SPECIAL SCHEME OF INSPECTIONS
1
Department of Occupational Safety and Health, Ministry of Human Resources,
Malaysia
MOHAMAD JAMIL,DIRECTOR OF MAJOR HAZARD DIVISION.
![Page 2: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/2.jpg)
Objective
2
To outline the DOSH perception towards RBI
To outline the Roles of DOSH to assist the Industry in Implementing RBI
To outline the arrangements of the Regulations
To outline Some Salient Provisions
![Page 3: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/3.jpg)
Why SSI?
3
To enable industry to forego the Time-based Inspection System
In-line with the International trend of conducting Statutory Inspection
![Page 4: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/4.jpg)
WHY SSI?
4
To replace the current practices of extending certificate of fitness of Pressurized machinery
As required by the Industries, so that they will remain competative.
![Page 5: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/5.jpg)
Extending C/F –Disadvantages of Current Practices
5
DOSH Experienced
No proper legal proceduresTime consumingDecision made not based on technical reasons
![Page 6: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/6.jpg)
Extending C/F –Disadvantages of Current
Practices
6
Industry Experienced
1. May lose Competitiveness Edge with foreign companies
2. Companies are not making profit
3. May affect Nation’s economy
![Page 7: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/7.jpg)
ADVANTAGES OF SSI
7
The SSI provides the basis for managing risk by making an informed decision on
inspection frequency, level of detail and types of NDT.
![Page 8: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/8.jpg)
SSI or RBI
8
“Risk-based Inspection- RBI” is one of the Inspection Scheme which falls under the definition of SSI
![Page 9: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/9.jpg)
RBI – Authority Perception
9
“Risk-based Inspection” is an inspection system where its inspection interval is scheduled based on the category of risk associated with each pressurized machinery
![Page 10: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/10.jpg)
Integrating RBI –Industry Tasks & Roles
Industry Roles are to : 1. implement RBI,
2. collect data;
3. identify the common degradation mode,
4. determine the likelihood & consequence of failure of machinery; and
5. rank it based on category of risk
to prepare an inspection plan based on the risk associated with each pressurized machinery
to submit to the Chief Inspector for approval
![Page 11: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/11.jpg)
Integrating RBI –Authority Roles
1. Authority to approve the proposed RBI
a) Review the documentsb) Carry out Audit and validate datac) grant maximum inspection interval to
the successful application
2. Chief Inspector to issue RBI Approval certificate;
3. Inspector at state office to issue certificate of fitness
![Page 12: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/12.jpg)
The Need For A New Legislations on RBI
12
“Factories and Machinery (Special Scheme of Inspection)(Risk-based Inspection) Regulations, 200X”
![Page 13: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/13.jpg)
The Needs of SSI-RBI Regulations
13
To improve “Delivery System” of DOSH
Reduce industries cost of operation and maintenance
Support industry to be more competitive in global market
![Page 14: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/14.jpg)
The Needs of SSI-RBI Regulations
14
To encourage Risk Based Inspection which is recognized as industrial best practice and latest technology to ensure machinery safety in lieu of Time based inspection
To introduce and promote RBI technology to industries and JKKP officers
To overcome issues relating to extension/exemption application
![Page 15: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/15.jpg)
Enabling & Related Provisions
15
Factories and Machinery Act, 1967
Section 56 (ga) conferred power for the Minister to make regulations
![Page 16: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/16.jpg)
SALIENT PROVISIONS
16
![Page 17: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/17.jpg)
R. 3- Application for Approval of risk-based inspection scheme
17
Industries to submit a written application to the Chief Inspector, include:
Document on OSH Management System, Documents on RBI; and A prescribed fee.
![Page 18: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/18.jpg)
R. 4 - Conditions for application
18
Document to be submitted to prove that –
(i) an occupational safety and health management system, OSH-MS 1722 or equivalent has been implemented;
![Page 19: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/19.jpg)
DOCUMENT TO BE SUBMTTED
19
(ii) a risk-based inspection has been established comprising of –
(a) a risk-based data; and
(b) calculation, evaluation and results of risk-based inspection scheme;
![Page 20: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/20.jpg)
DOCUMENT TO BE SUBMTTED
20
(c) a risk-based inspection team has been established;
(d) a Risk-based Inspection Team Leader has been employed; and
(iii) any other conditions as required by the Chief Inspector from time to time have been fulfilled.
![Page 21: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/21.jpg)
DOCUMENT TO BE SUBMTTED
21
The applicant shall also submit Document to prove that the pressurized machinery –
a. is fit for service; and
b. has no defect which can lead to failure.
![Page 22: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/22.jpg)
R6. - Risk-based data
22
Methods of collecting Data
i. off-line data collection; orii. on-line data collection.
![Page 23: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/23.jpg)
R17.- Risk-based Inspection Team Leader
23
Duty to employ a qualified person to act as a Risk-based Inspection Team Leader.
![Page 24: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/24.jpg)
Duties of a Risk-based Inspection Team Leader –
24
i. lead and manage the risk-based inspection team;
ii. notify the Risk-Based Inspection User and the Chief Inspector of any abnormality observed in the Risk-Based Inspection System;
![Page 25: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/25.jpg)
Duties of a Risk-based Inspection Team Leader –
25
iii. assign responsibilities and duties to each member of the risk-based inspection team;
iv. chair the meeting of the risk-based inspection team; and
v. present the progress status of the risk-based inspection scheme to the applicant or Risk-based Inspection User, as the case may be.
![Page 26: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/26.jpg)
ARRANGEMENT OF REGULATIONS
26
PART I
PRELIMINARY
1. Citation and application
2. Interpretation
![Page 27: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/27.jpg)
ARRANGEMENT OF REGULATIONS
27
PART II
APPLICATION FOR RISK-BASED INSPECTION SCHEME
3. Application for risk-based inspection scheme
4 Conditions for application
5. Risk-based data
6. Calculation, evaluation and results of risk-based inspection
7. Software for risk-based inspection
![Page 28: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/28.jpg)
ARRANGEMENT OF REGULATIONS
28
PART III : AUDIT, CERTIFICATE OF FITNESS AND INSPECTION
8. Audit of risk-based inspection scheme
9. Risk-based Certificate of Fitness
10. Intrusive inspection
11. Power of Inspector to conduct intrusive inspection
12. Preparation for intrusive inspection
13. Pressurized machinery not prepared for inspection
14. Renewal of Risk-based Certificate of Fitness
![Page 29: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/29.jpg)
ARRANGEMENT OF REGULATIONS
29
PART IV
DUTIES OF RISK-BASED INSPECTION USER, RISK-BASED INSPECTION
TEAM AND RISK-BASED INSPECTION TEAM LEADER
15. Duties of Risk-based Inspection User
16. Risk-based Inspection Team
17. Risk-based Inspection Team Leader
![Page 30: SSI_RBI by Tn Hj Mohamad b Jamil (DOSH)](https://reader036.fdocuments.in/reader036/viewer/2022081502/55cf992d550346d0339c04a7/html5/thumbnails/30.jpg)
ARRANGEMENT OF REGULATIONS
30
PART V
MISCELLANEOUS
18. Suspension and termination of Risk-based Approval
19. Suspension and termination of Risk-based Certificate of Fitness