SRP Summer Preparedness 2013

19
SRP Summer Preparedness 2013 Steve Hulet Senior Director Supply & Trading John Underhill Senior Director System Operations Renee Castillo Senior Director Customer Services April 25, 2013 4/25/2013 ACC Hearing 1 Summer Preparedness 2013

Transcript of SRP Summer Preparedness 2013

Page 1: SRP Summer Preparedness 2013

SRP

Summer Preparedness 2013

Steve Hulet Senior Director – Supply & Trading

John Underhill Senior Director – System Operations

Renee Castillo Senior Director – Customer Services

April 25, 2013

4/25/2013 ACC Hearing 1 Summer Preparedness 2013

Page 2: SRP Summer Preparedness 2013

4/25/2013 ACC Hearing Summer Preparedness 2013 2

SRP’s Electric Service Area

Page 3: SRP Summer Preparedness 2013

4/25/2013 ACC Hearing Summer Preparedness 2013 3

Summary

• Peak demand is expected to be slightly

lower than last year’s actual peak.

• Adequate resources have been

secured to meet anticipated demand.

Page 4: SRP Summer Preparedness 2013

Peak Retail Load Forecast

4/25/2013 ACC Hearing Summer Preparedness 2013 4

6598 MW (Net of DSM

Reductions)

325 MW

Demand Side

Management

Reductions

Page 5: SRP Summer Preparedness 2013

Summer 2013 Outlook

6577 MW

1764 MW

Expected Need

6598 MW

955 MW

Total 8341 MW

Expected Capability

Total 8341 MW

4/25/2013 ACC Hearing 5 Summer Preparedness 2013

788 MW

Purchased

Power

SRP

Generation

Reserves

Other Sales

SRP Forecast

Peak Retail

Load

Page 6: SRP Summer Preparedness 2013

4/25/2013 ACC Hearing Summer Preparedness 2013 6

Queen Creek Solar

Mesquite Generating Station

Page 7: SRP Summer Preparedness 2013

4/25/2013 ACC Hearing Summer Preparedness 2013 7

SRP 2013 Resources Expected Capability: 8341 MW

8%

26%

41%

7%

18%

Nuclear - 688 MW

Coal - 2208 MW

Gas - 3407 MW

Renewable Resources - 573MW

Other Purchases - 1465 MW

Page 8: SRP Summer Preparedness 2013

Purchased Power

• Purchased power portfolio is in place to meet

demand.

• Additional purchases may be needed to

respond to forced unit outages.

• Regional market conditions suggest that there

will be sufficient capacity to meet the Arizona

demand.

4/25/2013 ACC Hearing 8 Summer Preparedness 2013

Page 9: SRP Summer Preparedness 2013

Reserves

• Respond to load extremes above base forecast.

• Provide an immediate response to forced

outages.

• Quantity is based on NERC and WECC

operating criteria and contractual arrangements.

• A portfolio of resources is utilized to meet the

reserve requirements.

4/25/2013 ACC Hearing 9 Summer Preparedness 2013

Page 10: SRP Summer Preparedness 2013

Fuel Status

• Nuclear

– Full requirements under contract.

• Coal

– Plants will be above target inventories as we enter the

summer season.

– Full requirements under contract.

• Natural Gas

– Full transportation requirements are under contract with

two pipelines.

– Current supplies of natural gas are adequate.

4/25/2013 ACC Hearing 10 Summer Preparedness 2013

Page 11: SRP Summer Preparedness 2013

Transmission & Distribution

Overview

• Transmission and Distribution Systems are

prepared for summer operations.

• The system has sufficient capacity to

serve forecasted peak demand.

Summer Preparedness 2013 11 4/25/2013 ACC Hearing

Page 12: SRP Summer Preparedness 2013

2013 System Additions – Stations

NEW NUMBER

Substations 2

69/12kV Transformers (28MVA) 4

69/12kV Transformers (56MVA) 2

230/69kV Transformer (280 MVA) 1

69kV Breakers 11

230kV Breakers 2

500kV Breakers 2

12 Summer Preparedness 2013 4/25/2013 ACC Hearing

Page 13: SRP Summer Preparedness 2013

2013 System Additions – Lines

ADDITIONS NUMBER

Transmission Poles

(Replaced or

Installed)

282

Rebuilt or Upgraded

69kV Circuit Miles 16

Upgraded

230kV Circuit Miles 7.5

13 Summer Preparedness 2013 4/25/2013 ACC Hearing

Page 14: SRP Summer Preparedness 2013

System Preparation

• Transmission and substation maintenance and

training will be complete by summer. This includes:

– Line patrols/inspections

– Preventative maintenance

– Pole reinforcement

– Bushing Replacements

– Wildfire coordination

– Operations coordination

– Tree trimming

– Cable replacement

– Storm planning

– Emergency

procedure training

– Blackstart training

14 Summer Preparedness 2013 4/25/2013 ACC Hearing

Page 15: SRP Summer Preparedness 2013

Distribution

• Summer operating procedures reviewed and refresher training provided to O&M personnel.

• Nine mobile substation transformers are available for service if needed.

• If required, the process for implementing rotating outages has been automated.

– The planned sequence of substation outages and the duration of each outage is the same as in the past.

15 Summer Preparedness 2013 4/25/2013 ACC Hearing

Page 16: SRP Summer Preparedness 2013

SRP - Outage Information Resources • Reporting an Outage

• Via web, Mobile device, Phone, Automated Interactive Voice Response System

• Call centers are available 24x7 to report via a live person

• Automated power restoration messages are

delivered to the customer

• Proactive Communications via Text or Email

• Outage Map

• Accessible on SRP website and on mobile devices

• Social Media

• Twitter, Facebook

4/25/2013 ACC Hearing Summer Preparedness 2013 16

Page 17: SRP Summer Preparedness 2013

SRP – Outage Map

4/25/2013 ACC Hearing Summer Preparedness 2013 17

Page 18: SRP Summer Preparedness 2013

4/25/2013 ACC Hearing Summer Preparedness 2013 18

Additional Outage Services

• Ice Plan

• Triggered for widespread outages

• Medical Customers

• Annual emergency preparedness packet

• Designated phone number

• Care Facilities

• Partnered with sister facilities

• If desired, partnered with mobile generation providers

• “Outage School” Opportunities

Page 19: SRP Summer Preparedness 2013

Summary of Year 2013

Projected Conditions

• Transmission, distribution, SRP generation and

planned energy purchases are adequate to serve the

forecasted summer 2013 demand.

• Forecasted 2013 demand is comparable to 2012 and is

supported by a more robust transmission system.

• Contingency plans are in place to handle emergency

events.

• Proactive customer communication plan in place for

outage situations.

19 Summer Preparedness 2013 4/25/2013 ACC Hearing