Page 1: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     1 of 17 

Specification for Heating Pipe                   

Page 2: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     2 of 17 

TABLE OF CONTENTS 

1.SCOPE 3

2.DEFINITIONS 3

3.REFERENCES 3

4.RESPONSIBILITIES 4

5.GENERAL SPECIFICATIONS 5

6.TESTING 6

7.DIMENSIONAL AND ACCEPTABILITY STANDARDS 7

8.WORKMANSHIP 8

9.COATING 9

10.MARKING 9

11.HANDLING, STORING AND SHIPPING 10

12.CERTIFICATION, TRACEABILITY, AND DOCUMENTATION 10

13.WARRANTY 11

 

 APPENDIX A:  SUMMARY OF NDE TESTS 

APPENDIX B:  VENDOR DATA REQUIREMENTS LIST (VDRL) 

APPENDIX C:  INSPECTION MATRIX 

APPENDIX D:  LINE PIPE DATA SHEET 

 

Page 3: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     3 of 17 

1.  SCOPE 

 This  specification  sets  out  requirements  for ERW, or  SEAMLESS  line pipe of API  Spec 5L Grade X‐52  to be used  to provide buoyancy to a flowline bundle during installation. 

 

2.  DEFINITIONS 

 a)  COMPANY:   

 b)  VENDOR:  The  company  that  contracts 

to  furnish  pipe  according  to this specification 

 c)  CONTRACT:  The  entire  written 

procurement  agreement between  VENDOR  and COMPANY 

 d)  STANDARDS  Industry codes, standards, and 

recommended  practices referenced herein. 

 e)  WORKS  The  location(s)  at  which 

manufacturing, inspection and testing are performed. 

 f)  NONCONFORMITY :  An  instance  of  failure 

to  meet  contractual requirements,  including physical,  procedural  or performance deficiencies. 

 g)  NONCONFORMING MATERIALS:  

• Materials  which  do  not  meet requirements set out herein 

• Materials  for  which  documentation  is incomplete  according  to  the requirements set out herein 

• Materials  which  were  not  processed according  to  the  requirements  set  out herein 

• Materials which have not been subjected to or passed the tests required herein 

• Materials which,  if  used will  result  in  a non‐conformity 

• Documents  or  software which  does  not meet the requirements set out herein 

 2.1  CONTRACTOR REPRESENTATIVE  

Vendor shall designate in writing to Company an  authorized  representative  to  serve  as liaison with COMPANY on matters associated with  this  specification  and  on  the  purchase order  or  Contract  referencing  this specification.    This  representative  shall  be designated  prior  to  the  performance  of services associated with this specification and the  purchase  order  or  Contract  referencing this specification. 

 2.2  DOCUMENT PRECEDENCE  

In the event of conflict between documents, the priority shall be as follows: 

 a) purchase order or Contract b) This specification c) Referenced Standards 

 However,  conflicts  shall  be  reviewed  and resolved  with  COMPANY's  representative prior  to  initiation  or  continuation  of  the services  to be performed  in association with the purchase order or Contract. 

 

3.  REFERENCES 

 The  latest  edition  of  the  following  codes, standards and specifications are incorporated by  reference as  they apply  in  the context of this specification: 

 American Petroleum Institute 

 API  Spec  5L  (41st  Edition)  specification  For Line Pipe 

Page 4: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     4 of 17 

 ASTM A‐370  Standard  Methods  and Definitions  for  Mechanical  Testing  of  Steel Products 

 ASTM E‐23  Standard  Methods  for Notched  Bar  Impact  Testing  of  Metallic Materials 

 

4.  RESPONSIBILITIES 

4.1  GENERAL VENDOR  shall  provide  all  labor,  materials, tools,  equipment  and  shall  undertake  all inspection,  handling,  reporting,  storage  and shipping  necessary  to  furnish  materials and/or  perform  the  work  according  to  the requirements  of  this  specification  and  the CONTRACT.    If  VENDOR  believes  that  this specification conflicts with other terms of the CONTRACT,  VENDOR  shall  inform  the COMPANY and resolve the conflict according to the terms of the CONTRACT. 

 4.2  REPORTING AND APPROVALS 4.2.1  Deviations and Disclaimers 

Work carried out under this specification shall be performed  according  to  all  requirements herein without  deviations  or  disclaimers.    If COMPANY  approves  changes,  they  will  be incorporated into a revised specification, and this specification will be void. 

 4.2.2  Disposition of Non‐Conforming Materials 

COMPANY may  reject  any  pipe which  does not  conform  to  these  specifications.  Such rejections  shall  not  delay  the  delivery schedule or increase costs to COMPANY. 

 4.2.3  Certification 

VENDOR shall supply one original and seven copies of Mill certificates for all pipe supplied under  this  specification.    Such  certificates shall include all the requirements of API Spec 5L. 

 a) Material vendor and producer 

b) All  elements  of  the  alloy's chemical/metallurgical composition 

c) The  method  of  analysis  used  to determine composition 

d) Material specification e) Test  results,  as  specifically  required 

elsewhere in this specification f) Heat numbers 

 NOTE:  Pipe  may  be  furnished  without 

Impacts  on MTR's.    Impacts may be provided by independent third party testing laboratory approved by COMPANY. 

 4.3  RECORDS 

VENDOR  shall  keep  up‐to‐date  records adequate  to  confirm  the work,  including  all required tests,  inspections, certifications and reviews,  has  been  carried  out  according  to this  specification.    These  records  shall  be indexed and legibly recorded in enough detail that they can be accessed and understood by a  qualified,  independent  third  party.    In absence of other  instructions, VENDOR  shall keep these records available to COMPANY for inspection  or  photocopying  for  a  period  of five years.  The records should include:  

 a) A  description  of  each  test,  or 

inspection,  including  a  reference  to paragraph  number  of  the requirement herein, and its results, 

b) The date of the test or inspection, c) The  name  and  qualifications  or 

authority of the inspector or reviewer and his employer, 

d) Evidence of calibrations, e) Vendor  shall  record  pertinent 

information  about  non‐conformities or test failures, including: • Material  condition  that  caused 

rejection • Method of detection • Number of items involved, if more 

than one • Proposed and actual disposition 

Page 5: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     5 of 17 

4.4  INTERACTIONS  BETWEEN  VENDOR  AND COMPANY VENDOR  shall allow COMPANY access  to his facilities  and  processes  for  the  purposes  of monitoring,  surveillance  and  inspection, including but not limited to:  a) Review  of  adequacy  of  facilities  and 

equipment, b) Performing or witnessing  inspections 

test  and  analyses  COMPANY  deems necessary to confirm compliance with requirements. 

 Manufacturer  shall give COMPANY notice of all tests and inspections required herein.  The number of days notice  shall be according  to the requirements of the CONTRACT. 

 

5.  GENERAL SPECIFICATIONS 

5.1  GENERAL Pipe supplied under this specification shall be manufactured  to  the  requirements  of  API Spec  5L  and  shall  carry  the  API  stamp, certifying that it has been made according to the requirements of API Spec 5L. 

 5.2  PROCESS OF MANUFACTURE AND TYPE 

The welding process used in the manufacture of  the  pipe  shall  be  electric  welding  or welding as described  in Section 2.1.b.1.(b) or 2.1.b.2.(a) of API Spec 5L. 

 The  type of pipe  shall be Seamless, Electric‐Welded  Pipe  (ERW)  or  as  described  in Paragraphs 2.1.c.1, 2.1.c.3 and 2.1.c.4 of API Spec 5L.

Page 6: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     6 of 17 

5.3  PIPE GRADE AND CHEMICAL COMPOSITION The pipe grade shall be X‐60.  The carbon equivalent, C.E., determined by product check analysis, shall not exceed 0.4, derived using the following formula: 

 C.E. = C + Mn/6 + (Cr + Mo + V)/5 + (Cu + Ni)/15 

 5.4  PIPE WEIGHT 

The pipe weight per foot of the total order shall be within ±3% of the nominal pipe weight.  Based on the nominal thickness. 

 5.5  CHEMICAL COMPOSITION 

Elements of the steel composition shall not exceed the following combinations of constituents:  

Nb+V+Ti                      0.035%  5.6  TENSILE PROPERTIES 

Tensile properties of the pipe shall not exceed the following maximum values, as established by testing:  

Maximum Longitudinal Yield Strength ...................................................SMYS plus 10 KSI Maximum Longitudinal Yield to Tensile Ratio........................................0.90 Maximum Transverse Yield Strength......................................................SMYS plus 10 KSI Maximum Transverse Yield to Tensile Ratio ..........................................0.90 

 

6.  TESTING 

6.1  GENERAL Mill certificates shall include results of all tests required by API Spec 5L. 

 6.2  FRACTURE TOUGHNESS TEST 

Vendor shall furnish test certificates showing that Charpy impact tests have been successfully carried out according to the supplementary requirement of Section SR5 of API Spec 5L and the following.   The tests shall be performed at a temperature of 32 degrees F (0 degrees C) after the pipe is in its final heat treated condition.   Only  longitudinal  direction  tests  shall  be  performed.    Impact  tests  shall  be  done  on  three specimens each  from the base metal, the weld seam and the heat affected zone, as determined by the position of the notch.  The notch shall be perpendicular to the pipe surface in all specimens.  The following minimum requirements for absorbed energy shall be met.  Subsize samples when required per ASTM. 

 TEST LOCATION  ENERGY IN FT‐LB 

  Average of 3 Specimens 

Any One Specimen 

Base Metal  35  30 Weld Metal  35  30 

Heat Affected Zone  35  30  

Page 7: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     7 of 17 

6.2.1  Percent Shear One  set  of  three  Charpy  V‐notch  impact specimens  shall  be  removed  from  each  of two pipes per heat and  shall be  tested at 0 degrees Fahrenheit.   The specimens shall be oriented transverse to the length of the pipe.  They  shall  be  full  size  or  as  large  a  size  as possible  and  they  shall  be  notched  through the  thickness.    The  specimens  and  testing procedure shall be  in accordance with ASTM E‐23.    The  minimum  average  energy absorbed per set of three specimens shall be 35 ft‐lbs.  No specimen shall exhibit less than 60%  percent  shear  area  on  its  fracture surfaces.  Should  any  test  fail,  the  retest procedure  shall  be  the  same  as  that described  in  Supplementary  Requirement SR5 of API Spec 5L. 

 6.3  HYDROSTATIC TESTS 6.3.1  Each  length  of  pipe manufactured  shall  be 

hydrostatically tested to a minimum pressure equal  to  90  percent  of  the  Specified Minimum  Yield  Strength  (SMYS) of  the pipe for  a minimum duration of  10  seconds.   All other requirements of API Spec 5L regarding hydrostatic  testing  of  steel  line  pipe  shall apply.  All hydrostatic tests shall be recorded with  a  calibrated  chart  recorder.   Under  no circumstances shall distorted pipe be shipped to the COMPANY. 

 6.3.2  At  the beginning of production  and  at  least 

once during  the production of  this pipe,  the Vendor shall remove the hydrostatic pressure gauge  and  verify  calibration  using  a deadweight  tester  or  a  calibrated  master gauge.   Pressure  gauges used  in hydrostatic testing  shall preferably have dials graduated over  a  range  of  about  double  the  intended maximum  test pressure but  in no  case  shall the range be less than one and one‐half (1.5) nor than three (3.0) times that pressure. 

   

7.  DIMENSIONAL AND ACCEPTABILITY STANDARDS 

7.1  Outside diameter of  the pipe shall meet  the minimum  tolerances  specified  in  Section  6, Paragraph 6.2 and Table 6.3, of API Spec 5L. 

 7.2  The wall  thickness  at  any  location  on  each 

pipe  shall  meet  the  minimum  tolerances specified  in  Section 6, Paragraph 6.3, of API Spec 5L.  Wall thickness tolerances of +10% / ‐10%  shall  be  satisfied  in  lieu  of  the  values shown  in  Table  6.3  of  API  Spec  5L.    The remaining wall  thickness  in grind areas  shall be a minimum of 90 percent of the nominal wall  thickness.    The  wall  thickness  at  both ends  of  each  pipe  shall  be  measured  for conformance  to  this  requirement.    As  an alternate,  Vendor  should  also  supply  cost impact to reduce wall thickness tolerance to ±5%. 

 If the wall thickness at any point  is  less than 90% (95%  if ±5%  is selected) of the specified pipe wall thickness, it is classified as a defect.  The  above  wall  thickness  requirement  is applicable  to  the  remaining  wall  thickness caused  by  either  linear  or  non‐linear imperfections. 

 A  compression wave ultrasonic unit  shall be readily available to mill  inspection personnel in  order  to  determine  the  remaining  wall thickness of defect areas. 

 7.3  Each  length  of  pipe  shall  be  weighed 

separately,  and  carload weights  determined in accordance with Section 6, Paragraph 6.4, of  API  Spec  5L.    The  results  shall meet  the minimum  tolerance  set  forth  in Table 6.3 of API Spec 5L. 

 The  total  weight  of  each  carload  shall  be within  +5%  in  addition  to  API  5L  limit  of  ‐1.75%  of  the  weight  calculated  based  on nominal pipe wall thickness. 

 

Page 8: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     8 of 17 

Each length (or joint) of pipe shall be weighed to  an  accuracy  of  ±0.5%.    The  weighing equipment shall be calibrated at  intervals  to be  agreed  between  Manufacturer  and Purchaser.    As  a  minimum,  weighing equipment  shall  be  calibrated  at  the beginning and completion of each shift. 

 The  length  of  each  pipe  joint  shall  be measured to an accuracy of 0.1 foot. 

 Manufacturer  shall  provide  a  tally  of  pipe joints  with  joint  number,  measured  joint length and measured joint weight in a spread sheet  in hard copy and computer diskette  in Lotus or Exel. 

 7.4  Pipe  shall  be  furnished  in  double  random 

lengths with an average length of 40 feet.  No lengths shall exceed 43 feet or be less than 37 feet.  The use of short‐spliced joints shall not be permitted.   As an alternate, Vendor shall provide quote to furnish pipe with the length tolerance  reduced  such  that  no  length exceeds 41 feet and no length is less than 39 feet. 

 7.5  Deviation  from a straight  line  in any portion 

of a pipe  joint shall not exceed 0.15 percent of the length of that pipe joint. 

 7.6  Pipe ends shall be beveled in accordance with 

Section 7.3 of API Spec 5L and shall be square within  1/16‐inch,  measured  not  less  than three times per working shift.  If a pipe fails to meet  the  requirements  of  the  end squareness test the testing shall be increased to hourly.  The frequency may revert back to original  when  four  (4)  consecutive satisfactory measurements are made.  Special attention  shall  be  given  to  ensure  that  the deviation  from  the  required  root  face  of 1/16‐inch  at  the  beveled  ends  is  kept  to  a minimum  within  the  specified  tolerance  of plus or minus 1/32‐inch.    If  the  root  face  is less  than  1/32‐inch,  it  shall  not  be  brought into tolerance by filing or grinding; the entire 

bevel  shall  be  remachined.    After  beveling, protectors  shall be provided and must be  in place during any subsequent pipe movement. 

 

8.  WORKMANSHIP 

8.1  GENERAL The  pipe  shall meet  all  of  API  Spec  5L  for workmanship, visual  inspection and repair of defects.    Any  imperfections  having  a  depth greater  than  10%  of  the  specified  nominal wall thickness, measured from the surface of the  pipe,  shall  be  considered  a  defect  and unacceptable. 

8.1.1  COMPANY may wish to be represented at the mill by an agent who will be  responsible  for overseeing  the  inspection  of  the  pipe  and determining  the  general  quality.    In  such instances,  inspection notices shall be sent to COMPANY  and  its  agent  giving  the  time  at which production will begin at  least 10 days prior to production. 

 8.1.2  If  the  rejection  rate  during  production 

exceeds  5  percent,  COMPANY  shall  be entitled  to  refuse  acceptance  of  production until the cause thereof is rectified. 

 8.1.3  Repair welding to the parent metal shall not 

be permitted.  8.1.4  Dents  shall  not  be  removed  mechanically.  

Dents  of  1/16‐inch  or  more  in  depth  that contain gouges, grooves or scratches shall be removed by cutting out a piece of pipe in the form of a cylinder. 

 8.1.5  The pipe surface shall be free from all surface 

laminations, seams or laps.  8.1.6  Defect  removal  shall  be  by  grinding.    All 

grinding  or  filing  marks  made  on  the  pipe shall be properly blended out. 

 8.1.7  All  hammering  of  pipe  and  dropping  onto 

steel rails is prohibited.  

Page 9: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     9 of 17 

8.1.8  Overhead cranes must use nylon slings.  8.1.9  The  final  inspection  shall  include  a  visual 

examination of each pipe as follows:  

A. An  inspector shall walk  the  length of the pipe as required to examine 100% of  the outside surface.   Pipe shall be 1/4 turned. 

B. While  viewing  the  ID  from each end of  each  pipe  with  the  appropriate white light, the inspector shall visually examine 100% of the inside surface. 

C. An  inspector  shall examine each end of  each  pipe  and  perform  all dimensional measurements  required by  the  API  specification  and  this specification. 

D. All pipe shall be ring gauged and wall thickness checked. 

E. Pipe submitted  to  the  inspector shall be dry and clean. 

 8.1.10  COMPANY, at  its election, may  inspect with 

its own forces or use an inspection service to inspect any or all phases of the manufacture of  the  pipe  and  the materials  used  in  the manufacture  of  the  pipe  covered  by  these specifications.    Inspectors  representing COMPANY shall have  free entry at all times to  all  parts  of  the  Vendor's  Works  that concern  the  manufacture  of  the  pipe, covered  by  these  specifications.    The inspector  representing  COMPANY  shall  be given 5 days advance notice of  the  time at which the manufacture of said material is to be  performed.    The  inspector  representing COMPANY  shall  observe  Vendor's  existing safety requirements. 

 8.2  SHIPPING 

Shipping and Handling shall be in accordance with COMPANY specification SP‐051. 

 

9.  COATING 

Pipe shall be shipped bare with no external or internal oils or varnishes applied (except over external paint stencils) and shall be free from loose  mill  scale,  dirt,  oil,  grease  or  other extraneous material, both inside and outside, that might be detrimental to the satisfactory nondestructive  inspection of  the material at the  COMPANY's  inspection  facility  or application  of  an  internal  or  external coating/insulation  in a coating yard or  in the field.  If pipe is discovered in the inspection or coating  yard  facilities  to  have mill  scale  or other extraneous substances of mill origin on the  internal  or  external  surface  which requires abrasive blasting beyond that which is  normally  performed  in  order  to satisfactorily prepare  the pipe  for  inspection or coating,  the cost of said cleaning shall be borne  by  the Vendor.    The Vendor  shall  be notified  sufficiently  in  advance  of  any additional  cleaning  in  order  to  permit inspection of the pipe. 

 

10.  MARKING 

10.1  No  die  stenciling  (hot  or  cold)  shall  be permitted.    All  information  required  by  API Spec  5L  shall  be  paint‐stenciled  on  the surface of the pipe.   The OD stencils shall be protected with a  coat of  clear  lacquer.   The markings shall be  include, but not  limited to, the following information: 

 Outside Diameter ‐ Process of Manufacturer Wall Thickness ‐ Company purchase order Number Weight per Foot ‐ Grade of Pipe Test Pressure ‐ Heat Number and Treatment Length of Pipe ‐ SR4 API Monogram ‐ SR5A‐SRB (Ft.‐Lbs.)‐0ºF Weight of Pipe ‐ When Performed 

 10.2  If  additional  information  is  required  to  be 

paint‐stenciled on the surface of the pipe, this information  will  be  summarized  on  the purchase order or Contract. 

Page 10: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     10 of 17 

 10.3  Daily  and  summary  tally  sheets  shall  be 

maintained  showing  heat  number,  joint number, pipe  joint weight per foot of  length and  length  of  each  joint.    Summary  tally sheets shall list joint numbers consecutively. 

 10.4  Pipe joint numbers for each diameter of pipe 

shall be consecutive.  

11.  HANDLING, STORING AND SHIPPING 

11.1  Vendor shall handle and properly care for all materials  and  pipe  during  all  phases  of manufacturing  in  such  a  manner  as  to minimize mechanical damage and corrosion. 

 11.2  All handling shall be done with slings, padded 

hooks  or  unpadded  hooks  approved  by COMPANY.  In no case shall brass lined hooks be used. 

  11.3  Prior  to  loading,  all  rail  cars,  trucks,  barges, 

ships or other  conveyances  shall be cleaned of debris or any substance that might damage the pipe. 

 11.4  Suitable  timber  and  other  dunnage  shall  be 

used  to  protect  the pipe  against damage  in transit. 

 11.5  Loading onto or  into rail cars, trucks, barges, 

ships or other conveyances  shall be done  in accordance with API RP 5L1 and API RP 5LW, where  applicable,  and  in  all  cases  in accordance  with  a  procedure  approved  by COMPANY. 

 11.6  Finished  pipe  to  be  stored  for  a  significant 

period of time at the mill shall be stored in a manner to prevent corrosion. 

 11.7  Vendor  shall  provide  and  install  bevel 

protectors  and  end  closures  of  a  type approved by COMPANY. 

 

11.8  Vendor  shall  be  responsible  for  repairs  to pipe  sections  damaged  during  shipment  to the  point  of  delivery  specified  on  the purchase order or Contract. 

  

12.  CERTIFICATION, TRACEABILITY, AND DOCUMENTATION 

12.1  Pipe  shall be certified and  traceable per API specification  5L‐SR15.    In  addition  to  the requirements  of  SR15,  the  pipe  shall  be traceable  to  steel making  (heat). Along with the  requirements  outlined  in  SR15  the certificate  shall  also  include:    COMPANY purchase order Number, mill order number, quantity  produced,  and  a  statement  of compliance with this specification. 

 12.2  Vendor shall provide documentation of use of 

API monogram. 12.3  Document yield  to tensile ratio maximum of 

90. 12.4  Document longitudinal and transverse tensile tests and Charpy tests. 12.5  Calibration tests for equipment per NIST. 12.6  Document  maximum  20  gauss  residual 

magnetism. 12.7  Vendor shall submit a confirmed schedule for 

the  manufacture  of  pipes  along  with  the Vendor's  Bid.    Such  schedule  shall  contain dates  for material procurement,  fabrication, inspection,  testing,  and  shipping.    Vendor's manufacturing  schedule  shall  be  firm  for  a period of 45 days after submittal of Vendor's Bid. 

12.8  Vendor  shall  submit  six  copies  each  of  the following  documents  to  COMPANY  as  set forth below. 

 Document ‐ Schedule Submittal 

 a. Steel Making Procedure(s) ‐ With Bid 

b. Pipe Making Procedure(s) ‐ With Bid 

c. Inspection  and  Testing  Procedures  ‐ 

With Bid 

Page 11: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     11 of 17 

d. Quality Control Procedures ‐ With Bid 

e. Proposed  Steel  Composition  ‐  With 

Bid 

f. Ladle Analysis (for each heat of steel)  * 

g. Product Check Analysis  (for each heat of steel) ‐ * 

h. Results of Manufacturing  Procedure Qualification ‐ * 

i. Certified Examination Reports  * 

13.2  By the acceptance of the purchase order for the manufacture  of  pipe  covered  by  these specifications,  the  Vendor  guarantees  and warrants that the pipe will be manufactured in  accordance  with  the  aforesaid  API specifications  with  such  additional requirements  as  are  contained  in  these specifications. 

j. Certified Physical Test Reports 

k. Storage Procedures ‐ With Bid 

∗ When available during manufacturing  

13.  WARRANTY 

13.1  It  is  agreed  that  COMPANY  may hydrostatically test all or portions of the  line to be constructed with the pipe furnished on this order to a construction test pressure not exceeding  100  percent  of  the  specified minimum  yield  strength  based  on  nominal pipe  dimensions.    At  COMPANY  election, injurious  mill  defects  other  then  those resulting in failure under the line test, may be repaired  as  set  out  in  the  appropriate  API specification at Vendor's expense.   Any pipe that  fails  under  line  test  as  a  result  of laminations  or  other  mill  defects  shall  be replaced  by  the  Vendor  with  the  provision that  construction  and  testing  practices  are followed as set  forth  in Title 49, Part 192 of the  Code  of  Federal  Regulations  and  latest revisions thereto.   Total direct on‐set cost of such  replacement,  including cost  for  finding, cutting out and replacing the defective pipe, shall be borne by the Vendor.   The Vendor's undertaking herein shall not be construed as an agreement to hold the Purchaser harmless against costs and expenses  incurred by  it as the result of damage to the pipe in transit or from  damage  sustained  in  its  installation.  COMPANY may elect  to  raise and  lower  the field  test pressure one or more  times either 

as part of  a planned  testing  routine or  as  a consequence of a failure in the pipeline or in the  testing  equipment.    However,  these pressure  fluctuations  shall  in no way  relieve the manufacturers of their obligations herein. 

 

Page 12: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     1 of 17 

APPENDIX A SUMMARY OF TEST REQUIREMENTS 

 Table 1 ‐ Test Performed by Manufacturer (Mill Certificates) 

Full Length Test  Base Material Tests  Weld Tests 

Hydrostatic Test* 

Visual & Dimensional 

N.D.T.  Product Check Analysis 

Tensile Tests 

Charpy V‐Notch 

Ductility Tests 

Flattening Tests 

Macro Section & Grain Size 

Knoop Hardness 

API 5L  API‐5L  API‐5L  API‐5L  API‐5L 

API‐5L  API‐5L  API‐5L  API‐5L  API‐5L 

 *  Hydrostatic Test ‐ The end caps for hydrostatic testing will cover 4  inches of each end when testing  instead of full  length hydrostatic test. 

 Table 2 ‐ Frequency of Tests Performed by Vendor/Inspector  

Fracture Toughness Test* 

 

Visual & Dimensional Inspection 

Non‐Destructive Tests 

Two specimens from each heat 

Visual, all pipes  Measure dia., wall, 10%, dents, avg. weight tolerance 

Ultrasonic ‐ all pipes 

[API SPEC 5L]; {Sec. 6.2}  [API 5L Sec. 10.0]; {7.0; 5.4} 

[API SPEC 5L Sec. 9.0]  

 Notes:  *  Testing requirements beyond API is required when pipe is furnished off the shelf by third party 

 Specimen = 3 in Base Metal; 3 in Weld; 3 in HAZ 

 

Page 13: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     1 of 17 

APPENDIX B VENDOR DATA REQUIREMENTS LIST (VDRL) 

  CLIENT:   ___________________________________   P.O./S.C. NO.: _______________________  LOCATION:   _________________  SELLER/SUBCONTRACTOR: ____________________________  EQUIPMENT TAG NO.(S): __________________________________________________________  DESCRIPTION(S):  API 5L X‐60 SEAMLESS or ERW Line Pipe________________________________  The seller's/subcontractor's quotation shall state his intended compliance with this listing, as regards to the type of data required and schedule for data submittal, as well as the quantity and data form (reproducible, prints, etc.) indicated in the inquiry and purchase order/subcontract standard clauses.  The seller/subcontractor shall confirm responsibility for similar compliance by his subvendors and/or subcontractors.  As  a part of  the  seller's/subcontractor's quotation,  any deviation(s)  from  the data  submittal  schedule  shall be shown in the comments column.  All data submitted shall be  identified with equipment tag number, equipment description, buyer's  job number, and purchase order/subcontract number.  AFTER ORDER IS PLACED, UNLESS OTHERWISE NOTED IN THE COMMENTS COLUMN, the following data submittal schedule shall apply:  

FOR  APPROVAL  DATA  DUE    3    WEEKS  AFTER  PURCHASE  ORDER/SUBCONTRACT  IS  PLACED, 

CERTIFIED  CORRECT DATA DUE      4   WEEKS AFTER  BUYER'S APPROVAL, RECORD DATA DUE    8  

WEEKS AFTER PURCHASE ORDER/SUBCONTRACT IS PLACED. 

ABBREVIATIONS:  Q = With Quotation, A = Approval, C = Certified, R = Record, P = Prints, RP = Reproducible, M = Microfilm, S = Shotdown 

Page 14: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     2 of 17 

VENDOR DATA REQUIREMENTS LIST (VDRL)   Data      Data Required Code  Data Description/Definition  Q  A    C  R  Comments  

Vendor Data Schedule  3P        6P 

QA/QC Plan  3P  6P    6P 

Dimensional Check Procedures    6P    6P 

Internal Pressure Test Certificate, Records and Report        6P 

Heat Treatment Records Date/Time/Check Off Chart        6P 

Magnetic Particle Test Records Reports        6P 

Ultrasonic Test Records Report        6P 

Mill Test Certificate        6P 

Tensile Strength Test Records        6P 

Hardness Test Results        6P 

Charpy V‐Notch Test Results        6P 

Chemical Composition    6P    6P 

Specified Minimum Yield Strength    6P    6P 

Dimensional Check Results Wall Monitor + Final Inspection Report        6P 

 

Page 15: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     1 of 17 

 APPENDIX C 

INSPECTION MATRIX  

 APPROVAL/DATE:  INSPECTION LEVEL:  A 

 INSPECTION LEVEL:  

 SPECIFICATIONS/CODES/STANDARDS:  See Section 3 of this specification.  Other Sections/Paragraphs listed below are references to information with this specification. 

 A = Pre‐Fab Meeting, Regular In‐Process Insp. 

Witness Tests, Final Insp., Doc. Review   B = One or More In‐Process Insp., Witness 

Tests, Final Inspection, Doc. Review   C = Witness Tests, Final Insp., Doc. Review   D = No Inspection, Review Vendor Submitted 

Documentation (if applicable)  INSPECTION ACTIONS:  1 = Observe/Verify by Inspection 2 = Review of Documentation 3 = Obtain Certification/Test Documents               

 

Page 16: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     2 of 17 

  

INSPECTION MATRIX  

  ACTIVITIES  1  2  3  COMMENTS 

1  QA/QC Inspection Plan    X     

2  NDE Procedures    X    Ref. API‐5L  

3  Mill Certificates/Test Reports    X  X  Ref. API‐5L 

4  Certified Material Test Certificates    X  X  Ref. API‐5L 

5  Certified Examination/Test Reports    X  X  Ref.  

6  Contractors Inspection Reports    X  X  Ref.  

7  Pipe Type/Grade    X     

8  Pipe Size/Diameter/Wall Thickness  V      Sec.  Data Sheet 

9  Pipe End Verification  V      Ref. Sec.  

10  Pipe Length  V      Ref. Sec.  

11  Pipe Weight    X    Ref. Sec.  Data Sheet 

12  Yield and Tensile Strength Tests    X  X  Ref. Sec.  

13  Hardness Tests    X  X  Ref. Sec.  

14  Charpy V‐Notch Tests    X  X  Ref. Sec.  

15  Non‐Destructive Examinations  W  X  X  Ref. Sec. 

16  Pressure Tests    X  X  Ref. Sec 

17  Marking and Coatings  V      Ref. Sec 

18  Preparation for Shipment  W  X    Ref. Sec 

19  Release for Shipment  W  X  X  QA representative Release 

LEGEND:  X = Required, O = Observe, V = Verify, W = Witness (Hold Point)  

Page 17: Specification for Heating Pipe - ENGINEERING EXPERTSengineering-experts.com/specs/.../Specification_for_Heating_Pipe.pdf · This specification sets out requirements for ERW, or SEAMLESS

Specification for Heating Pipe     1 of 17 

APPENDIX D LINE PIPE DATA SHEET 

  

Nominal Outside Diameter (Inch)  4.5 

Nominal Wall Thickness (Inch)  Per purchase order 

Nominal Weight (lbs/ft)  ‐ 

Material Grade (API 5L)  X‐60 

Process of Pipe Manufacture  ERW/SEAMLESS 

Marking Designations  C001 Onward 

Type of Use  Heating Line Pipe 

Quantity (Feet)  Per purchase order