Standard Costs and the Balanced Scorecard

87
Standard Costs and the Balanced Scorecard Chapter 10

description

Chapter 10. Standard Costs and the Balanced Scorecard. Predetermined. Used for planning labor, material and overhead requirements. Benchmarks for measuring performance. Used to simplify the accounting system. Standard Costs. Standard Costs are. - PowerPoint PPT Presentation

Transcript of Standard Costs and the Balanced Scorecard

Standard Costs and the Balanced

Scorecard

Chapter 10

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Costs

Standard Costs are

Predetermined.

Used for planning labor, materialand overhead requirements.

Benchmarks formeasuring performance.

Used to simplify theaccounting system.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Costs

DirectMaterial

Managers focus on quantities and coststhat exceed standards, a practice known as

management by exception.

Type of Product Cost

Am

ou

nt

DirectLabor

ManufacturingOverhead

Standard

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Accountants, engineers, personnel administrators, and production managers combine efforts to set standards

based on experience and expectations.

Setting Standard Costs

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Setting Standard Costs

Should we usepractical standardsor ideal standards?

Engineer ManagerialAccountant

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Setting Standard CostsPractical standards should be set at levels that are currently attainable with reasonable and

efficient effort.

Productionmanager

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Setting Standard CostsI agree. Ideal standards,

based on perfection,are unattainable and

discourage mostemployees.

Human ResourcesManager

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Note

The argument that ideal standards are discouraging has been persuasive for many years. So “normal” defects and waste were built into the standards.

In recent years, TQM and other initiatives have sought to eliminate all defects and waste. Ideal standards, that allow for no waste, have

become more popular. The emphasis is on improvement over time, not

attaining the ideal standards right now.

The argument that ideal standards are discouraging has been persuasive for many years. So “normal” defects and waste were built into the standards.

In recent years, TQM and other initiatives have sought to eliminate all defects and waste. Ideal standards, that allow for no waste, have

become more popular. The emphasis is on improvement over time, not

attaining the ideal standards right now.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Setting Direct Material Standards

PriceStandards

Final, deliveredcost of materials,net of discounts.

QuantityStandards

Use product design specifications.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Setting Direct Labor Standards

RateStandards

Use wage surveys and

labor contracts.

TimeStandards

Use time and motion studies for

each labor operation.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Setting Variable Overhead Standards

RateStandards

The rate is the variable portion of the

predetermined overhead rate.

ActivityStandards

The activity is the base used to calculate

the predetermined overhead.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Cost Card – Variable Production Cost

A standard cost card for one unit of product might look like this:

A A x BStandard Standard StandardQuantity Price Cost

Inputs or Hours or Rate per Unit

Direct materials 3.0 lbs. 4.00$ per lb. 12.00$ Direct labor 2.5 hours 14.00 per hour 35.00 Variable mfg. overhead 2.5 hours 3.00 per hour 7.50 Total standard unit cost 54.50$

B

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Are standards the same as budgets?

A budget is set for total costs.

Standards vs. Budgets

A standard is a per unit cost.

Standards are often used when

preparing budgets.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Cost VariancesC

ost

Standard

This variance is unfavorablebecause the actual cost

exceeds the standard cost.

A standard cost variance is the amount by whichan actual cost differs from the standard cost.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Cost Variances

I see that thereis an unfavorable

variance.

But why arevariances

important to me?

First, they point to causes ofproblems and directions

for improvement.

Second, they trigger investigations in departments

having responsibility for incurring the costs.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Variance Analysis Cycle

Prepare standard cost performance

report

Analyze variances

Begin

Identifyquestions

Receive explanations

Takecorrective

actions

Conduct next period’s

operations

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Cost Variances

Standard Cost Variances

Price Variance

The difference betweenthe actual price and the

standard price

Quantity Variance

The difference betweenthe actual quantity andthe standard quantity

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

A General Model for Variance Analysis

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

Price Variance Quantity Variance

Standard price is the amount that should have been paid for the resources acquired.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Price Variance Quantity Variance

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

A General Model for Variance Analysis

Standard quantity is the quantity allowed for the actual good output.

Standard input per unit of outputtimes amount of good output.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

A General Model for Variance Analysis

AQ(AP - SP) SP(AQ - SQ)

AQ = Actual Quantity SP = Standard Price AP = Actual Price SQ = Standard Quantity

Price Variance Quantity Variance

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Costs

Let’s use the general model to calculate standard cost

variances for direct material.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Glacier Peak Outfitters has the following direct material standard for the fiberfill in its

mountain parka.

0.1 kg. of fiberfill per parka at $5.00 per kg.

Last month 210 kgs of fiberfill were purchased and used to make 2,000 parkas.

The material cost a total of $1,029.

Material VariancesExample

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

210 kgs. 210 kgs. 200 kgs. × × × $4.90 per kg. $5.00 per kg. $5.00 per kg.

= $1,029 = $1,050 = $1,000

Price variance$21 favorable

Quantity variance$50 unfavorable

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

Material VariancesSummary

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

210 kgs. 210 kgs. 200 kgs. × × × $4.90 per kg. $5.00 per kg. $5.00 per kg.

= $1,029 = $1,050 = $1,000

Price variance$21 favorable

Quantity variance$50 unfavorable

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

$1,029 210 kgs = $4.90 per

kg

Material VariancesSummary

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

210 kgs. 210 kgs. 200 kgs. × × × $4.90 per kg. $5.00 per kg. $5.00 per kg.

= $1,029 = $1,050 = $1,000

Price variance$21 favorable

Quantity variance$50 unfavorable

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

0.1 kg per parka 2,000 parkas = 200 kgs

Material VariancesSummary

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Note: Using the formulas

Materials price varianceMPV = AQ (AP - SP)

= 210 kgs ($4.90/kg - $5.00/kg)

= 210 kgs (-$0.10/kg)

= $21 F

Materials quantity varianceMQV = SP (AQ - SQ)

= $5.00/kg (210 kgs-(0.1 kg/parka 2,000 parkas))

= $5.00/kg (210 kgs - 200 kgs)

= $5.00/kg (10 kgs)

= $50 U

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Quick Check

Suppose only 190 kgs of fiberfill were used to make 2,000 parkas. What is the materials quantity variance? Remember that the standards call for 0.1 kg of fiberfill per parka at a cost of $5 per kg of fiberfill.

a. $50 F

b. $50 U

c. $100 F

d. $100 U

Suppose only 190 kgs of fiberfill were used to make 2,000 parkas. What is the materials quantity variance? Remember that the standards call for 0.1 kg of fiberfill per parka at a cost of $5 per kg of fiberfill.

a. $50 F

b. $50 U

c. $100 F

d. $100 U

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Suppose only 190 kgs of fiberfill were used to make 2,000 parkas. What is the materials quantity variance? Remember that the standards call for 0.1 kg of fiberfill per parka at a cost of $5 per kg of fiberfill.

a. $50 F

b. $50 U

c. $100 F

d. $100 U

Suppose only 190 kgs of fiberfill were used to make 2,000 parkas. What is the materials quantity variance? Remember that the standards call for 0.1 kg of fiberfill per parka at a cost of $5 per kg of fiberfill.

a. $50 F

b. $50 U

c. $100 F

d. $100 U

Quick Check

MQV = SP (AQ - SQ) = $5.00/kg (190 kgs-(0.1 kg/parka 2,000 parkas)) = $5.00/kg (190 kgs - 200 kgs) = $5.00/kg (-10 kgs) = $50 F

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

If the material quantity standard specifies exactly how much material should be in the final product without any wastage, is a favorable (F) materials quantity variance a good thing?

a. Yes

b. No

If the material quantity standard specifies exactly how much material should be in the final product without any wastage, is a favorable (F) materials quantity variance a good thing?

a. Yes

b. No

Quick Check

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Quick Check

If the material quantity standard specifies exactly how much material should be in the final product without any wastage, is a favorable (F) materials quantity variance a good thing?

a. Yes

b. No

If the material quantity standard specifies exactly how much material should be in the final product without any wastage, is a favorable (F) materials quantity variance a good thing?

a. Yes

b. No

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Costs

Let’s use the general model to calculate all standard cost

variances, starting withdirect material.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson Inc. has the following direct material standard to manufacture one Zippy:

1.5 pounds per Zippy at $4.00 per pound

Last week 1,700 pounds of material were purchased and used to make 1,000 Zippies.

The material cost a total of $6,630.

Material VariancesExample

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

What is the actual price per poundpaid for the material?

a. $4.00 per pound.

b. $4.10 per pound.

c. $3.90 per pound.

d. $6.63 per pound.

What is the actual price per poundpaid for the material?

a. $4.00 per pound.

b. $4.10 per pound.

c. $3.90 per pound.

d. $6.63 per pound.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

What is the actual price per poundpaid for the material?

a. $4.00 per pound.

b. $4.10 per pound.

c. $3.90 per pound.

d. $6.63 per pound.

What is the actual price per poundpaid for the material?

a. $4.00 per pound.

b. $4.10 per pound.

c. $3.90 per pound.

d. $6.63 per pound.

AP = $6,630 ÷ 1,700 lbs.AP = $3.90 per lb.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s material price variance (MPV)for the week was:

a. $170 unfavorable.

b. $170 favorable.

c. $800 unfavorable.

d. $800 favorable.

Hanson’s material price variance (MPV)for the week was:

a. $170 unfavorable.

b. $170 favorable.

c. $800 unfavorable.

d. $800 favorable.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s material price variance (MPV)for the week was:

a. $170 unfavorable.

b. $170 favorable.

c. $800 unfavorable.

d. $800 favorable.

Hanson’s material price variance (MPV)for the week was:

a. $170 unfavorable.

b. $170 favorable.

c. $800 unfavorable.

d. $800 favorable. MPV = AQ(AP - SP) MPV = 1,700 lbs. × ($3.90 - 4.00) MPV = $170 Favorable

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The standard quantity of material thatshould have been used to produce1,000 Zippies is:

a. 1,700 pounds.

b. 1,500 pounds.

c. 2,550 pounds.

d. 2,000 pounds.

The standard quantity of material thatshould have been used to produce1,000 Zippies is:

a. 1,700 pounds.

b. 1,500 pounds.

c. 2,550 pounds.

d. 2,000 pounds.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The standard quantity of material thatshould have been used to produce1,000 Zippies is:

a. 1,700 pounds.

b. 1,500 pounds.

c. 2,550 pounds.

d. 2,000 pounds.

The standard quantity of material thatshould have been used to produce1,000 Zippies is:

a. 1,700 pounds.

b. 1,500 pounds.

c. 2,550 pounds.

d. 2,000 pounds. SQ = 1,000 units × 1.5 lbs per unit SQ = 1,500 lbs

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Quick Check

Hanson’s material quantity variance (MQV)for the week was:

a. $170 unfavorable.

b. $170 favorable.

c. $800 unfavorable.

d. $800 favorable.

Hanson’s material quantity variance (MQV)for the week was:

a. $170 unfavorable.

b. $170 favorable.

c. $800 unfavorable.

d. $800 favorable.

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

1,700 lbs. 1,700 lbs. 1,500 lbs. × × × $3.90 per lb. $4.00 per lb. $4.00 per lb.

= $6,630 = $ 6,800 = $6,000

Price variance$170 favorable

Quantity variance$800 unfavorable

Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price

Material VariancesSummary

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Material Variances

Hanson purchased and used 1,700 pounds.

How are the variances computed if the amount purchased differs from

the amount used?

The price variance is computed on the entire

quantity purchased.

The quantity variance is computed only on

the quantity used.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson Inc. has the following material standard to manufacture one Zippy:

1.5 pounds per Zippy at $4.00 per pound

Last week 2,800 pounds of material were purchased at a total cost of $10,920, and 1,700 pounds were used to make 1,000

Zippies.

Material VariancesContinued

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Actual Quantity Actual Quantity Purchased Purchased × × Actual Price Standard Price 2,800 lbs. 2,800 lbs. × × $3.90 per lb. $4.00 per lb.

= $10,920 = $11,200

Price variance$280 favorable

Price variance increases because quantity

purchased increases.

ZippyMaterial Variances

Continued

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Actual Quantity Used Standard Quantity × × Standard Price Standard Price 1,700 lbs. 1,500 lbs. × × $4.00 per lb. $4.00 per lb.

= $6,800 = $6,000

Quantity variance$800 unfavorable

Quantity variance is unchanged because actual and standard

quantities are unchanged.

Material VariancesContinued

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Isolation of Material Variances

I need the price variancesooner so that I can better

identify purchasing problems.

You accountants just don’tunderstand the problems thatpurchasing managers have.

I’ll start computingthe price variancewhen material is

purchased rather thanwhen it’s used.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Responsibility for Material Variances

I am not responsible for this unfavorable material

quantity variance.

You purchased cheapmaterial, so my peoplehad to use more of it.

You used too much material because of poorly trained

workers and poorly maintained equipment.

Also, your poor scheduling sometimes requires me to

rush order material at a higher price, causing

unfavorable price variances.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Costs

Now let’s calculate standard cost variances for direct labor.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Note

Materials variances: Material price variance

MPV = AQ (AP - SP) Material quantity variance

MQV = SP (AQ - SQ)

Labor variances: Labor rate variance

LRV = AH (AR - SR) Labor efficiency variance

LEV = SR (AH - SH)

Actual hours

Actual rate

Standard rate

Standard hours allowed for the actual good output

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson Inc. has the following direct labor standard to manufacture one Zippy:

1.5 standard hours per Zippy at $12.00 perdirect labor hour

Last week 1,550 direct labor hours were worked at a total labor cost of $18,910

to make 1,000 Zippies.

Labor Variances Example Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

What was Hanson’s actual rate (AR)for labor for the week?

a. $12.20 per hour.

b. $12.00 per hour.

c. $11.80 per hour.

d. $11.60 per hour.

What was Hanson’s actual rate (AR)for labor for the week?

a. $12.20 per hour.

b. $12.00 per hour.

c. $11.80 per hour.

d. $11.60 per hour.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

What was Hanson’s actual rate (AR)for labor for the week?

a. $12.20 per hour.

b. $12.00 per hour.

c. $11.80 per hour.

d. $11.60 per hour.

What was Hanson’s actual rate (AR)for labor for the week?

a. $12.20 per hour.

b. $12.00 per hour.

c. $11.80 per hour.

d. $11.60 per hour.

Quick Check

AR = $18,910 ÷ 1,550 hours AR = $12.20 per hour

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s labor rate variance (LRV) for the week was:

a. $310 unfavorable.

b. $310 favorable.

c. $300 unfavorable.

d. $300 favorable.

Hanson’s labor rate variance (LRV) for the week was:

a. $310 unfavorable.

b. $310 favorable.

c. $300 unfavorable.

d. $300 favorable.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s labor rate variance (LRV) for the week was:

a. $310 unfavorable.

b. $310 favorable.

c. $300 unfavorable.

d. $300 favorable.

Hanson’s labor rate variance (LRV) for the week was:

a. $310 unfavorable.

b. $310 favorable.

c. $300 unfavorable.

d. $300 favorable.

Quick Check

LRV = AH(AR - SR) LRV = 1,550 hrs($12.20 - $12.00) LRV = $310 unfavorable

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The standard hours (SH) of labor thatshould have been worked to produce1,000 Zippies is:

a. 1,550 hours.

b. 1,500 hours.

c. 1,700 hours.

d. 1,800 hours.

The standard hours (SH) of labor thatshould have been worked to produce1,000 Zippies is:

a. 1,550 hours.

b. 1,500 hours.

c. 1,700 hours.

d. 1,800 hours.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The standard hours (SH) of labor thatshould have been worked to produce1,000 Zippies is:

a. 1,550 hours.

b. 1,500 hours.

c. 1,700 hours.

d. 1,800 hours.

The standard hours (SH) of labor thatshould have been worked to produce1,000 Zippies is:

a. 1,550 hours.

b. 1,500 hours.

c. 1,700 hours.

d. 1,800 hours.

Quick Check

SH = 1,000 units × 1.5 hours per unit SH = 1,500 hours

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s labor efficiency variance (LEV)for the week was:

a. $590 unfavorable.

b. $590 favorable.

c. $600 unfavorable.

d. $600 favorable.

Hanson’s labor efficiency variance (LEV)for the week was:

a. $590 unfavorable.

b. $590 favorable.

c. $600 unfavorable.

d. $600 favorable.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s labor efficiency variance (LEV)for the week was:

a. $590 unfavorable.

b. $590 favorable.

c. $600 unfavorable.

d. $600 favorable.

Hanson’s labor efficiency variance (LEV)for the week was:

a. $590 unfavorable.

b. $590 favorable.

c. $600 unfavorable.

d. $600 favorable.

Quick Check

LEV = SR(AH - SH) LEV = $12.00(1,550 hrs - 1,500 hrs) LEV = $600 unfavorable

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate

Labor VariancesSummary

Rate variance$310 unfavorable

Efficiency variance$600 unfavorable

1,550 hours 1,550 hours 1,500 hours × × × $12.20 per hour $12.00 per hour $12.00 per hour

= $18,910 = $18,600 = $18,000

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Labor Rate Variance – A Closer Look

Production managers who make work assignmentsare generally responsible for rate variances.

Production managers who make work assignmentsare generally responsible for rate variances.

High skill,high rate

Low skill,low rate

Using highly paid skilled workers toperform unskilled tasks results in an

unfavorable rate variance.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Labor Efficiency Variance –A Closer Look

UnfavorableEfficiencyVariance

Poorsupervisionof workers

Poorlymaintainedequipment

Poorlytrainedworkers

Poorquality

materials

Insufficientdemand

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Responsibility forLabor Variances

I am not responsible for the unfavorable labor

efficiency variance!

You purchased cheapmaterial, so it took more

time to process it.

You used too much time because of poorly

trained workers and poor supervision.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Responsibility forLabor Variances

Maybe I can attribute the laborand material variances to personnel

for hiring the wrong peopleand training them poorly.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Standard Costs

Now let’s calculate standard cost

variances for the last of the variable production costs –

variable manufacturing

overhead.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Note

Labor variances: Labor rate variance

LRV = AH (AR - SR) Labor efficiency variance

LEV = SR (AH - SH)

Variable overhead variances: Variable overhead spending variance

VOSV = AH (AR - SR) Variable overhead efficiency variance

VOEV = SR (AH Quick Check

Actual hours of the allocation base

Actual variable overhead rate

Standard variable overhead rate

Standard hours allowed for the actual good output

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s spending variance (VOSV) for variable manufacturing overhead forthe week was:

a. $465 unfavorable.

b. $400 favorable.

c. $335 unfavorable.

d. $300 favorable.

Hanson’s spending variance (VOSV) for variable manufacturing overhead forthe week was:

a. $465 unfavorable.

b. $400 favorable.

c. $335 unfavorable.

d. $300 favorable.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s spending variance (VOSV) for variable manufacturing overhead forthe week was:

a. $465 unfavorable.

b. $400 favorable.

c. $335 unfavorable.

d. $300 favorable.

Hanson’s spending variance (VOSV) for variable manufacturing overhead forthe week was:

a. $465 unfavorable.

b. $400 favorable.

c. $335 unfavorable.

d. $300 favorable.

Quick Check

SV = AH(AR - SR) SV = 1,550 hrs($3.30 - $3.00) SV = $465 unfavorable

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s efficiency variance (VOEV) for variable manufacturing overhead for the week was:

a. $435 unfavorable.

b. $435 favorable.

c. $150 unfavorable.

d. $150 favorable.

Hanson’s efficiency variance (VOEV) for variable manufacturing overhead for the week was:

a. $435 unfavorable.

b. $435 favorable.

c. $150 unfavorable.

d. $150 favorable.

Quick Check Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Hanson’s efficiency variance (VOEV) for variable manufacturing overhead for the week was:

a. $435 unfavorable.

b. $435 favorable.

c. $150 unfavorable.

d. $150 favorable.

Hanson’s efficiency variance (VOEV) for variable manufacturing overhead for the week was:

a. $435 unfavorable.

b. $435 favorable.

c. $150 unfavorable.

d. $150 favorable.

Quick Check

EV = SR(AH - SH) EV = $3.00(1,550 hrs - 1,500 hrs) EV = $150 unfavorable

1,000 units × 1.5 hrs per unit

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Spending variance$465 unfavorable

Efficiency variance$150 unfavorable

1,550 hours 1,550 hours 1,500 hours × × × $3.30 per hour $3.00 per hour $3.00 per hour

= $5,115 = $4,650 = $4,500

Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate

Variable ManufacturingOverhead Variances

Zippy

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Variable Manufacturing Overhead Variances – A Closer Look

If variable overhead is applied on the basisof direct labor hours, the labor efficiency

and variable overhead efficiency varianceswill move in tandem.

If variable overhead is applied on the basisof direct labor hours, the labor efficiency

and variable overhead efficiency varianceswill move in tandem.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Variance Analysis and Management by Exception

How do I know which variances to investigate?

Larger variances, in dollar amount or as a percentage of the

standard, are investigated first.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Advantages of Standard Costs

Management byexception

Improved cost control and performance

evaluation

Better Informationfor planning anddecision making

Possible reductionsin production costs

Advantages

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

PotentialProblems

Emphasis onnegative may

impact morale.

Emphasizing standardsmay exclude other

important objectives.

Favorable variancesmay be

misinterpreted.

Continuous improvementmay be moreimportant than

meeting standards.

Standard costreports may

not be timely.

Incentives to buildinventories.

Disadvantages ofStandard Costs

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The Balanced Scorecard

Management translates its strategy into performance measures that employees

understand and accept.

Management translates its strategy into performance measures that employees

understand and accept.

Performancemeasures

Customers

Learningand growth

Internalbusiness

processes

Financial

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The Balanced Scorecard

How do we lookto the owners?

How can wecontinually learn,

grow, and improve?

In which internalbusiness processes

must we excel?

How do we lookto customers?

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

The Balanced Scorecard

Learning improvesbusiness processes.

Improved businessprocesses improve

customer satisfaction.

Improving customersatisfaction improves

financial results.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Benefits of Balance Scorecard

If implemented well:Forces management to articulate a coherent

strategy.Strategy is communicated throughout

organization.Performance measures are more likely to be

consistent with strategy and actionable.Portfolio of measures reduces gaming

problems.Feedback loop makes strategy dynamic.

If implemented well:Forces management to articulate a coherent

strategy.Strategy is communicated throughout

organization.Performance measures are more likely to be

consistent with strategy and actionable.Portfolio of measures reduces gaming

problems.Feedback loop makes strategy dynamic.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Some Possible Problems

Cultural/behavioralProgram fatigue.

Culture shock/resistance.

Every existing performance measurehas a champion.

Gaming still possible.

Cultural/behavioralProgram fatigue.

Culture shock/resistance.

Every existing performance measurehas a champion.

Gaming still possible.

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Process time is the only value-added time.

Delivery Performance Measures

Wait TimeProcess Time + Inspection Time

+ Move Time + Queue Time

Delivery Cycle Time

Order Received

ProductionStarted

Goods Shipped

Throughput Time

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Delivery Performance Measures

ManufacturingCycle

Efficiency

Value-added time

Manufacturing cycle time=

Wait TimeProcess Time + Inspection Time

+ Move Time + Queue Time

Delivery Cycle Time

Order Received

ProductionStarted

Goods Shipped

Throughput Time

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Quick Check

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the throughput time? a. 10.4 daysb. 0.2 daysc. 4.1 daysd. 13.4 days

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the throughput time? a. 10.4 daysb. 0.2 daysc. 4.1 daysd. 13.4 days

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the throughput time? a. 10.4 daysb. 0.2 daysc. 4.1 daysd. 13.4 days

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the throughput time? a. 10.4 daysb. 0.2 daysc. 4.1 daysd. 13.4 days

Quick Check

Throughput time = Process + Inspection + Move + Queue = 0.2 days + 0.4 days + 0.5 days + 9.3 days = 10.4 days

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Quick Check

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the MCE? a. 50.0%b. 1.9%c. 52.0%d. 5.1%

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the MCE? a. 50.0%b. 1.9%c. 52.0%d. 5.1%

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the MCE? a. 50.0%b. 1.9%c. 52.0%d. 5.1%

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the MCE? a. 50.0%b. 1.9%c. 52.0%d. 5.1%

Quick Check

MCE = Value-added time ÷ Throughput time

= Process time ÷ Throughput time

= 0.2 days ÷ 10.4 days = 1.9%

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

Quick Check

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the delivery cycle time? a. 0.5 daysb. 0.7 daysc. 13.4 daysd. 10.4 days

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the delivery cycle time? a. 0.5 daysb. 0.7 daysc. 13.4 daysd. 10.4 days

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the delivery cycle time? a. 0.5 daysb. 0.7 daysc. 13.4 daysd. 10.4 days

A TQM team at Narton Corp has recorded the following average times for production:

Wait 3.0 days Move 0.5 days Inspection 0.4 days Queue 9.3 days Process 0.2 days

What is the delivery cycle time? a. 0.5 daysb. 0.7 daysc. 13.4 daysd. 10.4 days

Quick Check Delivery cycle time = Wait time + Throughput time = 3.0 days + 10.4 days = 13.4 days

© The McGraw-Hill Companies, Inc., 2003McGraw-Hill/Irwin

End of Chapter 10