SPP Transmission Constraint Mitigation in High Wind Areas
Transcript of SPP Transmission Constraint Mitigation in High Wind Areas
Mitigation of SPP Transmission Constraints in Areas with Relatively
Higher Wind Velocities
MAINTAINED BY
Southwest Power Pool
PUBLISHED: Draft – July 2006
Copyright © 2006 by Southwest Power Pool, Inc. All rights reserved.
Application of Higher Wind Overhead Conductor Capacities
1
TABLE OF CONTENTS
INTRODUCTION .......................................................................................................................................................2
DISCUSSION...............................................................................................................................................................5
Traditional Conductor Rating Calculations.......................................................................................................5 Natural Convection vs. Forced Convection........................................................................................................5 Higher Wind Conductor Capacity Calculations ................................................................................................6 Risk Reduction Factors.......................................................................................................................................7 Wind Shielding Factor (WSF) ............................................................................................................................8 Parallel Winds Factor (PWF) .............................................................................................................................8 Wind Correlation Factor (WCF) ........................................................................................................................9 Conductor Map Location ....................................................................................................................................9 Risk Assessment ................................................................................................................................................10
METHODOLOGY ....................................................................................................................................................12
Application Approach .......................................................................................................................................12 Real Time Monitoring Equipment....................................................................................................................13 Application A: OATT – Long Term Firm Service...........................................................................................14 Application B: OATT – Monthly Short Term Transmission Service: ............................................................15
APPENDIX A – CLASS 4 (GOOD) WIND AREAS WITHIN THE SPP REGION ...........................................17
APPENDIX B - DRAKE 795 ACSR 27/2 CONDUCTOR CAPACITIES VARIED BY WIND VELOCITY,
345 KV ........................................................................................................................................................................23
Application of Higher Wind Overhead Conductor Capacities
2
INTRODUCTION Several generation interconnection study requests are tendered in the SPP queue requesting the
integration of wind plants into the SPP network. When applying for new transmission service
many of these units encounter generation outlet difficulties because the transmission network in
most “high wind areas” is not developed to accommodate regional power transfer.
Certain areas within the Southwest Power Pool (SPP) footprint are fortunate to possess
consistently higher velocities of wind, as seen in Graph 1 (also refer to Appendix A for further
detail). These higher wind speeds may be realized as increased capacity to overhead conductors
within these areas.
GRAPH 1
(Data from National Renewable Energy Laboratory)
Exactly coinciding with these areas of increased wind are existing, planned and potential wind
plants. FERC Order 661 recognizes the unique nature of wind energy technologies “in an
Application of Higher Wind Overhead Conductor Capacities
3
attempt to remedy undue discrimination” in the interconnection of large wind plants. Many
FERC jurisdictionally-bounded entities have enacted renewable portfolio standards mandating
significantly more wind energy development in the near future.
SPP believes it is essential that it develop standards and procedures upon which to aid its
members and customers in this regard. A process allowing for implementation of Real Time
Monitor equipment as mitigation to identified network constraints can make excess capacity
available to the open market (i.e., long term or monthly firm transmission service). In addition,
Real Time Monitoring Equipment will reduce the number of curtailments of active service
schedules on the basis of the ability to track increased capacity due to higher wind.
GRAPH 2
As seen in Graph 2, the geography of SPP most suitable to wind energy development is the
Texas Panhandle, New Mexico, west Oklahoma and west Kansas. As is typical of many wind
siting studies, this happens to be the least densely populated areas of the SPP region. The
transmission system in these areas was generally designed to serve the limited load in the region
and not designed to carry generation capacity on a cross-regional basis. A key challenge to the
integration of wind energy resources into the SPP transmission network is acquiring adequate
Application of Higher Wind Overhead Conductor Capacities
4
transmission service over a transmission network designed to serve limited load and addressing
identified network constraints to the load market outside of the prime wind generation
geography. This same limitation likewise affects integration of other types of generation and, in
general, the market’s ability to use the system. Often, these network constraints are overhead
conductor emergency capacity limitations based on thermal loading limits derived from the
physical properties of the metal conductor.
Historically, emergency ratings for overhead conductors have been conservatively calculated
using cross-sectional wind velocity values of 2 ft/s. (This paper purposefully refers to conductor
‘capacity’ rather than ‘rating’ to distinguish between the rating as defined by SPP, and increased
ampacity due to increased wind velocity.) Current wind energy generating technologies require
approximately 10 ft/s wind to begin generating electricity, at least three times greater than the
commonly used values in typical overhead conductor rating formulas. With necessary wind
velocities for a unit to produce even 10% of name-plate capacity the correlating increase in
conductor capacity for the same wind velocity could be as much as a 80% increase in conductor
capacity. For typical 795 ACSR operated at 345 kV this is approximately an 875 MVA increase
in conductor capacity near a wind plant. Balanced with some Risk Reduction Factors, SPP
proposes to correlate higher wind velocities with the increased transmission capacity caused by
thermal cooling of transmission lines.
This approach is a mechanism for maximizing the use of the transmission system by eliminating
constraints to requests for monthly and long term firm transmission service under the SPP Open
Access Transmission Tariff. aid the integration of wind generation by instituting a process to
mitigate transmission constraints without costly physical upgrades with Risk Identification
Factors with Real Time Monitoring equipment.
Application of Higher Wind Overhead Conductor Capacities
5
DISCUSSION Traditional Conductor Rating Calculations
SPP Criteria 12.2
In accordance with SPP Criteria 12, this methodology applies to conductors 69
kV and above and abides by other general principles of section 12.2, specifically
12.2.2. Therefore, the SPP overhead conductor rating methodology is based on
IEEE Standard 738-1993.
SPP Criteria section 12.2.2. Overhead Conductor, subdivides calculations into the
following categories:
1. Conductor Physical Properties
2. Conduct Geography
3. Radiation Properties
a. Solar Absorbtivity
b. Infrared Emissivity
4. Weather Conditions
5. Max Conductor Temperature
IEEE Standard 738-1993
Standard 738-1996 details temperature related ampacity calculations for overhead
conductors and provides the detailed basis for SPP Criteria 12.2. This standard
outlines the necessary data and formulas for determining total conductor
ampacity.
Natural Convection vs. Forced Convection
Aside from physical conductor size and solar radiation, the rate at which a conductor is
able to convect heat, Qc is the primary determination of maximum conductor ampacity.
Forced and Natural Convection calculations, found among the thermal convection rate
formulas, are used to determine the rate at which the bare overhead conductor most
quickly emits heat (ref: IEEE Std. 738-1993, sec 2.4). The natural convection, formula 2.4.4,
is the rate at which a material in a vacuum convects heat, i.e. 0 ft/s wind. The forced
Application of Higher Wind Overhead Conductor Capacities
6
convection, formula 2.4.3, is the rate at which a material exposed to a given wind
velocity at a specified angle, Kangle, convects heat. The IEEE standard assumes 2 ft/s as
the maximum wind velocity and determines the greater convection rate of the two. For
Drake conductor, 795 kcmil 26/7 ACSR, the convection rate is greater in a vacuum.
(problem statement 2.6.1.1)
Problem statement 2.6.1.1 in the IEEE standard demonstrates where 795 ACSR 26/7
Drake conductor at 40 degrees C (104 deg F) and sea level has a higher Natural
Convection rate than would occur compared to the Forced Convection rate assuming heat
dissipation at a 2 ft/sec wind velocity. The results demonstrate the conservative
application of wind in the conductor rating calculations.
Comparison of Natural vs. Forced Convection is necessary on the assumption that only
low wind velocities are considered in the determination of conductor ampacities.
Industry practices, for conservative reasons, have implemented conductor ratings based
on low wind velocities in consideration of typical peak loading conditions.
Higher Wind Conductor Capacity Calculations
Conductor capacity based on increased wind velocity is calculated by application of a
range of wind velocities, Vw, applied in the forced convection (Qc) portion of the
capacity calculation. This is one of four components used to determine the total heating
of overhead conductors. The four components are: solar heat gain (Qs), radiated heat
loss (Qr), forced convection heat loss due to wind (Qc) and conductor heating due to the
current (I) and resistance (R) relationship, I2*R(Tc).
Velocity of wind in the forced convection formula, Qc = [1.01+0.371(DpfVw/UF)0.52],
has a significant impact on the final calculated ampacity of a conductor.
Application of Higher Wind Overhead Conductor Capacities
7
0 200 400 600 800
1000 1200 1400 1600 1800 2000 2200 2400 2600
Conductor Capacity Increase
2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 Wind Velocity (ft/sec)
GRAPH 3
Capacity Increase, MVA - 795 ACSR, 345 kV
Graph 3, below, shows ratings for a 795 ACSR (drake) conductor operated at 345 kV
(refer to Appendix B for further detail). Conductor capacities are recalculated for
increasing wind velocities through 42 ft/s. The standard rating for this conductor at 2 ft/s
is 1077 MVA. This is shown as the base graph in blue.
Risk Reduction Factors
Risk of violating line clearance and safety code or sacrificing conductor life are primary
concerns when increasing line capacities. With increased wind speed assumptions in
capacity calculations, the casual observer may be concerned that weather patterns are not
homogenous and, therefore, critical overhead conductors may not benefit from the same
wind patterns driving wind turbines. To reduce this associated risk, some conservative
assumptions are implemented into the proposed variable capacity application. These risk
Application of Higher Wind Overhead Conductor Capacities
8
reduction mechanisms explained in the following discussion include: Parallel Wind
Factor, Wind Shielding Factor and Wind Correlation Factor.
Wind Shielding Factor (WSF)
A 10% reduction is applied to account for the possible shielding of wind due to trees or
geographical anomalies.
Parallel Winds Factor (PWF)
This factor reduces effective convection values by 60% to account for the possibility of
winds only parallel to the conductor, rather than perpendicular. This rate is taken from
IEEE std. 738-1993 section 3.2 as the reduction in effectiveness of convective heat loss
due to parallel wind.
Combining the Parallel Winds and Wind Shielding Factors reduce any calculated wind
based conductor capacity increase by 70% resulting in a more conservative Conductor
Capacity Increase profile. See Graph 4 (compare with Graph 3).
GRAPH 4
Reduced by 60% Parallel Winds and 10% Shielding Factors Rating Increase, MVA – 795 ACSR, 345 kV
0
500
1000
1500
2000
2500
2.0 6.0 10.0 14.0 18.0 22.0 26.0 30.0 34.0 38.0 42.0
Wind Velocity (ft/sec)
Conductor Capacity Increase
Application of Higher Wind Overhead Conductor Capacities
9
Wind Correlation Factor (WCF)
Wind velocities at a nearby reference tower (or wind plant) can often be correlated to the
wind velocities at the transmission limiting overhead conductor. Wind correlations are
influenced by diurnal winds, microclimates and homogeneity of weather patterns. Given
specific geographical locations, this correlation can provide a basis for establishing the
variable velocity of wind for an identified transmission network constraint.
Similar to wind correlation studies performed when identifying potential wind sites, wind
Correlation Factors can be derived using data from environmental monitoring wind
stations, where available. For example, the Oklahoma Mesonet.org website lists one
hundred fifty-eight monitoring stations across the state with historical data posted for
these stations. This proposal requires a two year minimum of historical weather data to
establish a Wind Correlation Factor and applies to those wind power areas classified as
Fair (class 3) or better (refer to Conductor Map Location section; Appendix A). Data can
be compared with the initial data prepared for developed wind locations (accessible
online at: http://www.mesonet.org/).
Correlation Factors assign a percent value associating wind velocity at one location with
wind velocity at another. For example, if wind at location ‘A’ is considered 1 and wind
at location ‘B’ is correlated to ‘A’ by .5, there is a .5 relation or 50% correlation of
location ‘B’ to ‘A’. Or, if the wind velocity at location ‘A’ is measured 20 ft/s then the
Correlation Factor of .5 assumes wind is 10 ft/s at location ‘B’. Correlation Factors are
an average based on historical weather data.
If no data is available, a default 10% correlation will be assumed.
Conductor Map Location
1. To be qualified, the entire line (including both terminal ends) of identified
overhead conductor constraints must fall within a wind power area classified
as Good, or better.
Application of Higher Wind Overhead Conductor Capacities
10
2. Qualified conductors shall be determined by SPP Staff.
3. The maps utilized for the location assessment are included in Appendix A.
Risk Assessment
Graph 5 shows two overhead conductor capacities comparing traditional conductor rating
calculations with the previously outlined approach of implementing risk reduction
factors. The blue line represents an approximate conductor capacity increase with the
application of parallel winds and risk reduction factors, while the other more aggressively
increasing red line represents an approximate conductor capacity increase as affected by
traditional cross sectional winds in calculations.
GRAPH 5
Area of Risk
Application of Higher Wind Overhead Conductor Capacities
11
In this graph, increased risk associated with higher conductor capacities is represented as
a shaded area. The reduced amount of risk from application of the associated risk
reduction principles is shown as the cross section area under the blue line resulting in a
45% increase. This is taking into account the 60% decrease in convection for parallel
wind and the 10% decrease for potential conductor shielding.
Next, the application of Wind Correlation data results in further reduction in risk by tying
in a realistic expectation of wind levels. As examples show, the 50% correlation and
20% correlation factors reduce the potential conductor capacity increase to 22% and 9%
respectively. It must be kept in mind that a conductor has to meet the requirements of
Conductor Map Location to be eligible. Also, if no data is available, then a 10%
correlation will be assumed.
Finally, any remaining risk associated with the final calculated conductor capacity
increase is further mitigated with the requirement to install Real Time Monitoring
Equipment to all facility components subject to sag and clearance standards. The ability
to monitor conductor facilities for which this process is applied acts as a final safety net.
Application of Higher Wind Overhead Conductor Capacities
12
METHODOLOGY Application of Higher Wind Overhead Conductor Capacities determination can be
triggered whenever overhead line conductors (i.e., not associated terminal equipment)
located near areas of relatively higher wind velocities are identified as constraints to
transmission service. However, the Higher Wind Overhead Conductor Capacities
approach is not a guarantee of transmission service and does not apply to identified
transmission constraints outside of the SPP region. Also, facilities associated with
system voltage or angular stability concerns shall not be considered.
To determine if an identified conductor constraint can be mitigated the only information
required beyond existing information is historical weather data, to derive the Wind
Correlation Factor. If weather data is not available, the constraint may still be eligible for
mitigation if it meets the requirements of Conductor Map Location. Wind studies
conducted for purposes of wind generation siting/micrositing may be utilized if the
results apply to the geographic area containing the facility and if the results coincide with
the peak loading time frame of the facility.
Application Approach
1. An SPP tariff study identifies an overhead conductor constraint to
transmission service.
2. SPP staff will calculate the base conductor capacity increase of the monitored
overhead conductor using 40 ft/s wind velocity (simulates wind velocity for
typical wind turbine operating at 100% capability).
3. The calculated capacity will be reduced by applying the known 60% and 10%
Risk Reduction Factors.
4. The WCF will be determined via two-year historical weather station records
or generation wind siting studies. If no data exists to substantiate a WCF, then
the WCF will be assumed to be 0.1 as long as the constraint meets the
requirements of Conductor Map Location.
5. SPP staff will apply the Risk Reduction Factors:
Application of Higher Wind Overhead Conductor Capacities
13
A. Reduce by 60%;
B. Reduce by 10%; and
C. Multiply by Wind Correlation Factor.
6. The constraint can be considered mitigated if the remainder of the constrained
overhead conductor capacity increase is greater than zero:
A. After the reduction of the contingency loading level, and
B. Less the studied service request impact.
7. Service granted based on application of Higher Wind Overhead Conductor
Capacities will be curtailed based on SPP surveillance of Real Time
Monitoring Equipment output and analysis of results.
8. A constraint may only be mitigated once via Real Time Monitoring
Equipment, and mitigation applies only to the party or parties paying for said
equipment.
9. Service granted based on application of Higher Wind Overhead Conductor
Capacities will be included, as usual, in other Tariff and Planning studies.
Real Time Monitoring Equipment
Tension based transmission line monitoring systems provide real time data for
transmission lines upon which transmission operators can make real-time decisions.
These systems provide ready information by which transmission operators can monitor
how closely a conductor is to maximum clearances and loadings.
Installation of real-time monitoring equipment will improve the security aspect of the
transmission system. Real-time monitor systems installed on conductors identified as
constraints to transmission service will aid system operators in identifying system loading
risks.
Transmission Service Agreements approved through mitigation of identified overhead
conductor constraints via this procedure are not valid without an agreement to install
Real-Time Rating equipment on specified circuits. For practicality, Real-Time Rating
Application of Higher Wind Overhead Conductor Capacities
14
equipment installation costs will be estimated based on the current cost per
kilometer/mile from approved vendors.
Real-time monitoring systems are required as part of the Higher Wind Overhead
Conductor Capacity provision and must be funded by the Transmission Customer. At the
time of this publication, costs are approximately $2,000 per conductor km to equip. An
approved list of vendors supplying Real-Time Monitoring Equipment will be maintained
by SPP staff. All real-time monitoring equipment must be selected from the approved list
of vendors and agreed upon by the Transmission Owner(s) of the identified conductors.
Application A: OATT – Long Term Firm Service
Requests for transmission service found to be limited by identified overhead conductor
constraints can seek application of the Higher Wind Overhead Conductor Capacity
procedure as a constraint mitigation alternative to facility upgrades. The Transmission
Customer commits to install Real-Time Monitoring Equipment per that section.
Example:
POR = Control Area ‘A’
POD = Control Area ‘B’
Amount = 200 MW
Duration = 12 Months
The service request is evaluated via the SPP Aggregate Study process and a constrained
overhead conductor is identified having a 12.5% Transmission Distribution Factor (TDF)
response. The 795 ACSR conductor is operated at 345 kV and is simulated at 105%
loading with Rate B = 1077 MVA. There is no wind correlation data available, but the
line falls within a Good wind power area. So a Correlation Factor of 0.1 will be applied.
In this example, the line is overloaded by 2.3% or 25 MVA over the emergency rating.
SPP staff will determine the conductor capacity increase based on 40 ft/s wind and then
apply the Risk Reduction Factors. This facility at 40 ft/s wind velocity will have a
Application of Higher Wind Overhead Conductor Capacities
15
capacity of 1389 MVA. Application of the Risk Reduction Factors reduces this amount
by 60% for Parallel Winds, 10% for Wind Shielding and a 0.1 Wind Correlation ratio.
The resulting increase follows:
“High Wind Area” Overhead Conductor Capacity = 1077 + [1389 – (1389 x 0.6) – (1389
x 0.1)] x 0.1 = 1077 + 42 = 1119 MVA (1119 / 1077 = 3.9% capacity increase)
This constraint is mitigated since 42 MVA covers the calculated 25 MW service request
impact.
Application B: OATT – Monthly Short Term Transmission Service:
i.e. Flowgate Mitigation
This methodology can be applied toward mitigation of the constraining monitored
element of a traditional contingency based Flowgate.
Example:
POR = SPS, Source = Plant ‘A’
POD = ENTR
Amount = 100 MW
Duration = 1 Month (June)
Flowgates JUDGRNSPMUL, SPSSPPTIES and ELKXFRTUCOKU are identified as
possible constraints to flow in this direction. The Available Transfer Capability (ATC)
data associated with these flowgates for the SPS – ENTR transfer direction is as follows:
80 MW limit, JUDGRNSPEMUL, 3.4% TDF
287 MW limit, ELKXFRTUCOKU, 34.6% TDF
620 MW limit, SPSSPPTIES, 100% TDF
In this ATC analysis, the flowgate limits the service request to 80 MW of the requested
100 MW. This is a typical OTDF flowgate limited by the Judson Large to Greensburg
Application of Higher Wind Overhead Conductor Capacities
16
115 kV circuit with an 80 MVA emergency rating for the outage of the Spearville to
Mullergren 230 kV circuit. The TDF for this circuit is 3.4%.
The other two flowgates are not candidates for this application. The ELKXFRTUCOKU
flowgate consists of a transformer limitation not subject to capacity adjustments from
wind. The SPSSPPTIES is a PTDF flowgate representing the SPS stability interface limit
and is also not subject to modifications by this approach. However, in this analysis, the
transmission customer may see a benefit because the only limit to this service request is
the Judson Large overhead conductor facility. With a 3.4% TDF, the 80 MW limit
indicates a very small margin of additional capacity required to accommodate the request.
(20 MW * 0.034 = 0.68 MW)
For this example we will say a 15% wind correlation factor was identified. Working
through the numbers in this example, SPP staff will determine the conductor capacity
increase again based on 40 ft/s wind and then apply the Risk Reduction Factors. This
facility at 40 ft/s wind velocity will have a capacity of approximately 101 MVA.
Application of the Risk Reduction Factors reduces this number by 60% for Parallel
Winds, 10% for Wind Shielding and applies a 0.15 Wind Correlation ratio. The resulting
increase follows:
“High Wind Area” Overhead Conductor Capacity = 80 + [101 – (101 x 0.6) – (101 x
0.1)] x 0.15 = 80 + 5 = 85 MVA (85 / 80 = 6.3% capacity increase)
The constraint will be mitigated and the full 100 MW service requested can be granted
since the additional 5 MVA is adequate to cover the calculated 0.68 MVA overload.
Application of Higher Wind Overhead Conductor Capacities
17
APPENDIX A – Class 3 + Wind Areas within the SPP Region
Average Annual Wind Power by State
The wind resource is expressed in terms of wind power classes, ranging from class 1 (the lowest)
to class 7 (the highest). Each class represents a range of mean wind power density or
approximate mean wind speed at specified heights above the ground. Areas designated class 3 or
greater are suitable for most wind energy applications, whereas class 2 areas are marginal and
class 1 areas are generally not suitable (accessible online at: http://rredc.nrel.gov).
Power Class Legend:
Class Potential 1 Poor 2 Marginal 3 Fair 4 Good 5 Excellent 6 Outstanding 7 Superb
Application of Higher Wind Overhead Conductor Capacities
18
Arkansas
Application of Higher Wind Overhead Conductor Capacities
19
Missouri
Application of Higher Wind Overhead Conductor Capacities
20
Kansas
Oklahoma
Application of Higher Wind Overhead Conductor Capacities
21
West Texas
Application of Higher Wind Overhead Conductor Capacities
22
New Mexico
Higher Wind Overhead Conductor Capacities
23
APPENDIX B - DRAKE 795 ACSR 27/2 Conductor Capacities Varied by Wind Velocity, 345 kV
Conductor Capacity Calculations
Typical conductor capacity calculations assume a cross-sectional wind to the axis of the conductor. This is reflected as Kangle = 0 in the wind
direction multiplier. Application of a conservative assumption of only parallel wind, absence of any cross sectional wind benefit, provides the
most conservative wind-related convection numbers in the following calculations.
WEATHER INPUTWind Velocity (ft/s)= 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0
Angle (deg) between wind and conductor= 90.0Direction of Line (E-W =1 , N-S =0)= 1.0
Atmosphere (Clear =1: Indus =2)= 1.0Cond elevation (feet) above sea level= 1150.0
Cond. Latitude (degrees)= 38.5Local Sun Time (10, 11, 12, 13, 14)= 12.0
Ambient air temperature (Ta in celcius)= 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8 37.8Ambient air temperature (Ta in F)= 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
CONDUCTOR INPUTCond. O.D. (in.) = 1.2
Cond. Temperature (C):Tlo= 25.0Thi= 50.0
Cond. ac Resistance (R(Tc)) (ohm/mi):R(Tlo)= 0.0R(Thi)= 0.0
Emissivity (epsilon) = 0.7Solar absorptivity (alpha) = 0.9
Max. allowable cond. Temp (in C) = 100.0
Calc: THERMAL RATING IN AMPERES 1803.0 2122.3 2379.5 2583.0 2754.0 2902.9 3035.5 3155.6 3265.7 3367.6 3462.8 3552.1 3636.4 3716.3 3792.3 3864.9 3934.5 4001.2 4065.4 4127.3TR(Amps)= 1802.9 2122.3 2379.5 2583.0 2754.0 2902.9 3035.5 3155.6 3265.7 3367.6 3462.8 3552.1 3636.4 3716.3 3792.3 3864.9 3934.5 4001.2 4065.4 4127.3
Calc: THERMAL RATING IN MVAkV= 345.0
MVA= 1077.4 1268.2 1421.9 1543.5 1645.7 1734.6 1813.9 1885.6 1951.4 2012.4 2069.2 2122.6 2172.9 2220.7 2266.1 2309.5 2351.1 2390.9 2429.3 2466.3Normalized to MAX Ambient 1.0 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.8 1.9 1.9 2.0 2.0 2.1 2.1 2.1 2.2 2.2 2.3 2.3
Delta Increase in MVA 0.0 190.8 344.5 466.1 568.3 657.2 736.5 808.2 874.0 935.0 991.8 1045.2 1095.5 1143.3 1188.7 1232.1 1273.7 1313.5 1351.9 1388.9Incremental Increase 0.0 15.6 13.6 11.2 9.5 8.4 7.6 6.9 6.3 5.9 5.5 5.2 4.9 4.7 4.4 4.3 4.1 3.9 3.8 3.6
% Increase in Conductor Capacity 0.0 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.8 0.9 0.9 1.0 1.0 1.1 1.1 1.1 1.2 1.2 1.3 1.3
Base Conductor MVA @ 375kV Rating 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 1077 107760% Parallel Winds Factor and 10% Shielded Wind 0.0 57.2 103.3 139.8 170.5 197.2 220.9 242.5 262.2 280.5 297.5 313.6 328.7 343.0 356.6 369.6 382.1 394.1 405.6 416.7Adjusted % Increase in Conductor Capacity 0.000 0.053 0.096 0.130 0.158 0.183 0.205 0.225 0.243 0.260 0.276 0.291 0.305 0.318 0.331 0.343 0.355 0.366 0.377 0.387