 C. When the Engineer or the City deems it necessary, and so orders, such replacements 

or repairs under this section shall be undertaken by the Contractor within twenty‐four (24)  hours  after  service  of  notice.    If  the  Contractor  unnecessarily  delays  or  fails  to make  the  ordered  replacements  or  repairs  within  the  time  specified,  or  if  any replacements or repairs are of such nature as not to admit of the delay incident to the service of  a notice,  then  the City  shall  have  the  right  to make  such  replacements or repairs, and the expense thereof shall be paid by the Contractor or deducted from any moneys  due  the  Contractor.    The  Performance  Bond  shall  remain  in  full  force  and effect throughout the Warranty Period. 

 17. Where  a  developer’s  preferred  choice  of  sewering  a  property  or  subdivision  is  by  pumping 

sewage  from  the  development  to  a  discharge  point  in  the  City’s  existing  sewer  system,  a gravity  sewer  solution(s)  shall  also  be  submitted  for  consideration  by  the  City  Engineer’s Office.    Each  sewer  alternative  shall  include  a  construction  cost  estimate  to  aid  in  the comparison of the alternatives. 

 18. The equipment items furnished shall comply wit all governing federal and state laws regarding 

safety,  including all current requirements of the Occupational Safety and Health Act (OSHA).  The  Contractor  shall  be  solely  responsible  for  job  safety  in  accordance  with  all  laws, regulations, methods, etc. of OSHA and the state. 

  

Page 10: Standard Water and Sewer Specifications PDF

GENERAL MISCELLANEOUS SPECIFICATIONS  02010‐4 

PART 2 – NOT USED   PART 3 – NOT USED  

END OF SECTION  

TABLE OF CONTENTS

Page 11: Standard Water and Sewer Specifications PDF

CLEARING AND GRUBBING  02110‐1 

SECTION 02110  

CLEARING AND GRUBBING  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Clearing, grubbing, removal and disposal of vegetation, rocks, roots and debris within the limits of the work except objects designated on the drawings to remain.   

 B. Preserve from injury or defacement all vegetation and objects to remain. 

 1.02  RELATED WORK  

A. Section 02200:  Erosion Prevention and Sediment Control   

B. Section 02221:  Trenching, Bedding and Backfilling  1.03  LIMITS OF WORK  

A. Rights‐of‐way or easement area established by Owner.  

B. Construction  area  including  the  area  bounded  by  lines  five  feet  outside  the construction lines established by Owner. 

 C. Approved borrow pit areas. 

 D. Designated stockpiles of construction material other than borrow material. 

 1.04  PROTECTION  

A. The Contractor shall observe the requirements stated  in Clarksville City Ordinance 1‐1710, which describes the precautions required to protect any City trees.  If the work entails removal of any trees on City owned property, the City Forester shall be notified in advance of removing the trees. City trees are described as any tree 6” diameter or greater that is located on City owned property or right‐of‐ways. The City Forester may permit removal of the tree(s), and in some instances may require replacement in kind with a tree(s) of equal size (i.e. one 6” diameter tree or three 2” diameter trees). The replacement  requirements  are  described  in  City  Ordinance  1‐1708.  These requirements  must  be  included  in  any  bid  submittal  and  are  considered  incidental unless specifically addressed in the Bid Form.  

Page 12: Standard Water and Sewer Specifications PDF

CLEARING AND GRUBBING  02110‐2 

B. Protect  living trees not marked for removal  inside and outside the construction area. To protect trees from injury, erect construction fences around trees allowing one foot of space from the trunk for each inch of trunk diameter.  Treat cut or scarred surfaces of trees or shrubs with a paint prepared especially for tree surgery. 

 C. Protect benchmarks and existing structures, roads, sidewalks, paving and curbs against 

damage from vehicular or foot traffic.  

D. Maintain  designated  temporary  roadways,  walkways  and  detours,  for  vehicular  and pedestrian traffic.  

E. Establish all erosion prevention and sediment control devices.   PART 2 ‐ NOT USED   PART 3 ‐ EXECUTION  3.01  PREPARATION  

Maintain benchmarks, monuments  and other  reference points.    Re‐establish  if  disturbed or destroyed at no cost to Owner. 

 3.02  CLEARING AND GRUBBING  

A. Clear rights‐of‐way, borrow pit and other stockpile areas of objectionable material to the ground surface except for trees and stumps.  

B. Cut  trees  and  stumps  to  within  six  inches  of  ground  surface  or  low  water  level  in swampy  areas where  embankments  are  to  be  constructed  provided  undercutting or other corrective measures are not stipulated.  

C. Cut trees and stumps outside the construction area marked for removal by the Owner to within six inches of the ground surface.  

D. Remove low hanging, unsound or unsightly branches on trees or shrubs designated to remain.  

E. Trim branches  of  trees  extending  over  the  roadbed  to  a  clear  height  of  twenty  feet above the roadbed surface.  

F. Grub construction area of protruding obstructions except  sound undisturbed stumps and roots six inches or less above the ground which will be a minimum of 5 feet below subgrade  or  embankment  slope  provided  undercutting,  topsoil  stripping  or  other 

Page 13: Standard Water and Sewer Specifications PDF

CLEARING AND GRUBBING  02110‐3 

corrective measures are not stipulated.  

G. Grub borrow pit and stockpile areas of all objectionable material.  

H. Perform  clearing  and  grubbing  well  in  advance  of  construction  or  material  removal activities. 

 3.03  DEBRIS REMOVAL  

A. No cleared or grubbed material shall be used in backfills or embankment fills.  

B. Promptly  remove  cleared  debris  from  site  unless  property  owner  gives  written permission for onsite disposal. 

 C. Obtain permission from applicable regulatory authority for disposal of debris to waste 

disposal site.  

END OF SECTION  

TABLE OF CONTENTS

Page 14: Standard Water and Sewer Specifications PDF
Page 15: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐1 

SECTION 02200  

EROSION PREVENTION AND SEDIMENT CONTROL  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. This  work  shall  consist  of  erosion  control  on  all  cut  and  fill  operations,  excavation, backfill, or other construction activities within the limits of the construction site, within any temporary or permanent easements, and within any borrow site used during the period  of  construction.    The  protection  of  these  sites  shall  continue  throughout  the construction period. 

 B. During flood seasons, protect the sites by sandbagging, the pumping of water, and any 

other means appropriate  to  restrain  flooding.   During dry weather,  sprinkle  the sites with  water  or  use  other  means  as  necessary  to  provide  dust  control.    In  case  of abnormally cold weather,  any construction  such as excavation work may be delayed until warmer weather or covered to prevent freezing. 

 C. Either permanent stabilization or temporary seeding and mulching shall occur as soon 

as practical after  final  grade  is achieved, but under no circumstances  shall disturbed ground be exposed for longer than 14 days.   

 D. The  Contractor  shall  continuously  maintain  temporary  erosion  prevention  and 

sediment  control  measures  until  permanent  stabilization  is  established.    The temporary pollution control provisions contained herein shall be coordinated with the permanent erosion control  features, to ensure economical, effective, and continuous erosion control throughout the construction and post‐construction period. 

 E. All erosion prevention and sediment control work shall be in compliance with the City 

of  Clarksville  Storm Water Management Manual  and  the  Tennessee  Department  of Environment and Conservation Erosion and Sediment Control Handbook.  All projects shall comply with the State of Tennessee’s Construction General Permit.  The “General Permit for Discharges of Storm Water Associated with Construction Activities” may be reviewed  in  its  entirety  at http://www.state.tn.us/environment/permits/conststrm.shtml. 

 1.02 RELATED WORK  

A. Section 02410:  Cleanup and Restoration  

B. Section 02485:  Lawn and Grass Landscaping 

Page 16: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐2 

 PART 2 ‐ PRODUCTS  2.01  TEMPORARY BERMS  

A. A temporary berm is constructed of compacted soil, with or without a shallow ditch, at the top of fill slopes or transverse to centerline on fills. 

 B. These berms are used temporarily at the top of newly constructed slopes to prevent 

excessive erosion until permanent controls are installed or slopes stabilized.  2.02  TEMPORARY SLOPE DRAINS  

A  temporary  slope  drain  is  a  facility  consisting  of  stone  gutters,  fiber mats,  plastic  sheets, concrete or asphalt gutters, half  round pipe, metal pipe, plastic pipe,  sod, or other material that may be used to carry water down slopes to reduce erosion. 

 2.03  SEDIMENT STRUCTURES  

Sediment  basins,  ponds,  dewatering  structures  and  traps  are  prepared  storage  areas constructed to trap and store sediment from erodible areas in order to protect properties and stream channels below the construction areas from excessive siltation. 

 2.04  CHECK DAMS  

Check dams are barriers composed of large stones, sand bags, or other non‐erodible materials placed across or partially crossing a natural or constructed drain way. 

 2.05  TEMPORARY SEEDING AND MULCHING  

Temporary  seeding  and mulching  are  measures  consisting  of  seeding,  mulching,  fertilizing, and matting utilized to reduce erosion.  All cut and fill slopes including waste sites and borrow pits  shall  be  seeded  when  and  where  necessary  to  eliminate  erosion.    Either  permanent stabilization  or  temporary  seeding  and mulching  shall  occur  as  soon  as  practical  after  final grade is achieved, but under no circumstances shall disturbed ground be exposed for  longer than 14 days.   

 2.06  BALED HAY OR STRAW CHECKS  

A. Baled hay or straw checks are temporary measures to control and prevent erosion.  B. If approved, baled hay or straw checks may be used where the existing ground slopes 

toward or away from the embankment and shall  follow the contour along the toe of slopes, in ditches, or other areas where siltation erosion or water runoff is a problem.  

Page 17: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐3 

C. Baled  hay  or  straw  checks  can  only  be  used  in  conjunction with  silt  fence  or  other approved methods as temporary control measures. 

 2.07  TEMPORARY SILT FENCES  

Silt fences are temporary measures utilizing woven wire or other approved material attached to  posts  with  filter  cloth  composed  of  burlap,  plastic  filter  fabric,  etc.,  attached  to  the upstream side of the fence to retain the suspended silt particles in the runoff water. 

  PART 3 ‐ EXECUTION  3.01  PLANNING AND PERMITTING  

A. Unless  otherwise  provided,  it  shall  be  the  basic  responsibility  of  the  Contractor  to develop  an  erosion  prevention  and  sediment  control  plan,  including  a  Storm Water Pollution  Prevention  Plan  (SWPPP),  acceptable  to  the  Engineer  and  the  State  of Tennessee.   

 B. The Contractor  shall  submit  a  spill  prevention  plan  to  the  Engineer  for  review.    The 

contents  of  this  spill  prevention  plan  shall  depend  on  what  types  of  chemicals, lubricants and fuels will be used and if these will be stored on site.  As a minimum, if fuel or lubricants or other chemicals are stored on site, either temporarily in vehicular tanks  or  in  skid  or  trailer mounted  tanks,  a  plan  shall  be  supplied  which  directs  all employees of  the  Contractor  in  the  proper  procedures  to  be  followed  should  a  spill occur.   Under no circumstances shall spent oil wastes be discharged on the site.  For more complex chemical storage requirements, a more complex plan will be required. 

 C. The Contractor shall be responsible for filing the Notice of Intent (NOI) with the State.  

A sample copy of the NOI is included in Appendix B.  The complete application must be submitted  at  least  30  days  prior  to  commencement  of  construction  activities.    Land disturbing activities shall not start until a Notice of Coverage is prepared and written approval by TDEC Division of Water Pollution Control is obtained. 

 D. The  Contractor  shall  be  responsible  for  twice‐weekly  field  inspection  and 

documentation,  and  inspection  after  any  storm  event  (0.5  inches  or  greater)  of  all erosion prevention and sediment control devices to insure that all devices are in fully operable  condition.    A  sample  copy  of  the  Construction  Stormwater  Inspection Certification form has been included in Appendix C.   Copies of completed forms shall be made available to the City Engineer’s Office upon request. 

 E. Upon completion of construction, the Contractor shall be responsible for filing Notice 

of  Termination  (NOT)  with  the  State.    A  sample  copy  of  the  NOT  is  included  in Appendix D. 

 

Page 18: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐4 

F. The  project  drawings  and  SWPPP  indicate  the  minimum  erosion  prevention  and sediment control measures required for this job.  If the Contractor desires to stockpile construction materials, stone, earth, etc., the location of it and protection thereof shall be outlined in an Erosion Prevention and Sediment Control Plan to be submitted to the Engineer for review. 

 G. The  Contractor  shall  ensure  that  all  erosion  prevention  and  sediment  control 

documents,  including  the SWPPP and any permits obtained,  shall be available at  the project site at all times. 

 3.02  PRE‐CONSTRUCTION CONFERENCE  

At the Pre‐Construction Conference, the Contractor shall meet with the Engineer and go over in detail the expected problem areas in regard to the erosion prevention and sediment control work.    The  Contractor  shall  submit  for  acceptance  his  schedule  for  accomplishment  of temporary  and  permanent  erosion  control  work.    He  shall  also  submit  for  acceptance  his proposed method of erosion control on haul roads and borrow pits and his plan for disposal of waste materials.  No work shall be started until the erosion control schedules and methods of operations have been accepted by the Engineer. 

 3.03  CONSTRUCTION REQUIREMENTS  

A. The  Engineer  has  the  authority  to  limit  the  surface  area  of  erodible  earth material exposed by clearing and grubbing,  the surface of erodible earth material exposed by excavation,  borrow  and  fill  operations,  and  to  direct  the  Contractor  to  provide immediate  permanent  or  temporary  pollution  control  measures  to  prevent contamination of adjacent streams or other watercourses, lakes, ponds, or other water impoundment.    Such work may  involve  the  construction of  temporary  berms,  dikes, dams, sediment basins, slope drains, and use of temporary mulches, mats seeding or other control devices or methods as necessary to control erosion.  Cut and fill shall be seeded  and  mulched  as  the  excavation  proceeds  to  the  extent  directed  by  the Engineer.  Under no conditions shall the erodible earth material exposed at one time by clearing and grubbing exceed 5,000 linear feet for utility  line work or one (1) acre without approval of the Engineer. 

 B. The Contractor shall be required to incorporate all permanent erosion control features 

into the project at  the earliest practicable time as outlined  in his accepted schedule.  Temporary pollution control measures not associated with permanent control features shall  be  used  to  correct  conditions  that  develop  during  construction  that  were  not foreseen  during  the  pre‐construction  stage,  prior  to  the  installation  of  permanent pollution control features, or as needed to temporarily control erosion during normal construction practices. 

 C. Where erosion is likely to be a problem, clearing and grubbing operations should be so 

scheduled  and  performed  that  grading  operations  and  permanent  erosion  control 

Page 19: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐5 

features can follow immediately thereafter if the project conditions permit; otherwise erosion control measures may be required between successive construction stages.   

 D. The Engineer will limit the area of excavation, borrow, and embankment operations in 

progress commensurate with  the Contractor’s capability and progress  in keeping  the finish  grading,  mulching,  seeding,  and  other  such  permanent  pollution  control measures  current  in  accordance  with  the  accepted  schedule.    Should  seasonal limitations make  such  coordination  unrealistic,  temporary  erosion  control  measures shall be taken immediately to the extent feasible and justified. 

 E. Either permanent stabilization or temporary seeding and mulching shall occur as soon 

as practical after  final  grade  is achieved, but under no circumstances  shall disturbed ground be exposed for longer than 14 days.   

 F. In the event of conflict between these requirements and pollution control laws, rules 

or  regulations,  or  other  Federal,  State  or  Local  agencies,  the  more  restrictive  laws, rules, or regulations shall apply. 

 3.04  CONSTRUCTION OF STRUCTURES  

A. Temporary Berms 1. A  temporary  berm  shall  be  constructed  on  compacted  soil,  with  a minimum 

width  of  24  inches  at  the  top  and  a  minimum  height  of  12  inches,  with  or without  a  shallow ditch,  constructed at  the  top of  fill  slopes or  transverse  to centerline on fills.   

2. Temporary  berms  shall  be  graded  so  as  to  drain  to  a  compacted  outlet  at  a slope  drain.    The  area  adjacent  to  the  temporary  berm  in  the  vicinity  of  the slope drain must be properly graded to enable this inlet to function efficiently and with only minimum ponding in this area.   

3. All  transverse  berms  required  on  the  downstream  side  of  a  slope  drain  shall extend across the grade to the highest point at approximately a ten (10) degree angle with a perpendicular to centerline.  The top width of these berms may be wider  and  the  side  slope  flatter  on  transverse  berms  to  allow  equipment  to pass over these berms with minimal disruptions.   

4. When  practical  and  until  final  roadway  elevations  are  approached, embankments  should be  constructed with  a  gradual  slope  to one  side of  the embankment to permit the placement of temporary berms and slope drains on only one side of the embankment. 

 B. Temporary Slope Drains 

1.  Temporary slope drains shall consist of stone gutters, fiber mats, plastic sheets, concrete or  asphalt  gutters,  half  round pipe, metal  pipe,  plastic  pipe,  flexible rubber, or other materials which can be used as temporary measures to carry water  accumulating  in  the  cuts  and  on  the  fills  down  the  slopes  prior  to 

Page 20: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐6 

installation of permanent facilities or growth of adequate ground cover on the slopes. 

2.  Fiber matting and plastic sheeting shall not be used on slopes steeper than 4:1 except for short distances of 20 feet or less. 

3.  All  temporary  slope  drains  shall  be  adequately  anchored  to  the  slope  to prevent disruption by the force of the water flowing in the drains.  The base for temporary  slope  drains  shall  be  compacted  and  formed  to  create  a  concave channel for the water or to hold the slope drain in place.  The inlet end shall be properly constructed to channel water into the temporary slope drain.  Energy dissipated will be accomplished at  the discharge point using  riprap or a small sediment basin which would slow the water as well as pick up some sediment.  All temporary slope drains shall be removed when no longer necessary and the site restored to match the surroundings. 

 C. Sediment Structures 

1. Sediment  structures  shall  be  utilized  to  control  sediment  at  the  foot  of embankments where slope drains outlet; at the bottom as well as in the ditch lines  atop  waste  sites;  and  in  the  ditch  lines  of  borrow  pits.    Sediment structures  may  be  used  in  most  drainage  situations  to  prevent  excessive siltation of pipe structures.  All sediment structures shall be at least four times as long as they are wide. 

2. Dewatering structures shall be used to remove sediment from water pumped during dewatering operations.  The dewatering structure must be sized to allow pumped  water  to  flow  through  the  filtering  device  without  overtopping  the structure.    Portable  sediment  tanks,  straw  bale/silt  fence  pits  and  sediment filter  bags  are  types  of  dewatering  structures  recommended  in  the  TDEC Erosion and Sediment Control Handbook. 

3. When use of temporary sediment structures is to be discontinued, all sediment accumulation  shall  be  removed,  and  all  excavation  backfilled  and  properly compacted.   The existing ground shall be restored to  its natural and  intended condition.   

 D. Check Dams 

1.  Check dams shall be utilized to reduce the velocity of storm water  in areas of concentrated  flow,  and  to  capture  larger  soil  particles.   Materials  utilized  to construct check dams are varied and should be clearly illustrated or explained in the Contractor’s erosion control plan. 

2.  All  check  dams  shall  be  keyed  into  the  sides  and  bottom  of  the  channel.    A geotextile shall be set into soil to separate soil and rock.  

3.  The center of check dams should be at least 9‐inches lower than either edge.  4.  Check  dam  structures  shall  be  designed  and  installed  to  prevent  flooding  of 

adjacent property, buildings and residences.  

Page 21: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐7 

E. Temporary  Seeding  and  Mulching:    Seeding  and  mulching  shall  be  performed  in accordance  with  the  Section  02485.    Seeding  and  mulching  shall  occur  as  soon  as practical after final grade is achieved, but no later than 14 working days. 

 F. Baled Hay or Straw Erosion Checks 

1. Hay or straw erosion checks shall be embedded in the ground four (4) to six (6) inches  to  prevent  water  flowing  under  them.    The  bales  shall  be  installed turned upon the side of the bale.  The bales shall also be anchored securely to the ground by wooden stakes driven through the bales into the ground.  Bales can remain in place until they rot, or be removed after they have served their purpose, as determined by the Engineer.  The Contractor shall keep the checks in  good  condition  by  replacing  broken  or  damaged  bales  immediately  after damage  occurs.    Normal  debris  cleanout  will  be  considered  routine maintenance. 

2. Baled hay or  straw  checks  can only  be used  in  conjunction with  silt  fence or other approved methods as temporary control measures. 

 G. Temporary Silt Fences 

1. Temporary silt fences shall be placed on the natural ground, at the bottom of fill  or  cut  slopes,  below  soil  stockpiles,  or  other  areas  where  siltation  is  a problem.    Silt  fences  are  constructed  of  wire mesh  fence with  a  covering  of burlap or  some other  suitable material  on  the upper  grade  side of  the  fence and anchored  into  the  soil.    Temporary  silt  fence serves  small drainage areas (maximum ¼ acre per 100 feet of silt fence length). 

2. The  Contractor  shall  be  required  to  maintain  the  silt  fence  in  a  satisfactory condition for the duration of the project or until its removal is requested by the Engineer.  The silt accumulation at the fence may be left in place and seeded or removed, as directed by the Engineer.   The silt  fence remains the property of the Contractor whenever the fence is removed. 

3. Silt fences should not be installed across streams, ditches, waterways, or other concentrated flows. All silt fences should be installed along the contour, never up or down a slope. The bottom 4 inches of the silt fence must be entrenched and backfilled to be effective.  

 3.05  MAINTENANCE AND REMOVAL  

The temporary erosion prevention and sediment control features installed by the Contractor shall  be  satisfactorily  maintained  by  the  Contractor  until  no  longer  needed  or  permanent erosion control methods are  installed.   The Contractor shall be responsible  for removing silt fences and check dams after the permanent cover is established.  Any materials removed shall become the property of the Contractor. 

 

Page 22: Standard Water and Sewer Specifications PDF

EROSION PREVENTION AND SEDIMENT CONTROL  02200‐8 

3.06  EROSION CONTROL OUTSIDE PROJECT AREA  

Temporary erosion prevention and sediment control shall  include construction work outside the project area where such work is necessary as a result of construction such as borrow pit operations, haul roads, and equipment storage sites. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 23: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐1 

SECTION 02221  

TRENCHING, BEDDING AND BACKFILLING  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Excavation of all materials encountered  in trench excavation,  including earth, rock or other materials, whether wet or dry.  

B. Provide necessary sheeting, shoring and bracing.  

C. Dewater excavation as required.  

D. Undercut unsuitable materials and replace as required.   

E. Prepare a stable, satisfactory trench bottom.  F. Place and compact granular beds, check dams, and backfill as appropriate. 

 G. Dispose of any unsuitable or excess materials. 

 1.02  RELATED WORK  

A. Section 02110:  Clearing and Grubbing  

B. Section 02200:  Erosion Prevention and Sediment Control  

C. Section 02410:  Cleanup and Restoration  

1.03  PRECAUTIONS  

A. In accordance with the Tennessee State Law (Tennessee Underground Utility Damage Prevention Act), the Contractor shall properly notify underground utility owners prior to  beginning  excavation  activities.    Tennessee  State  Law  requires  notification  to  the statewide one‐call center, Tennessee One‐Call, at least three (3) working days prior to excavation, but not more than ten (10) working days in advance of beginning the work.  Locate requests, including emergency locate requests, to Tennessee One‐Call shall be processed  in  accordance with  Tennessee  State  Law.    Contact  Tennessee One‐Call  at 811 or 1‐800‐351‐1111 to process a locate ticket.  The City of Clarksville will not locate its natural gas, water and sewer utilities without a locate ticket from Tennessee One‐Call. 

Page 24: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐2 

 B. Protect  all  structures,  utilities,  sidewalks,  pavements,  fences,  vegetation  and  other 

features to remain.  

C. Protect all benchmarks, property pins, survey points and similar items.  If disturbed or damaged by construction operations, the Contractor shall pay the cost of restoration by a registered surveyor. 

 D. Follow all Federal, State, County, TVA, TDOT, and Railroad regulations when working in 

Rights‐of‐Way not owned by City or in utility easement.  

E. Establish all erosion prevention and sediment control devices.  

F. Precautions  shall  be  taken  to  eliminate  tracking  of  soil,  mud,  rock  and  gavel  onto streets and roadways. 

 1.04  DUST CONTROL  

A. When ordered by Engineer or his representative, furnish and distribute over traveled road  surfaces  which  have  not  been  fully  restored  an  application  of  regular  flake calcium chloride having a minimum calcium chloride content of 77 percent, or a brine solution consisting of 1.5 pound of calcium chloride and one pound of sodium chloride per 100 gallons of water applied by a pressure distributor.  Rate of application shall be 3 pounds/square yard for the flake calcium chloride, and 0.48 gallon/square yard for brine solution. 

 B. Whenever dust control is necessary, it shall be considered an integral part of the work, 

and no separate payment shall be made for it.  1.05  MAINTENANCE OF TRAFFIC AND CLOSING OF STREETS  

A. Carry on the work in a manner which will cause a minimum of interruption to traffic, and do not  close  to  through  travel more  than  two  consecutive  blocks,  including  the cross street  intersected.   Where  traffic must cross open trenches, provide bridges at street  intersections  and  driveways.    Post  signs  indicating  that  a  street  is  closed  and necessary  detour  signs  for  the  proper  maintenance  of  traffic.    Before  closing  any streets  notify  responsible  municipal,  state,  county,  emergency,  transit  and  school system authorities. 

 B. Place  and  maintain  barricades,  fences,  construction  signs,  lights  and  flagmen  as 

required during the progress of the construction work and until it is safe for traffic to use  the  roads  and  streets.    The  rules  and  regulations  of  OSHA,  TDOT  and  other appropriate authorities respecting traffic safety provisions shall be observed. 

  

Page 25: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐3 

PART 2 ‐ PRODUCTS  2.01  BEDDING AND BACKFILL MATERIALS  

A. Class I Material: Angular, 1/4 to 1 inch graded stone.  B. Class II Material: Coarse sands and gravels with a maximum particle dimension of   1‐

1/2 inch including variously graded sands and gravels containing small percentages of fines, generally granular and non‐cohesive, either wet or dry. 

C. Class  III  Material:  Fine  sand  and  clayey  gravels,  including  fine  sands,  sand‐clay mixtures, and gravel‐clay mixtures. 

 D. Class  IV  Material:  Silt,  silty  clays,  and  clays,  including  inorganic  clays  and  silts  of 

medium to high plasticity and liquid limits.  E. In  rock  cuts,  paved  areas,  roadways  or  other  areas where  free  drainage  bedding  or 

backfill material is required, use Class I angular material.  F. Flowable Fill:  See requirements described in Section 02575, Part 2. 

  PART 3 ‐ EXECUTION  3.01  PREPARATION  

A. Pre‐construction photographs and video shall be taken by the Contractor, with special attention to  improved areas,  to aid  in restoring  landscaping and other  items to their initial condition.  

B. Where controlled blasting is required for rock removal, the Contractor shall perform a pre‐blast survey and have a blasting program prepared as specified in Paragraph 3.04 of this Section.  

C. Clear and grub as specified in Section 02110.  

D. Establish erosion prevention and sediment controls as specified in Section 02200.  

E. Protect all features to remain.  

F. Put in place all traffic and other safety provisions as required.  3.02  EXCAVATION  

A. Unless specifically shown otherwise on the Bid Form, all excavation is unclassified, and includes excavation to subgrade elevations regardless of the character of materials and 

Page 26: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐4 

obstructions encountered.  It is to be understood that any reference to rock, earth or any  other material  on  the  drawings  is  not  to  be  taken  as  an  indication  of  classified excavation or the quantity of either rock, earth or any other material involved. 

 B. The  Bidder  should  make  such  investigations  as  deemed  necessary  to  determine 

existing  conditions  and  shall  draw  his  own  conclusions  as  to  the  conditions  to  be encountered.  When rock borings, soundings or test pit data are provided, they are for information only and do not guarantee existing conditions. 

 C. Align the trench as shown on the Contract Drawings.   Deviations due to obstructions 

are discussed in Paragraph 3.08 of this Section.  

D. Perform excavation in such a manner as to form a suitable trench in which to place the pipe and so as to cause the least inconvenience to the public. 

 E. The Contractor shall be responsible for stripping, storing and protecting topsoil that is 

to be removed prior to excavation.  This topsoil is to be reused during the cleanup and restoration.  The Contractor is responsible for obtaining and providing other topsoil as may  be  necessary  to  restore  the  excavated  area  to  its  original  topsoil  quantity  and quality. 

 F. Pavement cuts shall be made along neat, straight lines with either a pavement breaker 

or pavement saw prior to the excavation.  Cut pavement to be a minimum of 6 inches outside of trench cut.  Coordinate all street cuts with the State, County and City Street Departments as applicable. 

 G. Trenches shall be excavated to the depths indicated on the Contract Drawings.  Trench 

depth shall be sufficient to provide a minimum cover of 36 inches over the top of the pipe  in non‐traffic areas and 48  inches  in areas subject to vehicular traffic.   Depth of cover  is measured  from  finished  grade  to  top  of  the  pipe.   Where  approved  by  the Owner,  additional  pipe  protection  such  as  use  of  ductile  iron  pipe  or  concrete encasement may be used where minimum cover is not possible.  Increased depth may be required as noted on the Contract Drawings to avoid obstructions, avoid requiring an air release valve and other reasons. 

 H. Excavated material shall be placed a minimum of two feet back from the edge of the 

trench.  

I. When unstable soil or other unsuitable material is encountered at the trench bottom, undercut  these materials  to a depth required to assure support of  the pipeline or as directed  by  the  Engineer  and  backfill  to  the  proper  grade  with  compacted  crushed stone.  The top 6 inches shall be Class I angular material.  Crushed stone for backfilling undercut  unsuitable  material  will  be  a  pay  item  under  crushed  stone  for  undercut replacement as set forth in Section 01026, Paragraph 3.04. 

 

Page 27: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐5 

J. Remove rock encountered in trench excavation to a minimum depth of 6 inches below the bottom of  the pipe barrel, backfill with Class  I  angular material,  and compact  to uniformly  support  the pipe.    In no case  shall  solid  rock exist within  six  inches of  the finished pipeline. 

 K. Maximum width at the crown of the pipe shall be 2 feet plus the nominal diameter of 

the  pipe,  unless  specifically  approved  otherwise  by  the  Engineer  due  to  unusual bracing and shoring requirements.  Trenches constructed by mechanical trenching are allowed  only  with  prior  approval  of  Engineer.    Over‐excavation  will  be  required  at locations for fittings and valves and construction of concrete thrust blocks. 

 L. Trenches 4 feet or more in depth should be provided with a means of egress.  Spacing 

between ladders or other means of egress must be such that a worker will not have to travel more than 25 feet laterally to the nearest means of egress. 

 M. Open  excavations  shall  be  barricaded  when  the  Contractor  is  not  at  the  site.    At  a 

minimum,  this  shall  consist  of  orange  polyethylene  barricade  safety  fence.    See Paragraph  1.05  of  this  section  for  additional  requirements  for  excavations  in  traffic areas. 

 3.03  SHEETING, SHORING AND BRACING  

A. Furnish,  put  in  place,  and  maintain  such  sheeting,  shoring  and  bracing,  as  may  be required to support the sides of the excavation and to prevent movement as required by OSHA.   Damages  resulting  from  improper  shoring or  failure  to  shore  shall  be  the sole responsibility of the Contractor. 

 B. Comply with all OSHA standards  in determining where and in what manner sheeting, 

shoring and bracing are to be accomplished.  The sheeting, shoring and bracing system shall  be designed by  a professional  engineer  licensed  in  the  State  of  Tennessee and shall be subject to approval by the Engineer.  However, such approval does not relieve the  Contractor  of  the  sole  responsibility  for  the  safety  of  all  employees,  the effectiveness  of  the  system,  and  any  damages  or  injuries  resulting  from  the  lack  or inadequacy of the sheeting, shoring and bracing. 

 C. The Contractor may use a trench box, which is a prefabricated movable trench shield 

composed  of  steel  plates  welded  to  a  heavy  steel  frame.    The  trench  box  shall  be designed to provide protection equal to or greater than that of an appropriate shoring system. 

 D. Do  not  leave  sheeting,  shoring  or  bracing materials  in  place  unless  called  for  in  the 

Contract Drawings, ordered by the Engineer, or deemed necessary or advisable for the safety or protection of new or existing work or  features.   Remove these materials  in such a manner that the new structure or any existing structure or property, whether public or private, will not be endangered or damaged and that cave‐ins and slides are 

Page 28: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐6 

avoided.  3.04  ROCK REMOVAL  

A. Controlled blasting may be used  as  an  alternative  to  non‐explosive methods of  rock removal  at  the  approval  of  the Owner.    Controlled blasting  shall  be performed by  a qualified explosive specialist, employed by the Contractor.  The contractor shall have a Registration Certificate and each employee engaged in the blasting activity shall carry a valid identification card issued by the Division of Fire Prevention. 

 B. All blasting  shall be performed  in accordance with  the Tennessee Blasting Standards 

Act of 1975.  Conduct all blasting operations in accordance with prevailing municipal, state or other agency regulations, codes, ordinances, or laws. 

 C. The  Contractor  assumes  all  liability  for  all  personal  injury,  any  damage  to  real  or 

personal  property,  or  interference  with  the  use  or  enjoyment  of  any  property  by reason of  blasting or  the  resulting  vibration or  concussion.    The Contractor  assumes full responsibility for operating all equipment and performing all blasting in accordance with  Federal  and  State  laws,  and  regulations  prescribed by  any  other Governmental authority limiting the amount of vibration or concussion. 

 D. The Contractor  shall  prepare or  retain  a  consultant  to prepare  the blasting program 

and  to  supervise  and  assist  in  monitoring  the  blasting.    The  blasting  program  shall include,  but  not  be  limited  to,  data  on  the  locations,  hole  size,  depth,  over‐depth, pattern and inclination of the blast holes, the type, strength, amount, distribution and powder  factor  for  the  explosives  used,  per  hole  and  per  blast,  the  sequence  and pattern of delays, maximum amount of explosives  in  any one period, depth of  rock, and depth of overburden, if any, and the description and purpose of special methods to be used.  This data shall be submitted to the Engineer upon request. 

 E. The Contractor or his  consultant  shall  conduct a pre‐blast  survey of  the  surrounding 

structures  within  300  feet  of  any  blasting  operation  and  document  their  condition prior to any blasting.  Documentation shall include written descriptions, videos and/or photographs  of  the  structures,  and measures  of  obvious  signs  of  structural  distress such as cracks.  Gauge marks shall be located over existing cracks at selected locations to be measured before and after blasting to determine if widening or displacement has taken place. 

 F. All  blasts  shall  be  designed  to  prevent  fly  rock.    The  Contractor  shall  use  adequate, 

good  quality  stemming  material  and  cover  the  blasts  with  blasting  mats  or  an adequate soil cover. 

 G. If structures or pipelines are damaged, promptly replace or repair them at no expense 

to Owner.  

Page 29: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐7 

H. Seismographic  monitoring  shall  be  done  by  the  Contractor  or  his  consultant  and  a record made of the peak particle velocities caused by the blasting.  This data shall be included in the blasting report. 

 I. Air  blast  shall  be  monitored  with  an  approved  instrument  having  the  required 

frequency  response  and  capable  of  providing  a  permanent  record  of  the  air  blast effects.   These records,  identified by time and recording  location shall be  included in the blasting report. 

 J. The  Contractor  shall  maintain  a  daily  log  on  ready  inspection  by  the  Engineer.    A 

completed blasting report shall be submitted to the Engineer at the conclusion of all blasting. 

 3.05  DISPOSAL OF MATERIALS  

A. Whenever  practicable,  all  materials  removed  by  excavation  that  are  suitable  for backfilling pipe trenches or for other purposes shown on the drawings or directed by the Engineer shall be used for those purposes. 

 B. Any materials not so used shall be considered waste materials and disposed of by the 

Contractor.  Waste materials may be deposited in spoil areas at locations approved of by the Engineer, or shall be properly disposed of off‐site if there is no approved spoil area. 

 3.06  UNAUTHORIZED EXCAVATION  

A. Unauthorized  excavation  is  defined  as  all  excavation outside or  below  the proposed lines  and  grades  shown  on  the  Contract  Drawings  or  that  which  is  directed  by  the Engineer. 

 B. Backfill areas of unauthorized excavation with the type of material necessary to ensure 

the stability of the structure or construction involved.  

C. Unauthorized excavation and/or backfill to replace same shall not be a pay item.  3.07  DEWATERING  

A. The  Contractor  shall  furnish,  install  and  operate  all  necessary  equipment  to  keep excavated areas free of water while work is in progress.  Dewatering equipment shall be of adequate size and quantity to assure maintaining proper conditions for installing pipe, concrete, bedding, backfill or other material or structure in the excavation. 

 B. Well‐pointing shall be performed if required. 

 C. Take particular precautions to prevent the displacement of structures or pipelines as a 

Page 30: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐8 

result of accumulated water.   Any pipe displaced due to accumulated water shall be replaced by the Contractor at his expense. 

 D. Dewatering  operations  shall  be  performed  in  a manner  so  as  not  to  cause  injury  to 

public  or  private  property  or  nuisance  to  the  public  nor  contribute  to  pollution  to surface water.  The Contractor’s dewatering operations shall be in full compliance with Section 02200 of these Specifications. 

 3.08  OBSTRUCTIONS  

A. Obstructions  shown  on  the  Contract  Drawings  are  for  information  only  and  do  not guarantee  their  exact  locations  nor  that  other  obstructions  are  not  present.  The crossing of existing mains and services, which are approximately perpendicular to the proposed ditch line,  is considered normal construction practice.   The Contractor shall have the responsibility of making these crossings and repairing any damages to such crossings without additional reimbursement. 

 B. Whenever  unknown  obstructions  are  encountered  during  the  progress  of  the  work 

that  directly  interfere  with  the  vertical  or  horizontal  alignment  of  the  pipeline,  the Engineer shall have the authority to order a deviation from the grade or alignment or for  the  removal,  relocation  or  reconstruction  of  the  obstructing  utility  or  structure.  Likewise,  the  Contractor  may  request  to  relocate  the  proposed  line  or  request reimbursement for relocating the existing  line or performing unusual shoring beyond what is normally required for trench stabilization.  

 C. When utilities or obstructions are not shown on the Contract Drawings but are present 

off  the  roadway  at  the  location of  the proposed pipeline  route,  the Contractor may request  to  relocate  the  pipeline  in  the  roadway  if  necessary  to  avoid  disturbing  the utility or obstructions.  If the relocation is approved by the Engineer into a paved area, the  Contractor  shall  receive  compensation  for  additional  granular  backfill  and pavement  replacement  as  measured  and  paid  for  as  set  forth  in  Section  01026, Paragraph 3.07.  

 D. Exercise  due  care  in  excavating  adjacent  to  existing  obstructions  and  do  not  disturb 

same unless absolutely necessary.   E. In the event existing utilities are disturbed, repair or replace as quickly as possible to 

the condition existing prior to their disturbance at no cost to the Owner.  If required by the Owner,  pay  for  the  repair  or  replacement work  performed  by  the  forces  of  the utility company or other appropriate party.  

 F. If replacement or repair of disturbed obstructions is not performed after a reasonable 

period of time, the Owner may have the necessary work done and deduct the cost of same from payments to the Contractor. 

 

Page 31: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐9 

3.09  BEDDING OF GRAVITY SEWER MAINS  

A. Always maintain proper grade and alignment during the bedding and tamping process.  Any pipe damaged or displaced during this process shall be replaced by the Contractor at his expense. 

 B. Provide a minimum of 6 inches of compacted Class I angular material for bedding of all 

gravity  sanitary  sewer  pipe  regardless  of  pipe  material.    Dig  bell  holes  so  that  the barrel of  the pipe will  rest  for  its entire  length upon the prepared bedding to assure uniform support of the pipe. 

 C. Completely encapsulate each PVC sewer pipe section with a minimum of 6  inches of 

Class I angular material on the top, both sides and the bottom of the pipe.  

D. Where  gravity  sewer  pipe,  regardless  of  pipe  material,  is  laid  within  a  rock  cut, completely  encapsulate  each  pipe  section  with  a  minimum  of  6  inches  of  Class  I angular material on the top, both sides and the bottom of the pipe. 

 3.10  BEDDING OF WATER MAINS AND SEWER FORCE MAINS  

A. Water mains and sewer force mains may be laid on a stable earth bed in a trench cut in natural ground.  Excavate the trench in such a manner as to form a suitable bed on which  to  place  the  pipe.    Where  unstable  soil  or  other  unsuitable  material  is encountered at the trench bottom, undercut and replace these materials as discussed in Paragraph 3.02 of this Section. 

 B. Where  water  lines  and  sewer  force  mains  are  laid  within  a  rock  cut,  completely 

encapsulate each pipe section with a minimum of 6 inches of Class I angular material on the top, both sides and the bottom of the pipe. 

 C. Dig  bell  holes  so  that  the  barrel  of  the  pipe will  rest  for  its  entire  length  upon  the 

natural earth trench bed or prepared bedding to assure uniform support of the pipe.  3.11  INITIAL BACKFILLING  

A. Do  not  begin  backfilling  before  the  Engineer  or  his  representative  has  inspected  or approved the grade and alignment of the pipe, the bedding of the pipe, and the joints between the pipes.  If backfill material is placed over the pipe before an inspection is made,  the  Engineer  or  his  representative may  require  the  Contractor  to  reopen  the trench in order for an inspection to be made at no cost to the Owner. 

 B. Perform initial backfilling by hand or by carefully dumping small quantities of fill from a 

loader bucket, until fill has progressed to 6 inches above the top of the pipe.  

Page 32: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐10 

3.12  FINAL BACKFILLING   

A. Final backfilling shall be performed as soon as practicable after  inspection and  initial backfilling  is  complete.    Adequate  precautions  shall  be  taken  to  insure  proper placement and compaction of backfill without disturbing or damaging pipe.   Fill shall be properly  compacted and  suitable precautions  shall be  taken  to  insure permanent stability  for  pipe.    Utilities  shall  be  provided  with  adequate  cover  or  additional protection as described in Paragraph 3.02 of this Section. 

 B. Backfilling in unimproved areas: 

1. Dispose  of  all  soft,  yielding  or  organic  material  that  is  unsuitable  for  trench backfill  and  replace  with  suitable  material.    The  maximum  dimension  of individual  stones  and  broken  rock  within  the  backfill  should  not  exceed  6 inches. 

2. Deposit, spread and compact backfill  in even layers no greater than 12 inches deep  to  the  surface  with  suitable  equipment  in  such  a manner  so  as  not  to disturb the pipe.  If earth material for backfill is, in the opinion of the Engineer or  his  representative,  too  dry  to  allow  thorough  compaction,  the  Contractor shall add enough water so that the backfill can be properly compacted. 

3. Neatly  round  sufficient  surplus  excavated  material  over  the  trench  to compensate for settlement of the backfill. 

4. The top 12 inches of backfill material shall consist of fine loose earth free from large  clods,  vegetable  matter,  debris,  stone  and/or  other  objectionable materials. 

5. Properly dispose of all excess excavated material. 6. Prior  to  final  acceptance,  finish  grade,  restore  topsoil  and  reestablish 

landscaping as specified in Sections 02410 and 02485.  

C. Backfilling beneath flexible and rigid pavements: 1. Use Class  I  angular material  of  either  crushed  limestone or  crushed gravel  of 

high weight and density. 2. Carefully deposit in uniform layers, not to exceed 6 inches thick. 3. Compact  each  layer  thoroughly  by  rolling,  ramming  and  tamping  with  tools 

suitable for that purpose in such a manner so as not to disturb the pipe. 4. Flowable  fill  may  be  used  at  the  Contractor’s  request  with  approval  of  the 

Engineer,  when  specified  on  a  particular  project,  or  when  required  by  the Clarksville Street Department.  Payment for flowable backfill will be included as a separate pay item. 

 D. Backfilling of shoulders along streets and highways: 

1. Backfilling  methods  and  materials  for  shoulders  along  streets  and  highways shall be in accordance with the requirements of governing State, County or City departments maintaining the particular roadway or highway. 

2. Replace with similar materials, all shoulders that may be damaged or destroyed as a result of pipe trenching. 

Page 33: Standard Water and Sewer Specifications PDF

TRENCHING, BEDDING AND BACKFILLING  02221‐11 

3. Backfilling of shoulders shall not be directly measured for payment. 4. Where  shoulders  along  state  highways  have  seal  coat  surfaces,  replace  with 

double bituminous seal in accordance with TDOT requirements. 5. Where TDOT or local authority requires trenches to be backfilled entirely with 

granular material in the shoulder of roads, granular material so placed shall not be a pay item, but included in the prices per linear foot of pipe unless provided for specifically on the Bid Form. 

6. Backfill in state highways may also be performed utilizing flowable fill.  Refer to Section 02575, Paragraph 3.08 for installation requirements. 

 E. Crushed stone for pavement and shoulder replacement: 

1. Where  possible,  salvage  and  reuse  all  base  material  that  is  removed  during construction. 

2. Wet and thoroughly compact crushed stone and blade to tie  into the existing surface prior to final acceptance. 

3. Base  material  placed  as  a  portion  of  pavement  replacing  items  will  not  be measured for payment. 

 3.13  CHECK DAMS  

A. Check dams  shall  be  installed  in  the bedding  and backfill  of  new or  replaced gravity sewer  lines  to  limit  the  drainage  area  subject  to  the  French  drain  effect  of  gravel bedding.  Major rehabilitation projects should also include check dams in the design.  

B. Check dams shall consist of compacted clay bedding and backfill at least three (3) feet thick  to  the  top  of  the  trench  and  cut  into  the  walls  of  the  trench  two  (2)  feet.  Alternatively, concrete may be used, keyed into the trench walls.  

 C. Check dam material within one foot of the sewer main shall be carefully hand placed 

and compacted.  No gravel backfill or bedding shall be used in the check dam area.  

D. Check dams shall be installed upstream of each manhole.   

E. All stream crossings shall include concrete check dams on both sides of the crossing.  

END OF SECTION  

TABLE OF CONTENTS

Page 34: Standard Water and Sewer Specifications PDF
Page 35: Standard Water and Sewer Specifications PDF

CLEANUP AND RESTORATION  02410‐1 

SECTION 02410  

CLEANUP AND RESTORATION  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Work  included  in  this  section  consists  of  finish  grading,  site  cleanup,  patching  of pavement, repairing and/or reinstalling all public and private improvements disturbed by the construction. 

 B. Cleanup shall follow in close succession to other construction activities and shall be a 

daily  function.    Allowances  will  be  made  for  time  of  settling  of  backfilled  trenches before final grading and landscaping is attempted; however, drainage ditches are not to be  left obstructed.   The concept of  leaving cleanup until  the other construction  is completed is not acceptable.  

C. The City reserves the right to withhold payments (in part or  in whole)  if cleanup and restoration does not meet with the approval of the City. 

 1.02  RELATED WORK  

A. Section 02200:  Erosion Prevention and Sediment Control  

B. Section 02575:  Pavement Repair  

C. Section 02485:  Lawn and Grass Landscaping   PART 2 ‐ PRODUCTS  All  materials  and  products  used  for  repair  and/or  replacement  of  disturbed  areas  shall  meet  or exceed the type and quality of the original.   PART 3 ‐ EXECUTION  3.01  PRE‐CONSTRUCTION PHOTOGRAPHS  

The Contractor shall use the photographs and/or video taken prior  to construction to aid  in cleanup  and  restoring  landscaping  and  other  features,  public  or  private,  to  their  original condition or better. 

Page 36: Standard Water and Sewer Specifications PDF

CLEANUP AND RESTORATION  02410‐2 

 3.02  FINISH GRADING AND TOPSOIL RESTORATION  

A. After  allowing  backfill  adequate  time  to  settle,  finish  grade  all  areas  to  produce  a uniform,  satisfactory  finish  with  rounded  surfaces  at  the  top  and  bottom  of  abrupt changes in grade. 

 B. Refill areas where noticeable settlement has occurred. 

 C. Finish grading  shall be performed such  that  the area will drain  satisfactorily and will 

not hold or collect standing water.  

D. Restore topsoil as specified in Section 02485, Paragraph 3.02.  

E. Dress  for  final  inspection  such  that  the  surface  is  free  of  large  clods,  debris,  stone and/or other objectionable material. 

 F. Restore  lawn  and  grass  landscaping  in  accordance  with  Section  02485.    Final 

stabilization by lawn and grass landscaping shall occur within 14 days of completion of finish grading to begin establishment of ground cover to prevent erosion. 

 3.03  PAVEMENT MAINTENANCE AND REPLACEMENT  

A. All  excavation  in  traffic  areas,  whether  bituminous,  concrete,  or  gravel,  shall  be backfilled with compacted crushed stone.  The stone shall be brought to the grade of the surrounding pavement to provide a temporary surface for traffic.  The Contractor is responsible for grading and maintaining the gravel surface until the final pavement is in place. 

 B. Throughout the duration of the project, pavements shall be kept  free of mud, gravel 

and other construction debris to avoid unnecessary tracking of mud and spreading of dust.  If conditions warrant, the Contractor shall be responsible for arranging for street washing  to  remove  unnecessary  amounts  of  mud  from  the  pavement  and  also  to control dust.  This will not be a pay item but will be a responsibility of the Contractor when conditions warrant. 

 C. Damaged pavement, whether concrete or asphalt, shall be properly replaced with the 

corresponding  same  equal material.    In  some  cases  the  City  Street  Department will assume  the  responsibility  for  the  final  paving  after  the  Contractor  has  properly  cut, trimmed  and  backfilled  the  utility  trench.    The  Contractor  shall  assume  the  total responsibility  for  repaving  unless  stated  specifically  otherwise  in  the  Contract Documents.  Pavement repair shall be in accordance with Section 02575. 

   

Page 37: Standard Water and Sewer Specifications PDF

CLEANUP AND RESTORATION  02410‐3 

3.04  CURBS, SIDEWALKS, STEPS, ETC.  

A. All curbs, sidewalks, steps, etc. which are damaged or disturbed shall be replaced by squarely cutting or removing at the nearest sound joint or section and re‐pouring the new structure to match or exceed the quality and appearance of the original. 

 B. All repairs shall be compliant with the City Street Department and the Americans with 

Disabilities  Act  (ADA).    Any  new  curbs,  sidewalks,  steps,  etc  shall  be  designed  and installed to meet requirements of the ADA. 

 3.05  FENCES  

All fences and posts, which are damaged or removed, shall be re‐erected. Posts shall be firmly set and tamped.  Wire fences shall be tightly stretched.  New materials shall be used when it is obvious  that  the  existing  material  cannot  be  reinstalled  to  its  condition  prior  to  being disturbed. 

 3.06  SHRUBS, FLOWERS AND ORNAMENTALS  

Where noted on the plans or as directed by the City, all attempts shall be made to protect, preserve and reset shrubs, flowers and ornamentals disturbed by the construction. 

 3.07  MAILBOXES, ETC.  

A. Mailboxes  that  are  disturbed  by  the  construction  shall  be  reinstalled  or  relocated immediately  in a serviceable condition and  location.   After backfilling and re‐grading, the mailbox shall be permanently and properly erected. 

 B. All  other  public  or  private  improvements  disturbed  by  the  construction  shall  be 

repaired or replaced to original condition unless specifically exempted in the Contract Documents. 

 3.08  EROSION AND SEDIMENT CONTROL  

A. The Contractor shall maintain all areas where excavating and backfilling operations are being performed or have been performed in order that siltation and bank erosion will be kept to a minimum during construction.  This requirement includes construction of temporary erosion barriers and use of special methods to control erosion. 

 B. The Contractor shall be responsible for removing all temporary erosion protection and 

sediment  control devices,  including  silt  fences and check dams, after  the permanent cover is established. 

END OF SECTION  

TABLE OF CONTENTS

Page 38: Standard Water and Sewer Specifications PDF
Page 39: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐1 

SECTION 02485  

LAWN AND GRASS LANDSCAPING  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All activities necessary to restore areas disturbed by construction, or other designated areas, to their original landscaped condition and quality. 

 B. Preparation of landscape area including loosening, pulverizing and fertilizing. 

 C. Placement of seed, sprigging, sod and topsoil including mulch, where required. 

 D. Watering of landscaping. 

 1.02  RELATED WORK  

A. Section 02110:  Clearing and Grubbing  

B. Section 02200:  Erosion Prevention and Sediment Control  

C. Section 02410:  Cleanup and Restoration   PART 2 ‐ PRODUCTS  2.01  SEED MATERIALS  

A. Inspect and test seed for germination and purity prior to mixing.  

B. Uniformly mix by Group:  

Seed Name            Quantity % by Weight  

GROUP “A” Lespedeza (common or Korean)      20% Sericea Lespedeza          15% Kentucky 31 Fescue          40% English Rye            25%   

Page 40: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐2 

Seed Name            Quantity % by Weight  

GROUP “B” Kentucky 31 Fescue          55% Redtop             15% English Rye            30% 

 GROUP “C” Sericea Lespedeza          50% Kentucky 31 Fescue          30% English Rye            20% 

 C. Use Group “A” seed from February 1 to August 1. 

 D. Use  Group  “B”  seed  from  August  1  to  December  1,  with  the  exception  that  either 

Group “A” or “B” may be used during the month of August.  

E. Use Group “C” seed from December 1 to February 1, but only when specified on the Contract Drawings or otherwise approved. 

 F. All seed shall meet the requirements of the Tennessee Department of Agriculture. 

 G. Upon request, furnish the Engineer a certified laboratory report showing the analysis 

of  the  seed  to  be  furnished.  The  report  shall  bear  the  signature  of  a  senior  seed technologist. 

 H. Inoculant for Legumes: 

1. Nitrogen fixing bacteria cultures adapted to the particular seed to be treated. 2. Furnish in containers of a size sufficient to treat the specified quantity of seed 

to be planted.  2.02  MULCH MATERIALS  

A. Hay composed of approved stalks from grasses, sedges or legumes; or straw composed of stalks from rye, oats, wheat, or other approved grains. 

 B. Air dried and reasonably free from noxious weeds, weed seeds, and other detrimental 

plant growth.  

C. Suitable for spreading with mulch blower machinery.  

D. Wood fiber mulch, when used, shall meet the following specifications: 

Moisture Content  10.0 % ± 2.0% Organic Matter  99.4 % ± 0.2% Ash Content      0.6 % ± 0.2% 

Page 41: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐3 

Water Hold Capacity (per hundred ... 1050 grams minimum grams of oven dry fiber)  

E. Mulch Binders: 1. Cut back asphalt, Grade RC‐70 or RC‐250 conforming  to AASHTO M‐8l, M‐82, 

M‐l4l, for the type and grade specified. 2. Emulsified asphalt, Type SS‐l conforming to AASHTO M‐140. In addition to Type 

SS‐1, a special mixing material AE‐3 or a special priming material AE‐P may be specified. 

 2.03  JUTE MESH  

A. Open plain weave of  single  jute  yarn or photodegradable  straw‐filled mesh blankets and non‐toxic to vegetation. 

 B. Tag jute rolls for identification with 58 warp ends per yard, 4l weft ends per yard and 

weighing approximately 0.9 pounds per square yard with an acceptable tolerance of 5 percent. 

 2.04  STAPLES  

New and unused, machine‐made of No. 11 gauge steel wire formed into a "U” shape.  2.05  SOD MATERIALS  

A. Live,  dense,  well‐rooted  growth  of  permanent  grasses,  free  from  Johnson  grass, nutgrass,  and  other  undesirable  grasses  or  weeds  and well‐suited  for  the  proposed application to particular soils.  

B. Cleanly cut in strips having a reasonably uniform thickness of not less than 2‐l/2 inches, a uniform width of approximately 8 inches, and a minimum length of 12 inches. 

 2.06  COMMERCIAL FERTILIZERS  

A. Unless otherwise  specified,  inorganic  10‐10‐l0  nitrogen,  phosphoric  acid,  and potash for seeding and 15‐15‐15 or 10‐10‐l0 for sodding.  

B. Furnish  in standard containers with the brand name, weight and guaranteed analysis of the contents clearly marked.  

C. Comply with Federal, State, and local laws.  

D. Ammonium Nitrate shall be a standard commercial product, having a minimum of 33.5 percent nitrogen.  

Page 42: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐4 

E. Agricultural  limestone  shall  contain  a  minimum  of  85%  of  calcium  carbonate  and magnesium carbonate combined, and be of particular size that 85% will pass a No. 10 mesh sieve. 

 2.07  WATER  

Ensure that water is free of harmful organisms or other objectionable materials.  2.08  TOPSOIL  

A. Natural,  friable,  fertile,  fine  sandy  loam  possessing  characteristics  of  representative top soils in the vicinity, which produce heavy growths of vegetation. 

 B. Free  from  subsoil,  noxious  weeds,  stones  larger  than  one  inch  in  diameter,  lime, 

cement, ashes, slag, or other deleterious matter.  

C. Well drained  in  its original position and  free  from toxic quantities of acid or alkaline elements. 

  PART 3 ‐ EXECUTION  3.01 GENERAL   

A. All  unpaved  or  non‐graveled  areas  disturbed  by  the  construction  of  project  or  any other areas as specified shall have a stand of grass developed by one of the following methods:  Seeding will generally be acceptable; however, if repeated seeding fails due to continued erosion or other unsatisfactory conditions, sprigging or sodding shall be used.    If  the  imported  topsoil  or  seeds  result  in  Johnson  grass  or  other  undesirable weeds,  the Contractor  shall eliminate  this growth with herbicides and  reestablish an acceptable growth. 

 B. Before beginning seeding, sprigging or sodding operations in any area, complete finish 

grading  and  restoration  of  topsoil  and  have  work  approved  by  the  Engineer  or  his representative. 

 3.02  TOPSOIL  

A. The Contractor shall save and stockpile the topsoil removed from the excavation area or otherwise obtain topsoil to restore the area and reestablish an acceptable stand of grass. 

 B. Prepare  landscape area to receive topsoil  in close conformity to the  lines and grades 

shown on the drawings.   

Page 43: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐5 

C. Place topsoil at depths and locations shown on the drawings.  Otherwise, topsoil shall be restored to its original quantity and quality, but no less than necessary to establish and promote an acceptable stand of grass. 

 3.03  SEEDING  

A. Scarify, disc, harrow, rake or otherwise work each area to be seeded until it has been loosened and pulverized to a depth as directed by the Engineer. 

 B. Uniformly  incorporate  fertilizer  into  the  soil  to  a  depth  of  approximately  l/2"  at  the 

rate of: 1. Not less than 40 lbs. per 1000 square feet for grade 10‐l0‐10 or equivalent. 2. Not less than 100 lbs. per 1000 square feet for agricultural limestone. 

 C. Fertilizer  need  not  be  incorporated  in  the  soil  as  specified  above  when mixed  with 

seed in water and applied with power sprayer equipment.  

D. Sow  seed  of  the  specified  group  as  soon  as  preparation  of  the  seedbed  has  been completed.  

 E. Sow uniformly by means of a rotary seeder, hydraulic equipment, or other satisfactory 

means at the rate of 1½ pounds per l000 square feet, unless otherwise specified.   F. Inoculate Group "C" seed and seeds of  legumes, when sown alone, before sowing  in 

accordance with the recommendations of the manufacturer of the inoculant.   G. Do not perform seeding during windy weather, or when the ground surface is frozen, 

wet  or  otherwise  non‐tillable.  No  seeding  shall  be  performed  during  December through February unless otherwise permitted by Engineer.  

 H. When specified, provide seeding with mulch:  

1. Spread hay or straw mulch evenly over the seeded area at an approximate rate of  75  pounds  per  l000  square  feet  immediately  following  the  seeding operations. This rate may be varied by the Engineer depending on the texture and condition of the mulch material and the characteristics of the area seeded. 

2. Hold hay or straw mulch  in place by the use of a mulch binder applied at the approximate rate of 4 gallons per l000 square feet as required. 

3. Cover  bridges,  guardrails,  signs  and  appurtenances,  if  the  mulch  binder  is applied  in  such  a  way  that  it  would  come  in  contact  with  or  discolor  the structures. 

4. When wood fiber mulch is used, uniformly apply at the rate of 28 to 35 pounds per 1000 square feet with hydraulic mulching equipment. 

   

Page 44: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐6 

3.04  SPRIGGING  

A. Lightly  incorporate fertilizer  into the soil  to a depth of approximately  l/2" at the rate of: 1. 15 lbs. per 1000 square feet for grade 0‐20‐20 or equivalent. 2. 40 lbs. per 1000 square feet for agricultural limestone. 

 B. Perform sprigging during September‐November or April‐May and only when the soil is 

in tillable or workable condition.  

C. Do not set crowns during windy weather or when the ground surface is frozen.  

D. Set crowns as soon as preparation of the sprig bed has been completed.  

E. Set crowns at the rate of three sprigs per square yard by means of a tree‐planting bar or equal. 

 F. When specified, perform mulching before sprigging: 

1. Spread mulch material evenly over the area to be planted at the rate of 100 lbs. per 1000 square feet. This rate may be varied by the Engineer depending upon the texture and condition of the mulch material and the ground surface. 

2. Cover with a uniform layer of mulch so that 20 to 25 percent of the ground is visible. The mulch shall be loose enough to allow sunlight to penetrate and air to  circulate  slowly,  but  thick  enough  to  partially  shade  the  ground  and  to reduce erosion. 

3. Hold the mulch in place with mulch binders applied at the rate directed by the Engineer,  not  to  exceed  0.l  gallon  per  square  yard,  as  required  to  hold  the mulch in place. 

 3.05  SODDING  

A. Place sod at all locations shown on the Contract Drawings or where directed.  

B. Loosen the surface of  the ground to be sodded to a depth of not  less  than one  inch with a rake or other device. 

 C. If necessary, sprinkle with water until saturated for a minimum depth of one inch and 

keep moist until the sod is placed.  

D. Immediately before placing the sod, fertilize the prepared surface uniformly at the rate of: 1. 12 lbs. per l000 square feet for grade l0‐l0‐l0 or equivalent. 2. l00 lbs. per l000 square feet for agricultural limestone. 

 

Page 45: Standard Water and Sewer Specifications PDF

LAWN AND GRASS LANDSCAPING  02485‐7 

E. Place  sod  as  soon  as  practical  after  removal  from  the point  of  origin,  and  keep  in  a moist condition during the interim. 

 F. Carefully  place,  by  hand,  on  the  prepared  ground  surface  with  the  edges  in  closed 

contact and, as far as possible, in a position to break joints.  

G. Each strip of sod laid shall be fitted and pounded into place using l0 inch wood tramps, or other satisfactory implements. 

 H. Immediately  after  placing,  thoroughly  wet  and  roll  with  an  approved  roller  or 

hand‐tamp as approved by the Engineer.  

I. On slopes of two to one (2:1) or steeper, pinning or pegging may be required to hold the sod in place. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 46: Standard Water and Sewer Specifications PDF
Page 47: Standard Water and Sewer Specifications PDF

PAVEMENT REPAIR  02575‐1 

SECTION 02575  

PAVEMENT REPAIR  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. The work specified by  this  section shall  consist of  repairing or  replacing all damaged pavement, whether public or private.  Dirt shoulders, roads, streets, drives, and walks shall be restored to their original condition as an incidental part of the installation of utilities.  Repair damaged base on either side of a trench wherever necessary.  Trim the pavement surface to neat lines outside of the trench wall, and repave the entire area as specified below and as shown on the drawings or on the standard details.  

 B. These  specifications  make  reference  to  the  current  edition  of  the  standard 

specifications  of  the  Tennessee Department of  Transportation  (TDOT).    Even  though the weather limitations, construction methods, and materials specifications contained in the TDOT specifications may not be explicitly repeated in these specifications, they shall,  wherever  applicable  to  the  work  called  for  by  this  section,  be  considered  as implied  and  therefore  adhered  to.    However,  the  various  subsections  “Basis  for Payment” contained in the TDOT specifications shall not be considered applicable. 

 C. All pavement repair work shall be  in compliance with the requirements of  the State, 

County or Clarksville Street Department.  1.02  RELATED WORK  

Section 02410:  Cleanup and Restoration   PART 2 – PRODUCTS  Pavement materials shall conform to TDOT specifications as listed below.  2.01 MINERAL AGGREGATE BASE:   Class A, Grading D crushed stone (TDOT specifications, Section 

303, subsection 903.05).  

2.02 BITUMINOUS PRIME COATS:  Cutback asphalt, Grade RC‐250, or emulsified asphalt, Grade AE‐P (Section 402, subsections 904.02 and 904.03). 

 2.03 CRUSHED STONE CHIPS:  Size 6 or Size 7 (Subsection 903.14) 

 

Page 48: Standard Water and Sewer Specifications PDF

PAVEMENT REPAIR  02575‐2 

2.04 DOUBLE BITUMINOUS SURFACE:  For both courses, either cutback asphalt, Grade RC‐800, or RC‐3000, or emulsified asphalt, Grade RS‐2 (Subsections 904.02 or 904.03). 

 2.05 ASPHALTIC CONCRETE BINDER:  Grading B or C, as directed by the Engineer (Section 307). 

 2.06 BITUMINOUS TACK COAT:  Grade AE‐3 (Section 403, Subsection 904.03). 

 2.07 ASPHALTIC CONCRETE SURFACE:  Grading E (Section 411). 

 2.08 QUICK DRY TRAFFIC MARKING PAINT (WHITE AND YELLOW):  Subsection 910.05. 

 2.09 FLOWABLE FILL  

A. Portland Cement:  Section 901.01  

B. Fine Aggregate:  Section 903.01  

C. Fly Ash, Type C or F:  AASHTO M295  

D. Water:  Section 918.01  

E. Chemical Additives:  Section 918.09  

F. Air Entraining Mixtures:  Section 918.09   PART 3 ‐ EXECUTION  3.01 GENERAL  

All paving shall be completed using appropriate equipment and machinery.  All work must be coordinated  with  and  approved  by  the  City  or  County  Street  Department,  TDOT  or  other governing authority.  The Contractor shall perform all work in accordance with the governing authority and shall make all repairs as directed by that authority at no expense to the Owner. 

 3.02  SUBGRADE  

A. Before any base material is installed, compact the sub‐grade of the area to be paved to 95% of optimum density as determined by ASTM D698 (Standard Proctor). 

 B. The backfill material  shall  contain no  topsoil  or  organic matter.    For  all  areas where 

sub‐grade has been prepared, test for uniformity of support by driving a loaded dump truck at a speed of two (2) to three (3) miles per hour over the entire surface.  Make further  improvements  on  all  areas  that  show  a  deflection  of  one  (1)  inch  or more.  When  completed,  the  finished  sub‐grade  shall  be  hard,  smooth,  stable,  and 

Page 49: Standard Water and Sewer Specifications PDF

PAVEMENT REPAIR  02575‐3 

constructed  in  reasonably  close  conformance with  the  lines  and  grades  that  existed prior to beginning construction.   

 C. When  a  base  course  is  compacted,  cut  back  the  surface  course  of  the  existing 

pavement a minimum of one (1) foot beyond the limit of the joint between the old and new base course or as shown on the standard drawings.   Take special care to ensure good compaction of the new base course at the joint.  Apply and compact the surface to conform to the existing pavement so that it will have no surface irregularity. 

 D. No separate payment shall be allowed for sub‐grade preparation.  Cost for sub‐grade 

preparation shall be included in the applicable pay item for the proposed work related to pavement replacement. 

 3.03  BASE  

A. Install a mineral aggregate base of the type specified above in accordance with Section 303 of the TDOT specifications.  The maximum compacted thickness of any one layer shall  be  six  (6)  inches  and  total  thickness  of  the  base  shall  be  that  indicated  by  the standard drawings or as shown on the Contract Drawings. 

 B. No separate payment  shall be allowed  for base stone.   Costs  for additional make‐up 

base stone shall be included in the pavement replacement unit prices.  3.04  SEAL COAT SURFACE  

Uniformly  apply  a  bituminous  prime  coat  of  emulsified  asphalt,  Grade  AE‐P,  or  cutback asphalt, Grade RC‐250, over the entire width of the area to be surfaced at a rate of 0.3 gallon per  square yard.    Immediately after application, uniformly cover  the entire area with Size 7 crushed stone chips at a rate of 12 pounds per square yard. 

 3.05  DOUBLE BITUMINOUS SURFACE  

A. Apply the first course at a rate of 0.38 to 0.42 gallon per square yard with emulsified asphalt,  Grade  RS‐2,  or  cutback  asphalt,  Grade  RC‐800  or  RC‐3000,  and  then immediately  cover  the  Size  6  crushed  stone  chips  at  a  rate  of  33  to  37  pounds  per square  yard.    After  this  is  rolled,  apply  the  second  course  at  a  rate  of  0.30  to  0.35 gallon per square yard, and at once uniformly cover the Size 7 chips at a rate of 20 to 25 pounds per square yard.  Then roll the entire area. 

 B. After the application of the cover aggregate, lightly broom or otherwise maintain the 

surface for a period of four (4) days, or as directed by the Engineer.   Maintenance of the surface shall include the distribution of cover aggregate over the surface to absorb any free bitumen and cover any areas deficient  in aggregate.   Sweep excess material from  the  entire  surface  with  rotary  brooms.    Sweep  the  surface  at  the  time determined by the Engineer. 

Page 50: Standard Water and Sewer Specifications PDF

PAVEMENT REPAIR  02575‐4 

 3.06  ASPHALTIC CONCRETE BINDER  

A. Apply a bituminous prime coat of emulsified asphalt, Grade AE‐P, or cutback asphalt, Grade RC‐250, at a rate of 0.38 to 0.42 gallon per square yard.   Take care to prevent the bituminous material splashing on exposed faces of curbs and gutters, walls, walks, trees, etc.; if such splashing does occur, remove it immediately.  After the prime coat has been properly cured, apply an asphaltic concrete binder to the thickness shown on the standard drawings or the Contract Drawings.   

B. Carefully  place  the  material  to  avoid  segregation  of  the  mix.    Broadcasting  of  the material will not be permitted.  Remove any lumps that do not readily break down. 

 3.07  ASPHALTIC CONCRETE SURFACE  

A. If  the  asphaltic  concrete  surface  course  is  to  be  placed  directly  on  the  mineral aggregate base, place a bituminous prime coat as described above.    If, however,  the surface course is to be placed on a binder course, then apply a bituminous tack coat of the sort specified above under PRODUCTS at a rate of 0.05 to 0.10 gallon per square yard. 

 B. Take  care  to  prevent  the  bituminous material  splashing  on  exposed  faces  of  curbs, 

gutters, walls, walks, trees, etc.;  if such splashing does occur, remove it  immediately.  After the prime or tack coat has been properly cured, apply the asphaltic concrete to the thickness shown of the drawings or standard drawings.   Apply the surface course as described above for the binder course. 

 3.08  FLOWABLE FILL  

A. Flowable  fill  shall  be  used  where  designated  on  the  Contract  Drawings  and  on  any crossing of  a  State Highway or  as  required by City  Street Department or  the County Highway Department. 

 B. Flowable fill shall be covered or otherwise protected while  in the flowable state.   No 

embankment or fill shall be placed on the flowable fill prior to final set or hardening as determined by the Engineer. 

 C. All  sections  of  pipe  shall  be  securely  braced  or  anchored  both  horizontally  and 

vertically,  if  necessary,  to  prevent  movement  of  the  pipe  during  placement  of  the flowable  fill.   Pipe sections  shall be  joined so as  to prevent  the  influx of  flowable  fill around the joints.  The Contractor shall replace at his expense any pipe or sections of pipe which do not conform to the above requirements. 

 D. Flowable fill shall be proportioned as follows: 

1. Portland Cement Type 1, 100 lbs./c.y. 

Page 51: Standard Water and Sewer Specifications PDF

PAVEMENT REPAIR  02575‐5 

2. Fly Ash, 250 lbs. (minimum)/c.y. 3. Fine Aggregate, 2,800 lbs./c.y. 4. Water, 60 gal/c.y. 5. Proportions  may  be  adjusted  by  the  Engineer  to  achieve  a  consistency  for 

satisfactory flow.  3.09  SMOOTHNESS  

The finished surfaces shall conform to the lines and grades that existed prior to construction.  No  deviations,  variations,  or  irregularities  exceeding  1/4  inch  in  any  direction when  tested with a 12‐foot straightedge shall be permitted in the finished work, nor will any depressions that will not drain.  Correct all such defects. 

 3.10  SAMPLING AND TESTING  

A. Submit to the Engineer test reports made by an independent testing laboratory on the crushed stone aggregate, bituminous materials, and asphaltic concrete design mixes, and obtain his approval of these reports before starting paving operations. 

 B. Tests  shall  be  made  of  the  completed  elements  of  the  pavement  to  ascertain  the 

compacted  thickness  of  the  base  and  surface  courses.    If  sections  with  deficient thicknesses are  found,  the  full  section  for a  reasonable distance on each  side of  the deficiency shall be refused.  Remove and reinstall all such sections.  Patch all test holes in connection with thickness test. 

 C. When  making  surface  tests,  furnish  one  (1)  man  to  mark  all  surface  defects  for 

corrections.  3.11  PAVEMENT STRIPING   

All  disturbed  pavement  markings  including  stop  bars  shall  be  replaced  to  match  existing striping. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 52: Standard Water and Sewer Specifications PDF
Page 53: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐1 

SECTION 02713  

WATER DISTRIBUTION SYSTEMS  

TABLE OF CONTENTS  PART 1 – GENERAL  1.01 WORK INCLUDED  

Installation, testing, and disinfection of water lines and appurtenances.  1.02 RELATED WORK  

A. Section 02221:  Trenching, Bedding and Backfilling  B. Section 02715:  Fire Service Water Meters 

  PART 2 – MATERIALS, STORAGE AND HANDLING  2.01  MANUFACTURER’S RECOMMENDATION  

Care  shall  be  exercised  in  the  delivery,  storage  and  handling  of  all  materials  prior  to  their incorporation  into  the  work.    Follow  all  manufacturers’  recommendations  for  delivery  and storage (except where these specifications differ.)  Acceptance of questionable material shall be  based  solely  on  the  Engineer’s  interpretation  of  fabrication,  delivery,  storage  and installation practices of the material in question. 

 2.02  STORED PIPE  

Contractor shall  take special care to assure that no foreign matter  including, but not  limited to, soil, trash, trench water or other debris enters the pipe at any time.  Upon arrival of pipe shipment,  Contractor  shall  completely  seal  pipe  openings  in  a  manner  acceptable  to  the Engineer. 

 2.03  STORED FITTINGS  

Contractor shall take special care to assure that no foreign matter including, but not limited to soil, trash, trench water or other debris enters pipe appurtenances at any time.  Upon arrival of pipe shipment, Contractor shall completely seal pipe openings  in a manner acceptable to the Engineer. 

   

Page 54: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐2 

2.04  INSTALLED PIPE  

The installed pipe in the trench shall be plugged at the close of work each day or during any prolonged break period, including anytime workers are absent from the jobsite (lunch breaks, etc.).  The only acceptable method for plugging the installed pipe is with a watertight M.J. cap or M.J. plug.  

2.05  FAILURE TO FOLLOW SPECIFICATIONS  

Failure to take such preventative measures mentioned in these specifications, or flooding or contamination of the main for any reason, shall require the Contractor to clean the line with a hydraulically  propelled  foam  pig  (or  other  suitable  pigging  device  acceptable  to  the  City Engineer)  and  slug  chlorinate  the  line  as  specified  in  Paragraph  4.08  of  this  Section.    The Contractor  shall  also  be  required  to  take  whatever  other  measures  required  by  the  City Engineer  in  accordance  with  these  specifications  or  AWWA  C‐651  to  remove  the contamination.  All such procedures shall be fully documented and submitted for approval by the City Engineer. 

  PART 3 – PRODUCTS  3.01  POLYVINYL CHLORIDE PIPE (PVC) AND FITTINGS  

A. Provide PVC pipe meeting ASTM D02241 or AWWA C900.  

B. ASTM D02241 Pipe: 1. Manufactured from virgin, National Sanitation Foundation (NSF) approved Type 

1,  Grade  1  impact  improved  resin  suitable  for  use  in  transporting  potable water.  

2. Pipe and fittings pressure rated for 200 psi. 3. Use only where the maximum pressure shall not exceed 90 psi. 4. Maximum Standard Dimensional Ratio (SDR) of 21. 5. Joints  sealed  with  a  rubber  ring  and  non‐toxic  lubricant  as  provided  by  the 

manufacturer  meeting  or  exceeding  the  requirements  of  ASTM  D3139  and ASTM F477. 

6. Clearly  mark  with  the  manufacturer’s  name,  nominal  diameter,  SDR,  ASTM D02241, pressure rating, and NSF approval seal. 

7. Furnish in standard laying lengths of twenty (20) feet. 8. Color of pipe shall be blue or white. 

 C. AWWA C‐900 Pipe: 

1. PVC 1120 pipe manufactured from virgin, National Sanitation Foundation (NSF) approved compounds meeting the requirements of ASTM D1784. 

2. Pipe and fittings pressure rated for 200 psi. 3. Outside diameter equivalent to the same outside diameter of cast iron pipe. 

Page 55: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐3 

4. The minimum wall thickness of the bell, at any point, shall conform to the DR requirements of the pipe. 

5. Furnish in standard laying lengths of twenty (20) feet. 6. Clearly mark with the manufacturer’s name, nominal diameter, DR, PVC 1120, 

pressure class, AWWA C900, and NSF approval seal. 7. Color of pipe shall be blue or white. 8. To be used in areas where service pressure exceeds 90 psi. 

 D. PVC Fittings:  Not allowed for water mains. 

 3.02  DUCTILE IRON PIPE, FITTINGS AND RESTRAINING WEDGE‐ACTION GASKETS  

A. Pipe: 1. All pipe 10‐inch and larger shall be ductile iron. 2. Manufactured in accordance with ANSI A21.51 (AWWA C151). 3. A cement lining meeting the requirements of ASNI 21.4 (AWWA C104). 4. A minimum of 1 mil thick bituminous coating on the outside surface. 5. Clearly  mark  with  manufacturer’s  name,  D.I.  or  Ductile,  weight,  class  or 

nominal thickness, and casting period. 6. Unless  otherwise  specified  or  shown  on  the  plans,  ductile  iron  pipe  shall  be 

pressure class 350 for sizes up through 12‐inch.   Sizes 14‐inch and larger shall be class 250. 

7. For directional bores, restrained joint ductile iron pipe equivalent to American Flex Ring or U.S. Pipe T.R. Flex with minimum pressure class 350 shall be used. 

 B. Fittings:    All  fittings  and  specials  for  pipe  3”  in  diameter  and  larger  shall  be  cast  or 

ductile iron. 1. Fittings 3” – 24”:  Pressure rated at 350 psi meeting the requirements of ANSI 

21‐53/AWWA C153 for compact fittings. 2. Fittings 30” – 36”:  Pressure rated at 250 psi meeting the requirements of ANSI 

21.10/AWWA C110 for full size fittings or ANSI 21.53/AWWA C153 for compact size fittings. 

3. Joints meeting the requirements of ANSI 21.11/AWWA C111. 4. All mechanical joint ductile iron fittings shall be equipped with mechanical joint 

restraint devices as specified in Section 3.09.  

C. Restraining Wedge‐Action Gaskets: 1. Ductile  iron  pipe  with  push‐on  type  joints,  size  6‐inch  through  24‐inch 

diameter, shall use restraining wedge‐action gaskets meeting the requirements of ANSI A21.11/AWWA C111. 

2. Gaskets for 6” – 18” DI pipe:  Pressure rated at 350 psi working pressure. 3. Gaskets for 20” – 24” DI pipe:  Pressure rated at 250 psi working pressure. 4. Acceptable products are:  McWane SURE STOP 350 Gasket, U.S. Pipe Field Lok 

350 Gasket, Gripper Gasket LLC, American Fast‐Grip Gasket.  

Page 56: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐4 

3.03  HIGH DENSITY POLYETHYLENE PIPE (HDPE) FOR HORIZONTAL DIRECTIONAL DRILLING  

A. HDPE pipe shall only be used for directional bores as approved by the City Engineer.  

B. Pipe  shall  have  a  DR  number  9 with  a working  pressure  of  200  psi  and  be  sized  to provide inside diameter equal to or greater than the size shown on the plans. 

 C. Materials:    Polyethylene  pipe  and  fittings  shall  be  made  from  resin  meeting  the 

requirements  of  the  Plastic  Pipe  Institute  as  PE  3408.    The  resin  shall  meet  the requirements  of  ASTM  D3350‐02  with  a  cell  classification  of  345464C.    The requirements of this cell classification are: 

 HDPE Resin Specifications  Property      Specification    Unit              Typical Value Material Designation    PPI/ASTM          PE 3408 Material Approval    NSF #14             Material Classification   ASTM D1248          III C5 P34 Cell Classification    ASTM D3350‐02        345464C   Density    ASTM D1505    g/cm3      0.955   Melt Index    ASTM 1238    gm/10 min    0.11   Flexural Modulus  ASTM D790    psi      135,000   Tensile Strength  ASTM D638    psi      3,200   Slow Crack Growth   

ESCR    ASTM D1693    hours in 100% igepal  >5,000 PENT    ASTM F1473    hours      >100 HDB @73 deg F  ASTM D1693    psi      1,600 UV Stabilizer  ASTM D1603    %C      2.5% 

 D. Butt  Fusion  Fittings:    HDPE  fittings  shall  be  PE  3408,  HDPE,  Cell  Classification  of 

346464C as determined by ASTM D3350‐02,  and approved  for potable water use by the AWWA.  Butt fusion fittings shall have a manufacturing standard of ASTM D3261.  Molded  and  fabricated  fittings  shall  have  a  pressure  rating  equal  to  the  pipe  unless otherwise specified in the plans.  Fabricated fittings are to be manufactured using data loggers.  Temperature, fusion pressure and a graphic representation of the fusion cycle shall  be  part  of  the Quality  Control  records.    All  fittings  shall  be  suitable  for  use  as pressure conduit, and per AWWA C906, have a nominal burst value of 3.5  times  the working pressure rating of the fitting. 

 E. Pipe Manufacturer’s  Quality  Control:    The  pipe manufacturer  shall  have  an  ongoing 

Quality  Control  program  for  incoming  and  outgoing  materials.    HDPE  resins  for manufacturing of pipe shall be checked for density, melt flow rate, and contamination.  The manufacturer of the HDPE resin shall certify the Cell Classification as indicated in Paragraph C above.  These incoming resins shall be approved by plant Quality Control and verified as approved by NSF before being converted to pipe.  Pipe shall be checked 

Page 57: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐5 

for  outside  diameter,  wall  thickness,  length,  roundness  and  surface  finish  on  the inside, outside and end cut. 

 F. HDPE pipe shall be  joined together at  the transition points  to other mechanical  joint 

adapters.    Mechanical  joint  adapters  shall  have  a  manufacturing  standard  of  ASTM D3261.  They shall have a pressure rating equal to the pipe. 

 G. A minimum of 100  feet of  restrained  joint ductile  iron pipe shall be provided on  the 

pipe  preceding  and  the  pipe  following  the  HDPE.  Appropriate  restraint  methods include using restrained joints equivalent to American Flex Ring or U.S. Pipe T.R. Flex. 

 3.04  SERVICE PIPE  

A. Water  service  pipe  material  may  be  Municipex  crosslinked  polyethylene  (PEXa)  by Rehau, or alternatively may be Type K soft copper.   PEXa water service pipe shall be blue in color. Where compression fittings are used on Municipex pipe, insert stiffeners are required to ensure a proper connection is made.  Plastic insert stiffeners are to be used where pipe  is  less than 2  inches  in diameter and stainless steel  insert stiffeners are to be used where pipe is 2‐inch diameter and larger. 

 B. Copper Pipe: 

1. Seamless copper tubing meeting the requirements of ASTM B88, Type K for ¾” through 2”.   Copper tubing 1” and smaller shall be soft.   Copper tubing larger than 1” may be hard or soft.   All underground copper to copper connection is to be by compression coupling, no solder sweat joints. 

2. Contain not less than 99.90% copper and not more than 0.04% phosphorous. 3. Suitable for use with a working water pressure of 160 psi. 4. ¾” nominal diameter unless otherwise specified or shown on the Plans. 5. Service pipe shall be used to connect the corporation stop with the meter yoke.  

Use the minimum length required to make a straight‐line connection including a  goose  neck.    The  minimum  length  of  service  shall  be  5  feet  in  order  to facilitate the location of the services with metallic pipe locators. 

6. No 3” copper service pipe shall be allowed.  No 3” piping on Clarksville’s side of the water meter shall be allowed. 

7. All  copper  service  piping  shall  be  buried  at  a  minimum  depth  of  24”  below finished grade unless otherwise approved. 

 C. Ductile Iron Pipe: 

For  service  lines 4‐inches and  larger, ductile  iron pipe meeting  the  requirements  set forth in Paragraph 3.02 shall be used. 

 3.05  WATER SERVICE ASSEMBLIES  

A.  Water Meters (all water meters are issued by the City of Clarksville): 1. AWWA C700. 

Page 58: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐6 

2. 5/8”  x  ¾”  unless  otherwise  specified  or  shown  on  the  Plans.    For  customers requesting water meters larger than 5/8” x ¾” the “CGW Water Customer Data Sheet”  included  in  Appendix  E  shall  be  completed  and  submitted  with Construction Plans for review by the City. 

3. Frost proof with a cast bronze casing and a hinged cover. 4. Direct reading register, in gallons, unless otherwise specified. 5. Disc or piston operated with magnetic drive. 6. A  suitable  non‐corrosive  strainer  located  over  the  inlet  to  the  measuring 

chamber. 7. The name of the manufacturer imprinted in the lid of the register box and the 

meter serial number imprinted thereon. 8. Meters shall be located in non‐traffic areas. 9. Water services shall be located near the center of the lot in non‐traffic areas so 

that they are not in driveways.  Water meters shall be located in a landscaped area near the property line unless otherwise approved by the City Engineer. 

 B. Water Main Connections: 

1. For all multiple unit buildings,  individual taps on the main for single units (i.e. duplexes, triplexes, apartment buildings, etc.) will not be allowed.   The City will own and maintain only one meter per structure.  

2. Tap water mains in the upper half of the pipe at a 45‐degree angle. 3. Do not exceed the pipe manufacturer’s recommended maximum tap size. 4. Use service saddles on all taps for PVC pipe.  Water service tapping saddles for 

services 2” or less shall be of total brass or bronze construction with no ferrous materials.    Saddles are  to have double  straps or extra wide  single  straps and shall employ a dual o‐ring seal.  Saddles shall be Power Seal Model 3401 or pre‐approved equal. 

5. Service taps on line under construction that has not been tested and inspected by the City may be made by a qualified Contractor.  Taps on existing City mains must  be made  by  authorized  City  personnel  unless  specifically  authorized  by the City Engineer’s office. 

6. For  all  2”  taps  on  ductile  iron  lines,  a  ductile  iron  epoxy  coated  body  saddle with  double  stainless  steel  straps  equivalent  to  Smith  Blair  317  shall  be furnished.    For  ¾”  to  1”  connections,  ductile  iron mains  shall  be  drilled  and tapped with no need for a saddle. 

 C. Corporation  Stops/Service  Valves:    Corporation  stops  are  required  for  all  ¾”  and  1” 

services.  Services of 2” diameter shall use a 2” ball valve with a square operating nut.  All corporation stops shall have a minimum rating of 200 psi.   All service valves shall have  a  standard  valve  box  installed  and  brought  to  grade.    Corporation  stops  shall meet the following criteria: 1. AWWA C800 2. Cast of certified waterworks red brass, composed of 85% copper and 5% each 

of tin, lead, and zinc. 3. Water tight and individually tested for leaks. 

Page 59: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐7 

4. Waterway diameter approximately equal to the nominal size of the stop. 5. Coat or cap all threads for protection prior to installation. 6. Manufactured by Mueller Company (Model B‐25008) or pre‐approved equal. 

 D. Meter Yokes (all meter yokes are issued by the City of Clarksville): 

1. Copper tubing with an integral brace and meter stop. 2. Minimum rise of  7”. 3. Provide  with  outlets  designed  for  the  use  of  polyethylene  or  copper  service 

pipe. 4. Manufactured by Mueller Co. or pre‐approved equal. 

 E. Curb Valves:  All water services less than 2” diameter must terminate with a curb ball 

valve  immediately  prior  to  the  meter  yoke  location.    Approved  model  is  Mueller B25140R3  or  pre‐approved  equal.    Curb  ball  valves  that  are  buried  prior  to  the installation of a yoke shall have a bolt or pin placed in the stop wing to prevent the ball valve from being accidentally opened during back fill. 

 F. Meter Boxes (all meter boxes are issued by the City of Clarksville): 

1. Water  meters  shall  be  located  in  a  landscaped  area  near  the  property  line unless otherwise approved by the City Engineer. 

2. The depth of the meter yoke inlet for 5/8” – 1” meters shall be 18” to 24”. 3. The depth of the meter yoke inlet for 1 ½” – 6” meters shall be 24” to 36”. 4. Meter box to be of sufficient size to facilitate easy installation and removal of 

the water meter. 5. Where  the  service  assemblies  include  a  pressure  reducing  valve,  sufficiently 

size box for installation of the pressure reducing valve in the meter box.  

G. Pressure  Reducing  Valves  for  Service  Assemblies:    Pressure  reducing  valves  are  the responsibility of  the customer and may be  installed at any point downstream of  the meter  in  accordance  with  the  Standard  Plumbing  Code  and  the  City’s  “Cross Connection Control Policy and Program”.  Pressure reducing valves are required where the static pressure is greater than 80 psi. 

 H. Service Materials:   No galvanized pipe, galvanized nipples, black iron, glued plastic or 

sweated  fittings  are  to  be  used  between  the main  and  the meter  yoke.    Threaded brass, slip joints, mechanical joints, and bronze/brass compression fittings are allowed. 

 3.06  VALVES AND VALVE BOXES  

A. Gate Valves 1. AWWA C509 or C515. 2. Iron body, resilient seat, non‐rising stem type. 3. Stuffing boxes:   O‐ring seal  type with two (2)  rings  in  the stem  located above 

the thrust collar. 4. 2” square wrench nut for operation of the valve. 

Page 60: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐8 

5. Minimum design working water pressure of 200 psi  for valves with diameters of 2” – 12” and 150 psi for valves with diameter of 14” – 54”, unless otherwise specified or shown on the plans. 

6. Joints:  ANSI A21.11 (AWWA C111). 7. Bonnet or body markings:  Manufacturer’s name, year of casting, size, pressure 

rating, and open direction labeled with an arrow. 8. Epoxy coat interior and exterior in accordance with AWWA C550. 9. All main  line  valves  and  hydrants  in  old  Clarksville,  St.  Bethlehem  and  Sango 

water systems including new construction are to open by turning to the right.  Valve operating nuts and fire hydrants that open to the right shall be painted yellow.  All main line valves and hydrants in the old New Providence, Edgoten, Kirkwood and North Montgomery areas including new construction are to open by turning to the left.  Valve operating nuts and hydrants that open to the left shall  be  painted  red.    For  other  details  contact  the  City  Engineer’s  office  for clarification.  A copy of the valve and fire hydrant map for the City is included in Appendix A of these specifications. 

10. Shall  be  Mueller  A‐2360,  M&H  7571,  American  Flow  Control  2500  or  pre‐approved equal. 

 B. Butterfly Valves: 

1. AWWA C504. 2. Cast iron body, rubber seated tight‐closing type. 3. Cast markings:    valve  size, manufacturer’s  name,  class,  direction  of  opening, 

and the year of casting. 4. Class  250,  suitable  for  working  water  pressure  of  250  psi  unless  otherwise 

specified or shown on the plans. 5. Epoxy coat interior and exterior in accordance with AWWA C550. 6. All main line valves and hydrants in the old Clarksville, St. Bethlehem and Sango 

water systems including new construction are to open by turning to the right.  Valve operating nuts and fire hydrants that open to the right shall be painted yellow.  All main line valves and hydrants in the old New Providence, Edgoten, Kirkwood and North Montgomery areas including new construction are to open by turning to the left.  Valve operating nuts and hydrants that open to the left shall  be  painted  red.    For  other  details  contact  the  City  Engineer’s  office  for clarification.  A copy of the valve and fire hydrant map for the City is included in Appendix A of these specifications. 

7. Shall be Mueller LineSeal XP, M&H Style 4500, or pre‐approved equal.  

C. Valve Boxes: 1. Cast iron, 2‐piece or 3‐piece, screw type with shaft diameter of not less than 5” 

(John Bouchard 562‐S or equal). 2. Comply with AWWA M44. 3. Heavy  roadway  type equipped with  a  cover  containing  the word  “WATER”  in 

raised letters on the top. 

Page 61: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐9 

4. Base  of  such  size  as  to  permit  its  installation without  allowing  it  to  come  in contact with either the valve or the pipe. 

5. In paved areas, the top of the box casting shall be made level with the adjacent pavement.    In unpaved areas, the box shall be level with the adjacent ground and  encircled  with  a  concrete  collar  4”  thick  and  2’  in  diameter.    Pre‐cast concrete valve collars may also be used around valve boxes. 

 D. Tapping Valves and Sleeves: 

1. Tapping valves shall meet all the requirements of Paragraph A above and shall be Mueller T2360‐16, M&H 4751‐01 or pre‐approved equal.  

2. Tapping sleeves  shall be Mueller H‐304, Ford FTSS,  JCM 452, Smith Blair 665, Dresser Style 630 or pre‐approved equal.  

3. Tapping  sleeves  shall  be  two‐piece  fabricated  stainless  steel  with adjusting/tightening bolts on each side.  The fabricated sleeve must contain all stainless materials and be rated for the anticipated working pressure. Sleeves must  have  a  stainless  steel  outlet  flange.  Sleeves with  ductile  iron  or  carbon steel flanges will not be accepted. Care must be used to assure that all bolts are equally  tightened.    The  tapping  valve  is  to  be  solidly  supported with brick  or block and carefully bedded to prevent shifting due to settling back fill. 

4. After valve is bolted to sleeve, and with valve closed, remove test plug from the tap on sleeve and air test sleeve to 100 psi prior to making tap. 

5. For taps made on 16‐inch lines and larger, a ductile iron tapping sleeve, Mueller H‐615 shall be required. 

 3.07  AIR RELEASE ASSEMBLIES FOR WATER MAINS  

A.  Furnish 1” nominal diameter for 8” mains and smaller and 2” nominal diameter for 10” mains and larger, unless otherwise specified or shown on the Plans. 

 B. Air release assemblies and combination air release assemblies shall consist of: 

1. Double  strap,  bronze  service  clamp with  neoprene  gasket  for  PVC  lines  (see Paragraph 3.05). 

2. Double  stainless  steel  strap,  epoxy  coated  ductile  iron  body  saddle  shall  be used in 2‐inch assemblies for ductile iron (see Paragraph 3.05) 

3. Brass  pipe  of  the  nominal  diameter  required  by  the  size  of  the  valve.    No galvanized pipe is allowed.   

4. Red brass corporation stop. 5. Brass elbow. No galvanized materials are allowed.  6. Bronze  gate  valve  with  hand‐wheel  or  a metallic‐body  ball  valve  with  2‐inch 

square nut. 7. Air release valve. 

 C. Air and Vacuum Release Valves (Combination Valves): 

1. All  potable  water  lines  shall  have  air  and  vacuum  release  valves  installed  as they are indicated on the plans. 

Page 62: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐10 

2. The body/base of these valves shall be made from stainless steel or cast  iron, and all operating parts are to be made of engineered corrosion resistant plastic materials or stainless steel. 

3. The  valve  shall  be  designed  to  allow  larger  than  normal  automatic  orifice  to provide  efficient  air  release  and  minimize  potential  debris  build  up  and clogging. 

4. The  working  pressure  shall  be  250  psi  and  shall  have  a  2‐inch  threaded connection. 

5. All air and vacuum release valves shall be model ARI D‐040, Crispin Valve Model C, APCO Model 1800, or pre‐approved equal. 

 D. Automatic Air Release Valves: 

1. All potable water lines shall have automatic air release valves as shown on the plans. 

2. Valve shall be made from stainless steel or cast iron and all operating parts are to  be  made  of  engineered  corrosion  resistant  plastic  materials  or  stainless steel. 

3. The  valve  shall  be  designed  to  allow  larger  than  normal  automatic  orifice  to provide  efficient  air  release  and  minimize  potential  debris  build  up  and clogging. 

4. The working pressure shall be 250 psi and tested to 360 psi. 5. All air release valves shall be model ARI S‐050‐C, Crispin Valve Model PL, APCO 

Model 200, or pre‐approved equal.  

E. Install air release assemblies and combination air release valves in a pre‐cast concrete manhole, 48” in diameter and 48” deep, nominal diameter cast iron frame and cover.  Cover to be marked “WATER”. 

 F. Place crushed stone  from 12” below the bottom of  the main  to  the  top of  the main 

inside the pre‐cast manhole.  3.08  FIRE HYDRANTS AND BLOW‐OFF HYDRANTS  

A. Fire Hydrants: 1. AWWA C502.   Mueller  Super  Centurion  250  (Model  A‐423)  or M & H Model 

#129 are the standard for Clarksville. 2. Cast  iron  bodies,  fully  bronze mounted,  designed  for  operation  at  a working 

water pressure of 150 psi. 3. Furnish with two 2‐½” thread brass hose nozzles and one threaded 4‐½” brass 

pumper nozzle. 4. Compression  type  main  valve  5‐¼”  diameter  faced  with  a  suitable  yielding 

material such as rubber, leather, or balata. 5. So designed that, when it is installed, no excavation is required to remove the 

main valve or the movable parts of the drain valve. 6. Inside diameter of barrel:  at least 120 percent of the hydrant valve size. 

Page 63: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐11 

7. Inlet connection:  minimum of 6” mechanical joint on all lines, unless otherwise specified or shown on the Plans. 

8. Equipped with  safety  flange  located  not more  than  10”  above  ground  and  a two‐piece shaft break‐away assembly. 

9. All main line valves and hydrants in the old Clarksville, St. Bethlehem and Sango water systems including new construction are to open by turning to the right.  Valve operating nuts and fire hydrants that open to the right shall be painted yellow.  All main line valves and hydrants in the old New Providence, Edgoten, Kirkwood and North Montgomery areas including new construction are to open by turning to the left.  Valve operating nuts and hydrants that open to the left shall  be  painted  red.    For  other  details  contact  the  City  Engineer’s  office  for clarification.  A copy of the fire hydrant map is attached to this document (see Appendix A).  

10. Shop  paint  and mark  in  accordance with  AWWA  C502.    Open  right  hydrants yellow.  Open left hydrants red. 

11. Cast  markings:    manufacturer’s  name,  size  of  the  main  valve,  year  of manufacture, and direction of opening. 

12. Field  touch‐up,  if  the  surface  has  been  marred,  with  paint  supplied  by  the manufacturer of the same color and type as that used during shop painting. 

13. 4’  bury  hydrants  are  the  standard.   Where  the  line  depth  justifies  additional depth, hydrant extensions shall be installed. 

14. All hydrants shall be installed utilizing hydrant (swivel) tees.  Unless otherwise shown on  the plans,  tees with  all mechanical  joint  ends  shall  be used  if  field conditions  require  hydrant  isolation  valve  to  be  placed  away  from  the water main. 

15. All hydrants shall be installed with a 6‐inch isolation gate valve in valve box. 16. Fire hydrants shall not be installed on water lines less than 6‐inch in diameter. 17. A fire hydrant shall not be located closer than five (5) feet from any driveway. 18. Per  the  Clarksville‐Montgomery  County  Regional  Planning  Commission 

Subdivision  Regulations,  all  fire  hydrants  shall  be  located  on  a  minimum  6” water line.  Fire hydrants located within a single‐family residential district shall be spaced no more than 800’ apart, as measured along the street right‐of‐way.  Fire  hydrants  located  within  a  multi‐family,  commercial  or  industrial  district shall  be  spaced  no  more  than  300’  apart.    A  fire  hydrant  must  be  installed within 300’ of the dead‐end of a cul‐de‐sac.  All fire hydrant locations shall be approved  by  the  Clarksville  Fire  Department  or  the  Montgomery  County Emergency Management Agency. 

 B. Blow‐Off Hydrants: 

1. Post  type  having  cast  iron  bodies,  fully  bronze  mounted  and  designed  for operation at a working water pressure of 150 psi. 

2. Furnish with either two 1‐1/2” or 2‐1/2” threaded brass hose nozzles. 3. Compression type main valve 2‐1/8” minimum diameter faced with a suitable 

yielding material such as rubber, leather or balata. 

Page 64: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐12 

4. So designed that, when it is installed, no excavation is required to remove the main valve or the movable part of the drain valve. 

5. Inside diameter of the barrel:  at least 3”. 6. Inlet connection:  2” mechanical joint, unless otherwise specified or shown on 

the plans. 7. Equipped with a safety flange located not more than 2” above the ground. 8. Open on counter‐clockwise operation, unless otherwise specified. 9. Cast  markings:    manufacturer’s  name,  size  of  the  main  valve,  year  of 

manufacture, and direction of opening. 10. Field  touch‐up,  if  the  surface  has  been  marred,  with  paint  supplied  by  the 

manufacturer of the same color type as that used during shop painting. 11. Type of post hydrant:  Mueller A‐411 or M & H (Style 33 or 233). 

 3.09  MECHANICAL JOINT RESTRAINT DEVICE  

A. Pipe  restraint:    It  is  the  intention  of  these  specifications  that  all  mechanical  joint fittings  and  valves  be  restrained  at  each  opening  with  approved  mechanical  joint restraint devices.  Restrained fittings do not eliminate or replace the requirement for sufficient concrete thrust blocking and/or restrained pipe joints. 

 B. PVC Restraint Devices: 

1. Restraint devices shall consist of multiple gripping wedges incorporated into a follower  gland  meeting  the  applicable  requirements  of  ANSI/AWWA C111/A21.11. 

2. Devices shall have a working pressure rating equal to that of the pipe on which it  is used.  Ratings are for water pressure and must include a minimum safety factor of 2:1. 

3. Restraint devices shall have torque bolts. 4. Megalug series 2000 PV produced by EBAA Iron or equal. 

 C. Ductile Iron Pipe Restraint Devices: 

1. Restraint devices shall consist of multiple gripping wedges incorporated into a follower gland meeting the requirements of ANSI/AWWA C110/A21.10. 

2. Devices shall have a working pressure rating of 350 psi for 3” to 16” and 250 psi for 18” and larger.  Ratings are for water pressure and must include a minimum safety factor of 2:1. 

3. Restraint devices shall have torque bolts. 4. Megalug Series 1100 produced by EBAA Iron or equal. 

 D. Restraint Devices ‐ General: 

1. Gland body, wedges and wedge activating components shall be cast from grade 65‐45‐12 ductile iron material in accordance with ASTM A536. 

2. Installation  shall  be  performed  using  conventional  tools  and  installation procedures  as  specified  in  AWWA  C600  while  retaining  full  mechanical  joint deflection during assembly as well as allowing joint deflection after assembly. 

Page 65: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐13 

3. Proper activatin of  the gripping wedges  shall be ensured with  torque‐limiting twist‐off nuts. 

 3.10  CROSS CONNECTION  

A. All commercial properties must have backflow protection installed on incoming water lines  (domestic,  fire  and  irrigation).    The  type  and  location  of  commercial  property backflow prevention devices shall be as follows: 1. Reduced Pressure Assemblies for domestic and irrigation. 2. Double  Check  Assemblies  (with  fire  meter)  or  Double  Check  Detector 

Assemblies (where approved by the City Engineer without fire meter) for all fire systems unless the system contains chemicals or  is connected to an alternate water source. 

3. Backflow prevention devices shall be installed downstream of the meter before the first branch off the main line serving the building(s).  Outdoor installations require protective enclosures.  Inside installations require adequate drains. 

 B. Residential properties are required to install backflow protection on irrigation and fire 

systems.   Multi‐story, Multi‐  Family  (3‐story or more) buildings are  required  to have backflow  prevention  on  domestic,  irrigation  and  fire  system  lines.    Backflow prevention devices may also be required for other properties as directed by City due to connections  to  alternate water  sources  such  as wells  or  connection with  equipment that could alter water quality.  The type and location of residential property backflow prevention devices shall be as follows: 1. Reduced Pressure Assemblies for all  irrigation services and any domestic  lines 

deemed necessary by the Gas and Water Department. 2. Double Check Assemblies for all residential fire systems. 3. Backflow prevention devices shall be installed downstream of the meter before 

the first branch off the main line serving the building(s).  Outdoor installations require protective enclosures.  Inside installations require adequate drains. 

 C. Except  for  fire  systems,  all  backflow prevention  installations  are  required  to  have  a 

strainer installed immediately upstream of the device.  D. See  Cross  Connection  Ordinance  and  Policy  for  more  detail  on  installation  and 

maintenance requirements for backflow prevention devices.   PART 4 – EXECUTION  4.01  PREPARATION  

A. Follow  all  material  storage  and  handling  requirements  in  accordance  with  Section 02713, Part 2. 

 

Page 66: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐14 

B. Prior to laying pipe, prepare a suitable bedding according to Section 02221.  

C. Before placing pipe in the trench, remove temporary pipe plug, field inspect for cracks or other defect; remove defective pipe from the construction site.  

D. Swab the interior of the pipe to remove all undesirable material.  

E. Prepare  the  bell  end  and  remove  undesirable  material  from  the  gasket  and  gasket recess.  

F. Locate water lines in relation to other piped utilities.  4.02  INSTALLING WATER LINES  

A. Install PVC pipe in accordance with AWWA C605.  

B. Install DIP pipe in accordance with AWWA C600.  

C. Lay  all  pipe  on  a  uniform  grade  and  with  deflections  not  exceeding  the  pipe manufacturer’s recommendations.  

D. After  applying  gasket  lubricant,  take  extreme  care  to  keep  the  spigot  end  from contacting the ground.  

E. Hone the pipe with suitable tools or equipment to provide a smooth beveled edge on plain end sections or field cut sections.  

F. Closely follow the manufacturer’s instruction in laying and joining pipe.  

G. Cut pipe for inserting valves, fittings, etc., in a neat and workmanlike manner without damaging the pipe so as to leave a smooth end at right angles to the axis of the pipe.  

H. Cover pipe with a watertight mechanical  joint cap or plug during each  installation of pipe segment and at conclusion of each day’s construction activities.  

I. The location of all nonmetallic water mains installed under these specifications shall be marked by the use of a continuous blue tape, minimum three inches in width, made of minimum 5 mil thick polyethylene plastic with a 0.5 mil thick aluminum metallic core or backing.  The tape shall be buried in the trench, above the pipe, no more than two feet  below  the  surface.    The  tape  shall  be marked  indelibly with  the words  “Water Main Below” or similar wording to warn unwary excavators.  

J. Tracer  wire  shall  be  installed  along  all  water  main  and  water  services.  Tracer  wire installed  in open cut applications shall be Copperhead 1230‐HS, 12 AWG copper‐clad steel  tracer  wire  with  30  mil  HDPE  coating,  no  substitutions  allowed.    Tracer  wire 

Page 67: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐15 

installed  in horizontal directional drill applications shall be Copperhead 1245‐EHS, 12 AWG copper‐clad steel tracer wire with 45 mil HDPE coating, no substitutions allowed.  Tracer wire color shall be blue for water pipe.  Connectors at service connections and tees shall be DryConn Direct Bury Lug Aqua by King Innovation and at main line splices shall be DryConn King 6 Blue by King Innovation, no substitutions allowed.  Tracer wire shall extend at  least five feet beyond service stub terminations.   A piece of PVC pipe shall  be  buried  vertically  against  the  4”x4” marker  post  extending  about  two  inches above ground level.  The tracer wire shall be fed through the PVC pipe with the end of the wire  about  two  inches  above  the end of  the pipe  and  the  remainder  coiled  and buried beneath it.  A performance test will be performed on the completed tracer wire system  to  ensure  the  entire  system  is  trackable.  Any  part  of  the  system  that  is  not trackable shall be repaired or  replaced by the Contractor until  it  is  trackable prior  to final acceptance of utilities.  

K. The  Contractor  shall  stamp  the  concrete  curb with  a  “W” where water  services  are located.  The end of each service stub shall be marked with a 6‐foot long 4x4 wooden post  or metal  fence  post  embedded  2  feet  in  the  ground  and  be marked with  blue paint.  

L. Installing HDPE Water Lines (only for directional drilling applications): 1. HDPE pipe shall be assembled utilizing field‐site butt fusion joints. 2. Personnel  performing  butt  fusion  joining  shall  be  certified  by  pipe 

manufacturer. 3. Each piece of pipe must be held by a clamping device so it will not move. 4. Pipe ends shall be faced to establish clean mating surfaces. 5. Pipe  profiles  must  be  rounded  and  aligned  with  each  other  to  prevent 

mismatch of pipe walls. 6. Heat  the  ends  of  the  pipe  to  the  pipe  manufacturer’s  recommended 

temperature, interface pressure, and time duration. 7. Keep heater  faces clean to prevent molten plastic  from sticking to the heater 

faces. 8. After  heating,  remove  heater  tool  and  bring molten  pipe  ends  together with 

sufficient pressure to form a homogenous joint. 9. Hold the molten joint immobile under pressure until cooling has occurred and 

joint achieves strength. 10. Test line per the requirements of this Section. 

 4.03  SEPARATION OF WATER AND SEWER LINES  

A. Maintain a 10‐foot horizontal separation, measured edge to edge, between any new or proposed water main and any existing or proposed sanitary sewer. 

 B. Where  conditions  cause  the  required  horizontal  separation  to  be  impractical,  the 

water main may be laid closer provided it is laid in a separate trench and the elevation of the top of the sewer is at least 18 inches below the bottom of the water main. 

Page 68: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐16 

 C. Where a sewer crosses under a water main, the top of the sewer shall be at least 18 

inches below the bottom of the main.  

D. Where conditions cause the required vertical separation to be  impractical,  the water main shall be relocated to provide the required separation or else reconstructed with mechanical  joint ductile  iron pipe for a distance of 10 feet on each side of the sewer with a full joint of the water main centered over the sewer. 

 E. Where sewers must be constructed over water mains or less than 18 inches below the 

water  main,  the  sewer  shall  be  designed  and  constructed  equal  to  water  main standards and pressure tested to assume water tightness.   

F. Additional protection such as concrete encasement  shall be  installed where directed by the Engineer.   

G. To prevent cross connection, comply with the City’s “Cross Connection Control Policy and Program.” 

 4.04  INSTALLING APPURTENANCES  

A. Set  all  valves,  fittings,  hydrants,  and  other  special  fittings  in  a  neat  workmanlike manner.   Tapping valves are to be supported with blocking and surrounding bedding carefully compacted to prevent settlement. 

 B. Use thrust blocks, pipe anchors, or other approved means to prevent displacement of 

other fittings as shown on the Project Documents.  Do not allow concrete to cover nuts and bolts on fittings.  Gate valves on fire hydrant leads are to be restrained or blocked independently  of  the  hydrant  blocking  so  that  the  hydrant  may  be  excavated  and removed with the valve closed.   Mechanical restraint  is to be by the use of MegaLug devices or other similar devices.   Underground use of galvanized all thread rod is not allowed except where specifically approved by the Engineer.  Fittings for taps made on the reverse side of the main must be restrained joints.  All mechanical joints are to be restrained  with  mechanical  joint  restraining  devices  as  set  forth  in  Paragraph  3.09.  These  restraining  devices  do  not  eliminate  the  requirement  for  sufficient  concrete thrust blocking and/or restrained joint pipe. 

 C. Erect hydrants to stand plumb with the pumper nozzle facing the road.  Nozzles shall 

be installed a minimum of 12 inches above finished grade.  

D. Enhance drainage of hydrants by using 6 cubic feet of gravel around base of hydrant.  Do not allow concrete thrust block to obstruct drain holes.  

 E. Close  dead  end  pipe  with  a mechanical  joint  solid  sleeve  and  plug,  and  equip  with 

blow‐off assemblies, where shown on the drawings. 

Page 69: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐17 

 4.05  CONNECTING NEW SYSTEM TO EXISTING SYSTEM  

A. Initial filling of the new line shall be made at only one point and shall be via a metered backflow assembly (large sizes may not be metered at option of City) which is provided by  the  City,  installed  by  the  Contractor,  and  then  removed  by  the  Contractor  and returned  to  the  City  after  acceptance  of  the  line.    The  Contractor  is  responsible  for providing  all  necessary  sleeves,  reducers,  or  other  fittings  to  install  and  remove  the backflow assembly from the main. 

 B. All connection of new main extensions to existing systems shall be valved to prevent 

existing  customers  from  being  included  in  the  new  system  area  during  testing  and disinfection procedures.  

C. Connections of new mains  to existing mains  shall normally be made by  the use of  a tapping valve in order to avoid disrupting service to existing customers.  

D. Any  wet  connections  involving  the  shutdown  of  existing  system  valves  shall  be specifically  approved  by  and  coordinated  with  the  City  Engineer’s  Office.    Such coordination  shall  include  the  responsibility  of  the  Contractor  in  notifying  affected customers  and  scheduling  shutdowns  to  minimize  customer  inconvenience.    An authorized  shutdown  shall  not  relieve  the  Contractor  from  liabilities  resulting  from shutdowns  such  as  damaged  water  heaters,  discolored  water,  etc.    The  turning  of valves shall be scheduled with the City’s representative.  

E. Manipulation  of  valves  for  filling  or  flushing  lines  shall  be  minimized  to  avoid accumulations of air and discolored water in the affected areas.  No water valves shall be operated by anyone other than City of Clarksville personnel.  

F. Once new systems are fully activated, following disinfection, flushing and testing, the Contractor shall  inspect each valve  that has been  installed or manipulated  to ensure that all valves are in fully open position.  

G. The  Contractor  will  be  charged  for  the  consumption  volume  of  water  by  flushing, filling, leaks, etc. that exceeds twice the volume of the installed pipe. 

 4.06  HIGHWAY AND RAILROAD CROSSINGS  

A. Perform highway crossings by  the open cut method, unless otherwise  shown on  the Drawings or required by the appropriate authorities. 

 B. Boring  and  jacking,  tunneling,  or  horizontal  directional  drilling  of  crossings,  if 

necessary, will be performed in accordance with the appropriate specification sections.   

Page 70: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐18 

4.07  WATER LINE PRESSURE TESTS  

A. All  newly  laid  pipe  or  any  valved  section  thereof  shall  be  subjected  to  hydrostatic pressure  testing.    Conduct  hydrostatic  testing  in  accordance  with  AWWA  C600  for ductile iron pipe or AWWA C605 for PVC pipe. 

 B. Where practicable, pipelines shall be tested in lengths between line valves or plugs of 

no more than 3,000 feet.  C. Hydrostatic testing shall be conducted only with potable water.   Due to the  inherent 

safety  hazard  potential  associated  with  testing  components  and  systems  with compressed  air  or  other  compressed  gases,  pressure  testing  shall  never  be accomplished using compressed air.  

D. The  Contractor  shall  furnish  all  gauges,  recording  devices,  meters,  pumps,  pipe, connections and other equipment required to conduct the test and shall maintain said equipment in condition for accurate testing as determined by the Owner.  Gauges used for pressure tests shall be oil‐filled gauges.  

E. Hydrostatic  test  results  shall  be  recorded  on  an  appropriate  chart  recorder.    The Contractor  shall  furnish  a  recording  gauge  and  water  meter  for  recording  pressure charts  and  for  measuring  makeup  water  used  during  the  hydrostatic  testing.  Recording  pressure  charts  shall  be  submitted  to  the  Owner  at  the  conclusion  of testing.    The  pressure  recording  device  shall  be  suitable  for  outside  service,  with  a range  from 0–300 psig,  24‐hour  spring wound  clock,  designed  for  9‐inch  charts,  and shall be approved by the Engineer.   For Contractor’s  information only, such pressure recording devices may be available from Foxboro Company, Foxboro, Massachusetts; Bristol Division of ACCO, Waterbury, Connecticut; or Weksler Instruments Corporation, Freeport, New York.  

F. Prior  to  testing,  the  Contractor  shall  place  sufficient  backfill  to  prevent  pipe movement.  When local conditions require that the trenches be backfilled immediately after the pipe has been laid, the testing may be carried out after backfilling has been completed but before placement of permanent surfacing.  The Contractor shall ensure that  thrust  blocking  or  other  types  of  restraining  systems  will  provide  adequate restraint prior to pressurizing the pipeline.  

G. Cross Connection Control:   When existing water mains are used to supply test water, they  should  be  protected  from  backflow  contamination  by  temporarily  installing  a double  check  valve  assembly  between  the  test  and  supply main  or  by  other means approved  by  the  Engineer.    Prior  to  pressure  and  leakage  testing,  the  temporary backflow  protection  should  be  removed  and  the main  under  test  isolated  from  the supply main.  

Page 71: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐19 

H. Test Pressure Requirements: 1. The test pressure shall not be less than 1.25 times the stated working pressure 

of the pipeline measured at the highest elevation along the test section and not less than 1.5 times the stated working pressure at the lowest elevation of the test section, but not greater than 200 psi. 

2. The  test pressure  shall not exceed  the  thrust  restraint design pressure or 1.5 times the pressure rating of the pipe or joint, whichever is less (as specified by the manufacturer). 

3. The  test  pressure  shall  not  exceed  the  rated working  pressure  of  the  valves when  the  pressure  boundary  of  the  test  section  includes  closed,  resilient seated gate valves or butterfly valves. 

4. Valves  shall  not  be  operated  in  either  direction  at  a  differential  pressure exceeding the rated valve working pressure.   A test pressure greater than the rated valve working pressure can result  in trapped test pressure between the gates of a double‐disc gate valve.  For tests exceeding the rated valve working pressure,  the test setup should  include a provision,  independent of the valve, to reduce the line pressure to the rated valve working pressure on completion of  the  test.    The  valve  can  then  be  opened  enough  to  equalize  the  trapped pressure with the line pressure, or the valve can be fully opened if desired. 

 I. Test Procedure: 

1. Each valved section of pipeline shall be slowly filled with potable water using a metered backflow‐protected assembly provided by the Owner.  When venting air from pipelines, it is important to limit the pipeline fill rate to avoid excessive surge pressures when the water reaches the air venting opening(s). 

2. Before  applying  the  specified  test  pressure,  air  shall  be  expelled  completely from the pipeline section under test.  If permanent air vents are not located at all high points, corporation cocks shall be installed at such points to expel air as the  line  is  filled  with  water.    After  all  the  air  has  been  expelled,  close  the corporation  cocks  and  apply  the  test  pressure.    At  the  conclusion  of  the pressure test,  remove the corporation cocks and plug or  leave  in place at the discretion of the Engineer. 

3. The specified test pressure shall be applied using a suitable pump connected to the  pipeline  in  a  manner  satisfactory  to  the  Engineer.    The  specified  test pressure shall be based on the elevation of the lowest point of the pipeline or section  under  test  and  corrected  to  the  elevation  of  the  test  gauge,  in accordance with test pressure requirements specified herein. 

4. The pipeline shall be allowed to stabilize at the test pressure before conducting the  hydrostatic  test.    This  may  require  several  cycles  of  pressurizing  and bleeding  trapped air prior  to beginning  the  test.    It  is  recommended  that  the line remain pressurized for a minimum of 24 hours before testing in order for joints to tighten and pockets of air to dissolve in the water. 

5. The  hydrostatic  test  shall  be  at  least  2  hours  in  duration  after  reaching  the specified  test  pressure where  joints  are  exposed  and  at  least  8  hours where joints are covered. 

Page 72: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐20 

6. The test pressure shall not vary by more than +/‐ 5 psi for the duration of the test.  Test pressure shall be maintained within this tolerance by adding makeup water  through  the  pressure  test  pump  into  the  pipeline.    The  amount  of makeup  water  added  shall  be  accurately  measured  (in  gallons  per  hour)  by suitable  methods  and  shall  not  exceed  the  applicable  testing  allowance  as specified herein. 

 J. Visual Inspection: 

Any  exposed  pipe,  fittings,  valves,  hydrants  and  joints  shall  be  examined  carefully during  the  hydrostatic  pressure  test.    Any  damaged  or  defective materials  that  are discovered during or  following  the pressure  test  shall be  repaired or  replaced at  the Contractor’s  expense,  and  the  test  shall  be  repeated  until  satisfactory  results  are obtained.   Water main  repair and  replacement  shall be  in accordance with Part  L of this Paragraph. 

 K. Testing Allowance: 

1. Testing allowance shall be defined as the maximum quantity of makeup water that  is  added  into  a  pipeline  undergoing  hydrostatic  pressure  testing,  or  any valved  section  thereof,  in  order  to maintain  pressure within  +/‐  5  psi  of  the specified test pressure (after the pipeline has been filled with water and the air has been expelled).   

2. No pipe installation will be accepted if the quantity of makeup water is greater than that determined by the following formula: 

 L = S*D*(P)½          148,000 

Where: L = testing allowance (makeup water), in gallons per hour S = length of pipe tested, in feet D = nominal diameter of the pipe, in inches P  =  average  test  pressure  during  the  hydrostatic  test,  in  pounds  per square inch (gauge pressure)  

3. This formula is based on a testing allowance of 10.5 gpd/mile/inch of nominal diameter  at  a  pressure  of  150  psi.    Values  of  testing  allowance  at  various pressures are shown in the following table.  When testing against closed metal‐seated  valves,  an  additional  testing  allowance  per  closed  valve  of  0.0078 gal/hr/inch of nominal valve size shall be allowed.   When hydrants are  in  the test section, the test shall be made against the main valve of the hydrant. 

Page 73: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐21 

Hydrostatic Testing Allowance per 1,000 feet of pipeline (gallons per hour)* 

Average Test Pressure (psi) 

Nominal Pipe Diameter (inches) 

4  6  8  10  12  14  16  18  20  24  30 

250  0.43  0.64  0.85  1.07  1.28  1.50  1.71  1.92  2.14  2.56  3.21 

225  0.41  0.61  0.81  1.01  1.22  1.42  1.62  1.82  2.03  2.43  3.04 

200  0.38  0.57  0.76  0.96  1.15  1.34  1.53  1.72  1.91  2.29  2.87 

175  0.36  0.54  0.72  0.89  1.07  1.25  1.43  1.61  1.79  2.15  2.68 

150  0.33  0.50  0.66  0.83  0.99  1.16  1.32  1.49  1.66  1.99  2.48 

125  0.30  0.45  0.60  0.76  0.91  1.06  1.21  1.36  1.51  1.81  2.27 

100  0.27  0.41  0.54  0.68  0.81  0.95  1.08  1.22  1.35  1.62  2.03 

75  0.23  0.35  0.47  0.59  0.70  0.82  0.94  1.05  1.17  1.40  1.76 

50  0.19  0.29  0.38  0.48  0.57  0.67  0.76  0.86  0.96  1.15  1.43 

*  If the pipeline under test contains sections of various diameters, the allowable leakage will be the sum of the computed leakage for each size. 

 L. Acceptance of  the  installation  shall  be determined on  the basis of  testing allowance 

only.    Should  any  test  of  pipe  laid  disclose  leakage  greater  than  that  specified,  the Contractor  shall,  at  his  own expense,  locate and  repair  the defective  joints until  the leakage is within the specified allowance.  All visible leaks are to be repaired regardless of  the  allowance  used  for  testing.    Hydrostatic  test  results  shall  be  recorded  on  an appropriate  chart  recorder  as  specified  herein.    A  copy  of  the  test  chart  shall  be provided to the Engineer. 

 M. To  repair  or  replace  damaged  or  defective  water  main  pipe,  the  Contractor  shall 

maintain positive pressure on the main (valves left partially open) while he excavates around  and  under  (2’  clearance)  the  pipe  so  that  water  can  be  pumped  out  of  the excavation pit before it enters the newly constructed main during the repair process.  Contractor  shall  have  adequate  pumping  capacity  to  prevent  any  trench  water  or debris from entering the main during this process.  The interior of all pipe and fittings shall be sprayed with a 1% hypochlorite solution before they are installed in the repair process.    To  produce  this  one  percent  hypochlorite  solution,  one  gallon  of  5% hypochlorite  bleach  can  be  diluted  with  four  (4)  gallons  of  water.    Flooding  or contamination of the main during this process shall  invoke Paragraph 2.05 of Section 02713. 

 STANDARD OPERATION PROCEDURES FOR WATER MAIN DISINFECTION  4.08  CLEANING AND DISINFECTING OF WATER LINES  

A. Disinfection Tests:  Conduct disinfection tests in accordance with AWWA C‐651. 1. During  construction,  take  precautions  to  protect  pipe  interiors,  fittings,  and 

valves  against  contamination.    Follow  all  Material  Storage  and  Handling Requirements in Section 02713 Part 2. 

Page 74: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐22 

2. All  chlorine products  shall  be NSF  approved  chlorine.    Pool  chlorine products shall not be used. 

3. The Granular Method shall be used as the standard disinfection method on all newly installed pipelines unless prior approval for the continuous feed or slug method is obtained from the Engineer or his representative. 

4. Granular Method (Standard Method): a) Obtain NSF approved granular chlorine product from the Clarksville Gas 

and  Water  Department  Warehouse.  All  granular  chlorine  used  in pipeline disinfection must be obtained from Clarksville Gas and Water. A  fee may be  charged  to  cover  the  cost  of  this  product.  This  chlorine product  shall  be  OxyChem  ACL  60  Disinfecting  Granules  (sodium dichloroisocyanurate)  with  approximately  62%  available  chlorine  or approved equal. 

b) Place  granular  chlorine  in  the  pipe  at  the  beginning  of  the  line, beginning of each branch  line, and at 500‐feet  intervals (every 25 pipe joints).  

c) Place enough granular chlorine in the pipe to achieve a 25 ppm dosage in  the  pipeline.    Contractor  shall  obtain  granular  chlorine  in  pre‐measured  bottles  from  the  Clarksville  Gas  and Water  Department  to ensure proper dosage is achieved (see Table I). 

d) Slowly fill the pipeline with water and eliminate all air pockets.  Hold the disinfection solution in the pipeline for 24 hours. 

e) Flush thoroughly to clear the strong chlorine solution from the pipelines before bacteriological sampling (see Item 8 of this section). 

 

TABLE I ‐ GRANULAR METHOD 

GRANULAR CHLORINE DOSE SIZE FOR 500 FT OF PIPE AT 25 PPM (MG/L) 

Pipe Diameter (in)  Dose Size (oz) 

2  0.5 

4  2 

6  4 

8  7 

10  11 

12  16 

16  28 

24  63 

30  99 

36  142 

 5. Continuous Feed Method (Special Approval Required): 

a) Granular  chlorine  may  be  placed  (optional)  in  the  pipeline  during construction (see Granular Method). 

b) Thoroughly flush the pipeline to remove all sediments and air pockets. c) Add a continuous dose of chlorine while  flowing water slowly  into the 

new main until a 25 ppm chlorine concentration is reached throughout 

Page 75: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐23 

the new pipelines.  Contractor shall use Sodium Hypochlorite to obtain the  25  ppm  dosage  (see  Table  II  for  total  amount  of  Sodium Hypochlorite to be fed to establish 25 ppm dosage for 500 feet of pipe).  In the alternative, granular chlorine can be mixed to obtain the 25 ppm concentration  (see Table  I  for  total  amount of  granular  chlorine  to be fed  to establish 25 ppm concentration  for 500  feet of pipe).   Measure the chlorine residual at various locations to conform proper residual has been achieved. 

d) Hold the disinfection solution in the lines for 24 hours and confirm that the chlorine residual is at least 10 ppm after 24 hours. 

e) Flush thoroughly to clear the strong solution from the pipelines before bacteriological sampling (see Item A‐8 of this section). 

 

TABLE II – CONTINUOUS FEED METHOD 

SODIUM HYPOCHLORITE DOSE SIZE FOR 500 FT OF PIPE AT 25 PPM (MG/L) 

Pipe Diameter (in) 

Sodium Hypochlorite Volume (gal) 

5.0%  6.15%  10.0% 

2  0.04  0.03  0.02 

4  0.16  0.13  0.08 

6  0.37  0.30  0.18 

8  0.65  0.53  0.33 

10  1.0  0.83  0.51 

12  1.5  1.2  0.73 

16  2.6  2.1  1.3 

24  5.9  4.8  2.9 

30  9.2  7.5  4.6 

36  13.2  10.7  6.6 

 6. Slug Method (Special Approval Required): 

a) Granular  chlorine  may  be  placed  (optional)  in  the  pipeline  during construction (see Granular Method). 

b) Thoroughly flush the line to remove all sediments and air pockets. c) Admit  water  to  the  new  main  very  slowly  and  dose  with  enough 

chlorine to produce a residual of at least 100 ppm.  Contractor shall use Sodium  Hypochlorite  or  granular  chlorine  according  to  Table  III  to obtain  the  100  ppm  concentration.    The  objective  is  to  produce  a column of 100 ppm chlorine solution which will move slowly as a slug through  the  new  pipeline.    The  column  or  slug  of  highly  chlorinated water must be  long enough to contact all  surfaces of  the pipe  interior for at least 3 hours.  Measure chlorine residuals in the slug as it moves down the pipeline.  The residual must be maintained over 50 ppm. 

d) For emergency line repair situations only, to be performed only by, or in the  presence  of,  authorized  City  personnel,  and  where  no  service connections  exist,  the  standard  100  ppm  concentration  can  be 

Page 76: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐24 

substituted for a 300 ppm solution and the contact time can be reduced from the standard 3 hours to 15 minutes.  Table IV indicates the Sodium Hypochlorite  and  granular  chlorine  dose  sizes  to  be  used  for  this method.    Refer  to  Paragraph  4.08B  for  appropriate  situations  and procedures. 

e) Flush thoroughly to clear the strong chlorine solution from the pipelines before bacteriological sampling. 

 

TABLE III – SLUG METHOD 

CHLORINE DOSE SIZE FOR 500 FT OF PIPE AT 100 PPM (MG/L) 

Pipe Diameter 

(in) 

Sodium Hypochlorite Volume (gal) Granular Chlorine (oz. of weight) 

5.0%  6.15%  10.0%  62% 

2  0.2  0.1  0.1  2.1 

4  0.7  0.5  0.3  7.1 

6  1.5  1.2  0.7  16 

8  2.6  2.1  1.3  28 

10  4.1  3.3  2.0  44 

12  5.9  4.8  2.9  63 

16  10  8.5  5.2  112 

24  23  19  12  253 

30  37  30  18  395 

36  53  43  26  569 

   

TABLE IV – SLUG METHOD 

CHLORINE DOSE SIZE FOR 500 FT OF PIPE AT 300 PPM (MG/L) 

Pipe Diameter 

(in) 

Sodium Hypochlorite Volume (gal) Granular Chlorine (oz. of weight) 

5.0%  6.15%  10.0%  62% 

2  0.5  0.4  0.2  6.3 

4  2.0  1.6  1.0  21 

6  4.4  3.6  2.2  48 

8  7.8  6.4  3.9  84 

10  12  10  6.1  132 

12  18  14  8.8  190 

16  31  25  16  336 

24  70  57  35  758 

30  110  90  55  1185 

36  159  129  79  1706 

 7. While  chlorine  is  being  applied,  manipulate  valves  so  that  the  treatment 

dosage will not  flow back  into  the  line  that  is  supplying  the water.   Continue 

Page 77: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐25 

application  of  chlorine  until  the  entire  line  being  treated  is  filled  with  the chlorine solution.   

8. Final Flushing:  Conduct final flushing in accordance with AWWA C651. a) After applicable retention period,  flush heavily chlorinated water  from 

the  line  until  chlorine  concentration  in  water  leaving  the  main  is  no higher than that generally prevailing in the system, or less than 2 mg/l.  Unless special approval is obtained from City Engineer, all water shall be flushed  through  de‐chlorinating  diffusers  rated  to  remove  the appropriate  chlorine  concentration  (Arden  Industries’  Bazooka  with Liquid Calcium Thiosulfate Feed or pre‐approved equal).  The City may, at  its  option,  provide  such  devices  to  the  Contractor while  the  line  is flushed.    The  Contractor must  contact  the  Inspector  prior  to  flushing any water from the newly constructed line.  The Inspector shall provide de‐chlorinating  diffuser(s)  to  the  Contractor  before  flushing.    If  no diffusers are available through the city, the Contractor shall be required to provide diffusers.  The Inspector shall approve the flushing location.  The Inspector shall also check the chlorine level in the main before final flushing.  If the residual chlorine level is out of the effective range of the de‐chlorinating  diffuser,  the  Inspector  shall  require  the  Contractor  to wait until the residual level has dropped to within the range of the de‐chlorinating diffuser before flushing. 

b) In the alternative, but only with special approval from the City Engineer, neutralizing  chemicals may be applied externally as  the water  reaches the ground.  Perform such flushing only at sites where City Engineer has approved.    If  no  approved  point  of  discharge  is  available,  neutralizing chemicals  must  be  applied  to  the  water  in  order  to  neutralize  the chlorine  residual.    The  amount  of  chemicals  required  to  neutralize various residual chlorine concentrations in 100,000 gallons of water are shown in Table V. 

c) Flushing Velocity:  The velocity of water used to flush the line shall be at least  2  fps.    The  flow  rates  required  to  produce  this  velocity  varies depending  on  pipe  diameter.    To  approximate  this  velocity,  refer  to Table  VI  to  select  the  proper  number  of  taps  or  2‐½”  Fire  Hydrant Nozzles to open at the end of the line. 

d) Minimum  Flushing  Time:    At  minimum,  the  line  shall  be  flushed  to remove two complete volumes of water through the newly constructed pipeline,  approximately  7  minutes  per  500  ft.    The  Disinfection, Flushing,  and  Pressure  Testing  Worksheet  presents  the  minimum flushing time for various lengths of pipe. 

e) Additional Flushing:   After  flushing pipe for minimum time specified  in Item  d,  check  for  trapped  air  at  Air  Release  Valves,  Blow‐offs  and services  at  high  points.    Verify  that  all  mud,  air  cloudiness,  or  other discoloration  is  absent  from  flushing  stream.    If  such  problems  exist, continue to flush line until the stream is clear. 

Page 78: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐26 

f) Once  a  line  has  been  flushed,  test  to  make  certain  that  the  residual chlorine in the water is within acceptable limits. 

g) It must be noted  that  flushing  is  no  substitute  for  taking preventative measures  before  and  during  the  laying  of  water  lines.    Certain contaminants – especially those in caked deposits – are difficult or even impossible  to  remove  by  flushing,  no  matter  how  high  the  velocity.  Furthermore, in pipe with diameters of 16” or more, it can be difficult to achieve even the minimum recommended flushing velocity of 2.5 fps. 

 

TABLE V ‐ REQUIRED CHEMICALS TO NEUTRALIZE CHLORINE CONCENTRATION (PER 100,000 GALLONS OF WATER) 

Residual Chlorine

Concentration (mg/L)

Sulfur Dioxide (SO2) lb 

Sodium Bisulfite (NaHSO3) 

lb 

Sodium Sulfite (Na2SO3) 

lb 

Sodium Thiosulfate (Na2S2O3‐5H2O) lb 

1  0.08  1.2  1.4  1.2 

2  1.7  2.5  2.9  2.4 

3  8.3  12.5  14.6  12.0 

4  41.7  62.6  73.0  60.0 

   

TABLE VI ‐ MINIMUM NUMBER OF OPENINGS TO PRODUCE 2.5 FPS. (AT 40 PSI RESIDUAL) 

Pipe Diameter (in)

Number of 1" Taps 

Number of 2” Taps 

Number of 2‐1/2” FH Nozzles 

2  1  ‐‐‐  ‐‐‐ 

4  1  1  1 

6  ‐‐‐  1  1 

8  ‐‐‐  1  1 

10  ‐‐‐  2  1 

12  ‐‐‐  2  2 

16  ‐‐‐  4  2 

24  ‐‐‐  ‐  4 

30  ‐‐‐  ‐‐‐  6 

36  ‐‐‐  ‐‐‐  8 

 9. Bacteriological Testing: 

a) After  a water  line has  undergone  final  flushing but before  it  is  placed into service, collect a sample for bacteriological testing from the end of that line.  In the case of extremely long lines, take additional samples if the  Owner  so  directs.    Bacteriological  samples  shall  be  collected  at approximately  2,500‐foot  intervals  with  samples  near  the  beginning point  and  at  the  end  point  of  each  section  of  line.    Where  sanitary 

Page 79: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐27 

conditions were not maintained before, during or after construction, an additional  bacteriological  sample  shall  be  collected  from  a  location representing  the  water  from  the  contaminated  area.    Unsanitary conditions include failure to document sanitary handling of materials, to conduct  construction  inspections  and  to  maintain  records,  and  to document sanitary practices during construction and other hazards such as trench flooding during construction. 

b) Collect these samples in sterile bottles treated with sodium thiosulfate.  Fire  hydrants  shall  be  used  to  take  samples.    Other  locations may  be utilized if no fire hydrant is available. 

c) Samples  will  be  collected  by  water  plant  personnel  to  be  tested  for bacteriological quality in order to determine if they contain any coliform organisms.   The sample  is required to be taken 48 hours after flushing all new pipelines.    If the initial disinfection fails to produce satisfactory samples, repeat disinfection until satisfactory samples are obtained. 

d) When  the  samples  tested  are  found  to  be  satisfactory,  the water  line may be placed in service. 

e) The  Contractor  shall  fill  out  and  sign  a  Disinfection,  Flushing,  and Pressure  Testing  Worksheet  provided  by  the  City  documenting adherence  to  the  Standard  Specifications.  Contractor  shall  obtain  a blank  worksheet  from  the  City  Engineer’s  Office  upon  issuance  of  a construction  permit.    The  Contractor  shall  complete  the  worksheet during  the  construction  process  and  present  a  signed  copy  to  the Inspector  prior  to  bacteriological  testing.    If  improper  or  inadequate documentation  is  presented,  the  Contractor  shall  be  deemed  to  have failed  to  follow  the  specifications  and  shall  be  required  to  follow  the cleaning and chlorination procedures specified in Paragraph 2.05. 

 SECTION B AND C  BELOW ARE  FOR AUTHORIZED  CITY  PERSONNEL OR  CONTRACTORS WORKING UNDER DIRECT SUPERVISION OF  AUTHORIZED CITY PERSONNEL.  

B. Positive Pressure Method: 1. Contact  Tennessee  One  Call  to  have  all  other  utilities  located;  notify  Service 

Department and Water Treatment Plant of areas affected. 2. All  attempts  will  be made  to  repair  line  under  “wet”  conditions  to  avoid  or 

eliminate possible contaminants from entering the system. 3. Close nearest isolation valves on the downstream side of the leak. Reduce the 

flow from the upstream side of the leak by throttling back the remaining valve, leaving positive pressure on the line.   DO NOT OPEN ANY FIRE HYDRANTS TO REDUCE LINE PRESSURE PRIOR TO OPENING THE TRENCH TO A DEPTH OF AT LEAST  18‐INCHES  BELOW  THE  LINE.  This  will  prevent  contaminants  from entering the system. Complete the repair trench excavation. 

4. After  excavation  of  the  repair  trench  is  complete  (to  a  depth  of  at  least  18‐inches below  the  line)  close  the  remaining  valve  after  removing  the  standing 

Page 80: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐28 

water  to  fully  expose  the  pipe  360  degrees.    Treat  any  standing  water  now remaining in the repair trench with ½ oz. of Granular Chlorine (62% purity) for every one hundred gallons of trench water to achieve a 25‐ppm solution.  

5. To ensure a clean repair, inspect around the pipe in and near the damaged area and remove any debris, soil, or other material from the damaged area.  Swab or spray the damaged area of  the pipe and  interior of all  repair clamps or other appropriate  devices  with  a  1%  hypochlorite  solution  (5.2  fluid  oz.  of  6.15% bleach/quart of water) before installation.  Complete the repair. 

6. Open  the  appropriate  valve(s)  and  flush  the  water  main  toward  the  repair location from both directions  if valve and hydrant  locations permit.   Continue flushing  until  all  discolored  water  is  eliminated  and  a  satisfactory  chlorine residual is reached. 

7. Before the water main is returned to full service, collect a single water sample at a point nearest the repaired section.  If direction of flow can be determined, the  sample  should  be  collected  from  downstream  of  the  break  repair.    If direction  of  flow  cannot  be  determined,  samples  should  be  collected  from above and below the break repair.   These samples should be coded “D”.   This sample is to be delivered as soon as possible to the Water Treatment Plant for bacteriological testing. 

8. Check all valves to insure they have been returned to the open position. 9. If  the  test  results  are  negative,  the  test  results  will  serve  as  a  record  of 

compliance and no future work is required.  10. Fill out all appropriate forms indicating disinfection procedures.  11. If the test results are positive, then additional sampling should be undertaken 

immediately.  A total of three (3) additional samples should be taken. The first additional sample should be taken from the original sampling location and the other  two  additional  samples  should  be  taken  above  and  below  the  original sampling  location.    These  three  samples  should  be  coded  “R”.    If  all  three samples are negative, then no further work is required.  If any of the additional samples is positive, then follow the normal repeat monitoring procedure. 

 C. Dewatered Method:  If it is not possible to maintain positive pressure as stated above 

and  the  pipe must  be  dewatered  prior  to  opening  and  preparing  the  repair  trench, then the entire section of pipe must be disinfected in accordance with Section 6 of this document (Slug Method), which is derived from Section 4.7.4 of AWWA C651‐99. 1. Contact Tennessee One Call to have all other utilities located; notify the Service 

Department and Water Treatment Plant of areas affected. 2. Close the nearest isolation valves on all sides of main break. 3. If there are customers in the isolated area, turn off all services at the lock wing 

on  the meter  yokes.    Remove  the meters.  This  will  prevent  the  disinfectant from entering the customer’s premises. 

4. In order to lessen the possibility of additional contaminates from entering the exposed line, after excavation of the repair trench is complete, pump the water down below the main line.  Treat the standing water in the repair trench with ½ oz.  of  granular  chlorine  for  every  one  hundred  gallons  of  trench  water  to 

Page 81: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐29 

achieve a 25‐ppm solution. 5. Clean the area around the pipe. Swab or spray the interior of all repair pipe and 

fittings  with  a  1  percent  hypochlorite  solution  (5.2  fluid  oz.  of  6.15% bleach/quart of water) before installation. 

6. The  line  should be properly disinfected by  the  slug method  (see Appendix C) using a chlorine dosage of 100 mg/L and a contact time of at least 3 hours for areas where service connections are present. 

7. In areas where no service connections exist the line can be properly disinfected by the slug method using a chlorine dosage of 300 mg/L and a contact time of at least 15 minutes. 

8. After  the  disinfectant  has  been  added  to  the  line  by  using  a  sodium hypochlorite  solution  or  calcium  hypochlorite  granules,  an  upstream  valve should be opened slightly, along with an opened downstream hydrant, to allow air and highly discolored contaminated water to be removed.  The slow flowing concentrated slug will gradually move through the pipe allowing all parts to be exposed to the disinfectant.  

9. Once the highly discolored contaminated water has been flushed, the valve and flushing  hydrant  should  be  closed  to  allow  for  the  prescribed  disinfectant contact time. 

10. After  the  prescribed  contact  time  has  been  reached,  prepare  to  treat  (de‐chlorinate) the highly chlorinated water to be flushed from the isolated line if there  is  a  possibility  that  the  discharge  will  cause  any  damage  to  the environment.  

11. Open  the  upstream  valve  and  the  downstream  hydrant  and  flush  until  all discolored water is eliminated, de‐chlorinating the discharge if necessary.  Test for  highly  chlorinated  water  remaining  in  the  line  and  continue  flushing  if necessary until elimination is successful and the concentration is no higher than that in the prevailing water in the surrounding area. 

12. Before the water main is returned to full service, collect a single water sample at a point nearest the repaired section.  If direction of flow can be determined, the  sample  should  be  collected  from  downstream  of  the  break  repair.    If direction  of  flow  cannot  be  determined,  samples  should  be  collected  from above and below the break repair.   These samples should be coded “D”.   This sample is to be delivered as soon as possible to the Water Treatment Plant for bacteriological testing. 

13. Open  the  customer’s  services  at  the  lock  wings  and  flush  the  service  lines. Reinstall meters. 

14. Open the remaining valves in the isolated area. 15. Flush the area again at the highest hydrant in the area to insure the elimination 

of any discolored water. 16. If  the  test  results  are  negative,  the  test  results  will  serve  as  a  record  of 

compliance and no future work is required. 17. Fill out all appropriate forms indicating disinfection procedures.  18. If the test results are positive, then additional sampling should be undertaken 

immediately. A total of three (3) additional samples should be taken.  The first 

Page 82: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐30 

additional sample should be taken from the original sampling location and the other  two  additional  samples  should  be  taken  above  and  below  the  original sampling  location.    These  three  samples  should  be  coded  “R”.    If  all  three samples are negative, then no further work is required.  If any of the additional samples is positive, then follow the normal repeat monitoring procedure. 

 

 

 

 

Page 83: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐31 

 

 

DISINFECTION, FLUSHING AND PRESSURE TESTING WORKSHEET(MANDATORY BEFORE BACTERIOLOGICAL TESTING)

PRESENT TO INSPECTOR

Date:

Project Name:

Material: PVC D.I. Size:

Length of Section:

Contractor:

Instructions:

1. This worksheet references the Granular Method in the City of Clarksville's Standard Specifications.

2. This worksheet must be properly filled out and presented to inspector before bacteriological testing.

3. Use one worksheet per test section. If test pit is moved, use a new sheet. If pipe diameter changes, use a new sheet.

A. DISINFECTION

1. Select Granular Chlorine 2. Select Number of 3. Calculate Total Granular Chlorine Dose Size Doses Needed

x oz.Pipe Dia (in) Dose Size (oz) Pipe Length (ft) No. of Doses

Dose Size No. of

2 0.5 500 1 (Table 1) Doses

4 2 1000 2 (Table 2)

6 4 1500 38 7 2000 4

10 11 2500 512 16 3000 616 28 3500 724 63 4000 830 99 4500 936 142 5000 10

1. Check granular chlorine container for CGW approval (62% purity, NSF stamp)

2. Place 1 dose at the beginning of the line

3. Place 1 dose every 500 feet during construction

4. After construction, install test pit (back flow/meter assembly by sleeving into the line)

5. Partially open valve at test pit

6. Adjust valve to slowly fill line

7. Open blow-offs, services, and air release valves at high points to remove air

8. Allow water to sit for at least 24 hours

CGW- ___________________ WS- ___________________

Page 84: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐32 

 

B. FLUSHING 1. Select Number of Flushing Ports 2. Select Minimum Flushing Time 3. Select Flushing Location (circle below) (circle below) (list below)

Pipe Dia (in)

No. of 1" Taps

No. of FH Nozzles

2 1 - - 500 74 1 1 1 1000 146 - 1 1 1500 208 - 1 1 2000 27

10 - 2 1 2500 3412 - 2 2 3000 4016 - 4 2 3500 4724 - - 4 4000 5430 - - 6 4500 6036 - - 8 5000 67

4. Contact Inspector and attach dechlorinating diffuser (provided by Inspector) to each flushing port and open. 5. Fully open valve at test pit. 6. Flush for time selected in Step 2. 7. Check for trapped air at ARV's, blow-offs and services at high points.

8. Check for mud, air, and cloudiness (flush until clear).

C. PRESSURE TESTING 1. Apply 200 psi maximum test pressure (measured at pit or lowest point) through test pit. 2. Fix all defective parts of water line according to Standard Specifications

3. Call Inspector to witness pressure test.

4. The pressure held at _________ psi for __________ hrs.Inspector's Initials

D. SAMPLING PORTS 1. Provide smooth copper brass sampling taps and spacing described in Standard Specifications or required by City's Distribution Operator.

No. of Taps

E. SKETCH Attach a simple sketch identifying this section of test pit location, line, sampling location, flushing locations, and chlorine dosing locations.

F. BACTERIOLOGICAL TESTING 1. Sign statement below. 2. Call inspector for bacteriological testing.

G. STATEMENT I certify that the above information is correct and this water is ready to be tested by the City's DistributionOperator for bacteriological contamination.

Contractor's Authorized Signature

No. of 2” Taps

Pipe Length (ft)

Min. Flush Time (min)

Page 85: Standard Water and Sewer Specifications PDF

  WATER DISTRIBUTION SYSTEMS  02713‐33 

 

END OF SECTION  

TABLE OF CONTENTS

DISINFECTION, FLUSHING AND PRESSURE TESTING SKETCH

INCLUDES THE FOLLOWING FEATURES:

Test Pit Sample Ports Chlorine Dosing Locations North Arrow

Flush Ports Water Line Street Names Other Info

Page 86: Standard Water and Sewer Specifications PDF
Page 87: Standard Water and Sewer Specifications PDF

  FIRE SERVICE WATER METERS  02715‐1 

SECTION 02715  

FIRE SERVICE WATER METERS  

TABLE OF CONTENTS  PART 1 – GENERAL  1.01  WORK INCLUDED  

Installation of fire service meters, vaults and related appurtenances as shown on the Contract Drawings. 

 1.02  RELATED WORK  

Section 02713:  Water Distribution Systems   PART 2 – PRODUCTS  2.01  COLD WATER METERS/FIRE SERVICE COMPOUND METER TYPE  

A. General:  The City of Clarksville shall issue all fire service meters in exchange for a fee payable  at Gas  and Water Department  Service  Center.  All meters  furnished  shall  be manufactured by  a  registered  ISO  9001 quality  standard  facility.    Acceptable meters shall have a minimum of five years of successful field use.  All specifications shall meet or exceed the latest revision of AWWA C703. 

 B. Type:  Meters shall consist of a combination of an AWWA Class II in‐line horizontal axis 

turbine  for measuring  high  rates  of  flow  and  a  positive  displacement  bypass meter conforming to AWWA C700 for measuring low rates of flow.  An automatic valve shall direct the flow from the bypass meter to the mainline meter as flow rates increase and back  to  the  bypass  meter  as  flow  rates  decrease.    All  components  of  the  meter assembly shall be both UL (Underwriter’s Laboratory)  listed and FM (Factory Mutual) approved for fire service use. 

 C. Capacity:   The capacity of  the meters  in  terms of normal operating  range, maximum 

rate for continuous use, maximum loss of head, and extended low flow capability shall be as provided in the following table: 

 

Size (inches) 

Normal Operating Range (gpm) 

Maximum Rate for Continuous Use 

(gpm) 

Maximum Loss of Head at Max Rate (psi) 

Extended Low Flow (gpm) 

4”  ¾ ‐ 1200  1200  9  3/8 

6”  1 ½ ‐ 2500  2500  10.5  3/4 

8”  2 – 4000  4000  10.5  1 

10”  2 ‐ 6500  6500  9  1 

Page 88: Standard Water and Sewer Specifications PDF

  FIRE SERVICE WATER METERS  02715‐2 

D. Case and Cover 1. The meter body, strainer body, and valve body shall be fabricated steel with a 

coating of fusion‐bonded epoxy both internally and externally.  The meter body shall  be welded  to  the  valve body effecting  a uni‐body  construction with  the valve.    The  strainer  outlet  and meter  inlet  shall  be  connected  by  a  Style  77 Victaulic  or  other  UL  Listed/FM  Approved  grooved  coupling.    The  meter assembly shall have a rated working pressure of 175 psi. 

2. The meter cover shall be cast of lead free brass containing a minimum of 85% copper such as EnviroBrassTM  II.  An arrow indicating direction of flow shall be cast  in  raised  characters on  the  cover.    The  cover  shall  have a  rated working pressure of 175 psi.  The cover shall contain a calibration vane for the purpose of calibrating the turbine measuring element while in‐line and under pressure.  The calibration vane shall be mounted under the register that is attached in a tamper‐resistant manner. 

 E. Strainer 

1. Meters  shall  be  supplied  with  a  strainer  designed  and  approved  for  the  fire service used by UL and FM, and shall have a rated working pressure of 175 psi. 

2. The  Strainer  shall  be  constructed  of  steel  and  coated  with  fusion‐bonded epoxy.    The  strainer  basket  shall  be  constructed  of  AISI  Type  18‐8  stainless steel.    The  strainer  shall  contain  a  flushing  port  located  near  its  bottom  to facilitate easy cleaning. 

 F. External Bolts:   Meter cover bolts shall be made of AISI Type 316 stainless steel.   All 

other bolts shall be zinc‐plated steel or stainless steel.  

G. Connections:  Inlet and outlet flanges shall be rounded flanged per AWWA C207, Class D. 

 H. Registers:    Registers  shall  be  permanently  roll‐sealed,  straight  reading  in  gallons. 

Registers shall include a center‐sweep test hand and low flow indicator.  Registers shall be removable for replacement without interruption of the service line. 

 I. Register Boxes:  Register boxes and covers shall be of bronze composition.  The name 

of  the  manufacturer  and  the  meter  serial  number  shall  be  clearly  identifiable  and located on the register box covers. 

 J. Register Box Sealing:  The register box shall be affixed to the top cover by means of a 

plastic tamper‐proof seal pin that must be destroyed in order to remove the register.  

K. Meter Serial Number:  The meter serial number shall be on the meter flange or cover and on register box covers. 

 L. United  Measuring  Element:    A  UME  is  a  complete  assembly,  factory  calibrated  to 

AWWA Standards that include the cover, registers, and a turbine measuring element.  

Page 89: Standard Water and Sewer Specifications PDF

  FIRE SERVICE WATER METERS  02715‐3 

It  shall  be  easily  field  removable  from  the meter  body  without  the  requirement  of unbolting flanges. 

 M. Intermediate Gear Train:  The intermediate gear train shall be directly coupled to the 

turbine rotor and magnetically coupled to the register through the meter cover.   The gear train shall be housed within the turbine measuring chamber.  All moving parts of the  gear  train  shall  be made of  a  self‐lubricating  polymer or  AISI  Type  316  stainless steel for operation in water. 

 N. Bypass Meter:    The  bypass meter  shall  be  of  a  positive  displacement,  nutating  disc 

type.   The bypass meter may be piped on the left or right side of the assembly.   The bypass meter shall conform to AWWA C700 standards in the following sizes:  

Mainline Size  Bypass Meter Size 

4 inches  1 inch 

6 inches  1‐½ inches 

8 inches  2 inches 

10 inches  2 inches 

 O. Automatic Valve 

A. The  automatic  valve  shall  be  of  the  spring‐loaded,  knuckle‐joint  type.    All internal  linkage  parts  shall  be  stainless  steel.  A  vulcanized  rubber  disc  on  a stainless steel clapper plate shall seal against a bronze seat.   The springs shall be AISI Type 18‐8 stainless steel. 

B. The disc meter shall include a self‐actuated valve that directs flow through the disc meter at low flow rates, and through the turbine meter at high flow rates.  At  high  flow  rates,  the  self‐actuated  throttle  valve  shall  restrict  the  flow through the disc meter to minimize wear. 

 P. Registration Accuracy:  Registration accuracy over the normal operating range shall be 

98.5% to 101.5%.  

Q. Acceptable meters shall be Neptune HP PROTECTUS ® III or approved equal.  

R. To prevent cross connections, comply with the City’s “Cross Connection Control Policy and Program”. 

  PART 3 – EXECUTION  3.01  GENERAL INSTALLATION REQUIREMENTS  

A. Install meter  in an 8’x 6’x 6’ pre‐cast, reinforced concrete vault by Cloud Concrete or equal  as  shown  in  the  City’s  Standard  Detail  Drawing.    The  bottom  of  the  meter assembly  shall  be  located  a minimum  of  6‐inches  above  the  floor  of  the  vault.  The 

Page 90: Standard Water and Sewer Specifications PDF

  FIRE SERVICE WATER METERS  02715‐4 

vault  shall  be  installed  in  a  grassed  or  landscape  area.    If  no  such  area  exists,  upon prior approval from City Engineer, the vault may be placed in the edge of parking lots or sidewalk where only occasional wheel loadings may occur.  In all instances the vault shall  be  protected  from  traffic.  Such  protections  shall  include  concrete  filled  steel bollards or other approved method. 

 B. Vault shall be self‐draining by gravity sump or sump pump. 

 C. Meter assembly shall include a bypass line. 

 D. The  vault  shall  include  a  72”  x  48”  Halliday  Products Model  H2W7248  (H‐20 wheel 

loading  rated)  Double  Leaf  aluminum  access  door  with  spring  assist  and  lock.    The hatches  shall  be  offset  to  provide  accessibility  to  the  steps,  as  shown  in  the  City’s Standard Detail Drawing.  

E. Each installation shall have steps conforming to ASTM C478.  The steps shall be made of copolymer polypropylene plastic conforming to the latest revision of ASTM D‐4101 and  shall  have  a  ½‐inch  diameter  Grade  60  Steel  reinforcing  rod meeting  the  latest revision of ASTM A615 through its center.   Each step shall be 12  inches  in width and capable of supporting a load of 1,000 pounds in the center of the step when projected 6  inches  from  the  wall.    Each  step  shall  be  equipped  with  non‐skid  grooves.    Rung spacing  shall  be  12  inches.    The  location  of  the  steps  shall  be  coordinated with  the access hatch offset so that the steps are easily accessible.    

F. Piping shall be ductile iron Class 350 with flanged ends inside the vault.  All other joints and fittings shall be mechanically restrained (see Section 02713, Paragraph 3.09).  

G. Pipe and meter shall be adequately supported to prevent transmitting stress to meter or pipe.  Concrete blocks or bricks stacked beneath pipe will not be acceptable.  

H. A post indicator valve, Mueller A20806, or approved equal shall be used between the valve pit and customer’s building.  

I. The by‐pass line shall include gate valve with locking top valve box Tyler Union Box 91‐C or approved equal.  

J. Gate valves shall also be placed at the City main and on either side of the meter (just outside the pit) 

 END OF SECTION 

 TABLE OF CONTENTS

Page 91: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐1 

SECTION 02722  

SANITARY SEWER SYSTEMS  

TABLE OF CONTENTS  PART 1 – GENERAL  1.01  WORK INCLUDED  

The work  included  in  this  Section  includes  the  installation  and  testing of  sanitary  sewerage systems.    All  sanitary  sewerage  systems  shall  conform  to  the  design  and  construction standards  promulgated  by  the  Tennessee  Department  of  Environment  and  Conservation (TDEC). 

 1.02  RELATED WORK  

A. Section 02221:  Trenching, Bedding and Backfilling  

B. Section 11200:  Sewer Valves  1.03  DELIVERY, STORAGE AND HANDLING  

Care  shall  be  exercised  in  the  delivery,  storage  and  handling  of  all  materials  prior  to  their incorporation  into  the  work.    Follow  all  manufacturers’  recommendations  for  delivery  and storage (except where these specifications differ).  Acceptance of questionable material shall be  based  solely  on  the  City  Engineer’s  interpretation  of  fabrication,  delivery,  storage  and installation practices of the material in question. 

  PART 2 – PRODUCTS  2.01  GENERAL  

New sanitary sewer pipe may generally be constructed of PVC pipe as specified in Paragraphs 2.02 and 2.03 of this Section, with the following exceptions: 

 A. Sanitary sewers shall be specially coated and lined ductile iron pipe where indicated on 

the Contract Drawings.  

B. Open cut sanitary sewers crossing drainage ditches and swales, storm drain discharge, wet weather  streams, USGS blue‐line  streams,  and other  erosive environments  shall be  specially  coated  and  lined  ductile  iron  pipe  and  will  be  provided  with  concrete encasement. 

 

Page 92: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐2 

C. Sanitary sewers with less than the required 36 inches of cover in non‐traffic areas and 48 inches in areas subject to vehicular traffic shall be specially coated and lined ductile iron pipe. 

 D. Sanitary  sewers  installed  at  depths  greater  than  20  feet  shall  be  constructed  of 

specially coated and lined ductile iron pipe.  

E. Where  sanitary  sewers  are  installed  in  new  fill,  a  compaction  letter  sealed  by  a Geotechnical Engineer registered in the State of Tennessee shall be submitted to the Owner  prior  to  accepting  said  utilities.    An  acceptable  compaction  letter  shall  state that field density testing  indicates the fill has been compacted to at  least 95% of the maximum dry density according to the Standard Proctor.  If a compaction letter is not available,  special  protection  such  as  replacement  with  ductile  iron  pipe  with  joint restraint shall be required. 

 F. Where additional pipe protection  is  required due  to  loads,  insufficient  cover, erosive 

environments, crossing other utilities, etc., specially coated and lined ductile iron pipe, restrained  joints,  concrete  encasement  and  other  methods  shall  be  required  as directed by the City Engineer. 

 G. Pipe material for sanitary sewers larger than 24 inches in diameter shall be determined 

on a case‐by‐case basis by the City Engineer.  

H. Sanitary sewer pipe installed by horizontal directional drilling shall be HDPE pipe unless otherwise approved by the City Engineer.  See Section 02727 for product specifications of HDPE pipe. 

 2.02  POLYVINYL CHLORIDE (PVC) GRAVITY SEWER PIPE  

A. Manufactured  from  virgin,  National  Sanitation  Foundation  (NSF)  approved  resin conforming to ASTM D1784, suitable for use as a gravity sewer conduit with provisions for contraction and expansion at each joint, with a rubber ring and standard lengths of 20‐feet and 12.5‐feet plus or minus one (1) inch. 

 B. Joints shall meet  the requirements of ASTM D3212.    Joint design shall be tested and 

certified  to  result  in  no  leakage  under  prescribed  laboratory  test  conditions  of  joint alignment,  load  conditions,  pressure  and  vacuum,  and  deflection.    Pipe  and  fittings shall have  integral bell with elastomeric  seal  joint.   The gaskets used  for  joining PVC sewer pipe shall conform to ASTM F477. 

 C. PVC  gravity  sewer  main  pipe  8  inches  to  15  inches  in  diameter  shall  meet  and/or 

exceed the requirements of ASTM D3034, SDR 35.  PVC gravity sewer pipe installed at depths greater than 12 feet shall conform to SDR 26. 

 D. Large diameter PVC gravity sewer main pipe 18  inches to 30  inches  in diameter shall 

Page 93: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐3 

meet and/or exceed  the  requirements of ASTM F679, SDR 35 or PS 46.   PVC gravity sewer pipe installed at depths greater than 12 feet shall conform to SDR 26 or PS 115.  

E. Gravity sewer mains shall be at least 8 inches in diameter.  

F. All PVC gravity service line pipe and fittings from the sewer main to the sewer cleanout assembly shall conform to SDR 35 unless depth exceeds 12 feet, in which case service lines and fittings shall conform to SDR 26.  

G. Color of PVC gravity sewer pipe shall be green.  

H. All  PVC  gravity  sewer  pipe  shall  be  clearly  marked  with  the  manufacturer’s  name, nominal diameter, SDR, ASTM designation, and NSF approval seal. 

 2.03  POLYVINYL CHLORIDE (PVC) PRESSURE SEWER PIPE, FITTINGS AND PEXa SERVICES  

A. Manufactured  from virgin National  Sanitation  Foundation  (NSF)  approved  resin,  PVC 1120 made from PVC compounds 12454‐A or 12454‐B as defined in ASTM D1784. 

 B. PVC pressure sewer pipe 4  inches to 12 inches  in diameter shall meet and/or exceed 

the requirements of ASTM D2241, SDR 21, Pressure Class 200 or AWWA C900, DR14, Pressure Class 200.  PVC pressure sewer pipe 14 inches to 24 inches in diameter shall meet and/or exceed the requirements of AWWA C905, DR18, Pressure Class 235. 

 C. PVC  pressure  sewer  pipe  shall  have  bell  and  spigot  push‐on  joints manufactured  in 

accordance with ASTM D3139.  The bell shall consist of an integral wall section with a solid cross‐section elastomeric gasket securely locked in place to prevent displacement during  assembly.    The  gasket  shall  be  reinforced  with  a  steel  band  or  other  rigid material  and  shall  conform  to  ASTM  F477.    The  gasket  and  annular  groove  shall  be designed and shaped so  that when the  joint  is assembled,  the gasket will be radially compressed  to  the  pipe  and  locked  in  place  against  displacement,  thus  forming  a positive seal. 

 D. Color of PVC pressure sewer pipe shall be green. 

 E. All  PVC  pressure  sewer  pipe  shall  be  clearly marked with  the manufacturer’s  name, 

nominal  diameter,  type  of material,  SDR or  Class,  ASTM or AWWA designation,  and NSF approval seal. 

 F. All fittings for PVC pressure sewer mains shall be ductile iron with mechanical joints as 

described in Paragraph 2.04 of this section.  The gaskets shall be duck‐tipped transition gaskets for use with PVC pipe.  All adaptors, fittings and transition gaskets necessary to connect ductile iron fittings to PVC shall be furnished. 

 G. Sewer force main service material shall be Municipex crosslinked polyethylene (PEXa) 

Page 94: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐4 

by Rehau and shall be green in color.  

H. Where compression fittings are used on Municipex pipe, insert stiffeners are required to ensure a proper connection is made.  Plastic insert stiffeners are to be used where pipe is less than 2 inches in diameter and stainless steel insert stiffeners are to be used where pipe is 2‐inch diameter and larger. 

 2.04  DUCTILE IRON SEWER PIPE AND FITTINGS  

A. Ductile  iron  gravity  sewer  pipe  shall  conform  to  the  latest  revisions  of  ASTM  A746, ANSI/AWWA C151/A21.51 and ANSI/AWWA C111/A21.11. 

 B. Ductile iron pressure sewer pipe shall conform to the latest revisions of ANSI/AWWA 

C151/A21.51 and ANSI/AWWA C111/A21.11.  C. Unless otherwise specified or shown on the Contract Drawings, ductile iron sewer pipe 

shall be Pressure Class 350 for sizes 12‐inch and smaller.  Sizes 14‐inch and larger shall be Pressure Class 250.  

D. Unless otherwise specified or shown on the Contract Drawings, ductile iron sewer pipe shall  be  furnished  with  push‐on  joints,  with  mechanical  joint  fittings  and  valves.  Exposed piping shall be flanged.  

E. Ductile  iron  sewer  pipe  shall  be  specially  coated  and  lined  as  detailed  in  Paragraph 2.05 of this Section.  

F. All  pipe  shall  be  new  and  shall  have  the  manufacturer’s  name,  AWWA  or  ASTM designation, weight, pressure class and nominal diameter stamped on the outside of each pipe.  

G. Standard and special fittings shall be mechanical joint ductile iron fittings meeting the requirements  of  ANSI/AWWA  C110/A21.10  or  ANSI/AWWA  C153/A21.53,  as applicable.    Fittings  shall  have  a  pressure  rating  of  350  psi  for  24‐inch  and  smaller piping.   Fittings shall at a minimum have the same pressure rating as the connecting pipe.   Ductile iron fittings shall be specially coated and lined as detailed in Paragraph 2.05 of this Section. 

 2.05  SPECIAL COATINGS AND LININGS FOR DUCTILE IRON PIPE AND FITTINGS  

A. All  ductile  iron pipe  and  fittings  shall  be  coated outside with  a minimum 1 mil‐thick bituminous coating per AWW C151 for ductile iron pipe, AWWA C115 for flanged pipe and AWWA C110 and C153 for fittings.  

B. All ductile iron pipe and fittings shall be lined with 40 mils nominal dry film thickness of “Protecto 401 Ceramic  Epoxy.”    The  lining material  shall  be  an  amine  cured novalac 

Page 95: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐5 

epoxy containing at least 20% by volume of ceramic quartz pigment.    

C. Lining  application  shall  be  performed  by  an  applicator  approved  by  the  coating manufacturer,  in  accordance  with  the  manufacturer’s  instructions  and  under controlled conditions at the applicator’s shop or the pipe manufacturer’s plant.    

D. All  ductile  iron  pipe  and  fitting  linings  shall  be  inspected  in  accordance  with  the manufacturer’s  recommendations.    The  pipe  or  fitting  manufacturer  shall  submit  a certified  affidavit  of  compliance  with  the  manufacturer’s  instructions  and requirements specified herein. 

 2.06  JOINT RESTRAINT DEVICES  

A. Mechanical Joint Restraint Devices 1. All mechanical joint fittings and valves shall be restrained at each opening with 

approved  mechanical  joint  restraint  devices.    Restrained  fittings  do  not eliminate  or  replace  the  requirement  for  sufficient  concrete  thrust  blocking and/or restrained pipe joints. 

2. Restraint devices for joining plain end pipe to mechanical joint fittings, pipe and valves  shall  consist  of multiple  gripping wedges  incorporated  into  a  follower gland  meeting  the  applicable  requirements  of  ANSI/AWWA  C111/A21.11  for PVC pipe or ANSI/AWWA C110/A21.10 for ductile iron pipe. 

3. Devices for PVC pipe shall have a working pressure rating equal to that of the pipe  on which  it  is  used.    Ratings  are  for water  pressure  and must  include  a minimum safety factor of 2:1. 

4. Devices for ductile iron pipe shall have a working pressure rating of 350 psi for 3 to 16 inch and 250 psi for 18 inch and larger.  Ratings are for water pressure and must include a minimum safety factor of 2:1. 

5. Gland body, wedges and wedge actuating components shall be cast from grade 65‐45‐12 ductile iron material in accordance with ASTM A536. 

6. Mechanical  joint  restraint  shall  require  conventional  tools  and  installation procedures  per  AWWA  C600,  while  retaining  full  mechanical  joint  deflection during  assembly  as  well  as  allowing  joint  deflection  after  assembly.    Proper actuation of the gripping wedges shall be ensured with torque limiting twist off nuts. 

7. Mechanical  joint  restraint  shall  be Megalug  Series  2000PV or Megalug  Series 1100 produced by EBAA Iron Inc. or approved equal. 

 B. Bell Restraint Harness Devices 

1. Bell restraint harnesses for push‐on joint PVC pipe shall be Series 1600, 2800, or 6500 as manufactured by EBAA Iron, Inc., Series 1350 or 1390 by Uni‐Flange, or approved equal. 

2. Bell restraint harnesses for push‐on joint ductile iron pipe shall be Series 1700 by EBAA Iron, Inc., or approved equal. 

 

Page 96: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐6 

2.07  COMPRESSION COUPLINGS  

A. When joining together dissimilar types of pipe, such as PVC and vitrified clay pipe, for repairing and rejoining sections of gravity sewer, for joining new pipe to existing pipe, and for connecting the first full  joint of pipe to a short stub through a manhole wall, compression couplings complying with ASTM C425 shall be used.   

 B. Compression  couplings  shall  be  resistant  to  corrosion  by  soil  and  sewage  and  shall 

provide a permanent watertight  joint.   The compression couplings shall be of natural or synthetic rubber or rubber‐like material and the bands for attaching the couplings shall be of stainless steel. 

 2.08  PRECAST CONCRETE MANHOLES  

A. All  precast  concrete  manholes  shall  conform  to  the  requirements  of  AASHTO  M‐199 SR and ASTM C478, including steel reinforcement. 

 B. All concrete used in connection with the construction of precast manholes shall be at 

minimum 4,000 psi concrete.  

C. The precast manufacturer shall use XYPEX additive. Xypex Admix C‐1000 Red shall be added  to  the  concrete  during  batching  at  the  manufacturer's  specified  rate.  The amount  of  cement  shall  remain  the  same  and  not  be  reduced.  Precast  concrete structures shall have a reddish tint to verify the XYPEX admix. 

 D. Base, riser and top sections shall have tongue and groove joints. 

 E. The  Contractor  may  choose  to  order  new  precast  base  sections  with  monolithic 

bottoms and inverts already formed and manhole bases and risers with pipe openings and  integrally  cast  resilient  pipe  connectors  in  place.    Manhole  steps  may  also  be provided cast‐in‐place.  It shall be the Contractor’s responsibility to provide manholes with properly located and sized pipe openings and properly formed inverts.  Manholes not constructed in accordance with the Contract Drawings are subject to rejection and replacement at no additional cost to the Owner. 

 F. Unless otherwise specified, all manholes shall have an inside diameter of not less than 

4 feet and a vertical wall height of not less than 30 inches.  Drop manholes shall be a minimum of 5 feet in diameter and 6‐foot diameter manholes shall be used on sewers 30 inches and larger. 

 G. Top sections shall be eccentric cones where cover over the pipe exceeds 4 feet.   Top 

sections shall be flat top where cover over the pipe is 4 feet or less.  

H. The clear opening in the manhole shall be not  less than 24  inches.   30‐inch diameter openings may  be  required  at  the  City  Engineer’s  discretion  in  special  circumstances 

Page 97: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐7 

such as shallow manholes less than 4 feet deep or manholes on large diameter trunk sewers. 

 I. All manholes with drop assemblies or  force main entrances shall be epoxy coated or 

utilize an interior construction such as the A‐Lok® system to prevent H2S deterioration of the manhole interior. 

 2.09  MANHOLE INVERTS  

Manhole  inverts  shall  be  constructed  of  concrete  with  a  minimum  28‐day  compressive strength of 3,000 psi.  Inverts shall be shaped so as to form a smooth, even U‐shaped channel with  curves  formed with  as  large  a  radius  as  is  permitted by  the  size of  the manhole.    The height of  the  channel  shall  be at  least ½  the pipe diameter  for pipes  less  than 15  inches  in diameter and at  least ¾  the pipe diameter  for pipes 15  inches  in diameter and  larger.    The bench shall be sloped to drain to the channel, but no more steeply than a slope of 1 in 12. 

 2.10  JOINT SEALANT FOR PRECAST MANHOLES AND WET WELLS  

Joint  sealant  for  precast  manholes  and  wet  wells  shall  provide  permanently  flexible, watertight  joints,  shall  retain  workability  over  a  wide  temperature  range,  shall  form permanent bonds to concrete substrates and shall not shrink, harden or oxidize upon aging.  Joint sealant material shall consist of pre‐molded rubber or butyl rubber.  Sealants shall meet the requirements of Federal Specification SS‐S‐210A and AASHTO M‐198. 

 2.11  CASTINGS FOR FRAME AND COVERS  

A. Castings shall be gray cast iron conforming to the requirements of ASTM A48, Class 30.  Castings shall be made accurately to the required dimensions, shall be sound, smooth, clean, free from scale, lumps, blisters and other defects.  Castings shall be machined to provide solid bearing so that covers rest securely in the frames with no rocking. 

 B. Castings shall be thoroughly cleaned before rusting begins and coated with bituminous 

paint that will produce an acceptable finish that is not affected by exposure to hot or cold weather.  

C. Standard  frames  and  covers  shall  be  traffic  duty weighing not  less  than 410 pounds and  shall  have  a  minimum  24‐inch  clear  opening.    The  covers  shall  be  the  solid indented  type  with  no  holes  except  watertight  pick  notches,  with  the  words “SANITARY  SEWER”  cast  in  raised  letters  thereon.    Standard  manhole  frames  and covers shall be John Bouchard & Sons No. 1155 or approved equal.  

D. Watertight frames and covers shall be traffic duty weighing not less than 485 pounds and shall be the double cover type with rubber gaskets.  The surface cover shall be the solid  type with  no  holes  except watertight  pick  notches, with  the words  “SANITARY SEWER” cast in raised letters thereon.  The inner cover shall be of the solid type with 

Page 98: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐8 

no holes, shall have not less than two lifting handles and shall have a neoprene sealing gasket  with  at  least  3/8‐inch  diameter  cross  section.    The  inner  cover  shall  be mechanically sealed by means of a removable steel locking bar located over the inner cover with a centrally  located stainless steel  tightening bolt.   This bolt shall be  fitted for a tee‐handle or bent‐handle that shall be included with each cover.  The bolt shall have ACME threads for durability.  The inner cover shall have appropriate reinforcing ribs  to  prevent  cracking  or  distortion  when  tightened.    The  inner  cover  shall  have sufficient clearance to allow easy installation of the cover.  Watertight manhole frames and covers shall be John Bouchard & Sons No. 1123 or approved equal.  

E. Covers shall include the City logo where directed by the City Engineer.  Covers bearing the City logo shall be furnished for all projects in the downtown Clarksville area.  

F. Covers shall be bolted to the frame where indicated on the drawings or as otherwise specified.  

G. Frame  shall  be  bolted  to  the  precast  concrete  section  with  four,  ½‐inch  diameter expansion anchor bolts.  

H. Castings with 30‐inch openings may be used in special circumstances such as shallow manholes less than 4 feet deep or manholes on large diameter trunk sewers.  Refer to City Engineer for these special applications. 

 2.12  MANHOLE STEPS  

A. Manhole steps conforming to ASTM C478 shall be made of copolymer polypropylene plastic  conforming  to  the  latest  revision  of  ASTM  D‐4101  and  shall  have  a  ½‐inch diameter  Grade  60  Steel  reinforcing  rod  meeting  the  latest  revision  of  ASTM  A615 through its center.   

 B. Each step shall be 12 inches in width and capable of supporting a load of 1,000 pounds 

in  the center of  the step when projected 6  inches  from the wall.   Each step shall be equipped with non‐skid grooves.  Rung spacing shall be 12 inches. 

 2.13  RESILIENT PIPE CONNECTIONS AT MANHOLES  

A. Resilient pipe  connectors  shall  be manufactured  in accordance with ASTM C923 and shall provide a positive watertight joint and minimum of 10 degrees deflection in any direction.   There shall be no water leakage through the connector when pipe is  in  its maximum deflected  position.    Connectors  shall  be manufactured  of  durable  rubber, which offers  superior  resistance  to water,  sewage,  oils,  acid,  ozone, weathering  and aging.    Connectors  shall  be  securely  sealed  to  the  cut  out  in  the  manhole  wall  by means of stainless steel expansion sleeves, bands or rings and to the pipe by means of stainless steel clamps or bands.  Connectors shall be KOR‐N‐SEAL as manufactured by NPC, Inc., or approved equal. 

Page 99: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐9 

 B. Compression‐type  connectors  cast  integrally  into  the manhole wall  shall  be A‐Lok or 

equal.  

C. When making a main or service connection to an existing manhole or to any manhole for which  a  factory  installed booted opening has not been provided,  a hole  shall  be cored  into  the manhole  with minimal  damage  to  the  structure  and  a  resilient  pipe connector such as KOR‐N‐SEAL installed. 

 D. When setting a manhole over an existing sewer line, the exterior of the pipe shall be 

thoroughly cleaned and a double wrap of Ram Neck or equivalent bitumastic material placed around the pipe to form a gasket over which the concrete for the new manhole base is poured, in order to form a watertight connection. 

 2.14  MANHOLE FRAME SEALS  

A. Frame  seals  shall  consist  of  a  flexible  internal  rubber  sleeve,  interlocking  extensions and stainless steel expansion bands as manufactured by Cretex Specialty Products or pre‐approved  equal.    Frame  seals  shall  be  installed  in  areas  designated  by  the  City Engineer. 

 B. The  seal  shall  remain  flexible  throughout  a  25‐year  design  life,  allowing  repeated 

vertical movement of the frame of not  less than 2  inches and/or repeated horizontal movement  of  not  less  than ½  inch.    The  sleeve  portion  of  the  seal  shall  be  double, triple, or quadruple pleated with a minimum unexpanded vertical height of 8  inches, 10  inches, or 13  inches respectively. The sleeve and extension shall have a minimum thickness  of  3/16  inches  and  shall  be  made  from  a  high  quality  rubber  compound conforming  to  the applicable material  requirements of ASTM C923, with a minimum 1500  psi  tensile  strength,  a  maximum  18%  compression  set  and  a  hardness (durometer)  of  48±5.    The  area  of  the  seal  that  compresses  against  the  manhole frame/casting and  the chimney/cone shall have a  series of  sealing  fins  to  facilitate a watertight seal.  These sealing fins shall have teardrop holes or air pockets to allow the sealing area to conform to minor surface irregularities that may be encountered. 

 C. The  expansion  bands  used  to  compress  the  sleeve  against  the  manhole  shall  be 

integrally formed from 16‐gauge stainless steel conforming to the applicable portion of ASTM C‐923, Type 304, with no welded attachments, and shall have a minimum width of 1¾ inches. 

 D. The  bands  shall  have  a minimum adjustment  range  of  2‐½  diameter  inches  and  the 

mechanism used to expand the band shall have the capacity to develop the pressures necessary  to  make  a  watertight  seal.    The  band  shall  be  permanently  held  in  this expanded position by the positive locking mechanism located on the overlapping edge of the band. 

 

Page 100: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐10 

2.15  MANHOLE ENCAPSULATION SYSTEM  

Manhole encapsulation systems may be required  in special circumstances such as manholes within 100‐year flood plains.  Where required, the manhole encapsulation system shall consist of  a  heat‐shrinkable wrap  that  is  installed  on  the  outside  surface  of  all  joints  including  the manhole  casting  to manhole  connection.    The wrap  shall be a minimum width of 12  inches and  shall  be  installed  in  accordance  with  the  manufacturer’s  recommendations.    The encapsulation system shall be WrapidSeal as manufactured by Canusa or equal. 

 2.16  SEWER PUMP STATIONS  

A. New pump stations and force mains are not allowed if the development can be served by the extension of gravity sewer.  Where approved for use, the Developer’s Engineer shall submit pump curves, operational data, flow projections and hydraulic calculations for review.  Where a development is to be constructed in phases, master planning of a subdivision will be required to assure that the number of lift stations is kept minimal and  that  lift  station  facilitates are abandoned as adjacent phases are  constructed or adjacent property is developed. 

 B. The Developer shall provide a permanent dedicated site for the pump station and its 

access road to be owned by the City of Clarksville.  A quick claim deed shall accompany the final plat before signature by the City Engineer. 

 C. Acceptable pumping systems include the following: 

1. Grinder/E‐One 2. Suction Lift 3. Submersible 

 D. Pump Station Site Requirements 

1. Sewage pump stations should be located as far as practicable from present or proposed  built‐up  residential  areas  and  shall  be  installed  in  a  prepared, landscaped,  and  fenced  area.    Noise  control,  odor  control,  and  station architectural design should be taken into consideration. 

2. The  area  for  the  pump  stations  shall  be  large  enough  to  accommodate  odor control equipment, pump trucks and the placement of a generator if necessary.  Sites  for stations shall be of sufficient size  for  future expansion or addition,  if applicable.  At a minimum, the pump station site shall measure approximately 30’x30’  for  suction  lift  pump  stations  and  approximately  60’x60’  for submersible pump stations, not including access road. 

3. The  site  shall  be  graded  to  provide  satisfactorily  drainage  such  that  the  lift station and its access drive will not be inundated during storm events.  The top of  the  lift  station wet well  shall be 2  feet above  the 100‐year  flood  level and shall  also  be  at  least  6  inches  above  surrounding  grade  elevation.    Drainage swales shall be rip‐rapped or otherwise protected against erosion.   

4. The access road to the lift station shall be constructed at a grade not to exceed 

Page 101: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐11 

13  percent  and  shall  be  paved.    The  typical  required  pavement  section  will consist  of  6  inches  of  compacted  crushed  stone  base  course  and  2  inches  of asphalt.    Prior  to  placement  of  pavement materials,  the  access  road  shall  be proof‐rolled using a fully loaded dump truck in the presence of a representative of  the  City  and  any  unstable  areas  undercut  and  replaced.    The  access  road shall not be shared with residential driveways. 

5. The pump station yard shall be graveled with 6 inches of crushed stone gravel, paved  with  asphalt,  or  landscaped  with  a  grass  lawn  as  indicated  on  the Contract Drawings. 

6. At a minimum, the pump station site shall be enclosed by a chain link fence and gate in accordance with Section 02821.  A privacy fence may be required where the pump station is located near residences.  Landscaping may be required as a buffer to properties adjacent to the proposed lift station.   Noise control, odor control,  and  station  architectural  design  shall  be  considered  and  included on the Contract Drawings. 

 E. Wet Well Sizing 

1. A suitable wet well shall be provided for each sewer lift station.  The wet well shall  be  of  sufficient  size  to  permit  proper  operation  of  the  lift  station while minimizing the probability of an overflow event. 

2. Pre‐cast  concrete  wet wells  shall  have  a minimum  inside  diameter  of  six  (6) feet. 

3. All wet wells shall be sized to provide sufficient capacity to retain a minimum of 2 hours of average flow as measured from the pump cutoff level to the invert of  the  lowest  inlet  pipe.    Storage  volumes  from  sewer  main  and  associated manholes may also be considered, as well as wet well storage above the lowest invert,  provided  that  Developer’s  Engineer  can  demonstrate  that  overflow and/or service line backup into connected properties will not occur.  

4. The  Developer’s  Engineer  shall  also  consider  future  growth  within  the  lift station drainage basin during sizing of the lift station. 

 F. Wet Well Materials 

1. The wet well must be constructed of materials  to prevent deterioration  from acids  formed  from  H2S  and  other  chemicals  observed  or  expected  for  the operating conditions anticipated in the new wet well. 

2. The  preferred materials  of  construction  include  pre‐cast  concrete  or  formed concrete.    Pre‐cast  concrete wet wells  shall  conform  to  the  requirements  of AASHTO M‐199 SR and ASTM C478, including steel reinforcement.  All concrete used  in  connection  with  the  construction  of  precast  manholes  shall  be  at minimum 4,000 psi concrete. 

3. The precast manufacturer  shall  use  XYPEX  additive.  Xypex Admix  C‐1000 Red shall be added to the concrete during batching at the manufacturer's specified rate. The amount of cement shall remain the same and not be reduced. Precast concrete structures shall have a reddish tint to verify the XYPEX admix. 

4. Fiberglass,  HDPE  and  coated  steel  wet  wells  are  acceptable  for  use  in  pre‐

Page 102: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐12 

fabricated  or  “canned”  lift  stations  where  approved  by  the  City  Engineer.  Fiberglass or coated steel lift stations shall be certified by the manufacturer and accompanied by a warranty against deterioration. 

 G. Wet Well Construction 

1. Wet  well  penetrations  shall  be  mechanically  sealed  with  resilient  pipe connectors as specified in Paragraph 2.13 of this Section. 

2. Joint  sealant  for  precast  wet  wells  shall  comply  with  Paragraph  2.10  of  this Section. 

3. All external wet well  joints shall be sealed using a wrap seal  such as CANUSA Wrapidseal®  or  equivalent  to  prevent  infiltration  or  inflow  at  the  joint(s),  as specified in Paragraph 2.15 of this Section. 

4. Wet well bottoms shall be constructed with a minimum of a 4‐inch, 45o fillet at wall joints to prevent solids accumulation. 

5. Access steps  for wet wells will not be allowed.   At  the Engineer’s direction, a fiberglass reinforced plastic (FRP) ladder with approved fall‐protection devices shall be installed. 

6. Anti‐flotation  collars  shall  be  installed  where  groundwater  is  present  or expected to be present above the bottom of the lift station during dry or wet seasons. 

7. Access  hatches  for  submersible  wet  well  applications  shall  be  supplemented with  a  lockable  secondary  1‐inch  thick  aluminum  grating  panel,  such  as  the Halliday Products Retro‐Grate.   The grating panel shall be hinged and shall be supplied with a positive latch to maintain unit in an upright position.  A   6‐inch viewing area shall be provided on each  lateral unhinged side of grating panel for visual observation and limited maintenance procedures. 

 H. Station  piping  shall  be  specially  lined  and  coated,  flanged  ductile  iron  pipe.    Buried 

piping to the common force main shall be specially lined and coated mechanical joint ductile iron pipe. 

 I. Consideration  shall  be  given  during  inlet  design  to  minimize  flow  turbulence  that 

accelerates  release  of  trapped  gases  in  the  flow  stream.    Baffles,  interior  drop assemblies or other methods may be required.  The number of inlet pipes into the wet well should be minimized. 

 J. In areas where sanitary sewers drain  to a wastewater pumping station, an approved 

backwater valve shall be installed in all buildings subject to flooding during a failure of the pumping  facilities.   The  location of  said backwater valve shall be as  indicated on the drawing for a typical house connection or as directed by the City Engineer. 

 K. Appropriate valves, valve vaults and valve boxes shall be installed in accordance with 

the Contract Documents.  L. Pressure gauges are required on the discharge piping of all suction lift and submersible 

Page 103: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐13 

pump stations.  Flow meters shall be installed on the common discharge pipe within a concrete  vault  for  all  pump  stations  with  rated  flows  of  400  gpm  and  greater,  as specified in Section 13310. 

 M. Suction‐lift and submersible pump stations shall be equipped with a dual level sensor 

system,  which  shall  consist  of  a  pressure  transducer  with  a  float  back‐up  system.  Sensors should be located so as not to be affected by the flows entering the wet well or by the suction of the pumps. 

 N. All  electrical  wiring  shall  be  copper  conductor.    Aluminum  is  not  an  acceptable 

substitute.    O. All control and  instrument panels  shall be supported by galvanized steel posts set  in 

concrete.  Wooden posts are not acceptable.  P. To prevent potential settling damage, a suitable length of flexible conduit shall be used 

to connect rigid conduit to the lift station.  Q. A  riser  from  the  force main with  quick  connect  capabilities  and  appropriate  valving 

shall be provided for all lift stations with rated pump flows of 50 gpm or greater.  Quick connects shall be as specified in Section 11200. 

 R. An alarm  system  should be provided  for  all  pumping  stations  as  specified  in  Section 

13310. 1. For  lift stations with rated pump flows  less than 400 gpm, a cell phone‐based 

telemetry (or cellemetry) system shall be installed. 2. For lift stations with rated pump flows of 400 gpm or greater, real‐time SCADA 

systems shall be installed. 3. A backup power supply, such as a battery pack with an automatic switchover 

feature,  should  be  provided  for  the  alarm  system,  such  that  a  failure  of  the primary power source will not disable the alarm system. 

4. Test circuits should be provided to enable the alarm system to be tested and verified that it is in good working order. 

  PART 3 ‐ EXECUTION  3.01  WATER AND SEWER LINE SEPARATION  

A. Maintain a 10‐foot horizontal separation, measured edge to edge, between any new or proposed sanitary sewer and any existing or proposed water main.  

B. Where  conditions  cause  the  required  horizontal  separation  to  be  impractical,  the sewer may be  laid closer provided  it  is  laid  in a separate trench and the elevation of the top of the sewer is at least 18 inches below the bottom of the water main. 

Page 104: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐14 

 C. Where a sewer crosses under a water main, the top of the sewer shall be at least 18 

inches below the bottom of the main. D. Where conditions cause the required vertical separation to be  impractical,  the water 

main shall be relocated to provide the required separation or else reconstructed with mechanical  joint ductile  iron pipe for a distance of 10 feet on each side of the sewer with a full joint of the water main centered over the sewer.  

E. Where sewers must be constructed over water mains or less than 18 inches below the water  main,  the  sewer  shall  be  designed  and  constructed  equal  to  water  main standards and pressure tested to assume water tightness.  

F. Additional protection such as concrete encasement  shall be  installed where directed by the Engineer.  

G. To prevent cross connection, comply with the City’s “Cross Connection Control Policy and Program.” 

 3.02  GRAVITY SEWER INSTALLATION  

A. Properly  excavate  trench  to  required  lines  and  depths  and  install  any  necessary sheeting, shoring and bracing in accordance with Section 02221. 

 B. Prepare a satisfactory  trench bottom and  install  suitable bedding  in accordance with 

Section 02221.  

C. Lay pipe true to the lines and grades from the grade and alignment stakes, or equally usable references. 

 D. Carefully  inspect  all  pipe  and  each  fitting  prior  to  its  placement  in  the  trench,  and 

reject and remove any damaged or defective pipe or fitting from the job site.  

E. Dig  bell  holes  large  enough  to  allow  ample  room  for  the  pipe  joints  to  be  properly made.   Carefully grade the crushed stone bedding between bell holes such that each pipe barrel will rest for its entire length upon the prepared bedding to assure uniform support of the pipe. 

 F. Lay pipe progressively up grade, with bell upstream in such a manner as to form close, 

concentric joints with smooth bottom inverts.  Swab the interior of the pipe to remove all foreign material.  Prepare the bell and remove undesirable material from the gasket and  gasket  recess.    Joining  of  all  pipe  shall  be  in  accordance  with  manufacturer’s specifications. 

 G. When cutting short  lengths of PVC pipe, a pipe cutter will be used, and care shall be 

taken to make the cut at right angles to the centerline of the pipe.  In the case of push‐

Page 105: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐15 

on pipe, the cut ends shall be tapered with a portable grinder or course file to match the manufactured taper. 

 H. Compression couplings shall be used where indicated on the Contract Drawings or as 

specified in Paragraph 2.07 of this Section.  

I. Gravity sewer pipe shall be of the size and material indicated on the Contract Drawings and as specified in Part 2 of this Section.  No sewer main shall be less than 8 inches in diameter. 

 J. Gravity sewer pipe shall be installed at the grade indicated on the Contract Drawings.  

Sewer pipe  shall  be  installed with  slopes equal  to or exceeding  the minimum slopes provided in the following table. 

 

Nominal Sewer Size  Minimum Slope in Feet Per 100 Feet 

8 inch  0.40 

10 inch  0.28 

12 inch  0.22 

14 inch  0.17 

15 inch  0.15 

16 inch  0.14 

18 inch  0.12 

21 inch  0.10 

24 inch  0.08 

27 inch  0.067 

30 inch  0.058 

 K. Sewer  service  assemblies  shall  be  installed  with  the  sewer  main  as  it  is  being  laid 

where  indicated on the Contract Drawings and  in accordance with Paragraph 3.03 of this Section. 

 L. Additional pipe protection such as use of specially  lined ductile  iron pipe or concrete 

encasement shall be installed where indicated on the Contract Drawings or as directed by the Engineer.  Pipe protection may be required for shallow sewers, areas subject to erosion,  very  heavy  traffic,  utility  crossings,  along  property  lines where  future  fence posts could be anticipated, etc. 

 M. Sewers  on  18  percent  slope  or  greater  shall  be  anchored  securely  with  concrete 

anchors or equal.  Minimum anchorage spacing is as follows: 1. Not over 36 feet center to center on grades 18 percent and up to 24 percent. 2. Not over 24 feet center to center on grades 25 percent and up to 34 percent. 3. Not over 16 feet center to center on grades 35 percent and over. 

 N. As the work progresses, thoroughly clean the interior of the pipe in place.  After each 

joint of pipe has been laid, carefully inspect it and remove all foreign material from its 

Page 106: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐16 

interior.  Upon completion of a section between any two manholes, it shall be possible to view a complete circle of light when looking through the pipe. 

 O. Do not allow walking on complete pipelines until backfill has been placed to a depth of 

at least 6 inches above the crown of the pipe.  

P. When laying pipe ceases at the end of the workday or any other disruption, close the open  ends  of  the  pipe  with  a  suitable  watertight  plug  to  prevent  the  entrance  of foreign materials. 

 Q. Trench backfill and check dams shall be placed in accordance with Section 02221. 

 R. Make  connections  to  existing  manholes  by  core  drilling  a  hole  in  the  wall  of  the 

existing structure, installing a resilient pipe connector such as Kor‐N‐Seal, and securing the  sewer  pipe  in  the  connector  in  accordance  with  the  manufacturer’s recommendations.  Shape or re‐shape the invert of the manhole to accommodate the new flow channel.  

S. Measurement  of  the  depth  to  determine  depth  classification  shall  be  the  vertical distance between the original ground surface elevation and the  invert of  the pipe as shown  on  the  Contract  Drawings  except  where  the  profile  has  been  revised  and approved by the Owner. 

 3.03  SEWER SERVICE ASSEMBLY INSTALLATION  

A. The  standard  sewer  service  connection  shall  be  4  inches  in  diameter  unless  shown otherwise on the Contract Drawings and shall connect to the sewer main at a tee or wye  connection  installed with  the  sewer main  as  it  is  being  laid.    The  service  fitting shall be of the same material as the sewer main pipe. 

 B. Sewer  service  connections  into  manholes  are  discouraged  and  shall  not  be  made 

unless specifically approved by the City.  

C. Connection to an existing sewer main where no service fitting has been installed shall, with  the  approval  of  the  City,  be  accomplished  by  a  service  tap  to  the  sewer main through a tapping saddle.  The saddle shall be a gasketed saddle secured to the sewer main  by  at  least  two  stainless  steel  clamps.    Tapping  saddles  shall  be  approved  for connections to existing sewer lines only. 

 D. Where specifically approved by the City, connections to an existing gravity sewer main 

may be accomplished using a Romac Style CB sewer saddle by Romac Industies, Inc. or approved  equal.    Sewer  saddles  shall  be  installed  in  accordance  with manufacturer recommendations. 

 

Page 107: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐17 

E. Where sewer service connections are 8 feet in depth or greater, sewer risers shall be installed at the service connection to protect  the service connection and to  facilitate excavation of the sewer lateral.  Deep sewer risers shall be by Bates & Harrington, Inc., of Madison Heights, VA or equal. 

 F. The Contractor shall stub a capped service pipe from the service connection to a point 

approximately 3 feet onto a customer’s property across the Right‐of‐Way or easement line, with the exception that a minimum of one 13‐foot joint shall be installed.  Service stubs from manholes, where allowed, shall be a minimum of one 13‐foot joint. 

 G. Service  pipe  shall  be  of  the  same  material  as  the  sewer  main  and  shall  be  bed 

accordingly.    The minimum grade on  service pipe  shall be 1% or 1/8” per  foot.    The service stub shall be plugged, backfilled and marked at the plugged end. 

 H. The end of each  lateral  stub shall be marked with a 6‐foot  long 4x4 wooden post or 

metal fence post embedded 2 feet into the ground and be marked with green paint.  

I. Identifying tape shall be installed in accordance with Paragraph 3.09 of this Section.  

J. The contractor shall stamp the curb with an “S” where sewer services are located.  

K. It  shall  be  the  residential  plumber’s  responsibility  to  install  a  sewer  cleanout  at  the Right‐of‐Way or easement line.  Cleanout assemblies shall be constructed of Schedule 40,  solvent weld  pipe.    The  cleanout  shall  consist  of  a  sanitary  tee  (sweep),  vertical pipe or appropriate length, and a threaded cleanout plug.  All property line cleanouts shall  be  installed  inside  a  polyethylene  box measuring  9  inches  in  diameter  and  12 inches deep.  The cover shall be of cast iron and labeled “Sewer.”  Cleanout boxes and covers are issued by the City of Clarksville. 

 3.04  PRECAST CONCRETE MANHOLE INSTALLATION  

A. Manholes shall be installed at the end of each sewer main, at all changes in grade, size, or alignment, at all intersections, and at distances not greater than 400 feet for sewers 16 inches or less and 500 feet for sewers larger than 16 inches.  Where a sewer main extension is expected in the foreseeable future, the manhole shall be installed at least to the property line shared by the current and future development.  

B. Provide a stable, satisfactory subgrade for the new manhole.  Dewater the excavation as  required.    Any  unstable  or  otherwise  unsuitable  material  encountered  at  the subgrade shall be undercut and replaced with compacted Class I angular material. 

 C. Provide a bedding of at least 6 inches of compacted Class I angular material as crushed 

stone base material for the manhole.  

Page 108: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐18 

D. Manholes  shall  be  installed  such  that  they  are  fully  and  uniformly  supported,  set plumb  in  true  alignment  and  at  the  proper  grade  in  accordance  with  the  Contract Drawings. 

 E. Where  concrete  foundations  are  to  be  cast‐in‐place,  the  concrete  shall  have  a 

compressive strength of at least 4,000 psi.  The base section shall be carefully blocked above  the  prepared  base  stone  so  that  it  is  plumb  and  in  true  alignment  and  the concrete  foundation poured beneath  it.    The concrete  foundation  shall be at  least 8 inches thick.  Riser sections shall not be added until the concrete foundation has been allowed to set for at least 24 hours. 

 F. Concrete  anti‐flotation  collars  shall  be  installed  as  sized and where  indicated on  the 

Contract  Drawings,  or  where  directed  by  the  Engineer,  to  prevent  flotation  due  to groundwater. 

 G. Seal joints between sections with an approved joint sealant. 

 H. Where  pipe  openings  and  integrally  cast  resilient  pipe  connectors  have  not  been 

provided complete, the Contractor shall make connections to manholes by core drilling a hole in the wall of the structure, installing a resilient pipe connector such as Kor‐N‐Seal,  and  securing  the  sewer  pipe  in  the  connector  in  accordance  with  the manufacturer’s recommendations.  Shape the invert of the manhole to accommodate the flow channel as specified herein. 

 I. Thoroughly wet and then completely fill all lift holes, any defects and all interior joints 

with non‐shrink grout and smooth them to ensure watertightness.  

J. Where indicated on the Contract Drawings, the manhole encapsulation system shall be installed on the outside surface of all joints including the manhole casting to manhole connection.   The manhole and casting shall be clean and dry prior to application of a primer as recommended by the manufacturer.  Installation shall be in accordance with the manufacturer’s recommendations. 

 K. Trench check dams shall be installed upstream of each manhole as specified in Section 

02221, Paragraph 3.13.  

L. Backfill manholes in accordance with the requirements for trenching and backfilling as specified in Section 02221, Paragraph 3.12. 

 M. When completed, the manhole shall be free from channel obstructions and leakage. 

 N. All manhole inverts shall be finished with mortar to provide a smooth transition from 

the manhole into the pipe entrances and exits.  

Page 109: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐19 

O. Measurement  of  the  depth  to  determine  depth  classification  shall  be  the  vertical distance from the finished casting elevation to the invert of the outlet pipe as shown on  the  Contract  Drawings  unless  the  profile  has  been  revised  and  approved  by  the Owner. 

 3.05  MANHOLE FRAME AND COVERS INSTALLATION  

A. All  castings  shall  be of  the  types,  dimension,  and weights  as  shown on  the Contract Drawings  and  as  specified  in  Paragraph  2.11  of  this  Section  and  shall  be  set  at  the required elevation.  Bolted watertight manhole covers are required in areas subject to flooding.  Bolted down covers are also to be installed in all unimproved areas such as wooded areas that are subject to unsupervised vandalism.  

B. The manhole sidewall shall be adjusted with either steel or concrete grade adjustment rings as required to bring the casting to the required grade.  No more than 6 inches of grade adjustment rings will be permitted on newly constructed manholes.  

C. Where manholes are constructed in paved areas, the frame and cover shall be tilted so as to conform to the exact slope, crown and grade of the existing adjacent pavement.  

D. A  full  circle  of  an  approved  joint  sealant  shall  be  placed  between  the manhole  ring frame and the masonry portion of the manhole to assure water tightness.  The frame shall be further secured to the manhole by the use of mortar or grout placed from the outside edge of the masonry structure to a point approximately 1 inch below the top of  the  casting.    Manhole  frames  shall  be  bolted  to  the  manhole  using  four  ½‐inch diameter stainless steel expansion anchor bolts.  

E. Manhole  frame  seals  shall  be  installed on  sanitary manholes  in  accordance with  the manufacturer’s  recommendations  where  indicated  on  the  Contract  Drawings  or  as directed by the City Engineer.  

F. Existing  manhole  frames  shall  be  adjusted  utilizing  John  Bouchard  &  Sons,  Inc. manhole adjusting riser rings. 

 3.06  MANHOLE STEP INSTALLATION  

Where not provided already cast‐in‐place in new precast manhole sections, set manhole steps at  intervals  of  12  inches  along  the wall  of  the manhole.   Manhole  steps  shall  be  vertically aligned  in  each  section  of  the manhole.    In  precast manholes,  the  holes  left  to  receive  the steps  shall  be mortared  smooth  following placement of  the  steps.    The  treads of  the  steps shall be free of mortar or other material when the manhole is completed. 

    

Page 110: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐20 

3.07  DROP ASSEMBLY INSTALLATION  

A. Drop  assemblies  are  also  required  in  pump  station  wet  wells  where  the  difference between  the  invert  elevation  of  the  inlet  pipe  and  the  level  control  cutoff  point  is greater than 24 inches.  Down pipes shall be terminated approximately 3 inches above the level control cutoff point.  

B. Drop assemblies shall be internal to the manhole or wet well.  External drops shall not be permitted unless specifically approved by the Owner.  

C. Drop  assemblies  shall  be  constructed  of  PVC.    The  down  pipe  shall  be  12  inches  in diameter.    A  cross  fitting  shall  be  provided  at  the  pipe  entrance  to  the manhole  to provide  access  for  cleaning blockages.    Stainless  steel  straps  and  anchors  spaced no greater  than  6  feet  apart  shall  be  installed  to  support  the  assembly.    A  90  degree sweeping elbow shall be installed at the bottom of the drop pipe and a suitable invert shall be formed.    

D. Drop manholes  shall  be  a minimum  of  5  feet  in  diameter.    All manholes with  drop assemblies shall be epoxy coated or utilize an interior construction such as the A‐Lok® system to prevent H2S deterioration of the manhole interior. 

 3.08  SEWER FORCE MAIN INSTALLATION  

A. Properly  excavate  trench  to  required  lines  and  grades  and  install  any  necessary sheeting, shoring and bracing in accordance with Section 02221. 

 B. Prepare  a  satisfactory  trench  bottom  in  accordance  with  Section  02221,  Paragraph 

3.10.  

C. Lay  the  force main  true  to  the  lines and grades  indicated on  the Contract Drawings.  Particular care shall be taken to assure the line is maintained on a positive or negative grade and that increased depth is provided where indicated on the Contract Drawings so that no undesired local high point is created.   The Contractor shall relay any force main pipe with undesired high points at no additional expense to the Owner.  

D. Unless  otherwise  directed  by  the  Engineer,  lay  pipe  with  the  bell  ends  facing  the direction of laying.  

E. Carefully  inspect  all  pipe,  valves  and  fittings  prior  to  placement  in  the  trench,  and reject and remove any damaged or defective pipe from the job site.  

F. Dig  bell  holes  large  enough  to  allow  ample  room  for  the  pipe  joints  to  be  properly made.    Carefully  grade  the bottom of  the  trench between bell  holes  such  that  each pipe  barrel will  rest  for  its  entire  length  upon  the  trench  bottom  to  assure  uniform support of the pipe. 

Page 111: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐21 

 G. All pipe and  fittings  shall be carefully  lowered  into  the  trench  to prevent damage  to 

the materials  and  to  any protective  coatings  and  linings.    Specially  lined ductile  iron pipe  and  fittings  must  be  handled  only  from  the  outside.    No  forks,  chains,  hooks, timber, etc. shall be placed inside the pipe and fittings for lifting, positioning or laying.  

H. The interior of all pipe, valves and fittings shall be thoroughly cleaned to remove any accumulated mud, debris, etc. before being laid.  The spigot end shall be cleaned and the bell cleaned and prepared.  If the pipe cannot be laid without allowing earth and debris from entering the pipe, a suitable cover such as canvas or a plug shall be used to assure the pipe remains clean until it is joined to the next pipe.  Joining of all pipe shall be in accordance with the manufacturer’s recommendations.  

I. Cut pipe for inserting valves, fittings, etc. in a neat and workmanlike manner without damaging the pipe.   Follow the manufacturer’s recommendations concerning how to cut and machine the pipe in order to leave a smooth end at right angles to the axis of the pipe.  Hone the pipe with suitable tools to provide a smooth beveled edge on field cut sections.  

J. When pipe  laying ceases at  the end of  the workday or any other disruption,  such as inclement weather, close the open ends of the pipe with a suitable watertight plug or wrap to prevent entrance of foreign materials.  

K. Wherever pipe must be deflected from a straight  line, the amount of deflection shall not exceed that necessary for the joint to be satisfactorily made.  The deflection shall in no case exceed that recommended by the pipe manufacturer.  

L. At high points on the line profile, where a change from a positive to a negative grade occurs,  an  air  relief  or  combination  air/vacuum  relief  valve  shall  be  installed  as specified in the Contract Drawings and in Section 11200.  

M. Force main valves shall be installed where indicated on the Contract Drawings.  Valves and stems shall be installed plumb and in accordance with Section 11200.  

N. All  valves  and  fittings  are  to be  restrained with mechanical  joint  restraining devices.  These  restraining  devices  do  not  eliminate  the  requirement  for  sufficient  concrete thrust blocking and/or restrained joint pipe.  The distance from the fitting to the end of the restraint shall not be less than that indicated on the Contract Drawings.  

O. Concrete thrust blocks shall be installed at all fittings in accordance with the Contract Drawings.   The concrete shall be Class B concrete as specified  in Section 03300.   The thrust  block  shall  be  constructed  between  the  fitting  and  undisturbed  soil  with  a bearing  area  at  least  the  size  indicated  on  the  Contract  Drawings,  and  shall  be constructed such that the fittings, valves and joints are accessible for repairs.  All pipe, fittings  and  valves  that  will  be  in  contact  with  the  concrete  shall  be  lubricated  to 

Page 112: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐22 

prevent bonding with the thrust block.  

P. Backfill shall be as specified in Section 02221, Paragraphs 3.11 and 3.12.  

Q. Carsonite markers shall be installed where indicated on the Contract Drawings.  R. Where  the  force  main  discharges  into  a  gravity  sewer  manhole,  the  force  main 

entrance to the receiving gravity manhole shall be within 6 inches of the lowest invert of  the  manhole.    Deflector  fittings  or  new  inverts  shall  be  installed  if  necessary  to reduce the turbulence of the incoming flow.  All manholes with force main discharges shall be epoxy coated or shall utilize an interior construction such as the A‐Lok® system to prevent H2S deterioration of the manhole interior.  

S. New force main connections to existing force mains shall be as shown on the Contract Drawings. 

 3.09  IDENTIFYING TAPE AND TRACER WIRE  

A. The  location  of  all  service  laterals  and  force  mains,  regardless  of  material  type, installed under these specifications shall be marked by the use of a continuous tape, minimum three inches in width, made of 5 mil polyethylene plastic with a 0.5 mil thick aluminum metallic core or backing.  The tape shall be buried in the trench, above the pipe, not more than two feet below the surface.   The tape shall be marked  indelibly with  the words  “Sewer Main Below” or  similar wording  to warn unwary  excavators, and shall be green in color. 

 B. Tracer  wire  shall  be  installed  along  any  sewer  force  main  and  force  main  services.  

Tracer wire  installed  in open cut applications shall be Copperhead 1230‐HS, 12 AWG copper‐clad  steel  tracer  wire  with  30  mil  HDPE  coating,  no  substitutions  allowed.  Tracer  wire  installed  in  horizontal  directional  drill  applications  shall  be  Copperhead 1245‐EHS,  12  AWG  copper‐clad  steel  tracer  wire  with  45  mil  HDPE  coating,  no substitutions allowed.  Tracer wire color shall be green for sewer pipe.  Connectors at service connections and tees shall be DryConn Direct Bury Lug Aqua by King Innovation and  at  main  line  splices  shall  be  DryConn  King  6  Blue  by  King  Innovation,  no substitutions allowed.   Tracer wire shall extend at  least five feet beyond service stub terminations.   A piece of PVC pipe shall be buried vertically against the 4”x4” marker post  extending  about  two  inches  above  ground  level.    The  tracer  wire  shall  be  fed through the PVC pipe with the end of the wire about two inches above the end of the pipe  and  the  remainder  coiled  and  buried  beneath  it.    A  performance  test  will  be performed  on  the  completed  tracer  wire  system  to  ensure  the  entire  system  is trackable.  Any part of the system that is not trackable shall be repaired or replaced by the Contractor until it is trackable prior to final acceptance of utilities.  

Page 113: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐23 

C. Tracer  wire  test  stations  shall  be  installed  along  force  main  alignments  with  a maximum  spacing  of  500  feet  between  test  stations.    Coordinate  location  of  tracer wire test stations with CGW Inspector.  

 3.10  BYPASS PUMPING  

A. Where flow stoppage may be necessary and the flow is so great as to require pumping, the Contractor shall bypass the sewage around the section or sections of gravity sewer line  that  are  out  of  service  by  plugging  an  existing  upstream manhole  and  pumping sewage to a downstream manhole.   The pump and bypass  lines shall be of adequate capacity  and  size  to handle  the  flow.    Likewise, bypass pumping may be  required at pump stations through pump‐around ports, where available.  Alternatively, situations may demand that pumping and hauling be performed.   The Contractor shall perform whatever bypass operations are necessary to complete the required work and prevent overflow or spillage of raw sewage. 

 B. UNDER  NO  CIRCUMSTANCES  WILL  THE  DUMPING  OF  RAW  SEWAGE  ON  PRIVATE 

PROPERTY, OR INTO STREAMS, STORM SEWER OR CITY STREETS BE ALLOWED.  

C. Except as may be approved by the Owner’s Inspector, temporary connections shall be made  at  the  end  of  each  working  day  so  that  overnight  pumping  is  not  required.  Bypassing of sewage shall be considered a subsidiary obligation of the Contract and no separate payment shall be made for this work unless specifically listed as a pay item on the Bid Form. 

 3.11  STREAM CROSSINGS  

An Aquatic  Resource  Alteration  Permit  (ARAP) must  be  obtained  from  TDEC where  utilities cross USGS‐designated blue‐line streams or where utility line construction otherwise disturbs these streams.  Construction shall comply with the Contract Drawings and with the provisions of the ARAP and SWPPP.  Upon completion of construction, the stream and its banks shall be stabilized and/or returned as nearly as possible to their original condition.  Cleanup, grading, seeding, planting or restoration of the work area shall be carried out as early as practical as the construction proceeds and in accordance with the ARAP. 

  PART 4 ‐ TESTING  4.01  GENERAL  

A. Testing and inspection of the completed work shall be accomplished by one or more of the following methods: 1. Visual Inspection 2. Closed Circuit Television (CCTV)/Video Inspection 3. Leak Testing of Gravity Mains 

Page 114: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐24 

a) Low‐Pressure Air Testing b) Infiltration Testing c) Exfiltration Testing 

4. Deflection Testing of Gravity Mains 5. Vacuum Testing of Manholes 6. Hydrostatic Testing of Force Mains 7. Valve Testing 

 B. Upon completion of construction,  the Contractor shall  remove all  sand, dirt,  rock and 

other  foreign  materials  from  the  sewers  and  shall  conduct  his  own  inspection  and testing to locate and repair any defects, and determine when sewers are ready for final inspection and testing by the Owner’s Inspector.  After all apparent defects have been corrected, the Contractor shall notify the Owner and request a final inspection. 

C. The Owner will  not  conduct  a  final  inspection until  receiving written notice  from  the Developer’s Engineer that the construction  is completed  in accordance with approved Contract  Drawings  and  Specifications.    This  notification  shall  include  a  report  of  the results  of  the  inspection  and  testing  performed  on  the  sanitary  sewer  system components.  CCTV/Video files shall be submitted to the Owner at this time. 

 4.02  VISUAL INSPECTION  

A. Unscheduled  visual  inspection  of  the  sewer  and  construction  site  by  the  Owner’s Inspector shall occur during the course of the construction.  The Inspector shall make visual  inspection of pipe,  fittings,  valves and other materials  to be  incorporated  into the work before  they are  installed.    Items  found  to be defective or otherwise not  in accordance with Contract Drawings and Specifications shall be  immediately  removed from the site. 

 B. Visual  inspection  of  grade  and  alignment,  bedding,  pipe  jointing, manholes,  etc. will 

proceed as work progresses.  Acceptance of work at this stage in no way relieves the Contractor of responsibility and does not preclude additional testing at the discretion of  the Owner.    Any  sags,  humps,  bends  or  other  evidence  of misalignment  shall  be cause  for  rejection.    Improper  construction  and  work  not  in  accordance  with  the Contract Drawings and Specifications shall also be cause for rejection.  

C. Upon completion of the work, all sewers and manholes shall be inspected for foreign matter such as sand or mud brought  in by infiltration or  inflow, and any such matter shall  be  removed before  final  acceptance.    If  visual  inspection  of  lines, manholes  or other  items  reveals  leaks,  structural  failures  or  other  defects,  the  Contractor  shall repair such immediately. 

 4.03  CCTV/VIDEO INSPECTION  

A. The Contractor shall conduct an internal inspection and digital recording of the sewer system using a television instrument.  As an alternate to the Contractor performing the 

Page 115: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐25 

television inspection, the Contractor may choose to use the services of the City’s crews at a cost determined by the General Manager or his designated representative.   The Contractor shall be responsible  for correcting all deficiencies discovered by the CCTV inspection at no cost to the Owner.  

B. A remote controlled, adequately lit camera that will travel the length of each section of  gravity  sewer main  from manhole  to manhole  shall  be  used  to  televise  all  newly installed  sewers.    The  camera  shall  be  of  suitable  design  and manufactured  for  the express purpose of televising gravity sanitary sewer mains.  The camera’s path shall be recorded  with  an  onscreen  display  of  footage  traveled.    Auditory  notations  by  the camera operator regarding  locations of service connections, pipe defects,  indications of  faulty  installation  and  all  other  important  points  of  interest  shall  be  recorded  as permanent  record.   The view recorded by  the camera shall also  include an object of reference to assist the viewer in determining the scale of objects within the pipe.  

C. Video quality shall be such that the condition of all  interior sections of the main and service  laterals  on  that  section  of  the main  are  easily  discernible.    The  camera  shall allow  for  articulation  that  enables  a  clear  view  of  service  laterals  in  a  direction perpendicular to the direction of the main and at a variety of vertical angles to allow viewing of laterals at varying slopes.   The image must be clear to the test cap or first bend of the service lateral.  

D. Audio quality shall be adequate to clearly understand remarks of the camera operator.  

E. Video  inspection  shall  commence  immediately  after  line  cleaning  so  that  any  sag  or changes in grade shall be revealed and evidenced by puddling in areas where positive slope is not maintained.  

F. The  Contractor  shall  be  responsible  for  correcting  all  deficiencies  discovered  by  the CCTV inspection at no cost to the Owner.  

G. At the time of the request for final inspection, the Contractor shall submit to the City Engineer’s Office on CD‐ROM or DVD media 2 copies of digital files that represent the videotaping of all sewer mains in a project or development.  The video record of each section of gravity main between manholes shall be represented by a separate MPEG or AVI format digital file.  The disc and its jacket shall be clearly labeled with the name of the subdivision or project and its phase and/or section, as well as the installation date.  All references to manholes and mains with regard to videotaping shall be by the same naming  convention  as  that  shown  on  construction  plans  approved  by  the  City.    An index file shall be provided with each disc that explains the meaning of each file name and identifies the CCTV company that produced it. 

    

Page 116: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐26 

4.04  LOW‐PRESSURE AIR TESTING  

A. Low‐pressure air testing is the preferred method of leak testing of gravity sewer mains up through 24 inches in diameter when above groundwater.  If the groundwater level is 2 feet or more above the top of the pipe at the upstream end, air testing shall not be used. 

 B. Labor,  equipment  and  supplies  required  for  all  tests  shall  be  furnished  by  the 

Contractor.  The test shall be observed by the Owner’s Inspector.  

C. Low‐pressure  air  tests  shall  be  made  with  equipment  specifically  designed  and manufactured  for  the  purpose  of  testing  pipelines  using  low‐pressure  air.    The equipment shall be provided with an air regulator valve or air safety valve set such that the  internal air pressure  in  the pipeline cannot exceed 8 psig  (gauge pressure).   Test equipment  shall  be  top  quality,  in  good  condition  and  approved  by  the  Inspector.  Plugs  shall  have  a  sealing  length  equal  to  or  greater  than  the  diameter  of  the  pipe being tested and external bracing of the plugs should not be required in order for the plug to hold against internal air pressure.   The test equipment shall  include accurate, oil‐filled  pressure  gauges  to  monitor  test  pressure,  safety  relief  valve(s)  and  quick‐release air bleed valve(s). 

 D. The  procedure  for  low‐pressure  air  testing  shall  be  in  accordance with  ASTM  F1417 

unless modified herein. 1. Clean the section of sewer line to be tested by flushing or other means prior to 

conducting the low‐pressure air test. 2. Isolate the section of sewer line to be tested by suitable test plugs and plug all 

sewer  services  to be  included  in  the  test  to prevent air  leakage.    Such  sewer service  caps  shall  be  readily  removable,  and  their  removal  shall  provide  a socket suitable for making a lateral connection or extension.  All plugs and caps shall be securely braced to prevent blow‐out against internal pressures.  One of the plugs or caps should have an inlet tap, or other provision for connecting a hose  to  a  portable  air  control  source.    Allow  no  one  in  the manholes  while pressurizing the line or during the test. 

3. Immediately  following  this  check  or  cleaning,  test  the  pipe  installation  with low‐pressure air.  Supply the air slowly to the plugged pipe installation until the internal air pressure reaches 4.0 psi more than the average backpressure of any groundwater  that  may  submerge  the  pipe  (an  additional  0.43  psi  should  be added for each foot of groundwater above the pipe).  Allow at least 2 minutes for temperature stabilization. 

4. After  the  stabilization  period  and with  3.5  psi minimum pressure  (above  the average backpressure) in the pipeline, air supply shall be disconnected and the time measured which results in a 1 psi pressure drop. 

5. The  time  required  in  minutes  for  the  pressure  in  the  section  under  test  to decrease from 3.5 psi to 2.5 psi shall not be less than that shown in the table below. 

Page 117: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐27 

 

Low‐Pressure Air Test Requirements 

       Specified Time for Length Shown 

(min:sec) 

Pipe Dia. 

(inches) 

Min. Time (min:sec) 

Length for Min. Time (feet) 

Time for Longer Length 

100 ft  200 ft  300 ft  400 ft 

8  7:34  298  1.520*L  7:34  7:34  7:36  10:08 

10  9:26  239  2.374*L  9:26  9:26  11:52  15:49 

12  11:20  199  3.418*L  11:20  11:24  17:05  22:47 

15  14:10  159  5.342*L  14:10  17:48  26:42  35:36 

18  17:00  133  7.692*L  17:00  25:38  38:27  51:16 

21  19:50  114  10.470*L  19:50  34:54  52:21  69:48 

24  22:40  99  13.674*L  22:47  45:34  68:22  91:10 

 6. It is not necessary to hold the test for the entire period of time indicated in the 

above table when it  is evident that the rate of air  loss is zero or less than the allowable, and is authorized by the Inspector. 

7. Upon completion of the test, open the bleeder valve and allow all air to escape.  Plugs should not be removed until all air pressure in the test section has been reduced to atmospheric pressure. 

8. Failure of any section of the pipeline to meet the requirements of this test shall cause  the  Contractor  to  determine,  at  his  own  expense,  the  source(s)  of leakage.    The  Contractor  shall  excavate  and  repair  or  replace  all  defective materials or workmanship, and repeat all testing until results are satisfactory at no additional cost to the Owner. 

 4.05  INFILTRATION TESTING 

 A. Gravity  sewers  shall be  leak  tested by an  infiltration  test  if  the groundwater  is more 

than 2 feet above the crown of the pipe for the full length of the section to be tested.  

B. Pipe  shall  be  tested  for  infiltration  after  the  backfill  has  been  placed  and  the groundwater allowed to return to normal elevation.  If an inspection of the completed pipeline or any part thereof shows pipes or joints that allow noticeable infiltration of water, the defective work or material shall be replaced or repaired as directed by the Owner.  All visible leaks shall be repaired prior to testing. 

 C. The  length  of  line  to  be  tested  shall  not  be  less  than  the  length  between  adjacent 

manholes  and  not  more  than  the  total  length  of  each  size  of  pipe.    The measured infiltration shall not exceed 2.0 gallons per  inch of diameter per day per 100  feet of pipe in each section tested. 

 

Page 118: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐28 

D. Rates of infiltration shall be determined by means of V‐notch weirs, pipe spigots, or by plugs  in  the end of  the pipe  installed  in an approved manner and at  such  times and locations as may be directed by the Engineer. 

 E. Failure of any section of the pipeline to meet the requirements of this test shall cause 

the  Contractor  to  determine,  at  his  own  expense,  the  source(s)  of  leakage.    The Contractor shall excavate and repair or replace all defective materials or workmanship, and repeat all testing until results are satisfactory at no additional cost to the Owner. 

 4.06  EXFILTRATION TESTING  

A. Where  required  by  the  Engineer,  leakage  testing  by  exfiltration  shall  be  made  by creating a head  in  the pipeline  to be  tested by  filling  the  line and either manhole or temporary  riser on one end of  the  line with water.    The  length of pipe  to be  tested shall be such that the head over the crown at the upstream end is not less than 2 feet and the head over the downstream crown is not more than 5 feet. 

 B. The pipe shall be filled with water in such a manner that the air can be released from 

the pipe while it is being filled.  Before any measurements are made, the pipe shall be kept full of water long enough to allow absorption and the escape of any trapped air to take place.    Following  this, a  test period of at  least one hour  shall begin.   Provisions shall be made for measuring the amount of water required to maintain the water at a constant level during the test period.   If the quantity of water required to maintain a constant head in the pipe does not exceed 2.0 gallons per inch of diameter per day per 100 feet of pipe and if all the leakage is not confined to a few joints, workmanship shall be considered satisfactory. 

 C. Failure of any section of the pipeline to meet the requirements of this test shall cause 

the  Contractor  to  determine,  at  his  own  expense,  the  source(s)  of  leakage.    The Contractor shall excavate and repair or replace all defective materials or workmanship, and repeat all testing until results are satisfactory at no additional cost to the Owner. 

 4.07  DEFLECTION TESTING  

A. Flexible  PVC  pipe  shall  pass  a  go/no‐go  Mandrel  sized  to  95%  of  the  actual  pipe diameter with the pipe in place and properly backfilled.  No testing shall be performed until the pipe has been laid and backfilled for 30 days and any necessary line cleaning is complete. 

 B. The Mandrel size shall be based upon the maximum possible  inside diameter for the 

type  of  pipe  being  tested,  taking  into  account  the manufacturing  tolerances  of  the pipe.  

Page 119: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐29 

C. The Mandrel shall have an odd number of legs, or vanes, with a quantity of such equal to or greater than nine.  The legs of the Mandrel shall be permanently attached to the Mandrel. 

 D. The Mandrel shall be constructed of steel, aluminum, or other material approved by 

the Engineer or his representative, and shall have sufficient rigidity so the legs of the Mandrel will not deform when pulling through a pipe.  

E. A Mandrel with variable sizes shall not be allowed.  The Mandrel dimensions shall be checked by the Engineer or his representative before use by the Contractor. 

 F. Failure of any section of the pipeline to meet the requirements of this test shall cause 

the  Contractor  to  determine,  at  his  own  expense,  the  source(s)  of  deformity.    The Contractor shall excavate and repair or replace all defective materials or workmanship, and repeat all testing until results are satisfactory at no additional cost to the Owner. 

 4.08  VACUUM TESTING OF SEWER MANHOLES   

A. All new manholes are to be vacuum tested as soon as is practicable after assembly is completed.   No standing water shall be allowed  in the manhole excavation that may affect the accuracy of the test.  Leakage testing on newly rehabilitated manholes shall be accomplished in accordance with ASTM C1244‐05A rather than as specified in this Paragraph. 

 B. All lifting holes and exterior joints shall be filled and pointed with non‐shrink grout for 

concrete manholes or sealed with compatible sealant for other materials.  C. All pipes and other entrances into the manhole should be suitably plugged and blocked 

in such a manner as to prevent displacement of the plugs while  the vacuum is being pulled. 

 D. Installation and operation of the vacuum equipment and indicating devices shall be in 

accordance  with  equipment  specifications  and  instructions  provided  by  the manufacturer.  Gauges used for manhole testing shall be oil‐filled gauges. 

 E. The casting opening shall be sealed with an appropriate  testing/sealing device and a 

vacuum  of  10.0  inches  of mercury  (5  PSIG)  pulled  on  the manhole  (DO NOT  PUT  A POSITIVE  PRESSURE  ON  THE  MANHOLE).    The  time  for  the  vacuum  to  drop  to  9.0 inches of mercury shall be recorded. 

 F. Acceptance manholes shall be defined as when the time to drop from 10.0 inches to 

9.0 inches of mercury meets or exceeds the following:    

Page 120: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐30 

Minimum Time (seconds) to Drop From 10.0 Inches to 9.0 Inches of Mercury 

Manhole Diameter 

Manhole Depth 

4 feet to 10 feet  10 feet to 15 feet  15 feet to 25 feet 

4 feet  75  90  105 

5 feet  90  105  120 

6 feet  105  120  135 

 G. If  the  manhole  fails  the  test,  necessary  repairs  shall  be  made  at  the  Contractor’s 

expense and the vacuum test repeated until the manhole passes the test.  A significant number of  leaks on a single manhole may be considered as a basis  for  rejection and replacement at the Contractor’s expense.  

H. If the manhole joint mastic or gasket is displaced during the vacuum test, the manhole shall be disassembled and the seal replaced. 

 4.09  HYDROSTATIC TESTING OF SEWER FORCE MAINS  

A. All  newly  laid  pipe  or  any  valved  section  thereof  shall  be  subjected  to  hydrostatic pressure  testing.    Conduct  hydrostatic  testing  in  accordance  with  AWWA  C600  for ductile iron pipe or AWWA C605 for PVC pipe.  

B. Where practicable, pipelines shall be tested in lengths between line valves or plugs of no more than 3,000 feet.  

C. Hydrostatic testing shall be conducted only with potable water.   Due to the  inherent safety  hazard  potential  associated  with  testing  components  and  systems  with compressed  air  or  other  compressed  gases,  pressure  testing  shall  never  be accomplished using compressed air.  

D. The  Contractor  shall  furnish  all  gauges,  recording  devices,  meters,  pumps,  pipe, connections and other equipment required to conduct the test and shall maintain said equipment in condition for accurate testing as determined by the Owner.  Gauges used for pressure tests shall be oil‐filled gauges.  

E. Hydrostatic  test  results  shall  be  recorded  on  an  appropriate  chart  recorder.    The Contractor  shall  furnish  a  recording  gauge  and  water  meter  for  recording  pressure charts  and  for  measuring  makeup  water  used  during  the  hydrostatic  testing.  Recording  pressure  charts  shall  be  submitted  to  the  Owner  at  the  conclusion  of testing.    The  pressure  recording  device  shall  be  suitable  for  outside  service,  with  a range  from 0–200 psig,  24‐hour  spring wound  clock,  designed  for  9‐inch  charts,  and shall  be  approved by  the Owner.    Such pressure  recording devices may be available from Foxboro Company, Foxboro, Massachusetts; Bristol Division of ACCO, Waterbury, Connecticut; or Weksler Instruments Corporation, Freeport, New York.  

F. Prior  to  testing,  the  Contractor  shall  place  sufficient  backfill  to  prevent  pipe 

Page 121: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐31 

movement.  When local conditions require that the trenches be backfilled immediately after the pipe has been laid, the testing may be carried out after backfilling has been completed but before placement of permanent surfacing.  The Contractor shall ensure that  thrust  blocking  or  other  types  of  restraining  systems  will  provide  adequate restraint prior to pressurizing the pipeline.  

G. Cross Connection Control:   When existing water mains are used to supply test water, they  should  be  protected  from  backflow  contamination  by  temporarily  installing  a double  check  valve  assembly  between  the  test  and  supply main  or  by  other means approved  by  the  Owner.    Prior  to  pressure  and  leakage  testing,  the  temporary backflow  protection  should  be  removed  and  the main  under  test  isolated  from  the supply main.  

H. Test Pressure Requirements: 1. The test pressure shall not be less than 1.25 times the stated working pressure 

of the pipeline measured at the highest elevation along the test section and not less than 1.5 times the stated working pressure at the lowest elevation of the test section. 

2. The  test pressure  shall not exceed  the  thrust  restraint design pressure or 1.5 times the pressure rating of the pipe or joint, whichever is less (as specified by the manufacturer). 

3. The  test  pressure  shall  not  exceed  the  rated working  pressure  of  the  valves when  the  pressure  boundary  of  the  test  section  includes  closed,  resilient seated gate valves or butterfly valves. 

4. Valves  shall  not  be  operated  in  either  direction  at  a  differential  pressure exceeding the rated valve working pressure.   A test pressure greater than the rated valve working pressure can result  in trapped test pressure between the gates of a double‐disc gate valve.  For tests exceeding the rated valve working pressure,  the test setup should  include a provision,  independent of the valve, to reduce the line pressure to the rated valve working pressure on completion of  the  test.    The  valve  can  then  be  opened  enough  to  equalize  the  trapped pressure with the line pressure, or the valve can be fully opened if desired. 

 I. Test Procedure: 

1. Each valved section of pipeline shall be slowly filled with potable water using a metered backflow‐protected assembly provided by the Owner.  When venting air from pipelines, it is important to limit the pipeline fill rate to avoid excessive surge pressures when the water reaches the air venting opening(s). 

2. Before  applying  the  specified  test  pressure,  air  shall  be  expelled  completely from the pipeline section under test.  If permanent air vents are not located at all high points, corporation cocks shall be installed at such points to expel air as the  line  is  filled  with  water.    After  all  the  air  has  been  expelled,  close  the corporation  cocks  and  apply  the  test  pressure.    At  the  conclusion  of  the pressure test,  remove the corporation cocks and plug or  leave  in place at the discretion of the Owner. 

Page 122: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐32 

3. The specified test pressure shall be applied using a suitable pump connected to the pipeline in a manner satisfactory to the Owner.  The specified test pressure shall be based on  the elevation of  the  lowest point of  the pipeline or section under test and corrected to the elevation of the test gauge, in accordance with test pressure requirements specified herein. 

4. The pipeline shall be allowed to stabilize at the test pressure before conducting the  hydrostatic  test.    This  may  require  several  cycles  of  pressurizing  and bleeding  trapped air prior  to beginning  the  test.    It  is  recommended  that  the line remain pressurized for a minimum of 24 hours before testing in order for joints to tighten and pockets of air to dissolve in the water. 

5. The  hydrostatic  test  shall  be  at  least  2  hours  in  duration  after  reaching  the specified  test  pressure where  joints  are  exposed  and  at  least  8  hours where joints are covered. 

6. The test pressure shall not vary by more than +/‐ 5 psi for the duration of the test.  Test pressure shall be maintained within this tolerance by adding makeup water  through  the  pressure  test  pump  into  the  pipeline.    The  amount  of makeup  water  added  shall  be  accurately  measured  (in  gallons  per  hour)  by suitable  methods  and  shall  not  exceed  the  applicable  testing  allowance  as specified herein. 

 J. Visual  Inspection:    Any  exposed  pipe,  fittings,  valves,  hydrants  and  joints  shall  be 

examined  carefully  during  the  hydrostatic  pressure  test.    Any  damaged  or  defective materials that are discovered during or following the pressure test shall be repaired or replaced at the Contractor’s expense, and the test shall be repeated until satisfactory results are obtained. 

 K. Testing Allowance: 

1. Testing allowance shall be defined as the maximum quantity of makeup water that  is  added  into  a  pipeline  undergoing  hydrostatic  pressure  testing,  or  any valved  section  thereof,  in  order  to maintain  pressure within  +/‐  5  psi  of  the specified test pressure (after the pipeline has been filled with water and the air has been expelled).   

2. No pipe installation will be accepted if the quantity of makeup water is greater than that determined by the following formula: 

 L = S*D*(P)½  148,000 

Where: L =  testing allowance (makeup water), in gallons per hour S =  length of pipe tested, in feet D =  nominal diameter of the pipe, in inches P =  average test pressure during the hydrostatic test, in pounds per 

square inch (gauge pressure) 3. This formula is based on a testing allowance of 10.5 gpd/mile/inch of nominal 

diameter  at  a  pressure  of  150  psi.    Values  of  testing  allowance  at  various 

Page 123: Standard Water and Sewer Specifications PDF

  SANITARY SEWER SYSTEMS  02722‐33 

pressures are shown in the following table.  When testing against closed metal‐seated  valves,  an  additional  testing  allowance  per  closed  valve  of  0.0078 gal/hr/inch of nominal valve size shall be allowed. 

 

Hydrostatic Testing Allowance per 1,000 feet of pipeline (gallons per hour)* 

Average Test 

Pressure (psi) 

Nominal Pipe Diameter (inches) 

4  6  8  10  12  14  16  18  20  24  30 

250  0.43  0.64  0.85  1.07  1.28  1.50  1.71  1.92  2.14  2.56  3.21 

225  0.41  0.61  0.81  1.01  1.22  1.42  1.62  1.82  2.03  2.43  3.04 

200  0.38  0.57  0.76  0.96  1.15  1.34  1.53  1.72  1.91  2.29  2.87 

175  0.36  0.54  0.72  0.89  1.07  1.25  1.43  1.61  1.79  2.15  2.68 

150  0.33  0.50  0.66  0.83  0.99  1.16  1.32  1.49  1.66  1.99  2.48 

125  0.30  0.45  0.60  0.76  0.91  1.06  1.21  1.36  1.51  1.81  2.27 

100  0.27  0.41  0.54  0.68  0.81  0.95  1.08  1.22  1.35  1.62  2.03 

75  0.23  0.35  0.47  0.59  0.70  0.82  0.94  1.05  1.17  1.40  1.76 

50  0.19  0.29  0.38  0.48  0.57  0.67  0.76  0.86  0.96  1.15  1.43 

*  If the pipeline under test contains sections of various diameters, the allowable leakage will be the sum of the computed leakage for each size. 

 L. Acceptance of  the  installation shall be determined on the basis of  testing allowance.  

Should any test of pipe laid disclose leakage greater than that specified, the Contractor shall,  at  his  own  expense,  locate  and  repair  the  defective  joints  until  the  leakage  is within  the  specified allowance.   All  visible  leaks are  to be  repaired  regardless of  the allowance  used  for  testing.    Hydrostatic  test  results  shall  be  recorded  on  an appropriate  chart  recorder  as  specified  herein.    A  copy  of  the  test  chart  shall  be provided to the Owner. 

 4.10  VALVE TESTING  

Upon completion of the work, the Contractor shall operate all buried valves in the presence of the Owner’s Inspector to verify proper operation of each valve. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 124: Standard Water and Sewer Specifications PDF
Page 125: Standard Water and Sewer Specifications PDF

  BORING AND JACKING  02725‐1 

SECTION 02725  

BORING AND JACKING  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All water  and  sewer mains  installed  in  a  bore under  streets,  highways  and  railroads must be cased as specified herein. 

 B. Copper water services 2”  in diameter or smaller and schedule 40 PVC or ductile  iron 

sewer services may be installed without casing.  The bore for any such uncased service shall  not  be  greater  than 2  inches  larger  than  the maximum OD of  the  carrier  pipe.  Services encroaching TDOT right‐of‐way may be required to be cased at the discretion of TDOT. 

 1.02  RELATED WORK  

A. Section 02713:  Water Distribution Systems  

B. Section 02722:  Sanitary Sewer Systems  1.03  REGULATIONS AND PERMITS  

A. Permits  for  crossing  highways  or  railroads  will  be  obtained  by  the  Owner.    The Developer’s Engineer shall provide the Owner with any and all documents required by the Owner to obtain the necessary permit(s), including a profile of the road or railroad bore and  completed TDOT Pipeline Encroachment Form.    The Contractor  shall  verify that such permits have been obtained before construction commences. 

 B. For highway crossings, the Contractor shall satisfy TDOT to the extent of the Owner’s 

posted Surety Bonds.  

C. For railroad crossings, the Contractor shall furnish Certificates of Insurance in amounts established by the railroad company, naming the railroad as the insured, and complete required application forms to be used by the City to obtain the permit as specified by the railroad. 

 D. Notify all related agencies prior to commencing construction activities. 

   

Page 126: Standard Water and Sewer Specifications PDF

  BORING AND JACKING  02725‐2 

PART 2 ‐ PRODUCTS  

2.01  STEEL CASING PIPE  

A. Encasement pipe  shall  be  smooth wall welded  steel with minimum yield  strength of 35,000 psi.  A protective bituminous coating shall be applied to the outside of the pipe. 

 B. Steel casing pipe shall be of sufficient strength to meet the loading conditions of H‐20 

loading for highway crossings and Cooper E‐80 loading for railroad crossings, and shall have  the  minimum  pipe  diameter  and  wall  thickness  shown  in  the  following  table.  Where mechanical joint pipe requires a larger diameter casing pipe than push‐on joint pipe, a separate line item for MJ pipe has been provided in the following table.  Where bell restraint harnesses have been specified for the carrier pipe, an appropriately sized casing  pipe  shall  be  specified  to  accommodate  the  restraints  and  required  casing spacers. 

 

Carrier Pipe Nominal Diameter 

(inches) 

Minimum Steel Casing Pipe 

Diameter (inches) 

Minimum Wall Thickness (inches) 

Highway Crossing  Railroad Crossing 

4  12  0.188  0.188 

6  14  0.250  0.250 

8  16  0.250  0.250 

8 MJ  18  0.250  0.250 

10  18  0.250  0.250 

10 MJ  20  0.250  0.281 

12  20  0.250  0.281 

12 MJ  24  0.250  0.312 

14 ‐ 16  24  0.250  0.312 

16 MJ  30  0.312  0.406 

18 – 21  30  0.312  0.406 

24 ‐ 27  36  0.375  0.469 

30  42  0.500  0.562 

36  48  0.500  0.594 

36 MJ  54  0.500  0.719 

 2.02  CARRIER PIPE  

Carrier pipe installed in the casing pipe shall be as indicated on the Contract Drawings.  2.03  CASING SPACERS  

A. Casing  spacers  shall  be  provided  so  that  the  carrier  pipe  is  in  a  centered/restrained position.  The casing spacers shall be constructed of circular stainless steel bands that bolt  together  to  form a  shell  around  the  carrier  pipe  and  shall  be  lined with PVC or EPDM to protect the carrier pipe and prevent slippage.  The spacer shall be designed 

Page 127: Standard Water and Sewer Specifications PDF

  BORING AND JACKING  02725‐3 

with risers and runners to support the carrier pipe within the casing.  

B. The shell shall be minimum 14‐gauge T‐304 stainless steel and shall be manufactured in  minimum  widths  of  8  inches  and  12  inches.    The  riser  shall  be  constructed  of minimum  10‐gauge  T‐304  stainless  steel  and  shall  be  sized  to  support  all  loads  and shall  support  the  carrier  pipe  within  the  casing  in  the  centered/restrained  position.  The  runners  shall  be  a  minimum  width  of  2  inches  and  be  constructed  of  glass‐reinforced polymer with beveled ends. 

 C. The spacers shall at a minimum be positioned at 1 to 2 feet on either side of the joint 

and at the midpoint.  Additional spacers may be required where recommended by the manufacturer and/or Engineer. 

 D. Casing spacers shall be Models CSS8 and CSS12 by CCI Pipeline Systems or S8G‐2 and 

S12G‐2 by Pipeline Seal and Insulator, Inc.  2.04  END SEALS  

A wrap‐around self‐curing rubber end seal shall be applied to each end of the casing pipe.  End seals shall be Model ESW by CCI Pipeline Systems or Model “W” by PSI, Inc. 

  PART 3 ‐ EXECUTION  3.01  GENERAL REQUIREMENTS  

A. Perform  all  crossings  according  to  the  requirements  of  the  governing  highway department or railroad company. 

 B. Notify  the  appropriate  authorities  involved  and  request  their  supervisory  services 

during construction.  

C. Provide necessary safeguards to protect the crossing.  

D. Where bored highway installations are not shown on the Contract Drawings, open cut the  crossing  and  provide  a  casing  pipe  only  if  required  by  the  governing  highway department or Engineer. 

 E. All  uncased  roadway  punches  shall  be  approved  by  the  City  Engineer  prior  to 

construction.  

F. Excavation  shall  be  unclassified  and  no  distinction  shall  be made  between  rock  and other materials excavated. 

 G. No extra payment will  be provided  for  tunneling  through  rock.    The  contractor  shall 

Page 128: Standard Water and Sewer Specifications PDF

  BORING AND JACKING  02725‐4 

provide  whatever  means  necessary  to  complete  road  bores  even  if  rock  is encountered.  All line items referencing road bores shall include boring or tunneling as required.  No change orders shall be issued if rock is encountered during road boring. 

 3.02  INSTALLATION  

A. Perform  all  crossings  in  the  manner  shown  on  the  drawings,  except  as  otherwise directed by the governing highway department or railroad company. 

 B. Dry bore an opening under the crossing. 

 C. Jack the casing pipe, of the type and size specified, into the bored opening. 

 D. Install the appropriate carrier pipe into the casing pipe. 

 E. Test the carrier pipe according to the appropriate Utility Sections (02713 or 02722). 

 F. Alignment and grade shall be installed and maintained per the Contract Drawings. 

 G. Bores which are not on horizontal or vertical alignment shall be rebored.  Abandoned 

bore holes shall be filled with flowable fill.  

H. Install carrier pipe with casing spacers to maintain alignment inside casing pipe.  Casing spacers shall be installed 1 foot from each end of the pipe joint and at the midpoint. 

 I. Install casing end seals and casing vents upon completion of installation of carrier pipe. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 129: Standard Water and Sewer Specifications PDF

  TUNNELING  02726‐1 

SECTION 02726  

TUNNELING  

TABLE OF CONTENTS  

PART 1 – GENERAL  1.01  WORK INCLUDED  1 This item shall include the furnishing and installation of a tunnel with steel liner plates and carrier 

pipe.  2 The Contractor shall conform to all requirements of the Tennessee Department of Transportation 

or other governing highway department.  PART 2 – PRODUCTS  2.01  TUNNEL LINER PLATE  

A. The  tunnel  liner  shall be  constructed of 12 gauge, bituminous coated, galvanized, or Type 2,  aluminized  two or  four  flanged  steel  plates bolted  together  to  the diameter specified on the Contract Drawings, unless the Owner approves the use of an alternate material.  The space between the liner and the edge of excavation shall be filled with grout placed under pressure. 

 B. The steel lining shall consist of plates that have a minimum tensile strength of 42,000 

psi, minimum yield of 28,000 psi, elongation at 2 inches of 30% and do not exceed 18 inches in width.  Each circumferential ring shall be composed of the number and length of plates  to  complete  the  required diameter.    The Contractor  shall  submit details of the lining for approval. 

 C. All plates shall be punched for bolting on both longitudinal and circumferential seams 

and shall be so fabricated as to permit complete erection from the inside of the tunnel.  The longitudinal seam shall be of the lap type with offset equal to gauge of metal for full width  of  plates  including  flanges,  and  shall  have  staggered  bolt  construction,  so fabricated  as  to  allow  the  cross‐section  of  the  plate  to  be  continuous  through  the seam.  All plates shall be of uniform fabrication and those intended for one size tunnel shall be interchangeable. 

 D. The material used  for  the construction of  these plates  shall be new and unused and 

suitable  for  the  purpose  intended.    Plates  shall  be  fabricated  with  material  in accordance with ASTM A819 and AASHTO M274. 

  

Page 130: Standard Water and Sewer Specifications PDF

  TUNNELING  02726‐2 

E. After the plates are formed to shape and after all holes are punched, the plates shall be  galvanized  on  all  surfaces  by  the  hot‐dip  process.    A  coating  of  prime  western spelter, or equal, shall be applied at the rate of not less than 2 ounces per square foot of  double  exposed  surface.    If  the  average  spelter  coating  as  determined  from  the required  samples  is  less  than  the  amount  specified  above,  or  if  any  one  specimen shows a deficiency of 0.2 ounce, the lot shall be rejected.   Spelter coating shall be of first‐class  commercial  quality  free  from  injurious  defects  such  as  blisters,  flux  and uncoated spots. 

 F. All nuts and bolts shall be galvanized and shall be fabricated in accordance with ASTM 

A307, Grade A.  

G. Plates shall be fabricated with grout holes to facilitate grouting above and around the tunnel  liner.   These grout openings shall be 2‐inch  I.P.T. half couplings welded  into a hold in the center corrugation of a plate and a galvanized C.I. plug shall be provided for each  opening  to  permit  tight  closure  after  grout  is  pumped.    All  rings  are  to  be provided with grout holes so that the spacing of holes will be on a maximum spacing of 18‐inch centers at the top of the tunnel and at the top quarter points, staggered with the holes at the top. 

 2.02  GROUT  

The grout shall consist of Portland cement, water, sand and 2% approved additive (Bentonite, Septamine  Seaex,  Hydrocide  liquid,  etc.).    One  part  Portland  cement with  additive  shall  be combined to four parts clean sand and sufficient water added to provide a grout having the consistency of thick cream when well mixed. 

 2.03  CARRIER PIPE  

The carrier pipe shall be as specified in the Contract Drawings.   PART 3 – EXECUTION  3.01  EXCAVATION  

A. Excavation  shall  be  unclassified  and  no  distinction  shall  be made  between  rock  and other materials excavated.   Blasting  is acceptable only with explicit written approval from the authority having jurisdiction over tunneled area. 

 B. Construction of the tunnel shall be carried out in such a manner that settlement of the 

ground  surface  above  the  tunnel  shall  be  held  to  an  absolute  minimum.    Where ground conditions are unstable, poling plates or poling boards shall be used to prevent caving of material above the tunnel before the liner plates can be installed.  Steel liner plates  shall  be  installed  as  soon  as  possible  after  the  excavation  is  removed  and 

Page 131: Standard Water and Sewer Specifications PDF

  TUNNELING  02726‐3 

excavation  shall  not  be  removed  more  than  24  inches  ahead  of  the  installed  liner plates.    Excavation  shall  be  carried  on  in  such  a manner  that  voids  behind  the  liner plates will be held to a minimum.  However, should any boulders larger than 12 inches in  diameter  be  encountered,  they  shall  be  removed  so  that  none  are  closer  than  6 inches to the outer face of the liner plate.   Where boulders are excavated below the invert of  tunnel  liner plates,  the holes  shall be backfilled with crushed stone  (#57 or 67). 

 3.02  LINER PLATE  

A. When installing liner plate by the tunneling method, the excavation shall be performed in such a manner that voids between the undisturbed earth and the liner plate shall be maintained at a minimum.   Any void occurring shall be filled with a Portland cement and sand grout pumped under pressure through grouting openings in the liner plate. 

 B. The minimum provision  for grouting openings  shall be one opening  in a  top plate of 

the tunnel at locations not to exceed 54 inches apart.  Additional plates with grouting openings are  to be  installed at  the  top quarter points on each side between the  top openings.   The opening shall be staggered, but shall not exceed 54 inches in any one line.  Grout vent pipes will be required at a minimum of one per monolithic pour. 

 3.03  GROUTING  

A. A pump capable of exerting sufficient pressure to assure the filling of all voids between the  liner  plate  and  the  undisturbed  ground  shall  be  provided  for  placing  the  grout.  Minimum acceptance pressure to fill voids will be five pounds per square inch. 

 B. Pumping  of  grout  shall  be  done  (1)  at  the  completion  of  the  installation  of 

approximately each 9 feet of  liner plate,  (2) at more frequent  intervals than 9 feet  if conditions  indicate  the  necessity,  and  (3)  at  the  end  of  a work  shift  or  for  stopping work for any reason. 

 3.04  CARRIER PIPE  

A. Contractor  shall  jack  the  pipe  by  means  of  air  bladders,  blocks,  or  other  suitable method.    Once  carrier  pipe  is  established,  Contractor  shall  pour  a  lean  concrete bedding for the carrier pipe. 

 B. The carrier pipe shall be adequately  strapped  to  the  tunnel  flanges behind each bell 

with 2”  x ¼”  stainless  steel  straps bolted  to  the  liner plate  flanges with ½”  stainless steel  bolts  and  nuts.    Concrete  bulkheads will  be  placed  at  each  end  of  the  tunnel; thickness and placement of which shall be subject to the Engineer’s approval. 

 

Page 132: Standard Water and Sewer Specifications PDF

  TUNNELING  02726‐4 

3.05  BACKFILL  

Backfill of the tunnel shall consist of sand, #57 crushed stone, or pea gravel and shall be blown into the tunnel to fill the void between the inside wall of the tunnel and the outside edge of the carrier pipe to the top of the carrier pipe. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 133: Standard Water and Sewer Specifications PDF

  HORIZONTAL DIRECTIONAL DRILLING  02727‐1 

SECTION 02727  

HORIZONTAL DIRECTIONAL DRILLING  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A.  Furnish all materials and equipment necessary for the horizontal directional drilling of utility lines as called for on the Contract Drawings. 

 A. Provide all labor, equipment and materials to perform the directional bore. 

 C.  Comply with all permits and conditions related to the work for this location. 

 1.02  RELATED WORK  

A. Section 02713:  Water Distribution Systems  

B. Section 02722:  Sanitary Sewer Systems   PART 2 ‐ PRODUCTS  2.01  DUCTILE IRON PIPE  

Where  indicated  on  the  Contract  Drawings,  restrained  joint  ductile  iron  pipe  equivalent  to American Flex Ring or U.S. Pipe T.R. Flex with minimum pressure class 350 shall be used for directional bores. 

 2.02  HIGH DENSITY POLYETHYLENE PIPE (HDPE)  

A. HDPE pipe shall only be used for directional bores as approved by the City Engineer.  

B. Pipe  shall  have  a  DR  number  9 with  a working  pressure  of  200  psi  and  be  sized  to provide  inside  diameter  equal  to  or  greater  than  the  size  shown  on  the  Contract Drawings. 

 C. Materials:    Polyethylene  pipe  and  fittings  shall  be  made  from  resin  meeting  the 

requirements  of  the  Plastic  Pipe  Institute  as  PE  3408.    The  resin  shall  meet  the requirements  of  ASTM  D3350‐02  with  a  cell  classification  of  345464C.    The requirements of this cell classification are: 

 

Page 134: Standard Water and Sewer Specifications PDF

  HORIZONTAL DIRECTIONAL DRILLING  02727‐2 

HDPE Resin Specifications  Property      Specification    Unit            Typical Value Material Designation    PPI/ASTM          PE 3408 Material Approval    NSF #14             Material Classification   ASTM D1248          III C5 P34 Cell Classification    ASTM D3350‐02        345464C   Density    ASTM D1505    g/cm3      0.955   Melt Index    ASTM 1238    gm/10 min    0.11   Flexural Modulus  ASTM D790    psi      135,000   Tensile Strength  ASTM D638    psi      3,200   Slow Crack Growth   

ESCR    ASTM D1693    hours in 100% igepal  >5,000 PENT    ASTM F1473    hours      >100 HDB @73 deg F  ASTM D1693    psi      1,600 UV Stabilizer  ASTM D1603    %C      2.5% 

 D. Butt  Fusion  Fittings:    HDPE  fittings  shall  be  PE  3408,  HDPE,  Cell  Classification  of 

346464C as determined by ASTM D3350‐02,  and approved  for potable water use by the AWWA.  Butt fusion fittings shall have a manufacturing standard of ASTM D3261.  Molded  and  fabricated  fittings  shall  have  a  pressure  rating  equal  to  the  pipe  unless otherwise specified in the plans.  Fabricated fittings are to be manufactured using data loggers.  Temperature, fusion pressure and a graphic representation of the fusion cycle shall  be  part  of  the Quality  Control  records.    All  fittings  shall  be  suitable  for  use  as pressure conduit, and per AWWA C906, have a nominal burst value of 3.5  times  the working pressure rating of the fitting. 

 E. Pipe Manufacturer’s  Quality  Control:    The  pipe manufacturer  shall  have  an  ongoing 

Quality  Control  program  for  incoming  and  outgoing  materials.    HDPE  resins  for manufacturing of pipe shall be checked for density, melt flow rate, and contamination.  The manufacturer of the HDPE resin shall certify the Cell Classification as indicated in Paragraph C above.  These incoming resins shall be approved by plant Quality Control and verified as approved by NSF before being converted to pipe.  Pipe shall be checked for  outside  diameter,  wall  thickness,  length,  roundness  and  surface  finish  on  the inside, outside and end cut. 

 F. HDPE pipe shall be  joined together at  the transition points  to other mechanical  joint 

adapters.    Mechanical  joint  adapters  shall  have  a  manufacturing  standard  of  ASTM D3261.  They shall have a pressure rating equal to the pipe. 

 G. A minimum of 100  feet of  restrained  joint ductile  iron pipe shall be provided on  the 

pipe  preceding  and  the  pipe  following  the  HDPE.    Appropriate  restraint  methods include using restrained joints equivalent to American Flex Ring or U.S. Pipe T.R. Flex. 

  

Page 135: Standard Water and Sewer Specifications PDF

  HORIZONTAL DIRECTIONAL DRILLING  02727‐3 

PART 3 ‐ EXECUTION  3.01  SCOPE OF WORK  

A. Fabricate, directionally drill and install pipe as called for on the Contract Drawings.  B. Hydrostatically pressure test the pipe in accordance with the requirements of Sections 

02713 or 02722, as appropriate.  

C. Provide  complete  copies  of  as‐built  drawings  for  the  pipeline  crossing.    As‐built drawings shall include plan view and profile view.  

D. Clean up all affected sites, and restore all areas to pre‐construction condition.  3.02 SUBMITTALS  

The Contractor shall prepare a schedule for the work and submit to the Engineer for approval.  The schedule shall include all major tasks to be performed including the following: 

 A. Pipe delivery. 

 B. Rig mobilization and setup. 

 C. Pipe assembly. 

 D. Pilot hole drilling. 

 E. Pre‐reaming. 

 F. Pre‐testing and pigging before installation. 

 G. Pipe pulling. 

 H. Pre‐testing and pigging pipe after reinstallation. 

 I. Restoration and demobilization. 

 3.03 EQUIPMENT AND MATERIALS TO BE FURNISHED BY THE CONTRACTOR  

The Contractor  shall  furnish  all  equipment  and material  required  to  complete  the  Scope of Work that shall include but not be limited to the following: 

 A. Drilling equipment. 

 

Page 136: Standard Water and Sewer Specifications PDF

  HORIZONTAL DIRECTIONAL DRILLING  02727‐4 

B. Water  pumps,  hoses,  fittings,  storage  tanks,  filters,  and  erosion  prevention  and sediment control measures as required. 

 C. Drilling fluids containment, collection, cleaning and disposal equipment, and materials. 

 D. Fuel and lubricants. 

 E. Bentonite and related mixing equipment. 

 F. Carrier pipe 

 G. All welding equipment for HDPE as required. 

 H. All hydrostatic and pneumatic testing equipment and materials. 

 I. Sidebooms, cranes, backhoes, trucks, and other equipment and materials necessary to 

load and unload and  to  support and smoothly  transition  the pipe while being pulled into the reamed hole. 

 J. All  equipment  and  materials  necessary  to  restore  project  areas  to  pre‐existing 

condition or better.  3.04 INSTALLATION  

A. General: The Contractor shall  install appropriate sections of the pipeline indicated on the Contract Drawings  by  the horizontally  drilled,  directionally  controlled method of construction.    This  method  shall  consist  of  the  drilling  of  a  pilot  hole  within  the designated tolerances for radius requirements, followed by enlargement of the hole to accommodate the carrier pipe. 

 B. Instrumentation:  The  Contractor  shall  at  all  times  provide  and  maintain 

instrumentation that will accurately locate the pilot hole in the X, Y and Z axis relative to the ground surface.  Drill fluid flow rate and pressure must also be monitored. 

 C. Tolerances: 

1. A  smoothly  drilled  pilot  hole  shall  follow  the  design  centerline  of  the  pipe profile and alignment  indicated on the Contract Drawings.   At no point  in the bore  will  the  combined  radii  in  the  plan  and  profile  exceed  the  allowable minimum radius recommended by the pipe manufacturer. 

2. The course of the pilot hole must stay within the given right‐of‐way at all points along  the drilled  route.    Contractor  shall  provide and use a  separate  steering system employing a ground survey grid system, such as “Tru‐Tracker”. 

3. The Contractor  shall  have accurate working gauges  that  register  tensile  force being  used  to  pull  the  pipeline  back  through  the  reamed borehole.    It  is  the Contractor’s  responsibility  to prepare the reamed out hole such that pullback 

Page 137: Standard Water and Sewer Specifications PDF

  HORIZONTAL DIRECTIONAL DRILLING  02727‐5 

operations do not exceed the tensile strength of the pipe.  The Contractor shall provide estimated calculations for the pulling loads and allowable loads before pull  back  operations  begin.      If  during  the  pipeline  pulling  process  this  force reaches 75 percent of the allowable load for the pipeline, the project inspector shall be notified  immediately.   Logs must be kept  intact  referencing all  forces exerted on the pipeline during pullback. 

4. The  Contractor  shall  provide  adequate  supports  along  the  stringing  area  to protect the pipe and allow free movement of the pipeline during pullback. 

5. During pullback operations, Contractor  shall monitor  roller operation and use sidebooms if required to assist movement of the pipe.  Situations, which could cause damage to the pipe material, shall be corrected immediately.  Damaged pipe shall be replaced by the Contractor before pulling operations resume. 

 3.05  DRILLING AND MUD CUTTINGS  

A. The horizontal directional drilling operation is to be operated in a manner to eliminate discharge  of  water,  drilling  mud  and  cuttings  into  the  creek  or  land  areas  involved during  the  construction process.    Contractor  shall  immediately  contain  and  clean up any  inadvertent  returns,  spills  or  releases.    Contractor  shall  also  provide  equipment and procedures to maximize the re‐circulation and reuse of drilling mud to minimize waste disposal. 

 B. Disposal  of  drilling  fluids  shall  be  the  responsibility  of  the  Contractor  and  shall  be 

conducted  in  strict  compliance  with  all  applicable  environmental  regulations  and permit requirements.  All costs related to disposal shall be borne by the Contractor. 

 C. Water supply  is  the Contractor’s responsibility, whether purchased  locally, hauled  in, 

or pumped  from  the creek.    If pumped  from  the creek,  the Contractor must  comply with  the  rules  and  regulations  of  the  Tennessee  Department  of  Environment  and Conservation. 

 D. Drilling fluids must be free of all additives that will adversely affect the environment. 

 3.06  REAM AND PULLBACK  

A. Pre‐reaming:    Pre‐reaming  operations  shall  be  conducted  at  the  discretion  of  the horizontal  drilling  Contractor.    All  provisions  of  this  specification  relating  to simultaneous  reaming  and  pulling  back  operations  shall  also  pertain  to  pre‐reaming operations. 

 B. Pulling  Loads:    Contractor  shall  be  responsible  for  determining  safe  pulling  loads 

required for proper installation.  Such loads shall be minimized as required to prevent failure of the pipeline during installation. 

 

Page 138: Standard Water and Sewer Specifications PDF

  HORIZONTAL DIRECTIONAL DRILLING  02727‐6 

C. Torsional Stress:  A properly sized and fully operational swivel will be installed between the reaming assembly at the end of the drill pipe and the pipeline to restrict torsional stress from being transmitted to the pipeline. 

 D. Pull  Section  Support:    The  pull  section  shall  be  supported  as  it  proceeds  during  pull 

back so that it moves freely and the pipe material is not damaged.  3.07  INSTALLING HDPE PIPE  

A. HDPE  pipe  shall  be  assembled  utilizing  field‐site  butt  fusion  joints.    Personnel performing butt fusion joining shall be certified by pipe manufacturer. 

 B. Each piece of pipe must be held by a clamping device so it will not move and pipe ends 

shall be faced to establish clean mating surfaces.   Pipe profiles must be rounded and aligned with each other to prevent mismatch of pipe walls. 

 C. Heat  the  ends  of  the  pipe  to  the  pipe  manufacturer’s  recommended  temperature, 

interface  pressure,  and  time  duration.    Keep  heater  faces  clean  to  prevent  molten plastic from sticking to the heater faces. 

 D. After heating, remove heater tool and bring molten pipe ends together with sufficient 

pressure to form a homogenous joint.  Hold the molten joint immobile under pressure until cooling has occurred and joint achieves strength. 

 E. After  installation,  the  pipe  shall  be  tested  in  accordance  with  the  requirements  of 

Section 02713 or 02722, as appropriate.  3.08  CLEANUP, REPAIRS AND RESTORATION  

A. The Contractor is responsible for leaving all areas affected by his construction activities in a condition equal to or better than the condition before construction. 

 B. The Contractor shall fully restore all area around entry and exit pits as soon as work is 

completed.    Fill  to  previous  existing  ground  elevation  and  grade  any  areas  where settlement occurs due to subsidence. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 139: Standard Water and Sewer Specifications PDF

  CHAIN‐LINK FENCES AND GATES  02821‐1 

SECTION 02821  

CHAIN‐LINK FENCES AND GATES  

TABLE OF CONTENTS  PART 1 – GENERAL  1.01  WORK INCLUDED  

Construct  chain  link  fences,  gates  and  appurtenances  in  accordance  with  the  Contract Drawings and these specifications. 

 1.02  SUBMITTALS  

A. Product Data: For each product indicated  

B. Shop  Drawings:  Show  locations,  components,  materials,  dimensions,  sizes,  weights, finishes  of  components,  installation  and  operational  clearances,  gate  swings,  and details of post anchorage and attachment and bracing. 

 1.03 RELATED WORK  

Section 03300:  Cast‐In‐Place Concrete   PART 2 – PRODUCTS  2.01  CHAIN‐LINK FENCE FABRIC  

A.  Steel Chain‐Link Fence Fabric: Comply with Chain Link Fence Manufacturers Institute’s “Product Manual” and AASHTO M181. 

 B. Mesh  and  Wire  Size:  2‐inch  (50‐mm)  mesh,  0.120‐inch  (3.05‐mm)  diameter.  Vinyl 

coated, Type 1, Class D, color as specified by Owner.  

C. Fabric Selvage:  Twisted at top selvage and knuckled at bottom.  2.02  LINE POSTS  

A. The  line posts  shall  be one of  the  following  types,  and of  the  lengths  shown on  the Contract Drawings.   They shall be 1.5  inch (1.900 O.D.) galvanized steel pipe meeting the  requirements of ASTM A53, or  (1.875  inch by 1.625  inch) galvanized  rolled  form steel Standard C‐Section meeting the requirements of ASTM A570 Grade E, or (1.875 inch by 1.625 inch) galvanized H‐Section or O.D. (1.5 inch (1.900 O.D.)) aluminum‐alloy 

Page 140: Standard Water and Sewer Specifications PDF

  CHAIN‐LINK FENCES AND GATES  02821‐2 

standard (ANSI Schedule 40) pipe meeting the requirements of ASTM B241, Alloy 6063, Temper  T6,  or  1.5  inch  (1.900  O.D.)  triple  coated  steel  pipe  with  a  (0.120  inch) minimum wall thickness. 

 B. The pipe shall be manufactured by cold rolling and electric resistance welding of steel 

strip conforming to ASTM A569, ASTM A607 or ASTM A446, Grade D.  All tubing shall be given corrosion protection by in‐line application of hot‐dip galvanizing, followed by a  chromate  conversion  coating  and  an  electrostatically  applied  clear  acrylic  or polyester coating on the outside surface.   The  inside surface shall be given corrosion protection  by  hot‐dip  galvanizing  or  by  in‐line  application  of  a  zinc  rich  paint  after fabrication. 

 C. External Protective Coatings: 

1. Hot‐Dipped Zinc Coating per ASTM B6 high grade and special high grade.  The weight  of  the  hot‐dipped  zinc  coating  shall  be  a minimum  of  245  grams  per square meter  (0.8 oz/s.f.).    The weight of  zinc  coating  shall be determined  in accordance with ASTM A90. 

2. The electrostatically applied clear acrylic or polyester coating thickness shall be at least 2.5 µm (0.1 mils). 

 D. Internal Protective Coatings:  The interior surface shall be hot‐dipped galvanized with a 

minimum of 25 grams (0.9 ounce) of zinc, or painted after welding with a 7.5 µm (0.3 mil) thickness of zinc rich paint.  The coating shall be not less than 80% zinc powder by weight and capable of providing galvanic protection. 

 2.03 END POSTS, CORNER POSTS, GATE POSTS AND BRACES  

A. The end and corner posts shall be 2.5 inch galvanized standard steel pipe meeting the requirements of ASTM A53, or 2.5  inch, aluminum alloy standard (ANSI Schedule 40) pipe,  meeting  the  requirements  of  ASTM  B241,  Alloy  6063,  Temper  T6,  or  2.5  inch triple coated steel pipe with a  (0.130  inch) minimum wall  thickness and meeting the specified requirements as set forth under Paragraph 2.02.  End and corner post length shall be 9’‐6”. 

 B. End and corner post braces  shall be 1.25  inch  (1.660 O.D.) galvanized standard steel 

pipe meeting the requirements of ASTM A53, or 1.25 inch (1.660 O.D.) aluminum‐alloy standard  (ANSI  Schedule  40)  pipe,  meeting  the  requirements  of  ASTM  B241,  Alloy 6063,  Temper  T6,  or  1.25  inch  (1.660  O.D.)  triple  coated  steel  pipe  with  a  2.8mm (0.111  inch) minimum wall  thickness  and meeting  the  specified  requirements  as  set forth in Paragraph 2.02. 

 C. Gate Posts shall be 3.0 inch galvanized standard steel pipe meeting the requirements 

of ASTM A53, or 3‐inch aluminum‐alloy standard (ANSI Schedule 40) pipe meeting the requirements of ASTM B241, Alloy 6063, Temper T6.  Gate post length shall be 10’‐0”. 

 

Page 141: Standard Water and Sewer Specifications PDF

  CHAIN‐LINK FENCES AND GATES  02821‐3 

2.04  BARBED WIRE  

A. The  barbed wire  shall  consist  of  three  (3) No.  12‐1/2  gauge  twisted  steel  line wires with No. 14 gauge four‐point barbs spaced not more than 125 mm (5 inches) apart.  It may  be  either  galvanized  or  aluminum  coated.    The  galvanized wire  shall meet  the requirements of ASTM A121, chain link fence grade.  

B. At the option of the Contractor, high tensile strength barbed wire may be used.  If the Contractor  elects  to  furnish  high  tensile  strength  barbed  wire,  it  shall  meet  the requirements of ASTM A121 with the following exceptions: 1. The coated  line wires  shall have a nominal diameter of 1.70mm (0.067  inch).  

The  coated  barbed  wires  shall  have  a  nominal  diameter  of  1.45mm  (0.057 inch). 

2. The minimum weight of zinc coating shall be 230 grams per square meter (0.75 ounce/s.f.) for the line wire and 215 grams per square meter (0.70 ounce/s.f.) for the barbed wire. 

3. The  line wire  shall have a minimum tensile  strength of 2.10 kN  (475 pounds) per individual strand. 

 C. Aluminum alloy barbed wire shall consist of three (3) twisted strands of 2.8mm (0.110 

inch) line wire with 2mm (0.080 inch) diameter four‐point barbs spaced not more than 125mm (five inches) apart.  The wire and barbs shall meet the requirements of ASTM B211 alloys of 5052‐0 for the wire and 5052‐H38 for the barbs. 

 2.05  MISCELLANEOUS FITTINGS AND HARDWARE  

A. Zinc‐coated miscellaneous  fittings  and  hardware  shall  be  commercial  grade  steel  or better quality, pressed, wrought or cast as appropriate to the article, and sufficient in strength and other properties to provide a balanced design when used in conjunction with  fabric,  posts  and  wires  of  the  quality  specified  herein.    All  steel  fittings  and hardware shall be galvanized in accordance with AASHTO M111. 

 B. Aluminum  alloy  miscellaneous  fittings  and  hardware  shall  be  wrought  or  cast 

aluminum to the requirements of AASHTO M181, Table I.  2.06  WIRE TIES  

Wire  ties  shall  be  No.  9  gauge  and  shall  be  zinc‐coated  steel,  aluminum‐coated  steel,  or aluminum alloy, sufficient in strength and other properties to provide a balanced design when used in conjunction with fabric, posts and wire of the qualities specified herein. 

 2.07  TENSION WIRE  

Tension wire shall meet the requirements of AASHTO M181.  

Page 142: Standard Water and Sewer Specifications PDF

  CHAIN‐LINK FENCES AND GATES  02821‐4 

2.08 TRUSS RODS AND TURNBUCKLE  

Truss rods shall be 9.5mm (3/8 inch) diameter, shall be equipped with a turnbuckle having a take‐up  of  not  less  than  100mm  (four  inches)  and  shall  be  galvanized  in  accordance  with AASHTO M111. 

 2.09 POST TOPS AND EXTENSION ARMS  

A. Posts shall be fitted with ornamental tops or extension arms as shown on the Contract Drawings.  The post tops shall fit over the outside of posts and shall exclude moisture from posts. 

B. Extension arms shall be vertical or extend out from the fence line at approximately 45 degrees  as  shown  on  the  Contract  Drawings.    The  extension  arms  shall  be  suitably notched or slotted to support and space the barbed wire. 

 C. Fabrication  of  all materials  shall  be within  reasonable  close  conformity  to  the  sizes, 

shapes and dimensions and other factors set out  in these specifications or shown on the Contract Drawings, and shall display careful, finished workmanship. 

 D. The  weights  specified  for  steel  posts,  braces  and  rails  are  nominal  weights,  and  a 

tolerance of +/‐ 5% will be permitted.  2.10  GATES  

A. Fence gates shall be of the types and sizes shown on the Contract Drawings.  They shall be  swing‐type,  complete with  latches,  stops,  keepers,  hinges,  and  fabric.    The  latch shall have a provision  for  fastening with a padlock.    The gates  shall be  covered with fabric matching  the  fence.    The hinges  shall  be of  adequate  strength  to  support  the gate and shall not  twist or  turn under action of  the gate.   The gates, gate posts and braces shall be of the same kind and finish as the adjoining fence.  All gate posts and rails shall be furnished with ball caps and rail ends. 

 B. Posts, braces and framing members for chain‐link fence gates shall be standard weight 

pipe meeting the requirements of Paragraph 2.03.  

C. Fabric for chain‐link fence gates shall meet the requirements of Paragraph 2.01.  

D. Barbed wire for chain‐link fence gates shall meet the requirements of Paragraph 2.04.  

E. Miscellaneous  fittings  and  accessories  for  chin‐link  fence  gates  shall  meet  the applicable  requirements  of  Paragraphs  2.05,  2.06,  2.07,  2.08,  and  2.09.    The  hinges shall be of such design to allow the gate to swing back 180 degrees, parallel with the fence line. 

  

Page 143: Standard Water and Sewer Specifications PDF

  CHAIN‐LINK FENCES AND GATES  02821‐5 

2.11  CAST‐IN‐PLACE CONCRETE  

A. General:  Comply with ACI 301 for cast‐in‐place concrete.  Use materials consisting of Portland  cement  complying with ASTM C150,  aggregates  complying with ASTM C33, and potable water. 

 B. Concrete Mixes:  Class A as set forth in Section 03300. 

  PART 3 – EXECUTION  3.01  INSTALLATION  

A. General:    Install  chain‐link  fencing  to  comply  with  ASTM  F567  and  more  stringent requirements  if  indicated on the Contract Drawings or required by the Engineer.   Do not begin installation before final grading is completed, unless otherwise permitted by Engineer.  All fence installers shall carry insurance coverage as required by the City. 

 B. Post  Excavation:  Drill  or  hand‐excavate  holes  for  posts  to  diameters  and  spacing 

indicated, in firm, undisturbed or compacted soil.  

C. Post  Setting:  Hand‐excavate  holes  for  post  foundations  in  firm,  undisturbed  or compacted soil. 1. Concrete  Footings:  Place  concrete  around  posts  and  vibrate  or  tamp  for 

consolidation.   Verify  that posts are set plumb, aligned, and at correct height and  spacing,  and  hold  in  position  during  placement  and  finishing  operations until  concrete  is  sufficiently  cured.    Set  the  following  post  types  in  concrete footings and protect portion of posts above ground from concrete splatter: a) Terminal. b) Line;  using  mechanical  devices  to  set  line  posts  per  ASTM  F567  is 

permitted. c) Gate. d) Gate operator mounting. 

2. Pull  shall not be applied to posts set  in concrete until  the concrete has cured for a minimum of 72 hours. 

 D. Terminal  Posts:  Locate  terminal  end,  corner,  and  gate  posts  per  ASTM  F567  and 

terminal pull posts at changes  in horizontal or vertical alignment.   Terminal and gate posts shall be set in a minimum of 30” of concrete. 

 E. Line Posts: Space line posts uniformly at 10 feet (3.05m) o/c.  Line posts shall be set in 

a minimum of 24” of concrete.  

F. Intermediate Rails:  Install  in one piece at post‐height center  span,  spanning between posts, using fittings, special offset fittings, and accessories. 

Page 144: Standard Water and Sewer Specifications PDF

  CHAIN‐LINK FENCES AND GATES  02821‐6 

 G. Bottom Rails: Install, spanning between posts, using fittings and accessories. 

 H. Chain‐link Fabric: Apply fabric to outside of enclosing framework. 

 I. Tie Wires: Attach wire to chain‐link  fabric per ASTM F626.   Tie  fabric to  line posts at 

maximum interval of 12 inches (304 mm) o/c. and to braces at maximum interval of 24 inches (609mm) o/c. 

 J. When aluminum‐alloy fabric is used, a tension wire shall be attached to the bottom of 

the  fabric  by  means  of  a  hog‐ring  type  fastener  at  a  maximum  of  600mm  (2  foot) intervals and secured at the terminal posts by means of a brace band. 

 K. Gate  Installation:  Install  gates  level,  plumb,  and  secure  for  full  opening  without 

interference.    Attach  hardware  using  tamper‐resistant  or  concealed  means.    Install ground‐set items in concrete for anchorage.  Adjust gate to operate smoothly, easily, and  quietly  throughout  entire  operational  range.    Confirm  that  latches  and  locks engage accurately and securely without forcing or binding. 

L. Electrical grounds shall be constructed at each corner.  A No. 6 solid copper conductor shall be clamped to the nearby ground system and to the fence in such a manner that each element of the fence is grounded.  Installation of ground rods shall not constitute a pay item and shall be considered incidental to fence construction. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 145: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐1 

SECTION 03300  

CAST‐IN‐PLACE CONCRETE  

TABLE OF CONTENTS  

PART 1 ‐ GENERAL  1.01 WORK INCLUDED  

This work shall consist of all labor, materials, equipment, and incidentals required to install all concrete work, whether plain or reinforced, as shown on the Contract Drawings. 

 1.02 RELATED WORK  

A. Section 02221:  Trenching, Bedding, and Backfilling  

B. Section 02713:  Water Distribution Systems  

C. Section 02722:  Sanitary Sewer Systems  1.03 SUBMITTALS  

Submit concrete mix design for each mix proposed for use identifying constituent quantities per cubic yard, including admixtures, water‐cement ratio, and type of cement. 

 1.04 QUALITY ASSURANCE  

A. Measuring, batching, mixing, and transporting concrete shall conform to ASTM C94.  

B. Perform work in accordance with ACI 301.  

C. Conform to ACI 305 when concreting during hot weather.  

D. Conform to ACI 306 when concreting during cold weather.  

E. All detailing, fabrication, and erection of reinforcing steel shall conform to ACI 315.  

F. Reinforced concrete shall conform to ACI 318.   PART 2 – PRODUCTS  2.01  MATERIALS  

Page 146: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐2 

A. Water:    Water  used  in  mixing  concrete  shall  be  reasonably  clean  and  free  from objectionable  substances  such  as  oils,  acids,  alkalis,  organic matter,  clay  and  silt,  or other deleterious substances. 

 B. Portland  Cement:    Cement  shall  be  domestic  Portland  cement  and  shall  conform  to 

ASTM  C150.  Cement  shall  be  Type  I  or  Type  II  unless  otherwise  specified  by  the Engineer. Fly ash is not an acceptable substitute for Portland cement. 

 C. Fine  Aggregate:    Fine  aggregate  shall  be  washed,  inert  natural  sand  conforming  to 

ASTM C33.  

D. Coarse  Aggregate:    Coarse  aggregate  shall  be  well‐graded  crushed  stone  or  gravel conforming to ASTM C33 and shall be size No. 57. 

 E. Admixtures: 

1. Air  entraining  admixtures, mandatory  for  concrete  exposed  to weather,  shall comply with ASTM C260. Proportioning and mixing shall be in accordance with manufacturer’s recommendations. 

2. Water  reducing  admixtures  shall  comply  with  ASTM  C494,  Type  A. Proportioning  and  mixing  shall  be  in  accordance  with  manufacturer’s recommendations. 

3. The use of admixtures to retard setting of concrete during hot weather and to accelerate  setting of  concrete during  cold weather  shall  not be used without approval of the Engineer. Where approved, these admixtures shall comply with ASTM  C494.  Proportioning  and  mixing  shall  be  in  accordance  with manufacturer’s recommendations. 

 F. Steel Welded Wire Fabric:  Steel welded wire fabric for reinforcement shall conform to 

ASTM A185.  

G. Steel Reinforcing Bars:    Steel  reinforcing bars  shall be deformed,  intermediate grade steel conforming to ASTM A615 Grade 60. 

 H. Tie Wires:  Tie wires for reinforcing steel shall be 16 gauge or heavier, black annealed 

wire.  2.02  CLASSES OF CONCRETE MIXES AND USES  

A. Select  proportions  of  constituents  to  meet  the  design  strength  and  material  limits specified  in  Table  I  and  to  produce  concrete  having  proper  placability,  durability, strength, appearance, and other required properties. 

  

Page 147: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐3 

Class  Design  Strength psi (1) 

Cement Type (2) 

Cement Content (3) 

W/C (4) 

Slump  Range Inches (5) 

Air  Content % (6) 

A  4000  II  564  0.45  3‐5  5‐7 

B  3000  I  470  0.56  3‐5  5‐7 (1) Minimum compressive strength at 28 days in accordance with ASTM C39 

  (2) In accordance with ASTM C150   (3) Minimum cement content is lbs/cu. yd. of concrete   (4) Water‐to‐cement ratio   (5) In accordance with ASTM C143 

(6) Where concrete is exposed to freeze‐thaw conditions, the concrete shall be air‐entrained with air content of 6% +/‐ 1% according to ASTM C231.  Otherwise, air entrainment is not required. 

 B. Concrete shall be as follows: 

1. Class A concrete shall be used for all concrete work except as noted below. All reinforced concrete shall be Class A. 

2. Class  B  concrete  may  be  used  for  thrust  blocks,  concrete  cradles,  concrete anchors, concrete caps, concrete encasement, fill concrete, and where directed on the Contract Drawings. 

 C. Pumping of concrete will be permitted when approved design mix and aggregate sizes, 

suitable for pumping, are used.   PART 3 – EXECUTION  3.01  FORMS  

A. Construction: 1. Forms  shall be mortar‐tight and  sufficiently  rigid  to prevent distortion due  to 

the pressure of the concrete and other stresses  incidental to the construction operations, including vibration. 

2. The  forms  shall  be  built  true  to  line  and  grade  and  shall  be  held  in  place  by means  of  studs  or  uprights,  and  whaling,  which  shall  be  sufficiently  and substantially braced and tied. 

 B. Form Lumber:  Form lumber for all exposed concrete surfaces shall be dressed at least 

on  one  side  and  two  edges,  and  shall  be  so  constructed  as  to  produce mortar‐tight joints and smooth, even concrete surfaces. 

 C. Metal Ties:   Metal  ties or anchorages within  the  forms shall be so constructed as  to 

permit the removal to a depth of at  least one  inch for the face without  injury to the concrete. 

 D. Walls:    Sufficient  openings  shall  be  provided  at  intervals  along  the  bottom  of  wall 

forms to permit thorough cleaning prior to concrete placement.   Such openings shall be closed before placing concrete in the forms. 

Page 148: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐4 

 E. Surface  Treatment:    Prior  to  placing  reinforcement,  all  forms  shall  be  treated  to 

prevent the adherence of concrete.  Forms not provided with a special treatment shall be  treated  with  an  approved  oil.    Any  material  that  will  adhere  to  or  discolor  the concrete shall not be used. 

 F. Metal Forms:  The metal used for forms shall be of such thickness that the forms will 

remain  true  to  shape.    All  bolt  heads  shall  be  countersunk  on  the  face  forming  the concrete surface.  Clamps, pins or other connecting devices shall be designed to hold the forms rigidly together and to allow removal without injury to the concrete. 

 G. Removal of Forms:  Forms shall be removed in such a manner as not to impair safety 

and serviceability of the structure.  Concrete to be exposed by form removal shall have sufficient strength not to be damaged by removal operation. 

 3.02  REINFORCEMENT  

A. All  reinforcement  shall  consist  of  deformed  steel  bars meeting  the  requirements  of ASTM A615 Grade 60, unless otherwise indicated or directed. 

 B. Steel welded wire fabric may be furnished in rolls or sheets. 

 C. Reinforcing  steel  shall  be  stored  above  the  ground  surface  upon  platforms,  skids  or 

other supports.  

D. Reinforcing  steel, where  indicated,  shall  be  accurately  bent, without  heating,  to  the forms and dimensions indicated on the plans. 

 E. All  reinforcement  shall  be  furnished  in  the  full  length  shown  on  the  plans,  unless 

otherwise approved in writing by the Engineer.  

F. Steel welded wire fabric shall be spliced by overlapping of the sheets by not less than 1‐1/2  courses  or  12  inches,  whichever  is  greater,  and  tied  together  with  wire  ties spaced no more than 24 inches on center. 

 G. All  reinforcing  steel,  before  being  placed,  shall  be  thoroughly  cleaned  of  mill  scale, 

rust, dirt, paint, oil, or other  foreign substances or coating of any character  that will reduce the bond.  When there is a delay in depositing concrete after the reinforcement is in place, bars shall be re‐inspected and cleaned when necessary. 

 H. Unless otherwise shown, splices in reinforcing steel shall be lapped in conformity with 

ACI 318, but no  less  than 24 bar diameters. All  bar  splices  shall  be  staggered where possible.  When splicing bars of different diameters, the length of lap is based on the larger bar. 

 

Page 149: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐5 

I. Reinforcement shall be accurately placed and firmly held in position with metal clips or tie wire at each intersection as indicated on the plans or as directed by the Engineer. 

 J. Supports for reinforcement when in contact with the foundation material shall be pre‐

cast concrete block bar supports or steel chairs.  Maintain minimum concrete cover of 3 inches or as indicated on the plans. In no case shall reinforcement be in contact with ground or formwork.  

 3.03  DRAINAGE AND WEEP HOLES  

Drainage openings and weep holes shall be constructed using materials in the manner, and at the locations shown on the plans or established by the Engineer. 

 3.04  EXPANSION JOINTS  

Expansion devices shall be as indicated on the plans.  

3.05  MEASURING, BATCHING, MIXING, AND TRANSPORTING CONCRETE  

A. Measuring, batching, mixing, and transporting concrete shall conform to ASTM C94.  

B. Concrete shall be placed within 1‐1/2 hours of the time at which water was first added. Otherwise, it shall be rejected. 

 C. Concrete, which has been  re‐tempered by  adding water  to  a  ready mix  truck,  is  the 

sole responsibility of the Contractor.  In no case shall more than 1 gallon per cubic yard of concrete be added. 

 3.06  PLACING CONCRETE  

A. No concrete shall be placed until  forms, reinforcing steel, condition of sub‐grade and method  of  placement  has  been  approved  by  the  Engineer  or  the  Engineer’s representative.    The  Contractor  shall  advise  the  Engineer  at  least  24  hours  prior  to each concrete placement so that any necessary inspection or testing can be scheduled in a timely manner. 

 B. Concrete shall be placed as soon as practicable following excavation for footings, slabs, 

and other structural components.    If an extended period of time will elapse between excavation  and  the placement of  concrete,  a  thin  “mud mat”  at  least  2  inches  thick consisting  of  low  strength  concrete  shall  be  placed  to  protect  the  sub‐grade  from degradation  due  to  exposure.    The mud mat  shall  not  be  placed  prior  to  sub‐grade approval by the Engineer. 

 C. All  debris,  foreign matter,  loose  soil,  and  standing  water  shall  be  removed  prior  to 

placement of concrete.  Concrete shall not be placed on frozen ground. 

Page 150: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐6 

 D. Deposit concrete as near to its final position as possible to avoid segregation due to re‐

handling  or  flowing.    Movement  of  concrete  by  use  of  mechanical  vibrators  is  not allowed. 

 E. Concrete  shall  be  placed  so  as  to  avoid  segregation  of  the  materials  and  the 

displacement of the reinforcement.  Concrete shall not be dropped more than six feet. Tremies shall be used where drop exceeds six feet. 

 F. Pumping of  concrete will be permitted when an approved design mix and aggregate 

sizes, suitable for pumping, are used.  

G. All concrete shall be thoroughly consolidated by suitable mechanical vibrators during placement  and  shall  be  thoroughly  worked  around  reinforcement  and  embedded fixtures and into corners of form. 

 H. Concrete  within  any  unit  of  work  between  construction  joints  shall  be  placed 

continuously so as to prevent “cold joints.”  

I. If  the  forms  show  bulging  or  settlement while  concrete  is  being  placed,  the  placing shall be stopped until correction has been made. 

 3.07  CURING AND PROTECTION  

A. Protect  all  concrete work  against  injury  from  the  elements  and  defacements  of  any nature during construction operations. 

 B. All  concrete  shall  be  cured  in  conformity  with  ACI  301.  Reinforced  concrete  shall 

additionally conform to ACI 318.  

C. Concrete placed during  cold weather  shall  be batched, delivered, placed,  cured,  and protected in compliance with the recommendations of ACI 306. 

 D. Concrete  placed  during  hot weather  shall  be  batched,  delivered,  placed,  cured,  and 

protected in compliance with the recommendations of ACI 305.  3.08  TESTING  

A. Field‐testing  of  fresh  concrete  shall  be  performed  by  an  independent  testing laboratory where required by the Engineer. 

 B. Unless otherwise  specified,  the  field  testing program shall,  at  a minimum,  consist of 

the following activities. 1. Fresh  concrete  shall  be  sampled  not  less  than  once  for  each  concrete  mix 

placed each day, nor less than once each 100 cubic yards of each concrete mix 

Page 151: Standard Water and Sewer Specifications PDF

  CAST‐IN‐PLACE CONCRETE  03300‐7 

placed each day. Sampling shall be performed in accordance with ASTM C172. 2. Ambient and concrete temperature shall be measured at the time of sampling. 3. Slump tests shall be performed in accordance with ASTM C143. 4. Tests for air content shall be performed in compliance with either the pressure 

method complying with ASTM C231 or the volumetric method complying with ASTM C173. 

5. A  set  of  four  compressive  strength  cylinders  shall  be  molded  and  cured  in accordance with ASTM C31. 

 C. Unless otherwise specified,  the break schedule  for  sets of  four compressive strength 

cylinders  shall  be  as  follows:  one  at  7  days,  two  at  28  days,  and  one  reserve.    The compressive strength test shall be performed in accordance with ASTM C39. 

 3.09  DEFECTIVE CONCRETE  

Concrete  shall  be  placed,  completed,  finished,  and  cured  so  as  to  form  a  dense,  compact, impervious  artificial  stone  with  smooth  exposed  faces.    Any  part  of  the  work  found  to  be honeycombed,  porous,  or  otherwise  defective  that  cannot  be  satisfactorily  repaired,  in  the opinion  of  the  Engineer,  or  does  not  meet  strength  requirements,  shall  be  removed  and replaced in whole or in part at the expense of the Contractor. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 152: Standard Water and Sewer Specifications PDF
Page 153: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐1 

SECTION 11200  

SEWER VALVES  

TABLE OF CONTENTS  PART 1 – GENERAL  1.01 WORK INCLUDED  

Sewer valves and appurtenances shall be  installed by the Contractor  in accordance with the Contract Drawings and Specifications. 

  PART 2 – PRODUCTS  2.01 SWING CHECK VALVE  

A. The check valve shall be a counterweighted,  rubber  seated swing check valve unless otherwise specified.   The valve shall permit flow in one direction only and shall close tightly without slamming when the discharge pressure exceeds the inlet pressure.  The cushioned  swing  check  valve  shall  be  installed  with  the  flow  direction  either horizontally or vertically up and shall function to prevent reverse flow.  The valve shall provide a full equivalent pipe area when open fully. 

 B. The valve body shall be a one‐piece cast iron or cast steel casting with integral flanges.  

The flanges shall be faced and drilled in accordance with ANSI B16.1 Class 125 or Class 250 as shown on the Contract Drawings. 

 C. The  hinge  shaft  shall  be  located  completely  above  the  waterway  and  shall  be 

constructed of  stainless  steel with  the disc  arm and  counterweight arm keyed  there on.  The hinge shaft shall be one piece and shall extend through both sides of the valve body. 

 D. The  body  seat  shall  be  bronze  or  stainless  steel,  and  the  disc  shall  be  cast  iron 

conforming to ASTM A126 Class B.  The seat ring shall be a resilient field‐ replaceable ring that can be replaced without the use of special tools. 

 E. A lever and weight shall be provided to initiate closure unless otherwise specified. 

 F. The valve shall be a Golden Anderson Series 250 or approved equal. 

 

Page 154: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐2 

2.02 PLUG VALVES  

A. All  plug  valves  shall  be  eccentric  plug  valves  with  100%  full  port  unless  otherwise specified. 

 B. Valves shall be of the non‐lubricated eccentric type with resilient faced plugs and shall 

be furnished with end connections as designated on the Contract Drawings.  

C. Valve bodies shall be of ASTM A126 Class B cast  iron.   Bodies  in 4” and  larger valves shall be  furnished with a 1/8” welded overlay  seat of not  less  than 90% pure nickel.  Seat area shall be raised, with raised surface completely covered with weld to  insure that the plug face contacts only nickel. Screwed‐in seats shall not be acceptable. 

 D. Plugs shall be of ASTM A126 Class B cast iron.  The plug shall have a cylindrical seating 

surface  eccentrically  offset  from  the  center  of  the  plug  shaft.    The  interference between  the  plug  face  and  body  seat, with  the  plug  in  the  closed  position,  shall  be externally adjustable in the field with the valve in the line under pressure.   Plug shall be resilient faced with neoprene or hycar, suitable for use with sewage. 

 E. Valves shall have sleeve type metal bearings and shall be of sintered, oil impregnated 

permanently lubricated Type 316 ASTM A743 Grade CF‐8M or AISI Type 317L stainless steel.  Non‐metallic bearings shall not be acceptable. 

 F. Valve shaft seals shall be of the multiple V‐ring type and shall be externally adjustable 

and  re‐packable  without  removing  the  bonnet  or  actuator  from  the  valve  under pressure.    Valves  utilizing  O‐ring  seals  or  non‐adjustable  packing  shall  not  be acceptable. 

 G. Valve pressure ratings shall be 175 psi  through 12” and 150 psi  for 14”  through 72”.  

Each valve shall be given a hydrostatic and seat test with test results being certified.  

H. Non‐buried manual valves shall have hand‐wheel gear actuators.   Buried valves shall be provided with tee wrenches and extension stems.  All valves 6” and smaller may be equipped with gear actuators.  All manual actuators shall be rated for the full pressure rating  of  the  valve.    All  gearing  shall  be  enclosed  in  a  semi‐steel  housing  and  be suitable for running in a lubricant with seals provided on all shafts to prevent entry of dirt  and  water  into  the  actuator.    The  actuator  shaft  and  the  quadrant  shall  be supported on permanently lubricated bronze bearings.  Actuators shall clearly indicate valve position  and an  adjustable  stop  shall  be provided  to  set  closing  torque and  to provide  seat  adjustment  to  compensate  for  change  in  pressure  differential  or  flow direction change.  All exposed nuts, bolts and washers shall be zinc plated. 

 I. Valves and gear actuators for buried or submerged service shall have seals on all shafts 

and gaskets on the valve and actuator covers to prevent the entry of water.  Actuator 

Page 155: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐3 

mounting brackets for buried or submerged service shall be totally enclosed and shall have gasket seals.  All exposed nuts, bolts, springs and washers shall be stainless steel. 

 J. All valves shall be as manufactured by DeZURIK or approved equal. 

 2.03 RESILIENT SEAT GATE VALVES  

A. Resilient seat gate valves shall meet the requirements of AWWA C509.  

B. Gate valves shall have a non‐rising stem with valve opening as shown on the system map in Appendix A.  

C. Ends shall be mechanical joint by flanged ends suitable for use with tapping machine.  

D. Gate  valves  shall  only be used  in  sewage applications where  a  tapped  connection  is made to an existing forcemain.  

E. Gate  valves  are  not  allowed  for  sewage  applications  without  prior  approval  of  the Engineer. 

 2.04 SEWAGE AIR AND VACUUM RELEASE VALVES  

A. All force mains shall have air and vacuum release valves installed as indicated on the Contract Drawings. 

 B. Special  application  of  the  air  release  valves  at  pump  station  piping  shall  allow  for  a 

combination valve.  

C. The body of the valves shall be conical shaped to maintain maximum air gap with the spring loaded float and seal plug connection combining to ensure no contact between the sewage and the seal. 

 D. The valve shall have a double float design with the upper float being enclosed  in the 

upper section of the valve and shall be made of polypropylene.  

E. The lower float shall be in the main body of the valve and shall be constructed of 316 stainless steel. 

 F. The body,  cover  flange,  and  lower  flange  shall  be  constructed of 316  stainless  steel, 

and shall have a funnel shaped lower body to automatically drain sewage back into the system. 

 G. All  internal metal  parts  are  to  be made  from  corrosion  resistant  316  stainless  steel, 

with all operating parts in the upper section to be non‐metallic plastic materials.  

Page 156: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐4 

H. The hinge for operation for the opening and closing of the seal on the orifice shall be made of Buna N rubber. 

 I. The  rolling  resilient  seal  shall provide smooth positive opening,  closing and  leak‐free 

sealing over the fluctuation of the pressure differentials.  

J. The working pressure shall be 250 psi and tested to 375 psi.  

K. All hardware shall be of stainless steel bolts and nuts, and the entire valve, except to upper outlet, shall be constructed of 316 stainless steel.  

 L. The  type  of  valve  and  its  connection  shall  be  installed  as  specified  on  the  Contract 

Drawings.  

M. All  air  and vacuum combination  release valves  shall be model ARI D‐020, ARI D‐023, ARI D‐025, or approved equal, and the automatic air release valves shall be ARI model S‐020 or approved equal. 

 N. All  valves  shall  be  installed  in  accordance with manufacturer  recommendations  and 

shall have an isolation valve connection for control.  2.05 PUMP STATION AIR VALVES   

A. Special  application  of  the  air  release  valves  at  pump  station  piping  shall  allow  for  a combination valve. 

 B. These valves are to be located as shown on the Contract Drawings. 

 C. The body/base of these valves shall be made from 316 stainless steel and all operating 

parts shall be made of engineered corrosion resistant plastic materials.   

D. The rolling resilient seal shall provide smooth positive opening, closing, and leak free sealing over  the  fluctuation of pressure differentials.    The valve  shall be designed  to allow larger than normal automatic orifice providing efficient air release and minimize potential debris build up and clogging. 

 E. The working pressure shall be 250 psi. 

 F. All  air  and  vacuum  release valves  shall  be model ARI D‐020 or ARI D‐023 as per  the 

Contract Drawings.  

G. The connection to the system shall be a direct threaded connection on the top of the pipe with a saddle and isolation valve. 

 

Page 157: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐5 

2.06 PUMP STATION BYPASS PORT FITTINGS  

A. Each pump station shall be equipped with pump bypass port fittings and valves of the size and quantity as shown on the Contract Drawings. 

 B. Grinder  and  suction  lift  station  emergency  pump  port  installations  shall  generally 

include an  isolation valve on  the common discharge  line, a  tee with valve and a 90o elbow with a threaded end and cap.  The pump port side of the tee shall be 4‐inch or 6‐inch in diameter.  The isolation valves shall be installed in valve boxes and the pump port shall be  installed  inside a 2‐inch meter box.   A minimum of 6  inches of crushed stone gravel shall be placed beneath the meter box. 

 C. Submersible  lift  station emergency pump port  installations  shall generally  include an 

above‐ground flanged ball male discharge connection instead of the threaded port.  A flanged  female  suction  fitting  connected with  the wet  well  shall  be  installed  where indicated  on  the  Contract  Drawings.    Quick‐connect  fittings  shall  be  of  the  ball  and socket design securely seated by O‐ring for a vacuum‐tight seal.  Quick connects shall be capable of up to 30o articulation.  Couplings shall be galvanized and manufactured to ASA 150  flange patterns.   Male  fitting  shall be provided with a  lever‐locking haw, which  can  be  secured  with  a  locking  pin  to  prevent  accidental  or  deliberate uncoupling.  Quick‐connect fittings shall be manufactured by Bauer, Wil‐Loc Company, or approved equal. 

 2.07 VALVE BOXES   

A. Buried valves shall be installed in cast iron, 2‐piece or 3‐piece, screw type valve boxes with a shaft diameter of not  less  than 5  inches.   The base shall be of such size as  to permit  its  installation without allowing  it  to come  in contact with either  the valve or the  pipe.    Valve  boxes  shall  be  the  heavy  roadway  type  equipped  with  a  cover containing the word “SEWER” in raised letters on the top and shall be John Bouchard 562‐S or equal.  

B. In  paved  areas,  the  top  of  the  box  casting  shall  be  made  level  with  the  adjacent pavement.    In  unpaved  areas,  the  box  shall  be  level  with  the  adjacent  ground  and encircled with  a  concrete  collar  4  inches  thick  and  24  inches  in  diameter.    Pre‐cast concrete valve collars may also be used around valve boxes.  

C. Minimum 3‐inch diameter brass or aluminum valve markers shall be anchored  in the concrete valve collars.  The markers shall be stamped or engraved with the valve size (in  inches), valve type (P.V.  for plug valve, G.V.  for gate valve) and opening direction (O.L. or O.R.).  Valve markers are available from Wagco Marker in Longwood, Florida. 

 

Page 158: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐6 

2.08 VALVE VAULTS  

A. Reinforced concrete vaults with double leaf aluminum access hatches shall be installed as sized and where indicated on the Contract Drawings. 

 B. All concrete used in connection with the construction of precast concrete vaults shall 

be at minimum 4,000 psi concrete. The precast manufacturer shall use XYPEX additive. Xypex  Admix  C‐1000  Red  shall  be  added  to  the  concrete  during  batching  at  the manufacturer's specified rate. The amount of cement shall  remain the same and not be  reduced. Precast concrete structures shall have a  reddish  tint  to verify  the XYPEX admix. 

 C. The vault shall be self‐draining by gravity sump and drain line or shall have a minimum 

6‐inch crushed stone bottom as indicated on the Contract Documents.  

D. The vault shall include a double leaf aluminum access frame and cover consisting a ¼‐inch thick one‐piece, mill finish, extruded aluminum frame, incorporating a continuous concrete anchor.  Door panels shall be ¼‐inch aluminum diamond plate, reinforced to withstand a uniform live load of 300 psf with a maximum allowable deflection of 1/150 of  the  span.    Doors  shall  open  to  90  degrees  and  automatically  lock  with  T‐316 stainless steel hold open arms with aluminum release handles.  Doors shall close flush with the frame.  Hinges and all fastening hardware shall be T‐316 stainless steel.  Unit shall lock with a non‐corrosive locking bar and have a non‐corrosive handle.  Unit shall carry a  lifetime guarantee against defects  in material and/or workmanship.   The unit shall be the S2R series as manufactured by Halliday Products, Inc, or equal.  

E. Each  installation  shall  have  steps  conforming  to  ASTM  C478  and  shall  be  made  of copolymer polypropylene plastic conforming to the latest revision of ASTM D‐4101 and shall have a ½‐inch diameter Grade 60 Steel reinforcing rod meeting the latest revision of ASTM A615 through its center.  Each step shall be 12 inches in width and capable of supporting a  load of 1,000 pounds in the center of the step when projected 6  inches from the wall.  Each step shall be equipped with non‐skid grooves.  Rung spacing shall be  12  inches.    The  location  of  the  steps  shall  be  coordinated with  the  access  hatch provided.  

F. Pipe openings shall include watertight resilient pipe connectors as specified in Section 02722, Paragraph 2.13. 

  PART 3 – EXECUTION  3.01 GENERAL INSTALLATION  

A. Valves shall be installed per manufacturer’s recommendations.  

Page 159: Standard Water and Sewer Specifications PDF

  SEWER VALVES  11200‐7 

B. Buried valves shall be installed with a cast iron valve box.  

C. Check valves shall not be mounted in wet well but shall be mounted in a valve vault as shown on Contract Drawings. 

 D. Air  release  and  vacuum  valves  shall  be  installed  in  a  48‐inch  diameter  pre‐cast 

manhole  with  a  minimum  depth  of  48  inches,  but  with  sufficient  depth  to accommodate  the  specified  valve.    A  standard  traffic  casting  with  cover  marked “Sanitary Sewer” shall be installed on the manhole.  At least 1 cubic yard of stone shall be installed around pipeline. 

 E. Buried  valves  shall  include mechanical  joint  ends.    Valves  for  aboveground  or  vault 

installation shall include flanged ends.  

F. Valves  shall  be plumbed  for  level  installation  so as not  to place end  connection  in a bind. 

 G. Air release and vacuum valves shall be mounted with a tapping boss or tapping saddle 

with either a brass or bronze isolation valve that includes hand controls.  No galvanized piping shall be used. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 160: Standard Water and Sewer Specifications PDF
Page 161: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐1 

SECTION 11311  

SUBMERSIBLE SEWAGE PUMP STATIONS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  DESCRIPTION OF WORK  

A. The Contractor shall provide and install a complete submersible sewage pump station as  shown  on  Contract  Drawings.    The  pump  station  shall  be  complete  with  all equipment shown on the Contract Drawings and as specified herein. 

 B. The principle  items of equipment  to be  furnished  for  the pump station  shall  include 

submersible  non‐clog  sewage  pumps,  motors,  internal  and  external  piping,  pump accessories, bypass pump ports,  and valves;  concrete wet well  and valve vaults with access  hatches;  control  panel with  circuit  breakers, motor  starters,  automatic  pump control system, and other components as required; all internal and external wiring and appurtenances necessary to provide an operating pump station. 

 C. Where indicated on the Contract Drawings, the pump station shall also include water 

service to the site, a paved access road, fencing, lighting, emergency motor generator, odor control, flow meter and other instrumentation, telemetry and other items. 

 D. Where the required power supply does not exist, the Contractor shall coordinate with 

the appropriate power company to route the power supply to the site.  1.02  REFERENCES  

A. ANSI B16.1:  Cast Iron Pipe Flanges and Flanged Fittings, Class 25, 125, 250, and 800.  

B. ASTM A48:  Gray Iron Castings.  

C. ASTM A276:  Stainless and Heat‐Resisting Steel Bars and Shapes.  

D. ASTM  A311:  Steel  Bars,  Carbon,  Stress‐Relieved  Cold‐Drawn,  Subject  to  Mechanical Property Requirements. 

 E. ASTM A532:  Abrasion‐Resistant Cast Irons. 

 F. ASTM A576:  Steel Bars, Carbon, Hot‐Wrought, Special Quality. 

 G. The Hydraulic Institute Standards.  

 

Page 162: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐2 

1.03  GENERAL  

A. Make  certain  that  equipment  does  not  exceed  space  allocation,  including  hatch openings, and provide the manufacturer with Contract Drawings where necessary. 

 B. Pumps must  operate  at  specific  speeds below  the  “Upper  Limits  of  Specific  Speeds” 

established  by  the Hydraulic  Institute  so  that  the  pumps may  operate  at  the  stated capacity, head, and suction lift with reasonable assurance of freedom from cavitation. 

 C. Pumps, motors and control equipment shall conform to the requirements set forth in 

the following pages as to capacity, head, and other requirements.  Motors shall be of ample  size  to  operate  without  overload  through  the  entire  range  of  the  pump characteristic curve.  Ample means of lubrication shall be provided for all bearings and parts  where  required.    Alemite  industrial  type  fittings  shall  be  used  for  grease lubrication.  Pumps and motors shall perform the work intended without undue wear and undue heating. 

 D. Asbestos shall not be in any part of the pumps or in the seals. 

 1.04  TESTS  

A. Factory Test:   Each pump and motor shall be given the  following tests at  the  factory prior to shipment: 1. The mechanical and electrical integrity of the pump shall be established by the 

use of physical inspection and the use of a megger for verification of the stator resistance to short circuit. 

2. The power leads shall be connected to the motor in accordance to the jobsite voltage and the pump started to verify rotation and no load amp readings. 

3. The  pump  shall  be  installed  in  a  test  tank  on  a wet  pit  discharge  elbow  and complete hydraulic tests conducted.  The KW input, power factor, flow rate and head shall be measured and recorded.  The pump shall be operated at the duty point  for  the  project  and  checked  for  compliance  with  Hydraulic  Institute Standards prior to being certified.  The pump shall then be removed and given a  physical  inspection  and  additional  megger  insulation  test  to  re‐verify  the mechanical and electrical integrity. 

4. Certified copies of the results of the pump performance tests run in the factory shall be submitted to the Owner for approval prior to pump delivery. 

 B. Field Test:  Operate equipment for a period of five (5) successive 24‐hour days prior to 

request  of  Substantial  Completion.    Should  the  equipment  fail  to  operate  as prescribed,  the  equipment  shall  be  repaired  and  the  field  test  procedures  shall  be repeated until the equipment operates as required by these documents. 

 

Page 163: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐3 

1.05  WARRANTY REQUIREMENTS  

A. All  equipment  supplied  under  this  section  shall  have  a  base  warranty  from  the Contractor  and  each  equipment  manufacturer  covering  a  period  of  one  year  from start‐up.  The warranty period for the station’s equipment shall commence on the date of start‐up. 

B. The  equipment  shall  be  warranted  free  from  defects  in  workmanship,  design  and materials.  If any part of the equipment should fail during the basic warranty period, it shall be repaired at no additional cost to the Owner. 

 1.06  SUBMITTALS  

A. The submittals required in this section include (but are not limited to) the following: 1. Certified characteristic pump curves 2. Components and component materials of construction 3. Seal descriptions 4. Impeller diameter 5. Maximum impeller permissible 6. NPSH requirements 7. Operating point 8. Certified pump test 9. Electrical characteristics of motors 10. Manufacturer’s standard recommended start‐up report form 11. Printed warranty 12. Outline dimensions 13. Layout and operation of control panel 

 B. The Contractor shall submit for approval complete characteristic curves of the pumps 

before  fabrication  is  started.    Curves  shall  also  indicate  required  NPSH,  efficiency, horsepower,  maximum  diameter  impeller  that  can  be  installed  in  the  pump,  and proposed impeller diameter for the application. 

 C. Any  equipment  submittals  for  manufacturers  other  than  those  specified  must  be 

approved in all respects by the Owner to meet the proposed requirements.  1.07  ACCEPTABLE MANUFACTURERS  

A. ITT Flygt  

B. ABS  

Page 164: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐4 

PART 2 – PRODUCTS  2.01  SUBMERSIBLE, NON‐CLOGGING SEWAGE PUMPS  

A. The specifications contained herein are patterned around pumps manufactured by ITT Flygt.    Products  manufactured  by  Flygt  shall  set  the  minimum  standard  of  quality.  Some  modifications  to  the  specifications  have  been  made  to  allow  other manufacturers  to  be  considered,  provided  their  equipment  is  judged  equal  by  the Owner and  they are  listed as approved  in  the original Contract Documents or by an Addendum. 

 B. Furnish  and  install  submersible  non‐clog  wastewater  pump(s)  as  shown  on  the 

Contract Drawings and specified herein.  The pumps shall be totally submersible solids handling centrifugal pumps with submersible close‐coupled motors.  The overall pump design shall combine high efficiency, low required NPSH, large sphere passage and the ability to handle high solids concentrations efficiently.  The impeller/casing design shall result in a passage free of surfaces to which solid or fibrous materials can adhere. 

 C. Discharge Connection:   The pump shall be supplied with a mating cast iron discharge 

connection and be capable of delivering flow and total dynamic head as specified by the Engineer.  The pump casing shall have a machined connection system to attach to the  ASTM  A48,  Class  30  cast  iron  discharge  connection.    The  sealing  system  shall consist of two machined metal‐to‐metal flanges form fitted to the machined discharge coupling to insure and guarantee a positive leak‐proof system and to provide ease of pump removal.  The discharge connection shall be bolted to the floor of the sump with 316 stainless steel J‐bolt connections and shall be designed so as to receive the pump connection without the need of any bolts, nuts or other fastenings. 

 D. Guide Bars and Brackets: 

1. A  sliding  guide  bracket  shall  be  an  integral  part  of  the  pumping  unit.    The pump(s)  shall  be  tightly  sealed against  the discharge  connection  to provide a non‐leaking  connection  and  shall  be  accomplished  automatically  by  a  simple linear downward motion of the pump with the pumping unit guided by no less than two 316 stainless steel guide bars extending from the top of the station to the discharge connection.   No portion of  the pump shall bear directly on  the sump floor. 

2. Intermediate  guide  bar  brackets  fabricated  of  316  stainless  steel  shall  be furnished and installed so that the maximum length of unsupported guide bars will be no longer than 20 feet. 

3. The  pumps  shall  be  designed  to  be  easily  removed  from  their  discharge connections  and  the  wet  well  for  inspection  and  maintenance.    Lifting  the pumps from their discharge connections and the wet well shall require neither the removal of any bolts, nuts or other fastenings nor the need for personnel to enter the wet‐well. 

 

Page 165: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐5 

E. Lifting System:  Each pump shall be fitted with a stainless steel chain or stainless steel cable safely rated to lift the pump from the wet well.   The working load of the lifting system shall be 50% greater than the pump unit weight.  The length of the lifting chain or cable shall be at  least equal to the wet well depth (top slab finished grade to wet well bottom) plus 2 feet to permit raising the pump for inspection and removal. 

 F. Pump Construction: 

1. Major pump components shall be of gray cast iron, ASTM A‐48, Class 35B, with smooth surfaces devoid of blow holes or other irregularities.  All exposed nuts or bolts shall be AISI  type 304 stainless steel construction.   All metal surfaces coming into contact with the pumpage, other than stainless steel or brass, shall be  protected  by  a  factory  applied  spray  coating  of  acrylic  dispersion  zinc phosphate  primer  with  a  polyester  resin  paint  finish  on  the  exterior  of  the pump. 

2. Sealing  design  shall  incorporate  metal‐to‐metal  contact  between  machined surfaces.  Critical mating surfaces where watertight sealing is required shall be machined and  fitted with Nitrile or Viton  rubber O‐rings.    Fittings will  be  the result  of  controlled  compression  of  rubber  O‐rings  in  two  planes  and  O‐ring contact of four sides without the requirement of a specific torque limit. 

3. No  secondary  sealing  compounds,  elliptical  O‐rings,  grease,  or  other  devices shall be used. 

 G. Cooling System:  Motors are sufficiently cooled by the surrounding environment or by 

submergence in the pumped media.  A water cooling jacket is not required.  If a dry pit application is specified, a self‐contained cooling system shall be included. 

 H. Submersible Power Cable:   The power cable  shall be sized according  to  the NEC and 

ICEA standards and have P‐MSHA Approval and shall be suitable for submersible pump applications.  Submersible power cables shall be of sufficient length so that the cables will  be  continuous between  the  cable  entry  junction  chamber  at  the motor  and  the control panel without the need of any splices.  The outer jacket of the cable shall be oil resistant  chloroprene  rubber.    The motor  and  cable  shall  be  capable  of  continuous submergence underwater without loss of watertight integrity to a depth of 65 feet. 

 I. Cable  Entry  Seal:    The  cable  entry  seal  design  shall  preclude  specific  torque 

requirements  to  ensure  a  watertight  and  submersible  seal.    The  cable  entry  shall consist of dual cylindrical elastomer grommets, flanked by washers, all having a close tolerance  fit  against  the  cable outside diameter  and  the entry  inside diameter.    The grommets  shall be compressed by  the cable entry unit,  thus providing a  strain  relief function.  The assembly shall provide ease of changing the cable when necessary using the same entry seal.  The cable entry junction chamber and motor shall be sealed from each other, which shall isolate the stator housing from foreign material gaining access through the pump top. 

 

Page 166: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐6 

J. Motor: 1. The pump motor shall be a NEMA B design, induction type with a squirrel cage 

rotor, shell type design, housed in an air filled, watertight chamber.  The stator windings shall be insulated with moisture resistant Class H insulation rated for 180°C (356°F).  The stator shall be insulated by the trickle impregnation method using Class H monomer‐free polyester resin resulting in a winding fill factor of at least 95%.  The motor shall be inverter duty rated in accordance with NEMA MG1, Part  31.    The  stator  shall  be heat‐shrink  fitted  into  the  cast  iron  stator housing.    The  use  of multiple  step  dip  and  bake‐type  stator  insulation  is  not acceptable.    The  use  of  bolts,  pins,  or  other  fastening  devices  requiring penetration  of  the  stator  housing  is  not  acceptable.    The  motor  shall  be designed  for  continuous  duty  while  handling  pumped media  of  40°C  (104°F) and  shall  be  capable  of  at  least  15  evenly  spaced  starts  per  hour.    The  rotor bars  and  short  circuit  rings  shall  be made  of  cast  aluminum.    Three  thermal switches shall be embedded in the stator end coils, one per phase winding, to monitor  the  stator  temperature.    These  thermal  switches  shall  be  used  in conjunction with and supplemental to external motor overload protection and shall be connected to the control panel.  The junction chamber shall be sealed off from the stator housing and shall contain a terminal board for connection of power and pilot sensor cables using threaded compression type terminals.  The use of wire nuts or  crimp‐type  connectors  is not  acceptable.    The motor and the pump shall be produced by the same manufacturer. 

2. The motor  service  factor  (combined effect of voltage,  frequency, and  specific gravity) shall be a minimum of 1.15.  The motor shall have a voltage tolerance of plus or minus 10%.  The motor shall be designed for continuous operation in up to 40°C (140°F) ambient and shall have a NEMA Class B maximum operating temperature  rise  not  to  exceed  80°C.    A  motor  performance  chart  shall  be provided  upon  request  exhibiting  curves  for  motor  torque,  current,  power factor,  input/output  kW  and  efficiency.    The  chart  shall  also  include  data  on motor starting and no‐load characteristics. 

3. The motor horsepower shall be adequate so that the pump is non‐overloading throughout the entire pump performance curve from shut‐off through run‐out. 

 K. Bearings:    The  integral  pump/motor  shaft  shall  rotate  on  two  bearings.    Motor 

bearings  shall  be  sealed  and  permanently  grease‐lubricated  with  high‐temperature grease.  The upper bearing shall be a single roller bearing.  The lower bearing shall be a two‐row angular contact bearing to compensate for axial thrust and radial forces.  

L. Mechanical Seal 1. Each  pump  shall  be  provided  with  a  tandem  mechanical  shaft  seal  system 

consisting of two totally independent seal assemblies.  The seals shall operate in a  lubricant reservoir  that hydrodynamically  lubricates the  lapped seal  faces at a constant rate.  The lower primary seal unit, located between the pump and the  lubricant  chamber,  shall  contain one  stationary  and one positively driven rotating,  corrosion‐resistant  ring.    The  upper  secondary  seal  unit,  located 

Page 167: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐7 

between  the  lubricant  chamber  and  the  motor  hosing,  shall  contain  one stationary  and  one  positively  driven  rotating,  corrosion‐resistant  seal  ring.  Each seal interface shall be held in contact by its own spring system.  The seals shall  require neither maintenance nor adjustment nor depend on direction of rotation for sealing.  The position of both mechanical seals shall depend on the shaft. 

2. Each  pump  shall  be  provided  with  a  lubricant  chamber  for  the  shaft  sealing system.  The lubricant chamber shall be designed to prevent overfilling and to provide  lubricant  expansion  capacity.    The  drain  and  inspection  plug,  with positive  anti‐leak  seal  shall  be  easily  accessible  from  the  outside.    The  seal system shall not rely upon the pumped media for lubrication.  The motor shall be able to operate dry without damage while pumping under load. 

3. Seal lubricant shall be FDA approved and nontoxic.  

M. Pump Shaft:  Pump and motor shaft shall be a single‐piece unit.  The pump shaft is an extension  of  the  motor  shaft.    Shafts  using  mechanical  couplings  shall  not  be acceptable.  The shaft shall be ASTM A‐479 stainless steel. 

 N. Impeller:  The impeller(s) shall be of gray cast iron, ASTM A‐48 Class 35B, dynamically 

balanced,  semi‐open  multi‐vane,  back  swept,  screw  shaped,  non‐clog  design.    The impeller(s)  shall  be  capable  of  handling  solids,  fibrous  materials,  heavy  sludge  and other matter found in wastewater.  Impeller(s) shall be locked to the shaft, held by an impeller bolt, and treated with a corrosion  inhibitor.   All  impellers shall be coated or hardened to provide long life. 

 O. Wear Rings:  A wear ring system shall be used to provide efficient sealing between the 

volute and suction inlet of the impeller.  Each pump shall be equipped with a brass, or nitrile rubber‐coated steel ring insert that is drive fitted to the volute inlet. 

 P. Volute:  Pump volute(s) shall be single‐piece gray cast iron, ASTM A‐48, Class 35B, non‐

concentric design with smooth passages of sufficient size to pass any solids that may enter the impeller.  Minimum inlet and discharge size shall be as specified. 

 Q. Protection: 

1. All  stators  shall  incorporate  thermal  switches  in  series  to  monitor  the temperature of each phase winding.  The thermal switches shall open at 125°C (260°F), stop the motor and activate an alarm.  A float switch shall be installed in  the seal  leakage chamber and will activate  if  the  leakage  into the chamber reaches 50% chamber capacity, signaling the need to schedule an inspection. 

2. The  thermal  switches  and  float  switch  shall  be  connected  to  a  control  and status monitoring unit.  The unit shall be designed to be mounted in the pump control panel. 

 

Page 168: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐8 

2.02  PUMP CONTROL SYSTEM  

A. Manufacturer:  The  electrical  control  components  specified  herein  are manufactured by  ITT  Flygt.    Products  manufactured  by  Flygt  shall  set  the  minimum  standard  of quality.  Other manufacturers may be considered, provided their equipment is judged equal by the Owner. 

 B. General: 

1. A pressure transducer shall automatically start and stop the pumps, via control and time delay relays within the Pump Control Panel. 

2. Appropriate  electrical  power  service  shall  be  provided  to  the  pump  control panel.   The Contractor shall coordinate this work with the appropriate power company. 

3. Solid‐state reduced voltage starters , non‐reversing shall be provided. 4. Lightening and surge protection shall be provided. 

 C. The  control  panel  shall  consist  of  a  main  circuit  breaker,  an  electrically  operated 

manual  transfer  switch  (except  where  automatic  transfer  switches  are  required  for dedicated  emergency motor  generators),  a motor  circuit  protector,  and  full  voltage starter  for  each  pump  motor,  a  480‐volt  primary‐120/240  volt  control  power transformer (fused on primary and secondary), and 20‐ampere, 120‐volt and 240‐volt circuit breakers as required.  Size transformer for actual loads plus an additional 50% spare capacity.  A low and high level alarm and pump shut‐off shall be accomplished by a pressure transducer liquid level control system with all control components mounted in  one  common  enclosure.    Control  switches  shall  provide  means  to  operate  each pump manually or automatically.  When operated in the automatic mode, the control assembly  shall  provide  means  to  manually  select  or  automatically  alternate  the position for the sets of pumps after each pumping cycle.  

D. A pressure transducer‐type liquid level control system shall continuously monitor wet well liquid level and control operation of the low‐level cut off for the pumps.  

E. Provide auxiliary dry contracts as required for remote sensing and control.  

F. Panel Enclosure: 1. The electrical control equipment shall be mounted within a pad‐lockable NEMA 

Type  4X  deadfront  enclosure  constructed  of  not  less  than  14‐gauge  304 stainless  steel  and  shall  be  equipped  with  quarter‐turn  quick‐release  latches with all hardware and exterior components constructed of 304 stainless steel.  The  enclosure  shall  be  equipped  with  an  inner  door  and  shall  incorporate  a removable  back  panel  on which  control  components  shall  be mounted.    The back panel shall be secured to the enclosure with collar studs.   The door shall be  interlocked with the main circuit breaker.   Crouse‐Hinds Type “CGB” cable connectors  shall  be  provided  to  terminate  the motor  and  float  cables  in  the control panel.  The connectors shall be suitable for a 2‐inch (minimum) conduit 

Page 169: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐9 

with a neoprene bushing suitable for the cables supplied.   The enclosure shall be oversized  to prevent and dissipate excess heat building up and  to provide sufficient  space  for  maintenance  and  removal  of  internal  control  panel equipment.    The  enclosures  shall  be  floor‐mount  type  with  floor  stands  for mounting on a concrete pad.  The interior door shall be provided with a locking feature to hold the door open. 

2. Provide 20‐ampere circuit breakers for the following equipment. a) Alarm Light Fixture – 120 volts b) GFCI Receptacle – 120 volts c) Telemetry Radio Transmitter – 120 volts d) Control Panel Heater – 120 volts e) Control Panel Cooling Fan – 120 volts f) Spare – 120 volts g) Spare – 120 volts 

3. Components: a) All  motor  branch  circuit  breakers,  motor  circuit  protectors,  motor 

starters  and  control  relays  shall  be  of  the  highest  industrial  quality, securely  fastened  to  the  removable  back  panels with  screws  and  lock washers.    Back  panels  shall  be  tapped  to  accept  all mounting  screws.  Self‐tapping screws shall not be used to mount any component. 

b) A  thermal‐magnetic  molded  case  circuit  breaker,  Type  KH  as manufactured  by  Square  D  Company,  or  equal,  shall  be  furnished  for the  main  circuit  breaker  and  service  entrance  disconnect.    Provide  a Service  Entrance  (SE)  label.    The  manufacturer  shall  seal  all  circuit breakers  after  calibration  to  prevent  tampering.    Each  circuit  breaker shall  be  adequately  sized  to  meet  the  station  operating  conditions.  Motor  Circuit  Protectors  (MCP)  shall  be  molded  case  with  adjustable magnetic  trip  only,  Square  D  Class  680  “Mag‐Guard”  or  equal.    The control panel shall have a fully rated short circuit capacity of 65,000 AIC. 

c) Except  where  an  automatic  transfer  switch  is  required,  provide  an electrically operated non‐automatic transfer switch in the control panel to provide for manual transfer to standby power when utility power is not  available.    The  transfer  switch  shall  be  rated 240 volt,  3‐phase, 3‐pole,  4‐wire  with  solid  neutral.    The  transfer  switch  shall  have  an ampacity  rating  as  shown  on  the  Contract  Drawings.    The  transfer switch  shall  be  equal  to  ASCO  Series  386.    The  standby  side  of  the transfer  shall  be  connected  to  a  power  receptacle  for  connection  to portable generation equipment.  The power receptacle shall be the pin and  sleeve  type  in  a  NEMA  4X  enclosure  and  located  on  the  exterior side  of  the  control  panel.    Coordinate  receptacle  rating,  configuration and manufacturer with the Owner to match the existing cord‐and‐plug set. 

d) A mechanical  disconnect mechanism  shall  be  installed  on  each  circuit breaker  to  provide  a  means  of  disconnecting  power  to  the  pump motors. 

Page 170: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐10 

e) Time  delay  relays  shall  be  electronic,  600  volt,  20  amp  contacts, with calibrated knob operated adjustment and numerical time dial.  On delay and off delay types and timing shall be as required for proper operation of the actual equipment furnished.  Relays shall be Agastat Model 7012 or 7022 or equal. 

f) A  20  ampere  duplex  GFCI  utility  receptacle  (15  amp  circuit  breaker protected)  providing  120  volts,  60  Hz,  single  phase  current  shall  be mounted inside the enclosure. 

g) Provide  a  suitable  sized  electric  enclosure  heater  with  pre‐set thermostat.   

h) Provide a suitable sized electric cooling fan with pre‐set thermostat. i) The control panel shall include an adjustable time delay relay to prevent 

pumps  from  starting  simultaneously.    Relays  shall  be  Paragon  Electric Company, Series JW or equal. 

j) Each  pump  shall  be  provided  with  an  automatic  motor  insulation monitoring device.  The device shall be the EMU/Metropolitan, or equal by MotoSafe.  The unit shall be a completely enclosed, solid state, plug‐in  electronic  module  designed  to  automatically  monitor  the  motor winding  insulation  resistance.    Each  device  shall  be  provided  with  a reset  button,  emergency  bypass  switch,  power‐on  indicator  and  low meg  light.    Each  unit  shall  be  provided  with  two  output  circuits,  one rated at 3 amps for the motor starter circuit and one rated at one amp for connection to alarm devices.  The unit shall be designed to operate on a 120‐volt power supply. 

k) The  control  diagrams  and  overload  tables  shall  be  laminated  to  the inside of the exterior door. 

l) Print  storage  pockets  shall  be  provided  on  the  inside  of  each  panel.  Pocket shall be sufficient size as required to hold all prints necessary to service the equipment.  A set of reduced drawings shall be provided for each panel, sized to fit in the storage pocket. 

m) The controls shall operate off a 120‐volt control circuit.   A transformer shall be provided. 

n) Alternators shall be provided for the control panel.  Alternators shall be 008‐120‐13SP or 009‐120‐23AP as manufactured by Sta‐con or equal. 

o) A phase monitor shall be provided for the control panel.  Monitors shall be model SUA‐440‐ASA as manufactured by Diversified Electronics  Inc. or equal. 

p) The  control  panel  shall  be  provided  with  lightening  and  surge protection.   The surge protection devices shall be mounted within  the control panel enclosure.  Lead lengths shall not be longer than 12 inches from the main circuit breaker.   The devices shall have minimum surge current  capacity  rating  of  80  kA  per  phase.    The  surge  protection devices shall be listed in accordance with UL 1449 Second Edition and as defined  by  IEEE  C62.41  and  C62.45.    The  transient  voltage  surge 

Page 171: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐11 

suppressors  shall  be  as  manufactured  by  Advanced  Protection Technologies (APT) for the power supply voltage: 

TE/5XF – 480 VAC, 3‐Phase TE/4XF – 480/277 VAC, 3‐Phase TE/3XF – 120/240 VAC, 3‐Phase TE/2XF – 120/208, 3‐Phase TE/1XF – 120/240, 1‐Phase 

q) All  control  panel  wiring  shall  be  numbered  at  both  ends  with  type written heat‐shrinkable wire markers. 

r) Wiring  shall  be  stranded  copper,  minimum  size  #14  AWG  (except  for shielded  instrumentation  cable),  with  600‐volt,  90‐degree  C,  Flame‐retardant, Type MTW thermoplastic insulation. 

s) The  control  panel  shall  be  provided with  nameplates  identifying  each component,  selector  switches,  pilot  lights,  etc.    Nameplates  shall  be permanently  affixed  using  an  epoxy  process  (inner  door  nameplates shall  be  fastened  with  stainless  steel  screws).    Nameplates  shall  be laminated plastic, engraved white letters on a black background. 

t) All control panels shall be provided with a master nameplate located on the exterior door. 

u) Where applicable, provide a nameplate that reads as follows “CAUTION –  THIS  PANEL  CONTAINS  A  VOLTAGE  FROM  AN  EXTERNAL  SOURCE.”  Letters shall be black on a high visibility yellow background. 

v) Corrosion Inhibitor Emitter:  Inclusion of an industrial corrosion inhibitor emitter  that  shall  protect  internal  components  of  control  panel  from corrosion  for up to one year.   One spare emitter shall be provided for each control panel. 

w) All  control  relays  shall  have 10‐amp‐rated  contacts  (minimum),  11 pin with  mounting  base,  3PDT  (minimum),  with  LED  indicators  to  show relay status.  Relays shall be manufactured by Potter Brumfield or equal. 

x) Terminal blocks shall be 600‐volt heavy‐duty rated, tubular clamp type.  Terminal strips shall be Allen Bradley catalog #1492‐CA‐1 or equal.  Each terminal shall be individually labeled. 

y) The completed control panel assembly shall be UL certified.  The control panel and main circuit breaker shall be Service Entrance (SE) labeled. 

z) Intrinsically  safe  relays  shall  be  solid‐state  type  with  5‐amp  output contacts, suitable for use on 120‐volt, 60‐hertz power supply and shall be Factory Mutual approved for devices in Class1, Division 1 hazardous atmospheres.  Intrinsically safe relays shall be Gems Solid State Safe‐Pak as  manufactured  by  Gems  Sensors,  Division  of  Transamerica  Delaval, Inc. or equal. 

aa) A  copper  ground  bar  with  sufficient  terminals  for  all  field  and  panel ground connections shall be provided. 

bb) An 8‐inch (minimum) clear space within the enclosure shall be provided horizontally along the entire top and bottom of the control panel.  A 4‐inch  (minimum)  clear  space  within  the  enclosure  shall  be  provided 

Page 172: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐12 

vertically  along  the  entire  sides  of  the  control  panel.    No  devices, terminals,  etc.  shall  be  installed within  this  space.    The  space  shall  be provided for field conduit and wiring access only. 

cc) Provide  adequate  space  in  the  control  panel  for  a  telemetry  radio transmitter to be installed by others.  Provide a 120‐volt circuit for radio power. 

dd) Where included on the Contract Drawings, the pump control panel shall house the flow meter unit. 

4. Operating Controls and Instruments: a) All operating controls and equipment shall be securely mounted on the 

control compartment door.  All controls and instruments shall be clearly labeled to indicate function. 

b) Pump  mode  selector  switches  shall  be  hand‐off‐auto  type  to  permit over‐ride of automatic level control and manual actuation of shutdown of  either  pump  motor.    Operation  of  pumps  in  manual  mode  shall bypass  all  safety  shutdown  circuits  except  pump  motor  overload shutdown and low level pump shutdown via pressure transducer, back‐up  float  switch  and  control  relays.    Switches  shall  be  NEMA  4X  as manufactured  by  Allen  Bradley  or  equal  providing  three  (3)  switch positions, each of which shall be clearly labeled according to function. 

c) Indicator  lamps  shall  be  incandescent  type  and mounted  in NEMA  4X (800H) modules, as manufactured by Allen Bradley.  Lamp modules shall be  equipped  to  operate  at  120‐volt  input.    Lamps  shall  be  easily replaceable  from  the  front  of  the  control  compartment  door  without removing the lamp module from its mounted position.  Indicators shall be  provided  for  individual  motor  run  and  indicator  for  each  failure condition. 

d) A  6‐digit,  non‐reset  elapsed  time  meter  shall  be  connected  to  each motor  starter  to  indicate  the  total  running  time  of  each  pump  in “hours” and “tenth of hours.”  The elapsed‐time meters shall be Series T50 as manufactured by ENM Company or equal. 

e) A  pump  station  lead  selector  hand  switch  shall  be  provided  with inscriptions 1/2/ALT for the pump station lead pump selection or pump alternation  (or  similar  for  3  or  more  pumps).    Alternation  mode selection shall alternate pumps after each  run cycle.   Pump alternator shall be furnished as specified herein. 

f) A beacon light shall illuminate when there is a high wet well level alarm.  The  control  panel  shall  be provided with  an  alarm  silence pushbutton and an alarm reset pushbutton.  The beacon light shall be NEMA 4X, 120 VAC,  xenon  strobe  flasher  with  unbreakable,  red  Lexan  globe, manufactured by Federal Electric Co. or equal. 

5. Full  Voltage Magnetic Motor  Starters:    The motor  starters  shall  be mounted within the pump control panel.  Motor starters shall be equal to Square D Class 8536 with “Motor Logic” solid‐state overload relay protection. 

Page 173: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐13 

6. Make  provisions  in  the  pump  control  panel  for  future  telemetry  system provided  by  the  Owner,  including  termination  blocks,  as  a minimum  for  the following I/O: a) Pump No. 1 run status b) Pump No. 2 run status c) High wet well alarm d) Two pumps running e) RTU signal loss/failure alarm f) Power failure alarm g) Pump No. 1 failure alarm h) Pump No. 2 failure alarm i) Spare j) Spare k) 4‐20mA analog signal for flow rate l) Spare analog signal m) Additional discrete I/O as required for additional pumps 

7. Where  required,  make  provisions  for  flow  transmitters  as  specified  herein.  Transmitter unit shall be flush mounted on the inner door of the pump panel.  The pump control panel manufacturer shall be responsible for all coordination to ensure adequate space  is provided  in the pump control panel and the unit functions properly. 

G. Level Sensing System/Pump Control 1. General:  The control system shall be designed to operate the required number 

of pumps specified on the drawing at the power characteristics shown on the plans.    The  pump  control  system  shall  utilize  a  current  input  signal,  supplied from a submersible pressure transducer.   The controller shall  supply separate alarm outputs for each fault condition. 

2. The pump  controller  shall  be  the MultiTrode MultiSmart  Controller  and RTU.  This product shall set the minimum standard of quality.   Other manufacturers may  be  considered,  provided  their  equipment  is  judged  equal  by  the Owner and  they  are  listed  as  approved  in  the  original  Contract  Documents  or  by Addendum.  Products of other manufacturers shall be assembled to provide all specified  functions,  including  reliability  equal  to  or  exceeding  that  of  the manufacturers listed above. 

3. The control function shall provide for the operation of the pumps under normal conditions, and shall alternate the pumps on each pump down cycle to equalize the run time.  In the event the incoming flow exceeds the pumping capacity of the  lead  pump,  subsequent  pumps  shall  automatically  start  to  handle  the increased flow.  As the flow decreases, the pumps shall cut off at the elevations as shown on the plans. 

 

Page 174: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐14 

PART 3 – EXECUTION  3.01 INSTALLATION  

A. Install  base  elbows with  embedded anchor  bolts.   Use of  expanding  anchor  bolts  to secure base elbows is not permitted. 

 B. Install pumps in accordance with manufacturer’s instructions. 

 C. Provide for connection to electrical service. 

 D. Lubricate pumps before start‐up. 

 3.02 FIELD QUALITY CONTROL  

A. Perform field inspection testing.  

B. Manufacturer’s  Field  Services:    Furnish  factory‐authorized  service  representatives  to inspect equipment during  installation,  to assist  in  adjusting and  testing,  to  supervise initial  operation,  and  to  make  final  adjustments  as  necessary  to  assure  satisfactory operation. 

 C. Minimum Length of Field Services:  2 trips, 1 day per trip, exclusive of travel time from 

pump manufacturer.  

D. Test  pumps  in  presence  of  Owner  to  verify  specified  capacities  and  operating characteristics are developed.   

 E. Make  repairs  and  retest  pumps  and  drives  until  specified  capacities  and  operating 

characteristics are achieved.  

F. Furnish labor, piping, equipment, and materials necessary for conducting tests.  3.03 DEMONSTRATION  

A. Furnish 1 day of on‐the‐job instructions (exclusive of travel time) to Owner personnel on all pump‐related equipment. 

 B. Equipment  demonstrations  and  instructions  are  in  addition  to  other Manufacturer’s 

Field Services specified in Article 3.02.  3.04 INSTRUCTION MANUALS  

A. Contractor  shall  furnish,  prior  to  initial  testing,  three  (3)  copies  of  an  indexed maintenance manual composed of suppliers’ maintenance manuals on all equipment 

Page 175: Standard Water and Sewer Specifications PDF

  SUBMERSIBLE SEWAGE PUMP STATIONS  11311‐15 

and  suppliers’  brochures  on  all  specialty  equipment,  including  performance  curves with  size,  model,  figure  number,  etc.,  indicated  to  identify  unit  furnished.  Maintenance manuals are to be of a hardback, loose‐leaf type and of a durable quality.  Manuals are  to be  for  the  specific equipment provided.   Manuals describing general equipment lines will not be accepted. 

 B. Each set is to include the following: 

1. Manufacturer’s parts list identified with the make, model and serial number of the equipment furnished. 

2. Control and wiring diagrams. 3. Installation, operation, lubrication and maintenance instructions. 4. Manufacturer’s recommended spare parts lists. 5. Certified pump curves for each pump to be owned and operated by the City. 

 3.05 FINAL INSPECTION  

The  final  inspection will  be performed by City personnel  in  accordance with  the  “Clarksville Gas & Water Lift Station Final Inspection Checklist” included in Appendix F. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 176: Standard Water and Sewer Specifications PDF
Page 177: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐1 

SECTION 11330  

HYDRAULIC SEWAGE GRINDERS  

TABLE OF CONTENTS  PART 1 – GENERAL  1.01 SUMMARY  

This  section  of  the  specification  describes  the  sewage  grinder,  hydraulic  power  pack,  and motor  controller.    The  equipment  shall  be  installed  as  shown on  the Contract Drawings,  as recommended  by  the  supplier,  and  in  compliance  with  all  OSHA,  local,  state,  and  federal codes and regulations. 

 1.02 REFERENCES  

Grinder shall, as applicable, meet the requirements of the following industry standards:  

A. ASTM A 36:  Standard Specification for Carbon Steel Plate.  

B. ASTM A 536 – 84:  Standard Specification for Ferritic Ductile Iron Castings.  

C. ASTM A 48‐83:  Standard Specification for Grey Iron Casting.  

D. AISI 303 Stainless Steel  

E. AISI 304 Stainless Steel  

F. AISI 4130 Heat Treated Alloy Steel  

G. AISI 4140 Heat Treated Hexagon Steel  

H. Rockwell C  1.03 SUBMITTALS  

A. Shop Drawings: Supplier shall submit 3 sets of shop drawings.  Shop drawings shall include equipment descriptions,  specifications,  dimensional  and  assembly  drawings,  parts  lists,  and  job specific drawings. 

 B. Closeout Submittals: 

Supplier shall submit 3 sets of Operation and Maintenance manuals.  The manuals shall include  equipment  descriptions,  operating  and  maintenance  instructions,  drawings, 

Page 178: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐2 

troubleshooting  techniques,  recommended  maintenance  schedule,  and  the recommended lubricants. 

 1.04 QUALITY ASSURANCE  

A. Qualifications:   Qualified  suppliers  shall  have  a minimum 5  years  experience  at manufacturing  two‐shafted grinding equipment and motor controls with a minimum of 2,000 installations with similar equipment.  Supplier shall provide a list of names and dates of installations for verification by the Engineer. 

 B. Regulatory Requirements:   

Motor  controllers  shall,  as  applicable,  meet  the  requirements  of  the  following Regulatory Agencies. 1. National Electrical Manufacturer’s Association Standards 2. National Electrical Code 3. Underwriters Laboratory 

 1.05 DELIVERY, STORAGE AND HANDLING  

A. The  equipment  shall  be  packaged  in  containers  constructed  for  normal  shipping, handling and storage. 

 B. The  containers  shall  provide  adequate protection  for  the  equipment  in  a  dry  indoor 

environment between + 40°F and + 100°F until time for installation.  1.06 IDENTIFICATION  

Each  unit  of  equipment  shall  be  identified  with  a  corrosion  resistant  nameplate,  securely affixed  in  a  conspicuous  place.    Nameplate  information  shall  include  equipment  model number, serial number, supplier’s name, and location. 

  PART 2 – PRODUCTS  2.01 MANUFACTURERS  

A. Grinder, hydraulic power pack, and motor controller shall be in compliance with these specifications  and  Contract  Drawings  and  shall  be  supplied  by  one  of  the  following manufacturers: 1. JWC Environmental®:   Channel Monster®  single or double drum as  shown on 

the Contract Drawings. 2. Approved equal 

 

Page 179: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐3 

B. Manufacturers requesting to be  included as an approved equal shall  submit certified documentation showing compliance with  these specifications a minimum of  ten  (10) days prior  to bid opening.   Selected equipment manufacturers shall be added to  the list of approved manufacturers. 

 C. The manufacturer must certify  that  the unit can be returned for maintenance to the 

factory or a local repair facility.  The certification shall include a statement that there will be no charge for repair labor during the one‐year warranty period. 

 2.02 SUPPORT SYSTEM FOR IN‐CHANNEL GRINDER  

A. General: A grinder support frame with adjustable mounting brackets shall be provided sized to match the channel shown on the Contract Drawings. 

 B. Components: 

The support frame and additional supports shall be of welded square tube, angle, and plate construction.  The construction material shall be 304 stainless steel. 

 2.03 GRINDER(S)  

A. General: 1. Each  Channel  Monster®  grinder  shall  include  cutters,  spacers,  shafts, 

perforated  screen  drum,  bearings  and  seals,  side  rails,  end  housings,  covers, reducer, and hydraulic torque motor. 

2. The  grinder  shall  be  of  two‐shaft  design  and  be  capable  of  continuous operation, processing wet or dry.  Bar screens or single‐shaft devices utilizing a single  rotating  cutter  bar  with  stationary  cutters  shall  not  be  acceptable.  Grinders  designed  with  cutter  and  spacer  cartridges  rather  than  individual cutters and spacers, shall not be acceptable. 

3. Two‐shaft  design  shall  consist  of  two  parallel  shafts  alternately  stacked with individual  intermeshing cutters and spacers positioned on the shaft to  form a helical  pattern.    The  two  shafts  shall  counter‐rotate  with  the  driven  shaft operating at approximately two‐thirds (2/3) the speed of the drive shaft. 

4. Rotating  perforated  screen  drum(s)  shall  consist  of  a  cylindrical  perforated sheet,  support  rings and stub shafts.    The  rotating drum shall  direct all  solids toward and into the counter‐rotating dual‐shaft grinder.   The drum(s) shall be driven by the grinder drive mechanism. 

 B. Components: 

1. Individual Cutters and Spacers: a) The cutting chamber shall be a nominal height as shown on the Contract 

Drawings. 

Page 180: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐4 

b) Individual  cutters  and  spacers  shall  be  4130  heat  treated  alloy  steel, surface ground for uniformity and through‐hardened to a minimum 45 – 50 Rockwell C. 

c) The inside configuration of both the individual cutters and the individual spacers shall be hexagonal so as to fit the shafts with a total clearance not  to  exceed  0.015  inch  across  the  flats  to  assure  positive  drive, minimize wear on the cutters, and increase the compressive strength of the spacers. 

d) Cutter  configuration  shall  consist  of  one  shaft  having  5  tooth  double‐edged cutters and one shaft having 11 tooth cam cutters.  To maintain particle size, the height of the tooth shall not exceed ½ inch above the root diameter.  Cutter to cutter root diameter overlap shall be not less than  1/16  inch  or  greater  than  ¼  inch  to  maintain  the  best  possible cutting efficiency while incurring the least amount of frictional losses. 

e) The cutters shall exert a minimum force at the tooth tip of 991  lbs/hp during momentary load peaks. 

2. Shafts a) Grinder  drive  and  driven  shafts  shall  be  made  of  4140  heat  treated 

hexagon steel with a tensile strength rating of not less than 149,000 psi. b) Each hexagonal  shaft  shall measure a nominal 2  inches across parallel 

surfaces. 3. Intermediate Shaft Support 

a)  An  intermediate  shaft  support  shall  be  provided  in  the  center  of  the cutter  stack  for  all  grinders  with  24‐inch,  32‐inch  or  40‐inch  cutter stacks.    Grinders with  50‐inch  or  60‐inch  cutter  stacks  shall  have  two intermediate shaft supports. 

b)  The  intermediate  shaft  support  shall  provide  additional  support  for heavier  than normal  influent grinder demand  loads and protection  for the seal assemblies. 

c)  The intermediate shaft support shall be made of cast 303 stainless steel collar and two bushings.  The bushings shall act as bearings to allow the free rotation of the shafts. 

4. Perforated Screen Drum(s) a)  The  screen  drum  shall  be made  of  11  gage  304  stainless  steel  sheet.  

The  perforated  sheet  shall  have  ¼‐inch  diameter  holes  on  a  3/8‐inch stagger. 

b)  The drum supports shall be constructed of 304 stainless steel.  The end supports shall  include stub shafts  for the mounting of seal assemblies.  Center support ring(s) shall provide additional structure to the center of the drums. 

c)  Drum  stub  shafts  shall  be  made  of  304  stainless  steel  with  a  tensile strength  of  not  less  than  95,000  psi.    The  shaft  diameter  shall  be  a minimum of 1‐1/2‐inch. 

5. Shaft Bearings and Seals 

Page 181: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐5 

a) The radial and axial loads of the cutter shafts shall be borne by sealed, oversized, deep‐groove ball bearings at each end. 

b) The bearings shall be protected by a combination of a replaceable and independent tortuous path device and mechanical seals. 

c) Face materials shall be of tungsten carbide to tungsten carbide. d) O‐rings shall be made of Buna‐N elastomers. e) Products requiring continuous or occasional lubrication or flushing shall 

not be accepted. f) The mechanical seal shall be rated at 90 psi continuous duty by the seal 

supplier. g) The  bearings  shall  be  housed  in  a  replaceable  cartridge  that  supports 

and aligns the bearings and seals, as well as protects the shafts and end housings.    The  seal elements  shall be  independent of  the  stack height and  cutter  stack  tightness  shall  not  affect  seal performance.    The  seal elements  shall  maintain  their  factory  set  preload  independent  of  the cutter stack tightness. 

h) Seals shall meet required pressure rating regardless of cutter stack  fit.  The seal cartridge shall provide seal protection against axial  loading on shafts and bearings during shaft deflection. 

i) Each  seal  element  shall  be  positively  locked  to  its  corresponding rotating  or  static  cartridge  element.    This  positive  lock  on  the  seal elements  is  critical  to  long  seal  life  in applications where grit or other abrasive materials are present. 

6. Cutter Side Rail a) The  inside profile of  the cutter side rail  shall be concave  to  follow the 

radial arc of the cutters. b) Clearance between the major diameter of the cutters and the concave 

arc of the side rails shall not exceed 5/16 inch. c) The  cutter  side  rails  shall  have  evenly‐spaced  slots  that  increase  flow 

and decrease head loss. d) The side rails shall be cast of A 536‐84 ductile iron. 

7. Drum Side Rail a) The  inside  profile  of  the  drum  side  rail  shall  be  concave,  with  an 

adjustable UHMW plastic  extension  strip  to minimize  clearance at  the front of the drum.   This clearance shall not exceed 1/16‐inch from the major diameter of the perforated screen drum. 

b) The drum side rail shall be cast of A 536‐84 ductile iron. 8. End Housings and Covers 

a) Grinder end housings shall be cast A 526‐84 ductile iron with a cast‐in‐place  flow  deflector,  designed  to  protect  the  bushings  while  guiding particles directly into the flow chamber. 

b) Top  covers  shall  be  A  536‐84  ductile  iron  and  bottom  covers  shall  be A36 hot rolled plates. 

Page 182: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐6 

9. Hydraulic Motor:  The grinder motor shall be a low‐speed, high‐torque, rotary‐power hydraulic torque motor that utilizes the hydraulic pressure developed by the hydraulic power pack. 

10. Required Running Torque per Horsepower:  Momentary Load Peaks at 2,298 in‐lbs/hp. 

 2.04 GRINDER HYDRAULIC POWER PACK  

A. General 1. The hydraulic power pack shall provide hydraulic pressure and flow to operate 

the  grinder.    The  hydraulic  power  pack  shall  provide  pressure,  temperature, and  level  outputs  to  the  controller.    The  power  pack  and  grinder  hydraulic motor shall be designed for smooth operation during frequent starts, stops and reversals. 

2. The entire hydraulic system shall be designed for 3,000 psi maximum pressure.  Under no load conditions the system operating pressure shall be in the 200 to 400 psi range.  Continuous operating pressure greater than 2,000 psi shall not be acceptable. 

3. As  solids  are  encountered,  pressure  shall  be  automatically  increased  on  a demand basis providing the required torque necessary to continue rotation of the cutters. a) Should  an  obstruction  cause  the  grinder  demand  pressure  to  exceed 

2,850 psi, a pressure switch shall be activated and a 2‐way valve shifted.  The rotation of the cutters shall immediately reverse for about one‐half (1/2) to one (1) revolution.  Following this, the valve shall be shifted and the cutters returned to forward rotation. 

b) When  the  obstruction  is  cleared  the  unit  shall  continue  to  operate  in the forward direction. 

c) If  the  obstruction  is  not  cleared,  the  reversing  sequence  shall  repeat until  the obstruction  is  cleared or 9  reversals have occurred within 45 seconds.  If the reversing sequence has completed and the obstruction has  not  been  cleared,  the  controller  shall  de‐energize  the  hydraulic power  pack  electric  motor  and  activate  an  overload  relay  and  a  fail indicator. 

4. The hydraulic power pack shall be rain‐resistant and suitable for mounting in a remote location, as required by design parameters of the project. 

 B. Components: 

1. Power packs shall include the following components: a) 16‐inch  x  16‐inch  x  15‐inch,  epoxy  coated,  10  gallon  U.S.  capacity 

reservoir. b) Suction strainer. c) Positive displacement pump driven by a vertically mounted 5 hp, TEFC, 

C face, electric motor. d) Relief valve preset at 3,000 psi. 

Page 183: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐7 

e) 2‐1/2‐inch, 0 to 5,000 psi oil filled gauge. f) Pressure switch present at 2,850 psi. g) 110 volt two‐port directional valve. h) High pressure return line filter. i) Combination oil level and oil temperature gauge. j) Combination oil level switch and oil temperature limit switch. k) Temperature switch set at 160°F. l) Filler breather. m) Electrical enclosure. 

2. Hydraulic  connections  between  the  torque  motor  and  the  power  pack  shall consist of two, ½ inch flexible hoses. a) The  flexible  hoses  shall  be  rated  for  a  minimum  3,500  psi  working 

pressure with a 14,000 psi burst pressure. b) The  hose  pressure  loss  between  the  hydraulic  power  pack  and  the 

grinder  torque motor  shall  not  exceed 150 psi  at  50°F  above ambient temperature. 

3. The hydraulic power pack shall be filled with a high quality hydraulic fluid. a) The  hydraulic  fluid  shall  have  a  viscosity  of  approximately  100  to  250 

SSU at 100°F with good chemical stability and anti‐foaming properties. b) The grades of hydraulic fluid shall be in accordance with the supplier’s 

recommendations.  2.05 MOTOR CONTROLLER  

A. General: 1. The  controller  shall  provide  independent  control  of  the  hydraulically  driven 

grinder. 2. Controller shall be the supplier’s standard UL/cUL listed Model PC2240. 3. The controller shall be rated for 5 hp, 480/230 volts, 3‐phase, 60 Hz. 

 B. Operation: 

The  controller  shall  be  equipped  with  a  GRINDER  ON‐OFF/RESET‐AUTO  three  (3) position selector switch. 1. In the OFF/RESET mode the grinder shall not run.  In the ON mode the grinder 

will run. 2. In the AUTO mode the grinder shall start and stop as controlled by a remotely‐

located dry contact. 3. The grinder shall only be reset by switching the GRINDER ON‐OFF/RESET‐AUTO 

switch to the OFF/RESET position.  

C. Safety Features: 1. When  a  grinder  jam  condition  occurs  in  the  grinder  ON  or  AUTO mode,  the 

controller shall stop the grinder, and then reverse the grinder rotation to clear the  obstruction.    If  the  jam  is  cleared,  the  controller  will  return  to  normal operation.  If the jam condition still exists, the controller will go through eight 

Page 184: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐8 

additional reversing cycles within 45 seconds (nine times total) before signaling a grinder overload condition.  Upon a grinder overload condition, the controller will shut the grinder off and activate an overload contact. 

2. If  a  power  failure  occurs while  the  grinder  is  running,  operation will  resume when power is restored. 

3. If a power failure occurs while the grinder is in a fail condition, the fail indicator shall be reactivated when power is restored. 

4. The  controller  shall  provide  overload  protection  for  the  motor  through  an overload relay mounted directly on the grinder starters. 

5. Short‐circuit protection  requires  that  a properly  sized  circuit breaker or  fuses be installed by others. 

6. Controller reset shall be from the local panel controls only.  

D. Components 1. Enclosure 

a) Enclosures  shall  be  NEMA  4X,  fabricated  of  fiberglass‐reinforced polyester  resins,  and  shall  be  suitable  for wall mounting.    Doors  shall have hinges and corrosion resistant latches. 

b) Enclosure  shall  house  the  control  devices,  relays,  terminal  blocks,  and grinder non‐reversing hydraulic power pack oil pump motor starter. 

2. Control Devices a) Operator interface and pilot devices shall be mounted on the enclosure 

front panel door. b) The controller shall have indicator lights for GRINDER RUN, and FAIL. c) Indicator  lights  shall  be  of  an  integral‐transformer  type  with  6‐volt 

lamps.   Lamps and the selector switches shall be heavy duty NEMA 4X type. 

d) Control  transformer  shall  be  protected  by  two primary  fuses  and  one secondary fuse.  The 120‐volt secondary shall have one leg grounded. 

e) Relay  contacts  shall  be  included  for  GRINDER  RUN  and  FAIL  signal outputs.  The contacts shall be rated 10 amp, 240 VAC, resistive load. 

3. Motor Starter a) A non‐reversing contactor type motor starter shall be provided for the 

hydraulic power pack oil pump motor. b) Overload  relay  (OL)  shall  be  adjustable  so  that  the  range  selected 

includes the FLA (full load amperes) rating and service factor.  2.06 SOURCE QUALITY CONTROL  

Each  grinder,  hydraulic  power  pack,  and  controller  shall  be  factory  tested  to  ensure satisfactory operation. 

 

Page 185: Standard Water and Sewer Specifications PDF

  HYDRAULIC SEWAGE GRINDERS  11330‐9 

PART 3 – EXECUTION  3.01 INSTALLATION  

Grinder, hydraulic power pack and motor controller shall be installed in accordance with the supplier’s  installation  instructions, and  in compliance with all OSHA,  local, state, and federal codes and regulations. 

 3.02 FIELD QUALITY CONTROL  

Supplier  shall  provide  1  day  of  services  of  a  factory‐trained  representative  to  check  the installation and to start‐up each grinder and controller.  The factory representative shall have complete  knowledge  of  proper  installation,  operation,  and  maintenance  of  equipment supplied.  Representative shall inspect the final installation and supervise a start‐up test of the equipment.  Representative shall also train Owner personnel in the operation of the grinder. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 186: Standard Water and Sewer Specifications PDF
Page 187: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐1 

SECTION 11410  

WET WELL MOUNTED, SUCTION LIFT SEWAGE PUMP STATIONS WITH DUPLEX PUMPS 

 TABLE OF CONTENTS 

 PART 1 – GENERAL  1.01  DESCRIPTION  

A. The  Contractor  shall  furnish  and  install  factory‐built,  automatic  pumping  stations  as described herein and as manufactured by Smith & Loveless, Inc.  Each station shall be complete  with  all  needed  equipment,  factory  installed  on  a  welded  steel  baseplate with fiberglass cover as shown on the Contract Drawings.  

 B. The  principal  items  of  equipment  shall  include  two  vertical,  close‐coupled,  motor 

driven,  vacuum  primed,  non‐clog  sewage  pumps;  valves;  internal  piping;  central control  panel  with  circuit  breakers,  motor  starters  and  automatic  pumping  level controls;  heater,  ventilating  blower,  priming  pumps  and  appurtenances,  and  all internal wiring. 

 1.02  OPERATING CONDITIONS  

A. Each  station  shall  be  equipped  with  pumps  capable  of  delivering  the  flows  of wastewater against the total dynamic heads indicated on the Contract Drawings and at the efficiencies specified.  Operating Design Points will be developed for each specific application.  Hydraulic calculations will be required to demonstrate the methods used to determine the design point. 

 B. All openings and passages shall be large enough to permit the passage of a sphere 3” 

in diameter and  the pump shall have a  flanged suction and discharge connection no smaller than 4”. 

 C. The pump motors shall not be overloaded beyond their nameplate rating at the design 

conditions nor at any head in the operating range.  1.03  MANUFACTURED EQUIPMENT EVALUATION  

A. The specifications and drawings detail Smith & Loveless equipment and represent the minimum standard of quality for both equipment and materials of construction. 

 B. Substitution  of  other  makes  may  be  considered  if  the  equipment  proposed  for 

substitution  is  superior or  equal  in quality  and efficiency  to  the  standards  of  quality named in the specifications and is demonstrated to the satisfaction of the Owner. 

Page 188: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐2 

 C. Contractors  wishing  to  substitute  equipment  shall  include  the  following  submittal 

information with their proposal.  This submittal shall include all necessary information for  the  proper  determination  of  the  acceptability  of  the  proposed  substitution  and shall not necessarily be limited to the following: 1. Complete description of the equipment, system, process or function, including 

a  list  of  system  components  and  features,  drawings,  catalog  information  and cuts, manufacturer’s specifications, including materials descriptions. 

2. Performance data and curves, and horsepower requirements. 3. Outside utility requirements, such as water, power, air, etc. 4. Functional  description  of  any  internal  instrumentation  and  controls  supplied 

including list of parameters monitored, controlled or alarmed. 5. Addresses  and  phone  numbers  of  nearest  service  centers  and  listing  of  the 

manufacturer’s  or  representative’s  services  available  at  these  locations, including  addresses  and  phone  numbers  of  the  nearest  parts  warehouses capable of providing full parts replacement and/or repair services. 

6. A  list  of  five  installations  in  the  states  where  similar  equipment  by  the manufacturer  is  currently  in  similar  service;  include  contact  name,  telephone number, mailing  address of  the municipality or  installation;  Engineer, Owner, and installing Contractor.  If five  installations do not exist,  the list shall  include all that do exist, if any. 

7. Detailed  information  on  site,  architectural,  structural,  mechanical,  plumbing, electrical and control, and all other changes or modifications to the design and construction  work  necessary  to  adapt  the  equipment  or  systems  to  the arrangement shown and/or functions described on the Contract Drawings and in the technical specifications.  This shall include plan view and section sketches illustrating  any  additional  space  requirements  necessary  to  provide  the minimum adequate clear space within and around the equipment for operation and maintenance, as shown on the drawings and specified. 

8. All  differences  between  the  specifications  and  the  proposed  substitute equipment shall be clearly stated in writing under a heading of “differences”. 

9. Other  specific  submittal  requirements  listed  in  the  detailed  equipment  and material specifications. 

 D. Approval of the substitution as an alternate shall in no way relieve the Contractor from 

submitting  the  specified  shop  drawings  for  approval  or  complying  fully  with  all provisions of  the  specifications  and drawings.    If  substituted  equipment  is  accepted, the Contractor shall, at his own expense, make any changes in the structures, piping, electrical, etc. necessary  to accommodate  the equipment.    If engineering  is  required due to substitution of alternate equipment, the Contractor shall pay for all engineering changes.   To  receive  final  consideration,  copies of  the manufacturer’s quotations  for the  equipment may  be  required  to  document  the  savings  to  the  satisfaction  of  the Engineer.  It is the intent that the Owner shall receive the full benefit of the savings in cost of the equipment and the Contractor’s bid price shall be reduced by an amount 

Page 189: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐3 

equal  to  the  savings.    In  all  technical  and  other  evaluations,  the  decision  of  the Engineer is final. 

 1.04  WARRANTY  

A. The manufacturer of the pump station shall guarantee the structure and all equipment to be free from defects in materials and workmanship for a period up to one year from the date of start‐up, not to exceed 18 months from the date of shipment.  Warranties and  guarantees  of  suppliers  of  various  components  in  lieu  of  a  single  source responsibility  by  the  pump  station  manufacturer  will  not  be  accepted.    The  pump station manufacturer shall be solely responsible for the guarantee of the station and all components.   

 B. In the event a component fails to perform as specified or is proven defective in service 

during  the  guarantee  period,  the  pump  station  manufacturer  shall  provide  a replacement part without cost  to  the Owner.   He shall  further provide, without cost, such labor as may be required to replace, repair or modify major components such as the  steel  structure,  pumps,  pump  motors,  suction  and  discharge  piping  and  valve assembly. 

  PART 2 – PRODUCTS  2.01 STATION  

A. All openings and passages shall be large enough to permit the passage of a sphere 3” in diameter.  The station shall be constructed in one complete, factory‐built assembly.  It shall be sized to rest on the top of the wet well as detailed on the Contract Drawings.   

 B. The  supporting  floor  plate  shall  be  a  minimum  3/8”  thick  steel  with  reinforcing,  as 

required,  to  prevent  deflection  and  ensure  an  absolutely  rigid  support.    Steel  plate shall meet or exceed ASTM A36 specifications.  

C. The pump volutes and discharge piping shall be mounted in relation to the floor plate as detailed  in  the Contract Drawings.   The suction and discharge connections, where they pass the floor plate, shall be sealed by gaskets rather than being welded to allow adjustment and replacement. 

 2.02 FIBERGLASS COVER  

A. The  pump  station  shall  be  enclosed  by  a  hinged  fiberglass  cover  made  of  molded reinforced  orthopthlalic  polyester  resins with  a minimum of  30%  glass  fibers with  a minimum average length of 1‐1/4”. The outside of the enclosure shall be coated with a polyester protective in‐mold coating for superior resistance to weathering, ultraviolet radiation, yellowing and chalking. The completed fiberglass cover shall be resistant to 

Page 190: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐4 

mold, mildew, fungus and corrosive liquids and gasses normally found in pump station environments.  

 B. The dimensions of the enclosure shown on the Contract Drawings shall be considered 

for  internal  component  clearances  and  accessibility  and  nothing  smaller  will  be acceptable.  The  cover  shall  have  a  suitable  drip‐lid  around  the  edge  and  shall  be provided  with  a  hasp  and  staple  connection  to  the  floor  plate  to  allow  the  pump chamber to be locked with a padlock.   

C. The cover shall be attached with a multi segment stainless steel hinge, constructed of 7  gauge  (minimum)  type  304  stainless  steel with  a  3/8”  diameter  stainless  steel  pin and  supporting  at  least  75%  of  the  width  at  one  end.  Stainless  steel  bolts  with tamperproof heads and a full width 3/8” thick anodized aluminum backing plate shall anchor  the  hinge  to  the  fiberglass  cover.  Dual  high  pressure  gas  struts  shall  be provided to counteract the dead weight of the cover assembly and limit the maximum lifting  force  required  for  opening  to  less  than  20  pounds.  The  cover  shall  be  self‐latching  upon  opening,  with  a  manually  operated  release  for  closing.  Duplex  heavy gauge safety chains shall be provided to prevent over extension.   

D. All  hardware  and  components  of  the  cover  assembly  which  are  exposed  to  the weather  shall  be  constructed  of  corrosion  resistant  materials.  Heavy  extruded aluminum  adjustable  louvers  shall  be  provided  on  each  end  of  the  fiberglass  cover, which are capable of being closed during cold weather operation. 

 2.03 MANWAY  

A. An  aluminum  manway  cover  fabricated  of  1/4”  treadplate,  located  exterior  to  the fiberglass pump chamber shall be provided, complete with padlocking provisions.  The manway shall be an integral part of the pump station floor and shall provide access to the wet well.  The minimum open area of the manway access into the wet well shall be at least 4.2 square feet.   

 B. The manway cover shall have a three color 7”x10” (minimum) corrosion resistant sign 

permanently  affixed  to  it,  reading  “DANGER  –  Before  Entering,  Test  for  Explosive Gasses.  Test for Oxygen Deficiency.  Supply Fresh Air to Work Area.” 

 2.04 LIFTING ARM  

To allow on‐site maintenance of the pumps, a stanchion with lifting arm shall be provided to lift each pump.  The stanchion requirement will apply to both vertical and horizontal pumps, whichever is supplied by the installing Contractor.  The lifting arm shall have a hook over the center of the motor to support a hoist for removal of the motors, impellers and pumps from the station. 

  

Page 191: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐5 

2.05 WELDING  

All  steel  structural members  shall  be  joined by electric  arc welding with welds of  adequate section for the joint involved.  Structural welding shall be performed in accordance with AWS standards and procedures. 

 2.06 CORROSION PROTECTION  

After welding, all inside and outside surfaces of the structure shall be blasted with steel grit to remove  rust,  mill  scale,  weld  slag  etc.    All  weld  splatter  and  surface  roughness  shall  be removed by grinding.  Immediately following the cleaning, a single heavy inert coating shall be factory  applied  to  all  inside  and  outside  surfaces  prior  to  shipment.    This  coating  shall  be Versapox  epoxy  resin  specially  formulated  for  abrasion  and  corrosion  resistance.    The  dry coating  shall  contain  a minimum  of  86%  epoxy  resin with  the  balance  being  pigments  and thixotropic agents. 

 2.07 MAIN PUMPS  

A. The  pumps  shall  be  4”  vertical,  non‐clog  type  of  heavy  cast  iron  construction, especially designed for the use of mechanical seals and vacuum priming.    In order to minimize seal wear caused by linear movement of the shaft, the shaft bearing nearest the pump impeller shall be  locked  in place so that end play  is  limited to the clearing within the bearing. 

 B. To minimize seal wear resulting from shaft deflection caused by the radial thrust of the 

pump,  the  shaft  from  the  top  of  the  impeller  to  the  lower  bearing  supporting  the impeller shall have a minimum diameter of 1‐7/8” for motor sizes 1.5 H.P. through 15 H.P.  (motor  frame sizes 213 through 286); 2‐1/8” for motor sizes 20 H.P.  through 30 H.P. (motor frame sizes 324 and 326); and 3” for motor sizes 40 H.P. and larger (motor frame sizes 364 and larger).  The dimension from the lowest bearing to the top of the impeller shall not exceed 6”. 

 C. The bearing nearest the impeller shall be designed for the combined thrust and radial 

load. The upper bearing shall be free to move  linearly with the thermal expansion of the  shaft  and  shall  carry  only  radial  loads.    The  shaft  shall  be  solid  stainless  steel through the pump and bottom bearing to eliminate corrosion within the pump or the mechanical seal.  Removable shaft sleeves will not be acceptable if the shaft under the sleeve does not meet the specified minimum diameter. 

 D. The pump impellers shall be of the enclosed type made of close‐grained cast iron and 

shall be balanced.  The impeller shall be keyed with a stainless steel key and secured to the motor shaft by a stainless steel cap screw equipped with a Nylock or other suitable self locking device. 

 

Page 192: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐6 

E. The  impeller  shall  not  be  screwed or  pinned  to  the motor  pump  shaft,  and  shall  be readily removable without the use of special tools.   To prevent the buildup of stringy materials, grit and other foreign particles around the pump shaft, all impellers less that full diameter shall be trimmed inside the impeller shroud.  The shroud shall remain full diameter so that close minimum clearance from shroud to volute is maintained.  Both the end of the shaft and bore of the impeller shall be tapered to permit easy removal of the impeller from the shaft.  The pump shall have an adapter providing a large water reservoir above the impeller to provide for positive exclusion of air from the impeller.  The seal shall be inside this area to assure lubrication.  Pumps which do not use hollow priming adapters for positive lubrication of the seal will not be acceptable. 

 F. The  pump  shall  be  constructed  so  as  to  permit  priming  from  the  low  pressure  area 

behind the impeller.   Priming from high pressure connections tending to cause solids to enter and clog the priming system will not be acceptable.  The priming bowl shall be transparent to enable the operator to monitor  the priming  level.   The pump shall be arranged so that the rotating element can easily be removed from the volute without disconnecting the electrical wiring or disassembling the motor,  impeller, backhead or seal so that any foreign object may be removed from the pump or suction line. 

 G. The pump shaft shall be sealed against leakage by a single mechanical seal constructed 

so  as  to  be  automatically  drained  and  primed  each  time  the  pump  is  drained  and primed.  The seal housing shall be bronze.  Water which lubricates the mechanical seal shall be automatically drained from around the seal if the pump loses prime, in order to  allow  both  the  pump  and  seal  to  be  drained,  thereby  preventing  freezing  and breakage  of  the  seal  during  power  outages  in  sub‐freezing  temperatures.    The  seal shall be of carbon and ceramic materials with mating surfaces lapped to a flatness of one  light  band.    The  rotating  ceramic  shall  be  held  in  mating  position  with  the stationary carbon by a stainless steel spring. 

 H. The  pump  volute  shall  be  furnished  with mounting  lugs  and  shall  be  bolted  to  the 

station floor plate, forming a gas‐tight seal.  2.08 MOTORS  

A. The pump motors shall be vertical,  solid shaft, NEMA P‐base,  squirrel‐cage  induction type, suitable for 3 Phase, 60 Cycle, 230 Volt electric current.  They shall have Class F insulation  suitable  for  temperatures  up  to  105  degrees  C.    Insulation  temperature shall,  however,  be maintained  below  80  degrees  C.    The motors  shall  have  normal starting torque and low starting current, as specified by NEMA Design B characteristics.  They  shall  be  open  drip‐proof  design  with  forced  air  circulation  by  integral  fan.  Openings  for  ventilation  shall  be  uniformly  spaced  around  the motor  frame.    Leads shall be terminated in a cast connection box and shall be clearly identified. 

 B. The motors shall have a 1.15 service factor.  The service factor shall be reserved for the 

Owner’s  protection.    The  motors  shall  not  be  overloaded  beyond  their  nameplate 

Page 193: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐7 

rating, at the design conditions, nor at any head in the operating range specified under Operating Conditions. 

 C. The motor pump shaft shall be centered, in relation to motor base, within 0.005”.  The 

shaft  runout  shall  not  exceed  0.003”.    The  motor  shaft  shall  equal  or  exceed  the diameter specified under Main Pumps, at all points  from  immediately below the  top bearing  to  the  top of  the  impeller hub.   A bearing cap shall be provided  to hold  the bottom motor  bearing  in  a  fixed  position.    Bearing  housings  shall  be  provided with fittings for lubrication as well as purging old lubricant. 

 D. The motor shall be fitted with heavy lifting eyes, each capable of supporting the entire 

weight of the pump and motor rotating assembly.  2.09 CONTROLS  

A. The  control  equipment  shall  be mounted  in  a  NEMA  Type  1  steel  enclosure  with  a removable  access  cover.    The  circuit  breakers,  starter  reset  buttons  and  control switches  shall  be  operable  without  removing  the  access  cover,  for  deadfront protection.  

B. A grounding type convenience outlet shall be provided on the side of the cabinet for operation  of  120  volt  AC  devices.    Thermal  magnetic  air  circuit  breakers  shall  be provided for branch disconnect service and short circuit protection of all motor control and auxiliary circuits.  

C. Magnetic  across‐the‐line  starters  with  under‐voltage  release  and  overload  coils  for each  phase  shall  be  provided  for  each  pump motor  to  give  positive  protection.    All starters shall be NEMA rated –  IEC type starters shall not be acceptable.   Each single phase  auxiliary  motor  shall  be  equipped  with  an  over‐current  protection  device  in addition to the branch circuit breaker, or shall be impedance protected.   All switches shall be labeled and a coded wiring diagram shall be provided.  

D. To control the operation of the pumps with variation of liquid level in the wet well, a Devar Model 332 Controller shall be installed in the control panel by the pump station manufacturer.    The  liquid  level  shall  be  monitored  by  a  submersible  hydrostatic pressure transducer with stainless steel sensor diaphragm providing a 4‐20 mA signal to the pump controller.  The submersible transducer shall be a Blue Ribbon “Bird Cage” unit.  Three (3) float displacement switches shall be provided to automatically operate the pumps in back‐up mode in the event the digital control system or the submersible level transducer fails.  The back‐up system shall be independent of the digital system.  A minimum of 30 feet of cord shall be provided with each switch.  The cord shall have a  corrosion  resistant  vinyl  jacket  and  shall  be  multi‐stranded  in  order  to  prevent fatigue.    The  displacement  switch  cords  and  the  cable  for  the  submersible  pressure transducer shall enter the wet well through cord grip seals. 

 

Page 194: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐8 

E. An automatic alternator with manual switch shall be provided to change the sequence of  operation  of  the  pumps  after  every  cycle.    The manual  switch  shall  allow  either pump to be selected as a base pump or for automatic operation.   

F. Provisions shall also be made for the pumps to operate in parallel should the level  in the wet well continue to rise above the starting level for the low level “Lead” pump.  

 2.10 ACCESSORIES  

A. An  adjustable  displacement  switch  shall  be  provided  to  sense  a  high  water  level condition.    The  switch  shall  hang  into  the  wet  well  and  shall  activate  a  contact  to indicate the high water condition. 

 B. A  vapor‐proof  light  fixture with  a  12  V  50 watt  lamp,  red  globe  and  guard  shall  be 

furnished for outdoor mounting to signal the alarm condition.  

C. A running time meter shall be supplied for each pump to show the number of hours of operation.   The meter shall be enclosed  in a dust and moisture‐proof molded plastic case. The flush mounted dial shall register in hours and tenths of hours up to 99999.9 hours before repeating.  The meter shall be suitable for operation on 120 VAC supply. 

 D. A  2  or  3  KVA  insulating  type  transformer  shall  be  provided  to  supply  power  lights, 

controls and auxiliary devices.   A 2 KVA transformer shall be used where the suction pipes are 4” size.  A 3 KVA transformer shall be used where the suction pipe sizes are  

 6” or larger.  The transformer shall have 240/460 volt primary, 120/240 volt secondary, Class  F  insulation,  with  temperature  rise  not  to  exceed  115  degrees  C  above  a  40 degree C ambient.  The core and coil shall be protected by a metal housing to prevent damage. 

 E. A relay with double pole double throw contacts to monitor and protect against phase 

loss  (single  phase),  under  voltage  (brown  outs)  and  phase  reversal  (improper sequence)  shall  be provided  in  the  control  system.    The  relay  shall  activate  the high water  alarm  light  in  the  event  of  a  failure.    The  relay  shall  automatically  reset whenever three phase service returns to normal. 

 F. Adjustable time delay relays shall be provided to prevent simultaneous starting of the 

pump motors after power failure.  

G. Glycerin  filled pressure/vacuum gauges with diaphragm protectors  shall  be provided for each pump.  Each gauge shall be furnished with isolation valve and tubing. 

 2.11 VACUUM PRIMING SYSTEM  

Page 195: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐9 

A. A  separate  and  independent  priming  system  shall  be  furnished  for  each  pump, providing complete standby operation.   Each priming system shall  include a separate vacuum  pump.  Vacuum  pumps  shall  have  corrosion  resistant  internal  components.  The vacuum priming system shall be complete with large port vacuum control solenoid valves,  Sonic  Start™  prime  level  sensor,  float  operated  check  valves  to  protect  the vacuum  pumps,  and  all  necessary  shut‐off  valves.    The  float  operated  check  valves shall have a transparent body for visual inspection of the liquid level and shall have an automatic drain check valve.  All hoses and tubing used in the priming system shall be at least 3/8” nominal diameter. 

 B. The solenoid valves used in the vacuum priming system shall be of the high flow, direct 

acting brass body type, with threaded ports, NBR seals and 300 Series stainless steel plunger,  rod,  plate  and  springs.    The minimum orifice  diameter  shall  be  5/16”.    The solenoid  valves  shall  be  UL  Listed,  with  Class  F  coil  rating  and  suitable  voltage  and thermal capacity for the application. 

 C. Each  solenoid valve  shall be protected by a vapor  filter,  installed  in  the vacuum  line 

between  the  valve  and  the  priming  dome.    The  vapor  filter  shall  be  constructed  of corrosion resistant materials and shall have a minimum filtration area of 2.74 square inches and shall be suitable  for operation  from 25”Hg to 100 PSI.   The  filter  shall be readily replaceable without the use of special tools. 

 D. Liquid  level  in  the  pump  priming  chamber  shall  be  monitored  by  a  Sonic  Start™ 

resonant frequency liquid level sensor with piezoelectric drive and sensitive circuits to detect frequency shifts when the sensor is covered by liquid.  This type of system shall be used rather than an electrode system or mechanical means such as a float, to avoid electrical or moving parts inside the chamber, which may accumulate debris, short out, bind or fail.  Only a resonant frequency level sensor with no electrical components or floats in the priming chamber shall be used. 

 E. The priming system shall automatically provide positive lubrication of the mechanical 

seal each time a main pump is primed.  To prevent excessive stoppage due to grease accumulation, no passageway in the priming system through which the pumped liquid must pass shall be smaller than the equivalent of a 2‐1/2” opening. 

 F. The vacuum priming system shall have two field selectable modes of operation.  In the 

“ON DEMAND” mode, the priming system will operate only after a pump is called on to run,  and  if  it  is  not primed.   Once primed,  the pump will  be  allowed  to  run.    In  the “CONSTANT PRIME” mode,  both pumps  are  kept  primed  continuously,  and  ready  to start immediately when called for. 

 2.12 ENVIRONMENTAL EQUIPMENT  

A. A ventilating blower capable of delivering 250 CFM at 0.1” static water pressure shall be provided  in order  to  remove  the heat generated by  continuous motor operation.  

Page 196: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐10 

The  ventilating  blower  shall  be  turned  on  and  off  automatically  by  the  preset thermostat.  A heavy extruded aluminum louvered grill with adjustable openings shall cover the discharge of the blower.  A similar grill shall be provided in the other end of the station enclosure for air intake. 

 B. A 500 watt electric heater controlled by a preset thermostat shall be furnished.   The 

heater shall be rigidly mounted in the station to prevent removal.  2.13 MAIN PIPING  

A. The  pump  suctions  shall  be  drilled  and  tapped  for  a  125  pound  American  Standard flange for easy connection of the suction risers.  

B. The discharge line from each pump shall be fitted with a clapper‐type check valve and eccentric plug valve.   Size, location and quantity of check valves and plug valves shall be as shown on the Contract Drawing.  

C. The  check  valve  shall  be  of  the  spring‐loaded  type  with  external  lever  arm  and  an easily replaced resilient seat for added assurance against priming leaks.  Check valves shall  have  stainless  steel  shaft  with  replaceable  bronze  shaft  bushings  and  shall  be sealed through the bearings with O‐rings.   To facilitate back flushing of either pump, only  check valves with outside  lever arms will be acceptable.   Ball‐type check valves are specifically unacceptable for this application.  

D. All station piping and fittings shall be capable of passing a 3” solid.  

E. An operating wrench shall be provided for the plug valves.  

F. Protrusions through the floor plate shall be gas‐tight where necessary to effect sealing between the equipment chamber and the wet well.  Bolted and sealed joints shall be provided at the pump volutes or suction pipes  in order to prevent corrosive, noxious fumes  from  entering  the  station.    The  pump  station manufacturer  shall  extend  the suction  and  discharge  connections  below  the  floor  plate  at  the  factory  so  that  field connections can be made without disturbing the gas‐tight seals.  

G. The  manufacturer  of  the  pump  station  shall  provide  a  compression  type  sleeve coupling for  installation  in the common discharge pipe.   Provisions shall be made for securing the coupling to the station floor plate. 

 2.14 FLEXIBLE CONDUIT  

To prevent  potential  settling  damage,  at  least  four  feet  of  flexible  conduit  shall  be used  to connect rigid conduit to the lift station. 

  

Page 197: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐11 

2.15 SPARE PARTS  

A complete replacement pump shaft seal assembly shall be furnished with each pump station.  The spare seal shall be packed in a suitable container and shall  include complete installation instructions.  A spare volute gasket and seal gasket shall be provided. 

  PART 3 – EXECUTION  3.01 FACTORY TESTS  

A. All  components  of  the  pump  station  shall  be  given  an  operational  test  at  the  pump station manufacturer’s facility to check for excessive vibration or leaks in the piping or seals, and to correct operation of the automatic control and vacuum priming systems and all auxiliary equipment.  Installed pumps shall take suction from a deep wet well, simulating actual service conditions.  The control panel shall undergo both a dry logic test and a full operational test with all systems operating. 

 B. Factory  test  instrumentation must  include  flow measuring with  indicator;  compound 

suction  gauge;  bourdon  tube  type  discharge  pressure  gauge;  electrical  meters  to measure  amperes,  volts,  kilowatts  and  power  factor;  speed  indicator;  and  a vibrometer capable of measuring both amplitude and frequency. 

 3.02 INSTALLATION AND OPERATING INSTRUCTIONS  

A. Installation  of  the  pump  station  shall  be  done  in  accordance  with  the  written instructions provided by the manufacturer.  

B. The Manufacturer shall supply four (4) copies of Operation and Maintenance manuals which  will  include  parts  lists  of  components  and  complete  service  procedures  and troubleshooting guide. 

 3.03 START‐UP  

The pump  station manufacturer  shall  provide  complete  start‐up  service.    The pump  station manufacturer  representative  or  factory  service  technician  will  inspect  the  completed installation  to  determine  if  the  installed  equipment  meets  the  purpose  and  intent  of  the specifications.    Tests  shall  demonstrate  that  all  equipment  is  electrically,  mechanically, structurally and otherwise acceptable; the station installation is safe and in optimum working condition; and conforms to the specified operating conditions.   The start‐up technician shall instruct the Owner’s personnel in the proper operation and maintenance procedures. 

    

Page 198: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH DUPLEX PUMPS  11410‐12 

3.04 FINAL INSPECTION  

The  final  inspection will  be performed by City personnel  in  accordance with  the  “Clarksville Gas & Water Lift Station Final Inspection Checklist” included in Appendix F. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 199: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐1 

SECTION 11411  

WET WELL MOUNTED, SUCTION LIFT SEWAGE PUMP STATIONS WITH SERIES PUMPS 

 TABLE OF CONTENTS 

 PART 1 – GENERAL  1.01  DESCRIPTION  

A. The Contractor shall furnish and install factory‐built, automatic pumping stations with pumps  in  series  as  described  herein  and  as manufactured  by  Smith &  Loveless,  Inc.  Each  station  shall  be  complete  with  all  needed  equipment  factory  installed  on  a welded steel base plate with fiberglass cover as shown on the Contract Drawings.  

B. The principal  items of equipment in each station shall  include vertical, close‐coupled, motor driven, vacuum primed, non‐clog sewage pumps; valves; internal piping; central control  panel  with  circuit  breakers,  motor  starters  and  automatic  pumping  level controls;  heater,  ventilating  blower,  priming  pumps  and  appurtenances,  and  all internal wiring. 

 1.02  OPERATING CONDITIONS  

A. Each station shall be equipped with four  (4) pumps (two pumps  in series) capable of delivering  the  flows  of  raw  water  or  wastewater  against  the  total  dynamic  heads indicated and at the efficiencies specified in the contract documents.  Operating design points will  be developed  for  each  specific  application.   Hydraulic  calculations will  be required to demonstrate the methods used to determine the design points. 

 B. All openings and passages shall be large enough to permit the passage of a sphere 3” 

in diameter and each pump shall have a flanged suction and discharge connection no smaller than 4”. 

 C. The pump motors shall not be overloaded beyond the nameplate rating at the design 

conditions nor at any head in the operating range.  1.03  MANUFACTURED EQUIPMENT EVALUATION  

A.  The specifications and drawings detail Smith & Loveless equipment and represent the minimum standard of quality for both equipment and materials of construction. 

 B.  Substitution  of  other  makes  may  be  considered  if  the  equipment  proposed  for 

substitution  is  superior or  equal  in quality  and efficiency  to  the  standards  of  quality named in the specifications and is demonstrated to the satisfaction of the Owner. 

Page 200: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐2 

 C.  Contractors  wishing  to  substitute  equipment  shall  include  the  following  submittal 

information with their proposal.  This submittal shall include all necessary information for  the  proper  determination  of  the  acceptability  of  the  proposed  substitution  and shall not necessarily be limited to the following: 1. Complete description of the equipment, system, process or function, including 

a  list  of  system  components  and  features,  drawings,  catalog  information  and cuts, manufacturer’s specifications, including materials descriptions. 

2. Performance data and curves, and horsepower requirements. 3. Outside utility requirements, such as water, power, air, etc. 4. Functional  description  of  any  internal  instrumentation  and  controls  supplied 

including list of parameters monitored, controlled or alarmed. 5. Addresses  and  phone  numbers  of  nearest  service  centers  and  listing  of  the 

manufacturer’s  or  representative’s  services  available  at  these  locations, including  addresses  and  phone  numbers  of  the  nearest  parts  warehouses capable of providing full parts replacement and/or repair services. 

6. A  list  of  five  installations  in  the  states  where  similar  equipment  by  the manufacturer  is  currently  in  similar  serve;  include  contact  name,  telephone number, mailing  address  of  the municipality  or  installation;  engineer,  owner, and installing Contractor.  If five  installations do not exist,  the list shall  include all that do exist, if any. 

7. Detailed  information  on  site,  architectural,  structural,  mechanical,  plumbing, electrical and control, and all other changes or modifications to the design and construction  work  necessary  to  adapt  the  equipment  or  systems  to  the arrangement  shown  and/or  functions  described  on  the  drawings  and  in  the technical  specifications.    This  shall  include  plan  view  and  section  sketches illustrating  any  additional  space  requirements  necessary  to  provide  the minimum adequate clear space within and around the equipment for operation and maintenance, as shown on the drawings and specified. 

8. All  differences  between  the  specifications  and  the  proposed  substitute equipment shall be clearly stated in writing under a heading of “differences”. 

9. Other  specific  submittal  requirements  listed  in  the  detailed  equipment  and material specifications. 

 D. Approval of the substitution as an alternate shall in no way relieve the Contractor from 

submitting  the  specified  shop  drawings  for  approval  or  complying  fully  with  all provisions of  the  specifications  and drawings.    If  substituted  equipment  is  accepted, the Contractor shall, at his own expense, make any changes in the structures, piping, electrical, etc. necessary  to accommodate  the equipment.    If engineering  is  required due to substitution of alternate equipment, the Contractor shall pay for all engineering changes.   To  receive  final  consideration,  copies of  the manufacturer’s quotations  for the  equipment may  be  required  to  document  the  savings  to  the  satisfaction  of  the Engineer.  It is the intent that the Owner shall receive the full benefit of the savings in cost of the equipment and the Contractor’s bid price shall be reduced by an amount 

Page 201: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐3 

equal  to  the  savings.    In  all  technical  and  other  evaluations,  the  decision  of  the Engineer is final. 

 1.04   WARRANTY  

A. The manufacturer of the pump station shall guarantee the structure and all equipment to be free from defects in materials and workmanship for a period up to one year from the date of start‐up, not to exceed 18 months from the date of shipment.  Warranties and  guarantees  of  suppliers  of  various  components  in  lieu  of  a  single  source responsibility  by  the  pump  station  manufacturer  will  not  be  accepted.    The  pump station manufacturer shall be solely responsible  for the guarantee of the station and all components.   

 B. In the event a component fails to perform as specified or is proven defective in service 

during  the  guarantee  period,  the  pump  station  manufacturer  shall  provide  a replacement part without cost to the Owner.   He shall  further provide, without cost, such labor as may be required to replace, repair or modify major components such as the  steel  structure,  pumps,  pump  motors,  suction  and  discharge  piping  and  valve assembly. 

  PART 2 – PRODUCTS  2.01  STATION  

A. All openings and passages shall be large enough to permit the passage of sphere 3” in diameter.  Each station shall be constructed in one complete factory‐built assembly.  It shall be sized to rest on top of the wet well as detailed in the contract drawings.    

B. The  supporting  floor  plate  shall  be  a  minimum  1”  thick  steel  with  reinforcing  as required  to prevent deflection and  to  insure an absolutely  rigid  support.    Steel plate shall meet or exceed ASTM A‐36 specifications.   

C. The pump volutes and discharge piping shall be mounted in relation to the floor plate as detailed  in  the Contract Drawings.   The suction and discharge connections, where they pass the floor plate, shall be sealed by gaskets rather than being welded to allow adjustment and replacement. 

 2.02  FIBERGLASS COVER  

A. Each  pump  station  shall  be  enclosed  by  a  hinged  fiberglass  cover  made  of  molded reinforced  orthopthlalic  polyester  resins with  a minimum of  30%  glass  fibers with  a minimum average length of 1‐1/4”.  The outside of the enclosure shall be coated with a  polyester  protective  in‐mold  coating  for  superior  resistance  to  weathering, ultraviolet radiation, yellowing and chalking.   The completed fiberglass cover shall be 

Page 202: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐4 

resistant to mold, mildew, fungus and corrosive  liquids and gasses normally  found  in pump station environments. 

 B. The dimensions of the enclosure shown on the Contract Drawings shall be considered 

for  internal  component  clearances  and  accessibility  and  nothing  smaller  will  be acceptable.    The  cover  shall  have  a  suitable  drip‐lid  around  the  edge  and  shall  be provided  with  a  hasp  and  staple  connection  to  the  floor  plate  to  allow  the  pump chamber to be locked with a padlock.   

 C. The cover shall be attached with a multi segment stainless steel hinge, constructed of 

7  gauge  (minimum)  type  304  stainless  steel with  a  3/8”  diameter  stainless  steel  pin and  supporting  at  least  75%  of  the  width  at  one  end.    Stainless  steel  bolts  with tamperproof heads and a full width 3/8” thick anodized aluminum backing plate shall anchor  the  hinge  to  the  fiberglass  cover.    Dual  high  pressure  gas  struts  shall  be provided to counteract the dead weight of the cover assembly and limit the maximum lifting  force  required  for  opening  to  less  than  20  pounds.    The  cover  shall  be  self‐latching  upon  opening, with  a manually  operated  release  for  closing.    Duplex  heavy gauge safety chains shall be provided to prevent over extension.   

 D. All  hardware  and  components  of  the  cover  assembly  which  are  exposed  to  the 

weather  shall  be  constructed  of  corrosion  resistant  materials.    Heavy  extruded aluminum  adjustable  louvers  shall  be  provided  on  each  end  of  the  fiberglass  cover, which are capable of being closed during cold weather operation. 

 2.03  LIFTING ARM  

To allow on‐site maintenance of the pumps, a stanchion with lifting arm shall be provided to lift/pull  each  pump.    The  stanchion  requirement  will  apply  to  both  vertical  and  horizontal pumps, whichever is supplied by the installing Contractor.  The arm shall have a hook over the center of the motor to support a hoist for removal of the motors, impellers and pumps from the station.   

 2.04  MANWAY  

A. An  aluminum  manway  cover  fabricated  of  1/4”  treadplate,  located  exterior  to  the fiberglass pump chamber shall be provided, complete with padlocking provisions.  The manway shall be an integral part of the pump station floor and shall provide access to the wet well.  The minimum open area of the manway access into the wet well shall be at least 4.2 square feet.    

B. The manway cover shall have a three color 7”x10” (minimum) corrosion resistant sign permanently  affixed  to  it,  reading  “DANGER  –  Before  Entering,  Test  for  Explosive Gasses.  Test for Oxygen Deficiency.  Supply Fresh Air to Work Area.” 

  

Page 203: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐5 

2.05  WELDING  

All  steel  structural members  shall  be  joined by electric  arc welding with welds of  adequate section for the joint involved.  Structural welding shall be performed in accordance with AWS standards and procedures. 

 2.06  CORROSION PROTECTION  

After welding, all inside and outside surfaces of the structure shall be blasted with steel grit to remove  rust,  mill  scale,  weld  slag  etc.    All  weld  splatter  and  surface  roughness  shall  be removed by grinding.  Immediately following the cleaning, a single heavy inert coating shall be factory  applied  to  all  inside  and  outside  surfaces  prior  to  shipment.    This  coating  shall  be Versapox  epoxy  resin  specially  formulated  for  abrasion  and  corrosion  resistance.    The  dry coating  shall  contain  a minimum  of  86%  epoxy  resin with  the  balance  being  pigments  and thixotropic agents. 

 2.07  MAIN PUMPS  

A. The  pumps  shall  be  4”  vertical,  non‐clog  type  of  heavy  cast  iron  construction, especially designed for the use of mechanical seals and vacuum priming.    In order to minimize seal wear caused by linear movement of the shaft, the shaft bearing nearest the pump impeller shall be  locked  in place so that end play  is  limited to the clearing within the bearing.  

B. To minimize seal wear resulting from shaft deflection caused by the radial thrust of the pump,  the  shaft  from  the  top  of  the  impeller  to  the  lower  bearing  supporting  the impeller shall have a minimum diameter of 1‐7/8” for motor sizes 1.5 H.P. through 15 H.P.  (motor  frame sizes 213 through 286); 2‐1/8” for motor sizes 20 H.P.  through 30 H.P. (motor frame sizes 324 and 326); and 3” for motor sizes 40 H.P. and larger (motor frame sizes 364 and larger).  The dimension from the lowest bearing to the top of the impeller shall not exceed 6”.  

C. The bearing nearest the impeller shall be designed for the combined thrust and radial load. The upper bearing shall be free to move  linearly with the thermal expansion of the  shaft  and  shall  carry  only  radial  loads.    The  shaft  shall  be  solid  stainless  steel through the pump and bottom bearing to eliminate corrosion within the pump or the mechanical seal.  Removable shaft sleeves will not be acceptable if the shaft under the sleeve does not meet the specified minimum diameter.  

D. The pump impellers shall be of the enclosed type made of close‐grained cast iron and shall be balanced.  The impeller shall be keyed with a stainless steel key and secured to the motor shaft by a stainless steel cap screw equipped with a Nylock or other suitable self locking device.  

Page 204: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐6 

E. The  impeller  shall  not  be  screwed or  pinned  to  the motor  pump  shaft,  and  shall  be readily removable without the use of special tools.   To prevent the buildup of stringy materials, grit and other foreign particles around the pump shaft, all impellers less that full diameter shall be trimmed inside the impeller shroud.  The shroud shall remain full diameter so that close minimum clearance from shroud to volute is maintained.  Both the end of the shaft and bore of the impeller shall be tapered to permit easy removal of the impeller from the shaft.  The pump shall have an adapter providing a large water reservoir above the impeller to provide for positive exclusion of air from the impeller.  The seal shall be inside this area to assure lubrication.  Pumps which do not use hollow priming adapters for positive lubrication of the seal will not be acceptable.  

F. The  pump  shall  be  constructed  so  as  to  permit  priming  from  the  low  pressure  area behind the impeller.   Priming from high pressure connections tending to cause solids to enter and clog the priming system will not be acceptable.  The priming bowl shall be transparent to enable the operator to monitor  the priming  level.   The pump shall be arranged so that the rotating element can easily be removed from the volute without disconnecting the electrical wiring or disassembling the motor,  impeller, backhead or seal so that any foreign object may be removed from the pump or suction line.  

G. The pump shaft shall be sealed against leakage by a single mechanical seal constructed so  as  to  be  automatically  drained  and  primed  each  time  the  pump  is  drained  and primed.  The seal housing shall be bronze.  Water which lubricates the mechanical seal shall be automatically drained from around the seal if the pump loses prime, in order to  allow  both  the  pump  and  seal  to  be  drained,  thereby  preventing  freezing  and breakage  of  the  seal  during  power  outages  in  sub‐freezing  temperatures.    The  seal shall be of carbon and ceramic materials with mating surfaces lapped to a flatness of one  light  band.    The  rotating  ceramic  shall  be  held  in  mating  position  with  the stationary carbon by a stainless steel spring.  

H. The  pump  volute  shall  be  furnished  with mounting  lugs  and  shall  be  bolted  to  the station floor plate, forming a gas‐tight seal. 

 2.08  MOTORS  

A. The pump motors shall be vertical,  solid shaft, NEMA P‐base,  squirrel‐cage  induction type, suitable for 3 Phase, 60 Cycle, 230 Volt electric current.  They shall have Class F insulation  suitable  for  temperatures  up  to  105  degrees  C.    Insulation  temperature shall,  however,  be maintained  below  80  degrees  C.    The motors  shall  have  normal starting torque and low starting current, as specified by NEMA Design B characteristics.  They  shall  be  open  drip‐proof  design  with  forced  air  circulation  by  integral  fan.  Openings  for  ventilation  shall  be  uniformly  spaced  around  the motor  frame.    Leads shall be terminated in a cast connection box and shall be clearly identified. 

 B. The motors shall have a 1.15 service factor.  The service factor shall be reserved for the 

Owner’s  protection.    The  motors  shall  not  be  overloaded  beyond  their  nameplate 

Page 205: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐7 

rating, at the design conditions, nor at any head in the operating range specified under Operating Conditions. 

 C. The motor pump shaft shall be centered, in relation to motor base, within 0.005”.  The 

shaft  runout  shall  not  exceed  0.003”.    The  motor  shaft  shall  equal  or  exceed  the diameter specified under Main Pumps, at all points  from  immediately below the  top bearing  to  the  top of  the  impeller hub.   A bearing cap shall be provided  to hold  the bottom motor  bearing  in  a  fixed  position.    Bearing  housings  shall  be  provided with fittings for lubrication as well as purging old lubricant. 

 D. The motor shall be fitted with heavy lifting eyes, each capable of supporting the entire 

weight of the pump and motor rotating assembly.  2.09  CONTROLS  

A. The  control  equipment  shall  be mounted  in  a  NEMA  Type  1  steel  enclosure  with  a removable  access  cover.    The  circuit  breakers,  starter  reset  buttons  and  control switches  shall  be  operable  without  removing  the  access  cover,  for  deadfront protection. 

 B. A grounding type convenience outlet shall be provided on the side of the cabinet for 

operation  of  120  volt  AC  devices.    Thermal  magnetic  air  circuit  breakers  shall  be provided for branch disconnect service and short circuit protection of all motor control and auxiliary circuits. 

 C. Magnetic  across‐the‐line  starters  with  under‐voltage  release  and  overload  coils  for 

each  phase  shall  be  provided  for  each  pump motor  to  give  positive  protection.    All starters shall be NEMA rated –  IEC type starters shall not be acceptable.   Each single phase  auxiliary  motor  shall  be  equipped  with  an  over‐current  protection  device  in addition to the branch circuit breaker, or shall be impedance protected.   All switches shall be labeled and a coded wiring diagram shall be provided. 

 D. To control the operation of the pumps with variation of liquid level in the wet well, a 

Devar Model 332 Controller shall be installed in the control panel by the pump station manufacturer.    The  liquid  level  shall  be  monitored  by  a  submersible  hydrostatic pressure transducer with stainless steel sensor diaphragm providing a 4‐20 mA signal to the pump controller.  The submersible transducer shall be a Blue Ribbon “Bird Cage” unit.  Three (3) float displacement switches shall be provided to automatically operate the pumps in back‐up mode in the event the digital control system or the submersible level transducer fails.  The back‐up system shall be independent of the digital system.  A minimum of 30 feet of cord shall be provided with each switch.  The cord shall have a  corrosion  resistant  vinyl  jacket  and  shall  be  multi‐stranded  in  order  to  prevent fatigue.    The  displacement  switch  cords  and  the  cable  for  the  submersible  pressure transducer shall enter the wet well through cord grip seals. 

 

Page 206: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐8 

E. An automatic alternator with manual switch shall be provided to change the sequence of  operation  of  the  pumps  after  every  cycle.    The manual  switch  shall  allow  either pump to be selected as a base pump or for automatic operation.  

 F. Provisions shall also be made for the pumps to operate in parallel should the level  in 

the wet well continue to rise above the starting level for the low level “Lead” pump.   

G. A time delay relay shall be provided to cause the second stage pump in each pump set to  start  and  come up  to  speed before  the  lower  stage pump  in  the  set  is  started  in order to prevent starting of a pump with pressure on the seal. 

 2.10  VACUUM PRIMING SYSTEM  

A. A  separate  and  independent  priming  system  shall  be  furnished  for  each  pump, providing complete standby operation.   Each priming system shall  include a separate vacuum  pump.  Vacuum  pumps  shall  have  corrosion  resistant  internal  components.  The vacuum priming system shall be complete with large port vacuum control solenoid valves,  Sonic  Start™  prime  level  sensor,  float  operated  check  valves  to  protect  the vacuum  pumps,  and  all  necessary  shut‐off  valves.    The  float  operated  check  valves shall have a transparent body for visual inspection of the liquid level and shall have an automatic drain check valve.  All hoses and tubing used in the priming system shall be at least 3/8” nominal diameter.  

B. The solenoid valves used in the vacuum priming system shall be of the high flow, direct acting brass body type, with threaded ports, NBR seals and 300 Series stainless steel plunger,  rod,  plate  and  springs.    The minimum orifice  diameter  shall  be  5/16”.    The solenoid  valves  shall  be  UL  Listed,  with  Class  F  coil  rating  and  suitable  voltage  and thermal capacity for the application.  

C. Each  solenoid valve  shall be protected by a vapor  filter,  installed  in  the vacuum  line between  the  valve  and  the  priming  dome.    The  vapor  filter  shall  be  constructed  of corrosion resistant materials and shall have a minimum filtration area of 2.74 square inches and shall be suitable  for operation  from 25”Hg to 100 PSI.   The  filter  shall be readily replaceable without the use of special tools.   

D. Liquid  level  in  the  pump  priming  chamber  shall  be  monitored  by  a  Sonic  Start™ resonant frequency liquid level sensor with piezoelectric drive and sensitive circuits to detect frequency shifts when the sensor is covered by liquid.  This type of system shall be used rather than an electrode system or mechanical means such as a float, to avoid electrical or moving parts inside the chamber, which may accumulate debris, short out, bind or fail.  Only a resonant frequency level sensor with no electrical components or floats in the priming chamber shall be used. 

 E. The priming system shall automatically provide positive lubrication of the mechanical 

seal each time a main pump is primed.  To prevent excessive stoppage due to grease 

Page 207: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐9 

accumulation, no passageway in the priming system through which the pumped liquid must pass shall be smaller than the equivalent of a 2‐1/2” opening. 

 F. The vacuum priming system shall have two field selectable modes of operation.  In the 

“ON DEMAND” mode, the priming system will operate only after a pump is called on to run,  and  if  it  is  not primed.   Once primed,  the pump will  be  allowed  to  run.    In  the “CONSTANT PRIME” mode,  both pumps  are  kept  primed  continuously,  and  ready  to start immediately when called for. 

 2.11  PUMP STATION ACCESSORIES  

A. An  adjustable  displacement  switch  shall  be  provided  to  sense  a  high  water  level condition.    The  switch  shall  hang  into  the  wet  well  and  shall  activate  a  contact  to indicate the high water condition.  

B. A  vapor‐proof  light  fixture with  a  12  V  50 watt  lamp,  red  globe  and  guard  shall  be furnished for outdoor mounting to signal the alarm condition.  

C. A running time meter shall be supplied for each pump to show the number of hours of operation.   The meter shall be enclosed  in a dust and moisture‐proof molded plastic case. The flush mounted dial shall register in hours and tenths of hours up to 99999.9 hours before repeating.  The meter shall be suitable for operation on 120 VAC supply.  

D. A  2  or  3  KVA  insulating  type  transformer  shall  be  provided  to  supply  power  lights, controls and auxiliary devices.   A 2 KVA transformer shall be used where the suction pipes are 4” size.  A 3 KVA transformer shall be used where the suction pipe sizes are 6” or larger.  The transformer shall have 240/460 volt primary, 120/240 volt secondary, Class  F  insulation,  with  temperature  rise  not  to  exceed  115  degrees  C  above  a  40 degree C ambient.  The core and coil shall be protected by a metal housing to prevent damage.  

E. A relay with double pole double throw contacts to monitor and protect against phase loss  (single  phase),  under  voltage  (brown  outs)  and  phase  reversal  (improper sequence)  shall  be provided  in  the  control  system.    The  relay  shall  activate  the high water  alarm  light  in  the  event  of  a  failure.    The  relay  shall  automatically  reset whenever three phase service returns to normal.  

F. Adjustable time delay relays shall be provided to prevent simultaneous starting of the pump motors after power failure.  

G. Glycerin  filled pressure/vacuum gauges with diaphragm protectors  shall  be provided for each pump.  Each gauge shall be furnished with isolation valve and tubing. 

   

Page 208: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐10 

2.12  ENVIRONMENTAL EQUIPMENT  

A. A ventilating blower capable of delivering 250 CFM at 0.1” static water pressure shall be provided  in order  to  remove  the heat generated by  continuous motor operation.  The  ventilating  blower  shall  be  turned  on  and  off  automatically  by  the  preset thermostat.  A heavy extruded aluminum louvered grill with adjustable openings shall cover the discharge of the blower.  A similar grill shall be provided in the other end of the station enclosure for air intake.  

B. A 500 watt electric heater controlled by a preset thermostat shall be furnished.   The heater shall be rigidly mounted in the station to prevent removal. 

 2.13  MAIN PIPING  

A. The  pump  suctions  shall  be  drilled  and  tapped  for  a  125  pound  American  Standard flange for easy connection of the suction risers.  

B. The discharge line from each pump shall be fitted with a clapper‐type check valve and eccentric plug valve.   Size, location and quantity of check valves and plug valves shall be as shown on the Contract Drawing.  

C. The  check  valve  shall  be  of  the  spring‐loaded  type  with  external  lever  arm  and  an easily replaced resilient seat for added assurance against priming leaks.  Check valves shall  have  stainless  steel  shaft  with  replaceable  bronze  shaft  bushings  and  shall  be sealed through the bearings with O‐rings.   To facilitate back flushing of either pump, only  check valves with outside  lever arms will be acceptable.   Ball‐type check valves are specifically unacceptable for this application.  

D. All station piping and fittings shall be capable of passing a 3” solid.  

E. An operating wrench shall be provided for the plug valves.  

F. Protrusions through the floor plate shall be gas‐tight where necessary to effect sealing between the equipment chamber and the wet well.  Bolted and sealed joints shall be provided at the pump volutes or suction pipes  in order to prevent corrosive, noxious fumes  from  entering  the  station.    The  pump  station manufacturer  shall  extend  the suction  and  discharge  connections  below  the  floor  plate  at  the  factory  so  that  field connections can be made without disturbing the gas‐tight seals.  

G. The  manufacturer  of  the  pump  station  shall  provide  a  compression  type  sleeve coupling for  installation  in the common discharge pipe.   Provisions shall be made for securing the coupling to the station floor plate. 

   

Page 209: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐11 

2.14  FLEXIBLE CONDUIT  

To prevent  potential  settling  damage,  at  least  four  feet  of  flexible  conduit  shall  be used  to connect rigid conduit to the lift station. 

 2.15  SPARE PARTS  

A complete replacement pump shaft seal assembly shall be furnished with each pump station.  The spare seal shall be packed in a suitable container and shall  include complete installation instructions.  A spare volute gasket and seal gasket shall be provided. 

  PART 3 – EXECUTION  3.01  FACTORY TESTS  

A.  All  components  of  the  pump  station  shall  be  given  an  operational  test  at  the  pump station manufacturer’s facility to check for excessive vibration or leaks in the piping or seals, and to correct operation of the automatic control and vacuum priming systems and all auxiliary equipment.  Installed pumps shall take suction from a deep wet well, simulating actual service conditions.  The control panel shall undergo both a dry logic test and full operational tests with all systems operating.   

 B.  Factory  test  instrumentation must  include  flow measuring with  indicator;  compound 

suction  gauge;  bourdon  tube  type  discharge  pressure  gauge;  electrical  meters  to measure  amperes,  volts,  kilowatts  and  power  factor;  speed  indicator;  and  a vibrometer capable of measuring both amplitude and frequency. 

 3.02  INSTALLATION AND OPERATING INSTRUCTIONS  

A. Installation  of  the  pump  station  shall  be  done  in  accordance  with  the  written instructions provided by the manufacturer.  

 B. Four  (4)  operation  and  maintenance  manuals  shall  be  furnished  with  each  pump 

station which will include parts lists of components and complete service procedures, and a troubleshooting guide. 

 3.03  START‐UP   

The pump  station manufacturer  shall  provide  complete  start‐up  service.    The pump  station manufacturer  representative  or  factory  service  technician  will  inspect  the  completed installation  to  determine  if  the  installed  equipment  meets  the  purpose  and  intent  of  the specifications.    Tests  shall  demonstrate  that  all  equipment  is  electrically,  mechanically, structurally and otherwise acceptable; the station installation is safe and in optimum working 

Page 210: Standard Water and Sewer Specifications PDF

  WET WELL MOUNTED, SUCTION LIFT SEWAGE PS WITH SERIES PUMPS  11411‐12 

condition; and conforms to the specified operating conditions.   The start‐up technician shall instruct the Owner’s personnel in the proper operation and maintenance procedures. 

 3.04  FINAL INSPECTION  

The  final  inspection will  be performed by City personnel  in  accordance with  the  “Clarksville Gas & Water Lift Station Final Inspection Checklist” included in Appendix F. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 211: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐1 

SECTION 11420  

LOW PRESSURE GRINDER PUMP STATIONS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  GENERAL DESCRIPTION   

A. The  manufacturer  shall  furnish  complete  Grinder  Pump  Station(s),  consisting  of  a grinder  pump,  a  tank  constructed  of  high  density  polyethylene,  NEMA  6P  electrical quick  disconnect,  pump  removal  system,  discharge  piping  assembly  with  shut‐off valve, anti‐siphon valve, check valve, electrical alarm panel, and all necessary internal wiring and controls.  For ease of serviceability, all pump motor/grinder units shall be of like type and horsepower throughout the system.  

 B. Prior  to design of  a  low pressure  sewer  system, discussion  shall  be undertaken with 

the City Engineer to determine the applicability of this type of system.  

C. The City  Engineer  at  his  discretion  shall  request  that  the Developer/Builder  utilize  a low pressure system (LPS)  in whole or  in part when this approach would best  fit  the requirements of the Clarksville Gas & Water Department, eliminate the need for one or more sewer lift stations and best satisfy the needs of customers.  The application of LPS  will  be  used  to  supplement  the  existing  gravity  sewer  systems  in  areas  where gravity  conveyance  sewers  cannot  properly  and  efficiently  meet  customer  needs, including but not limited to the following situations: 1. Portions of subdivisions where terrain features preclude gravity sewers. 2. Locations where unique circumstances dictate LPS. 3. The use of the LPS approach will not be allowed in lieu of off‐site gravity sewer 

needed to serve a larger sewershed/drainage basin.  D. Where  LPS  is  approved,  the  Developer  shall  bear  the  entire  cost  of  the  system 

including the hydraulic model of the affected area.  The Developer and/or Builder must provide  the electrical  connection  for  the grinder pump and  the electrical  installation must  be  inspected  and  approved  by  the  State  electrical  inspector.    Each  pump installation must  be  run  in  the  presence  of  an  inspector  from  the  Clarksville  Gas  & Water Department to demonstrate proper performance prior to final acceptance.  

E. Where  a  property  owner  wishes  to  connect  a  private  grinder  pump(s)  to  existing gravity system or force main adjacent to the property, the property owner shall install the pump at his own expense subject to obtaining all required permits and inspections.  The  property  owner  is  responsible  for  the  electrical  connection,  all  excavations, provision  and  installation  of  tap  material,  backfilling  and  payment  of  applicable connection  fees  per  Clarksville  Code.    In  addition,  if  the  pump  discharges  into  an 

Page 212: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐2 

existing  force  main,  the  City  Engineer  may  request  that  a  hydraulic  analysis  be performed to assure proper performance.  The tap shall be made by the City provided the main has been accepted by the City for operation and maintenance. 

 F. After inspection, testing and approval by all parties of the new service installation, the 

property  owner  shall  bear  the  responsibility  for  operation,  maintenance  and replacement (including grinder pump assembly) up to the point of connection to the City’s main. 

 G. Connection fees shall be charged as per the Clarksville Code. 

 1.02  SHOP DRAWINGS   

After receipt of notice to proceed, the manufacturer shall furnish a minimum of six (6) sets of shop  drawings  detailing  the  equipment  to  be  furnished  including  dimensional  data  and materials of construction.   The Engineer shall promptly  review this data, and return  two  (2) copies as accepted, or with requested modifications.  Upon the Engineer's acceptance of the shop drawings and  the manufacturer's  receipt of notice  to proceed,  the manufacturer  shall begin fabrication of the equipment.  

 1.03  MANUFACTURER  

A. Grinder pump stations, complete with all appurtenances, form an integral system, and as such, shall be supplied by one grinder pump station manufacturer.  The Contractor shall  be  responsible  for  the  satisfactory  operation  of  the  entire  system.    The equipment  specified  shall be a product of a  company experienced  in  the design and manufacture of grinder pumps for specific use  in  low pressure sewage systems.   The company shall submit detailed installation and user instructions for its product, submit evidence  of  an  established  service  program  including  complete  parts  and  service manuals, and be responsible  for maintaining a continuing  inventory of grinder pump replacement parts.   The manufacturer shall provide a reference and contact list from ten of  its  largest contiguous grinder pump  installations of  the type of grinder pumps described within this specification.  

 B. The manufacturer of the grinder pump station shall be Environment One Corporation, 

or approved equal.  

C. The  specifications  contained  herein  are  patterned  around  pumps  manufactured  by Environmental  One  Corporation.    Products  manufactured  by  Environmental  One Corporation  shall  set  the minimum  standard  of  quality.    Some modifications  to  the specifications  have  been  made  to  allow  other  manufacturers  to  be  considered, provided  their  equipment  is  judged  equal  by  the  Owner  and  they  are  listed  as approved in the original Contract Documents or by Addendum. 

 

Page 213: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐3 

1.04  OPERATING CONDITIONS  

The pump(s) shall be capable of delivering 15 GPM against a total dynamic head of 0 feet (0 PSIG)  and  9 GPM against  a  total  dynamic  head  of  138  feet  (60  PSIG)  at  a maximum of  8.0 amps.  The pump(s) must also be capable of operating at negative total dynamic head without overloading  the motor(s).   Under no  conditions  shall  in‐line piping or  valving be  allowed  to create a false apparent head.  

 1.05  WARRANTY  

The grinder pump manufacturer shall provide a part(s) and  labor warranty on  the complete station,  accessories  and  control  panel  for  a  period  of  twelve  (12) months  from  the  date  of acceptance.  Any manufacturing defects found during the warranty period will be reported to the manufacturer by the City.  

 1.06  WARRANTY PERFORMANCE CERTIFICATION  

As  a  pre‐construction  requirement,  the  Contractor  shall  provide  a  Warranty  Performance Certification  statement  executed  by  the most  senior  executive  officer  of  the  grinder  pump manufacturer, which certifies a minimum of a twelve (12) month warranty.  They must further detail  any  exclusions  from  the  warranty  or  additional  cost  items  required  to  maintain  the equipment  in  warrantable  condition,  including  all  associated  labor  and  shipping  fees,  and certify that the manufacturer will bear all costs to correct any original equipment deficiency for  the effective period of  the warranty.   All preventive maintenance  requirements  shall be included  in this  form as exclusions.   These requirements  include, but are not  limited to, un‐jamming  of  grinder  mechanism,  unplugging  of  lines,  periodic  motor  maintenance,  and periodic cleaning of liquid level controls.  

  PART 2 ‐ PRODUCTS   2.01  PUMP  

A. The  pump  shall  be  a  custom  designed,  integral,  vertical  rotor,  motor  driven,  solids handling pump of the progressing cavity type with a single mechanical seal.  The rotor shall be constructed of stainless steel. Plating on the rotor will not be acceptable due to  its  tendency  to  delaminate.    The  stator  shall  be  of  a  specifically  compounded ethylene propylene  synthetic elastomer.    The material  shall be  suitable  for domestic wastewater  service.  Its  physical  properties  shall  include  high  tear  and  abrasion resistance,  grease  resistance,  water  and  detergent  resistance,  temperature  stability, excellent aging properties, and outstanding wear resistance.  Buna‐N is not acceptable as a stator material because it does not exhibit the properties as outlined above and as required for wastewater service. 

 B. Requirements for grinder pump (LPS) installation: 

Page 214: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐4 

1. Proposed  tank  location  should  be  no  more  than  25  feet  from  control  panel unless permitted otherwise by the City. 

2. Service line valves/valve box is to be placed within property line, near right of way. 

3. Minimum amount of bends in all service line installations. 4. House connection to tank subject to approval by the City of Clarksville Building 

and Codes Department. 5. Service  line  and  tank  installation must  be  inspected  by  the  City  of  Clarksville 

Gas & Water Department. 6. The tank shall be located to preclude entry of surface water through the lid of 

the tank under all circumstances.  The grade must slope away from the station.  Covering or burying the top of the station is prohibited. 

2.02  GRINDER  

The  grinder  shall  be  placed  immediately  below  the  pumping  elements  and  shall  be  direct‐driven by a single, one‐piece, stainless steel motor shaft.  The grinder impeller assembly shall be securely fastened to the pump motor shaft.  The grinder will be of the rotating type with a stamped, stainless steel shredder ring assembly spaced  in accurate, close annular alignment with the driven impeller assembly, which shall carry two hardened, 400 series stainless steel cutter bars.  This assembly shall be dynamically balanced and shall operate without vibration over the entire range of specified operating pressures.  The grinder shall be constructed so as to  eliminate  clogging  and  jamming  under  all  normal  operating  conditions  including  pump starting.  Sufficient vortex action shall be created to scour the tank free of deposits or sludge banks  which  would  impair  the  operation  of  the  pump.    These  requirements  shall  be accomplished by the following, in conjunction with the pump:  

 A. The  grinder  shall  be positioned  in  such  a way  that  solids  are  fed  in  an upward  flow 

direction.   B. The maximum  flow  rate  through  the cutting mechanism must not exceed 4  feet per 

second.    This  is  a  critical  design  element  to  prevent  jamming  and  as  such must  be adhered to.  

 C. The inlet shroud shall have a diameter of no less than 5 inches.  Inlet shrouds that are 

less  than 5  inches  in diameter will not be accepted due to their  inability  to maintain the  specified  4  feet  per  second  maximum  inlet  velocity  which  by  design  prevents unnecessary jamming of the cutter mechanism and eliminates blinding of the pump by large objects blocking the inlet shroud.  

 D. The impeller mechanism must rotate at a nominal speed of no greater than 1800 rpm.   E. The grinder shall be capable of reducing all components  in normal domestic sewage, 

including a reasonable amount of "foreign objects," such as paper, wood, plastic, glass, rubber  and  the  like,  to  finely  divided  particles  that  will  pass  freely  through  the passages of the pump and the 1‐1/4" diameter discharge piping.  

Page 215: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐5 

 2.03  ELECTRIC MOTOR  

As a maximum, the motor shall be a 1 HP, 1725 RPM, 240 Volt 60 Hertz, 1 Phase, capacitor start,  ball  bearing,  air‐cooled  induction  type  with  a  low  starting  current  not  to  exceed  30 amperes  and  high  starting  torque  of  8.4  foot  pounds.    Inherent  protection  against  running overloads or  locked rotor conditions for the pump motor shall be provided by the use of an automatic‐reset, integral thermal overload protector incorporated into the motor.  This motor protector  combination  shall  have  been  specifically  investigated  and  listed  by  Underwriters Laboratories,  Inc.,  for  the  application.    Non‐capacitor  start  motors  or  permanent  split capacitor  motors  will  not  be  accepted  because  of  their  reduced  starting  torque  and consequent  diminished  grinding  capability.    To  reduce  the  potential  of  environmental concerns, the expense of handling and disposing of oil, and the associated maintenance costs, oil‐filled motors will not be accepted.  

 2.04  MECHANICAL SEAL  

The  pump  shall  be  provided with  a mechanical  shaft  seal  to  prevent  leakage  between  the motor and pump.   The seal shall have a stationary ceramic seat and carbon rotating surface with faces precision lapped and held in position by a stainless steel spring.  

 2.05  TANK AND INTEGRAL ACCESSWAY   

A. Simplex Unit: The tank shall be made of high density polyethylene, with a melt index of 2.0 grams/10 minutes or lower to assure high environmental stress cracking resistance.  Corrugated sections  are  to  be made  of  a  double  wall  construction with  the  internal  wall  being generally smooth to promote scouring.  Corrugations of the outside wall are to be of a minimum amplitude of 1‐½” to provide necessary transverse stiffness.  Any incidental sections of a single wall construction are to be a minimum 0.250 inch thick.  All seams created  during  tank  construction  are  to  be  thermally welded  and  factory  tested  for leak  tightness.    Tank  wall  and  bottom  must  withstand  the  pressure  exerted  by saturated soil loading at maximum burial depth.  All station components must function normally when exposed to 150 percent of the maximum external soil and hydrostatic pressure.  

 B. Duplex Unit: 

The tank shall be made of rotationally molded high density polyethylene, with a melt index of 2.0 grams/10 minutes or  lower to assure high environmental stress cracking resistance.   The tank shall have a nominal  thickness of ½”.   All seams created during tank  construction  are  to  be  thermally  welded  and  factory  tested  for  leak  tightness.  Tank wall and bottom must withstand the pressure exerted by saturated soil loading at maximum burial depth.  All station components must function normally when exposed to 150 percent of the maximum external soil and hydrostatic pressure. 

 

Page 216: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐6 

C. The tank shall be furnished with one EPDM grommet fitting to accept a 4.50” OD DWV or Schedule 40 pipe.  Tank capacities shall be as shown on the Contract Drawings.  

D. The accessway shall be an  integral extension of  the wet well assembly and  include a lockable  cover  assembly  providing  low  profile  mounting  and  watertight  capability.  Accessway design and construction shall enable field adjustment of the station height by adding either 2‐inch or 4‐inch vertical extensions without the use of any adhesives or sealants requiring cure time before installation can be completed.  

E. The  station  shall  have  all  necessary  penetrations molded  in  and  factory  sealed.    To ensure a leak free installation no field penetrations shall be acceptable.  

F. All  discharge  piping  shall  be  constructed  of  304  Series  Stainless  Steel  and  terminate outside the accessway bulkhead with a stainless steel, 1‐¼ inch female NPT fitting.  The discharge piping shall  include a stainless steel ball valve  rated  for 200 psi WOG; PVC ball  valves will not be accepted.   The bulkhead penetration shall be  factory  installed and warranted by the manufacturer to be watertight.  

G. The accessway shall include a single NEMA 6P electrical quick disconnect (EQD) for all power and control functions, factory installed with accessway penetrations warranted by the manufacturer to be watertight.  Plug‐type connections of the power cable onto the pump housing will not be acceptable due to the potential for  leaks and electrical shorts.   The accessway shall also  include a 2‐inch PVC vent  to prevent sewage gases from accumulating in the tank. 

 2.06  CHECK VALVE  

A. The  pump  discharge  shall  be  equipped  with  a  factory  installed,  gravity  operated, flapper‐type  integral  check  valve  built  into  the  stainless  steel  discharge  piping.    The check  valve will  provide  a  full‐ported  passageway when open,  and  shall  introduce  a friction loss of less than 6 inches of water at maximum rated flow.  Moving parts will be made of  a  300  series  stainless  steel  and  fabric  reinforced  synthetic  elastomer  to ensure corrosion resistance, dimensional stability, and fatigue strength.  A nonmetallic hinge shall be an integral part of the flapper assembly providing a maximum degree of freedom to assure seating even at a very low back‐pressure.  The valve body shall be an  injection  molded  part  made  of  glass  filled  PVC.    Ball  type  check  valves  are unacceptable due to their limited sealing capacity in slurry applications.  

 B. Each grinder pump installation shall also include one separate check valve of the type 

detailed above for installation in the 1‐1/4" service lateral between the grinder pump station and the sewer main, preferably next to the curb stop.  

 

Page 217: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐7 

2.07  ANTI‐SIPHON VALVE  

A. The  pump  discharge  shall  be  equipped  with  a  factory‐installed,  gravity  operated, flapper‐type integral anti‐siphon valve built into the stainless steel discharge piping.  

 B. Moving parts will be made of 300 series stainless steel and fabric‐reinforced synthetic 

elastomer  to ensure corrosion resistance, dimensional  stability, and  fatigue strength.  A  nonmetallic  hinge  shall  be  an  integral  part  of  the  flapper  assembly,  providing  a maximum degree of freedom to ensure proper operation even at a very low pressure.  The valve body shall be injection‐molded from a glass‐filled thermoplastic resin.  Holes or ports  in  the discharge piping  are not  acceptable  anti‐siphon devices,  due  to  their tendency to clog from the solids in the slurry being pumped.  

 2.08  CORE UNIT  

The  Grinder  Pump  Station  shall  have  an  easily  removable  core  assembly  consisting  of  the pump, motor, grinder, all motor controls, check valve, anti‐siphon valve, EQD and wiring.  The watertight  integrity  of  the  core  unit  shall  be  established  by  100  percent  factory  test  at  a minimum of 5 PSIG.  

 2.09  CONTROLS  

A. All necessary controls,  including motor and  level controls, shall be  located  in the top housing  of  the  core  unit.    The  top  housing  will  be  attached  with  stainless  steel fasteners.  Non‐fouling wastewater level controls for controlling pump operation shall be  accomplished  by  monitoring  the  pressure  changes  in  an  integral  air  column connected to a pressure switch.  The level detection device shall have no moving parts in direct contact with the wastewater.  High‐level sensing will be accomplished in the manner detailed above by a separate air‐bell sensor and pressure switch of the same type.  Closure of the high‐level sensing device will energize an alarm circuit as well as a redundant  pump‐on  circuit.    For  increased  reliability,  pump ON/OFF  and  High  Level Alarm functions shall not be controlled by the same switch.  Float switches of any kind, including  float  trees,  will  not  be  accepted  due  to  the  periodic  need  to  maintain (rinsing, cleaning) such devices.  

 B. To  assure  reliable  operation  of  the  differential  pressure  switches  each  core  shall  be 

equipped  with  a  pressure  equalization  chamber.    The  equalization  chamber  shall continuously calibrate the level sensing pressure switches to fluctuations in barometric pressure and prevent fluid from entering the control compartment during high water level  conditions.    The  equalization  chamber  shall  be  constructed  from  EPDM,  High Impact Polystyrene and stainless steel and measure 12”  in diameter by 6” high.   The chamber shall be assembled by the core manufacturer and factory tested at the point of assembly to verify proper operation.   The grinder pump will be furnished with a 6 conductor,  14  gauge,  type  SJOW  cable,  pre‐wired  and  watertight  to  meet  UL requirements with a FACTORY INSTALLED NEMA 6P EQD half attached to it.  

Page 218: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐8 

 2.10  ALARM PANEL  

A. Each Grinder Pump Station shall  include a NEMA 4X, Alarm Panel suitable for wall or pole mounting.  The NEMA 4X enclosure shall be manufactured of corrosion resistant thermoplastic and be furnished with a hinged cover and padlock.  

 B. For each core, the panel shall contain one (1) ‐ 15 amp, double pole circuit breaker for 

the power circuit and one (1) 15 amp single pole circuit breaker for the alarm circuit.  The Alarm Panel shall include an audio and visual alarm, push‐to‐run switch, and high level  (redundant) pump starting control.   The visual alarm  lamp shall be  inside a  red fluted lens mounted to the top of the enclosure in such a manner as to maintain NEMA 4X  rating.    For duplex units,  in  addition  to  the  above,  two high  level  indicator  lights shall be mounted behind the access cover. 1. When liquid level in the sewage wet well rises above the alarm level, visual and 

audio alarms will be activated.  The contacts on the alarm pressure switch will close.  The redundant pump starting system will be energized. 

2. The audio alarm may be silenced by means of the externally mounted, push‐to‐silence button. 

3. Visual alarm remains  illuminated until  the sewage  level  in  the wet well drops below the “off” setting of the alarm pressure switch. 

 C. The  control  panel  shall  be  equipped  with  an  outside  quick  disconnect  to  facilitate 

usage of a generator during a power outage.  2.11  SERVICEABILITY  

The grinder pump core unit shall be furnished with polypropylene lifting harness connected to the  pump  body  to  facilitate  easy  removal  when  necessary.    All  mechanical  and  electrical connections must provide easy disconnect accessibility for core unit removal and installation.  All motor control components shall be mounted on a readily replaceable bracket for ease of field service.  

 2.12  SAFETY 

 The Grinder Pump Station shall be free from objectionable noise, odor, or health hazards, in its  capability  to  perform  as  specified  in  either  individual  or  low  pressure  sewer  system applications.  

  

Page 219: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐9 

PART 3 ‐ EXECUTION  3.01  FACTORY TEST  

Each grinder pump shall be submerged and operated for 5 minutes (minimum).    Included in this procedure will  be  the  testing of  all  ancillary  components  such as  the anti‐siphon valve, check  valve,  level  sensors  and  each  unit's  dedicated  controls.    All  factory  tests  shall incorporate  each  of  the  above  listed  items.    Certified  test  results  shall  be  available  upon request showing the operation of each grinder pump at two (2) different points on its curve, with the maximum discharge pressure no less than 60 psi.  The Engineer reserves the right to inspect  such  testing  procedures  with  representatives  of  the  City,  at  the  grinder  pump manufacturer’s facility.  

 3.02  INSTALLATION  

A. Earth excavation and backfill  are  specified under Sections 02210 and 02221, but are also  to  be  done  as  a  part  of  the  work  under  this  section,  including  any  necessary sheeting and bracing.   The Contractor shall be responsible for handling ground water to provide a firm, dry subgrade for the structure, and shall guard against flotation or other damage resulting from general water or flooding. 

 B. The Grinder Pump Stations  shall  not be  set  into  the excavation  until  the  installation 

procedures and excavation have been approved by the Engineer.  

C. Remove  packing material.    Users  instructions MUST  be  given  to  the  City.  Hardware supplied  with  the  unit,  if  required,  will  be  used  at  installation.    The  basin  will  be supplied  with  a  standard  4"  inlet  grommet  (4.50"  OD)  for  connecting  the  incoming sewer  line.   Appropriate  inlet piping must be used.    The basin may not be dropped, rolled or laid on its side for any reason.  Installation shall be accomplished so that 1" to 4" of accessway, below the bottom of the  lid, extends above the finished grade  line.  The finished grade shall slope away from the unit.  The diameter of the excavated hole must be large enough to allow for the concrete anchor.  A 6‐inch (minimum) layer of naturally rounded aggregate, clean and free flowing, with particle size of not less than 1/8" or more than 3/4" shall be used as bedding material under each unit.  A concrete anti‐flotation  collar,  as  detailed  on  the  drawings,  and  sized  according  to  the manufacturer's  instructions,  shall  be  required  and  shall  be  pre‐cast  to  the  grinder pump or poured  in place.   Each Grinder Pump Station with  its pre‐cast anti‐flotation collar  shall  have  a  minimum  of  three  (3)  lifting  eyes  for  loading  and  unloading purposes.    If  the concrete  is poured  in place, the unit shall be  leveled and filled with water,  to  the  bottom  of  the  inlet,  to  help  prevent  the  unit  from  shifting  while  the concrete is being poured.  The concrete must be manually vibrated to ensure there are no voids.  If it is necessary to pour the concrete to a level higher than the inlet piping, an  8"  sleeve  is  required  over  the  inlet  prior  to  the  concrete  being  poured.    The Contractor  will  provide  and  install  a  4‐foot  piece  of  4‐inch  SCH  40  PVC  pipe  with 

Page 220: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐10 

watertight cap, to stub‐out the  inlet for the property owners'  installation Contractor, as depicted on the Contract Drawings.  

D. When the grinder pump is being installed at the property with an existing septic tank, the Contractor shall  install two (2) knife valves at the point of intercepting the 4‐inch diameter  service  line  between  the  building  and  the  septic  tank.    The  existing  septic tank shall  remain  in an operable condition  in case of pump failure.   Valve  leading  to pump shall be tagged accordingly (open/closed).  

E. The electrical  enclosure  shall  be  furnished,  installed  and wired  to  the Grinder  Pump Station by the Contractor.  An alarm device is required on every installation; there shall be NO EXCEPTIONS.    It will be the responsibility of the Contractor to coordinate with the  individual  property  owner(s)  to  determine  the  optimum  location  for  the  Alarm Panel.  The Contractor shall mount the alarm device in a conspicuous location, as per national  and  local  codes.    The  Alarm  Panel  will  be  connected  to  the  Grinder  Pump Station  by  a  length  of  six  (6)  conductor  12  gauge  type  TC  cable,  in  conduit  where exposed.    The  power  and  alarm  circuits  must  be  on  separate  power  circuits.    The grinder pump stations will be provided with a minimum of 32 feet of electrical supply cable (25 feet of useable electrical supply cable outside the station) to connect to the alarm panel.  This cable shall be supplied with a factory installed EQD half to connect to the mating EQD half on the core.   

F. Minimum electrical wiring requirements: All LPS electrical systems are to be single phase, 240V AC, 30A, four‐wire weatherproof disconnect  service.    The  external  NEMA  3  electrical  disconnect,  installed within  five feet (5’) of the present location of the sewer line leaving the house to the septic tank, can  be  fused,  non  fused  or  breaker  type.    The  height  of  the  disconnect  shall  be  a minimum of  four  feet  (4’)  from the grade.   The wiring  from the main breaker  to the disconnect  shall  be  four‐wire  (two hot,  one  insulated neutral  and one ground wire).  The  installation of  these  conductors  shall  be  in  conduit where exposed.    The permit can  be  obtained  at  the  Clarksville  Department  of  Electricity,  2001  Wilma  Rudolph Boulevard.  All work shall be inspected by the State Electrical Inspector.  

3.03  BACKFILL REQUIREMENTS  

A. Proper  backfill  is  essential  to  the  long‐term  reliability  of  any underground  structure.  Several methods  of  backfill  are  available  to  produce  favorable  results with  different native  soil  conditions.    The  most  highly  recommended  method  of  backfilling  is  to surround the unit to grade using Class I or Class II backfill material as defined in ASTM 2321.  Class 1A and Class 1B are recommended where frost heave is a concern, Class 1B is a better choice when the native soil is sand or if a high, fluctuating water table is expected.   Class 1, angular crushed stone offers an added benefit  in  that  it does not need to be compacted.   

Page 221: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐11 

B. Class II, naturally rounded stone, may require more compactive effort, or tamping, to achieve the proper density.    If  the native soil condition consists of clean compactible soil, with  less  than 12 percent  fines,  free of  ice,  rocks,  roots and organic material,  it may be an acceptable backfill.  Soil must be compacted in lifts not to exceed one foot to reach a final Proctor Density of between 85 percent and 90 percent.   Heavy, non‐compactible  clays  and  silts  are  not  suitable  backfill  for  this  or  any  underground structure such as inlet or discharge lines.   

C. Another option is the use of a flowable fill (i.e., low slump concrete).  This is acceptable when installing grinder pump stations in augured holes where tight clearances make it difficult to assure proper backfilling and compaction with dry materials.  Flowable fills should not be dropped more than four feet from the discharge to the bottom of the hole to avoid separation of the constituent materials.   

D. Backfill  of  clean  native  earth,  free  of  rocks,  roots,  and  foreign  objects  shall  be thoroughly compacted in  lifts not exceeding 12" to a final Proctor Density of not  less than 85 percent.  Improper backfilling may result in damaged accessways.  The grinder pump station shall be installed at a minimum depth of 30 inches below finished grade to the top of the 1‐1/4" discharge line to assure frost protection.  The finish grade line shall  be 1"  to 4" below  the bottom of  the  lid;  final  grade  shall  slope away  from  the grinder pump station.   

E. All  restoration  will  be  the  responsibility  of  the  Contractor.    The  properties  shall  be restored  to  their original  condition  in all  respects,  including, but not  limited  to,  curb and  sidewalk  replacement,  landscaping,  loaming and  seeding,  and  restoration of  the traveled ways, as directed by the Engineer.  

 3.04  START‐UP AND FIELD TESTING  

A. The manufacturer  shall provide  the  services of qualified  factory‐trained  technician(s) who  shall  inspect  the  placement  and  wiring  of  each  station,  perform  field  tests  as specified herein, and instruct the City’s personnel in the operation and maintenance of the  equipment  before  the  stations  are  accepted  by  the  City.    All  equipment  and materials  necessary  to  perform  testing  shall  be  the  responsibility  of  the  installing Contractor.  This will include, as a minimum, a portable generator (if temporary power is  required)  and  water  in  each  basin.    The  services  of  a  trained  factory‐authorized technician shall be provided at a rate of one (1) four (4) day week for each 100 grinder pump stations supplied.  Each day shall be ten (10) person hours in duration.   

B. Upon  completion  of  the  installation,  the  authorized  factory  technicians will  perform the following test on each station:  1. Make certain the discharge shut‐off valve is fully open.  This valve must not be 

closed  when  the  pump  is  operating.    In  some  installations,  there  may  be  a valve(s) at the street main that must also be open.  

2. Turn ON the alarm power circuit.  

Page 222: Standard Water and Sewer Specifications PDF

  LOW PRESSURE GRINDER PUMP STATIONS  11420‐12 

3. Fill  the  tank with water  to  a depth  sufficient  to  verify  the high  level  alarm  is operating. Shut off water.  

4. Close the pump power circuit breaker.  The pump should immediately turn ON. Within one (1) minute the alarm light will turn OFF.   Within three (3) minutes the pump will turn OFF.  

 C. Upon  completion  of  the  start‐up  and  testing,  the manufacturer  shall  submit  to  the 

Owner  the  start‐up authorization  form describing  the  results  of  the  tests performed for  each Grinder  Pump  Station.    Final  acceptance  of  the  system will  not  occur  until authorization  forms  have  been  received  for  each  pump  station  installed  and  all installation deficiencies have been corrected.  

 3.05  OPERATION AND MAINTENANCE   

The manufacturer shall supply two (2) copies of Operation and Maintenance Manuals to the  Owner. 

 END OF SECTION 

TABLE OF CONTENTS 

Page 223: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐1 

SECTION 13310  

SEWAGE SYSTEM FIELD INSTRUMENTATION  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  SECTION INCLUDES  

A. In‐Line Flow Meters.  

B. Strap‐On Flow Meters.  

C. Telemetry (Large Stations).  

D. Wide Area Wireless Telemetry (Small Stations).  1.02  REFERENCES  

A. I.S.A. – Instrument Society of America  

B. Hydraulic Institute  

C. ANSI – American National Standards Institute  

D. NEMA – National Electrical Manufacturers Association  

E. UL – Underwriters Laboratories  

F. NEC – National Electric Code  1.03  PERFORMANCE – GENERAL REQUIREMENTS  

A. The  instrumentation  equipment  shall  be  furnished  by  a  manufacturer  regularly engaged  in  the manufacture  of  process  instrumentation  equipment  and  systems  for water  and  wastewater  treatment  facilities.    The  instrument  manufacturer  shall produce  detailed  drawings  for  the  complete  coordination  and  installation  of  the various  system  components;  shall  provide  the  services  of  a  qualified  engineer  to supervise  the  installation;  and  shall  test  and make  any  adjustments  required,  at  no additional  cost  to  the  Owner,  to  the  extent  that  the  system  initially  functions  as intended by this specification to the satisfaction of the Owner.  

B. Owner’s  Representative  will  check  after  the  Contractor  certifies  that  all  the instruments  are  installed  and  are  operating  as  per  intended  specification.    The 

Page 224: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐2 

Contractor shall be  required  to correct, at no extra cost  to  the Owner, all deviations and/or deficiency from the intended use of the instruments individually as well as the system  in  its  entirety, which  the Owner’s  Representative may  find  during  the  detail checkup of the system(s). 

 C. Equipment  shall  be  located  and  installed  so  that  it  will  be  readily  accessible  for 

operation  and  maintenance.    The  Contractor  shall  examine  the  architectural, structural,  mechanical,  electrical,  and  shop  drawings  for  the  various  pieces  of equipment in order to determine the exact routing and final terminations for conduits and  signal  lines.    Instrumentation  work  shall  be  carefully  coordinated  between  the various  trades  in order  to  secure  the best arrangement of  the work as a whole.   No changes in the work shall be made without written acceptance of the Owner.  

D. The  Instrument  Contractor  shall  submit  evidences  of  his  prior  experience,  technical skill,  capacity  to  handle  a  project  of  the  volume  and  reference  of  other  clients  for whom he has performed similar installations.  

E. Services by Manufacturer and Guarantee: 1. Certification sheets shall be prepared by the Instrumentation Manufacturer to 

guarantee  that each component has been calibrated and commissioned prior to  start‐up.    Certification  sheets  shall  be  signed  and  dated  by  the Instrumentation  Manufacturer.    All  instruments  shall  be  calibrated  by  an instrument traceable to a primary standard.  All instruments shall be calibrated to within  the accuracy  stated by  the manufacturer.   Each  instrument shall be checked  for  zero  and  full  span  and  in  addition,  a  check  shall  be  made  of  a minimum of 5 points between 10 and 90 percent of  the actual  span  for each analog instrument.  The certification sheets shall show “as found” and “as left” readings. 

2. After all  tests  and adjustments have been made,  the manufacturer  shall  fully instruct the Owner’s Representative in all details of operation and maintenance of equipment installed under his work. 

3. The Contractor and his surety shall guarantee in writing for a period of one year from  the  date  of  final  acceptance  that  all  materials,  equipment  and  labor furnished by him are free from defects.  The Contractor shall further guarantee that if any piece is found to be defective within the guarantee period because of  faulty manufacturing,  faulty  installation or workmanship,  in  the opinion of the  Owner’s  Representative,  the  Contractor  will  replace  and  install  such material or equipment without any additional expense to the Owner. 

 F. Installation, Calibration, Commissioning and Start‐Up Assistance: 

1. Install, calibrate, commission and assist in the start‐up of instrumentation and controls  including  those  furnished  with  purchased  equipment  in  accordance with  this  specification  section,  the  applicable  design  drawings  and  other Contract Documents. 

Page 225: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐3 

2. Furnish and install all necessary instrumentation materials and piping required to perform the work. 

 1.04  GENERAL INSTRUMENT CONSTRUCTION  

A. Attachments and Supports: 1. All  instrumentation  and  electrical  equipment  shall  be  securely  supported.    It 

shall be the responsibility of the Contractor to provide adequate support for all equipment he installs.  Methods of support shall be subject to the approval of the Owner. 

2. All  fastenings,  supports,  hangers,  clamps,  and  anchors  shall  be  of  the  type made for the specific purpose for which they are to be used.   Toggle bolts or machine  bolt  fastenings  shall  be  used  for  hollow  tile,  terra‐cotta,  or  lath construction.  Machine screws shall be used for structural steel fastening.  Lead expansion shield and machine screws shall be used for solid masonry fastening.  Lag  screws or bolts  shall be used  for wood  fastening.   All  conduit and  tubing shall be rigidly and firmly installed to prevent swaying, vibration or sagging by malleable  or  wrought  steel  hangers  of  standard  design,  pipe  clamps,  or fabricated  steel  supports of approved design.   Hangers  for horizontal  conduit runs  shall  be  adjustable  clevis  type.    Perforated  strap  iron  hangers  are  not permitted. 

3. All exterior fastening devices shall be Series 304 stainless steel. 4. Panels and other equipment  that are  located on subgrade walls  in unfinished 

areas or in damp locations, shall be mounted on square aluminum channel.  

B. Identification Nameplates: 1. All  sensors,  transmitters,  terminal  and  junction  boxes,  and  similar  or  related 

items shall be  identified by name,  function, and/or control.   Nameplates shall be at least 1” x 3” with characters not less than ¼ inch.  They shall be made up of 2 laminated white plastic sheets bonded with a middle sheet of black plastic and characters engraved  in one white sheet to the depth of the black plastic.  Nameplates shall be attached with sheet metal screws or bolts and nuts. 

2. Plastic tape embossed nameplates will not be acceptable.  

C. Instructions: After all tests and adjustments have been made, the Contractor shall fully instruct the representatives of the Owner in all details of operation and maintenance of equipment installed under his work. 

 D. Materials: 

1. All  material  shall  be  new,  free  from  defects,  and  of  the  quality  specified  or shown.  Each type of material shall be of the same manufacture throughout the work.  All material shall be the product of established, reputable manufacturers normally engaged in the production of the particular item being furnished. 

Page 226: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐4 

2. Care shall be exercised in the installation of all equipment to avoid damage or disfiguration  of  any  kind.    All  equipment  shall  be  protected  from  dust  and moisture  prior  to  and  after  installation.    The  panels  and  consoles  shall  be covered  with  a  heavy  polyethylene  plastic  sheet  or  laminated  kraft  paper having a moisture barrier during all stages of construction. 

3. Equipment which  is stored  in unheated or open areas on the  job site shall be provided  with  thermostatically  controlled  heating  units  of  sufficient  size  to keep the temperature of the equipment above the dew point. 

4. Failure of the Contractor to protect the equipment as outlined herein shall be grounds for rejection of the equipment. 

 E. Indicating Scales: 

All instrument components furnished under this Contract requiring indicating scales or meters  shall  be  furnished  with  the  appropriate  ranges  and  engineering  units.  Indicating scale reading 0‐100 percent will not be acceptable. 

 1.05  TESTING, CALIBRATION AND COMMISSIONING  

As preparation for the calibration and commissioning of the instrumentation, the Contractor shall: 

 A. Visually  inspect electrical devices and connections for compliance with specifications, 

drawings and manufacturer’s recommended installation practice.  B. Remove  all  shipping  stops  and  install  components  such  as  charts,  etc.,  which  have 

been supplied separately but are integral parts of the instruments.  C. Operationally  check  all  instruments,  including  those  provided  with  equipment  and 

marked  on  the  “Piping  and  Instrument  Diagrams”.    After,  or  during  checking,  each instrument shall be calibrated and commissioned. 

 D. Furnish and report forms recording the calibration of all devices and settings of all final 

adjustments.  E. Check calibration of all instruments with respect to zero, span and linearity.  Calibrate 

instruments  individually.    Attach  a  calibration  sticker  to  each  item  after  calibration.  Furnish a signed calibration report for each instrument. 1. If,  during  calibration  procedures,  any  reason  is  discovered  to  question  the 

conformance  of  any  device  or  installation  with  applicable  codes  and regulations,  the Owner  shall  be  notified  so  that  corrective measures may  be taken. 

2. When doubt exists as to the correct method of calibrating an  instrument, the manufacturer’s printed recommendations shall be used. 

 

Page 227: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐5 

1.06  INSTRUCTION MANUALS  

The  Contractor  shall  provide  the  Owner  with  three  (3)  complete  sets  of  manufacturer’s operating  and  maintenance  instructions  and  recommended  spare  parts  lists  for  all instrumentation equipment furnished. 

  PART 2 – PRODUCTS  2.01 IN‐LINE MAGNETIC FLOW METERS  

A. In‐line flow meters shall be  installed on all new pump stations with rated pump flow equal to or greater than 400 gpm.  

B. Size as shown on Contract Drawings.  

C. Flow Meter Characteristics: 1. Accuracy:  ± 0.25% of rate > 2.0 fps; ± 0.50% for < 2.0 fps. 2. Flow range:  0 – 2 fps minimum to at least 30 fps maximum. 3. Environmental  Protection:    NEMA  6  and  IP68  indefinitely  submersible  to  30 

feet water column. 4. Grounding electrode on each sensor. 5. Field replaceable sensors. 6. Electrodes:  AISI 361 stainless steel. 7. 120 V, 60 Hz transmitter supply. 8. ANSI 150 RF flanged connections. 

 D. Transmitter: 

1. Wall‐mounted UV resistant fiberglass with lockable stainless steel latches. 2. Cable entry:  4 non‐threaded holes for ½” conduit. 3. Ambient temperature range:  ‐ 4° to 158°F. 4. Analog outputs:  two (2), 4‐20 mA outputs from separate terminals. 5. Pulsed outputs:  one (1) externally powered, 2‐wire scaled output. 6. Communication output:  HART Protocol, RS232. 7. Relay outputs:  2 user configurable form C. 8. Contact Inputs:  2 user configurable. 9. Non‐full pipe detection. 10. Analog Inputs:  two (2) 4‐20 mA inputs with 2‐wire, 18V DC supply. 11. Display:  4 lines of 20 character of waterproof, backlit LCD display. 12. Front panel keyboard:  tactile feedback, waterproof sealed. 13. Diagnostics:    all  necessary  diagnostics,  readings  and  system  status  to  be 

available via front panel keypad without opening the door. 14. Windows interface connection via serial connection.  

Page 228: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐6 

E. Meter and transmitter shall be manufactured by Advanced Flow Technology Company, UniMag  DS  Series,  Magnetoflow  Mag  Meter  with  remote  Primo  Amplifier  by BadgerMeter, Inc. 

 2.02 CLAMP‐ON FLOW METERS  

A. Where  clamp‐on  flow  meters  are  specified  for  installation  on  existing  piping,  the following shall apply: 1. AquaTrans ™ AT868 as manufactured by GE Infrastructure Sensing. 2. Clamp‐on flow transducer. 3. Suitable  for  use  with  clean  water  and  liquids  with  entrained  solids  and  air 

bubbles. 4. Suitable for use on ductile iron or PVC pipe. 5. Flow Accuracy 

a) ± 2% to 5% of reading on pipe ≤ 6‐inch. b) ±1% to 2% of reading on pipe > 6‐inch. 

6. Repeatability:  ± 0.1% to 3% of reading. 7. Range:  ‐ 40 to 40 ft/sec. 8. Rangeability:  overall 400:1 9. Measurement Parameters 

a) Volumetric flow b) Totalized Flow c) Flow Velocity 

10. Mounting:  as shown on Contract Drawings.  

B. Electronics 1. Correlation Transit‐Time mode. 2. Enclosure:  NEMA 4X. 3. Channels:  One. 4. Display:  2‐line x 16 character backlit LCD display, configurable to display up to 

four measurement parameters in sequence. 5. Six button internal keypad. 6. Power supply:  85 to 265 VAC, 60 Hz. 7. Operating Temperature:  14° ‐ 158°F. 8. Standard Input/Output:  one (1) 4‐20 mA isolated output per channel.  600 ohm 

maximum load. 9. RS 232 Interface. 

 C. Clamp‐On Ultrasonic Flow Transducer 

1. Temperature Range:  ‐ 40° to 140°F. 2. Mounting:  stainless steel chain or strap. 3. Weatherproof NEMA 4 submersible. 4. Cable:   one pair of coaxial cables, type RG62 AU; distance as required by field 

conditions.  

Page 229: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐7 

2.03 TELEMETRY  

A. General: 1. All  telemetry  shall  be  supplied  by  one  supplier  and  shall  be  compatible  and 

integrated into the existing Foxboro SCADA system operated by the City using open system interconnect. 

2. All  telemetry data  shall be  received by  the master SCADA unit  located at  the Clarksville Gas and Water Main Office located at 2215 Madison Street. 

3. All new equipment shall be Foxboro to match existing components. 4. Manufacturer  shall  provide  the  Owner  with  updated  telemetry  system 

documentation after the installation of new equipment is completed. 5. Manufacturer  shall  conduct  a  site  survey  of  the  proposed  sites  to  guarantee 

line  of  radio  communication  between  new  radio  and  the  nearest  repeater station.  Repeater station shall also communicate with master unit. 

6. At  a  minimum,  telemetry  for  new  pumping  stations  shall  be  capable  of monitoring the following station functions: a) Pump status for all pumps (off‐on). b) Power failure. c) High wet well level alarm. d) Pumped flow. e) Man down. f) spare digital input/output. g) spare analog input/output. 

B. Data Acquisition and Multi‐Loop Control Unit requirements: 1. Modbus communication. 2. Provide  signal  conditioning,  alarm  monitoring,  remote  data  acquisition  and 

developed control. 3. Base unit shall include internal I/O bus and mounting supports, an Input Output 

Controller, and analog and digital modules to meet the requirements of signals to be monitored. 

4. Live plug‐in capability. 5. Diagnostic LED’s. 6. Operating  temperature  0  ‐  55°C  with  5°  to  95°  non‐condensing  relative 

humidity. 7. Manufacturer:  Invensys‐Foxboro Model 2500.  

C. Radio requirements: 1. Frequency‐hopping  spread  spectrum  radio  operating  in  the  license  free  902‐

928 MHz Band. 2. 1 watt receiver. 3. Allow for communication up to 25 miles, line of sight. 4. User‐configurable encryption key. 5. RS‐232 serial data port. 6. Remote control, statistics, diagnostics. 7. 10‐30 VDC power supply. 

Page 230: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐8 

8. Operating environment, ‐ 40° to 75°C. 9. Extruded aluminum, powder coated enclosure. 10. Reverse gender antenna connector. 11. LED indicators for power, transmit, receive, and signal strength. 12. Function as a master, slave or repeater unit. 13. Meet requirements of FCC Part 15.247 and IC RSS210. 14. Manufacturer:  American Control Technologies, Model IP920 Wireless Ethernet 

Bridle/Serial Gateway Data Hopper.  

D. Antenna requirements: 1. Omnidirectional. 2. Gain as determined during site survey (6 or 9 dBd). 3. Moisture resistant. 4. Lightning resistant. 5. Suitable for use with 902 ‐ 928 MHz radio. 6. Stainless steel mounting hardware. 7. Dual purpose mounting unit. 8. Mast:  Height and configuration as determined by field site survey. 9. ½”  coaxial  cable  of  length  to  connect  antenna  and  radio  with  coaxial  cable 

connectors.  

E. UPS: American Power Conversion Backup UPS RS 1000/VA 1500VA. 

 F. Control Panel requirements: 

1. Minimum size, 24”(w) x 36”(h) x 16”(d), NEMA Type 4,12 with lockable door. 2. Square D DPDT 120 VAC relay with pilot and operator. 3. 20 amp simplex receptacle for UPS. 4. 20 amp duplex receptacle for convenience. 5. 10 amp breaker. 6. 120 VAC surge arrestor 7. Piloted fuse blocks. 8. Grounding bar. 9. Wireway as needed. 10. Mounted external  to pump station on galvanized  steel post or unistrut  set  in 

concrete.  2.04 WIDE AREA WIRELESS TELEMETRY (SMALL STATIONS)  

A. General: 1. The equipment  to be  furnished will  be  the product of  a qualified  firm  that  is 

regularly engaged in the manufacture and/or supply of this type of equipment.  A qualified firm will be defined as one that has manufactured and sold 100 of the specified units during the last two years.  

Page 231: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐9 

2. It  is  the  intent  of  the  specifications  to  secure  equipment  that  can  be maintained  and  serviced  without  necessity  of  stocking  expensive  parts inventory or being subject to long periods of interrupted service due to lack of spare parts. 

3. The company, shall have on staff, engineering and operation personnel with at least  five  years  experience  in  designing,  manufacturing  and  operating  wide area  wireless  telemetry  systems,  microprocessor  based  monitoring  systems and  interactive,  remotely  accessible  (Internet  or  otherwise)  database management systems and computer telephony. 

4. The  company  shall  be  the  actual  manufacturer  and  operator,  or  a  duly authorized and trained agent of the manufacturing company or a combination of both, who will actually provide, maintain and warranty the system. 

5. The manufacturing company of the field equipment shall also be the provider of  all monitoring  related  services associated with  the  field equipment and all ongoing  service  agreements  will  be  with  the  actual  company  providing  the monitoring service, not a subContractor or agent. 

6. The company shall provide 24/7 technical support. 7. The  company  shall  be  able  to  provide  field  equipment  that  either  transmits 

alarms only and daily status events or continuously transmits all digital, analog and pulse inputs on an “as occurs” basis or at least once every two (2) minutes and the City may choose to utilize either type of field unit at any proposed site. 

8. The  systems  shall  be  equivalent  to  the  Mission  Communications  C110 GSM/GPRS RTU or Omni‐Site XR‐50 GSM/GPRS Generation 3.5 RTU systems. 

 B.  Field Hardware Requirements: 

1. All  field hardware  shall  come enclosed  in a NEMA 4X durable  steel or  similar enclosure capable of housing all electronics and backup batteries.   

2. The field hardware shall have at least 8 digital (dry contact) inputs. 3. The  field  hardware  trip  inputs  must  have  end  of  line  resistor  supervision  or 

similar  supervision  that  can detect normal  alarm  trip  inputs  and detect  input writing disconnection as a distinctly different signal and report. 

4. The  field  unit  shall  be  capable  of  reporting  for  each  input  alarm,  return  to normal and fault condition. 

5. The  field unit  shall be made available with a  radio  that  transmits alarms only and daily status events. 

6. The field unit shall have on‐board diagnostic enunciator  lights  for each digital input, which indicate real time the state of the dry contact inputs. 

7. The field unit shall have at least two (2) analog inputs (0‐5 Vdc or 4‐20mA) of at least 10 bit resolution.  Each analog input shall have at least 4 threshold alarm set points. 

8. The  field  unit  shall  be  capable  of  reporting  analog  threshold  alarms,  daily high/low analog values and /or current analog values. 

9. The field hardware trip  inputs must operate normally when either side of the trip  inputs  circuitry  is  shorted  to  ground  and  send  a  trouble  signal  upon detection of such short to ground. 

Page 232: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐10 

10. The field hardware trip inputs must have a programmable trip input detection delay between 0 and 90 seconds. 

11. The  field  units  shall  have  on‐board  diagnostics  that  indicate  received  signal strength of the wireless carrier’s signal, wiring faults and message transmission progress and status. 

12. The  field  hardware  unit  shall  have  some  methodology  that  enables  a  single input to be temporarily disabled that does not conflict with the disabled inputs end of line resistor or wiring supervision method. 

13. At  least  three  of  the  field  hardware  trip  inputs  must  be  capable  of  being programmed  to  record  and  report  pump  run  times  as  indicated  by  a  relay opening and closing for up to three pumps.  If only two pumps are monitored, then the unit shall also record and report simultaneous pump run times. 

14. The unit shall record and report individual pump starts on a one day or seven day basis.  The unit shall also have the ability to report within one (1) hour any individual  pump  starting  in  excess  of  a  preprogrammed  amount.    The  excess pump start messages shall be automatically forwarded to City via pager, email or fax. 

15. The field unit shall be optionally capable of counting voltage pulses or contact closure from two different sources and reporting those pulse counts daily or as they occur.  This shall be in addition to the other inputs described above. 

16. The  field  unit  shall  have  a  means  of  being  put  in  local  shut  down  without powering  the  unit  down.    This  shall  effectively  stop  any  alarms  from  being either transmitted from the unit or sent from the central computer facility.  The action of putting a field unit in local shut down mode must be authorized and documented via an electronic access control key or card reader.  The act of the local shutdown shall be recorded, along with the name of identity of the person performing the local shut down at the central computer facility. 

17. The field hardware shall monitor its primary AC power supply input and shall be capable  of  sending  an  AC  failure  alarm.    The  unit  shall  delay  the  AC  failure report for 300 seconds.  The unit shall report AC power restoration. 

18. The  field  hardware  shall  have  a  built‐in  supervised  battery  backup  power supply.    This  power  supply  shall  be  tested and operate  the equipment  for  at least  15  seconds  every  day.    The  unit  shall  detect  and  report  any  backup battery power supply test failure. 

19. The field unit shall have a built‐in electronic key or card reader which will, when activated, cause the central monitoring/alarm notification facility to cancel any in‐progress alarm notifications for that field unit.  Additionally, the key use will prevent any subsequent alarms from being processed for a period of one hour, and record at a central facility the time and name of the electronic key used for the activation.  Alarm notifications will resume when the electronic key is used again or automatically resume one hour after the last alarm message was sent from the monitored site. 

20. The  field  unit  shall  have  the  capability  of  being  shut  down  from  transmitting any alarms by use of  a push button  switch.    The push button  switch  shall  be activated by use of an electronic key or card.  The unit shutdown switch will not 

Page 233: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐11 

allow unit shut down until said electronic key or card has been used within the preceding one minute.  The electronic key or card use and the subsequent unit shut  down  shall  be  transmitted  immediately  and  the  event  be  logged  at  the central computer.  The field unit shall be capable of re‐enabling itself for alarm use  by  a  subsequent  electronic  key  or  card  use  or  subsequent  push  button activation and shall automatically re‐enable at midnight.  Such re‐enabling shall be transmitted to the central computer for logging. 

21. The field hardware shall utilize a transmission scheme and subsequently report individual transmission failures. 

22. The field hardware shall utilize, in the case of a continuously transmitting field unit, a transmission scheme that encrypts the transmitted data utilizing an 128 bit  encryption  method  that  meets  or  exceeds  the  advanced  encryption standard  (AES).   Additionally,  the continually  transmitting  field units will have an effective, continuous transfer rate of at least 19,200 baud. 

23. The  field  hardware  unit  shall  utilize  a  transmission  scheme  that  individually identifies each transmitted message by sequence number. 

24. The field hardware shall optionally be capable of sending test transmissions at least  every  seven  days  and  have  the  capability  for  daily  and  on‐demand  test transmissions of transmitting a signal at least once a minute. 

25. The field hardware test transmissions shall indicate current and historical radio signal reception quality and shall report radio signal outage and the duration of the outage. 

26. The field hardware must be capable of  reporting, on‐demand or on‐schedule, operational  status,  accumulated pulse  input  values, pump  run  time durations and  current  operation  status  of  normal  alarm  trip  inputs  (trouble,  alarm, normal states).  

27. The field unit shall be capable of being put into a service mode at the remote site  and  such  service mode  operations  shall  be  logged  and  accessible  to  the customer at a central monitoring facility. 

28. The field unit shall be capable of optionally providing a method to monitor the wet  well  float  circuit  directly  while  providing  auxiliary  wet  well  alarm  relay contact  closures without  the addition of  a  separate high wet well  float.    This optional  circuitry  shall  detect  high wet well  conditions  in  the  event  of  pump station AC failures. 

29. The field unit shall not present any electric shock hazard. 30. The  field  unit  shall  be  capable  of  being  listed  as  complying  with  the 

Underwriter’s Laboratory requirements for remote signaling devices. 31. The  system shall have a primary  central monitoring and control  center and a 

fully  redundant,  physically  separate,  backup‐computer  monitoring  center.  Either center  shall have  the capability of operating all  the  remote monitoring and control field RTUs. 

 C.  Monitoring and Control Center Software/Hardware Requirements: 

Page 234: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐12 

1. The  monitoring  center  functionality  and  customer  alarm  and  supervisory information  must  be  made  available  to  customer  via  secure  Internet connection or other access manor acceptable to the City. 

2. The monitoring  center must  be  capable  of  interfacing  and  transferring,  on  a continuous  basis,  all  RTU  data  to  an  OPC  compliant  database  for  access  by other OPC compliant HMI software packages.   Such transfer method will have 128  bit,  or  better  encryption,  and  meet  or  exceed  the  advance  encryption standard (AES). 

3. The  monitoring  center  must  be  housed  in  a  secured,  access‐controlled facility/enclosure. 

4. The  monitoring  center  critical  equipment  must  be  supplied  power  from  an uninterruptible power source capable of stand‐alone operation for at  least 12 hours. 

5. The monitoring center customer  Internet Web site shall provide the City with on‐demand  capability  of  shutting  down/waking  up  individual  units,  remotely status  testing  individual  units,  remotely  controlling  individual  units  on‐board relay,  individually  polling  units  for  current  trip  inputs  or  accumulator  input status  and  values,  and  be  capable  of  remotely  reprogramming  other  critical field unit operating parameters. 

6. The monitoring  center  shall  provide  individual  log  on  access  and  operations security  levels  as  well  as  require  logged,  individual acceptance/acknowledgement  of  all  presented  alarms  or  supervisory messages. 

7. The monitoring center shall provide an easy to use/understand general system overview graphic representation of the current state of all remote points being monitored by the system. 

8. The monitoring center shall provide screens that can display the current status or value from field units that provide continuously transmitted digital, analog, or pulse counting data. 

9. The  monitoring  center  shall  provide  screens  that  can  display  historical  data trends  in  a  graphic  format  from  field  units  that  provide  continuously transmitted digital, analog or pulse counting data. 

10. The monitoring  center  shall  provide  the  ability  to manually  control  field  unit relays from field units that provide continuously transmitted digital, analog or pulse  counting  data.    All  such  control  functions  shall  be  password  protected and logged in a secured database. 

11. The monitoring  center  shall  provide  for  the  remote  command and  control  of the customers monitored field hardware in a manner consistent with the field unit’s  capabilities.    The  access  to  this  remote  command  and  control functionality shall be security level controlled and all events of use logged in a secure database. 

12. The  monitoring  center  shall  provide  functions  for  the  City  to add/delete/change a field unit’s alarm notification delivery methodologies and destinations. 

Page 235: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐13 

13. The monitoring center shall provide easy to understand and use screens for the City to securely access, globally or individually, alarms, testing and notification results for the field monitoring units. 

14. The monitoring center shall provide a methodology to enable/disable an entire unit  from reporting, or any of  the unit’s  individual  inputs  from reporting with such enabling/disabling to be time scheduled. 

15. The  monitoring  center  must  have  a  methodology  to  track  the  results  of  all alarm notifications as to its success or failure.  If alarm notifications fail, a log of said procedures and their causes shall be provided. 

16. The monitoring center must have the ability to analyze and display, graphically or tabular, all pump runtimes on a daily basis.  The pump runtime analysis shall use regression analysis over the preceding thirty days.  The analysis shall have preset  variance  limits,  which  when  exceeded,  automatically  cause  emails, pages or faxes to be generated to a customized list of recipients.   

 D. Notification Capabilities Requirements: 

1. The monitoring center shall be equipped with adequate communications  links to provide  reasonable assurance  that alarms will be delivered via any chosen delivery  methodology  to  selected  recipients  within  30  seconds  of  the monitoring center receiving such alarms from field equipment. 

2. The  monitoring  center  shall  be  capable  of  automatically  delivering  alarm  or other  selected  message  to  numeric  pagers,  alphanumeric  pages,  email addresses, facsimile machines or voice telephones (hardwired or wireless, local or  long  distance).    Such  delivered  messages  will  include  a cancellation/acceptance code (or other such methodology) that is used by the recipient  to  indicate  the  monitoring  system  that  the  recipient  has received/accepted  the  sent  message.    All  message  notification  attempts, failures and delivery/acceptance confirmations will be logged. 

3. The  monitoring  center  shall  be  capable  of  scheduling  alarm  notifications  to recipients by time of day, day of week, holiday and input type. 

4. The monitoring center shall be capable of delivering  to  the alarm notification recipient  the  pump  running  status  of  all monitored  pumps  at  the monitored site in the same alarm notification message as the initiating alarm message. 

5. The  monitoring  center  must  have  the  ability  to  suppress  erroneous  digital alarms that occur in conjunction with AC power failures. 

6. The monitoring center must have  the ability  to selectively suppress  repeat or duplicate alarms from a particular field unit and a particular input. 

7. The monitoring center shall be capable of buffering AC power failure messages for  a  City‐defined  amount  of  time  and  then  issuing  a  single  group  alarm notification message that embodies a list of all of the monitored sites that have an AC power failure.  The same group alarm notification function shall apply to monitored sites that have AC power restoring to normal. 

8. The monitoring  center  shall  store  all  system messaging  transaction,  operator commands,  notification  attempts  and  message  delivery  confirmations  in  a secure, non‐alterable database. 

Page 236: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐14 

9. The  monitoring  center  shall  automatically  report  and  notify  customer designated recipients of RTU telemetry link loss within five minutes of link loss for  continuous  telemetry  RTUs,  or  twenty  five  hours  of  link  loss  for  daily reporting RTUs. 

 E. Administrative Reports Requirements: 

1. The  monitoring  center  shall  provide  the  customer  with  automatically generated,  weekly  reports  of  all  alarms,  notifications,  delivery confirmations/acceptances and unit test failures.  Such weekly reports shall be automatically faxed or emailed to up to four (4) City‐designated recipients. 

2. The  monitoring  center  shall  be  capable  of  generating  historical  reports  of any/all  field  monitoring  unit’s  alarms,  notifications,  delivery confirmations/acceptances and test failures. 

3. The monitoring center shall automatically archive all logged system activity on a daily basis to a physically separate database and computer. 

4. The monitoring center shall analyze (by percent variance or regression analysis) all pump routines on a daily basis and automatically generate and send via fax or email out‐of‐bounds reports to up to four (4) recipients. 

5. The monitoring center must have the ability to display, by site or by electronic key‐holder, all uses of the electronic key for at least a month’s period of time.  Such electronic key use records will be accessible in a report form for hard copy storage. 

6. The monitoring  center must have  the ability  to  transfer alarm, electronic  key use, analog values, pulse count values, and pump run times to other computers via a comma‐delineated text string file transfer so as the data can be imported into other generally accepted spreadsheet computer programs.   

  PART 3 – EXECUTION  3.01 MANUFACTURER’S SERVICES  

A. All manufacturer’s visits to construction site prior to final performance test shall be the responsibility of the Contractor.  The Contractor shall furnish the Owner with services of equipment manufacturers’ representatives for a period of 1 man‐day. 

 B. Applicable  Contract  prices  shall  include  the  furnishing  of  all  said  services.  

Furthermore,  said  services  shall  be  additional  to  those  furnished  in  connection with equipment erection,  installation,  testing  and  the  correction of  deficiencies.    Services provided  shall  consist  of  furnishing  detailed  instructions  to  personnel  of  the  Owner regarding equipment operation and maintenance. 

 3.02 INSTRUCTION MANUALS  

Page 237: Standard Water and Sewer Specifications PDF

  SEWAGE SYSTEM FIELD INSTRUMENTATION  13310‐15 

A. Contractor  shall  furnish,  prior  to  initial  testing,  three  (3)  copies  of  an  indexed maintenance manual composed of supplier’s maintenance manuals on all equipment and  supplier’s  brochures  on  all  specialty  equipment,  including  performance  curves with  size,  model,  figure  number,  etc.,  indicated  to  identify  unit  furnished.  Maintenance manuals are to be a hardback,  loose‐leaf type and of a durable quality.  Manuals are  to be  for  the  specific equipment provided.   Manuals describing general equipment lines will not be accepted. 

 B. Each set is to include the following: 

1. Manufacturer’s parts list identified with the make, model and serial number of the equipment furnished. 

2. Control and wiring diagrams. 3. Installation, operation, and maintenance instructions. 

 END OF SECTION 

 TABLE OF CONTENTS 

Page 238: Standard Water and Sewer Specifications PDF
Page 239: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐1 

SECTION 16010  

GENERAL ELECTRICAL PROVISIONS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Provide all labor, material, tools and services for a complete installation of equipment and systems specified herein.  

B. No project is considered complete unless it is functional.  1.02  QUALITY ASSURANCE  

A. Comply with applicable local, state and federal codes.  

B. Comply  with  applicable  requirements  of  recognized  industry  associations  that promulgate standards for the various trades.  

C. Employ  only  qualified  journeymen  for  this  work.    Employ  a  competent  qualified electrician to supervise the work. 

 1.03  STANDARDS 

 A. Perform work specified in Division 16 in accordance with standards listed below 

including amendments or revisions.  When these specifications are more stringent, they take precedence.  In case of conflict, obtain a decision from the owner's representative. 

 B. National Fire Codes (NFPA) including, but not limited to following: 

1. NFPA‐70 ‐ National Electrical Code. Most recent edition adopted by the City of Clarksville. 

2. NFPA‐101 ‐ Life Safety Code. Current Edition.  

C. Applicable codes: 1. Standard Building Code.  Current Edition. 2. ANSI Handicapped Code ‐ A117.1.  Current Edition. 3. Applicable State Energy Code.  Current Edition. 4. City of Clarksville Electrical Code.  Current Edition. 5. State of Tennessee "Chapter 0780‐2‐1 Code," 1981 Edition. 

 

Page 240: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐2 

D. Should any work be construed as being contrary to or not conforming to aforementioned codes, such alleged conflict shall be brought to attention of Engineer in writing ten (10) days prior to bid date for review so that such point in question may be resolved.  All work to be installed in strict conformity with applicable codes without additional cost to Owner.  

E. Contractor shall submit and/or file with proper authorities all necessary specifications and drawings as required by governing authorities. 

 1.04 SUBMITTALS  

A. Submit  letter  from  each  equipment manufacturer  stating  that  equipment  furnished will  withstand  horizontal  forces  evaluated  using  a  "Cp"  factor  of  0.2  applied  in  any direction.   See mechanical drawings for seismic bracing and anchorage of equipment being furnished under this Division.  

B. Within  fifteen  (15) days after contract has been awarded, Contractor shall  submit  to Engineer  for  approval  a  complete  list  of  materials,  equipment,  and  accessories proposed for use, listing the item and manufacturer's name only.  

C. Based upon aforementioned approved listing, Contractor shall submit three (3) copies for the Owner’s use plus any additional copies required by the Engineer of COMPLETE BROCHURES  AND  SHOP  DRAWINGS  OF  ALL MATERIALS,  FIXTURES  AND  EQUIPMENT that Contractor proposes to use, giving the names of manufacturers, trade name and specific catalog numbers.  

D. Brochures to be submitted in time to allow 15 days from date of receipt in Engineer's office before final approval or disapproval  is required to meet construction schedule.  Submittals  to  bear  Contractor's  stamp  of  approval  evidencing  he  has  examined  and checked  same  and  information  contained  therein  is  in  accordance  with  contract requirements, and any deviations to be clearly marked.  Approval of shop drawings not to be construed as permitting departure from the contractual documents.  

E. Above mentioned  brochures  to  be  submitted  and  approved  by  Engineer  before  any materials are installed.  

F. Proposed  items  to be  clearly  indicated when other  items are  shown on  same  sheet.  When proposing items other than those specified, brochures to contain both specified item  sheets  and  proposed  item  sheets  for  ease  of  comparison.    On  request  from Engineer  samples  shall  be  submitted  and/or  set  up,  as  directed,  for  inspection  and approval. Samples will be returned to Contractor.  

G. Shop drawings:  Submit specific shop drawings for major materials where called for or when requested by Engineer. 

 

Page 241: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐3 

1.05 OPERATING AND MAINTENANCE MANUALS  

A. Prior to final acceptance of the project, furnish to the Owner complete three (3) bound sets of operation and maintenance manuals  for all pieces of equipment and systems provided under this division of specifications.  

B. Manuals  to  also  include  all  submittal  data  on  all  materials  and  equipment.    Clearly indicate  items  provided  on  this  project.    A  list  giving  name  and  address  of  nearest supply house carrying spare parts and name of Installation Subcontractor to be given to Owner.  

C. Verbally instruct Owner's Representatives in the start‐up, operation and maintenance of  all  equipment  provided.    Contractor  to  obtain  letter  signed  by  the  Owner's Representative indicating that the in‐service training has been completed.  

D. Arrange  each  set  of  data  in  an  orderly way,  and  bind  each  set  in  a  separate  3‐ring, hard‐cover binder.  

E. As  soon  as  data  accumulates,  prepare  one  of  the  sets  and  deliver  to  the  Owner's Representative.  Continuously update this set as additional data is obtained.  

F. At  completion  of  work,  submit  three  complete  sets  of  data  to  the  Owner's Representative. 

 1.06  DELIVERY AND STORAGE  

A. Insofar  as  possible,  deliver  items  in  manufacturer's  original  unopened  packaging.  Where this is not practical, cover items with protective materials, to keep them from being  damaged.    Use  care  in  loading,  transporting,  unloading,  and  storage  to  keep items from being damaged.  

B. Store items in a clean dry place and protect from damage.  

C. All damaged painted surfaces of equipment to be touched up to match original paint.  1.07  RECORD DRAWINGS  

A. Keep a set of project drawings at the job site exclusively for recording deviations from the drawings which are necessary because of job conditions.  

B. Mark  deviations  in  colored  pencils  so  that  work  of  various  systems  can  be  easily identified.  

C. When work is completed, record all deviations on drawings and return to the Owner.  AutoCAD compatible drawings may also be required. 

Page 242: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐4 

 D. Contractor  shall  submit corrected drawings  to  the Owner as  record copies within  six 

weeks of acceptance of the project.   PART 2 ‐ PRODUCTS  2.01  MATERIALS AND EQUIPMENT  

All materials and equipment used in carrying out these specifications shall be new and have UL  listing,  or  listing by other  recognized  testing  laboratory when  such  listings  are  available.  Specifications  and  drawings  indicate  name,  type,  and  catalog  numbers  of  materials  and equipment  to  be  used  as  "standards"  and  shall  not  be  construed  as  limiting  competition.  Contractor may  at  his  option,  use materials  and  equipment  when,  in  the  judgment  of  the Engineer,  they  are  equivalent  to  that  specified  and  are  approved  by  the  Engineer  prior  to starting work or ordering material. 

  PART 3‐ EXECUTION  3.01  COORDINATION  

A. Deviations: 1. No  deviations  from  specifications  and  drawings  shall  be  made  without  full 

knowledge and consent of Engineer. 2. Should Contractor  find during progress of work  that existing conditions make 

desirable a modification of the requirements of any particular item, report such item promptly to Engineer for his decision and instructions. 

 B. Insofar as it is possible to determine in advance, leave proper chases and openings.  

Place all outlets, anchors, sleeves, and supports prior to pouring concrete or installation of masonry work.  Should the Contractor neglect doing this, any cutting and/or patching required to be done is at this Contractor's expense.  

C. Visit site and be informed of conditions under which work must be performed.  No subsequent allowance will be made because of error or failure to obtain necessary information to completely estimate and perform work involved.  

D. Coordinate to assure that proper points of service transformer locations, voltage characteristics and capacity of service are in accordance with Contract Drawings. 

 3.02  CUTTING AND PATCHING  

A. Repair or replace routine damage caused by cutting in performance of this contract.  

Page 243: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐5 

B. Correct  unnecessary  damage  caused  due  to  installation  of  electrical  work,  brought about through carelessness or lack of coordination.  

C. Holes cut through existing floor slabs or walls to be core drilled with drill designed for this purpose.   All  openings,  sleeves and holes  in  slabs between  floors or walls  to be properly sealed, fire proofed and water proofed.  

D. Repairs  to  be  performed  with  materials  that  match  existing  materials  and  to  be installed in accordance with appropriate sections of these specifications. 

 3.03  TRENCHING, EXCAVATION, BACKFILLING, AND REPAIRS  

Provide trenching, excavation, and backfilling necessary for performance of electrical work in accordance with Section 02221 and the governing power company. 

 3.04  FOUNDATIONS AND PADS  

A. Contractor  to  furnish  and  install  all  foundations  and  pads  required  for  equipment provided under this division of specifications.  Contractor to be responsible for proper size and  location of  foundations, pads, anchor bolts and other  items  to be built  into structure.  

B. Concrete to be in accordance with Section 03300 of these specifications.  3.05  TESTS  

A. On completion of work, installation shall be entirely free from grounds, short circuits, and open circuits.   Perform a  thorough operational  test  in presence of Owner or his representative.    Balance all  circuits  so  that  feeders  to panels  are not more  than  ten percent  out  of  balance  between  phases  with  all  available  loads  energized  and operating.  Furnish all labor, materials and instruments for above tests.  

B. Prior  to  final  observation  and  acceptance,  test  and  leave  in  satisfactory  operating condition all electrical systems and equipment. 

 3.06  INSPECTION FEES AND PERMITS  

Obtain  and  pay  for  all  necessary  permits  and  inspection  fees  required  for  electrical installation. 

 3.07  IDENTIFICATION OF EQUIPMENT  

Properly  identify  all  boxes  with  permanently  attached  black  phenolic  plates  with  1/4‐inch white engraved lettering on the face of each attached, with two sheet metal screws.  Starters and  relays  connected by  the Contractor  shall  be  identified.    CLX  cable  and  conduit  systems 

Page 244: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐6 

containing 15 KV cables  shall be  identified with "15 KV" markings and/or phenolic plates as previously described. 

 3.08  TEMPORARY LIGHTS AND POWER IF REQUIRED  

A. Provide a temporary electrical lighting and power distribution system of adequate size to  properly  serve  the  following  requirements,  including  adequate  feeder  sizes  to prevent  excessive  voltage  drop.    Temporary work  to  be  installed  in  a  neat  and  safe manner  in accordance with  the National Electrical Code and as  required by OSHA or applicable local safety codes.  

B. Check  prior  to  installation  to  determine  if  any  lighting  or  power  outlets  over  the maximum quantity noted above are required.  

C. Provide  service  tap  and  panelboards  required  for  above  lighting  and  power  outlets.  Verify tap location with Engineer prior to starting work.  

D. Power consumption will be paid for by the Contractor.  

E. Contractor  to maintain  the existing  lights  and power during normal  regular hours as directed by Owner.  Any interruption of power must be approved by and coordinated with Owner's representative. 

 3.09  DEMOLITION  

A. Schedule all demolition work as to cause minimal interference with facility operations and to comply with provisions of these specifications.  

B. Obtain  prior  approval  of  the  Owner  at  least  seven  days  in  advance  before  starting demolition  of  any  equipment.    Under  no  circumstances  will  demolition  work  be approved until new equipment is ready for installation.  

C. Disconnect  or  arrange  for  disconnection  of  utility  service  connections  to  equipment and areas to be demolished before starting demolition.  

D. Preserve in operating condition all active utilities transversing the project site.  Protect all equipment  that  remains  (electrical and mechanical) during demolition, and  repair all damage caused by this work to satisfaction of Engineer.  

E. Maintain the continuity of the existing branch circuits serving all existing light fixtures that are to remain, whether indicated or not on the drawings.  

F. All existing walls, ceilings, floor slabs, etc., being cut or damaged under this contract to be patched back to match existing.  

Page 245: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐7 

G. All existing switchgear,  lighting  fixtures,  receptacles, control equipment and switches being removed to be cleaned and turned over to the Owner.  

H. Remove exposed ground conductor back to source or point of contact with slab.  Cut conductor off below slab and abandon with hole being patched back to match existing surface (floor, wall or ceiling).  If reusable, simply disconnect ground conductor.  

I. Conduits, wire and wood products that are not salvageable shall be disposed of legally.  

J. Primary work shall be completed with all facilities kept in service or with short periods of scheduled momentary outages.  

K. Holes  in  slabs  or  into  classified  areas  to  be  patched  to  provide  a  gas,  vapor  and watertight barrier.  

L. The Owner reserves the right to save materials that are a part of the demolition work, and  the  Contractor  shall  turn  over  and  store  any  such  materials  at  the  Owner's direction.  

M. All  materials  not  turned  over  to  Owner  shall  become  property  of  Contractor  and removed promptly from plant site at no additional cost to the Owner.  Any permits or fees for disposal shall be the responsibility of the Contractor. 

N. Burn no materials or debris on premises.  

O. Remove  from  site  rubbish  and  debris  found  thereon  and,  except  as  otherwise specified, materials and debris  resulting  from work of demolition.    Leave site  in  safe and clean condition. 

3.10  OBSERVATIONS  

A. The Engineer or his representative will provide periodic observation of the progress of work specified herein and will also observe tests required of Contractor as called for in other sections of specifications.  

B. Specifications  and  drawings  represent  work  to  be  done  in  view  of  total  project requirements.    Final  location  of  conduits,  switchgear,  etc.,  to  eliminate  possible conflict with existing equipment is responsibility of Contractor.  Contractor to provide all  supervision  required  for  his  personnel  to  insure  that  installation  is  made  in accordance with  specifications  and drawings  and all  safety  rules  and  regulations  are observed.    In  event  of  conflicts  of work  on  project with  other  trades,  Contractor  to make  every  reasonable  effort  to  resolve  conflict  through  meetings  and  discussions with other parties  involved,  by preparation of  drawings or other  appropriate  action.  Only after this has been done shall the Engineer's assistance be requested. 

 

Page 246: Standard Water and Sewer Specifications PDF

  GENERAL ELECTRICAL PROVISIONS  16010‐8 

3.11  WARRANTY‐GUARANTEE  

A. Engineer  reserves  right  to  accept  or  reject  any  part  of  installation  that  does  not successfully meet requirements as set out in these specifications.  

B. Contractor shall and hereby does guarantee all work installed under this division shall be free from defects in workmanship and materials for a period of one year from date of final acceptance.  The Contractor shall repair and replace any defective material or workmanship which becomes defective within the terms of this warranty‐guarantee at no additional cost to the Owner. 

 END OF SECTION 

 TABLE OF CONTENTS

Page 247: Standard Water and Sewer Specifications PDF

  OVERCURRENT PROTECTIVE DEVICE COORDINATION AND ARC FLASH STUDY  16030‐1 

SECTION 16030  

OVERCURRENT PROTECTIVE DEVICE COORDINATION AND ARC FLASH STUDY  

TABLE OF CONTENTS  

PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Section  includes  short  circuit,  protective  device  coordination  and  Arc  Flash  study encompassing portions of electrical distribution system from normal power source or sources up to and including main breaker in each panelboard. 

B. Contractor  shall  engage  services  of  independent  engineering  firm  for  purpose  of 

performing electric power system studies as specified.  1.02  REFERENCES  

A. Institute of Electrical and Electronics Engineers:  IEEE 242 ‐ Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems (Buff Book). 

 B. National Fire Protection Association:  NFPA 70 ‐ National Electrical Code. 

 1.03  DESIGN REQUIREMENTS  

A. Complete Short Circuit, Protective Device Coordination, and Arc Flash Study  to meet requirements of NFPA 70 and NFPA 70E.  

B. Report Preparation: 1. Prepare  study  prior  to  ordering  distribution  equipment  to  verify  equipment 

ratings required. 2. Perform study with aid of computer software program. 3. Calculate short circuit interrupting and, when applicable, momentary duties for 

assumed 3‐phase bolted  fault  short  circuit  current and phase  to ground  fault short circuit current at each of the following: a) Utility supply bus. b) Medium voltage air interrupter switchgear. c) Medium voltage circuit breaker switchgear. d) Secondary unit substations. e) Automatic transfer switch. f) Manual transfer switch. g) Engine generator. h) Medium voltage motor controllers i) Medium voltage oil switchgear. 

Page 248: Standard Water and Sewer Specifications PDF

  OVERCURRENT PROTECTIVE DEVICE COORDINATION AND ARC FLASH STUDY  16030‐2 

j) Low‐voltage switchgear. k) Switchboards. l) Motor control centers. m) Distribution panelboards. n) Branch circuit panelboards. o) Each other significant equipment location throughout system. 

 C. Report Contents: 

1. Include the following: a) Calculation methods and assumptions. b) Base per unit value selected. c) One‐line diagram. d) Source  impedance  data  including  power  company  system  available 

power and characteristics. e) Typical calculations. 

i. Fault impedance. ii. X to R ratios. iii. Asymmetry factors. iv. Motor fault contribution. v. Short circuit kva. vi. Symmetrical  and  asymmetrical  phase‐to‐phase  and  phase‐to‐

ground fault currents vii. Tabulations of calculation quantities and results. 

f) One‐line diagram revised by adding actual  instantaneous short circuits available. 

g) State conclusions and recommendations. 2. Prepare  time‐current  device  coordination  curves  graphically  indicating 

coordination proposed  for  system, centered on conventional,  full‐size,  log‐log forms. 

3. Prepare with each  time‐curve sheet complete  title and one‐line diagram with legend  identifying  specific  portion of  system covered by  that particular  curve sheet. 

4. Prepare  detailed  description  of  each  protective  device  identifying  its  type, function,  manufacturer,  and  time‐current  characteristics.  Tabulate recommended  device  tap,  time  dial,  pickup,  instantaneous,  and  time  delay settings. 

5. Plot device characteristic curves at point reflecting maximum symmetrical fault current  to which  device  is  exposed.  Include  on  curve  sheets  the  following  as applicable: a) Power company relay characteristics. b) Power company fuse characteristics. c) Medium voltage equipment protective relay characteristics. d) Medium voltage equipment protective fuse characteristics. e) Low voltage equipment circuit breaker trip device characteristics. f) Low voltage equipment fuse characteristics. 

Page 249: Standard Water and Sewer Specifications PDF

  OVERCURRENT PROTECTIVE DEVICE COORDINATION AND ARC FLASH STUDY  16030‐3 

g) Cable damage point characteristics. h) Pertinent transformer characteristics including: 

i. Transformer full load current ii. Transformer magnetizing inrush. iii. ANSI transformer withstand parameters. iv. Significant symmetrical fault current 

i) Pertinent motor characteristics. j) Generator characteristics including: 

i. Phase and ground coordination of generator protective devices. ii. Decrement curve and damage curve. iii. Operating characteristic of protective devices. iv. Actual impedance value. v. Time constants. vi. Current boost data. vii. Do not use typical values for generator. 

6. Perform Arc Flash Analysis to include the following at each distribution bus: a) Bolted fault current. b) Arc fault current. c) Protective device characteristic and arc fault duration. d) System voltages and equipment class. e) Working distances. f) Calculated incident energy. g) Calculated arc flash protective boundary. 

 1.04  SUBMITTALS  

A. Submit results of study in report format including the following: 1. Descriptions, purpose, basis, and scope of study. 2. Tabulations of circuit breaker,  fuse and other protective device ratings versus 

calculated short‐circuit duties, and commentary regarding same. 3. Protective device time versus current coordination curves, tabulations of relay 

and  circuit  breaker  trip  settings,  fuse  selection,  and  commentary  regarding same. 

4. Fault  current  calculations  including  definition  of  terms  and  guide  for interpretation of computer printout. 

5. Arc flash calculations and printout of labels.  

B. Submit five (5) copies of final report signed by professional engineer.  Make additions or changes required by review comments. 

 1.05  QUALIFICATIONS  

A. Perform study under direct supervision of Professional Engineer experienced in design of this Work and licensed at project location with minimum of five years experience in power system analysis. 

Page 250: Standard Water and Sewer Specifications PDF

  OVERCURRENT PROTECTIVE DEVICE COORDINATION AND ARC FLASH STUDY  16030‐4 

 B. Demonstrate  company  performing  study  has  capability  and  experience  to  provide 

assistance during system start up.  1.06  SEQUENCING  

A. Submit  short  circuit  and  protective  device  coordination  study  to  Engineer  prior  to receiving final approval of distribution equipment shop drawings and prior to releasing equipment for manufacturing. 

 B. When formal completion of study will cause delay in equipment manufacturing, obtain 

approval  from Engineer  for preliminary submittal of  study data sufficient  in scope to ensure selection of device ratings and characteristics will be satisfactory. 

 1.07  SCHEDULING  

Schedule work to expedite collection of data to ensure completion of study for final approval of distribution equipment shop drawings prior to release of equipment for manufacturing. 

  PART 2 ‐ NOT USED   PART 3 ‐ EXECUTION  3.01  ADJUSTING  

Perform  field  adjustments  of  protective  devices  and  modifications  to  equipment  to  place equipment  in  final  operating  condition. Adjust  settings  in  accordance with  short  circuit  and protective device coordination study. 

 3.02  ARC FLASH SIGN INSTALLATION  

Implement the Arc Flash sign installation requirements for electrical equipment as specified in NEC Article 110.16 Flash Protection and NFPA 70E. 

 END OF SECTION 

 TABLE OF CONTENTS 

Page 251: Standard Water and Sewer Specifications PDF

  RACEWAYS AND CONDUIT SYSTEMS  16109‐1 

SECTION 16109  

RACEWAYS AND CONDUIT SYSTEMS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  A. Provide a complete conduit system with associated couplings, connectors, and fittings.  B. Conduits  shall  be  mechanically  and  electrically  continuous  from  outlet  to  outlet  and  from 

outlets to cabinets, pull or junction boxes.  1.02  SUBMITTALS  

Submittal for products furnished under this section is not required. 

PART 2 ‐ PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  A. IMC or EMT conduit shall be hot‐dip galvanized, or electro galvanized steel. 

B. Erickson couplings shall be used where neither length of conduit can be rotated.  C. Conduit  connectors  shall  use  the  two  locknut  type  for  EMT  or  IMC.    Associated  couplings, 

connectors, and fittings shall be all steel.  Die cast fittings are not acceptable.  D. Weatherproof  hub  shall  be  furnished  where  required,  complete  with  sealing  "O"  ring  or 

sealing locknuts.  E. Provide polyvinyl chloride (PVC) conduit, Type 40, and associated couplings, connectors, and 

fittings.  PVC conduit shall be UL listed and 90 degrees C UL rated.  F. Provide aluminum conduit in areas requiring non‐ferrous materials.  2.02  ELECTRICAL METALLIC TUBING (EMT)  

A. Use Electric Metallic Tubing (EMT) for: 1. Branch circuits installed overhead, both exposed and concealed, installed more 

than 6 feet above finished floor. 2. Branch circuits installed in floor slabs other than ground floor. 

Page 252: Standard Water and Sewer Specifications PDF

  RACEWAYS AND CONDUIT SYSTEMS  16109‐2 

 2.03  INTERMEDIATE METAL CONDUIT (IMC)  

A. Use Intermediate Metal Conduit (IMC) for: 1. Paperboard feeders. 2. Branch circuits installed in hazardous areas. 3. Branch circuits and feeders installed in concrete slabs at ground floor. 4. Branch circuits installed exposed below 6 feet above finished floor. 5. Branch circuits installed in wet locations. 6. Pendant drops. 

 2.04  POLYVINYL CHLORIDE (PVC)  

A. Use PVC for: 1. Service entrance conduits for power. 2. Riser conduits on utility poles. 3. Exterior feeders and branch circuits. 

 B. PVC conduit shall not be used for feeders or branch circuits inside the building except 

within chlorine atmosphere.  2.05  FLEXIBLE METAL CONDUIT  

A. Provide a flexible metal conduit system for the termination points at equipment that may possibly vibrate such as motors, welders, etc.  The length shall not exceed 6 feet. 

 B. Conduit  shall  be electrically  continuous  from outlet or  conduit  end  to  the utilization 

equipment.  

C. The total length of flexible conduit in any circuit shall not exceed 6 feet.  

D. Where  exposed  to  continuous  or  intermittent moisture,  conduit  shall  be  liquid  tight flexible type, U.L. Type EF. 

  PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Minimum size of conduits shall be ½ inch.  

B. Conduit  joints shall be cut square,  threaded,  reamed smooth, and drawn up tight so conduit ends will butt in couplings, connectors, and fittings. 

 C. Make bends or offsets with standard ells or field bends with an approved bender. 

Page 253: Standard Water and Sewer Specifications PDF

  RACEWAYS AND CONDUIT SYSTEMS  16109‐3 

 D. Run conduits concealed in floor slabs, below slabs, or  in walls  in direct  line with long 

sweep bends or offsets.  Run exposed conduits and conduits run above lay‐in ceilings parallel to and at right angles to building lines.  Group multiple conduit runs in banks. 

 E. Secure conduits  to all boxes and cabinets with  two  locknuts and bushings  so  system 

will be electrically continuous from service to all outlets.  

F. Cap ends of conduits to prevent entrance of water and other foreign material during construction. 

 G. Complete conduit systems before pulling conductors. 

 H. Conduits shall be divided according to voltage and amperage service level.  Conduits of 

different voltage levels shall be physically separated by the following distances unless otherwise  specified  on  the  drawings  by  the  electrical  engineer  or  control  system supplier. 1. Level  1  conduits  shall  contain  low  level  input/output  signal  conductors 

including RTD cables,  thermocouple  cables,  and 4‐20 mA dc  cables  from  field transmitters. 

2. Level 2 conduits shall contain all conductors for 24 volts dc power and signal. 3. Level 3 conduits shall contain all conductors  for 120 volt ac power to the PLC 

control cabinets, motor control circuits, field devices requiring 120‐volt power, etc. 

4. Level  4  conduits  shall  contain  all  conductors  for  120  volts  dc  control  power greater  than  3  amps,  all  120  volts  ac  power  greater  than  20  amps,  and  all power  circuits with  voltage  ratings  higher  than  120  volts  ac  (277,  480,  4160, 13,200 volts etc.).    Examples  include 480‐volt motor  feeds, 5‐kV  feeders,  and 120‐volt  lighting  circuit  and  input/output  devices  such  as  limit  switches  and solenoid valves. 

5. Conduits  shall  be  physically  separated  from  each  other  by  the  following distances: 

 

SPACING REQUIREMENTS (IN INCHES) FOR METALLIC CONDUITS 

From Level  To Level 2  To Level 3  To Level 4 

Level 1  Minimum 1"  Minimum 6"  Minimum 26" 

Level 2  0"  Minimum 6"  Minimum 26" 

Level 3  Minimum 6"  0"  Minimum 18" 

 6. Levels 1, 2, and 3 conductors shall additionally be routed away from sources of 

high  voltage  or  RF  radiation  such  as  switchgear,  transformers,  radio transmitters,  and  repeaters.    Minimum  separation  from  these  sources  of interference shall be 5 feet. 

Page 254: Standard Water and Sewer Specifications PDF

  RACEWAYS AND CONDUIT SYSTEMS  16109‐4 

7. Data  highway  communications  cable  is  generally  considered  Level  1 conductors;  however,  special  requirements  apply  for  routing  to  assure  a  low noise  environment.    Refer  to  electrical  drawings  and  controls  supplier requirements for special considerations before routing these conduits. 

 I. Where  conduits  of  different  levels  must  cross,  the  minimum  separations  shall  be 

maintained, and they shall cross at right angles.  

J. Provide  cable  supports  in  conduits  rising  vertically  in  accordance  with  the  National Electrical Code.  

K. Provide nylon pull cord in all empty conduits.  Steel wire not acceptable as pull wire.  

L. Conduits  that  pass  through  floor  slabs  (except  ground  floor)  shall  be  sealed  with concrete  grout.    Seal  around  conduits  or  other  wiring  materials  passing  through partitions, which extend to the underside of the slab above, and those passing through smoke partitions and fire‐rated walls. Refer to appropriate details on architectural and mechanical drawings.  

M. Conduits  that  enter  crawl  space,  tunnels,  and  basements  from  outside  the  building shall  be  grouted‐in  to  prevent  entry  of  gases,  vapors,  insects,  or  rodents  to  these spaces from street mains.  

N. Conduit  not  serving  elevator  equipment  shall  not  be  permitted  to  pass  through elevator shafts or elevator equipment rooms.  

O. Where IMC conduit is installed in a cabinet, junction box, pull box, or auxiliary gutter, conductors shall be protected by an insulated bushing.  Locknuts shall be installed on conduit outside and inside enclosure.  

P. In areas where enclosed and gasketed fixtures and weatherproof devices are specified, where rigid conduit enters a sheet metal enclosure, junction box and outlet box, and not  terminated  in  a  threaded  hub,  a  steel,  or  malleable  iron  nylon  insulated  hub, complete with recessed sealing "O" ring or sealing locknut shall be used.  

Q. Where  conduits  stub  up  in  conduit  space  beneath  switchgear  and  do  not  connect directly  to equipment enclosures, use malleable  iron nylon  insulated ground bushing with a lay‐in lug design complete with bonding screw, Raco 1212‐1296.  

R. Provide  seal‐off  fitting  in  all  conduits  entering  hazardous  areas  and  any  conduits entering a cold temperature area such as freezers and dry refrigerators.  

S. In  concrete  slabs,  block  up  conduit  from  forms  and  securely  fasten  in  place.    All conduits  in slabs shall have a minimum of 1‐1/2 inches concrete coverage above and below. 

Page 255: Standard Water and Sewer Specifications PDF

  RACEWAYS AND CONDUIT SYSTEMS  16109‐5 

 T. Encase in 4 inches of 1:2:4 mix concrete on all sides for all feeder conduits laid below 

ground outside building foundation line.  

U. Where conduits running overhead pass through building expansion joints, they shall be connected by flexible metal conduit of same size with sufficient slack to allow conduits on  either  side  of  expansion  joint  to move  a  minimum  of  3  inches  in  any  direction.  Provide  supports  as  required on each  side of expansion  joint,  all  in  accordance with seismic requirements of specific area.  

V. Vertical  runs  of  emergency  system  feeder  conduit  shall  be  installed  in  a  2‐hour enclosure in accordance with applicable high rise codes.  

W. Conduits for feeders and branch circuits shall be terminated directly  into paperboard enclosure without the use of pull boxes, junction boxes, wireways, or auxiliary gutters, unless  the  paperboard  enclosure  does  not  provide  sufficient  surface  area  for  all conduits.  Where such cases exist, the contractor shall notify the Engineer.  In no case will splices in such boxes, wireways, etc., be permitted.  

X. Failure  to  route  conduit  through  building  without  interfering  with  other  equipment and construction shall not constitute a reason for an extra charge. Equipment, conduit, and fixtures shall fit  into available spaces in building and shall not be introduced into building  at  such  times  and  manner  as  to  cause  damage  to  structure.    Equipment requiring servicing shall be readily accessible. 

 3.02  EMT  

Do not use electric metallic tubing in cinder concrete or cinder fill where subject to permanent moisture unless protected on all sides by a layer of non‐cinder concrete at least 2 inches thick or unless the EMT is at least 18 inches under the fill.  Use of set‐screw fitting is not acceptable in concrete or in fill under slab. 

 3.03  PVC  

A. Use threaded fittings for all connectors and adapters.  

B. Provide code sized ground conductors in all power conduit runs.  

C. Provide 1/4‐inch nylon pull rope in all primary power and incoming telephone service entrance conduits. 

 D. Encase all PVC conduit  in reinforced concrete with a minimum of 4‐inch encasement 

on all sides except exterior branch circuits.  

Page 256: Standard Water and Sewer Specifications PDF

  RACEWAYS AND CONDUIT SYSTEMS  16109‐6 

E. No PVC shall emerge from the ground or the concrete slab or encasement.  PVC shall convert to galvanized rigid metal prior to its emergence. 

 F. Make bends with standard ells or with an approved heat bender.  

 3.04  FLEXIBLE METAL CONDUIT  

A. Flexible metal conduits shall be ½‐inch minimum size.  

B. Where  fittings  for  liquid  tight  flexible  conduit  are  brought  into  an  enclosure  with  a knock‐out,  a  gasket  assembly,  consisting  of  one  piece  "O"  ring, with  Buna‐N  sealing material  shall be used.    Fittings  shall be made of either  steel or malleable  iron only, and shall have insulated throats or insulated bushings. 

 C. In dry locations, where final connections to motors and other equipment may be made 

with  flexible  metal  conduit,  fittings  shall  be  of  steel  or  malleable  iron  only  with insulated throats or insulated bushings, and shall be of wedge and screw type having an angular wedge fitting between convolutions of conduit. 

 D. An  additional  copper  ground  wire  shall  be  installed  inside  of  flexible  conduit  and 

bonded at each end  to assure continuity of ground  to  lighting  fixtures,  controls, and other utilization equipment. 

 E. All  recessed  lighting  fixtures  shall  be  connected  with  flexible  metallic  conduit  from 

outlet box to fixture.  Rigid conduit connections to lighting fixtures are not acceptable.  

F. Install liquid tight flexible conduit in such a manner as to prevent liquids from running on the surface toward fittings. 

 G. Allow sufficient slack conduit to reduce the effect of vibration. 

 END OF SECTION 

TABLE OF CONTENTS

Page 257: Standard Water and Sewer Specifications PDF

  CONDUCTORS – CONTROLS AND INSTRUMENTATION  16119‐1 

SECTION 16119  

CONDUCTORS – CONTROLS AND INSTRUMENTATION  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All work specified in this section shall comply with the provisions of Section 16010.  

B. Provide a complete system of conductors for sensing devices, transducers, and various control components as required by the control system. 

 C. All  conductors  shall  be  continuous  from  origin  to  equipment  terminations  without 

splices where possible.  Where splices are required, they shall be made in splice boxes with suitable connectors. 

 D. Refer to drawings for sizes and number of conductors. 

  PART 2 ‐ PRODUCTS  2.01  CONDUCTORS – CONTROLS  

A. Class B stranded soft‐drawn copper with 600 volt thermoplastic insulation.  

B. Size 14 AWG.  

C. Type THHN/THWN.  2.02  CONDUCTORS – INSTRUMENTATION  

A. Class  B  concentrically  stranded  copper  with  300  volt  PVC  insulation  rated  for  105 degrees C. 

 B. Single twisted pair or triad shielded cables as required. 

 C. Overall foil shield with stranded, tinned copper drain wire. 

 D. Separate communication wire for calibration. 

 E. Size 18 AWG. 

 

Page 258: Standard Water and Sewer Specifications PDF

  CONDUCTORS – CONTROLS AND INSTRUMENTATION  16119‐2 

F. Temperature rating:  90 degrees C.  2.03  CONDUCTORS – THERMOCOUPLE  

A. Solid thermocouple extension wire with PVC insulation (nominal 15 mils) rated for 105 degrees C. 

 B. Color coded per ANSI ‐ MC96.1 ‐ 1982. 

 C. Single twisted pair, one conductor identified, with overall aluminum/mylar shield with 

a tinned copper drain wire.  

D. PVC insulated copper communications wire.  

E. Size 16 AWG for runs over 100 feet ‐ otherwise 20 AWG.  

F. Temperature rating:  90 degrees C.  

G. Thermocouple  extension  wire  metals  shall  match  the  metals  used  in  the thermocouples. 

 2.04  ACCEPTABLE MANUFACTURERS AND TYPES  

A. Use Anixter or approved equal.  

B. Control Wiring:  Anixter #6G‐1401.  

C. Instrumentation:  Twisted Pair ‐ Anixter #323‐221‐1801.  

D. Instrumentation:  Twisted Triad ‐ Anixter #323‐321‐1801.  

E. Thermocouple Extension:  Anixter #327‐221‐2001 or ‐1601 series.   PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Install pull boxes in circuits or feeders over 100 feet long.  

B. Make all splices or connections only at outlet, pull or junction boxes.  

C. Use powdered soapstone or pulling compound to pull conductors.  

D. Deliver all conductors to job site new and in original wrapping, package or reel. 

Page 259: Standard Water and Sewer Specifications PDF

  CONDUCTORS – CONTROLS AND INSTRUMENTATION  16119‐3 

 E. All conductors and connections shall test free of grounds, shorts and opens. 

 F. Prior  to  pulling  conductor,  Contractor  shall  verify  that  thermocouple  wire  is 

compatible to the devices served.  

END OF SECTION  

TABLE OF CONTENTS

Page 260: Standard Water and Sewer Specifications PDF
Page 261: Standard Water and Sewer Specifications PDF

  CONDUCTORS (600 VOLT AND BELOW)  16120‐1 

SECTION 16120  

CONDUCTORS (600 VOLT AND BELOW)  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

Provide a complete system of conductors for lighting, power, fire alarm systems, and communication systems throughout the project. 

  PART 2 ‐ PRODUCTS  2.01  MATERIALS  

A. All conductors to be 98 percent conductivity copper with 600‐volt minimum insulation.  

B. All interior conductors to have type THWN or THHN insulation.  

C. 600‐volt insulation for conductors installed in underground raceways shall have XLP (cross‐linked polyethylene) insulation/jacket. 

 D. Conductors size #12 feeding interior lights and receptacles shall be solid.  All other 

interior conductors shall be stranded.  

E. Feeders between variable frequency drivers and inverter driven motors will be shielded copper conductor designed for this duty.  Conductor will be a three‐conductor cable with over all jacket.  A ground conductor will be provided for and close‐coupled to the phase conductor. Conductor to be equal to Belden variable frequency drive cable, symmetrical design with XLPE insulation. 

  PART 3 ‐ EXECUTION  3.01  Install pull boxes in circuits or feeders over 100 feet long or as shown on the plan sheets.  3.02  Make all splices or connections only at outlet or junction boxes. 

END OF SECTION 

TABLE OF CONTENTS 

Page 262: Standard Water and Sewer Specifications PDF
Page 263: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE CABLE TERMINATIONS   16127‐1 

SECTION 16127  

MEDIUM VOLTAGE CABLE TERMINATIONS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All work specified in this section shall comply with the provisions of Section 16010.  

B. Provide  a  complete  system  of  cable  terminations  for  medium  voltage  power  as indicated on the drawings. 

 C. Refer to drawings for sizes of conductors. 

 D. This  section  governs  the  installation  of  cable  stress  cones,  load  break  elbows,  dead 

front "T's", and Electra.   PART 2 ‐ PRODUCTS  2.01  STRESS CONES  

Live front stress cones shall be 3M‐7600 Series termination (cold shrink type) with grounding kits.    Rated  5  KV  or  15  KV  as  required.    Raychem  Heat  Shrink  type  of  equal  rating  is  also acceptable. 

 2.02  DEADFRONT ELBOWS AND CONNECTORS  

A. Applicable Standards:  The 200 Amp Loadbreak and Deadbreak elbow connectors and 630  Amp  Deadbreak  bolted  tee  connectors  purchased  under  this  specification  shall comply with the following standards: 1. ANSI/IEEE  Standard  386:    Separable  Insulated  Connectors  for  Power 

Distribution Systems Above 600V. 2. IEEE Standard 592 (Included in the Standard Above):  IEEE Standard for Exposed 

Semiconducting Shields on Premolded High Voltage Cable Joints and Separable Insulated Connectors. 

*ANSI/IEEE 386 ‐ 199  is the proposed revision that  includes new testing to ensure the current carrying capability of the 200 ampere load break separable connectors. 

 B. Service Conditions:   Modular insulated connectors shall be suitable for use under the 

following service conditions: 1. In air, including exposure to direct sunlight. 

Page 264: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE CABLE TERMINATIONS   16127‐2 

2. Intermittently or continuously submerged in water. 3. Environmental temperature between ‐20 degrees C to 65 degrees C. 

 C. Ratings: 

1. Phase to phase voltage = 14.4 KV. 2. Phase to Ground = 8.3 KV. 3. B1L = 95 KV. 4. Current = 200 Amp or 600 Amp as required. 

 D. Manufacturers: 

1. 200 Amp LB Elbow Connector, 15 KV ‐ 36 KV: Cooper LE series, with capacitive test port, or equal. 

2. 200 Amp and 400 Amp DB Elbow Connector, 15 KV ‐ 36 KV: Cooper DE series, with capacitive test port, or equal. 

3. 630  Amp  DB  Bolted  Tee  Connector,  24  KV  ‐  36  KV:  Cooper  DT  series,  with capacitive test port, or equal. 

  PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Install in strict compliance with manufacturer requirements and industry standard.  

B. Ground units as shown on the drawings.  

C. Exercise care to keep units clean and install with neat workmanship.  

D. Test units with cable as set forth in the cable sections. 

END OF SECTION 

TABLE OF CONTENTS 

Page 265: Standard Water and Sewer Specifications PDF

  PANELBOARDS  16134‐1 

SECTION 16134  

PANELBOARDS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Provide circuit breaker type panelboards as indicated on drawings and as specified in this section. 

 B. Refer  to  drawings  for  numbers  of  branch  circuits,  their  ratings,  number  of  poles, 

arrangements, etc.   PART 2 – PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS/EQUIPMENT  

A. Provide  panelboards  by  Square  D,  G.E.,  Siemens,  Cutler‐Hammer,  or  approved substitute.    Square  D  type  designations  are  used  to  indicate  type  and  quality  of panelboards. 

 B. Lighting panelboards for 120/208‐volts, 3‐phase, 4‐wire service shall be Square D type 

NQOD.  

C. Lighting panelboards for 277/480‐volts, 3‐phase, 4‐wire service shall be Square D type NF. 

 D. Power panelboards  for  120/208‐volt,  and 480/277‐volt,  3‐phase,  4‐wire  service  shall 

be Square D I‐Line distribution type.  

E. Lighting  and  power  panelboards  and  their  associated  circuit  breakers  shall  be furnished with  a  short‐circuit  current  rating  greater  than  the  available  fault  current shown on the panel schedules. 

 F. Provide panelboards of circuit breaker, dead‐front safety type, UL labeled and meeting 

all applicable requirements of the National Electrical Manufacturers Association.  

G. Provide panelboards with lugs (both main lugs and branch circuit lugs) suitable and UL approved for aluminum and copper 75 degree C rated conductors. 

 H. Provide shunt trip and GFI breakers where indicated on panel schedule. 

Page 266: Standard Water and Sewer Specifications PDF

  PANELBOARDS  16134‐2 

 I. Provide electrically isolated neutral bars. 

 J. Provide separate ground bars complete with lugs or connectors on bar. 

 K. Provide panel doors equipped with chrome‐plated  locks and catches, all keyed alike.  

Provide two keys for each lock. Provide fronts with adjustable indicating trim clamps.  

L. Provide thermal magnetic circuit breakers that are fully rated and temperature rated for a 40 degree C ambient.   Breakers shall be quick‐make, quick‐break type with trip indication shown by handle position other than ON or OFF and with a common trip on all multi‐pole breakers. 

  PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Ground separate ground bars to panel boxes and to the main service entrance ground bus with a code‐sized grounding conductor installed in the same conduit as the phase and neutral conductors. 

 B. Install all circuits which use a common neutral in accordance with the latest edition of 

the National Electrical Code, Article Nos. 210‐4, 210‐5, 215‐4, and 220‐4d.  Balance all circuits to achieve not greater than 10% unbalanced neutral current in panel feeders. 

 C. Provide  six  circuit  breaker  handle  lock‐on  devices  for  each  lighting  paperboard  for 

installation  by  the  Contractor  on  circuits  as  directed  by  the  Owner  to  prevent unauthorized personnel from turning off circuits to controls, unit heaters, clocks, night lights, etc.  Turn the spare lock‐on devices over to the Owner for his use. 

 D. Provide typed directory cards mounted under plastic on the doors of all panelboards.  

The  directories  shall  indicate  the  type  of  devices  being  served,  including  the  space number or space names in which the devices or fixtures are located. 

 E. Provide  engraved  Bakelite  nameplates  for  all  the  circuit  breakers  in  use  on  power 

panelboards.  Indicate the device, panel, or motor being served with 1/4" high letters.  Provide nameplates without engraving for the spare breakers and/or spaces.   Secure all nameplates to the paperboard trim with two roundhead sheet metal screws. 

 F. Provide  engraved  Bakelite  nameplates  on  the  visible  face  of  all  lighting  and  power 

panels indicating the panel and emergency system branch designation in 3/8" letters.  Secure  the  nameplates  with  a  minimum  of  two  round‐head  sheet  metal  screws.  Normal power nameplates  shall be black and emergency power nameplates  shall be red. 

Page 267: Standard Water and Sewer Specifications PDF

  PANELBOARDS  16134‐3 

 G. Provide  the Owner with  seven  (7)  sets of  final  as‐built drawings  for  the panels  after 

delivery of the panels. 

END OF SECTION 

TABLE OF CONTENTS 

Page 268: Standard Water and Sewer Specifications PDF
Page 269: Standard Water and Sewer Specifications PDF

  CABLE TRAYS  16137‐1 

SECTION 16137  

CABLE TRAYS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All  work  in  this  section  shall  comply  with  the  provisions  of  Section  16010  (General Electrical Provisions). 

 B. Furnish and install a complete cable tray system.  System shall include all straight trays, 

fittings and related support/accessory items as required for a complete installation.  

C. Use: 1. Exposed six feet above finished grade. 2. Where shown on the plan sheets. 3. In dry locations, not exposed to dirty atmospheres. 4. Cable tray shall not be used where exposed to physical damage. 

 D. Standards: 

1. The cable tray shall conform to NEMA Standard VE‐1.  The tray installation shall be in conformance with the National Electric Code. 

2. If used as an equipment grounding conductor, the tray shall be as classified by Underwriters Laboratories and rated in accordance with NEC Table 318‐10. 

  PART 2 – PRODUCTS  2.01  RACEWAY TYPE  

A. Tray Type: 1. Trays shall be of the ladder, trough, solid bottom or channel type as indicated 

on the drawings. 2. Ladder Type Tray: 

a) Shall  have  required  rung  spacing  to  ensure  adequate  cable  bearing surface for the installed conductors. 

b) Rungs shall be of the double rung or box type and shall be free of sharp edges or corners. 

c) Rungs  shall  be  capable  of  supporting  a  200  lb.  concentrated  load (applied  to  the  middle  six  inches  of  width)  without  permanent deformation. 

3. Trough Type Tray: 

Page 270: Standard Water and Sewer Specifications PDF

  CABLE TRAYS  16137‐2 

a) Shall be of the closely‐spaced rung type (less than four inches apart) to allow  for  simple entry/exit of wires and cables  through  the bottom of the tray without the need of special bushing or adaptors. 

b) Trough bottoms  shall be  capable of  supporting a 200‐lb.  concentrated load without permanent deformation. 

4. Solid Bottom Type Tray: a) Shall offer no openings at all in the bottom of the tray. b) The solid bottoms shall be of flat sheet or corrugated construction. c) Solid (flat) covers shall be provided when installed outdoors. 

5. Channel  Type  Tray:    Shall  be  of  one‐piece  construction  with  ventilation openings in bottom of tray.  

 2.02  MATERIALS/FINISH  

Steel trays are to be fabricated from carbon steel per ASTM A‐569, A‐366 or A‐526.  Finish to be Hot Dip Galvanized after fabrication per ASTM A123‐84. 

 2.03  STRENGTH  

The cable tray shall be capable of carrying a uniformly distributed cable  load as required on the drawings. 

 2.04  DIMENSIONS  

Cable tray shall be 3‐5/8”, 4‐5/8” or 6” in overall height with an interior cable loading depth of 3”, 4” or 5‐3/8”.  Widths shall be as shown on project drawings. 

  PART 3 ‐ EXECUTION  3.01  CONSTRUCTION  

Tray shall be of all‐welded construction and utilize "C" shaped channel side rails with flanges facing inward. 

 3.02  SUPPORTS  

Installer shall supply all clamps, clips and associated parts for a complete support system.  3.03  FITTINGS  

All elbows, tees and cross fittings shall be supplied without straight tangents beyond the point of curvature.  Fittings shall be supplied in 36‐inch radius. 

 

Page 271: Standard Water and Sewer Specifications PDF

  CABLE TRAYS  16137‐3 

3.04  ACCESSORIES  

Cable tray system shall  include all  related accessory  items such as dropouts, end plates and barrier strips to separate services in the trays.  Covers shall be furnished as required for cable protection (e.g., for vertical, riser trays as they penetrate floors, etc.). 

 3.05  INSTALLATION  

A. The  straight  sections  of  cable  tray  shall  be  furnished  in  12‐foot  lengths.    Shorter lengths  shall  be  field‐cut  and  spliced  using  the  standard  cable  tray  splice  plate  as  a drilling jig (24‐ft. lengths shall be used for long‐span support applications). 

 B. Make bends or offsets with standard ells where possible. 

 C. Secure  conduits  to  cable  tray  with  double  locknuts  and  bushings  so  system will  be 

electrically continuous.  See Supporting Devices and Hangers Section 16190.  

D. Complete all raceway systems before installing conductors.  

E. Install a continuous raceway ground in back run of cable tray.  Size per NEC. 

END OF SECTION 

TABLE OF CONTENTS 

Page 272: Standard Water and Sewer Specifications PDF
Page 273: Standard Water and Sewer Specifications PDF

  VARIABLE FREQUENCY DRIVES  16162‐1 

SECTION 16162  

VARIABLE FREQUENCY DRIVES  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1. WORK INCLUDED  

This  section  provides  specification  requirements  for  AC  inverter  type  adjustable  frequency, variable speed drives or herein  identified as AC drives  for use with NEMA A or B design, AC motors. 

 1.02  QUALITY ASSURANCE  

A. The AC drive and all options shall be UL  listed according to Electric  Industrial Control Equipment Specification UL 508C.   A UL label shall be attached  inside each enclosure as verification. 

B. The AC drive shall be designed, constructed and tested in accordance with NEMA, NEC, VDE, IEC standards and CSA certified. 

 C. The manufacturer of the AC drive shall be a certified ISO 9002 facility. 

 D. The AC drive manufacturer shall offer 24 hour a day product and application response 

via a nationwide network of factory certified technical support personnel.  1.03  WARRANTY  

A manufacturer's warranty shall be provided on all materials and workmanship of no less than one year from the date of start‐up. 

  PART 2 ‐ PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  

A. Allen Bradley  

B. Cutler Hammer  

C. Square D  

D. General Electric  

Page 274: Standard Water and Sewer Specifications PDF

  VARIABLE FREQUENCY DRIVES  16162‐2 

2.02  EQUIPMENT GUIDE SPECIFICATIONS  

A. Drives to conform to the following requirements 1. Drive  to  be  of  the  Pulse Width Modulation  Type  (PWM)  rated  for  the  horse 

power or full load current of the driven equipment. 2. Drives to be voltage source type. 3. Standard  applications  will  require  6  pulse  input  rectifiers  with  3%  input  line 

reactor, one per phase. 4. Harmonic  critical  applications  will  require  18  pulse  input  rectifier  without 

reactor. 5. Motors located further than 25 feet from the VFD will require output filters to 

the motors or as required by the manufacturer. 6. Motors located further than 100 feet from the VFD will require output isolation 

transformers  between  the  motors  and  drive  or  as  required  by  the manufacturer. 

 B. Use  only  inverter  rated motors  in  VFD  applications  unless  the  drives  are  specifically 

designed for a specific application by the vendor.  

C. Torque rating to be 150 % of the driven equipment.  

D. Enclosure: 1. Indoor: NEMA 1A (NEMA 1 with Gasket) 2. Outdoor: NEMA 3R 3. Paint with ANSI 61 Light Gray 4. May be included within a Motor Control Center Section 

 2.03  CONTROL  

A. External  pilot  devices  shall  be  able  to  be  connected  to  a  terminal  strip  for starting/stopping  the  AC  drive,  speed  control  and  displaying  operating  status.    All control inputs and outputs will be software assignable. 

 B. 2‐wire or 3‐wire control strategy shall be defined within the software.  External relays 

or logic devices will not be allowed.  

C. The  internal power supply  incorporates an automatic current  fold‐back  that protects the  internal  power  supply  if  incorrectly  connected  or  shorted.    The  transistor  logic outputs  will  be  current  limited  and  not  be  damaged  if  shorted  or  excess  current  is pulled. 

 D. All logic connections shall be furnished on pull‐apart terminal strips. 

 

Page 275: Standard Water and Sewer Specifications PDF

  VARIABLE FREQUENCY DRIVES  16162‐3 

E. There  will  be  two  software  assignable,  analog  inputs.    The  analog  inputs  will  be software selectable and consist of the following configurations:  0‐20 ma, 4‐20 ma, 20‐4 ma, 0‐5V, 1‐5V, or 0‐10V. 

 F. There will be four software assignable,  isolated  logic  inputs that will be selected and 

assigned in the software.  

G. There  will  be  two  software  assignable  analog  outputs  that  can  be  selected  and assigned in the software.  The analog output assignments shall be proportional to the following  motor  characteristics:    frequency,  current,  power,  torque,  voltage  and thermal state.  The output signal will be selectable from 0‐20 ma or 4‐20 ma. 

 H. Two voltage‐free Form C relay output contacts will be provided.  One of the contacts 

will indicate AC drive fault status.  The other contact will be user assignable.  2.04  DRIVE ISOLATION AND BYPASS CONTACTORS  

A. The  AC  drive  shall  include  mechanically  and  electrically  interlocked  isolation  and bypass  contactors  complete  with  Class  20  thermal  overload  relay,  circuit  breaker disconnect,  control  circuit  transformer,  AFC/OFF/BYPASS  switch  and  TEST/NORMAL selector switch. 

 B. The  operator  shall  have  full  control  of  the  bypass  starter  by  operation  of  the 

AFC/OFF/BYPASS selector switch.  

C. In  the AUTOMATIC mode of operation,  the bypass contactors  shall be sequenced by the 110‐volt rated auto start contact provided by the user. 

 D. The  isolation contactor  for  the bypass shall be sequenced to provide motor  isolation 

during a drive ready state of operation.  

E. A TEST/NORMAL selector switch shall provide  test operation of  the power converter while operating the motor in bypass. 

  PART 3 ‐ EXECUTION  3.01  INSPECTION  

A. Verify that the location is ready to receive work and the dimensions are as indicated.  

B. Verify that power is available to the AC drives prior to installation.  

Page 276: Standard Water and Sewer Specifications PDF

  VARIABLE FREQUENCY DRIVES  16162‐4 

3.02  PROTECTION  

Before  and  during  the  installation,  the  AC  drive  equipment  shall  be  protected  from  site contaminants. 

 3.03  INSTALLATION  

A. Installation  shall  be  in  compliance  with  manufacturers’  instructions,  drawings,  and recommendations. 

 B. The AC drive manufacturer shall provide a factory certified technical representative to 

supervise the Contractor's installation, testing and start‐up of the AC drive(s) furnished under this specification for a maximum total of 1 day for each UFD type. 

3.04  TRAINING  

An on‐site training course of two (2) training days shall be provided by a representative of the AC drive manufacturer. 

 3.05  WIRING PRACTICES  

A. Use metallic  conduit  for  all  drive  controller  wiring.    Do  not  run  control  and  power wiring,  or  output  power  wiring  from  more  than  one  drive  controller,  in  the  same conduit. 

 B. Separate metallic conduits carrying power wiring or low‐level control wiring by at least 

3 in. (76 mm).  

C. Separate non‐metallic conduits or cable trays used to carry power wiring from metallic conduit carrying low‐level control wiring by at least 12 in. (305 mm). 

 D. Whenever  power  and  control  wiring  cross,  the  metallic  conduits  and  non‐metallic 

conduits or trays must cross at right angles.  

E. Equip  all  inductive  circuits  near  the  drive  (relays,  contactors,  solenoid  valves)  with noise suppressors or connect them to a separate circuit. 

 F. The  ferrite  core  included  with  the  terminal  block  cover  is  not  required  for  North 

American installations.  

G. For  cable  tray  applications,  use  inverter  duty  rated  feeder  cable  between  drive  and motor. 

END OF SECTION 

TABLE OF CONTENTS 

Page 277: Standard Water and Sewer Specifications PDF

  SUPPORTING DEVICES AND HANGERS  16190‐1 

SECTION 16190  

SUPPORTING DEVICES AND HANGERS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

Provide a system of supporting devices and hangers to ensure secure support or bracing for conduit  and  electrical  equipment,  including  safety  switches,  fixtures,  panelboards,  outlet boxes, junction boxes, cabinets, etc. 

  PART 2 ‐ PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  

A. Provide  appropriate  supporting  devices  and  hangers  as  manufactured  by  Erico Products, Inc., Steel City, Rayco, or approved substitute: 1. Vertical flange clamps (beam clamps). 2. "Z" purlin clips. 3. Conduit clips. 4. Universal clamps (Beam clamps). 5. Beam clamps (set screw type). 6. Combination push‐in conduit clips. 7. Combination conduit hanger clamps. 8. Flexible conduit clips. 9. Special combination conduit clips. 10. One hole steel straps. 11. Minerallac conduit hangers. 

  PART 3 – EXECUTION  3.01  INSTALLATION  

A. Secure conduits to within 3' of each outlet box, junction box, cabinet, fitting, etc., and at  intervals not  to exceed ten  feet  (10')  for EMT and  IMC conduit and  in accordance with the NEC for Rigid Steel conduit.  In seismic zones, support conduits 1" and under at 6' intervals. 

 

Page 278: Standard Water and Sewer Specifications PDF

  SUPPORTING DEVICES AND HANGERS  16190‐2 

B. Install  clamps  secured  to  structure  for  feeder and other  conduits  routed against  the structure.  Use drop rods and hangers or racks to support conduits run apart from the structure. 

 C. Furnish  and  install  suitable  angle  iron,  channel  iron  or  steel  metal  framing  with 

accessories  to  support  or  brace  electrical  equipment  including  safety  switches, fixtures, panelboards, outlet boxes, etc. 

D. Paint  all  supporting  metal  not  otherwise  protected,  with  rust  inhibiting  primer  and then  with  a  finish  coat  if  appropriate  to  match  the  surrounding  metal  surfaces.  (Prepainted or galvanized support material is not required to be painted or repainted.) 

 E. Use of chains, perforated iron, bailing wire, or tie wire for supporting conduit runs will 

not be permitted. 

END OF SECTION 

TABLE OF CONTENTS 

Page 279: Standard Water and Sewer Specifications PDF

  EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  16216‐1 

SECTION 16216  

EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. This  specification  defines  requirements  for  an  emergency  standby  engine/generator system  to  be  installed  as  per  plans  and  specifications.    System  shall  provide  for completely  automatic  unattended  operation,  for  the  duration  of  any  loss  of  normal utility power.  System shall be capable of reaching operating range within 10 seconds of  initial  start  signal  (NFPA  99,  Chapter  3).    Unit  shall  be  of  a  continuous  standby KW/KVA capacity as required. 

 B. Full  service  responsibility  for  satisfactory  operation  and  performance  of  this  system 

shall  rest  with  Division  16  contractor  supplying  the  emergency  power  system.  Engine/generator to be furnished with all necessary features and options to comprise a complete operable system when installed as per manufacturers’ recommendations. 

 C. Unit to meet requirements of NFPA‐99 and NFPA‐110. 

 D. Warranty  to be  furnished on all  equipment  covered by  specifications  for a period of 

one  (1)  year  from date of Owner's  acceptance of  equipment.   Warranty  to  cover  all components and consist of repair and/or replacement of all parts judged defective due to faulty material or workmanship, at no charge to the Owner. 

 E. Unit to be equipped for indoor or outdoor installation as required. 

  PART 2 – PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS/EQUIPMENT  

A. Caterpillar  

B. Cummins  

C. Kohler  

Page 280: Standard Water and Sewer Specifications PDF

  EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  16216‐2 

2.02  ENGINE  

Engine shall be full diesel, compression ignition, liquid‐cooled, domestically manufactured and capable of producing the rated KW at a governed speed of 1800 rpm as specified under  job site  conditions.    Engine  to  be  equipped  with  electric  starting,  battery  charging  generator, electronic governor, fuel filters, oil  filters, air cleaners, cooling system, and other equipment to  provide  a  complete  operable  system.    Selling  distributor  shall  be  a  factory  authorized distributor of the diesel engine utilized in the standby engine generator system. 

 2.03  COOLING  

Engine shall be cooled by plant mounted radiator with engine driven fan, jacket water pump, and fan guard. 

 2.04  OUTDOOR INSTALLATIONS  

A. Complete  engine/generator  and  associated  accessories  shall  be  installed  in  an enclosure for outdoor installation and service.  Enclosure shall be mounted directly to engine/generator base and shall be of sheet steel construction.   Hinged access doors shall  be  provided  for  access  to  control  gear  and  areas  of  unit  requiring  periodic maintenance  and/or  service.    Intake  and  outlet  louvers  shall  be  furnished  to  allow proper  flow  of  cooling  and  combustion  air  with  all  doors  closed,  but  arranged  to prevent entrance of rain. 

 B. Mufflers shall be  installed on enclosure  top  in a horizontal position.   Discharge pipe, 

batteries,  day  tank,  battery  charger,  control  gear  and  water  jacket  heater,  shall  be completely installed, wired and piped prior to delivery to job site. 

 C. All devices requiring AC service (day tank pump, battery charger, water jacket heater, 

battery  heaters,  etc.)  shall  be  connected  to  an  AC  service  panel  installed  inside  the enclosure.  This panel shall be mounted in an accessible location and equipped with a main breaker and branch breakers as required. 

 D. AC wiring  inside enclosure shall be neatly  routed and enclosed  in same type conduit 

used in building.  

E. In  addition  to  the  above  devices,  a  duplex,  grounded,  120‐volt,  weatherproof convenience receptacle shall be provided for maintenance, servicing and lighting.  This receptacle shall be connected to an emergency circuit. 

 2.05  SILENCERS AND BATTERIES  

A. Furnish  and  install  critical  zone  exhaust  silencer.    VEE‐type  engines  shall  have  dual inlet,  single  outlet.    The  silencer  shall  be  as  recommended  by  the manufacturer  for critical  silent  installations.    Condensate  trap,  pet  cock  drain  shall  be  installed  in  the 

Page 281: Standard Water and Sewer Specifications PDF

  EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  16216‐3 

silencer.  A flexible section, 36 inches minimum, shall be provided between the engine exhaust manifold and the silencer.  This section shall be carbon steel bellows type.  All exhaust  system  fittings  shall  be  flanged  n.p.t.  connections.    The  silencer  shall  be provided with mounting brackets for ceiling suspension.  The silencer shall be installed from the equipment room ceiling in a horizontal position. 

 B. Engine/generator manufacturer shall specify exhaust line size required for acceptable 

back pressure.  Exhaust line shall be Schedule 40 pipe and shall be connected to engine manifold  through  seamless,  flexible,  carbon  steel  bellows‐type  connection.    Exhaust systems  installed  inside  structure  shall  be  fully  insulated  and  lines  passing  through walls shall pass through sleeves. 

 C. Provide  starting  batteries  capable  of  starting  unit  in  time  specified  under  installed 

conditions and capable of 60‐seconds of engine cranking.   Batteries to be installed in steel, insulated rack(s). 

 D. Battery heater pads to be furnished on outdoor installations. 

 E. Provide  batteries  of  the  heavy‐duty,  nickel  cadmium  type,  plastic  case,  shipped  dry 

with  electrolyte  installed  at  start‐up.    Battery  cables  to  be  sized  and  provided  by engine/generator vendor. 

 F. Provide  an  automatic  battery  charger.    Charger  shall  operate  on  120‐volt  input  and 

shall be AC line compensated.  Input and output shall be fused.  Charger shall provide continuous taper charging and provide float and equalize function.  Charger shall be in NEMA‐1 cabinet and equipped with DC ammeter, DC voltmeter, high/float switch, and low DC voltage alarm relay.  Minimum continuous DC output shall be 10 amperes. 

 2.06  FUEL TANKS  

A. Day Tank: (Required on units fed from a main tank.) 1. Provide a fuel day tank.  Engine/generator distributor shall specify fuel line size 

between fuel source and tank, as well as day tank to engine.  Day tank shall be of heavy‐duty steel construction, self‐supporting. 

2. Fuel transfer pumps shall be duplex electric motor‐driven, float controlled and capable  of  delivering  fuel  from  source  at  a  rate  of  three  times  full  load  fuel consumption.  Provide check valve on pump inlet to prevent loss of prime. 

3. Provide manual hand pump of a size sufficient  to supply adequate  fuel under manual operation. 

4. In addition to standard fittings, day tank shall also include manual fill cap, fuel level gauge, pump test switch, drain petcock, and  low fuel alarm float switch.  This alarm switch shall operate annunciator "Low Level Supply." 

5. Day tank shall be of sufficient capacity to operate the unit at full  load for not less than 2 hours. 

 

Page 282: Standard Water and Sewer Specifications PDF

  EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  16216‐4 

B. Main Fuel Tank (if required): 1. If  required,  provide  an  above  ground  fuel  storage  tank  as  per  details  on 

drawings.   Tank to bear the Underwriter’s Label and the STI‐P3 Labels and be installed  in  accordance with  applicable  codes  regarding  same.    A pick‐up  line shall be installed to within 8" of tank bottom and equipped with check valve. 

2. Subbase  Fuel  Tank:    Provide  a  subbase  fuel  tank  and  associated  fuel  line connections suitable for 48 hours of operation. 

 2.07  GENERATOR  

A. Alternator  shall  be  four  pole  revolving  field,  twelve  lead,  reconnectable,  one  single bearing, brushless type for units below 2000 KVA.  Larger units will be two bearing.  All generators to be wound to 3/4 pitch. 

 B. Entire  insulation system shall be Class F or better and  temperature  rise  to be within 

NEMA MG‐1‐22.40 for all nameplate voltages at full rated load.  

C. Rotating rectifier shall employ three phase sensing.  Voltage regulation shall be plus or minus  1%  from  no  load  to  full  load  with  steady  state  modulation  of  ½%.    Voltage regulator  shall be  static‐type and a voltage adjusting  rheostat  to be  furnished  in  the control panel.   Voltage change to not exceed 15% upon application of full rated  load with  recovery  to  steady  state  conditions  within  1‐second.    Frequency  regulation  by engine governor to be within 1% steady state with a maximum 2% drop, no load to full load.   Generator/regulator  system  shall  be  capable  of  producing  250% of  a  full  load rated current for a minimum of 10 seconds under a three phase short circuit. 

 D. Provide  a  line  circuit  breaker  on  generator  output,  3‐pole, molded  case;  frame  size 

shall be approximately 125% of full load capacity with trip setting at full load capacity (unless otherwise indicated on plans). 

 E. Provide  ground  fault  sensing  at  the  generator  output  terminals.    This  sensor  shall 

annunciate at the generator‐mounted control panel and remote annunciator.  2.08  GENERATOR CONTROL PANEL  

A. Generator  control  panel  shall  be  NEMA‐1,  dead  front  construction  and  includes following: 1. A.C. ammeter (2%), with phase selector switch. 2. A.C. voltmeter (2%), with phase selector switch. 3. Frequency meter. 4. Elapsed time meter. 5. Panel illumination lamps. 6. Voltage adjusting rheostat. 7. Governor speed control switch. 

Page 283: Standard Water and Sewer Specifications PDF

  EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  16216‐5 

8. Automatic start/stop control (solid state, cycle crank, four cycles of 10‐seconds rest). 

9. Mode selector switch for "off", "manual", "automatic", "test." 10. Automatic engine shutdown with indicating lamps to indicate that a shut‐down 

took place for: a) "excessive engine temperature." b) "low oil pressure." c) "overcrank" (failed to start). d) "overspeed." 

11. Red  lamp  to  function when mode  selector  switch  is  in  a  position  other  than "automatic." 

12. Adjustable timer shall provide up to 30‐minute unload running of engine after automatic  transfer  switch  returns  to  normal.    Factory  to  preset  timer  to  5 minutes unload time. 

13. Engine oil pressure gauge. 14. Engine water temperature gauge. 15. Battery charging ammeter. 16. A sensor device, plus visual warning device with alarm horn and silence switch 

indicating "low  fuel  level",  "low water  temperature" and visual pre‐shutdown alarms for "low oil pressure", "high water temperature", and "ground fault". 

17. Generator  control  panel  shall  be  shock  mounted  on  unit  unless  otherwise shown on drawings. 

 2.09  REMOTE ANNUNCIATOR  

A. Provide solid state remote annunciator panel, storage battery powered, in compliance with /NFPA 99 ‐ 1984, Section 8‐2.3.5//NFPA 110/. 

 B. Panel  shall  be mounted where  shown  on  drawings  to  include  indicating  lamps with 

alarm horn and silence switch for: 1. Low oil pressure pre‐alarm (shutdown). 2. Battery charger malfunction. 3. Low water temperature (warning). 4. Excessive engine temperature (shutdown). 5. Low fuel level (main tank). 6. Overspeed shutdown. 7. Overcrank shutdown (failed to start). 8. Ground fault (warning). 9. Indicating lamps only for generator carrying load and generator running. 10. Red  lamp  to  indicate when mode  selector  switch  is  in  a  position  other  than 

"automatic".   

Page 284: Standard Water and Sewer Specifications PDF

  EMERGENCY STANDBY ENGINE GENERATOR SYSTEM  16216‐6 

PART 3 ‐ EXECUTION  3.01  INSTALLATION REQUIREMENTS  

A. Entire unit shall be installed in accordance with manufacturer’s recommendations.  

B. Mounting:    Complete  engine/generator  and  all  mounted  accessories  shall  be assembled  on  a  common  channel  steel  base.    Fuel  oil  lines  and  lube  oil  drain  shall terminate  in  base.    Lube  oil  drain  line  shall  be  brought  out  to  beyond  the  base  to facilitate  changing  of  the  oil.    Flexible  fuel  line  sections  (18"  long)  shall  be  installed between  base  and  fuel  lines.    Heavy‐duty,  steel  spring  vibration  isolators  shall  be installed between the base and mounting pad.  Isolators shall be sized and located as recommended by generator manufacturer. 

 C. Contractor shall provide the services of a factory‐trained engineer for periodic job site 

visits during installation to ensure that the system is being installed in accordance with manufacturer’s recommendations. 

 D. Complete engine/generator system shall be tested after installation to ensure that the 

engine/generator,  automatic  transfer  switch,  alarm  annunciators,  and  all  other equipment function in accordance with the specifications. 

 E. After Owner acceptance, Contractor and/or vendor, shall conduct a minimum 4‐hour 

training  session  in  operation  and  maintenance  for  Owner's  personnel.    After installation,  a  4‐hour  full  load  test  shall  be  conducted  by  the  distributor’s  engineer.  This  test  shall  be  conducted using  available  building  load,  plus  temporary  load bank capacity so that full nameplate reading  is utilized during test.   Temporary  load banks shall be  furnished by generator distributor and connected by Division 16 Contractor.  Test data shall be recorded and become a part of the three (3) Owners Manuals to be supplied. 

 F. Contractor shall receive, store, uncrate and temporarily connect resistive type load(s) 

furnished  by  the  generator  supplier  for  full‐load  testing  of  the  system.    After completion  of  this  testing,  the  Contractor  shall  disconnect,  crate  and  load  for shipment, the temporary load banks. 

 G. Ground  the  engine  generator  frame  and  enclosure  using  an  equipment  grounding 

conductor sized in accordance with the NEC.  Do not ground generator neutral. 

END OF SECTION 

TABLE OF CONTENTS 

Page 285: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐1 

SECTION 16252  

UNDERGROUND DUCTS AND UTILITY STRUCTURES  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. This  Section  includes  underground  conduits  and  ducts,  duct  banks,  pull  boxes  and handholes, manholes, and other underground utility structures. 

 B. Products  furnished  but  not  installed  under  this  Section  include  pulling  eyes,  cable 

stanchions,  cable  arms,  and  insulators.    For  each  manhole/handhole,  furnish  1 stanchion for each 30 linear inches (750 mm) of interior floor perimeter.  In addition, furnish 1  arm  for  each  stanchion,  3  insulators  for  each arm,  and a  total  of  3 pulling eyes.  Furnish materials complete with associated fasteners, packaged with protective covering for storage and with identification labels clearly describing contents. 

 1.02  DEFINITIONS  

A. Duct:    Electrical  conduit  and  other  raceway,  either  metallic  or  nonmetallic,  used underground, embedded in earth or concrete. 

 B. Duct Bank:   2 or more conduits or other  raceway  installed underground  in  the same 

trench or concrete envelope.  

C. Manhole:    An  underground  utility  structure,  large  enough  for  a  person  to  enter, connecting with ducts to facilitate installation and maintenance of cables. 

 1.03  SUBMITTALS  

A. Product  data  for  metal  accessories  for  manholes  and  handholes,  conduit  and  duct, duct bank materials, and miscellaneous components. 

 B. Shop  drawings  showing  details  and  design  calculations  for  precast  manholes  and 

handholes,  including  reinforcing  steel.    Stamp  drawings  with  seal  of  registered professional structural engineer. 

 C. Certificate  for  concrete  and  steel  used  in  underground  precast  concrete  utility 

structures, according to ASTM C 858.  

D. Inspection report for factory inspections, according to ASTM C 1037.  

Page 286: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐2 

E. Field  test  reports  indicating  and  interpreting  test  results  relative  to  compliance with performance requirements of "Field Quality Control" Article in Part 3 of this Section. 

 F. Record Documents:    Show  dimensioned  locations  of  underground  ducts,  handholes, 

and manholes.  1.04  QUALITY ASSURANCE  

A. Manufacturer Qualifications:  Firm experienced in manufacturing underground precast concrete utility structures of types and sizes required and similar to those indicated for this Project.  Firm must have a record of successful in‐service performance. 

 B. Comply  with  NFPA‐70  "National  Electrical  Code"  and  ANSI  C2  "National  Electrical 

Safety Code" for components and installation.  

C. Listing  and  Labeling:    Provide  products  specified  in  this  Section  that  are  listed  and labeled. 1. The Terms "Listed" and "Labeled":  As defined in the "National Electrical Code," 

Article 100. 2. Listing  and  Labeling  Agency  Qualifications:    A  "Nationally  Recognized  Testing 

Laboratory" (NRTL) as defined in OSHA Regulation 1910.7.  

D. Coordinate  layout  and  installation  of  ducts  and manholes with  final  arrangement  of other utilities as determined in the field. 

 E. Coordinate  elevations  of  duct  and  duct  bank  entrances  into  manholes  with  final 

profiles  of  conduits  as  determined  by  coordination  with  other  utilities  and underground  obstructions.    Revise  locations  and  elevations  from  those  indicated  as required  to  suit  field  conditions  and  ensure  duct  runs  drain  to  manholes  and handholes, and as approved by the Engineer. 

 1.05  DELIVERY, STORAGE AND HANDLING  

A. Deliver  ducts  to  site  with  ends  capped.    Store  nonmetallic  ducts  with  supports  to prevent bending, warping, and deforming. 

 B. Store  precast  concrete  units  at  site  as  recommended  by  manufacturer  to  prevent 

physical damage.  Arrange so identification markings are visible.  

C. Lift and support precast concrete units only at designated lifting or supporting points.  

Page 287: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐3 

1.06  EXTRA MATERIALS  

A. Furnish extra materials matching products installed, packaged with protective covering for storage and with identification labels clearly describing contents. 

 B. Furnish extra cable stanchions, support arms, insulators, and associated fasteners each 

in quantities equal to 5 percent of quantities installed.   PART 2 – PRODUCTS  2.01  MANUFACTURERS  

C. Manufacturers:  Subject to compliance with requirements, provide specified products by one of the following: 1. Underground Precast Concrete Utility Structures: 

a) Precast Oldcastle. b) Elmhurst‐Chicago Stone Co. c) Utility Vault Co. d) Wausau Concrete Co. 

2. Frames and Covers: a) Campbell Foundry Co. b) McKinley Iron Works, Inc. c) Neenah Foundry Co. 

3. Nonmetallic Ducts: a) Arnco Corp. b) Electri‐Flex Co. c) Spiraduct, Inc. 

 2.02  CONDUIT AND DUCT  

A. PVC, Type EB Conduit:   Rated for use with 90 deg C conductors under all  installation conditions. 

 B. PVC, Schedule 40 Conduit, direct buried without concrete. 

 C. PVC Conduit and Tubing Fittings:  NEMA TC 3. 

 D. Plastic Utilities Duct:  NEMA TC 6. 

 E. Plastic Utilities Duct Fittings:  NEMA TC 9; match to duct type and material. 

 F. Plastic Communication Duct and Fittings:  NEMA TC 10. 

 G. Manufactured Bends:  Not less than 36‐inch (900 mm) radius. 

Page 288: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐4 

 H. Coilable Plastic Duct:  NEMA TC 12. 

 2.03  PULL BOXES  

A. Cast  Metal  Boxes:    Cast  aluminum,  sized  as  indicated,  with  outside  flanges  and recessed, gasketed cover for flush mounting.  Nonskid finish on cover. 

 B. Cover Legend:  ELECTRIC. 

 2.04  UNDERGROUND PRECAST CONCRETE UTILITY STRUCTURES  

A. Precast Units:  Interlocking, mating sections, complete with accessory items, hardware, and features as indicated.  Include concrete knockout panels for conduit entrance and sleeve for ground rod. 

 B. Design structure according to ASTM C 858. 

 C. Structural Design Loading:  ASTM C 857, Class A‐16. 

 D. Fabricate according to ASTM C 858. 

 E. Joint  Sealant:    Continuous  extrusion  of  asphaltic  butyl  material  with  adhesion, 

cohesion,  flexibility,  and  durability  properties  necessary  to  withstand  the maximum hydrostatic pressures at the installation location with the ground water level at grade. 

 F. Source Quality Control:  Inspect structures according to ASTM C 1037. 

 2.05  ACCESSORIES  

A. Duct  Supports:    Rigid  PVC  spacers  selected  to  provide  minimum  duct  spacings  and concrete cover depths indicated, while supporting ducts during concreting. 

 B. Frames and Covers:   Cast  iron with cast‐in  legend ELECTRIC as appropriate.   Machine 

cover‐to‐frame bearing surfaces.  

C. Sump Frame and Grate:   Comply with FS RR‐F‐621, Type VII  for  frame and Type  I  for cover. 

 D. Pulling  Eyes  in Walls:    Eyebolt with  reinforcing bar  fastening  insert.    2‐inch  (50 mm) 

diameter eye, 1‐inch (25 mm) by 4‐inch (100 mm) bolt.  Working load embedded in 6‐inch (150 mm), 4000 psi (27.6 MPa) concrete:  13,000 pounds minimum tension. 

 E. Pulling and Lifting  Irons  in Floor:   7/8‐inch‐diameter  (21 mm), hot‐dipped galvanized, 

bent steel rod, stress relieved after forming, and fastened to reinforced rod.  Exposed 

Page 289: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐5 

triangular opening.  Ultimate yield strength:  40,000 pounds shear and 60,000 pounds tension. 

 F. Bolting  Inserts  for  Cable  Stanchions:    Flared,  threaded  inserts  of  non‐corrosive, 

chemical  resistant,  nonconductive  thermoplastic  material;  ½‐inch  (12  mm)  internal diameter  by  2‐3/4  inches  (68 mm)  deep,  flared  to  1‐1/4  inch  (30 mm) minimum  at base.  Tested ultimate pull‐out strength:  12,000 pounds minimum. 

 G. Expansion  Anchors  for  Installation  After  Concrete  is  Cast:    Zinc‐plated  carbon  steel 

wedge  type with  stainless‐steel  expander  clip ½‐inch  (12 mm) bolt  size,  5300‐pound rated pull‐out strength, and 6800‐pound rated shear strength minimum. 

 H. Cable Stanchions:   Hot‐rolled, hot‐dipped galvanized "T" section steel, 2‐1/4‐inch  (56 

mm)  size,  punched  with  14  holes  on  1‐1/2‐inch  (35  mm)  centers  for  cable  arm attachment. 

 I. Cable  Arms:    3/16‐inch  (5  mm)  thick  hot‐rolled,  hot‐dipped  galvanized  sheet  steel 

pressed to channel shape, approximately 12 inches (300 mm) wide by 14 inches (350 mm) long and arranged for secure mounting in horizontal position at any position on cable stanchions. 

 J. Cable Support Insulators:  High glaze, wet‐process porcelain arranged for mounting on 

cable arms.  

K. Ground  Rods:    Solid  copper  clad  steel,  3/4‐inch  (18 mm)  diameter  by  10‐feet  (3 m) length. 

 L. Ground Wire:  Stranded bare copper, No. 6 AWG minimum. 

 M. Duct Sealing Compound:  Non‐hardening, safe for human skin contact, not deleterious 

to  cable  insulation,  workable  at  temperatures  as  low  as  35  degrees  F  (1  degree  C), withstands temperature of 300 degrees F (149 degrees C) without slump, and adheres to  clean  surfaces  of  plastic  ducts,  metallic  conduits,  conduit  coatings,  concrete, masonry,  lead,  cable  sheaths,  cable  jackets,  insulation  materials,  and  the  common metals. 

 2.06  CONSTRUCTION MATERIALS  

A. Brick:  Conform to ASTM C 55, concrete brick Type I, Grade N.  

B. Mortar:  Conform to ASTM C 270, Type M, except for quantities less than 2.0 cu. ft. (60 L), where packaged mix complying with ASTM C 387, Type M may be used. 

 C. Concrete:    Conform  to  Division  3  Section  "Cast‐In‐Place  Concrete"  for  concrete  and 

reinforcing. 

Page 290: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐6 

1. Strength:    3000  psi  (20.7  MPa)  minimum  28‐day  compressive  strength  for ductbanks and 4000 psi (27.6 MPa) minimum 28‐day compressive strength for manholes. 

2. Aggregate For Duct Encasement:  3/8‐inch (10 mm) maximum size.   PART 3 – EXECUTION  3.01  APPLICATION  

A. Underground Ducts for Electrical Utility Service:  Plastic conduit encased in concrete.  

B. Underground  Ducts  for  Cable  Circuits:    Plastic  underground  conduit  encased  in concrete. 

 C. Underground Ducts for Cable Circuits:  PVC, Schedule 40 direct buried. 

 D. Manholes:  Underground precast concrete utility structures. 

 E. Underground Ducts for Site Lighting:  Plastic conduit direct buried. 

 3.02  EXAMINATION  

Examine site  to  receive ducts and manholes  for compliance with  installation  tolerances and other  conditions  affecting  performance  of  the  underground  ducts  and  manholes.    Do  not proceed with installation until unsatisfactory conditions have been corrected. 

 3.03  EARTHWORK  

A. Excavation  and  backfill  in  accordance  with  Section  02221  and  governing  power company. 

 B. Restore  surface  features  at  areas  disturbed  by  excavation,  and  reestablish  original 

grades except as otherwise indicated.  Replace removed sod as soon as possible after backfilling is completed.  Restore all areas disturbed by trenching, storing of dirt, cable laying,  and  other  work.    Restore  vegetation  and  include  necessary  topsoiling, fertilizing, liming, seeding, sodding, sprigging or mulching. 

 C. Restore disturbed paving in accordance with Section 02575 of these specifications. 

 3.04  CONDUIT AND DUCT INSTALLATION  

A. Install nonmetallic conduit and duct as  indicated according to manufacturer's written instructions. 

 

Page 291: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐7 

B. Slope:  Pitch ducts minimum of 4 inches per 100 feet (1:300) to drain toward manholes and  away  from  buildings  and  equipment.    Slope  ducts  from  a  high  point  in  runs between 2 manholes to drain in both directions. 

 C. Curves  and  Bends:    Use  manufactured  elbows  for  stub‐ups  at  equipment  and  at 

building entrances.  Use manufactured long sweep bends with a minimum radius of 25 feet (7.5 m) both horizontally and vertically at other locations. 

 D. Make  joints  in ducts and fittings watertight according to manufacturer's  instructions.  

Stagger couplings so those of adjacent ducts do not lie in the same plane.  

E. Duct Entrances  to Manholes:   Space end bells approximately 10  inches  (250 mm) on center  for  5‐inch  (125  mm)  ducts  and  varied  proportionately  for  other  duct  sizes.  Change  from  regular  spacing  to  end‐bell  spacing  10  feet  (3  m)  from  the  end  bell without  reducing duct  line  slope  and without  forming  a  trap  in  the  line.   Grout  end bells into manhole walls from both sides to provide watertight entrances. 

 F. Building  Entrances:    Transition  from  underground  duct  to  conduit  10  feet  (3  m) 

minimum  outside  the  building  wall.    Use  fittings  manufactured  for  this  purpose.  Follow appropriate installation instructions below. 1. Concrete‐Encased  Ducts:    Install  reinforcing  in  duct  banks  passing  through 

disturbed  earth  near  buildings  and  other  excavations.    Coordinate  duct  bank with structural design to support duct bank at wall without reducing structural or watertight integrity of building wall. 

2. Waterproofed Wall and Floor Entrances:    Install a watertight entrance‐sealing device  with  the  sealing  gland  assembly  on  the  inside.    Anchor  device  into masonry  construction  with  1  or  more  integral  flanges.    Secure  membrane waterproofing to the device to make permanently watertight. 

 G. Concrete‐Encased Nonmetallic Ducts:  Support on plastic separators coordinated with 

duct size and required duct spacing, and install according to the following: 1. Separator  Installation:   Space separators close enough to prevent sagging and 

deforming of ducts, and secure separators to the earth and to ducts to prevent floating during concreting.   Do not use tie wires or  reinforcing steel  that may form conductive or magnetic loops around ducts or duct groups. 

2. Concreting:  Spade concrete carefully during pours to prevent voids under and between  conduits  and  at  exterior  surface  of  envelope.    Do  not  use  power‐driven  agitating  equipment  unless  specifically  designed  for  duct  bank application.    Pour  each  run  of  envelope  between  manholes  or  other terminations  in  1  continuous  operation.    When  more  than  one  pour  is necessary, terminate each pour in a vertical plane and install 3/4‐inch (18 mm) reinforcing rod dowels extending 18 inches (450 mm) into the concrete on both sides of joint near the corners of the envelope. 

3. Reinforcing:    Reinforce  duct  banks  where  they  cross  disturbed  earth  i.e., roadways and sidewalks where indicated on Drawings. 

Page 292: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐8 

4. Forms:    Use  the walls  of  the  trench  to  form  the  side walls  of  the  duct  bank where the soil is self‐supporting and concrete envelope can be poured without soil inclusions, otherwise, use forms. 

5. Minimum  Clearances  Between  Ducts:    3  inches  (75 mm)  between  ducts  and exterior envelope wall, 2 inches (50 mm) between ducts for like services, and 4 inches (100 mm) between power and signal ducts. 

6. Depth:    Except  as  otherwise  indicated,  install  top  of  duct  bank  at  least    30 inches (750 mm) below finished grade. 

7. Ladder:   Manhole  ladder  shall  not  be  a permanent  fixture;  it  shall  be  a hook type ladder extended to bottom of structure. 

 H. Stub‐Ups:   Use rigid steel conduit or  IMC for stub‐ups to equipment.   For equipment 

mounted on outdoor concrete pads, extend steel conduit a minimum of 5 feet (1.5 m) from edge of pad.    Install  insulated grounding bushings on the  terminations.   Couple steel conduits  to  the ducts with adapters designed for  this purpose and then encase coupling with 3 inches (75 mm) of concrete. 

 I. Sealing:  Provide temporary closure at terminations of ducts that are wired under this 

Project.    Seal  spare  ducts  at  terminations.    Use  sealing  compound  and  plugs  to withstand at least 15 psi (1.03 MPa) hydrostatic pressure. 

 J. Pulling Cord:  Install 100‐pound‐test nylon cord in ducts, including spares. 

 3.05  UNDERGROUND UTILITY STRUCTURE INSTALLATION  

A. Elevation:    Install manholes with roof top at least 15 inches (375 mm) below finished grade. 

 B. Manhole depth shall be 7'‐0" unless specified otherwise. 

 C. Drainage:    Install  drains  in  bottom  of  units where  indicated.    Arrange  to  coordinate 

with drainage provisions indicated or specified.  

D. Access:  Install cast‐iron frame and cover.  For manholes, use 30‐inch (750 mm) cover offset to the end as close as possible except as indicated.  Use 30‐inch (750 mm) cover for handholes, except use 24‐inch  (600 mm) covers  for 24‐inch  (600 mm) by 24‐inch (600 mm) handholes.   Install brick chimney to support frame and cover and to connect cover  with  roof  opening.    Provide  moisture‐tight  masonry  joints  and  waterproof grouting  for cast‐iron  frame to chimney.    Set  frames  in paved areas and  traffic ways flush with finished grade.  Set other frames 1 inch (25 mm) above finished grade. 

 E. Waterproofing:   Apply waterproofing  to exterior  surfaces of units after  concrete has 

cured  at  least  3  days.    After  ducts  have  been  connected  and  grouted,  and  prior  to backfilling,  waterproof  joints  and  connections  and  touch  up  abrasions  and  scars.  

Page 293: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐9 

Waterproof  exterior  of manhole/handhole  chimneys  after  brick mortar  has  cured  at least 3 days. 

 F. Hardware:  Install removable hardware, including pulling eyes, cable stanchions, cable 

arms, and insulators, as required for installation and support of cable and conductors and as indicated. 

 G. Field‐Installed  Bolting  Anchors:    Do  not  drill  deeper  than  3‐7/8  inches  (96  mm)  for 

anchor  bolts  installed  in  the  field.    Use  a  minimum  of  2  anchors  for  each  cable stanchion. 

 H. Grounding:    Install  ground  rod  through  floor  in each structure with  top protruding 4 

inches  (100 mm) above floor.   Seal  the  floor opening against water penetration with waterproof non‐shrink grout.  Ground exposed metal components and hardware with bare  copper  ground  conductor.    Train  conductors  neatly  around  corners.    Install  on walls and roof using cable clamps secured with expansion anchors. 

 I. Precast Concrete Underground Structure Installation:  Install as indicated, according to 

manufacturer's written instructions and ASTM C 891. 1. Install units plumb and level and with orientation and depth coordinated with 

arrangement of  connecting ducts  to minimize bends and deflections  required for proper entrances. 

2. Support units on a level bed of crushed stone or gravel, graded from the 1‐inch (25 mm) sieve to the No. 4 sieve and compacted to same density as adjacent undisturbed earth. 

 3.06  FIELD QUALITY CONTROL  

A. Testing:  Demonstrate capability and compliance with requirements upon completion of installation of underground duct and utility structures. 1. Grounding:  Test manhole grounding to ensure electrical continuity of bonding 

and  grounding  connections.   Measure  ground  resistance  at  each  ground  rod and  report  results.    Use  an  instrument  specifically  designed  for  ground‐resistance measurements. 

2. Duct Integrity:  Rod ducts with a mandrel 1/4 inch (6 mm) smaller in diameter than internal diameter of ducts.  Where rodding indicates obstructions in ducts, remove the obstructions and retest. 

3. Water  Tightness:    Make  internal  inspection  of  manholes  3  months  after completion of construction for  indications of water  ingress.   Where leakage is noted,  remove  water  and  seal  leak  sources.    Re‐inspect  after  2 months  and reseal remaining leak sources.  Repeat process at 2 month intervals until leaks are corrected. 

 B. Correct  installations  where  possible,  and  retest  to  demonstrate  compliance.  

Otherwise, remove and replace defective products and retest. 

Page 294: Standard Water and Sewer Specifications PDF

  UNDERGROUND DUCTS AND UTILITY STRUCTURES   16252‐10 

 3.07  CLEANING  

A. Pull brush through full length of ducts.  Use round bristle brush with a diameter ½ inch (12 mm) greater than internal diameter of duct. 

 B. Clean internal surfaces of manholes including sump.  Remove foreign material. 

END OF SECTION 

TABLE OF CONTENTS 

Page 295: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐1 

SECTION 16260  

UNINTERRUPTIBLE POWER SYSTEM (UPS)  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. The  Uninterruptible  Power  System  shall  be  a  continuous  duty,  bi‐polar,  solid‐state uninterruptible power system, designed to provide emergency power to critical loads.  The  unit  shall  provide  power  conditioning  and  power  distribution  at  all  phases  of operation  even  during  the  emergency  power  mode.    The  system  shall  consist  of  a microprocessor  controlled,  solid  state  inverter,  power  purification  system,  sealed maintenance‐free battery charger, sealed maintenance free batteries, monitor system, accessories and options. 

 B. Modes of Operation:  The UPS shall operate as a fully regulated and conditioned power 

system in the following modes: 1. Normal Mode:   The critical  load shall be continuously supplied with regulated 

output  power  without  battery  backup  power  even  under  extreme  brownout conditions (‐20 percent of nominal).  Line power shall be supplied to the Power Purification  System  and  battery  charger  simultaneously  maintaining  a continuous float charge on the batteries. 

2. Emergency Mode:  Upon failure of the commercial AC power, battery power is transferred through the inverter to the Power Purification System.  There shall be no interruption of regulated and conditioned power to the critical load upon failure of restoration of the commercial AC power. 

3. Bypass Mode (Manual and Internal):  If a problem occurs within the system due to an overload or internal failure, the manual bypass switch shall be activated to connect the commercial AC power to the Power Purification System.  Thus, regulated and conditioned power  is  still  supplied  to  the critical  load until  the problem  is  corrected.    The  bypass  shall  be  internal  to  the  UPS.    System requiring external switchgear shall not be acceptable. 

 C. Recharge:    Upon  restoration  of  the  commercial  AC  power,  a  totally  isolated  and 

regulated battery charger shall recharge the battery automatically at an optimal level for maximum battery life. 

 1.02  REFERENCED STANDARDS  

A. ETL listed to UL 1012 and UL 478 standard.  

B. Meets IEEE‐587 guide for surge withstandability. 

Page 296: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐2 

 C. FCC Article 15, Section J, Class A. 

  PART 2 – PRODUCTS  2.01  UPS equipment shall be as manufactured by Controlled Power Company Series 1000, Model D 

or approved equal.  2.02  GENERAL SPECIFICATIONS  

A. Temperature Rise:   Conservative  transformer magnetic design shall  limit  transformer rise to 120 degrees Celsius or less. 

 B. Ambient Operating Temperature:  ‐10 to +40 degrees Celsius without derating normal 

mode.  

C. Storage Temperature:  ‐20 to +50 degrees Celsius.  

D. Relative Humidity:  95 percent non‐condensing.  

E. Elevation:  5,000 ft. (1500M) without derating.  

F. Audible Noise:  45 dB to 60 dB depending on KW.  

G. Isolation:  Output fully isolated from input, battery and bypass.  

H. Battery Charger:  Fully isolated and regulated.  

I. Power Purification System:  All copper construction.  

J. Inverter Line Sync Range:  +2.5 Hertz.  

K. Slew Rate:  Less than 0.2 Hertz per second.  2.03  INPUT SPECIFICATION  

A. Power Rating: As required at unity P.F.  

B. Input Voltage and Interface: 1. KVA: As required. 2. Input Voltage:  As required. 3. Output Voltage: As required. 

 

Page 297: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐3 

C. Operating  Input  Voltage  Range  (Without  Battery  Consumption):    +15  percent  to  ‐20 percent of nominal.  

D. Input Surge Capability:  Per IEEE 587B.  2.04  OUTPUT SPECIFICATION  

A. Output Voltage Regulation:  The output voltage will not change more than +2 percent under a change of input voltage from 120 percent to 0 percent of nominal rated input. 

 B. Load  Regulation:    The  output  voltage will  not  change more  than  +2  percent with  a 

change in load from 0 percent to 100 percent of rated load.  

C. Harmonic Distortion:  Shall be less than 5 percent THD for 100 percent linear load.  

D. Fault Clearing Capacity:   Will withstand a current surge of 150 percent rated load for 1,000 cycles while maintaining the output voltage to 90 percent of nominal rating. 

 2.05  PERFORMANCE SPECIFICATIONS  

A. Dynamic Voltage Response:  Shall be to +8 percent of nominal voltage for a 10 percent to 100 percent step load within one cycle. 

 B. Dynamic Voltage Recovery:  Shall be five cycles to within +2 percent with load change 

of 0 percent to 100 percent to 10 percent.  

C. Inverter Frequency Regulation:  Shall be +0.5 Hz free running.  

D. Overload Capability:   Will withstand an overload current of 125 percent continuously while maintaining the output voltage to 94 percent of output voltage rating with input at nominal. 

 E. Output Load Configuration:  Full rated KVA can be drawn from any output voltage tap.  

No load balancing shall be required.  

F. Common Mode Noise Attenuation:  Shall be 140 dB.  

G. Transverse Mode Noise Attenuation:  Shall be 120 dB.  

H. Coupling Capacitance:  0.001 pf.  

I. Electrostatic Discharge Withstand Voltage:  25,000 volts.  

J. Input Power Factor:  Is 0.9 lagging at full load and nominal input voltage.  

Page 298: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐4 

K. Efficiency and BTU/HR Emitted:  The following table indicates the minimum efficiency and maximum allowable BTU/HR. 

 

KW  MINIMUM EFFICIENCY MAXIMUM BTU/HR 

EMITTED 

2  85%  1023 

2.5  86%  1193 

3  87%  1466 

3.5  89%  1527 

5  87%  2216 

6  88%  2455 

8  86%  3819 

9.5  87%  4211 

10  85% 5115 

12  87% 5320 

15  89%  5626 

18  90%  6138 

20  90%  6820 

24  90%  8184 

 L. MTBF:  MTBF shall exceed 20,000 hours. 

 2.06  BATTERY SPECIFICATION  

A. Batteries:    Shall  mount  in  a  fully  accessible  rack  assembly  within  the main  cabinet.  Additional battery time is supplied in a matching cabinet and is connected by means of a quick connect connector. 

 B. Battery  Type:    Shall  be  sealed,  starved  electrolyte maintenance  free  lead  acid  cells.  

Battery  support  time  shall  be  provided  by  a  15  minute  battery  pack.    Gelled electrolytes will not be accepted. 

 C. Expected Battery Life:  Shall be five year service life. 

 D. Maintenance  Free:    There  shall  be  no  need  to  check  the  specific  gravity  of  the 

electrolyte or add water.  

E. Minimum Final Discharge Voltage:  Shall be 1.67 volts per cell.  

F. Nominal Float Voltage:  Shall be 2.27 volts per cell.  

G. Operating Temperature: 1. Charge:  ‐15 degrees C to 50 degrees C (5 degrees F to 122 degrees F). 2. Discharge:  ‐5 degrees C to 50 degrees C (‐40 degrees F to 122 degrees F). 

Page 299: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐5 

3. Storage:  ‐5 degrees C to 60 degrees C (‐40 degrees F to 140 degrees F).  

H. Capacity:   The  lead acid battery shall be sized to support the  inverter at rated KW at 0.8 power factor.  

I. Battery  Ventilation:    Batteries  shall  be  provided  with  a  safe  low  pressure  venting system  designed  to  release  excess  gas  and  reseal  automatically  in  the  event  that pressure rises to a level above the normal.  There shall be no excessive build‐up of gas in the batteries.  

J. Battery  Charger:    A  current  limited  and  voltage  regulated  charger  maintains  the batteries  at  full  charge whenever  the  system  is  operating  on  utility  power.    Current limited  to  5,  10 or  20  ampere depending on  charger  option  and not  to  exceed 0.25 battery/amp  hour  rating.    Hysteresis  loop  cycled  battery  chargers  will  not  be permitted.  

K. Battery  Circuit  Breaker:    A  manual  means  of  disconnection  and  protection  against short circuit shall be provided via a molded case thermo‐magnetic breaker.  

L. Battery Recharge Time:  Shall be no greater than 10 times the discharge time to 90% capacity. 

 2.07 SERVICE AND MAINTENANCE  

Shall be designed for ease in servicing.  2.08  SYSTEM DESCRIPTION  

A. Power  Purification  System:    (Regulator  and  Conditioner)  shall  receive  either  utility power (normal mode) or inverter power from the battery, and convert that power to clean well  regulated power  for  the  load.    The output power  shall  be distortion  free, (5% THD) regardless of the harmonic distortion on the input.  Construction shall be all copper, Class H insulation and vacuum impregnated. 

 B. Inverter:  Shall convert the DC battery power to the Power Purification System during 

the normal mode of operation.  

C. Battery Charger:  Shall totally isolate the current and voltage regulated battery charger to charge the batteries at a proper rate to assure maximum battery life. 

 D. Circuit  Breakers:    Input  molded  case  breaker  and  DC  molded  case  breaker  for  the 

battery shall be provided for additional protection.  

Page 300: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐6 

E. Control Circuit:   The control circuit shall  integrate logic for continuous sensing of  line voltage status.  Immediate correcting action shall be instituted if abnormal conditions exist. 

 F. Sentinel Monitor  System:    This monitor  shall  be  standard  on  all  UPS’s,  designed  to 

indicate the system status (refer to detailed description).  2.09  MONITOR SYSTEMS  

A. System Sentinel:  The standard monitor on all UPS’s shall include the following: 1. Line Power Present. 2. Battery Charger. 3. Reserve Battery Power. 4. Conditioned Power Present. 5. Percent Load. 6. Overload. 

 2.10  BATTERY POWER DESCRIPTION  

A. The Battery Power display shall be a 10 LED bar graph.  When in normal operation the top LED will be lit indicating the batteries are charged to the float voltage.  When the unit  switches  to  battery  power  during  a  power  interruption,  the  bar  graph  LED's proportional  to  the  load,  thus  providing  a  visual  indication  of  percent  of  reserve battery.  Shut down will occur when battery voltage reaches preset minimum.  The 10 percent level on the bar graph indicates shut down is imminent. 

 B. Alarm Panel:   The alarm panel  shall provide audible/visual warning of  specified  fault 

conditions.  Two membrane switches shall be located on the membrane panel.  Alarm Silence will silence audible alarm (during a  fault condition or when unit  is on battery power).  Visual alarm (LED's) remain lit until fault is cleared. 

 2.11  MECHANICAL CHARACTERISTICS  

A. Construction:    The  UPS  system  shall  be  housed  in  an  enclosed  metal  cabinet(s) designed  to  conform  to  UL  safety  standards.    Power  input  and  output  to  the  UPS system shall be via junction boxes with input and output cable lugs for hard wiring in lieu of flexible cables and/or receptacles. 

 B. All  cabinets  will  include  casters  for  ease  of  installation  and  mobility  and  include 

appropriate AC and/or DC circuit breakers.  

C. Ambient Operating Temperature:  10 to 40 degrees Celsius without derating.  

D. Storage Temperature:  20 to 50 degrees Celsius, prolonged storage above 50 degrees Celsius will cause battery to deteriorate or discharge. 

Page 301: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐7 

 E. Temperature Rise:   Conservative  transformer magnetic design  limits  transformer rise 

to 120 degrees Celsius or less.  

F. Relative Humidity:  95 percent non‐condensing.  

G. Elevation:  5,000 feet (1500M) without derating.  

H. Audible Noise:  45 dB to 60 dB depending on KVA size of the unit.  

I. Isolation:  Output fully isolated from utility and battery.  

J. Transformer:  All current carrying elements are of electrical grade copper.  2.12  MONITOR SYSTEMS  

A. Standard Monitor:  The standard monitor on all UPS's shall include the following: 1. Line Power:  Green LED. 2. Battery Charger:  Green LED. 3. Conditioner and Regulator ‐ Power Purification System:  Green LED. 4. Overload Condition:  Red LED. 

 2.13  PERCENT LOAD  

The  percent  load  display  shall  be  a  10  segment  bar  graph  providing  visual  indication proportional to the percent of load. 

 2.14  BATTERY POWER  

The Battery Power Display shall be a 10 segment LED bar graph.   When in normal operation the  top LED will be  lit  indicating  the batteries are  charged  to  float  voltage.   When a power interruption occurs  the  LED bar  graph will  provide a  visual  indicator of  the  reserve battery.  Shut down will occur when the battery voltage reaches a pre‐set minimum of 1.67 VPC.  The 10 percent level on the bar graph indicates shut down is imminent. 

 2.15  ALARMS  

A. The alarm panel shall provide audible/visual warning of the following conditions: 1. High temperature. 2. Low battery warning. 3. Battery disabled. 4. On battery power. 5. UPS in bypass. 6. Manual restart required. 

 

Page 302: Standard Water and Sewer Specifications PDF

  UNINTERRUPTIBLE POWER SYSTEM (UPS)  16260‐8 

B. The alarm conditions shall not shut down the UPS.  2.16  SHUT DOWN ANNUNCIATION  

A. Shut down annunciation shall provide audible/visual alarm of the following condition shut downs: 1. Low battery. 2. Remote emergency power off. 3. Data Guard. 4. Overtemperature. 

 2.17  MEMBRANE SWITCHES  

Two membrane switches shall be located on the membrane panel.  2.18  ALARM – SILENCE  

Silence shall silence audible alarm (during a fault condition or when unit is on battery power).  Visual alarm (LED's) shall remain lit until fault is cleared. 

 2.19  MANUAL RESTART  

Will restart the unit if shut down conditions are cleared or reset.   PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Provide flexible conduit to and from UPS cabinet for hardwire installation.  

B. Install UPS unit in accordance with manufacturer’s recommendations.  

C. Provide working clearances as required by NEC.  

D. Ground UPS enclosure with bonding jumper.  

E. Provide both primary and secondary protection by use of fuses or circuit breakers as shown on drawings. 

END OF SECTION 

TABLE OF CONTENTS 

Page 303: Standard Water and Sewer Specifications PDF

  PAD‐MOUNTED TRANSFORMERS  16320‐1 

SECTION 16320  

PAD‐MOUNTED TRANSFORMERS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

This  Section  includes  distribution  transformers  with  medium‐voltage  primaries.    Types  of transformers  specified  in  this  Section  include  pad‐mounted,  liquid‐filled  transformers.  Installation  of  pad‐mounted  transformers  also  includes  construction  of  the  concrete  pad  in accordance with the requirements and standard details of the governing power company. 

 1.02  DEFINITIONS  

A. Listed:  As defined in the "National Electrical Code," Article 100.  

B. Nationally Recognized Testing Laboratory (NRTL):  A testing agency qualified as defined in OSHA Regulation 1910.7. 

 1.03  QUALITY ASSURANCE  

A. Installer Qualifications:   Engage an experienced Installer of medium‐voltage electrical distribution equipment to perform the installation specified in this Section. 

 B. Field Testing Agency Qualifications:  To qualify for acceptance, the testing agency must 

demonstrate,  based on evaluation of  agency‐submitted  criteria  conforming  to ASTM E 699,  that  it  has  the  experience  and  capability  to  satisfactorily  conduct  the  testing indicated. 

 C. Comply with NFPA 70 "National Electrical Code." 

 D. Comply with IEEE C2 "National Electrical Safety Code." 

  PART 2 – PRODUCTS  2.01  MANUFACTURERS  

A. Manufacturers:  Subject to compliance with requirements, provide products by one of the following: 1. General Electric Company 2. ABB Power T & D Co., Inc. 

Page 304: Standard Water and Sewer Specifications PDF

  PAD‐MOUNTED TRANSFORMERS  16320‐2 

3. Cooper. 4. Square D Co. 5. Virginia Transformers 

 2.02  TRANSFORMERS – RATINGS  

A. Windings:  Two‐winding type configured as required.  

B. Voltages: Primary and secondary as required.  

C. Rating: In KVA, 3 Phase, 60 Hz to supply the connected load.  

D. Low‐Sound Level Transformers: Units with a sound level rating a minimum of 3 dB less than NEMA TR 1 standard sound levels for the transformer type and rating. 

 E. Windings: Copper. 

 F. Impedance: ANSI C57.12.00 Standard with ± 7.5% tolerance. 

 G. Insulation Temperature Rise:  55/65 degree C rise. 

 H. Basic Impulse Insulation Level (BIL) as follows: 

 Operating Voltage      BIL 480 V          30 KV 5 KV          60 KV 15 KV          95 KV 25 KV          150 KV 

 2.03  TRANSFORMERS – GENERAL  

A. Comply with IEEE C57.12.22 and C57.12.28.  

B. Insulating  Liquid:    Insulating  liquid  shall  be  bio‐degradable,  FR3  or  approved equivalent. 

 C. Full‐Capacity Voltage Taps:  Four nominal 2.5‐percent taps, 2 above and 2 below rated 

high voltage, with externally operable tap changer for de‐energized use, with position indicator. 

 D. High‐Voltage Arrangement:  Dead‐front equipped for radial or loop feed as required.  

 E. Fusing:  Internal Bay‐O‐Net fuses in series with current limiting fuses.  Size to protect 

transformer.  

Page 305: Standard Water and Sewer Specifications PDF

  PAD‐MOUNTED TRANSFORMERS  16320‐3 

F. Surge Arresters:   Distribution class, one for each primary phase.   Comply with NEMA Standard LA 1 "Surge Arresters."  

 G. High‐Voltage  Terminations  and  Equipment:    The  high  voltage  terminations  and 

equipment shall be dead‐front and conform to ANSI C57.12.22 requirements.   

H. 200‐amp, 15‐kV, feed‐through 4‐position switch if required.  

I. 200‐amp, 15‐kV, 2‐position switch if required.  

J. Accessories:  Provide the following accessories: 1. One‐inch (25‐mm) drain valve with sampling device. 2. Dial‐type thermometer. 3. Liquid level gauge. 4. Pressure‐vacuum gauge. 5. Pressure‐Relief Device:  Self‐sealing with indicator. 6. Mounting  provision  for  low‐voltage  current  transformers  and  potential 

transformers.  2.04  FINISHES  

Enclosure  Coating  System  for  Outdoor  Units:    Comply  with  IEEE  Standard  C57.12.28  "Pad‐Mounted Equipment‐Enclosure Integrity," regardless of transformer type. 

 2.05  SOURCE QUALITY CONTROL  

A. Factory Tests:  Design and routine tests conform to the referenced standards.  

B. Factory  Sound‐Level  Tests:    Conduct  sound  level  tests on equipment  for  this  Project where specifying sound levels below the standard ratings. 

  PART 3 – EXECUTION  3.01  INSTALLATION  

A. Comply  with  IEEE  Standard  C2,  "National  Electrical  Safety  Code"  and  the manufacturer's written installation instructions. 

 B. Identify transformers and install warning signs as appropriate. 

 C. Tighten  electrical  connectors  and  terminals  according  to  manufacturer’s  published 

torque‐tightening values.  Where manufacturer’s torque values are not indicated, use those specified in UL 486A and UL 486B. 

 

Page 306: Standard Water and Sewer Specifications PDF

  PAD‐MOUNTED TRANSFORMERS  16320‐4 

3.02  GROUNDING  

Ground  transformers  and  systems  served  by  transformers  according  to  Division  16  Section "Grounding" and as shown on drawings. 

 3.03  FIELD QUALITY CONTROL  

A. Manufacturer's Field Services:  Arrange and pay for the services of a factory‐authorized service representative to supervise the field assembly and connection of components, and the pretesting and adjustment of transformer components and accessories. 

 B. Pretesting:   After completing system  installation, perform the  following preparations 

for tests: 1. Conduct insulation‐resistance tests for transformers. 2. Conduct a continuity test for windings.  3. Provide a set of Contract Drawings to the testing agency. 4. Provide  manufacturer's  installation  and  testing  instructions  to  the  testing 

agency.  

C. Test  Objectives:    To  ensure  transformer  installation  complies  with  Contract Documents,  is  operational  within  industry  and  manufacturer's  tolerances,  and  is suitable for energizing.  

D. Test  Labeling:    Upon  satisfactory  completion  of  tests  for  each  transformer,  attach  a dated and signed "Satisfactory Test" label to the unit.  

E. Schedule  tests  and  provide  notification  at  least  one  week  in  advance  of  test commencement.  

F. Report:  Submit a written report of observations and tests.  Report defective materials and workmanship.  

G. Tests:    Include  the  following  minimum  inspections  and  tests  according  to  the manufacturer's instructions.  For test method and data correction factors, conform to IEEE Standard Test Codes C57.12.90 for liquid‐filled units, and IEEE C57.12.91 for dry‐type units. 1. Inspect  accessible  components  for  cleanliness,  mechanical,  and  electrical 

integrity,  for presence of  damage or deterioration,  and  to ensure  removal  of temporary  shipping bracing.   Do not proceed with  tests until  deficiencies  are corrected. 

2. Inspect bolted electrical connections for tightness according to manufacturer’s published  torque values or, where not available,  those of UL Standards 486A and 486B. 

3. Insulation Resistance:   Perform megohm meter test of primary and secondary winding‐to‐winding and winding‐to‐ground according to the following: 

Page 307: Standard Water and Sewer Specifications PDF

  PAD‐MOUNTED TRANSFORMERS  16320‐5 

WINDING RATING (VOLTS) 

MINIMUM TEST [VOLTS (dc)] 

MINIMUM RESISTANCE DRY 

TYPE 

INSULATION (MEGOHMS) LIQUID FILLED 

0  ‐ 600  1,000  500  100 

5,000 ‐ 35,000  5,000  25,000  5,000 

a) Duration of Each Test:  10 minutes. b) Temperature Correction:  Correct results for test temperature deviation 

from 20 deg C standard. 4. Turns Ratio:  Measure between windings at each tap setting.  Measured ratios 

deviating  more  than  0.5  percent  from  the  calculated  ratio  or  the  measured ratio for adjacent coil are not acceptable. 

5. Winding Resistance:   Measure  for winding at nominal  tap  setting.   Measured resistance deviating more than 1 percent from that of adjacent winding is not acceptable. 

6. Liquid‐Filled  Transformer  Insulation  Power  Factor  Test:    Determine  overall dielectric loss and power factor for winding insulation.  Limit test voltage to the line‐to‐ground voltage of the winding being tested.   

7. Test  Failures:    Compare  test  results  with  specified  performance  or manufacturer's data.  Correct deficiencies identified by tests and retest.  Verify that transformers meet specified requirements. 

 3.04  ADJUSTING  

A. After  completing  installation  and  cleaning,  touch up  scratches  and mars on  finish  to match original finish. 

 B. Adjust  transformer  taps  to  provide  optimum  voltage  conditions  at  utilization 

equipment throughout the normal operating cycle of the facility.  Record voltages and tap settings to submit with test results. 

 3.05  DEMONSTRATION  

A. Training:    Arrange  and  pay  for  the  services  of  a  factory‐authorized  service representative  to demonstrate  transformers and accessories and  train Owner's  staff.  Include a minimum of 8 hours of training in operation and maintenance.  Provide both classroom training and hands‐on equipment operation covering the following: 1. Safety precautions. 2. Features and construction of project transformers and accessories. 3. Routine inspection, test and maintenance procedures. 4. Routine cleaning. 5. Features,  operation,  and  maintenance  of  integral  disconnect  and  protective 

devices. 6. Interpretation of readings of indicating and alarm devices. 7. Fuse selection. 8. Protective relay setting considerations. 

Page 308: Standard Water and Sewer Specifications PDF

  PAD‐MOUNTED TRANSFORMERS  16320‐6 

9. Features, operation and maintenance of separable insulated connector system. 10. Tap‐changing procedures. 

 B. Schedule training with at least 7 days advance notice. 

 3.06  ADDITIONAL EQUIPMENT  

A. Provide lightning arresters on each incoming primary phase.  

B. Provide one spare set of fuses for each type of the internally fused units. 

END OF SECTION 

TABLE OF CONTENTS 

Page 309: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL ENCLOSED SWITCHES  16343‐1 

SECTION 16343  

MEDIUM VOLTAGE METAL ENCLOSED SWITCHES  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All work specified in this section shall comply with the provisions of Section 16010.  

B. The  outdoor  padmounted  gear  shall  consist  of  a  single  self‐supporting  enclosure, containing  three‐phase  gang  operated  interrupter  switches  and  three‐phase  sets  of single  pole  hook  stick  operable  fuses  with  the  necessary  accessory  components,  all completely factory assembled and operationally checked. 

 C. To ensure a completely coordinated design, the switchgear shall be integrally designed 

and produced by the manufacturer of the basic switching equipment.  

D. Certification of Ratings: 1. The  manufacturer  shall  be  completely  and  solely  responsible  for  the 

performance of the basic switch and fuse components as well as the complete integrated padmount gear assembly as rated. 

2. The manufacturer  shall  furnish certification of  ratings of  the basic  switch and fuse components and/or the integrated padmounted gear assembly consisting of  the  switch  and  fuse  components  in  combination with  the  enclosure.    This certification of  the  integrated unit  shall  include  testing  the  switchgear  to  the fault close requirements of the specification to assure the bus support system and components are adequate. 

  PART 2 – PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  

A. Cutler Hammer  

B. S&C  

C. General Electric  2.02  EQUIPMENT GUIDE SPECIFICATIONS  

A. Main Bus will be tin plated non‐insulated bus copper or aluminum. 

Page 310: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL ENCLOSED SWITCHES  16343‐2 

1. Current rating for the switchgear Bus will be calculated on the connected load and any expected future loads.  

2. Electrical  Designer  shall  perform  fault  current  calculations  based  on  utility available  fault  current  and  specify  bracing  to meet  or  exceed  the  calculated value. 

3. For  equipment  that must  be maintained  while  energized,  Electrical  Designer will perform Arc Flash analysis as required by NFPA‐70E or task the Contractor to do so and affix required labels to the face of the enclosure. 

 B. Main  switch  will  be  load  break  switch  fusible  or  non‐fused  as  required  by  the 

application meeting UL and ANSI requirements.  

C. Provide main switch where required by Code 1. Lightning arresters will be provided on the main incoming lines. 

a) Distribution class arresters  rated  for  the operating voltage and system configuration. 

b) Install arresters with adequate clearance from incoming lines. 2. If required, provide revenue grade meter on the main to monitor the following: 

a) Total Demand:  b) Total Usage: KWH c) System Power Factor 

 D. Voltage will be specified to match system requirements. 

1. Ungrounded systems are not allowed. 2. Voltage reference provided by solidly grounded systems is preferred. 3. Absence of a ground reference will be compensated for by providing a high or 

low resistance ground and protective relaying.  

E. Basic Impulse Level (BIL) for the Switchgear construction will conform to the following:  Operating Voltage      BIL 5 KV          60 KV 15 KV          95 KV 25 KV          150 KV 

 F. Feeder Protection: 

1. Provide three phase fusible disconnects. 2. Provide fault locators on each phase. 3. Metering 

a) KW Demand b) KWH Usage c) Power Factor 

 G. Enclosure: 

1. Enclosure to be pad mounted or free‐standing as required by the application. 

Page 311: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL ENCLOSED SWITCHES  16343‐3 

2. Provide  view  ports  to  allow  “switch‐open  status”  to  be  verified  without exposure to the energized components.  

3. Indoor: NEMA 1A (NEMA 1 with Gasket) 4. Outdoor: NEMA 3R 5. Paint with ANSI 61 Light Gray 6. Provide  anti‐condensation  heater  units  in  each  section.  Units  to  be 

thermostatically controlled and powered from a remote source.  2.03  LABELS  

A. Provide phenolic labels with ¼” high white letters on black background.  

B. Identify equipment controlled and one line designation.  2.04  LABELING  

A. Warning Signs: 1. All  external  doors  shall  be  provided  with  NEMA  approved  "WARNING  ‐ 

HAZARDOUS VOLTAGE INSIDE ‐ KEEP OUT" signs. 2. The  inside  of  each  door  and  each  of  the  front  insulating  barriers  shall  be 

provided with NEMA approved "DANGER ‐ HAZARDOUS VOLTAGE ‐ KEEP OUT" signs. 

 B. Rating Nameplates and Connection Diagrams: 

1. The  outside  of  both  the  front  and  back  shall  be  provided  with  nameplates indicating the manufacturer's name, catalog number, and model number. 

2. The  inside  of  each  door  shall  be  provided with  a  ratings  label  indicating  the following:    Voltage  ratings;  main  bus  continuous  rating;  short‐circuit  ratings (amperes,  RMS  symmetrical  and  MVA  three‐phase  symmetrical  at  rated nominal  voltage);  the  type  of  fuse  and  its  ratings  including  duty‐cycle  fault‐closing  capability;  and  interrupter  switch  ratings,  including  duty‐cycle  fault closing  capability  and  amperes,  short‐time,  RMS  (momentary,  asymmetrical and one‐second, symmetrical). 

3. A  three‐line  connection  diagram  showing  interrupter  switches,  fuses  with integral load interrupter, and bus along with the manufacturer's model number shall be provided on the inside of the front and rear doors, and on the inside of each switch operating hub access cover. 

 2.05  AUXILIARIES  

A. End fittings or holders, and fuse units or refill units for original installation, as well as one spare fuse unit or refill unit for each fuse mounting, shall be furnished. 

 B. A fuse handling tool as recommended by the fuse manufacturer shall be furnished. 

 

Page 312: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL ENCLOSED SWITCHES  16343‐4 

 PART 3 – EXECUTION  3.01  INSTALLATION  

A. Unit to be bolted to an appropriately sized concrete pad.  

B. The Contractor shall encircle  the pad with a ground grid 18  inches below final grade and  18  inches  horizontally  from  the  edge  of  the  switchgear  pad  as  shown  on  the drawings.    At  each  corner  of  the  pad  and  5'‐8"  horizontally  from  the  corner,  the Contractor shall drive a 3/4" X 10' copper clad ground rod to a depth where the rod top is 18" below final grade.  Each of the four ground rods shall be thermally welded to the encircling ground grid.  A ground wire shall be thermally bonded to each rod and extended 18" below grade to the ground lug inside the switch.  Ground wire size shall be #6 bare copper minimum. 

 C. The  Contractor  shall  stub  out  appropriately  sized  conduits  for  each  switch.    Main 

compartment  shall  contain  three  five‐inch  conduits,  minimum,  and  fusible  switch compartments shall contain two four‐inch conduits, minimum. 

 D. Final field test and trip settings shall be made by factory representatives. 

 3.02  FINAL TEST AND ACCEPTANCE  

A. Contractor shall perform high potential test on all cable and terminations.  (WARNING:  Terminations cannot be high voltage tested while attached to the switch.) 

 B. Switches shall be shown to be operational. 

 C. Apply touch‐up paint to all abrasions. 

 D. Clean all components of dirt, grease and construction debris. 

END OF SECTION 

TABLE OF CONTENTS 

Page 313: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL CLAD SWITCHGEAR  16346‐1 

SECTION 16346  

MEDIUM VOLTAGE METAL CLAD SWITCHGEAR  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All work specified in this section shall comply with the provisions of Section 16010.  

B. The main switchgear shall be 13.2 KV, 3‐phase, 4‐wire system,  impedance grounded, 60 hertz. 

 C. Furnish  and  install  metal‐clad  switchgear  as  described  in  this  specification  and  as 

detailed on the plan sheets.  

D. The  contractor  shall  be  responsible  for  the  erection,  installation  and  start‐up  of  the equipment covered by the specifications and plans. 

 E. The metal‐clad  switchgear  and all  components  shall  be designed, manufactured and 

tested  in  accordance  with  the  latest  applicable  standards  of  ANSI,  NEMA  and  IEEE including, but not limited to, ANSI 37.20, NEMA SG‐4 and SG‐5. 

  PART 2 – PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  

A. Cutler Hammer  

B. Square D  

C. General Electric  2.02  EQUIPMENT GUIDE SPECIFICATIONS  

A. Main Bus shall be tin plated insulated bus copper. 1. Current rating for the switchgear bus will be calculated on the connected load 

and any expected future loads.  2. Electrical  Designer  will  perform  fault  current  calculations  based  on  utility 

available  fault  current  and  specify  bracing  to meet  or  exceed  the  calculated value. 

Page 314: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL CLAD SWITCHGEAR  16346‐2 

3. For  equipment  that must  be maintained  while  energized,  Electrical  Designer will perform Arc Flash analysis as required by NFPA‐70E or task the Contractor to do so and affix required labels to the face of the MCC. 

4. Provide Bus Differential protection (ANSI 87) including all main breakers, main bus,  tie breaker and  feeder breakers. Where  the main bus  is divided with  tie breakers the switchgear will include multiple differential zones to prevent loss of the entire line up due to a single bus fault. 

 B. Main and feeder breakers shall be vacuum type, metal clad, draw out circuit breakers 

meeting UL and ANSI requirements. All breakers will be provided with the following: 1. Remote  racking  device  to  allow  breaker  extraction  from  a  safe  operating 

location with the breaker door closed. 2. Protective  relaying  except  in  special  circumstances  where  main  and  tie 

breakers  will  not  coordinate  and  the  breakers  are  grouped  in  a  common differential protective zone. 

 C. Ground  and  Test  Device:    Provide  a  ground  and  test  device  for  each  lineup  where 

feeder or service cables cannot be accessed except through the breaker compartment for testing. 

 D. Provide Main Metal Clad breaker where required by Code 

1. Lightning arresters will be provided on the main incoming lines a) Distribution class arresters  rated  for  the operating voltage and system 

configuration. b) Install arresters with adequate clearance from incoming lines. 

2. Provide revenue grade meter on each main to monitor the following: a) Total Demand: KW b) Total Usage: KWH c) System Power Factor 

 E. Voltage will be specified to match system requirements 

1. Ungrounded systems are not allowed. 2. Voltage reference provided by solidly grounded systems is preferred 3. Absence of a ground reference will be compensated for by providing a high or 

low resistance ground and protective relaying.  

F. Basic Impulse Level (BIL) for the Switchgear construction will conform to the following:  Operating Voltage      BIL 5 KV          60 KV 15 KV          95 KV 25 KV          150 KV 

 G. Feeder and Main Protection: 

Page 315: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL CLAD SWITCHGEAR  16346‐3 

1. Provide  three  phase  microprocessor  based  protection  with  the  following minimum features. a) ANSI 87: Bus differential protection  b) ANSI 27/59:  Under / Over Voltage Protection. c) ANSI 81 o/u: Under / Over Frequency  Protection d) ANSI  46: Negative Sequence Current Protection e) ANSI  50 / 51 Instantaneous / Time Overcurrent Protection  (Note: May 

not be required on Main and Tie breakers if coordination is not practical and  if  they  are  included  in  the  same  differential  zone  with  feeders provided with protective relaying) 

f) ANSI  50  /  51G  Instantaneous  /  Time  Ground  Overcurrent  Protection. (Note: May not be required on Main and Tie breakers if coordination is not practical and are included in the same differential zone with feeders provided with protective relaying) 

g) Phase temperature from motor mounted RTD inputs. 2. Display 

a) Relay will display set points and parameters on the front screen of the relay, flush mounted in the front door of the starter 

b) Voltage displays: Average and each  c) Current displays: Average and each phase 

3. Metering a) KW  b) KWH Usage c) Power Factor 

4. Programming:  will  be  by  laptop  computer  through  RS  Port  in  front  of  relay.  Program access will be password protected. 

5. Each line up will be provided with a satellite time link system to automatically set the time on the protective relaying. Time is to be reset hourly. 

 H. Enclosure: 

1. Indoor: NEMA 1A (NEMA 1 with Gasket) 2. Outdoor: NEMA 3R 3. Paint with ANSI 61 Light Gray 4. Indoor  and  outdoor  enclosures  will  be  provided  with  rear  and  front  access 

hinged doors with lockable “T” handles. All handles will be keyed alike. 5. Provide  anti‐condensation  heater  units  in  each  section.  Units  to  be 

thermostatically controlled and powered from a remote source.  

I. Control Power 1. Control  power will  be  provided  by  a  125  Volt  battery  system with  regulated 

trickle charger. 2. Battery system will be rated to power the control system for 8 hours without 

recharging. 3. Individual sections will be powered from a control distribution panel provided 

with the charging system. 

Page 316: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL CLAD SWITCHGEAR  16346‐4 

 2.03  LABELS  

A. Provide phenolic labels with ¼” high white letters on black background.  

B. Identify equipment controlled and one line designation.   PART 3 – EXECUTION  3.01  INSTALLATION  

A. Bus:    The  switchgear  shall  be  constructed  so  that  all  buses,  bus  supports  and connections shall withstand stresses that would be produced by currents equal to the momentary  ratings  of  the  circuit  breakers.    A  set  of  1,200  ampere  copper  insulated main buses shall have provisions for the addition of future units.  

B. All  doors,  hinged  bolted  panels,  and  screen  doors  giving  access  to  high‐voltage components or buswork to be provided with a "Danger ‐ High Voltage" sign.  

C. The  integrated  switchgear  assembly  to  be  provided with  a  nameplate  indicating  the manufacturer's  drawing  number  and  the  following  ratings:    voltage  (kV  nominal, maximum  design,  and  BIL),  short‐circuit  rating  ‐  interrupting,  momentary,  and  fault closing  (MVA,  3  phase  symmetrical).    In  addition,  each  bay  to  bear  a  nameplate indicating continuous and interrupting ratings of the circuit breaker in amps.  

D. Each unit to have a label on the outside stating the equipment being served.  

E. Accessories:    The  switchgear  manufacturer  shall  furnish  accessories  for  test, inspection, maintenance and operation, including: 1. Maintenance  tool  for  manually  charging  the  breaker  closing  spring  and 

manually opening the shutter. 2. Levering crank for moving the breaker between test and connected positions. 3. Test jumper for electrically operating the breaker while out of its compartment. 4. Breaker lifting yoke used for attachment to breaker for lifting breaker on or off 

compartment. 5. "Dockable" transport dolly for moving breaker outside its compartment. 6. Set of rail extensions and rail clamps per each vertical section. 7. Set of test plugs for use with Flexitest relays and meters. 8. Remote racking device. 9. Test cabinet for testing electrically operated breakers outside housing. 10. Mobile lift for lifting the breaker on or off the rails. 

 F. Fuses:  The switchgear manufacturer shall furnish a complete set of spare fuses of each 

size installed in the switchgear including potential transformer primary and secondary 

Page 317: Standard Water and Sewer Specifications PDF

  MEDIUM VOLTAGE METAL CLAD SWITCHGEAR  16346‐5 

fuses,  control  power  transformer primary  and  secondary  fuses,  and 230  volt  control circuit fuses. 

 G. Documentation:    The  contractor  shall  supply  six  (6)  sets  of  documentation  on  all 

equipment  supplied  under  this  contract.    The  documentation  will  include  the following: 1. Device Summary. 2. Elementary  diagram  (power  and  control  circuits  showing  each  wire  and 

terminal point). 3. Connection diagram showing physical location of devices and wiring connection 

points. 4. Interconnection diagram showing inter‐unit wiring. 5. Arrangement drawing including one‐line diagram, front view, and floor plan. 6. Complete relay data sheets indicating settings and test data. 

 H. Services:    The  contractor  shall  provide  a  field  service  engineer  or  factory 

representative  from the switchgear manufacturer  for a minimum of  four  (4) days on two separate occasions for check‐out and unit start‐up. 

END OF SECTION 

TABLE OF CONTENTS 

Page 318: Standard Water and Sewer Specifications PDF
Page 319: Standard Water and Sewer Specifications PDF

  CIRCUIT BREAKER DISTRIBUTION SWITCHBOARD  16420‐1 

SECTION 16420  

CIRCUIT BREAKER DISTRIBUTION SWITCHBOARD  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

Provide  service  entrance  distribution  switchgear  as  herein  specified  and  shown  on  the associated  electrical  drawings.    Switchboard  to  meet  Underwriters'  Laboratories  enclosure requirements. 

  PART 2 – PRODUCTS  2.01  APPLICATION  

A. For large electrical services 1000 amps and larger.  B. Heavy duty electrical service not requiring critical energized maintenance, as outlined 

above, and insulated case breakers in non‐draw‐out‐ switchboards.  2.02  ACCEPTABLE MANUFACTURERS  

A. Cutler Hammer  B. Square D  C. General Electric 

 2.03  EQUIPMENT GUIDE SPECIFICATIONS  

A. Main Bus shall be tin plated insulated bus copper. 1. Current rating for the switchboard bus will be calculated on the connected load 

and any expected future loads.  2. Electrical  Designer  will  perform  fault  current  calculations  based  on  utility 

available  fault  current  and  specify  bracing  to meet  or  exceed  the  calculated value. 

3. For  equipment  that must  be maintained  while  energized,  Electrical  Designer will perform Arc Flash analysis as required by NFPA‐70E or task the Contractor to do so and affix required labels to the face of the MCC. 

 

Page 320: Standard Water and Sewer Specifications PDF

  CIRCUIT BREAKER DISTRIBUTION SWITCHBOARD  16420‐2 

B. Main  Breakers  and  feeder  breakers  1200  amps  and  above  will  be  insulated  case breaker of non‐draw‐out construction. 1. Provide revenue grade meter on each main to monitor the following: 

a) Total Demand: KW b) Total Usage: KWH c) System Power Factor 

 C. Feeder breakers less than 1200 amps will be molded case circuit breakers meeting UL 

and ANSI requirements.   

D. Voltage will be specified to match system requirements 1. Ungrounded systems are not allowed. 2. Voltage reference provided by solidly grounded systems is preferred. 3. Absence of a ground reference will be compensated for by providing a high or 

low resistance ground and protective relaying.  

E. Insulated Case Breaker Digital Electronic Trip Unit 1. Provide three phase electronic trip units with ground fault protection. 2. Interchangeable rating plugs. 3. Adjustable Long time pickup and delay settings. 4. Adjustable Short time pickup and delay settings. 5. Adjustable ground fault pickup and delay settings. 6. Adjustable instantaneous pickup. 

 F. Feeder Protection: 

1. Provide three phase standard trip breakers. 2. Molded case (80% rated) circuit breaker with thermal‐magnetic trip. 

 G. Enclosure: 

1. Indoor: NEMA 1A (NEMA 1 with Gasket) 2. Outdoor: NEMA 3R 3. Paint with ANSI 61 Light Gray 4. Indoor  and  outdoor  enclosures  will  be  provided  with  rear  and  front  access 

hinged doors with lockable “T” handles. All handles will be keyed alike. 5. For outdoor enclosures, provide anti‐condensation heater units in each section. 

Units to be thermostatically controlled and powered from a remote source  2.04  LABELS  

A. Provide phenolic labels with ¼” high white letters on black background.  

B. Identify equipment controlled and one line designation.  

Page 321: Standard Water and Sewer Specifications PDF

  CIRCUIT BREAKER DISTRIBUTION SWITCHBOARD  16420‐3 

2.05  METERING  

A. Provide  full  function  electronic  metering.  Meter  to  provide  true  RMS  metering, including voltage line‐to‐line to ground, amperage, wattage, volt‐amps, power factor, frequency, watt‐hour demand. 

 B. If  required,  provide  separate  metering  compartment  for  metering  equipment, 

provided by local power company.  2.06  METERING TRANSFORMERS  

A. All instrument transformers shall be UL listed and classified as indicated on drawings.  

B. Current  transformers  shall  be  as  shown  on  drawings  with  burden  and  accuracy  to support connected meters and relays as required by ANSI/IEEE C57.13. 

 C. Potential  transformers  shall  be  as  shown  on  drawings with  burden  and  accuracy  to 

support connected meters and relays as required by ANSI/IEEE C57.13.  2.07  FINISH  

A. All steel surfaces shall be chemically cleaned prior to painting.  

B. Exterior paint color shall be Light Gray (ANSI 61) over phosphate‐type rust inhibitor.   PART 3 – EXECUTION  3.01  EXAMINATION  

A. The following procedures shall be performed by the Contractor. 1. Examine  installation  area  to  assure  there  is  enough  clearance  to  install 

switchboard. 2. Check concrete pads for uniformity and level surface. 3. Verify that switchboards are ready to install. 4. Verify field measurements are as shown on drawings. 5. Verify that required utilities are available, in proper location and ready for use. 6. Beginning of installation means installer accepts conditions. 

 3.02  INSTALLATION REQUIREMENTS  

A. Install per manufacturer’s instructions.  

B. Identify with Bakelite nameplates (with letters a minimum of 3/8" high) every switch, circuit breaker, ground fault system test panels, relays, etc., and other  items.   Circuit 

Page 322: Standard Water and Sewer Specifications PDF

  CIRCUIT BREAKER DISTRIBUTION SWITCHBOARD  16420‐4 

identification shall  include panelboard or motor being served.   Spares or spaces only shall have nameplates with no engraving.  Nameplates shall be secured to switchboard with two sheet metal screws. 

 C. As‐built shop drawings shall become a part of final brochures. 

END OF SECTION 

TABLE OF CONTENTS 

Page 323: Standard Water and Sewer Specifications PDF

  LOW VOLTAGE MOTOR CONTROL CENTERS  16443‐1 

SECTION 16443  

LOW VOLTAGE MOTOR CONTROL CENTERS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

Provide  a  motor  control  center  as  herein  specified  and  as  scheduled  on  the  electrical drawings. 

  PART 2 – PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  

A. Allen Bradley  

B. Cutler Hammer  

C. Square D  

D. General Electric  2.02  EQUIPMENT GUIDE SPECIFICATIONS  

A. Main Bus shall be tin plated copper bus. 1. MCC wiring shall be Class I, Type B. 2. Current  rating  for  the MCC Bus will be  calculated on  the connected  load and 

any expected future loads.  3. Electrical  Designer  will  perform  fault  current  calculations  based  on  utility 

available  fault  current  and  specify  bracing  to meet  or  exceed  the  calculated value. 

4. For  equipment  that must  be maintained  while  energized,  Electrical  Designer will perform Arc Flash analysis as required by NFPA‐70E or task the Contractor to do so and affix required labels to the face of the MCC. 

 B. Main Circuit Breaker: 

1. Provide revenue grade meter on each main to monitor the following: a) Total Demand: KW b) Total Usage: KWH c) System Power Factor 

Page 324: Standard Water and Sewer Specifications PDF

  LOW VOLTAGE MOTOR CONTROL CENTERS  16443‐2 

2. MCC Main will be equipped with electronic  trip, with phase and ground  fault protection. 

 C. Voltage will be specified to match system requirements. 

1. Ungrounded systems are not allowed. 2. Voltage reference provided by solidly grounded systems is preferred. 3. Absence of a ground reference will be compensated for by providing a high or 

low resistance ground and protective relaying.  

D. Main  Lugs  (where  required): Main  lugs  shall  be  supplied  with motor  control  center with adequate capacity to receive cables as indicated on drawings.  Main lugs shall be copper mechanical type.  

E. Neutral  Lugs  (where  required): Motor Control Center  shall be equipped with neutral landing lug(s) for 3‐phase, 4‐wire requirements.   Lug(s) shall receive the quantity and size of main incoming neutral conductors as indicated on drawings. 

 F. Bussing: 

1. Power Bus: Power shall be distributed to all sections by a main horizontal bus as  rated  per  drawings.    Distribution  from  the  horizontal  bus  to  each  vertical section  shall  be  by  means  of  a  vertical  bus  of  adequate  capacity  for  loads indicated.  All power bussing and connectors shall be tin‐plated copper. 

2. Ground Bus: Motor Control Center shall be equipped with a separate horizontal copper ground bus that runs the entire length of the motor control center.  The horizontal  ground  bus  shall  be  supplied  with  mechanical  lugs  sufficient  to terminate main  incoming  ground  conductors  as  indicated on  drawings.    Each vertical  section  will  contain  a  copper  vertical  ground  bus  connected  to  the horizontal ground bus.  This vertical ground bus will be installed so the plug‐on units engage the ground bus prior to engagement of the power stabs, and will disengage  only  after  the  power  stabs  are  disconnected  upon  removal  of  the plug‐on unit.  The vertical and horizontal ground bus assembly shall be ground to the enclosure. 

3. Neutral Bus: A neutral bus shall be provided which runs the entire length of the motor control center.  The neutral bus shall be of the same material, rating and plating  as  the main  bus.    Holes  shall  be  provided  in  the  neutral  bus  in  each vertical section to accommodate customer load neutral wire connections. 

 G. Basic Impulse Level (BIL) for the MCC construction will conform to the following: 

 Operating Voltage      BIL 480 Volts        30 KV 

 H. Contactors will be sized for the horse power and voltage rating or the full load current 

of the motor.  

Page 325: Standard Water and Sewer Specifications PDF

  LOW VOLTAGE MOTOR CONTROL CENTERS  16443‐3 

I. Provide each Contactor with an isolating switch with external lockable disconnect.  

J. Circuit Breakers: Feeder breakers shall be of the molded case type.  

K. Motor Protection: 1. Provide three phase Motor Circuit Protectors with external lockable operators 

in each bucket. 2. Overload Protection 

a) For standard installations, supply eutectic alloy class‐20 motor overload relays with external reset operator. 

b) For special applications,  including remote  located motors,  submersible motors,  etc.,  provide  ambient  compensated  IEC  bimetallic  strip overloads  with mechanical  current  comparison  or  electronic  overload relay units. 

c) Special applications requiring class‐10 or 30 protection will be equipped with electronic ambient compensated overload relay units. 

3. Pilot devices: each starter will be provided with the following: a) Enclosure door mounted Run (Green) light. b) Enclosure door mounted Stop (Red) light. c) Hand‐off‐Automatic  selection  switch  or  start/stop  push  buttons  as 

required  (Note:  this will not be  required where equipment damage or injury is at risk from improper operation). 

4. Auxiliary  

L. Enclosure: 1. Indoor: NEMA 1A (NEMA 1 with Gasket) 2. Outdoor:  NEMA  3R  with  rodent  barriers,  fluorescent  lights,  GFI  convenience 

receptacle, and thermostatically controlled strip heaters. 3. Paint with ANSI 61 Light Gray 

 M. Provide horse power rated capacitors to correct system power factor.  Capacitors to be 

mounted  in  the  motor  starter  section.    Do  not  mix  variable  frequency  drives  with power factor correction capacitors in a common enclosure. 

 2.03  LABELS  

A. Provide phenolic labels with ¼” high white letters on black background.  

B. Identify equipment controlled and one line designation.   

Page 326: Standard Water and Sewer Specifications PDF

  LOW VOLTAGE MOTOR CONTROL CENTERS  16443‐4 

PART 3 – EXECUTION  3.01  INSTALLATION  

A. All units shall be identified with permanent type engraved Bakelite nameplates on face of  units  showing  motor  or  equipment  being  served.    Bakelite  nameplates  shall  be fastened with two round head screws.  All terminal blocks, relays, starters, timers, etc., shall be identified internally with designation as shown on drawings.  

 B. Unit to be stored in a dry location. 

 C. Torque all cable lugs and bus connections to assure tight fit. 

 D. Once energized, check bus with IR monitoring camera and repair any hot spots. 

 E. Set all overload relays and mep per NEC based on actual run currents measured in the 

field. 

END OF SECTION 

TABLE OF CONTENTS 

Page 327: Standard Water and Sewer Specifications PDF

  GROUNDING  16450‐1 

SECTION 16450  

GROUNDING  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

The entire system of  raceways and equipment shall be grounded  in accordance with Article No. 250 and No. 517 of  latest edition of National Electrical Code and any  local regulation or governing authority.  

  PART 2 ‐ PRODUCTS  2.01  Main  service  disconnect means  shall  be bonded  to  street  side of  first  flange or  coupling of 

incoming main water  line  serving project with heavy‐duty ground clamp  in accordance with Article 250.104 of N.E.C.  The bonding jumper shall be sized in accordance with Table 250.66 of N.E.C.  An additional ground wire of same size shall be run to a tripod grounding rod system driven in ground outside foundation of building.  This system shall consist of three 3/4" x 10' copperweld  ground  rods  driven  in  ground  in  an  equilateral  triangular  configuration  with  a minimum of 15' spacing between each.  Connection of each ground rod to one another shall be made using a conductor of same size as being run for main service ground.  Building steel shall be connected to ground bus on main service with a conductor the same as required on the service.  This ground will be in addition to the previously specified grounds. 

 2.02  Ground  Clamps:    OZ  Electrical  Manufacturing  Company,  Steel  City,  Appleton,  or  approved 

substitute.  2.03  Feeder circuits to panels, motor control centers, etc., shall have a separate green grounding 

conductor in conduit sized in accordance with Table 250.122 of N.E.C.  2.04  All branch circuits shall have a separate green grounding conductor installed in same conduit 

as phase and neutral conductor from panel ground bus to device.   The grounding conductor shall be sized in accordance with Table 250.122 of N.E.C.  

 2.05  Flexible conduit will not be approved as achieving continuity of ground.   All  flexible conduit 

shall  have  a  jumper  wire  sized  to  ampacity  of  branch  breaker  and  shall  be  connected  to conduit system on both ends; this applies to fixtures, motors, controls, etc. 

 2.06  All  PVC  conduit  shall  have  separate ground wire  installed  in accordance with Tables 250‐94 

and 250‐95 of N.E.C.  

Page 328: Standard Water and Sewer Specifications PDF

  GROUNDING  16450‐2 

PART 3 – EXECUTION  3.01  INSTALLATION  

A. Effectively  bond  all  grounding  conductors  to  grounding  electrodes,  equipment enclosures and ground busses. 

 B. Provide a shunt path around main water meter by bonding around both sides of meter 

to assure continuity.  

C. Locate  all  grounding  attachments  away  from  areas  subject  to  physical  damage.  Provide protective covering as required. 

 D. Clean  all  non‐conductive  surfaces  on  equipment  to  be  grounded,  to  assure  good 

electrical continuity.  

E. Ground on main service shall be tested to obtain no greater than 10 ohms using test equipment  similar  to  a  "Biddle"  test.    Test  data  shall  be  submitted  to  Engineer  for review and such test data shall become a part of the final brochure. 

 END OF SECTION 

TABLE OF CONTENTS 

Page 329: Standard Water and Sewer Specifications PDF

  DRY TYPE TRANSFORMERS  16460‐1 

SECTION 16460  

DRY TYPE TRANSFORMERS  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. All work specified in this section shall comply with the provisions of Section 16010.  

B. Provide dry type transformer as shown on transformer schedules on drawings.   PART 2 ‐ PRODUCTS  2.01  ACCEPTABLE MANUFACTURERS  

Transformers  shall  be  as  manufactured  by  Square  D,  G.E.,  Cutler‐Hammer,  or  approved substitute. 

 2.02  EQUIPMENT REQUIREMENTS  

A. Single‐phase and three‐phase general purpose dry type transformers shall be equal to Hevi‐Duty  Electrical  Class  1100  and  Class  1200  respectively,  be  of  the  two‐winding type, self‐cooled, with ratings (KVA) as indicated on the drawings.  Transformers shall be  built  in  accordance  with  applicable  NEMA,  ANSI,  IEEE,  OSHA,  UL  standards,  and regulations on listings. 

 B. Transformers shall contain copper windings.  Aluminum not allowed. 

 C. Sound levels shall not exceed the following ranges: 

1. 0‐9 KVA: 40 db. 2. 10‐50 KVA: 45 db. 3. 51‐150 KVA: 50 db. 4. 151‐300 KVA: 55 db. 5. 301‐500 KVA: 60 db. 6. 501‐700 KVA: 62 db. 

 D. Transformers with  single  phase  ratings  through 10 KVA  shall  have  a  voltage  ratio  of 

240/480 volts primary‐120/240 volts secondary with a maximum temperature rise of 115  degrees  C  at  full  load  rating  for  the  non‐ventilated  type,  suitable  for  indoor  or outdoor use.  

Page 330: Standard Water and Sewer Specifications PDF

  DRY TYPE TRANSFORMERS  16460‐2 

E. Transformers  with  three  phase  ratings  through  9  KVA  shall  have  a  voltage  ratio  as indicated  on  drawings.    Provide  four  2‐1/2%  full  capacity  voltage  adjusting  taps,  2 above and 2 below primary rated voltage.   Maximum full  load temperature rise shall be 115 degrees C for the non‐ventilated, HARDSHELL, encapsulated type, suitable for indoor or outdoor use.  

F. Transformers  shall  have  voltage  ratios  as  indicated  on  drawings.    Transformers between 15 KVA and 300 KVA to be provided with six (6) 2‐1/2% full capacity taps‐‐two above and four below primary rated voltage.  

G. Transformer  core  shall  be  of  low  loss  type,  high  quality,  grain  oriented  steel.    Core clamping members  shall  cover  a minimum of  90% of  the  top and bottom core  yoke laminations.    Vertical  framing members  shall  be  contained within  the  insulated  coil form to minimize external flux path.  

H. Coils  shall  be  wound  of  electrical  grade,  edge‐conditioned  aluminum  strip  on preformed  rigid  coil  base,  and  shall  be  provided with  corrugated  aluminum positive spacing  air  duct  forms,  to  increase  air  circulation  and  reduce  hot  spot  temperature rise.   Each coil  to have a  final protective outer wrap of electrical  insulating material.  Coils with exposed magnet wire will not be acceptable.  Coil leads shall be terminated to suitable solderless lugs (thru 75 KVA), fully approved for use with either copper or aluminum cable and located on a solidly‐braced, insulated terminal board.  

I. Immediately prior to initial varnish impregnation, entire core and coil assembly to be thoroughly  dried  in  a  preheat  cycle,  and  then  thoroughly  baked  to  ensure  that  all volatiles  have  been  driven  off  in  process.    Core  and  coil  assembly  to  be  internally isolated from enclosure through use of an effective vibration dampening system. 

  PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Provide flexible conduit to and from transformer.  

B. Install transformers in accordance with manufacturer’s recommendations.  

C. Provide trapeze type hangers for transformers supported from the structure or mount on the floor as shown on the drawings.  Floor mounted transformers shall be securely anchored to a 4" reinforced concrete housekeeping pad. Provide working clearances as required by NEC. 

 D. Ground  secondary  neutral  of  all  transformers  to  grounding  conductor  in  primary 

feeder  and  to  building  steel  or  other  approved  electrode  using  grounding  electrode 

Page 331: Standard Water and Sewer Specifications PDF

  DRY TYPE TRANSFORMERS  16460‐3 

conductor sized in accordance with NEC.  Ground transformer enclosure with bonding jumper. 

 E. Provide both primary and secondary protection by use of fuses or circuit breakers as 

shown on drawings. 

END OF SECTION  

TABLE OF CONTENTS 

Page 332: Standard Water and Sewer Specifications PDF
Page 333: Standard Water and Sewer Specifications PDF

  HEAT TRACING CABLE  16505‐1 

SECTION 16505  

HEAT TRACING CABLE  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

Furnish  a  complete  Factory  Mutual  Approved  SYSTEM  of  pipe  heating  cable  for  freeze prevention in hazardous (classified) areas complete with components, installation accessories and controls and installed in strict accordance with NFPA 70 and NEC 1990 Section 500‐5(a) of the NATIONAL ELECTRIC CODE. 

  PART 2 ‐ PRODUCTS  2.01  The heating cable shall consist of two (2) 14 AWG Nickel‐coated‐copper bus wires wrapped in 

a  radiation‐crosslinked  conductive  fiber  core  capable  of  regulating  its  power  output  in response to temperature changes all along its length.  The heating cable shall be covered with a  radiation‐crosslinked  modified  polyolefin  dielectric  jacket,  a  tinned  copper  shield  and fluoropolymer  outer  jacket  capable  of  withstanding  exposure  to  chemicals,  solvents  and hydrocarbons and exposure to temperatures up to 420 degrees F. 

 2.02  The  cable's  self‐regulating  technology  shall  be  such  that  surface  temperature  of  the  cable 

does not exceed  its built‐in maximum or  "ceiling" even  if  overlapped or  installed with poor pipe contact. 

  PART 3 ‐ EXECUTION  3.01  The heating cable shall be installed under the pipe's thermal insulation without spiraling and 

with  sufficient  heat  output  to maintain  the  pipe  temperature  of  no  less  than  40  degrees  F when outside ambient is ‐20 degrees F and the average wind speed is 15 MPH. 

 3.02  After  cable  installation  and  before  and  after  installation  of  THERMAL  pipe  insulation,  the 

heating  cable  shall  be  tested  using  a  5,000  volt  megger.    Minimum  ELECTRICAL  insulation resistance shall be 20 megohms regardless of circuit length.  Both bus wires shall be tested to verify the connection of all splices and tees.  All material shall be installed in accordance with the manufacturer's recommendations. 

 3.03  Provide class B ground fault trip on all circuit breakers feeding heat tracing circuits.  

Page 334: Standard Water and Sewer Specifications PDF

  HEAT TRACING CABLE  16505‐2 

3.04  Heat tracing circuits to be thermostatically controlled. 

END OF SECTION 

TABLE OF CONTENTS 

Page 335: Standard Water and Sewer Specifications PDF

  WOODEN POLES   16532‐1 

SECTION 16532  

WOODEN POLES  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  Provide poles as shown and sized on the plan sheets.   PART 2 – PRODUCTS  2.01  Wooden  poles  used  for  all  electrical  installations,  if  required,  shall  be  of  the  size  and  class 

required having an ultimate fiber strength of 7,500 psi and treated with a minimum of ASA 12 lb. "Penta."  Class limitations are given in the following table. 

 

POLE DIMENSIONS, STRENGTHS AND LOADS 

  Pole Class   

1  2  3  4  5  6  7 

Min. Top Circum. (in.) 

27  25  23  21  19  17  15 

Min. Top Dia. (in.)  8.6  8.0  7.3  6.7  6.0  5.4  4.8 

Length (Feet) 

Minimum Circumferences Six Feet from Butt (in.) 

Setting Depth 

30  37.5  35.0  32.5  30.0  28.0  26.0  24.0  5'‐6" 

35  40.0  37.5  35.0  32.0  30.0  27.5  25.2  6'‐0" 

40  42.0  39.5  37.0  34.0  31.5  29.0  27.0  6'‐0" 

45  44.0  41.5  38.5  36.0  33.0  30.5  28.5  6'‐5" 

50  46.0  43.0  40.0  37.5  34.5  32.0  29.5  7'‐0" 

55  47.5  44.5  41.5  39.0  36.0  33.6  ‐‐  7'‐6" 

60  49.5  46.0  43.0  40.0  37.0  34.5  ‐‐  8'‐0" 

65  51.0  47.5  44.5  41.5  38.5  ‐‐  ‐‐  8'‐6" 

70  52.5  49.0  46.0  42.5  39.5  ‐‐  ‐‐  9'‐0" 

 2.02  Poles to be compatible to REA Specifications.   PART 3 ‐ EXECUTION  3.01  Pole top to be protected by a pole cap to prevent rain entry.  3.02  Poles set for electrical equipment shall be installed as shown on the plan sheets.  

Page 336: Standard Water and Sewer Specifications PDF

  WOODEN POLES   16532‐2 

3.03  Holes  shall be vertically drilled or hand dug  to  the depth specified on  the plan sheets.   The hole shall be twelve (12) inches in diameter larger than the butt end of the pole. 

 3.04  Upon digging of the hole, the pole shall be placed in a vertical position and held in place until 

backfill is complete.  Backfill shall be hand placed and tamped to 95% in six‐inch layers using materials expelled from the hole.   Upon completion, backfill shall be mounded not less than eight inches around the pole. 

END OF SECTION 

TABLE OF CONTENTS 

Page 337: Standard Water and Sewer Specifications PDF

  LIGHTNING PROTECTION  16601‐1 

SECTION 16601  

LIGHTNING PROTECTION  

TABLE OF CONTENTS  PART 1 ‐ GENERAL  1.01  WORK INCLUDED  

A. Contractor  shall  provide  all  labor,  materials  and  items  of  service  required  for  the completion  of  a  functional  and  unobtrusive  system  of  air  terminals,  conductor, grounds  and  other  components  necessary  for  the  protection  of  the  building  against damage by lightning. 

 B. The system shall be completely concealed where possible, with only the air terminals 

and roof conductor visible, and complying in all respects with the following Codes: 1. Underwriters' Laboratories, Inc. ‐ No. UL96A. 2. National Fire Protection Association ‐ No. NFPA780. 

 C. The  installing  contractor  shall  be  actively  engaged  in  the  installation  of  lightning 

protection systems, and shall be so listed by Underwriters' Laboratories.  He shall have a minimum of three years experience in this work. 

 D. The  Contractor  shall  have  the  shop  drawings  signed  and  sealed  by  a  registered 

engineer specializing in lightning protection design.   PART 2 ‐ PRODUCTS  2.01  MATERIALS  

A. All  materials  used  shall  be  new  and  be  the  product  of  a  manufacturer  member  of Lightning Protection Institute, approved and labeled by U.L. and L.P.I. 

 B. All  conductors,  terminals  and  fittings  at  the  roof  line  shall  be  aluminum  and  all 

components below the roof line shall be copper.  

C. All conductors, terminals and fittings shall be copper or bronze.   

Page 338: Standard Water and Sewer Specifications PDF

  LIGHTNING PROTECTION  16601‐2 

PART 3 ‐ EXECUTION  3.01  INSTALLATION  

A. Submit a list of materials and system shop drawings to Engineer for review.  

B. Install all conductors in a downward direction, avoiding trapping or any sharp bends of cables. 

 C. New construction:  Upon completion of the installation, the Contractor shall complete 

the  application  for  the  U.L.  "Master  Label"  and  forward  to  the  manufacturer  for processing.  The Contractor shall provide a copy of such application to the Engineer.  A copy of the application shall be made a part of the project closing files. 

 D. Existing  construction:    If  it  is  determined  that  the  existing  buildings  do  not  have UL 

approved and labeled lightning protection systems, proceed with the new installation, using all labeled materials and meeting all the requirements of the UL 96A Code.  Upon completion,  the  manufacturer  shall  certify,  in  writing  to  the  Engineer,  that  the installation on the new building meets all requirements for the "Master Label" so that the Owner may obtain  the UL  label at a  later date, when an approved  installation  is made on the older buildings. 

END OF SECTION 

TABLE OF CONTENTS 

Page 339: Standard Water and Sewer Specifications PDF
Page 340: Standard Water and Sewer Specifications PDF

 

APPENDIX A – Opening Direction for Sewer Valves, Water Valves and Fire Hydrants 

APPENDIX A 

Page 341: Standard Water and Sewer Specifications PDF
Page 342: Standard Water and Sewer Specifications PDF

 

APPENDIX B­ Notice of Intent (NOI) Form 

 

    APPENDIX B 

Page 343: Standard Water and Sewer Specifications PDF

 

    APPENDIX B 

                                                

Page 344: Standard Water and Sewer Specifications PDF

 

APPENDIX C­Construction Storm Water Inspection Certification Form   

(see following page)                                              

APPENDIX C 

Page 345: Standard Water and Sewer Specifications PDF

 

APPENDIX C 

APPENDIX C­Construction Stormwater Inspection Certification Form  

                              

             

Page 346: Standard Water and Sewer Specifications PDF

 

APPENDIX D 

APPENDIX D­ Notice of Termination (NOT) Form 

 

                                           

Page 347: Standard Water and Sewer Specifications PDF

APPENDIX D

  

Page 348: Standard Water and Sewer Specifications PDF

 

APPENDIX E 

APPENDIX E­ CGW Water Customer Data Sheet  

 

CLARKSVILLE GAS & WATER WATER CUSTOMER DATA SHEET 

                          Customer        Address                Building Address                 Zip Code       Subdivision        Lot No.        Build No.       Type of Occupancy                                                                                         Fixture Value     No. of     Fixture Fixture           60 psi     Fixtures     Value Bathtub           8  X    = 0 Bedpan Washers           10  X    = 0 Bidet           2  X    = 0 Dental Unit           2  X    = 0 Drinking Fountain ‐ Public        2  X    = 0 Kitchen Sink           2.2  X    = 0 Lavatory           1.5  X    = 0 Showerhead (Shower Only)        2.5  X    = 0 Service Sink           4  X    = 0 Toilet ‐ Flush Valve           35  X    = 0          ‐ Tank Type           4  X    = 0 Urinal ‐ Pedestal Flush Valve        35  X    = 0          ‐ Wall Flush Valve        16  X    = 0 Wash Sink ( Each Set of Facets)     4  X    = 0 Dishwasher           2  X    = 0 Washing Machine           6  X    = 0 Hose (50 ft Wash Down) ‐ 1/2 in.     5  X    = 0                                             ‐ 5/8 in.     9  X    = 0                                             ‐ 3/4 in.     12  X    = 0                           Combined Fixture Value Total                    0 

                          Customer Peak Demand From Fig. 4‐2 or 4‐3 X Press. Factor        = gpm                          Add Irrigation ‐              Sections* X 1.16 or 0.40†           = gpm                          ‐              Hose Bibs X Fixture Value X            Press. Factor      = gpmAdded Fixed Load                    = gpmTOTAL FIXED DEMAND                 = gpm                          * 100 ft2 area = 1 section                      † Spray System ‐ Use 1.16; Rotary Systems ‐ Use 0.40    

Page 349: Standard Water and Sewer Specifications PDF

 

                                      Fixture Value     No. of     Fixture Fixture           60 psi     Fixtures     Value Bathtub           8  X     =  0 Bedpan Washers           10  X     =  0 Bidet           2  X     =  0 Dental Unit           2  X     =  0 Drinking Fountain ‐ Public        2  X     =  0 Kitchen Sink           2.2  X     =  0 Lavatory           1.5  X     =  0 Showerhead (Shower Only)        2.5  X     =  0 Service Sink           4  X     =  0 Toilet ‐ Flush Valve           35  X     =  0          ‐ Tank Type           4  X     =  0 Urinal ‐ Pedestal Flush Valve        35  X     =  0          ‐ Wall Flush Valve        16  X     =  0 Wash Sink ( Each Set of Facets)     4  X     =  0 Dishwasher           2  X     =  0 Washing Machine           6  X     =  0 Hose (50 ft Wash Down) ‐ 1/2 in.     5  X     =  0                                             ‐ 5/8 in.     9  X     =  0                                             ‐ 3/4 in.     12  X     =  0                           Combined Fixture Value Total                    0 

                          Customer Peak Demand From Fig. 4‐2 or 4‐3 X Press. Factor        = gpm                          Add Irrigation ‐              Sections* X 1.16 or 0.40†           = gpm                          ‐              Hose Bibs X Fixture Value X            Press. Factor      = gpmAdded Fixed Load                    = gpmTOTAL FIXED DEMAND                 = gpm                          

* 100 ft2 area = 1 section                      

† Spray System ‐ Use 1.16; Rotary Systems ‐ Use 0.40             

                          

APPENDIX E ‐ 2 

Page 350: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 1 

APPENDIX F­ CGW Lift Station Final Inspection Check List  

Clarksville Gas & Water Lift Station 

Final Inspection Checklist  

 Date:_______________________________    Location:_________________________________________________  Lift Station ID:_______________________    kW Meter Number:________________________________________  Pump Manufacturer:___________________   Pump Suppler:____________________________________________  Pump Model:________________________    Serial Number:____________________________________________  Voltage:____________________________    Phase:___________________________________________________  Hertz:______________________________    Horsepower:______________________________________________  Control Panel Model:_________________    Control Panel Supplier:_____________________________________  Contractor:__________________________    Engineer:__________________________________________________  

  

I. ELECTRIC  

A. Is the power system 3 phase or 1 phase? ________________________  

B.    If 3 phase, is grounded neutral power provided?    _____ Yes   _____No  C.  If above answer is “No”, is transformer installed?    _____Yes   _____No  D. Voltage readings 

• Between phases:      L1, L2 _______   L1, L3 _______  L2, L3 ______ • High phase to ground  ________________________ • Other legs to ground _________________________ 

       E.  Is High Leg (L3) connected to motor only, and not  _______Yes    _______No   connected to any auxiliary circuits?       F.  Do latches on control panel work smoothly?   _______Yes  _______No 

 II. PUMP AND MOTOR CONTROLS 

 A. Do breaker switches operate properly? 

• Pump #1        ______Yes   ______No • Pump #2        ______Yes  ______No • Pump #3        ______Yes  ______No • Pump #4        ______Yes  ______No • Control Circuit        ______Yes  ______No • Remote Control Monitor      ______Yes  ______No 

Page 351: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 2 

 B. Hand‐Off‐Automatic switches: 

• Pump #1 hand position operates    ______Yes  ______No • Pump #2 hand position operates    ______Yes  ______No • Pump #3 hand position operates    ______Yes  ______No • Pump #4 hand position operates    ______Yes  ______No • Do floats sequence all pumps 

with relation to lead, lag and alternation?  ______Yes  ______No  

C. Amperage: • Name Plate Rating (amps) Pump #1 Motor  ______Yes   ______No • Amps pulled by Pump #1 Motor    ______Yes  ______No • Name Plate Rating (amps) Pump #2 Motor  ______Yes  ______No • Amps pulled by Pump #2 Motor    ______Yes  ______No • Name Plate Rating (amps) Pump #3 Motor  ______Yes  ______No • Amps pulled by Pump #3 Motor    ______Yes  ______No • Name Plate Rating (amps) Pump #4 Motor  ______Yes  ______No • Amps pulled by Pump #4 Motor    ______Yes  ______No 

 D. Seal Failure/Heat Sensor: 

• Seal failure wires connected properly to seal failure circuit?      ______Yes  ______No 

• Test seal failure circuit OK?      ______Yes  ______No • Heat sensor wires connected properly 

to heat sensor circuit?      ______Yes  ______No • Test heat sensor circuit OK?      ______Yes  ______No 

     E. Control Components: 

• Verify all electrical components are  locally available        ______Yes  ______No 

          F. Alarms: 

• High water alarm light and horn activated   with test button        ______Yes  ______No 

• Horn silences with silence button.    ______Yes  ______No • High water alarm light and horn activate  

with float.        ______Yes  ______No  

G. Float Settings: • Lead pump kicks on at Elevation   ____________’_______”     from wet well bottom • Lag pump kicks on at Elevation   ____________’_______”     from wet well bottom • Back up pump kicks on at Elevation ____________’_______”     from wet well bottom • Back up pump kicks on at Elevation ____________’_______”     from wet well bottom • Height of influent sewer above floor of wet well ____________’_______”      • Height of high water alarm above floor of wet well ____________’_______”      • Top of basin Elevation ____________’_______”      • Total basin depth ____________’_______”       

Remarks:      ______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

    

Page 352: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 3 

III. PUMPS AND MOTORS  

A. Operations:   1.  Are Pumps running quietly? 

• Pump #1  ______Yes  ______No • Pump #2  ______Yes  ______No • Pump #3  ______Yes  ______No • Pump #4  ______Yes  ______No 

 2. Are Motors running quietly? 

• Pump #1  ______Yes  ______No • Pump #2  ______Yes  ______No • Pump #3  ______Yes  ______No • Pump #4  ______Yes  ______No 

 3. Is excessive Vibration noted? 

• Pump #1  ______Yes  ______No • Pump #2  ______Yes  ______No • Pump #3  ______Yes  ______No • Pump #4  ______Yes  ______No 

B. Installation:  

• Are guide rails exactly vertical (plumb)? • Is base elbow installed level? 

 Remarks:__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________   

 IV. REMOTE MONITOR PANEL 

A.    Verify  start‐up  procedure  completed  properly  and  put  “On‐Line”  with  the  Control  SCADA               room remote monitor panel supplier.        ______Yes    ______No 

 V. VALVES 

 A. Check valves: 

• Do clappers swing freely?        ______Yes  ______No • Does packing leak?          ______Yes  ______No • Are counter weights adjusted properly?     ______Yes  ______No 

 B. Plug valves: 

 • Do valves open and close freely?      ______Yes  ______No • Does packing leak?          ______Yes  ______No • During operation, are all gates completely open?  ______Yes  ______No   

 Remarks:_____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

Page 353: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 4 

VI. PUMP STATION TESTING  

A. Draw Down Test Diameter of wet well ________________’________” 

   (5’‐0”=147 gal/ft      6’‐0”=212 gal/ft     7’‐0”=288 gal/ft       8’‐0”=376 gal/ft      10’‐0”=587 gal/ft)  

       Time     Depth    Vol. Per Unit Depth        Total Vol.    Pump Capacity 

 Pump #1 On    ______  ______              ____________      ___________    ____________   Pump #1 Off    ______  ______   Pump #2 On    ______  ______              ____________     ___________    ____________   Pump #2 Off    ______  ______   Pump #3 On    ______  ______              ____________    ___________    ____________   Pump #3 Off    ______  ______   Pump #4 On    ______  ______              ____________      ___________    ____________   Pump #4 Off    ______  ______   Pump #1,2 On    ______  ______              ____________     ___________    ____________   Pump #1,2 Off    ______  ______   Pump #1,3 On    ______  ______              ____________      ___________    ____________

  Pump #1,3 Off    ______  ______   Pump #1,4 On    ______  ______              ____________      ___________    ____________

  Pump #1,4 Off    ______  ______   Pump #2,3 On    ______  ______              ____________    ___________    ____________

  Pump #2,3 Off    ______  ______   Pump #2,4 On    ______  ______              ____________    ___________    ____________

  Pump #2,4 Off    ______  ______   Pump #3,4 On    ______  ______              ____________    ___________    ____________

  Pump #3,4 Off    ______  ______   Pump #1,2,3 On  ______  ______             ____________    ___________    ____________

  Pump #1,2,3 Off  ______  ______ 

Page 354: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 5 

  

    Time     Depth      Vol. Per Unit Depth        Total Vol.             Pump Capacity 

 Pump #1,2,4 On  ______  ______ 

            ____________      ___________    ____________   Pump #1,2,4 Off  ______  ______ 

 Pump #1,3,4 On  ______  ______ 

            ____________      ___________    ____________ Pump #1,3,4 Off  ______  ______ 

 Pump #2,3,4 On  ______  ______ 

            ____________      ___________    ____________ Pump #2,3,4 Off  ______  ______ 

 Pump #1,2,3,4 On  ______  ______ 

            ____________      ___________    ____________ Pump #1,2,3,4 Off  ______  ______ 

  

B. Pressure Test • No Pumps Running – Static Back Pressure:    _____________ • Pump No. 1 Operating – Pressure:      _____________ • Pump No. 2 Operating – Pressure:      _____________ • Pump No. 3 Operating – Pressure:      _____________ • Pump No. 4 Operating – Pressure:      _____________ • Pump Nos. 1 & 2 Running – Pressure:      _____________ • Pump Nos. 1 & 3 Running – Pressure:      _____________ • Pump Nos. 1 & 4 Running – Pressure:      _____________ • Pump Nos. 2 & 3 Running – Pressure:      _____________ • Pump Nos. 2 & 4 Running – Pressure:      _____________ • Pump Nos. 3 & 4 Running – Pressure:      _____________ • Pump Nos. 1,2 & 3 Running – Pressure:      _____________ • Pump Nos. 1,2 & 4 Running – Pressure:      _____________ • Pump Nos. 1,3 & 4 Running – Pressure:      _____________ • Pump Nos. 2,3 & 4 Running – Pressure:      _____________ • Pump Nos. 1,2,3 & 4 Running – Pressure:    _____________ 

  Remarks:____________________________________________________________________________________________________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

Page 355: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 6 

   

VII. EQUIPMENT  (Verify operation and list what is in need of correction)   

• Pumps  

• Motors  

• Pump Circuit Breaker  

• Starters  

• Heaters  

• Control Circuit Breaker  

• Remote Monitor Circuit Breaker  

• Alternator  

• H‐O‐A Switches  

• Plug Valves  

• Check Valves  

• Pressure Gauge  

• Transducer  

• Floats  

• Other   

Remarks:____________________________________________________________________________________________________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

Page 356: Standard Water and Sewer Specifications PDF

 

APPENDIX F ‐ 7 

  

VIII. SCADA ALARM SYSTEM  

A.   Do latches on control panel work smoothly?      _______Yes  ______No  B.   Code indication functioning 

 • Pump overload trip          ______Yes  ______No • Crew on site key switch         ______Yes  ______No • Wet well high water          ______Yes  ______No • Dry pit high water or submersible seal failure    ______Yes   ______No • Power failure            ______Yes  ______No • Open              ______Yes  ______No • Restore to normal          ______Yes  ______No • Low battery            ______Yes  ______No 

   

Remarks:____________________________________________________________________________________________________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ 

   

        I CERTIFY THIS REPORT IS ACCURATE  

______________________________ Start‐up date/time 

  

_______________________________________   __________________________________________ Start‐up Coordinator             Factory Representative 

  

_______________________________________   __________________________________________ Wastewater Utility Superintendent         Wastewater Utility Operator 

  

_______________________________________   __________________________________________  Engineer               Contractor