Standard Offer and Feed-in Tariff Development Lessons Learned
-
Upload
johndalton -
Category
Business
-
view
1.118 -
download
1
description
Transcript of Standard Offer and Feed-in Tariff Development Lessons Learned
John Dalton
Tel: 978 369-2465
Vermont Public Service Board
Standard Offer Workshop
Lessons Learned in the Design
of Standard Offer and Feed-in Tariff Programs
July 10, 2009
Power Advisory’s Relevant Standard Offer Experience
Distinguishing between Standard Offers and Feed-in Tariffs
Ontario’s Standard Offer Program
Objectives
Review of Program Design
Program Impacts
Lessons Learned
Ontario’s Feed-in Tariff
Context for Feed-in Tariff
Objectives
Review of Program Design
Assessment of Feed-in Tariffs
Florida’s Standard Offer Contract
Objectives
Assessment of Program
Presentation Outline
Power Advisory LLC 2009
All Rights Reserved 2
Power Advisory: small consulting firm focused on the
electricity sector
Major standard offer and feed-in tariff assignments:
Advised regarding Ontario SOP design in 2005
Advised regarding reforms to SOP for PV in 2007
PV program design not part of initial work
Assisted with redesign of SOP in 2008, became FIT
program design in late 2008
Testified regarding FPL’s standard offer contract in 2008
Clients include project developers, electric utilities and public
utility commissions
Consulting support includes policy development, price
forecasting, market assessment and project development
Renewable energy project development a major focus
Relevant experience of Power Advisory with Standard
Offer Program (SOP) Design
Power Advisory LLC 2009
All Rights Reserved 3
The pricing for standard offer programs typically value-
based
Prices don’t distinguish between the type of resource
Value often based on avoided costs
The pricing for feed-in tariffs typically cost-based
Different prices set for different renewable energy
resources, based on cost differences
Feed-in tariffs typically designed to provide greater
price stability
Long-term price schedule, e.g., degression
Proven to be effective in promoting rapid adoption of
renewable energy technologies
Often used as economic development policy
Distinguishing between Standard Offers and Feed-in Tariffs
Power Advisory LLC 2009
All Rights Reserved 4
Ontario implemented a Standard Offer Program in
November 2006
Objective to remove barriers that prevented smaller
renewable energy projects from proceeding
Addressed barriers RFP processes present to
small generators:
1. Financial security requirements
2. Complexity of the contracting process
3. High cost of proposal development relative to
project size
4. Uncertainty of proposal outcome
5. Administrative burden of RFP processes
Ontario’s experience with Standard Offer Program
Power Advisory LLC 2009
All Rights Reserved 5
Program provided a fixed price of 11 cents/kWh (Can$)
for eligible renewable technologies
20% of contract price escalated with CPI
Pricing based on recent renewable RFP, along with
distribution premium
Premium (3.52 cents/kWh) available for projects
which could focus output into peak periods
Solar PV received 42 cents/kWh
Projects no more than 10 MW and connected to
distribution network
20-year contract terms provided
Ontario’s Standard Offer Program Design
Power Advisory LLC 2009
All Rights Reserved 6
Standard Offer Contract was 34 pages
No security or contract deposits required
No cap on the amount of capacity contracted
Program to be evaluated after two years
In May 2008 program was suspended
314 contracts representing over 1,300 MW
56% of capacity was wind
34% solar
The Standard Offer Contract and program evolution
Power Advisory LLC 2009
All Rights Reserved 7
With 750 MW represented by wind projects,
connection requests in areas with most attractive wind
resources overwhelmed distribution capacity
Transmission capacity also becoming constrained
Considerable portion of capacity from larger
projects broken into 10-MW blocks
OPA proposed limiting developers ability to connect
more than one project to a substation or more than 50
MW per developer until commercial operation
Distribution capacity proved to be a major constraint
Power Advisory LLC 2009
All Rights Reserved 8
With more challenging credit market and declines in Can
$, considerable portion of capacity won’t be developed
Capacity reserved until contract terminates (3 years)
Valuable connection capacity held by proponents
that are unlikely to develop projects
Some queue positions sold
Without security deposit, proponents had a free option
Supply response likely to determine the natural system
constraint which became connection capacity
Less of an issue in Vermont given smaller project sizes
and 50 MW program limit
Should ensure that projects are likely to be developed
Financial security or project development status
Ontario Standard Offer: Lessons Learned & Postmortem
Power Advisory LLC 2009
All Rights Reserved 9
Objectives of policymakers not clearly articulated and
not reflected in program design
Importance increased with new political leadership
Diversity of technology and project types became
more important
Community group-based projects unable to
compete for connection capacity (queue position)
Smaller farm-based bio-energy projects not able
to be developed given transmission constraints
Ontario Standard Offer: Lessons Learned & Postmortem
Power Advisory LLC 2009
All Rights Reserved 10
Ontario has moved to a Feed-in Tariff to achieve renewable
policy objectives
Increase renewable energy supply to ensure adequate
generation and reduce emissions
Create new “green” industries and jobs through
investment
Enable the participation of a broader range of developers
and technologies
Ontario’s Standard Offer Program has migrated to a Feed-in
Tariff
Power Advisory LLC 2009
All Rights Reserved 11
Ontario’s Standard Offer Program and Feed-in Tariff DevelopmentMinister
Directs OPA
& OEB to
Develop
Standard Offer
Program
OPA & OEB
submit
recommendations
on Program
Design to
Minister
SO
Program
launched
SO Program
1st
Aniversary
842 MW
under
contract
SO
Program
suspended
1,300 MW
under
contract
FIT
Program
design
work
initiated
FIT Program
formally
announced
Green
Energy Act
filed
Stakeholder
Consultation
on FIT
Program
Design
Aug-05 Nov-05 Nov-06 Nov-07 May-08 Nov-08 Feb-09 March-May 09
Green Energy and Green Economy Act (GEGEA) filed
and passed in 3 months: job creation a major focus
Auto sector major employer, seeking new industry
Recognized that had to compete with RPS and federal
tax incentives offered in the US
Feed-in Tariff to provide stability to attract industry
Promoting investor confidence which is key to
investment decisions by manufacturers
Risk if you get the Feed-in Tariff (FIT) price wrong
Ability to reset prices to limit rate impacts
Undermines investor confidence
Major source of tension with FIT implementation
New Ontario Energy Minister impressed with German and
Spanish Feed-in Tariffs
Power Advisory LLC 2009
All Rights Reserved 12
Accelerated the development of the transmission
network to accommodate more renewable energy
FIT program evaluated connection capacity upfront
prior to contract award
Economic test developed to evaluate where wires
expansion economic. Expansion costs socialized.
Streamlined approvals process for renewable projects
Reducing municipal oversight
Domestic content requirements can be specified
Essential to economic development benefits
GEGEA cornerstone of broader framework to promote
renewables
Power Advisory LLC 2009
All Rights Reserved 13
Development security required with contract
application
Prices differentiated by technology to promote wide
range of technologies
Prices differentiated by proponent
Community group and aboriginal projects to receive
premium prices
Based on higher development costs and inability
to obtain economies commercial developers
realize with equipment vendors
Feed-in Tariff program design addressed the failings of
Standard Offer Program
Power Advisory LLC 2009
All Rights Reserved 14
Setting the Feed-in Tariff
The FIT is cost-based, with
prices set to provide a
reasonable return
11% After tax ROE
OPA anticipates updating FIT
prices every two years, based
on changes in costs and
considering market uptake
Community project prices $4
to $10/MWh higher
depending on technology
Power Advisory LLC 2009
All Rights Reserved 15
Technology Size Price
($/MWh)
Biogas ≤ 500 kW $160
> 500 kW ≤ 10 MW $147
> 10MW $104
Biomass ≤ 10 MW $138
> 10 MW $130
Landfill gas ≤ 10 MW $111
> 10 MW $103
Solar PV
Rooftop or
ground mounted ≤ 10 kW $802
Rooftop > 10 kW ≤ 250 kW $713
Rooftop > 250 kW ≤ 500 kW $635
Rooftop >500 kW $539
Ground
mounted > 10 kW ≤ 10 MW $443
Waterpower ≤ 10 MW $131
> 10 MW ≤ 50 MW $122
Wind
Onshore any $135
Offshore any $190
Note: prices in Can$
Assessment of FITs
FITs can be an effective strategy for promoting
the development of renewable energy resources
where:
Costs and operating performance of
renewable resources are well understood and
subject to limited variation
Project size is such that the costs of
participating in a formal competitive
procurement process cannot be justified
Power Advisory LLC 2009
All Rights Reserved 16
Assessment of FITs
Significant risk associated with FIT pricing
Cornerstone of the program is stability
Essential if economic development benefits
from siting of major renewable energy
production facilities to be realized
If price too high significant market response
can leave consumers exposed to higher costs
Risk most significant for PV given its pricing
The 50 MW program cap mitigates these risks
for Vermont
Power Advisory LLC 2009
All Rights Reserved 17
Assessment of Ontario FIT
Ontario program could be a victim of its own success
and be “oversubscribed”
Renewable survey indicated 15,000 MW under
development (88% wind and 8% solar)
Ability of Ontario to integrate the baseload
generation provided by FIT
6 week period this spring when wholesale prices
were negative for 1/3 of hours
Ability to put enough transmission/distribution
wires in place in time to integrate FIT projects
Need to incent production during times when
most valuable
Power Advisory LLC 2009
All Rights Reserved 18
Review of Florida Power & Light Standard Offer
Program
Florida utilities mandated to provide Standard
Offer Contract (SOC)
Objective to promote development of
renewable energy in Florida
Under Florida PSC rules SOC prices based on
next avoidable fossil fueled generating unit
Not an appropriate avoided cost benchmark
given objective of promoting renewable
energy
Required similar operating performance as fossil
units
Not realistic or appropriatePower Advisory LLC 2009
All Rights Reserved 19
Review of Florida Power & Light Standard Offer
Program
Risk allocation in SOC disadvantaged renewable
energy project developers
Capacity factor of 97% required to receive
full capacity payment
No capacity payment if capacity factor below
80%
FPL able to interrupt purchases when
uneconomic, adversely affecting capital cost
recovery for renewable projects
FPL had right of first refusal for RECs, even
though price paid was based on fossil unit
Power Advisory LLC 2009
All Rights Reserved 20
Considerations for the design of Vermont’s Standard
Offer
Program design must balance objectives:
Ensure customer value?
Eliminate undue barriers to project
development?
Promote development of a range of
technologies and project sizes?
50 MW program cap limits price risks
Program design will influence impacts, e.g.,
range of prices for different size projects
Power Advisory LLC 2009
All Rights Reserved 21
Considerations for the design of Vermont’s Standard
Offer (Cont’d)
With 50 MW cap, need to ensure that projects in
“queue” are likely to be developed
Financial security: easy to administer, but
potential barrier;
Evidence of project development
Establish development milestones
Power Advisory LLC 2009
All Rights Reserved 22
Considerations for the design of Vermont’s Standard
Offer (Cont’d)
Considerable risks with establishing Standard
Offer price schedule
Publicly available data with opportunity for
stakeholder feedback on assumptions
Supply curve likely to be relatively flat
Small price change, significant supply
response
Linkage between model assumptions and
program design
Power Advisory LLC 2009
All Rights Reserved 23
Considerations for the design of Vermont’s Standard
Offer (Cont’d)
Provide appropriate incentives to enhance value
of production
On-peak production
REC generation
Capacity value
Power Advisory LLC 2009
All Rights Reserved 24
Thank you for your attention
John Dalton
Power Advisory LLC
(978) 369-2465
www.poweradvisoryllc.com
Power Advisory LLC 2009
All Rights Reserved 25