Spider excavator contour drainage v11
-
Upload
eric-lestock-kay -
Category
Engineering
-
view
89 -
download
0
Transcript of Spider excavator contour drainage v11
1
Stabilizing Slides
Using a Spider Excavator
Eric L Kay
Rob Wilson
2
Part 1 - Spider Excavator, (the tool)
Part 2 – Stabilizing Landslide Headscarps
Part 3 - Multiflow Drainpipe
Part 4 - Contour Drainage
Eric
Eric
Rob
Rob
Stabilizing Slides
3.. . Part 1 - Spider Excavator Description
Kaiser X5 M
4
Work on steep slopes 100% (One to One slope)
Walks on 4 legs
Extending stick
Twist wrist bucket
Hydraulic thumb
Hydraulic winch 12,000lbs
Pushes and pulls itself around
Optional Hydrostatic drive (6kmph) Kaiser X5 M
Rolls on two back wheels
5
Agility
Step over;
- Logs
- Shrubs
- Small trees
- Boulders
Schaeff HS 40 D
6
Safely work on a 1 to 1 slopeaiser X5 M
7
Previously deactivated road system
site accessibility
Schaeff 41 M
8
Beyond the reach of a normal excavator
Perched material in the gully
Schaeff 41 M
9
The power of an excavator1 1/2 times the size
Schaeff HS 40 D
10Working in water 2 meters deep
Schaeff HS 40 D
11
Transportable by HelicopterFor remote site work
Fueled and ready to work
12
Part 2 – Stabilizing
Landslide Headscarps
13
Retrogressive Failures – Issues:• Maintenance costs/problems – Loss of road use, temporary/permanent
• Impediment to re-establishment of vegetation
• Destruction of remedial works
• Loss of productive land inventory
14
Unstable headscarp
15
Kaiser X5 M
Sloping back of the headscarp
16
Large woody debrisKaiser X5 M
Sloping back of the headscarp
17
Caution
� � � � �
Need good
understanding
of soils, water
and slope processes
18Part 3 - Multiflow Drainpipe
19
Multiflow pipeAvailable in 15,30 & 46 cm widths
Made up of multiple
miniature “Big O” pipes
laid flat, joined together
and covered in a filter
fabric
A viable alternative for
Drain rock
20
Part 4 - Contour Drainage
21
This site is located in the Cariboo Mountains where a “hanging glacial” valley slopes into a typical “U shaped glacial valley”.
Glacial fluvial out-wash deposits are buried below glacial till, resulting in seepage related slope instability problems.
22
Road cut-slope. Tension crack showing evidence of slope
ilure, along with visible evidence of retrogression of the headscarp.
This site has been a an ongoing maintenance problem, with some
restriction of road use.
Tension crack – indicator
of slope failure
23
The Spider Excavator digs a trench above the crest of the headscarp and behind the tension crack.
The trench is 3m in depth with the objective to interrupt the sub-surface water flows.
he base of the trench should lope at least 2% towards an utlet end of the drainage.
24
he multiflow drainage composite was put
to the bottom of the trench, against the uphill
ope, and a 6 mil polyethylene sheet placed
ainst the down slope side for an impervious
arrier.
l placement was done from the surface. Workers
re not permitted to enter the trench.
e Multiflow pipe was attached to the poly and
wered into the trench from the surface.
25
The multiflow drainage composite was put
into the bottom of the
trench, against the uphill slope, and a 6
mil polyethylene sheet against the down
slope side.
Excavator starts backfilling the
trench. Woody
debris is then scattered over top
Alternatively a composite
“Blanket Drain”
material such as Nudrain DM50 could
be employed
26
Excavator starts backfilling the
trench. Woody
debris is then scattered over top
27
Steady
seepage from
subsurface
drainage
collector
(Multiflow)
5 liters/min
X
60 min/hr
X
24 hrs day
= 7200 liters/day
That’s over 7000 kg less weight
within the slope on a day to day
basis!
What
difference
does a month
or two make?
28
inished swale above head scarp with debris scattered over top.
wale directs surface water away from problem area.(Picture has been stretched to emphasize the swale)
29
Finished drainage swale directing surface run-off to the flank of slide area
30table cut slope with reduced seepage after finishing the contour drainage worNo longer a continuous road maintenance issue not is there the problem of loss of road use.
31
Thank You
Eric Kay - Rob Wilson
32
ReferencesKaiser X5 M - JOHOE IncJoe Gisler 250 398-3507
Schaeff HS 40 D - Nu Creek DevelopmentsLen Masson 250 833-0173
Schaeff HS 41 M - J W Berry Trucking
Brad Berry 250 724-4912
Rob Wilson - Weldwood - 250 392-7731
Eric L Kay - Kay & Associates - 250 337-5096