Wellington City Council

Forecasting beyond 30-yearsAsset Analytics

SPM User Group

March 2014

Page 2: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

The Journey…….

Real World Problem

The Foundations

Our ‘Strategy’

The Plan

The Rationale

The Models (Analytics)

The Benefits

Our Vision

Page 3: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Real World Problem - Schematic

Page 4: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

The Practical Problem – Deterioration Curves

WCC’s Assets are decaying at a rate of $2m per week

Page 5: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Wellington City’s 3-Water Assets Problem

Page 6: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Here’s where we started….

Data Quality – low mathematical precision < 35%(data confidence)

Data Consistancy < 30%(data completeness)

Data not aligned

Data not integrated (‘joined up’ or ‘accessible’)

Advanced analytics simply not possible

.........off to the drawing board

Page 7: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

The Foundations3-Pillars (Strategic Decisions)

Page 8: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

1st Pillar - Meta-Data Standards

1st Strategic Decision

3-Waters

& Transport

& Built

& Green

Page 9: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

2nd Pillar - Asset Mgt. Information Systems

2nd Strategic Decision

Page 10: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

3rd Pillar - Analytics

3rd Strategic Decision

DATA SCIENCE

(Statistical Models)

MATERIALS SCIENCE

(Physical Models)

Page 11: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

3 Pillars - Integrated

Having Set the Scientific Platform…..

These must line up

Page 12: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

3 Pillars – Disparate Data Alignment

Where we were

Page 13: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

3 Pillars - Integrated

Where we are / working towards………

Page 14: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Our ‘Strategy’Standards & Models

Page 15: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Building Competency

Page 16: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Adopting Standards

International StandardsLocal, Regional, National StandardsDesign & Build StandardsTechnical StandardsGIS StandardsMeta-Data Standards

Heirarchy

Page 17: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – The Model HierarchySocial ModelsCultural ModelsEnvironmental ModelsEconomic ModelsFinancial ModelsDemand ModelsCapacity ModelsResilience Models, Criticality ModelsCondition ModelsStatistical Models

Heirarchy

Page 18: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – The Model Hierarchy

Fundamental Rethink

The most fundamental of all the building blocks are not / have never been established

Meta-Data Schema’s & Statistical Models

Page 19: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – The first blocks

Page 20: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Asset Agnostic

Page 21: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – WCC’s Asset Platform

Page 22: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

The Plan‘Build it’

Page 23: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Current StateDetermining Attribute Deficiency

Developing Statistical Models – At an Asset Attribute Level of Data

Statistical Models(Harmonics)

Page 24: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Current State – Future StateDeveloping the Plan and “The Case”

Resourcing the Plan

Work Packages

Better Busines Case

Proof of Concept(Harmonics)

Page 25: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

The Models (Analytics)Achievements to Date

Page 26: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Investment Analytics – Wastewater (Pipes)

Statistical Language - RKarori - Renewals Karori - Growth Karori - Both

Page 27: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Investment Analytics – Wastewater (Pipes)

Statistical Language - RMiramar - Both Karori & Miramar - Both Wellington - Both

Page 28: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Investment Analytics – Roading (reseals)

Statistical Language - RKarori - Renewals Wellington Renewals

Page 29: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

The Benefits

Page 30: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Captured Interdisciplinary Benefits

Balanced / Informed evidence-based decision-making

Page 31: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Benefits – In Practice

Engineering (Asset / BU)

• Forwards Works Programs – clear line of sight• Investigation (e.g. Condition Assesments, R&M,

Materials Sampling, CCTV) • Replacement (incl. Interactivity – Roading Reseals vs.

Pipe Renewals)

• Carrying ‘Risk’ – on Criticality Paradigm (e.g. Run-to-Fail)

• Asset Performance (Practical & Financial)

Page 32: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Benefits – In Practice

Financial

• Forwards Works Programs – transparency (30+ years)Renewals Forecasting (depreciation commitments)Growth Forecasting (LOS and Dev. Cont. Commitments)

• WCC Borrowing Implications (e.g. Funding Caps)

• Asset Performance Financial – Economic Development Headroom

• Carrying ‘Risk’ – on Cost / Benefit / Risk Paradigm

• Meeting OAG Audit Requirements 30 year Infrastructure Plan

Page 33: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Benefits – In Practice

Page 34: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Benefits – In Practice

Spatial Planning

• Economic Development (evidence base decision-making)• Economic Utility – Optimised urban planning –

infrastructural capacity• Opportunity Cost of Investment – by Suburb (e.g.

Karori vs. Mirimar vs. Linclonshire Farm)

• Spatial Planning • Capacity Metrics – e.g. HEU’s maximum density• Social Metrics – e.g. Walking distance to a park

Page 35: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Our ‘Vision’

Page 36: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – WCC’s Asset Platform

Page 37: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Intra-sectoral

Page 38: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Intra-sectoral

Page 39: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – The Sector

Page 40: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Inter-Sectoral

Page 41: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Inter-Sectoral

Page 42: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Interdisciplinary Model – Inter-Sectoral

Page 43: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Practical Vision – Returning to ‘First Principles’

Doing the ‘BASICS’ well...

Page 44: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Here’s where we started are (<2 years)….

Data Quality – low mathematical precision < 35% / 68%(data confidence)

Data Consistancy < 30% / 73%(data completeness)

Data not aligned / Data Aligned

Data not integrated (‘joined up’ or ‘accessible’) / Data Integrated

Advanced analytics simply not possible / possible & proven

.........off to file the drawing board

Page 45: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Some ‘Cool Stuff’

Page 46: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Electronic Transfer from BIM to WCC Asset Database SPM• Taking information from Building Design through to As Built

documentation and transferring it to Asset Management Database to allow for Analysis of Assets.

• Also useful for Facilities Management of the Building asset with both Database information & 3D model

• Less input/cost into setting up building information in Database• Higher quality & accurate information to allow better management of

building

Presenter
Presentation Notes
Title pages
Page 47: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Proof of Concept 1

• Using Revit model of an existing 5 unit stand alone site, populating the model & then transferring information via Access or Excel to then transfer information into SPM

• Existing information in SPM• Model designed in 2 parts. A site

model with individual buildings linked to site

Page 48: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.
Page 49: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.
Page 50: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.
Page 51: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

SPM OUTPUT ON PROJECT IN EXCEL

Page 52: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

SPM INFO FOR REVIT

Page 53: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

How Revit Stores information

Page 54: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Revit can schedule these parameters

Page 55: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

BIM to Database• Main BIM software in buildings is Archicad, Revit, Bently &

Vectorworks. Predominantly Revit & Archicad used by Architects & Engineers on buildings.

• Vendor neutral or common methods of data transfer• Revit DB Link & Schedule to Excel both freeware add=-ins to Revit• To import into SPM only so much information required from Model,

so an intermediate step is needed• Excel & Access are used as common software that can manage

the amount of data exported from Revit. Excel more common in construction industry

• An important next step is developing a validation process to insure all relevant fields are not empty and in correct format

Page 56: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Data Exchange Revit DB link• Exporting from Revit Model for this project was

successful to both Access & Excel.• Information overload. Exporting data from this model

into Excel created over 250 worksheets with over 3500 headers. These are the generic Revit exports of all Family types, whether there are any actual families in model or not.

• Trying to find relevant fields was difficult to get to

Page 57: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Revit Schedule to Excel• This only exported what was in schedule, so could be more

targeted.• Shared parameters that matched SPM database were developed

and put into Revit at Project & Family (component ) level.• Each individual family had to have its own schedule.• These were exported to individual Excel files• One file (Ceilings) was imported into SPM and then exported again

to give SPM Unique Key to component• This was then successfully transferred back into the Model. So

individual component in model has SPM key assigned to it.

Page 58: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Lessons Learned to Date on Standalone• We have demonstrated a 2 way link between 3D model & SPM database, using

shared parameters to harmonise fields between SPM and Model• The process used is cumbersome using schedules, so for larger projects the Full

Export to Excel or Access will need to be investigated with setup search functions to obtain relevant information

• Generally most elements & components fall into the Database Hierarchy but a few items do not schedule well at present

• Walls do not schedule by space. As a family they have 2 sides so relate to spaces either side. In the Wall Schedule or Material take off the information falls out by wall types, which is not useful. Further investigation is required.

• A further step is to explore services which extend through site & rooms such as hot or cold water pipes and drainage

• And the next project for Proof of Concept is……….

Page 59: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

150 unit apartment block

Page 60: SPM User Group - SPM Assets · SPM User Group March 2014. The Journey… ... DATA SCIENCE (Statistical Models) ... all relevant fields are not empty and in correct format.

Wellington City Council

Forecasting beyond 30-yearsInfrastructural Asset Analytics

QUESTIONS?Haydn Read BSc.(Hons), MSc., Adv. Dip Fin., MBA (Dist.), MIoDNZ, MIGENIUM, MIPENZ

Strategic Asset Planning Manager, WCC

[email protected]