Squeezer Update
4
G1000099-v1 Squeezer Update February 10, 2010 H1 Squeezer Experiment ANU, AEI, MIT, CIT and LHO collaboration
description
Squeezer Update. February 10, 2010 H1 Squeezer Experiment ANU, AEI, MIT, CIT and LHO collaboration. Progress. On budget & no major roadblocks so far No major schedule setback (maybe ~2 month behind with optics procurement ) 2nd update review was held on February 9 New postdoc (Lisa B.) - PowerPoint PPT Presentation
Transcript of Squeezer Update
![Page 1: Squeezer Update](https://reader035.fdocuments.in/reader035/viewer/2022062323/568161e5550346895dd20504/html5/thumbnails/1.jpg)
G1000099-v1
Squeezer Update
February 10, 2010H1 Squeezer Experiment
ANU, AEI, MIT, CIT and LHO collaboration
![Page 2: Squeezer Update](https://reader035.fdocuments.in/reader035/viewer/2022062323/568161e5550346895dd20504/html5/thumbnails/2.jpg)
G1000099-v1
On budget & no major roadblocks so far No major schedule setback (maybe ~2 month behind with optics
procurement) 2nd update review was held on February 9
New postdoc (Lisa B.) Lasers ready at MIT; locked together OPO ready at ANU with 5-6dB of squeezing
Ready to ship in March, required in early May Electronics is 80% complete; will be done by May Developed a noise and servo model Next: Set up the AEI SHG at MIT
Progress
2H1 Squeezer Status
![Page 3: Squeezer Update](https://reader035.fdocuments.in/reader035/viewer/2022062323/568161e5550346895dd20504/html5/thumbnails/3.jpg)
G1000099-v1 H1 Squeezer Status 3
![Page 4: Squeezer Update](https://reader035.fdocuments.in/reader035/viewer/2022062323/568161e5550346895dd20504/html5/thumbnails/4.jpg)
G1000099-v1
ANU Traveling wave OPO
H1 Squeezer Status 4