500MW Generator
500MW GeneratorInitial IsolationGenerator Circuit Breaker outUAT A n B Breaker Racked outField Excitaion fuses to be removed by Testing LabTurbine on BarringIsolation
Blower IsolationEmergency actuatorExciter Flap Gates ActuatorTube LightsStroboscopeEarth fault BrushesStroboscope LightsConnections RemovalPMG Rotor Outgoing cableD.C Supply of Main exciterD.C Earth fault Connections removalQuardature axis Connections
Important PointsGenerator will move by 27mm when it runsCRO Coupled run out to be taken.It is measured by setting dial guage at 50 and will see the deviation at each bolt if the minimum is 48mm then it is less by 0.02mmAfter decoupling with the help of Loose coupling bolts alignment readings of generator rotor coupling and LP coupling to be checked.Radial readings will be taken with the help of clamp tighten on master coupling of LP coupling and checked on Turbine couplingAxial clearance here is checked by Slip guage by setting at 0 and noting the difference of which side generator is
Swing checkThe top half of Bearing no 7 is removed Now shaft of bearing no 7 is taken on load by sling by keeping copper plate and by rotating the shaft readings will be taken on Exciter side coupling
Exciter Coupling and Generator Coupling Run outWith decoupled LP coupling by rotating the shaft run out is takenRemoval of Exciter RotorBy removing bearing no 7 bottom half and taking load on sling and resting the exciter load on resting device and with the help of jacking bolts we will separate the generator and exciter rotor and with the help of guiding pins after jacking by removing CC bolts in between exciter n Generator coupling Exciter rotor will be removedSeal body removalAfter removing top half bearing Seal body is loosened by taking the load on lifting device the exciter side bottom half is removed then seal body is moved to front and after giving rest on the bottom half the top half is dismantled and removed with the help of jugad.Then the top seal ring is removed by dismantling the half portion after that the top half is moved up and removed and then seal ring bottom half is removed and then again bearing is placed and the lifting device load is removed.While lifting lift it by max 0.2mmSeal body Lifting DevicesExciter side lifting device is having large OD than Turbine side lifting device because the lifting device will be placed on coupling in exciter side and on shaft towards turbineTwo stoppers will be used they are used for both locking the rotor and also for moving axiallyInner oil catcherThe bolts will be fixed from outer sidei.e seal body End shield and inner oil catcher.there will be oil deflectors also.Bottom End shield Downing First load will be taken on sling and then bearing is removed then Teflon piece is placed on the rotor bottom and sling is removed then sling will be taken on hooks and bottom end shield is removedThen again load is taken on sling and piece is removed and sliding plate on top of it and again piece is placed and load is taken off. Repeat the procedure on turbine side also.
Exciter side top endshield
Exciter side end shield Bolting system
Exciter side CC bolt Housing retaining rings and bottom end shield
Exciter side Bottom End Shield
Coolers Holes
Jacking Bolts and seal body Removal Hooks
Turbine side Top End Shield Lifting Device
Exciter side H2 Coolers and bottom End Shield
Compressor Baffle Rings
Compressor Movinf Blades
Compressor Blades
Axial Clearances
Seal body Lifting Device
Lp and Generator alignment Clamp
Lifitng Device of Bearing and Compressor Moving Blades(B and C marking done on holes)
Lifitng of Compressor moving Blades
Lifitnf Device arrangement
Rotating of Top Right Moving Blades to centre for Removal
Rotating of Moving Blades
Jugad for Rotating Bottom Half of Compressor Moving Blades
Lifting Device Arrangement and its placement towards turbine side
Rotating Jugad with the help of loose bolt because while shifting bottom half to top it will rotate fastly and cannot be stopped at top
Rotating of Rotor very much Precisely with the help of Loose bolts
Compressor Gaskets1mm gaskets is placed at first and last moving blades to move top Left o,right or bottom blades.while moving with the help of thread it will scratch the rotor so we will place the gaskets.If we place at first n last automically other three will rise.For shifting bottom to top gasket is needed for placing near the bottom of Jugad.they kept 3mm water sheet16mm bolts are needed for lifting the moving blades segmentFor Axially moving of the blades there are check nuts we can adjust them by tightening it will hit the end shield and come backThese moving bolts are tightened to end shield with bolts passing through these check nuts and argon welding will be done latterFor checking radial clearance of Fixed plates a thickness piece plate is given by keeping instrument we can check it.These plates are given by leaving one moving plate set i.e top left ,right and bottom it will be availableExciter rotor pressure test with N2 done at 5.8kscMain rotor pressure test done with n2 at 6Ksc for 6 hoursWater Winding Connection
Generator Schedule
Exciter Side Box Connection
Turbine Side Box Connection
Winding Connection
Water Hose Pipe Connection
Generator rotor shoe Blocks
Gen rotor Racking out Device
When rotor is threaded out it is kept on wooden block for adjusting its height it is used
Compressor blades hub covering.While racking out it must not touch the stator
Skit Plate for racking out the rotor
Downing the exciter side bottom end shield
Tying rope for Skit plate
For removing seal body bottom
Compressor moving blades removal Jugad
Placing the skit shoe
Skit shoe
Pressurisation Jugad for Exciter n main rotor
Small and Large blocks used for Raising device
Pedestal of rotor placed in between both beams
For keeping on rotor while lifting with sling
For Drawing out rotor
Jugad placed on exciter side main rotor
Downing turbine side Bottom End shield
Jugad on turbine side rotor for skitting
Shoe placed at the bottom of rotor
Taking one side of rotor on wooden Blocks
Taking load on slings
Air gap measurement Device
Bearing no 6 Stoppers
Bottom Pedestal
Wedge Tightness Test