Standard Specifications

872
STANDARD SPECIFICATIONS STATE OF CALIFORNIA BUSINESS, TRANSPORTATION AND HOUSING AGENCY DEPARTMENT OF TRANSPORTATION MAY 2006 ISSUED BY DEPARTMENT OF TRANSPORTATION Current price for additional copies of this book may be obtained by writing STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION PUBLICATION DISTRIBUTION UNIT 1900 Royal Oaks Drive Sacramento, California 95815 Telephone (916) 445-3520

description

State of California Business, transportation and housing agency

Transcript of Standard Specifications

  • 1STANDARD SPECIFICATIONS STATE OF CALIFORNIA

    BUSINESS, TRANSPORTATION AND HOUSING AGENCY

    DEPARTMENT OF TRANSPORTATION

    MAY 2006

    ISSUED BY

    DEPARTMENT OF TRANSPORTATION

    Current price for additional copies of this book may be obtained by writing

    STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION PUBLICATION DISTRIBUTION UNIT

    1900 Royal Oaks Drive Sacramento, California 95815

    Telephone (916) 445-3520

  • 2

    TABLE OF CONTENTS

    GENERAL PROVISIONS SECTION 1: DEFINITIONS AND TERMS ...........................................................1 SECTION 2: PROPOSAL REQUIREMENTS AND CONDITIONS.....................9 SECTION 3: AWARD AND EXECUTION OF CONTRACT.............................15 SECTION 4: SCOPE OF WORK ..........................................................................17 SECTION 5: CONTROL OF WORK....................................................................23 SECTION 6: CONTROL OF MATERIALS .........................................................31 SECTION 7: LEGAL RELATIONS AND RESPONSIBILITY ...........................41 SECTION 8: PROSECUTION AND PROGRESS................................................77 SECTION 9: MEASUREMENT AND PAYMENT..............................................91

    MISCELLANEOUS SECTION 10: DUST CONTROL .......................................................................115 SECTION 11: MOBILIZATION.........................................................................117 SECTION 12: CONSTRUCTION AREA TRAFFIC CONTROL DEVICES ....119 SECTIONS 13 AND 14: (BLANK) ....................................................................130 SECTION 15: EXISTING HIGHWAY FACILITIES.........................................131

    GRADING SECTION 16: CLEARING AND GRUBBING ..................................................143 SECTION 17: WATERING ................................................................................147 SECTION 18: DUST PALLIATIVE ...................................................................149 SECTION 19: EARTHWORK ............................................................................151 SECTION 20: EROSION CONTROL AND HIGHWAY PLANTING..............177 SECTION 21: (BLANK) .....................................................................................220 SECTION 22: FINISHING ROADWAY............................................................221 SECTION 23: (BLANK) .....................................................................................222

    SUBBASES AND BASES SECTION 24: LIME STABILIZATION.............................................................223 SECTION 25: AGGREGATE SUBBASES ........................................................229 SECTION 26: AGGREGATE BASES................................................................233 SECTION 27: CEMENT TREATED BASES.....................................................237 SECTION 28: LEAN CONCRETE BASE..........................................................251 SECTION 29: TREATED PERMEABLE BASES..............................................257 SECTIONS 30 THROUGH 36: (BLANK)..........................................................262

    SURFACINGS AND PAVEMENTS SECTION 37: BITUMINOUS SEALS................................................................263 SECTION 38: BLANK........................................................................................277 SECTION 39: ASPHALT CONCRETE..............................................................279 SECTION 40: PORTLAND CEMENT CONCRETE PAVEMENT...................307 SECTION 41: PAVEMENT SUBSEALING AND JACKING...........................325 SECTION 42: GROOVE AND GRIND PAVEMENT .......................................331 SECTIONS 43 THROUGH 48: (BLANK)..........................................................334

    STRUCTURES SECTION 49: PILING.........................................................................................335 SECTION 50: PRESTRESSING CONCRETE ...................................................349 SECTION 51: CONCRETE STRUCTURES ......................................................363

    i

  • TABLE OF CONTENTS

    SECTION 52: REINFORCEMENT ....................................................................403 SECTION 53: SHOTCRETE...............................................................................425 SECTION 54: WATERPROOFING....................................................................429 SECTION 55: STEEL STRUCTURES ...............................................................431 SECTION 56 : SIGNS .........................................................................................451 SECTION 57: TIMBER STRUCTURES ............................................................461 SECTION 58: PRESERVATIVE TREATMENT OF LUMBER, TIMBER AND PILING .................................................................................................................467 SECTION 59: PAINTING...................................................................................469 SECTION 60: (BLANK) .....................................................................................478

    DRAINAGE FACILITIES SECTION 61: CULVERT AND DRAINAGE PIPE JOINTS.............................479 SECTION 62: ALTERNATIVE CULVERTS.....................................................483 SECTION 63: CAST-IN-PLACE CONCRETE PIPE.........................................485 SECTION 64: PLASTIC PIPE ............................................................................489 SECTION 65: REINFORCED CONCRETE PIPE..............................................495 SECTION 66: CORRUGATED METAL PIPE...................................................505 SECTION 67: STRUCTURAL METAL PLATE PIPE ......................................517 SECTION 68: SUBSURFACE DRAINS ............................................................521 SECTION 69: OVERSIDE DRAINS ..................................................................533 SECTION 70: MISCELLANEOUS FACILITIES ..............................................537 SECTION 71: (BLANK) .....................................................................................541 SECTION 72: SLOPE PROTECTION................................................................543 SECTION 73: CONCRETE CURBS AND SIDEWALKS .................................555 SECTION 74: PUMPING PLANT EQUIPMENT..............................................561 SECTION 75: MISCELLANEOUS METAL......................................................571 SECTIONS 76 THROUGH 79: (BLANK)..........................................................582

    RIGHT OF WAY AND TRAFFIC CONTROL FACILITIES SECTION 80: FENCES.......................................................................................583 SECTION 81: MONUMENTS............................................................................595 SECTION 82: MARKERS AND DELINEATORS ............................................597 SECTION 83: RAILINGS AND BARRIERS .....................................................603 SECTION 84: TRAFFIC STRIPES AND PAVEMENT MARKINGS ..............623 SECTION 85: PAVEMENT MARKERS............................................................631 SECTION 86: SIGNALS, LIGHTING AND ELECTRICAL SYSTEMS ..........639 SECTION 87: (BLANK) .....................................................................................735

    MATERIALS SECTION 88: ENGINEERING FABRICS .........................................................737 SECTION 89: (BLANK) .....................................................................................739 SECTION 90: PORTLAND CEMENT CONCRETE .........................................741 SECTION 91: PAINT..........................................................................................779 SECTION 92: ASPHALTS .................................................................................783 SECTION 93: LIQUID ASPHALTS...................................................................789 SECTION 94: ASPHALTIC EMULSIONS ........................................................801 SECTION 95: EPOXY ........................................................................................809

    ii

  • 3

    STATE OF CALIFORNIA

    DEPARTMENT OF TRANSPORTATION

    STANDARD SPECIFICATIONS

    GENERAL PROVISIONS SECTION 1: DEFINITIONS AND TERMS

    1-1.01 GENERAL x Unless the context otherwise requires, wherever in the specifications and other contract documents the following abbreviations and terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as provided in this Section One. x Working titles having a masculine gender, such as "workman" and "journeyman" and the pronoun "he", are utilized in the specifications for the sake of brevity, and are intended to refer to persons of either gender.

    1-1.02 ABBREVIATIONS AAN American Association of Nurserymen.

    AASHTO American Association of State Highway and Transportation Officials.

    AISC American Institute of Steel Construction.

    AISI American Iron and Steel Institute.

    ANSI American National Standards Institute.

    APHA American Public Health Association.

    API American Petroleum Institute.

    AREMA American Railway Engineering and Maintenance-of-Way Association.

    ASME American Society of Mechanical Engineers.

    ASTM American Society for Testing and Materials.

    AWG American Wire Gage.

    AWPA American Wood-Preservers' Association.

    AWS American Welding Society.

    AWWA American Water Works Association.

    EIA Electronic Industries Association.

    IEEE Institute of Electrical and Electronics Engineers.

    NEMA National Electrical Manufacturers Association.

    UL Underwriters' Laboratories Inc.

    1

  • x

    SECTION 1 DEFINITIONS AND TERMS

    UNITS OF MEASUREMENT Some of the symbols for U. S. Customary units of measurement used in the

    specifications and in the Engineer's Estimate are defined as follows:

    Symbols as used in the Specifications

    Symbols as used in the Engineer's Estimate Definitions

    A amperes ACRE acre

    CF cubic foot CY cubic yard

    EA each g gram

    ksi kips per square inch GAL gallon

    h H hour LB pound

    LS lump sum LF linear foot

    LNMI lane mile MFBM thousand foot board measure

    MI mile MSYD thousand station yard

    ohm pcf pounds per cubic foot s second

    STA 100 feet SQFT square foot SQYD square yard TAB tablet

    ton TON 2,000 pounds W watt V volt

    1-1.03 ACCEPTANCE x The formal written acceptance by the Director of Transportation of an entire contract which has been completed in all respects in accordance with the plans and specifications and any modifications thereof previously approved.

    1-1.04 (BLANK)

    1-1.05 BASE x A layer of specified material of planned thickness placed immediately below the pavement or surfacing.

    1-1.06 BASEMENT MATERIAL x The material in excavation or embankments underlying the lowest layer of subbase, base, pavement, surfacing or other specified layer which is to be placed.

    2

  • 4

    SECTION 1 DEFINITIONS AND TERMS

    1-1.07 BIDDER x Any individual, firm, partnership, corporation, or combination thereof, submitting a proposal for the work contemplated, acting directly or through a duly authorized representative.

    1-1.08 BRIDGE x Any structure, with a bridge number, which carries a utility facility, or railroad, highway, pedestrian or other traffic, over a water course or over or under or around any obstruction.

    1-1.085 CONDUIT x A pipe or tube in which smaller pipes, tubes or electrical conductors are inserted or are to be inserted.

    1-1.09 CONTRACT x The written agreement covering the performance of the work and the furnishing of labor, materials, tools and equipment in the construction of the work. The contract shall include the notice to contractors, proposal, plans, specifications, special provisions and contract bonds; also any and all supplemental agreements amending or extending the work contemplated and which may be required to complete the work in a substantial and acceptable manner. Supplemental agreements are written agreements covering alterations, amendments or extensions to the contract and include contract change orders.

    1-1.10 CONTRACTOR x The person or persons, firm, partnership, corporation, or combination thereof, private or municipal, who have entered into a contract with the Department of Transportation, as party or parties of the second part or their legal representatives.

    1-1.11 CULVERT x Any structure, other than a bridge, which provides an opening under a roadway for drainage or other purposes.

    1-1.12 DAYS x Unless otherwise designated, days as used in the specifications will be understood to mean calendar days.

    1-1.13 DEPARTMENT x The Department of Transportation of the State of California, as created by law.

    1-1.14 DETOUR x A temporary route for traffic around a closed portion of a road.

    1-1.15 DIRECTOR x The executive officer of the Department of Transportation, as created by law.

    1-1.16 DIVIDED HIGHWAY x A highway with separated traveled ways for traffic, generally in opposite directions.

    3

  • SECTION 1 DEFINITIONS AND TERMS

    1-1.17 (BLANK)

    1-1.18 ENGINEER x The Chief Engineer, Department of Transportation, acting either directly or through properly authorized agents, the agents acting within the scope of the particular duties delegated to them.

    1-1.19 ENGINEER'S ESTIMATE x The list of estimated quantities of work to be performed as contained in the "Proposal Form."

    1-1.20 FEDERAL AGENCIES x Whenever, in the specifications, reference is made to any Federal agency or officer, the reference shall be deemed made to any agency or officer succeeding in accordance with law to the powers, duties, jurisdiction and authority of the agency or officer mentioned.

    1-1.21 FIXED COSTS x Any necessary labor, material and equipment costs directly expended on the item or items under consideration which remain constant regardless of the quantity of the work done.

    1-1.22 FRONTAGE ROAD x A local street or road auxiliary to and located generally on the side of an arterial highway for service to abutting property and adjacent areas and for control of access.

    1-1.23 GRADING PLANE x The surface of the basement material upon which the lowest layer of subbase, base, pavement, surfacing or other specified layer is placed.

    1-1.24 HIGHWAY x The whole right of way or area which is reserved for and secured for use in constructing the roadway and its appurtenances.

    1-1.25 LABORATORY x The Division of Engineering Services - Materials Engineering and Testing Services and Division of Engineering Services - Geotechnical Services of the Department of Transportation, or established laboratories of the various Districts of the Department, or other laboratories authorized by the Department to test materials and work involved in the contract. When a reference is made in the specifications to the "Transportation Laboratory", the reference shall mean Division of Engineering Services - Materials Engineering and Testing Services and Division of Engineering Services - Geotechnical Services, located at 5900 Folsom Boulevard, Sacramento, CA 95819, Telephone (916) 227-7000.

    1-1.255 LEGAL HOLIDAYS x Those days designated as State holidays in the Government Code.

    4

  • 5

    SECTION 1 DEFINITIONS AND TERMS

    1-1.26 LIQUIDATED DAMAGES x The amount prescribed in the specifications, pursuant to the authority of Public Contract Code Section 10226, to be paid to the State or to be deducted from any payments due or to become due the Contractor for each day's delay in completing the whole or any specified portion of the work beyond the time allowed in the specifications.

    1-1.265 MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES x The Manual on Uniform Traffic Control Devices for Streets and Highways, 2003 Edition (MUTCD) is administered by the Federal Highway Administration.

    1-1.266 MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES CALIFORNIA SUPPLEMENT x The MUTCD 2003 California Supplement (MUTCD California Supplement) is issued by the Department of Transportation to provide amendments to the MUTCD. The MUTCD and MUTCD California Supplement supersede the Department's Manual of Traffic Controls.

    1-1.27 MEDIAN x That portion of a divided highway separating the traveled ways for traffic in opposite directions including inside shoulders.

    1-1.275 OFFICES OF STRUCTURE DESIGN x The Offices of Structure Design of the Department of Transportation. When the specifications require working drawings to be submitted to the Offices of Structure Design, the drawings shall be submitted to: Offices of Structure Design, Documents Unit, Mail Station 9-4/4I, 1801 30th Street, Sacramento, CA 95816, Telephone (916) 227-8252.

    1-1.28 PAVEMENT x The uppermost layer of material placed on the traveled way or shoulders. This term is used interchangeably with surfacing.

    1-1.29 PLANS x The official project plans and Standard Plans, profiles, typical cross sections, working drawings and supplemental drawings, or reproductions thereof, approved by the Engineer, which show the location, character, dimensions and details of the work to be performed. These documents are to be considered as a part of the plans. x In the above definition, the following terms are defined as follows:

    Standard Plans x The Standard Plans issued by the Department of Transportation.

    Project Plans x The project plans are specific details and dimensions peculiar to the work and are supplemented by the Standard Plans insofar as the same may apply.

    1-1.30 PROCESSING x Any operation or operations of whatever nature and extent required to produce a specified material.

    5

  • SECTION 1 DEFINITIONS AND TERMS

    1-1.31 PROPOSAL x The offer of the bidder for the work when made out and submitted on the prescribed proposal form, properly signed and guaranteed.

    1-1.32 PROPOSAL FORM x The approved form upon which the Department of Transportation requires formal bids be prepared and submitted for the work.

    1-1.33 PROPOSAL GUARANTY x The cash, cashier's check, certified check or bidder's bond accompanying the proposal submitted by the bidder, as a guaranty that the bidder will enter into a contract with the Department of Transportation for the performance of the work if the contract is awarded to the bidder.

    1-1.34 ROADBED x The roadbed is that area between the intersection of the upper surface of the roadway and the side slopes or curb lines. The roadbed rises in elevation as each increment or layer of subbase, base, surfacing or pavement is placed. Where the medians are so wide as to include areas of undisturbed land, a divided highway is considered as including 2 separate roadbeds.

    1-1.35 ROADWAY x That portion of the highway included between the outside lines of sidewalks, or curbs, slopes, ditches, channels, waterways, and including all the appertaining structures, and other features necessary to proper drainage and protection.

    1-1.36 SHOULDERS x The portion of the roadway contiguous with the traveled way for accommodation of stopped vehicles, for emergency use, and for lateral support of base and surface courses.

    1-1.37 SPECIAL PROVISIONS x The special provisions are specific clauses setting forth conditions or requirements peculiar to the work and supplementary to these Standard Specifications. The Department of Transportation publication entitled Labor Surcharge And Equipment Rental Rates is to be considered as a part of the special provisions.

    1-1.38 SPECIFICATIONS x The directions, provisions and requirements contained in these Standard Specifications as supplemented by the special provisions. Whenever the term "these specifications" or "these Standard Specifications" is used in this book, it means the provisions set forth in this book.

    1-1.39 STATE x The State of California, including the Department, California Highway Patrol, or any other State of California agency whose action or oversight is related to the work.

    6

  • 6

    SECTION 1 DEFINITIONS AND TERMS

    1-1.40 STATE CONTRACT ACT x Chapter 1, Part 2, Division 2 of the Public Contract Code. The provisions of this act and other applicable laws form and constitute a part of the provisions of this contract to the same extent as if set forth herein in full.

    1-1.41 SUBBASE x A layer of specified material of planned thickness between a base and the basement material.

    1-1.42 SUBGRADE x That portion of the roadbed on which pavement, surfacing, base, subbase, or a layer of any other material is placed.

    1-1.43 SUBSTRUCTURE x All that part of the bridge below the bridge seats, tops of piers, haunches of rigid frames, or below the spring lines of arches. Backwalls and parapets of abutments and wingwalls of bridges shall be considered as parts of the substructure.

    1-1.44 SUPERSTRUCTURE x All that part of the bridge except the bridge substructure.

    1-1.45 SURFACING x The uppermost layer of material placed on the traveled way, or shoulders. This term is used interchangeably with pavement.

    1-1.46 TRAFFIC LANE x That portion of a traveled way for the movement of a single line of vehicles.

    1-1.47 TRAVELED WAY x That portion of the roadway for the movement of vehicles, exclusive of shoulders.

    1-1.48 WORK x All the work specified, indicated, shown or contemplated in the contract to construct the improvement, including all alterations, amendments or extensions thereto made by contract change order or other written orders of the Engineer.

    7

  • 7

    SECTION 2: PROPOSAL REQUIREMENTS AND CONDITIONS

    2-1.01 CONTENTS OF PROPOSAL FORMS x Prospective bidders will be furnished with proposal forms which will refer to the special provisions and project plans for the work to be done and will include a schedule of items for which bid prices are asked, showing the approximate estimate of the various quantities and kinds of work to be performed or materials to be furnished.

    2-1.02 APPROXIMATE ESTIMATE x The quantities given in the proposal and contract are approximate only, being given as a basis for the comparison of bids. The Department does not, expressly or by implication, agree that the actual amount of work will correspond therewith, and reserves the right to increase or decrease the amount of any class or portion of the work, or to omit portions of the work, as may be deemed necessary or advisable by the Engineer.

    2-1.03 EXAMINATION OF PLANS, SPECIFICATIONS, CONTRACT, AND SITE OF WORK x The bidder shall examine carefully the site of the work contemplated, the plans and specifications, and the proposal and contract forms therefor. The submission of a bid shall be conclusive evidence that the bidder has investigated and is satisfied as to the general and local conditions to be encountered, as to the character, quality and scope of work to be performed, the quantities of materials to be furnished and as to the requirements of the proposal, plans, specifications and the contract. x The submission of a bid shall also be conclusive evidence that the bidder is satisfied as to the character, quality and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information was reasonably ascertainable from an inspection of the site and the records of exploratory work done by the Department as shown in the bid documents, as well as from the plans and specifications made a part of the contract. x Where the Department has made investigations of site conditions including subsurface conditions in areas where work is to be performed under the contract, or in other areas, some of which may constitute possible local material sources, bidders or contractors may, upon written request, inspect the records of the Department as to those investigations subject to and upon the conditions hereinafter set forth. x Where there has been prior construction by the Department or other public agencies within the project limits, records of the prior construction that are currently in the possession of the Department and which have been used by, or are known to, the designers and administrators of the project will be made available for inspection by bidders or contractors, upon written request, subject to the conditions hereinafter set forth. The records may include, but are not limited to, as-built drawings, design calculations, foundation and site studies, project reports and other data assembled in connection with the investigation, design, construction and maintenance of the prior projects.

    9

  • SECTION 2 PROPOSAL REQUIREMENTS AND CONDITIONS

    x Inspection of the records of investigations and project records may be made at the office of the district in which the work is situated, or in the case of records of investigations related to structure work, at the Transportation Laboratory in Sacramento, California. x When a log of test borings or other record of geotechnical data obtained by the Department's investigation of surface and subsurface conditions is included with the contract plans, it is furnished for the bidders' or Contractor's information and its use shall be subject to the conditions and limitations set forth in this Section 2-1.03. x In some instances, information considered by the Department to be of possible interest to bidders or contractors has been compiled as "Materials Information." The use of the "Materials Information" shall be subject to the conditions and limitations set forth in this Section 2-1.03 and Section 6-2, "Local Materials." x When cross sections are not included with the plans, but are available, bidders or contractors may inspect the cross sections and obtain copies for their use, at their expense. x When cross sections are included with the contract plans, it is expressly understood and agreed that the cross sections do not constitute part of the contract, do not necessarily represent actual site conditions or show location, character, dimensions and details of work to be performed, and are included in the plans only for the convenience of bidders and their use is subject to the conditions and limitations set forth in this Section 2-1.03. x When contour maps were used in the design of the project, the bidders may inspect those maps, and if available, they may obtain copies for their use. x The availability or use of information described in this Section 2-1.03 is not to be construed in any way as a waiver of the provisions of the first paragraph in this Section 2-1.03 and bidders and contractors are cautioned to make independent investigations and examinations as they deem necessary to be satisfied as to conditions to be encountered in the performance of the work and, with respect to possible local material sources, the quality and quantity of material available from the property and the type and extent of processing that may be required in order to produce material conforming to the requirements of the specifications. x The Department assumes no responsibility for conclusions or interpretations made by a bidder or contractor based on the information or data made available by the Department. The Department does not assume responsibility for representation made by its officers or agents before the execution of the contract concerning surface or subsurface conditions, unless that representation is expressly stated in the contract. x No conclusions or interpretations made by a bidder or contractor from the information and data made available by the Department will relieve a bidder or contractor from properly fulfilling the terms of the contract.

    2-1.04 (BLANK)

    2-1.05 PROPOSAL FORMS x The Department will furnish to each bidder a standard proposal form, which, when filled out and executed may be submitted as that bidder's bid. Bids not

    10

  • 8

    SECTION 2 PROPOSAL REQUIREMENTS AND CONDITIONS

    presented on forms so furnished, and copies or facsimiles of the bidder's completed and executed proposal forms submitted as a bid will be rejected. x The proposal form is bound together with the contract in a book entitled "Proposal and Contract." The proposal shall set forth the item prices and totals, in clearly legible figures, in the respective spaces provided, and shall be signed by the bidder, who shall fill out all blanks in the proposal form as therein required. x The proposal shall be submitted as directed in the "Notice to Contractors" under sealed cover plainly marked as a proposal, and identifying the project to which the proposal relates and the date of the bid opening therefor. Proposals which are not properly marked may be disregarded. x All proposal forms other than for "District Opening" projects shall be obtained from the Department of Transportation, Plans and Bid Documents, Room 0200, Transportation Building, 1120 N Street, Sacramento, California 95814, or as otherwise designated in the "Notice to Contractor." x Proposals for "District Opening" projects shall be made on forms obtained from the District Director of Transportation in whose district the work is to be performed, but in all other respects the provisions in this Section 2-1.05 shall apply.

    2-1.054 REQUIRED LISTING OF PROPOSED SUBCONTRACTORS x Each proposal shall have listed therein the name and address of each subcontractor to whom the bidder proposes to subcontract portions of the work in an amount in excess of one-half of one percent of the total bid or $10,000, whichever is greater, in accordance with the Subletting and Subcontracting Fair Practices Act, commencing with Section 4100 of the Public Contract Code. The bidder's attention is invited to other provisions of the Act related to the imposition of penalties for a failure to observe its provisions by using unauthorized subcontractors or by making unauthorized substitutions. x A sheet for listing the subcontractors, as required herein, is included in the "Proposal and Contract" book.

    2-1.056 STATE EMPLOYEES AND DESIGN ENGINEERS MAY NOT BID ON CONSTRUCTION CONTRACT x No employee of the State shall be eligible to submit a proposal for, nor to subcontract for any portion of, nor to supply any materials for any contract administered by the Department. x No engineering or architectural firm which has provided design services for a project shall be eligible to submit a proposal for the contract to construct the project nor to subcontract for any portion of the work. The ineligible firms include the prime contractor for design, subcontractors of portions of the design and affiliates of either. An affiliate is a firm which is subject to the control of the same persons, through joint ownership or otherwise.

    2-1.06 REJECTION OF PROPOSALS x Proposals may be rejected if they have been transferred to another bidder, or if they show any alteration of form, additions not called for, conditional bids, incomplete bids, erasures, or irregularities of any kind. x When proposals are signed by an agent, other than the officer or officers of a corporation authorized to sign contracts on its behalf or a member of a partnership,

    11

  • SECTION 2 PROPOSAL REQUIREMENTS AND CONDITIONS

    a "Power of Attorney" must be on file with the Department prior to opening bids or shall be submitted with the proposal; otherwise, the proposal may be rejected as irregular and unauthorized.

    2-1.07 PROPOSAL GUARANTY x All bids shall be presented under sealed cover and accompanied by one of the following forms of bidder's security:

    Cash, a cashier's check, a certified check, or a bidder's bond executed by an admitted surety insurer, made payable to the Director of Transportation.

    x The security shall be in an amount equal to at least 10 percent of the amount bid. A bid will not be considered unless one of the forms of bidder's security is enclosed with it. x The bidder's bond shall conform to the bond form in the book entitled "Proposal and Contract" for the project and shall be properly filled out and executed. The bidder's bond form included in that book may be used. Upon request "Bidder's Bond" forms may be obtained from the Department.

    2-1.08 WITHDRAWAL OF PROPOSALS x Any bid may be withdrawn at any time prior to the date and time fixed for the opening of bids only by written request for the withdrawal of the bid filed at the location at which the bid was received by the Department. The request shall be executed by the bidder or the bidder's duly authorized representative. The withdrawal of a bid does not prejudice the right of the bidder to file a new bid. Whether or not bids are opened exactly at the time fixed for opening bids, a bid will not be received after that time, nor may any bid be withdrawn after the time fixed for the opening of bids.

    2-1.09 PUBLIC OPENING OF PROPOSALS x Proposals will be opened and read publicly at the time and place indicated in the "Notice to Contractors." Bidders or their authorized agents are invited to be present.

    2-1.095 RELIEF OF BIDDERS x Attention is directed to the provisions of Public Contract Code Sections 5100 to 5107, inclusive, concerning relief of bidders and in particular to the requirement therein, that if the bidder claims a mistake was made in the bid presented, the bidder shall give the Department written notice within 5 days after the opening of the bids of the alleged mistake, specifying in the notice in detail how the mistake occurred.

    2-1.10 DISQUALIFICATION OF BIDDERS x More than one proposal from an individual, firm, partnership, corporation, or combination thereof under the same or different names will not be considered. Reasonable grounds for believing that any individual, firm, partnership, corporation or combination thereof is interested in more than one proposal for the work contemplated may cause the rejection of all proposals in which that individual, firm, partnership, corporation or combination thereof is interested. If there is

    12

  • 9

    SECTION 2 PROPOSAL REQUIREMENTS AND CONDITIONS

    reason for believing that collusion exists among the bidders any or all proposals may be rejected. Proposals in which the prices obviously are unbalanced may be rejected.

    2-1.105 PREVIOUS DISQUALIFICATION, REMOVAL OR OTHER PREVENTION OF BIDDING x Pursuant to Section 10162 of the Public Contract Code the bidder shall complete, under penalty of perjury, the questionnaire in the Proposal relating to previous disqualification, removal or other prevention of bidding of the bidder, or officers or employees of the bidder because of violation of law or a safety regulation. x A bid may be rejected on the basis of a bidder, any officer of the bidder, or any employee of the bidder who has a proprietary interest in the bidder, having been disqualified, removed, or otherwise prevented from bidding on, or completing a federal, state or local project because of a violation of law or a safety regulation.

    2-1.108 COMPLIANCE WITH ORDERS OF THE NATIONAL LABOR RELATIONS BOARD x Pursuant to Public Contract Code Section 10232, the Contractor shall swear by a statement, under penalty of perjury, that no more than one final, unappealable finding of contempt of court by a Federal court has been issued against the Contractor within the immediately preceding 2-year period because of the Contractor's failure to comply with an order of a Federal court which orders the Contractor to comply with an order of the National Labor Relations Board. For purposes of Section 10232, a finding of contempt does not include any finding which has been vacated, dismissed, or otherwise removed by the court because the Contractor has complied with the order which was the basis for the finding. The State may rescind any contract in which the Contractor falsely swears to the truth of the statement required by Section 10232. x The statement required by Public Contract Code Section 10232 is on the page preceding the signature page of the Proposal.

    2-1.11 INELIGIBILITY TO CONTRACT x Public Contract Code Section 10285.1 provides as follows:

    Any state agency may suspend, for a period of up to three years from the date of conviction, any person from bidding upon, or being awarded, a public works or services contract with the agency under this part or from being a subcontractor at any tier upon the contract, if that person, or any partner, member, officer, director, responsible managing officer, or responsible managing employee thereof, has been convicted by a court of competent jurisdiction of any charge of fraud, bribery, collusion, conspiracy, or any other act in violation of any state or federal antitrust law in connection with the bidding upon, award of, or performance of any public works contract, as defined in Section 1101, with any public entity, as defined in Section 1100, including, for the purposes of this article, the Regents of the University of California or the Trustees of the California State University. A state agency may determine the eligibility of any person to enter into a contract under this

    13

  • SECTION 2 PROPOSAL REQUIREMENTS AND CONDITIONS

    article by requiring the person to submit a statement under penalty of perjury declaring that neither the person nor any subcontractor to be engaged by the person has been convicted of any of the offenses referred to in this section within the preceding three years.

    x A form for the statement required by Section 10285.1 is included in the Proposal.

    2-1.12 MATERIAL GUARANTY x The successful bidder may be required to furnish a written guaranty covering certain items of work for varying periods of time from the date of acceptance of the contract. The work to be guaranteed, the form and the time limit of the guaranty will be specified in the special provisions. The guaranty shall be signed and delivered to the Engineer before acceptance of the contract. Upon completion of the contract the amounts of the 2 contract bonds required in Section 3-1.02, "Contract Bonds," may be reduced to conform to the total amount of the contract bid prices for the items of work to be guaranteed, and this amount shall continue in full force and effect for the duration of the guaranty period. The payment bond shall not be reduced until the expiration of the time required by Section 3249 of the Civil Code.

    14

  • 10

    SECTION 3: AWARD AND EXECUTION OF CONTRACT

    3-1.01 AWARD OF CONTRACT x The right is reserved to reject any and all proposals. x The award of the contract, if it be awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed. The award, if made, will be made within 30 days after the opening of the proposals. This period will be subject to extension for such further period as may be agreed upon in writing between the Department and the bidder concerned. x All bids will be compared on the basis of the Engineer's Estimate of the quantities of work to be done.

    3-1.02 CONTRACT BONDS x The successful bidder shall furnish the 2 bonds required by the State Contract Act. One bond shall secure the payment of the claims of laborers, mechanics or materialmen employed on the work under the contract, and the other bond shall guarantee the faithful performance of the contract. The bond forms will be furnished to the successful bidder by the Department. x Except as otherwise provided in Section 3248 of the Civil Code and Section 30154 of the Streets and Highways Code, the payment bond shall be in a sum equal to the contract price and the performance bond shall be in a sum equal to at least one-half of the contract price. x All alterations, extensions of time, extra and additional work, and other changes authorized by these specifications or any part of the contract may be made without securing the consent of the surety or sureties on the contract bonds.

    3-1.025 INSURANCE POLICIES x The successful bidder shall submit:

    A. Copy of its commercial general liability policy and its excess policy, including the declarations page, all amendments, riders, endorsements, and other modifications in effect at the time of contract execution. Standard ISO form No. CG 0001 or similar exclusions are allowed if not inconsistent with Section 7-1.12, "Indemnification and Insurance." Allowance of any additional exclusions is at the discretion of the Department.

    B. Certificate of Insurance showing all other required coverages. Certificates of Insurance, as evidence of required insurance for the auto liability and any other required policy shall set forth deductible amounts applicable to each policy and all exclusions that are added by endorsement to each policy. The evidence of insurance shall provide that no cancellation, lapse, or reduction of coverage will occur without 30 days prior written notice to the Department.

    x If the successful bidder uses any form of self-insurance, it shall submit:

    A. A notice of election to self-insure.

    15

  • SECTION 3 AWARD AND EXECUTION OF CONTRACT

    B. The coverages for which self-insurance applies. C. The amount of self-insurance. D. Declaration under the penalty of perjury by a certified public accountant

    certifying the accountant has applied Generally Accepted Accounting Principles (GAAP) guidelines and the successful bidder has sufficient funds or other resources to cover the self-insurance amounts.

    E. Copy of its commercial general liability policy and its excess policy, including the declarations page, all amendments, riders, endorsements and other modifications in effect at the time of contract execution, for those amounts not covered by self-insurance.

    3-1.03 EXECUTION OF CONTRACT x The contract shall be signed by the successful bidder and returned, together with the contract bonds, copy of insurance policies, and Certificates of Insurance, with documents to verify any self-insurance coverage within 10 days, not including Saturdays, Sundays and legal holidays, after the bidder has received the contract for execution.

    3-1.04 FAILURE TO EXECUTE CONTRACT x Failure of the lowest responsible bidder, the second lowest responsible bidder, or the third lowest responsible bidder to execute the contract and file acceptable bonds as provided herein within 10 days, not including Saturdays, Sundays and legal holidays, after that bidder has received the contract for execution shall be just cause for the forfeiture of the proposal guaranty. The successful bidder may file with the Department a written notice, signed by the bidder or the bidder's authorized representative, specifying that the bidder will refuse to execute the contract if it is presented. The filing of this notice shall have the same force and effect as the failure of the bidder to execute the contract and furnish acceptable bonds within the time hereinbefore prescribed.

    3-1.05 RETURN OF PROPOSAL GUARANTIES x The proposal guaranties accompanying the proposals of the first, second and third lowest responsible bidders will be retained until the contract has been finally executed, after which those proposal guaranties, except bidders' bonds and any guaranties which have been forfeited, will be returned to the respective bidders whose proposals they accompany. The proposal guaranties, other than bidder's bonds, submitted by all other unsuccessful bidders will be returned upon determination, by the Department, of the first, second and third lowest responsible bidders.

    16

  • 11

    SECTION 4: SCOPE OF WORK

    4-1.01 INTENT OF PLANS AND SPECIFICATIONS x The intent of the plans and specifications is to prescribe the details for the construction and completion of the work which the Contractor undertakes to perform in accordance with the terms of the contract. Where the plans or specifications describe portions of the work in general terms, but not in complete detail, it is understood that only the best general practice is to prevail and that only materials and workmanship of the first quality are to be used. Unless otherwise specified, the Contractor shall furnish all labor, materials, tools, equipment, and incidentals, and do all the work involved in executing the contract in a satisfactory and workmanlike manner.

    4-1.02 FINAL CLEANING UP x Before final inspection of the work, the Contractor shall clean the highway, material sites and all ground occupied by the Contractor in connection with the work of all rubbish, excess materials, falsework, temporary structures and equipment. All parts of the work shall be left in a neat and presentable condition. Full compensation for final cleaning up will be considered as included in the prices paid for the various contract items of work and no separate payment will be made therefor. x Nothing herein, however, shall require the Contractor to remove warning, regulatory, and guide signs prior to formal acceptance by the Director.

    4-1.03 CHANGES x The Department reserves the right to make such alterations, deviations, additions to or deletions from the plans and specifications, including the right to increase or decrease the quantity of any item or portion of the work or to delete any item or portion of the work, as may be deemed by the Engineer to be necessary or advisable and to require such extra work as may be determined by the Engineer to be required for the proper completion or construction of the whole work contemplated. x Those changes will be set forth in a contract change order which will specify, in addition to the work to be done in connection with the change made, adjustment of contract time, if any, and the basis of compensation for that work. A contract change order will not become effective until approved by the Engineer. x Upon receipt of an approved contract change order, the Contractor shall proceed with the ordered work. If ordered in writing by the Engineer, the Contractor shall proceed with the work so ordered prior to actual receipt of an approved contract change order therefor. In those cases, the Engineer will, as soon as practicable, issue an approved contract change order for the ordered work and the provisions in Section 4-1.03A, "Procedure and Protest," shall be fully applicable to the subsequently issued contract change order. x When the compensation for an item of work is subject to adjustment under the provisions of this Section 4-1.03, the Contractor shall, upon request, furnish the Engineer with adequate detailed cost data for that item of work. If the Contractor

    17

  • SECTION 4 SCOPE OF WORK

    requests an adjustment in compensation for an item of work as provided in Sections 4-1.03B(1) or 4-1.03B(2), the cost data shall be submitted with the request.

    4-1.03A Procedure and Protest x A contract change order approved by the Engineer may be issued to the Contractor at any time. Should the Contractor disagree with any terms or conditions set forth in an approved contract change order not executed by the Contractor, the Contractor shall submit a written protest to the Engineer within 15 days after the receipt of the approved contract change order. The protest shall state the points of disagreement, and, if possible, the contract specification references, quantities and costs involved. If a written protest is not submitted, payment will be made as set forth in the approved contract change order, and that payment shall constitute full compensation for all work included therein or required thereby. Unprotested approved contract change orders will be considered as executed contract change orders as that term is used in Sections 4-1.03B to 4-1.03D, inclusive. x Where the protest concerning an approved contract change order relates to compensation, the compensation payable for all work specified or required by that contract change order to which the protest relates will be determined as provided in Sections 4-1.03B to 4-1.03D, inclusive. The Contractor shall keep full and complete records of the cost of that work and shall permit the Engineer to have access thereto as may be necessary to assist in the determination of the compensation payable for that work. x Where the protest concerning an approved contract change order relates to the adjustment of contract time for the completion of the work, the time to be allowed therefor will be determined as provided in Section 8-1.07, "Liquidated Damages." x Proposed contract change orders may be presented to the Contractor for consideration prior to approval by the Engineer. If the Contractor signifies acceptance of the terms and conditions of the proposed contract change order by executing the document and if the change order is approved by the Engineer and issued to the Contractor, payment in accordance with the provisions as to compensation therein set forth shall constitute full compensation for all work included therein or required thereby. A contract change order executed by the Contractor and approved by the Engineer is an executed contract change order as that term is used in Sections 4-1.03B to 4-1.03D, inclusive. An approved contract change order shall supersede a proposed, but unapproved, contract change order covering the same work. x The Engineer may provide for an adjustment of compensation as to a contract item of work included in a contract change order determined as provided in Sections 4-1.03B to 4-1.03D, inclusive, if that item of work is eligible for an adjustment of compensation thereunder.

    4-1.03B Increased or Decreased Quantities x Increases or decreases in the quantity of a contract item of work will be determined by comparing the total pay quantity of that item of work with the Engineer's Estimate therefor.

    18

  • 12

    SECTION 4 SCOPE OF WORK

    x If the total pay quantity of any item of work required under the contract varies from the Engineer's Estimate therefor by 25 percent or less, payment will be made for the quantity of work of the item performed at the contract unit price therefor, unless eligible for adjustment pursuant to Section 4-1.03C, "Changes in Character of Work." x If the total pay quantity of any item of work required under the contract varies from the Engineer's Estimate therefor by more than 25 percent, in the absence of an executed contract change order specifying the compensation to be paid, the compensation payable to the Contractor will be determined in accordance with Sections 4-1.03B(1), 4-1.03B(2), or 4-1.03B(3), as the case may be.

    4-1.03B(1) Increases of More Than 25 Percent x Should the total pay quantity of any item of work required under the contract exceed the Engineer's Estimate therefor by more than 25 percent, the work in excess of 125 percent of the estimate and not covered by an executed contract change order specifying the compensation to be paid therefor will be paid for by adjusting the contract unit price, as hereinafter provided, or at the option of the Engineer, payment for the work involved in the excess will be made on the basis of force account as provided in Section 9-1.03. x The adjustment of the contract unit price will be the difference between the contract unit price and the actual unit cost, which will be determined as hereinafter provided, of the total pay quantity of the item. If the costs applicable to the item of work include fixed costs, the fixed costs will be deemed to have been recovered by the Contractor by the payments made for 125 percent of the Engineer's Estimate of the quantity for the item, and in computing the actual unit cost, the fixed costs will be excluded. Subject to the above provisions, the actual unit cost will be determined by the Engineer in the same manner as if the work were to be paid for on a force account basis as provided in Section 9-1.03; or the adjustment will be as agreed to by the Contractor and the Engineer. x When the compensation payable for the number of units of an item of work performed in excess of 125 percent of the Engineer's Estimate is less than $5,000 at the applicable contract unit price, the Engineer reserves the right to make no adjustment in the contract unit price if the Engineer so elects, except that an adjustment will be made if requested in writing by the Contractor.

    4-1.03B(2) Decreases of More Than 25 Percent x Should the total pay quantity of any item of work required under the contract be less than 75 percent of the Engineer's Estimate therefor, an adjustment in compensation pursuant to this Section will not be made unless the Contractor so requests in writing. If the Contractor so requests, the quantity of the item performed, unless covered by an executed contract change order specifying the compensation payable therefor, will be paid for by adjusting the contract unit price as hereinafter provided, or at the option of the Engineer, payment for the quantity of the work of the item performed will be made on the basis of force account as provided in Section 9-1.03, provided however, that in no case shall the payment for that work be less than that which would be made at the contract unit price.

    19

  • SECTION 4 SCOPE OF WORK

    x The adjustment of the contract unit price will be the difference between the contract unit price and the actual unit cost, which will be determined as hereinafter provided, of the total pay quantity of the item, including fixed costs. The actual unit cost will be determined by the Engineer in the same manner as if the work were to be paid for on a force account basis as provided in Section 9-1.03; or the adjustment will be as agreed to by the Contractor and the Engineer. x The payment for the total pay quantity of the item of work will in no case exceed the payment which would be made for the performance of 75 percent of the Engineer's Estimate of the quantity for the item at the original contract unit price.

    4-1.03B(3) Eliminated Items x Should any contract item of the work be eliminated in its entirety, in the absence of an executed contract change order covering the elimination, payment will be made to the Contractor for actual costs incurred in connection with the eliminated contract item if incurred prior to the date of notification in writing by the Engineer of the elimination. x If acceptable material is ordered by the Contractor for the eliminated item prior to the date of notification of the elimination by the Engineer, and if orders for that material cannot be canceled, the material will be paid for at the actual cost to the Contractor. In this case, the material paid for shall become the property of the State, and the actual cost of any further handling will be paid for. If the material is returnable to the vendor and if the Engineer so directs, the material shall be returned and the Contractor will be paid for the actual cost of charges made by the vendor for returning the material. The actual cost of handling returned material will be paid for. x The actual costs or charges to be paid by the Department to the Contractor as provided in this Section 4-1.03B(3) will be computed in the same manner as if the work were to be paid for on a force account basis as provided in Section 9-1.03.

    4-1.03C Changes in Character of Work x If an ordered change in the plans or specifications materially changes the character of the work of a contract item from that on which the Contractor based the bid price, and if the change increases or decreases the actual unit cost of the changed item as compared to the actual or estimated actual unit cost of performing the work of that item in accordance with the plans and specifications originally applicable thereto, in the absence of an executed contract change order specifying the compensation payable, an adjustment in compensation therefor will be made in accordance with the following. x The basis of the adjustment in compensation will be the difference between the actual unit cost to perform the work of that item or portion thereof involved in the change as originally planned and the actual unit cost of performing the work of the item or portion thereof involved in the change, as changed. Actual unit costs will be determined by the Engineer in the same manner as if the work were to be paid for on a force account basis as provided in Section 9-1.03; or the adjustment will be as agreed to by the Contractor and the Engineer. The adjustment will apply only to the portion of the work of the item actually changed in character. At the option of

    20

  • 13

    SECTION 4 SCOPE OF WORK

    the Engineer, the work of the item or portion of item which is changed in character will be paid for by force account as provided in Section 9-1.03. x If the compensation for an item of work is adjusted under this Section 4-1.03C, the costs recognized in determining that adjustment shall be excluded from consideration in making an adjustment for that item of work under the provisions in Section 4-1.03B, "Increased or Decreased Quantities." x Failure of the Engineer to recognize a change in character of the work at the time the approved contract change order is issued shall in nowise be construed as relieving the Contractor of the duty and responsibility of filing a written protest within the 15 day limit as provided in Section 4-1.03A, "Procedure and Protest."

    4-1.03D Extra Work x New and unforeseen work will be classed as extra work when determined by the Engineer that the work is not covered by any of the various items for which there is a bid price or by combinations of those items. In the event portions of this work are determined by the Engineer to be covered by some of the various items for which there is a bid price or combinations of those items, the remaining portion of the work will be classed as extra work. Extra work also includes work specifically designated as extra work in the plans or specifications. x The Contractor shall do the extra work and furnish labor, material and equipment therefor upon receipt of an approved contract change order or other written order of the Engineer, and in the absence of an approved contract change order or other written order of the Engineer, the Contractor shall not be entitled to payment for the extra work. x Payment for extra work required to be performed pursuant to the provisions in this Section 4-1.03D, in the absence of an executed contract change order, will be made by force account as provided in Section 9-1.03; or as agreed to by the Contractor and the Engineer.

    4-1.04 DETOURS x The Contractor shall construct and remove detours and detour bridges for the use of public traffic as provided in the special provisions, or as shown on the plans, or as directed by the Engineer. Payment for this work will be made as set forth in the special provisions or at the contract prices for the items of work involved if the work being performed is covered by contract items of work and no other method of payment therefor is provided in the special provisions, otherwise the work will be paid for as extra work as provided in Section 4-1.03D. x The cost of repairing damage to detours caused by public traffic will be paid for as extra work as provided in Section 4-1.03D. x When public traffic is routed through the work, provision for a passageway through construction operations will not be considered as detour construction or detour maintenance, and this work shall conform to and be paid for as provided in Section 7-1.08, "Public Convenience," unless otherwise specified in the special provisions. x Detours used exclusively by the Contractor for hauling materials and equipment shall be constructed and maintained by the Contractor at the Contractor's expense.

    21

  • SECTION 4 SCOPE OF WORK

    x The failure or refusal of the Contractor to construct and maintain detours at the proper time shall be sufficient cause for closing down the work until the detours are in satisfactory condition for use by public traffic. x Where the Contractor's hauling is causing such damage to the detour that its maintenance in a condition satisfactory for public traffic is made difficult and unusually expensive, the Engineer shall have authority to regulate the Contractor's hauling over the detour.

    4-1.05 USE OF MATERIALS FOUND ON THE WORK x Unless designated as selected material as provided in Section 19-2.07, "Selected Material," the Contractor, with the approval of the Engineer, may use in the proposed construction such stone, gravel, sand or other material suitable in the opinion of the Engineer as may be found in excavation. The Contractor will be paid for the excavation of those materials at the contract price for the excavation, but the Contractor shall replace at the Contractor's expense with other suitable material all of that portion of the material so removed and used which was contemplated for use in the work, except that the Contractor need not replace at the Contractor's expense, any material obtained from structure excavation used as structure backfill. No charge for materials so used will be made against the Contractor. The Contractor shall not excavate or remove any material from within the highway location that is not within the excavation, as indicated by the slope and grade lines, without written authorization from the Engineer.

    22

  • 14

    SECTION 5: CONTROL OF WORK

    5-1.01 AUTHORITY OF ENGINEER x The Engineer shall decide all questions which may arise as to the quality or acceptability of materials furnished and work performed and as to the manner of performance and rate of progress of the work; all questions which may arise as to the interpretation of the plans and specifications; all questions as to the acceptable fulfillment of the contract on the part of the Contractor; and all questions as to compensation. The Engineer's decision shall be final, and the Engineer shall have authority to enforce and make effective those decisions and orders which the Contractor fails to carry out promptly.

    5-1.02 PLANS AND WORKING DRAWINGS x The contract plans furnished consist of general drawings and show such details as are necessary to give a comprehensive idea of the construction contemplated. All authorized alterations affecting the requirements and information given on the contract plans shall be in writing. x The contract plans shall be supplemented by such working drawings prepared by the Contractor as are necessary to adequately control the work. No change shall be made by the Contractor in any working drawing after it has been approved by the Engineer. x Working drawings for any part of the permanent work shall include, but not be limited to stress sheets, anchor bolt layouts, shop details, erection plans, equipment lists and any other information specifically required elsewhere in the specifications. x Working drawings for cribs, cofferdams, falsework, temporary support systems, haul bridges, centering and form work and for other temporary work and methods of construction the Contractor proposes to use, shall be submitted when required by the specifications or ordered by the Engineer. Working drawings shall be subject to approval insofar as the details affect the character of the finished work and for compliance with design requirements applicable to the construction when specified or called for, but details of design will be left to the Contractor who shall be responsible for the successful construction of the work. x Working drawings shall be approved by the Engineer before any work involving the drawings is performed. It is expressly understood that approval of the Contractor's working drawings shall not relieve the Contractor of any responsibility under the contract for the successful completion of the work in conformity with the requirements of the plans and specifications. Approval of working drawings shall not operate to waive any of the requirements of the plans and specifications or relieve the Contractor of any obligation thereunder, and defective work, materials and equipment may be rejected notwithstanding the approval. x Full compensation for furnishing all working drawings shall be considered as included in the prices paid for the contract items of work to which the drawings relate and no additional compensation will be allowed therefor.

    5-1.02A Excavation Safety Plans x The Construction Safety Orders of the Division of Occupational Safety and Health shall apply to all excavations. For all excavations 5 feet or more in depth,

    23

  • SECTION 5 CONTROL OF WORK

    the Contractor shall submit to the Engineer a detailed plan showing the design and details of the protective systems to be provided for worker protection from the hazard of caving ground during excavation. The detailed plan shall include any tabulated data and any design calculations used in the preparation of the plan. Excavation shall not begin until the detailed plan has been reviewed and approved by the Engineer. x Detailed plans of protective systems for which the Construction Safety Orders require design by a registered professional engineer shall be prepared and signed by an engineer who is registered as a Civil Engineer in the State of California, and shall include the soil classification, soil properties, soil design calculations that demonstrate adequate stability of the protective system, and any other design calculations used in the preparation of the plan. x No plan shall allow the use of a protective system less effective than that required by the Construction Safety Orders. x If the detailed plan includes designs of protective systems developed only from the allowable configurations and slopes, or Appendices, contained in the Construction Safety Orders, the plan shall be submitted at least 5 days before the Contractor intends to begin excavation. If the detailed plan includes designs of protective systems developed from tabulated data, or designs for which design by a registered professional engineer is required, the plan shall be submitted at least 3 weeks before the Contractor intends to begin excavation. x Attention is directed to Section 7-1.01E, "Trench Safety."

    5-1.03 CONFORMITY WITH CONTRACT DOCUMENTS AND ALLOWABLE DEVIATIONS x Work and materials shall conform to the lines, grades, typical cross sections, dimensions and material requirements, including tolerances, shown on the plans or indicated in the specifications. Although measurement, sampling and testing may be considered evidence as to conformity, the Engineer shall be the sole judge as to whether the work or materials deviate from the plans and specifications, and the Engineer's decision as to any allowable deviations therefrom shall be final.

    5-1.04 COORDINATION AND INTERPRETATION OF PLANS, STANDARD SPECIFICATIONS, AND SPECIAL PROVISIONS x These Standard Specifications, the Standard Plans, project plans, special provisions, contract change orders and all supplementary documents are essential parts of the contract, and a requirement occurring in one is as binding as though occurring in all. They are intended to be complementary, and to describe and provide for a complete work. x Project plans shall govern over Standard Plans; Standard Plans and project plans shall govern over these Standard Specifications; and the special provisions shall govern over both these Standard Specifications and the plans. x Should it appear that the work to be done or any of the matters relative thereto are not sufficiently detailed or explained in these specifications, the special provisions or the plans, the Contractor shall apply to the Engineer for such further explanations as may be necessary and shall conform to them as part of the contract. In the event of any doubt or question arising respecting the true meaning of these

    24

  • 15

    SECTION 5 CONTROL OF WORK

    specifications, the special provisions or the plans, reference shall be made to the Engineer, whose decision thereon shall be final. x In the event of any discrepancy between any drawing and the figures written thereon, the figures shall be taken as correct. Detail drawings shall prevail over general drawings.

    5-1.05 ORDER OF WORK x When required by the special provisions or plans, the Contractor shall follow the sequence of operations as set forth therein. x Full compensation for conforming to those requirements will be considered as included in the prices paid for the various contract items of work and no additional compensation will be allowed therefor.

    5-1.06 SUPERINTENDENCE x The Contractor shall designate in writing before starting work, an authorized representative who shall have the authority to represent and act for the Contractor. x When the Contractor is comprised of 2 or more persons, firms, partnerships or corporations functioning on a joint venture basis, the Contractor shall designate in writing before starting work, the name of one authorized representative who shall have the authority to represent and act for the Contractor. x The authorized representative shall be present at the site of the work at all times while work is actually in progress on the contract. When work is not in progress and during periods when work is suspended, arrangements acceptable to the Engineer shall be made for any emergency work which may be required. x Whenever the Contractor or the Contractor's authorized representative is not present on any particular part of the work where it may be desired to give direction, orders will be given by the Engineer, which shall be received and obeyed by the superintendent or foreman who may have charge of the particular work in reference to which the orders are given. x Any order given by the Engineer, not otherwise required by the specifications to be in writing, will on request of the Contractor, be given or confirmed by the Engineer in writing.

    5-1.07 LINES AND GRADES x Stakes or marks will be set by the Engineer as the Engineer determines to be necessary to establish the lines and grades required for the completion of the work specified in these specifications, on the plans and in the special provisions. x When the Contractor requires the stakes or marks, the Contractor shall notify the Engineer of the requirements in writing a reasonable length of time in advance of starting operations that require the stakes or marks. In no event, shall a notice of less than 2 working days be considered a reasonable length of time. x Stakes and marks set by the Engineer shall be carefully preserved by the Contractor. In case the stakes and marks are destroyed or damaged, the stakes and marks will be replaced at the Engineer's earliest convenience. The Contractor will be charged for the cost of necessary replacement or restoration of stakes and marks which in the judgment of the Engineer were carelessly or willfully destroyed or damaged by the Contractor's operations. This charge will be deducted from any moneys due or to become due the Contractor.

    25

  • SECTION 5 CONTROL OF WORK

    5-1.08 INSPECTION x The Engineer shall, at all times, have safe access to the work during its construction, and shall be furnished with every reasonable facility for ascertaining that the materials and the workmanship are in accordance with the requirements and intentions of these specifications, the special provisions and the plans. All work done and all materials furnished shall be subject to the Engineer's inspection. x The inspection of the work or materials shall not relieve the Contractor of any of the Contractor's obligations to fulfill the contract as prescribed. Work and materials not meeting the requirements shall be made good, and unsuitable work or materials may be rejected, notwithstanding that the work or materials have been previously inspected by the Engineer or that payment therefor has been included in a progress estimate. x Projects financed in whole or in part with Federal funds shall be subject to inspection at all times by the Federal agency involved.

    5-1.09 REMOVAL OF REJECTED AND UNAUTHORIZED WORK x All work which has been rejected shall be remedied, or removed and replaced by the Contractor in an acceptable manner, and no compensation will be allowed to the Contractor for the removal, replacement or remedial work. x Any work done beyond the lines and grades shown on the plans or established by the Engineer, or any extra work done without written authority will be considered as unauthorized work and will not be paid for. Upon order of the Engineer unauthorized work shall be remedied, removed or replaced at the Contractor's expense. x Upon failure of the Contractor to comply promptly with any order of the Engineer made under this Section 5-1.09, the Department may cause rejected or unauthorized work to be remedied, removed or replaced, and to deduct the costs from any moneys due or to become due the Contractor.

    5-1.10 EQUIPMENT AND PLANTS x Only equipment and plants suitable to produce the quality of work and materials required will be permitted to operate on the project. x Plants shall be designed and constructed in accordance with general practice for the equipment and shall be of sufficient capacity to ensure the production of sufficient material to carry the work to completion within the time limit. x The Contractor shall provide adequate and suitable equipment and plants to meet the above requirements, and when ordered by the Engineer shall remove unsuitable equipment from the work and discontinue the operation of unsatisfactory plants. x The Contractor shall identify each piece of equipment, other than hand tools, by means of an identifying number plainly stenciled or stamped on the equipment at a conspicuous location, and shall furnish to the Engineer a list giving the description of each piece of equipment and its identifying number. In addition, the make, model number and empty gross weight of each unit of compacting equipment shall be plainly stamped or stenciled in a conspicuous place on the unit. The gross weight shall be either the manufacturer's rated weight or the scale weight, expressed in pounds.

    26

  • 16

    SECTION 5 CONTROL OF WORK

    x The make, model, serial number and manufacturer's rated capacity in pounds for each scale shall be clearly stamped or stenciled on the load receiving element and its indicator or indicators. All meters shall be similarly identified, rated and marked. Upon request of the Engineer, the Contractor shall furnish a statement by the manufacturer, designating sectional and weighbridge capacities of portable vehicle scales.

    5-1.11 ALTERNATIVE EQUIPMENT x While certain of these specifications may provide that equipment of a particular size and type is to be used to perform portions of the work, it is to be understood that the development and use of new or improved equipment is to be encouraged. x The Contractor may request, in writing, permission from the Engineer to use equipment of a different size or type in place of the equipment specified. x The Engineer, before considering or granting the request, may require the Contractor to furnish, at the Contractor's expense, evidence satisfactory to the Engineer that the equipment proposed for use by the Contractor is capable of producing work equal to, or better than, that which can be produced by the equipment specified. x If permission is granted by the Engineer, it shall be understood that the permission is granted for the purpose of testing the quality of work actually produced by the equipment and is subject to continuous attainment of results which, in the opinion of the Engineer, are equal to, or better than, that which can be obtained with the equipment specified. The Engineer shall have the right to withdraw permission at any time that the Engineer determines that the alternative equipment is not producing work that is equal, in all respects, to that which can be produced by the equipment specified. Upon withdrawal of permission by the Engineer, the Contractor will be required to use the equipment originally specified and shall, in accordance with the directions of the Engineer, remove and dispose of or otherwise remedy, at the Contractor's expense, any defective or unsatisfactory work produced with the alternative equipment. x Neither the State nor the Contractor shall have any claim against the other for either the withholding or the granting of permission to use alternative equipment, or for the withdrawal of the permission. x Permission to use alternative equipment in place of equipment specified will only be granted where the equipment is new or improved and its use is deemed by the Engineer to be in furtherance of the purposes of this Section 5-1.11. The approval for use of particular equipment on any project shall in no way be considered as an approval of the use of the equipment on any other project. x Nothing in this Section 5-1.11 shall relieve the Contractor of the responsibility for furnishing materials or producing finished work of the quality specified in these specifications or in the special provisions.

    5-1.115 ALTERNATIVE METHODS OF CONSTRUCTION x Whenever the plans or specifications provide that more than one specified method of construction or more than one specified type of material or construction equipment may be used to perform portions of the work and leave the selection of

    27

  • SECTION 5 CONTROL OF WORK

    the method of construction or the type of material or equipment to be used up to the Contractor, it is understood that the State does not guarantee that every specified method of construction or type of material or equipment can be used successfully throughout all or any part of any project. It shall be the Contractor's responsibility to select and use the alternative or alternatives which will satisfactorily perform the work under the conditions encountered. In the event some of the alternatives are not feasible or it is necessary to use more than one of the alternatives on any project, full compensation for any additional cost involved shall be considered as included in the contract price paid for the item of work involved and no additional compensation will be allowed therefor.

    5-1.116 DIFFERING SITE CONDITIONS x During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering those conditions shall promptly notify the other party in writing of the specific differing conditions before they are disturbed and before the affected work is performed. x Upon written notification, the Engineer will investigate the conditions, and if the Engineer determines that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding loss of anticipated profits, will be made and the contract modified in writing accordingly. The Engineer will notify the Contractor of the Engineer's determination whether or not an adjustment of the contract is warranted. x No contract adjustment which results in a benefit to the Contractor will be allowed unless the Contractor has provided the required written notice. x No contract adjustment will be allowed under the provisions specified in this section for any effects caused on unchanged work. x Any contract adjustment warranted due to differing site conditions will be made in conformance with the provisions in Section 4-1.03, "Changes," except as otherwise provided.

    5-1.12 CHARACTER OF WORKERS x If any subcontractor or person employed by the Contractor shall appear to the Engineer to be incompetent or to act in a disorderly or improper manner, they shall be discharged immediately on the request of the Engineer, and that person shall not again be employed on the work.

    5-1.13 FINAL INSPECTION x When the work has been completed, the Engineer will make the final inspection.

    5-1.14 COST REDUCTION INCENTIVE x The Contractor may submit to the Engineer, in writing, proposals for modifying the plans, specifications or other requirements of the contract for the sole purpose of reducing the total cost of construction. The cost reduction proposal

    28

  • 17

    SECTION 5 CONTROL OF WORK

    shall not impair, in any manner, the essential functions or characteristics of the project, including but not limited to service life, economy of operation, ease of maintenance, desired appearance, or design and safety standards. x Cost reduction proposals shall contain the following information:

    1. A description of both the existing contract requirements for performing the work and the proposed changes.

    2. An itemization of the contract requirements that must be changed if the proposal is adopted.

    3. A detailed estimate of the cost of performing the work under the existing contract and under the proposed change. The estimates of cost shall be determined in the same manner as if the work were to be paid for on a force account basis as provided in Section 9-1.03, "Force Account Payment."

    4. A statement of the time within which the Engineer must make a decision thereon.

    5. The contract items of work affected by the proposed changes, including any quantity variation attributable thereto.

    x The provisions of this Section 5-1.14 shall not be construed to require the Engineer to consider any cost reduction proposal which may be submitted hereunder; proposed changes in basic design of a bridge or of a pavement type will not be considered as an acceptable cost reduction proposal; and the Department will not be liable to the Contractor for failure to accept or act upon any cost reduction proposal submitted pursuant to this section nor for any delays to the work attributable to any cost reduction proposal. If a cost reduction proposal is similar to a change in the plans or specifications, under consideration by the Department for the project, at the time the proposal is submitted or if the proposal is based upon or similar to Standard Specifications, standard special provisions or Standard Plans adopted by the Department after the advertisement for the contract, the Engineer will not accept the proposal, and the Department reserves the right to make the changes without compensation to the Contractor under the provisions of this section. x The Contractor shall continue to perform the work in accordance with the requirements of the contract until an executed change order, incorporating the cost reduction proposal has been issued. If an executed change order has not been issued by the date upon which the Contractor's cost reduction proposal specifies that a decision thereon should be made, or such other date as the Contractor may subsequently have specified in writing, the cost reduction proposal shall be deemed rejected. x The Engineer shall be the sole judge of the acceptability of a cost reduction proposal and of the estimated net savings in construction costs from the adoption of all or any part of the proposal. In determining the estimated net savings, the right is reserved to disregard the contract bid prices if in the judgment of the Engineer, those prices do not represent a fair measure of the value of work to be performed or to be deleted.

    29

  • SECTION 5 CONTROL OF WORK

    x The Department reserves the right where it deems such action appropriate, to require the Contractor to share in the Department's costs of investigating a cost reduction proposal submitted by the Contractor as a condition of considering the proposal. Where this condition is imposed, the Contractor shall indicate acceptance thereof in writing, and that acceptance shall constitute full authority for the Department to deduct amounts payable to the Department from any moneys due or that may become due to the Contractor under the contract. x If the Contractor's cost reduction proposal is accepted in whole or in part the acceptance will be by a contract change order, which shall specifically state that it is executed pursuant to this Section 5-1.14. The change order shall incorporate the changes in the plans and specifications which are necessary to permit the cost reduction proposal or that part of it as has been accepted to be put into effect, and shall include any conditions upon which the Department's approval thereof is based if the approval of the Department is conditional. The change order shall also set forth the estimated net savings in construction costs attributable to the cost reduction proposal effectuated by the change order, and shall further provide that the Contractor be paid 50 percent of that estimated net savings amount. The Contractor's cost of preparing the cost reduction incentive proposal and the Department's costs of investigating a cost reduction incentive proposal, including any portion thereof paid by the Contractor, shall be excluded from consideration in determining the estimated net savings in construction costs. x Acceptance of the cost reduction proposal and performance of the work thereunder shall not extend the time of completion of the contract unless specifically provided for in the contract change order authorizing the use of the cost reduction proposal. x The amount specified to be paid to the Contractor in the change order which effectuates a cost reduction proposal shall constitute full compensation to the Contractor for the cost reduction proposal and the performance of the work thereof pursuant to the change order. x The Department expressly reserves the right to adopt a cost reduction proposal for general use on contracts administered by the Department when it determines that the proposal is suitable for application to other contracts. When an accepted cost reduction proposal is adopted for general use, only the Contractor who first submitted that proposal will be eligible for compensation pursuant to this section, and in that case, only as to those contracts awarded to that Contractor prior to submission of the accepted cost reduction proposal and as to which the cost reduction proposal is also submitted and accepted. Cost reduction proposals identical or similar to previously submitted proposals will be eligible for consideration and compensation under the provisions of this Section 5-1.14 if the identical or similar previously submitted proposals were not adopted for general application to other contracts administered by the Department. Subject to the provisions contained herein, the State or any other public agency shall have the right to use all or any part of any submitted cost reduction proposal without obligation or compensation of any kind to the Contractor. x This Section 5-1.14 of the specifications shall apply only to contracts awarded to the lowest bidder pursuant to competitive bidding.

    30

  • 18

    SECTION 6: CONTROL OF MATERIALS

    6-1 GENERAL

    6-1.01 SOURCE OF SUPPLY AND QUALITY OF MATERIALS x The Contractor shall furnish all materials required to complete the work, except materials that are designated in the specifications to be furnished by the State and materials furnished by the State in conformance with the provisions in Section 9-1.03, "Force Account Payment." x Only materials conforming to the requirements of the specifications shall be incorporated in the work. x The materials furnished and used shall be new, except as may be provided elsewhere in these specifications, on the plans or in the special provisions. The materials shall be manufactured, handled and used in a workmanlike manner to ensure completed work in accordance with the plans and specifications. x Materials to be used in the work will be subject to inspection and tests by the Engineer or the Engineer's designated representative. The Contractor shall furnish without charge such samples as may be required. x The Contractor shall furnish the Engineer a list of the Contractor's sources of materials and the locations at which those materials will be available for inspection. The list shall be submitted on a State-furnished form and shall be furnished to the Engineer in sufficient time to permit inspecting and testing of materials to be furnished from the listed sources in advance of their use. The Engineer may inspect, sample or test materials at the source of supply or other locations, but the inspection, sampling or testing will not be undertaken until the Engineer is assured by the Contractor of the cooperation and assistan