Specification for Fabrication of Pipeline End Manifold 1 of 23 Specification for Fabrication of Pipeline End Manifold

Transcript of Specification for Fabrication of Pipeline End...

Page 1: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

Specification for Fabrication of Pipeline End Manifold  1 of 23 

Specification for Fabrication of Pipeline End Manifold  

Page 2: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

Table of Contents 

 1.0  SCOPE ..................................................................................................................................... 3 2.0  DEFINITIONS ........................................................................................................................... 3 3.0  REFERENCE DOCUMENTS........................................................................................................ 3 4.0  CONTRACTOR RESPONSIBILITIES............................................................................................. 5 5.0  GENERAL SPECIFICATIONS ...................................................................................................... 7 6.0  PRESSURE TESTING ............................................................................................................... 17 7.0  PLEM ACCEPTANCE TESTING................................................................................................. 17 8.0  TRANSPORTATION................................................................................................................ 18 9.0  DOCUMENTS ON COMPLETION OF FABRICATION ................................................................. 18 

 

 

Specification for Fabrication of Pipeline End Manifold  2 of 23 

Page 3: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

1.0  SCOPE 

This  specification  describes  the  minimum requirements for the fabrication of the pipeline end  manifold  (PLEM)  other  structural  steel assemblies  required  for  Boomvang  Nansen Project  located  in  the Gulf  of Mexico  in water depths of 3500 ft.  This  specification  describes  the  materials, fabrication,  testing  and  inspection  for  the pipeline end manifold (PLEM).  The  work  includes  the  furnishing  of  all  labor, materials,  tools  and  equipment  and  the performance  of  all  operations  and  incidentals necessary for the fabrication, assembly, testing, inspection  and  repair  of  these  items.    Further, the work shall meet any additional requirements stated in the CONTRACT. 

2.0  DEFINITIONS 

For  the  purpose  of  this  specification,  the following definitions shall apply:  COMPANY:   CONTRACTOR: The  company  with  whom  the COMPANY enters into a CONTRACT to which this specification applies. CONTRACT:  The  entire  written  agreement 

between  COMPANY  and CONTRACTOR  for  the  work  of this specification. 

STANDARDS:  Industry  codes,  standards,  and recommended  practices referenced herein. 

WORKS:  The  location(s)  at  which manufacturing,  inspection  and testing are performed. 

Manufacturer: The  person,  firm  or  company who  supplies  the  CONTRACTOR with materials for the work. 

 2.1  Contractor Representative  CONTRACTOR  shall  designate  in  writing  to COMPANY an authorized representative to serve as liaison with COMPANY on matters associated with  this  Specification  and  on  the  Purchase Order or Contract referencing this Specification.  This  representative shall be designated prior  to the performance of services associated with this Specification  and  the  Purchase  Order  or Contract referencing this Specification.  2.2  Document Precedence   In the event of conflict between documents, the priority shall be as follows:  

a) Purchase Order or Contract b) This Specification c) Referenced Standards 

 However,  conflicts  shall  be  reviewed  and resolved with COMPANY's Representative prior to initiation or continuation of the services to be performed  in  association  with  the  Purchase Order or Contract. 

3.0  REFERENCE DOCUMENTS 

3.1  General  This specification  is based on  the  latest version of  the  appropriate  sections  of  the  following codes, regulations, specifications, standards and guidelines.  This specification shall prevail where there are differences between this specification and  references.    CONTRACTOR may  use  other 

Specification for Fabrication of Pipeline End Manifold  3 of 23 

Page 4: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

standards  that  are  suitable  for  the  work  with prior approval by COMPANY.  3.2  Codes and Standards   The PLEM shall be fabricated, assembled, tested and transported according to the latest editions and  addenda  of  the  following  codes  and standards.  ANSI  B16.5  Pipe Flanges and Flanged Fittings 

 ANSI  B16.9  Factory  ‐  Made  Wrought  Steel 

Buttwelding Fittings  

ANSI  B16.11  Forged  Steel  Fittings,  Socket  ‐ Welding and Threaded 

 API  API 1104  Standard  for  Welding 

Pipelines and Related Facilities  API  API RP2X  Ultrasonic Examination of 

Offshore  Structures  and Qualification  of  Ultrasonic Technicians. 

 ASTM A20  Standard  Specification  for 

General  Requirements  for  Steel Plates for Pressure Vessels 

 ASTM A36  Specifications for Structural Steel  ASTM A106  Specification  for  Seamless 

Carbon  Steel  Pipe  for  High‐Temperature Service 

 ASTM A307  Specification  for  Carbon  Steel 

Externally  Threaded  Standard Fasteners 

 ASTM A435  Method  and  Specification  for 

Straight‐Beam  Ultrasonic Examination  of  Steel  Plate  for Pressure Vessels 

 ASTM D2240  Test  Method  for  Rubber 

Property‐Durometer Hardness  ASTM E 23  Notched  Bar  Impact  Testing  of 

Metallic Materials  ASME SEC 9  Welding  ASTM E 140  Hardness  Conversion  Tables 

Vickers vs. Brinell vs. Rockwell  ASTM E 165  Recommended  Practice  for 

Liquid Penetrant Inspection  ASTM E 709  Magnetic Particle Examination  AWS  AWS D1.1  Structural Welding Code   ASNT  SNT‐TC‐1A  Recommended  Practice 

for Nondestructive Testing  NAS  1638  Standard  for  Cleanliness  of 

Hydraulic Systems  SSPC  SSPC‐SP‐5  White  Metal  Blast 

Cleaning  3.3  Company Specifications     Seamless Line Pipe   Ball Valves   Subsea Check Valves   Standoff Anodes 

Specification for Fabrication of Pipeline End Manifold  4 of 23 

Page 5: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

  Pipe Fittings   Pipe Flanges   DSAW Pipe   Welding and NDE Inspection   Diverless Connection System   Pipe Bends   Pipe Handling and Storage 

4.0  CONTRACTOR RESPONSIBILITIES 

Forty‐five (45) days before the scheduled start of fabrication,  the  CONTRACTOR  shall  submit  a work  plan,  including  as  a  minimum  the documentation  listed  below,  to  the  COMPANY for approval:  • Fabrication drawings; • Work schedule; • Welding Procedure Specifications (WPS) and 

Supporting Procedure Qualification Records (WPQ); 

• Weld repair procedures.  Fabrication procedures including procedures for pipe  cleaning,  alignment  of  pipe  joints  and elbows,  cutting  and preparation of  saddle  cuts on tubular members, fit‐up, details of temporary supports, etc.  • Cleaning,  surface  preparation  and  coating 

procedures; • Pressure test procedures; • Acceptance testing procedures; • Handling, transport and storage procedures.  The  CONTRACTOR  shall  provide  all  labor, materials and equipment and shall undertake all fabrication,  testing,  inspection,  NDE,  handling, reporting, documenting required to perform the work according  to  this  specification,  references and  drawings.    Conflicts  in  these  documents 

shall  be  brought  to  the  attention  of  the COMPANY for resolution prior to starting work.  CONTRACTOR may select alternative fabrication methods  or  use  non‐specified  materials,  only with advance COMPANY review and approval.  CONTRACTOR  shall  be  responsible  for  the actions  and  performance  of  subcontractors, including  those  hired  for  handling  and transportation.  The  COMPANY  shall  provide  materials  and services  listed  in  the  Appendices  of  this specification.    All  other  material  shall  be provided by the CONTRACTOR.  The CONTRACTOR  shall  check  the drawings  for accuracy,  completeness  and  for  fabrication suitability.    Any  additional  drawings  required shall be produced by  the CONTRACTOR as part of this contract.  CONTRACTOR shall provide reasonable  facilities which  includes  sufficient  office  space,  files, furniture,  office  supplies,  telephones,  fax machine,  secretarial  services,  janitorial  services and  vehicle  parking  for  inspection  staff  use during  the  assembly  of  material,  fabrication, inspection  and  testing  of  the  units  of  this specification.  4.1  Quality Assurance   All  of  the  work  of  fabrication  and  services according  to  this  specification  shall  be performed  under  the  control  of  a  quality assurance control program.  Forty‐five  (45)  days  before  starting  fabrication, CONTRACTOR  shall  provide  COMPANY  with  a quality  assurance  program  for  review  and approval.   COMPANY and CONTRACTOR are  to 

Specification for Fabrication of Pipeline End Manifold  5 of 23 

Page 6: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

reach  agreement  on  amendments  and adjustments  before  starting  the  fabrication work. The  quality  and  integrity  of  the Work  shall  be related  to  the  best  offshore  oil  industry  and marine  practices  for  gas  transmission  pipeline systems, the inaccessible location in deep water, the  permanent  nature  of  the  facilities  and  the risks to the marine environment.  This specification and  the  referenced standards are  intended  to  achieve  a  high  fabrication quality without imposing unnecessary difficulties on  the  CONTRACTOR.  The  CONTRACTOR  shall have  an  effective  quality  control  system acceptable to the COMPANY.  CONTRACTOR shall provide the specified quality without  regard  to  COMPANY  presence  or absence.  The  COMPANY  shall  have  access  to  the CONTRACTOR's  facilities,  plant,  factory  or fabrication  site,  and  similarly,  the Subcontractor's  facilities at any time during the work  period  of  this  Contract,  for  inspection purposes of work in progress or finished work.  COMPANY has the right to accept or reject work that  does  not  satisfy  the  requirements  of  this specification and its referenced documents.  Rejected work  shall be  repaired or  replaced  to COMPANY's  satisfaction  without  extension  of delivery date or additional  cost.   Such  rejected work  that  is  repaired  or  replaced  shall  be  at CONTRACTOR's expense.  COMPANY  shall  advise  CONTRACTOR  of  the Project  Chief  Inspector.    CONTRACTOR  shall designate  their  supervisor  for  liaison  and coordination with the Chief Inspector.  

COMPANY  Inspection Staff may use any of  the visual,  mechanical,  destructive  and  non‐destructive  tests  available  for  quality  control purposes.  4.2  Deviations and Disclaimers   Work  done  under  this  specification  shall  be according  to  all  requirements  herein,  without deviations or disclaimers.  If COMPANY approves changes, they will be incorporated into a revised specification and this specification will be void.  4.3  Records   CONTRACTOR  shall  keep  up  to  date  records adequate to confirm that the work, including all required  tests,  inspections  and  reviews,  has been  carried  out  to  this  specification.    These records shall be indexed and legibly recorded in enough  detail  that  they  can  be  accessed  and understood  by  a  qualified,  independent  third party.    In  absence  of  other  instructions, CONTRACTOR shall keep these records available to COMPANY for inspection or photocopying for five years.  The records shall include:  • A description of each test or  inspection and 

its results, with a reference to the paragraph number  of  this  specification  or  the manufacturer's work plan  that required  the test; 

• The date of the test or inspection; • The name and qualifications or authority of 

the inspector or reviewer and his employer; • Evidence of calibrations.  CONTRACTOR shall record pertinent information about  non‐conformities  or  test  failures, including:  

Specification for Fabrication of Pipeline End Manifold  6 of 23 

Page 7: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

• Material or condition that caused rejection; • Method of detection; • Number of items involved, if more than one; • Proposed and actual disposition; Preventive action taken. 

 4.4  Conflicts with Contract   If  CONTRACTOR  believes  this  specification conflicts  with  other  terms  of  the  CONTRACT, CONTRACTOR  shall  inform  COMPANY.    Such conflicts  shall  be  resolved  by  the  terms  and specific requirements of the CONTRACT.  4.5  Deviations to Specification   CONTRACTOR  shall  obtain  COMPANY's written approval  for  any  deviations  from  the requirements  of  this  specification  or specifications,  standards  and  drawings referenced  herein  or  elsewhere  in  the CONTRACT.  4.6  Performance of Work   This document is not intended to be all inclusive, and the use of the requirements set forth does not  relieve  the  CONTRACTOR  of  his responsibility  to  perform  all  services  in  a  safe manner, to meet applicable codes and standards specified  by  the  COMPANY,  to  comply  with government  regulations or  to  supply a product capable of performing its intended service. 

5.0  GENERAL SPECIFICATIONS 

5.1  Materials   5.1.1  General  All  materials  used  in  the  fabrication  of  the PLEMs  shall  be  new  and  conform  to  this 

specification.    Before  starting  fabrication,  the CONTRACTOR  shall  provide  selected  material lists  with  material  information  for  COMPANY review  and  approval.    Material  substitutions require prior COMPANY approval.   All structural and flowline materials used  in the PLEMs  shall  satisfy  the  requirements  of  the applicable  referenced  codes  and  standards  in Section 3.2.  All structural materials shall demonstrate Charpy V‐Notch  impact  energy  at  32º  F  =  35  ft/lb. average with 50% minimum shear.  The  quality  assurance  control  system  shall  be followed.   Mill Test Reports shall accompany all material deliveries  for  review  according  to  this specification.    CONTRACTOR  furnished  steel materials  shall  have  complete mill  test  reports for COMPANY review and approval prior to using any  such material  in  the Work.    Such  reports shall include the following:  • Material vendor and producer; • All elements of alloy's chemical composition; • The method of analysis; • Material specification; • Evidence  of  satisfactory  performance  test 

results, as specifically required elsewhere  in this specification. 

 5.1.2  Pipe  Export Oil and Gas Pipelines  COMPANY  furnished  line pipe  for  the pipelines and  pipe  bends  shall  be  according  to  API Standard 5L X‐60 and COMPANY Specifications.    Structural Tubulars 

Specification for Fabrication of Pipeline End Manifold  7 of 23 

Page 8: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

 Tubular  material  for  the  fabrication  of  the PLEMs  shall  be  ASTM  A106  Grade  B  or  API Standard 5L Grade B.  5.1.3  Valves  All valves used permanently on  the PLEM  shall be  suitable  for  subsea  service  to  a maximum external  pressure  of  3500  feet  of  sea  water.  Sealant ports to be plugged with pipe plugs.   The  following  valves  shall  be  required  for  the PLEMs.  For sea flooding of tubulars:  • Ball Valve 2" dia. Regular Port, ANSI 600 

Class with  removable  handle  and  extra long shaft for ROV; 

• Cameron  C2W  80  06  0  2‐1‐212  ‐  4 required per sled. 

 All valves shall have the surface preparation and coating according to the epoxy coating system in Section 5.10.2 of this specification.  5.1.4  Structural Steel Plates  The  plate  for  fabrication  of  sleeves,  padeyes, stiffeners,  saddles,  brackets  and  other  items shall be mild steel to SA‐516‐70. The  steel  plates  shall  be  tested  according  to Pressure  Vessel  Standard  ASTM  A20,  for  the mechanical properties of this grade of steel.  All steel  plates  shall  be  ultrasonically  tested according  to  Pressure  Vessel  Standard  ASTM A435.  Standard  rolled  structural  steel  shapes  shall be to ASTM A36. 

 5.1.5  Fittings  The  fittings  shall  be  according  to  ANSI  B16.5, B16.9  and  B16.11  as  appropriate.    All  forged fittings shall meet requirements of MSS SP‐75.  5.1.6  Control Tubing and Fittings  The COMPANY supplied control line tubing shall be  super  duplex  (Sandvik  2507  or  equivalent) stainless steel.  Tubing shall meet the "Class 6" standard of NAS 1638  Standard  for  Cleanliness  in  Hydraulic Systems.    Plastic  end  caps  shall  be  installed  in tube  ends  at  the  mill  or  immediately  after cleaning if the tube is cleaned after it leaves the mill.   These caps shall remain  in place until the tubing is delivered.  5.1.7  Steel Wire Rope  Steel wire rope shall be of improved plow steel, 6  x  36  IWRC  construction  according  to  the applicable military specifications.  The wire rope and end fittings shall be galvanized.  5.1.8  Shackles and Wire Rope Fittings  The  shackles  and wire  rope  fittings  shall be  as manufactured by Crosby‐Laughlin or COMPANY approved equal and shall be galvanized.  5.1.9  Pipe Bends  COMPANY will furnish line pipe bends.  5.1.10 Pins  

Specification for Fabrication of Pipeline End Manifold  8 of 23 

Page 9: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

Pins shall be of high carbon steel, heat treated to produce  a minimum  yield  strength  (defined  as 0.2 percent proof  stress) of 87  ksi  and  surface hardness of HB 230 minimum. 

 5.1.11  Screws, Bolts and Nuts  Hexagon  headcounter  sunk  screws,  and hexagonal head screws and bolts shall be made from  teflon  coated,  high  carbon  steel  with  a minimum yield strength 72 ksi or equal.  When assembled, contact surfaces shall be free of  paint,  dirt,  sand,  metal  particles  or  other foreign  materials  that  would  prevent  full  and complete seating contact of the components.  Bolt holes shall be drilled and the burrs shall be removed.   No  flame  cutting of bolt holes.   No bolt holes shall be enlarged by flame cutting.  5.2  Anodes  All  anodes  shall  be  according  to  COMPANY Specification SP‐007.  5.3  Fabrication  5.3.1  General  All  provisions  in  ANSI/AWS  D  1.1,  Structural Welding  Code,  shall  apply,  unless  otherwise stated in this specification.  5.3.2  Vent Holes  All of the vent holes in the sled units shall be at locations  shown  on  drawings.    CONTRACTOR shall maintain a record of  inspecting vent holes prior  to making  welds  that  could  render  vent holes inaccessible.  

5.3.3  Fabrication Tolerances  The dimensions of the fabricated units shall not have a variation more  than 1/16‐inch  from  the lengths shown on the drawings.  The  dimension  variation  of  welded  structural members shall be according to AWS D 1.1.  Tolerances shall not be accumulative.  5.4  Welding Requirements   All  welding  performed  shall meet  the  general requirements of  this section and the applicable sections  for  flowlines,  stainless  tubing  and structural welding.  CONTRACTOR  shall  qualify  the  Welding Procedure Specifications (WPS) required for the fabrication and testing of the bundle sleds.  The welding procedures shall be according to Section 3.0  entitled  "Reference  Documents"  and  this specification.  Pipe Welding:  According  to  COMPANY 

Specification  2136600‐SP‐012 and API‐1104 

Structural Welding:  According  to  Section  5.7 of  this  specification  and  AWS D1.1 

 The material required for the welding procedure tests  shall  be  furnished  by  the  CONTRACTOR except  for  the  flowline pipe and  stainless  steel tubing  that  is  listed  to  be  provided  by COMPANY.    The welding  procedure  tests  shall be performed on material of the same size and grade as will be used in unit fabrication.  5.4.1  Material 

Specification for Fabrication of Pipeline End Manifold  9 of 23 

Page 10: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

 Line Pipe and Pipe Bends   All flowline  line pipe and pipe bends shall meet the requirements of:  • COMPANY Specification 2136600‐SP‐002; • COMPANY Specification 2136600‐SP‐011; • COMPANY Specification 2136600‐SP‐015  Stainless Steel Tubing  Stainless  steel  tubing  shall  be  super  duplex (Sandvik 2507).   The  sizes are 1‐inch, 0.75‐inch and  0.5‐inch.    Tubing  shall  be  flushed  and cleaned to NASG.  Material Verification  On receipt of the COMPANY provided materials, the CONTRACTOR shall  inspect the materials to determine  that  the  quantities  are  correct  and the material  is free from damage.   Any damage or shortages shall be reported to the COMPANY in writing.  Material Substitutions  CONTRACTOR furnished material shall be of the type,  quantity  and  quality  required  in  the Contract.    No  substitutions  shall  be  made without  the  COMPANY's  written  approval.  Where applicable, material certification shall be obtained  and  presented  to  the  COMPANY  for approval prior to use.  5.4.2  Weldability  CONTRACTOR  is  advised  to  select  compatible materials  to be  joined by welding  for achieving full strength welds. 

 Materials with  a  carbon  equivalent more  than 0.42  percent  shall  not  be  used  in  the  Work.  Carbon equivalent of 0.42 percent or less with a single  qualification  is  satisfactory  without requalifying.    Greater  carbon  equivalent materials  shall be evaluated on a  case by  case basis.  The  carbon  equivalent  shall  be  determined  as follows:  Carbon  Equivalent  equals  the  Carbon  percent plus 1/6 Manganese percent + 0.05.  5.4.3  Cleaning and Beveling  Construction materials  and  the  inside  of  each joint of pipe  shall be  adequately  swabbed  and cleaned by a method approved by COMPANY to remove  dirt,  debris  and  other  visible  foreign matter  before  welding.    CONTRACTOR  shall provide  a  cleaning  procedure  for  COMPANY approval.  The beveled ends and adjacent 2‐inches of each joint  of  pipe  shall  be  thoroughly  cleaned  of paint,  rust,  mill  scale,  dirt  or  other  foreign matter.  CONTRACTOR  shall  re‐cut  and bevel pipe  ends according  to  the  approved Welding  Procedure Specification to ensure proper fit‐up.  All  bevel  cuts  shall  be  done  with mechanized equipment.  Where  the methods  of  preparation  are  other than  machining,  the  cut  surface  shall  be prepared  by  grinding  or  machining  to  bright metal.  

Specification for Fabrication of Pipeline End Manifold  10 of 23 

Page 11: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

All  surfaces  and  edges  to  be  welded  shall  be smooth,  uniform  and  free  from  tears,  cracks, gouges  and  other  discontinuities  which  might otherwise  affect  the  quality  or  integrity  of  the weld.  The  joint,  or  preparation,  and  the  surrounding areas  shall  be  clean  and  free  of moisture,  oil, grease, scale, protective coatings, oxides or any other  foreign matter  before  the  application  of pre‐heat or the beginning of welding.  5.4.4  Alignment and Fit‐Up  The CONTRACTOR shall take all necessary steps to ensure  that  joints are adequately  supported and  prevented  from  moving  during  welding.  The  alignment  and  fit‐up  of  joints  shall  be subject  to  inspection  by  the  COMPANY  before welding commences.  All saddle cuts on structural pipe members shall be  done  with  a  mechanized  contour  cutting machine.  CONTRACTOR shall submit alignment and fit‐up procedures prior to production start.  5.4.5  Welding Process  GMAW  (MIG)  welding,  regardless  of  transfer mode, shall not be allowed for PLEM fabrication.  5.4.6  Welding Procedure Specification  CONTRACTOR  shall  submit  complete  Welding Procedure Specifications (WPS) and weld repair procedures for COMPANY approval.  Welding  Procedure  Specifications  shall  include full  details  of welding  processes,  consumables, preheat  and  weld  parameters,  essential  and 

non‐essential  variables  as  specified  by  the applicable code.   Welding  Procedure  Specifications  shall  be submitted to the COMPANY a minimum of forty five  (45)  days  prior  to  the  scheduled  start  of production welding.  5.4.7  Procedure Qualification Records  The  CONTRACTOR  shall  submit  all  Procedure Qualification Records (PQR) to the COMPANY for approval  before  starting  any  production welding.    The  approval  of  welding  procedure qualifications will be based on satisfactory non‐destructive examination and mechanical testing of the test welds according to this specification.  CONTRACTOR  shall  qualify  proposed  Welding Procedures  in  accordance  with  the  applicable construction code as defined  in Section 5.4 and with  the  same  equipment  to  be  used  in fabrication.  All  necessary  welding  equipment  and  welding materials  shall  be  provided  by  the CONTRACTOR.  5.4.8  Procedure Qualification Tests  The test welds shall be 100% radiographed by a COMPANY approved third party NDE contractor.  The welded  joints  shall  be  destructively  tested and  interpreted by a COMPANY approved third party mechanical  testing  laboratory,  according to the applicable code and this specification. 5.4.9  Procedure Approval  COMPANY  approval  of  welding  procedure qualifications will  be  based  on  non‐destructive examination and mechanical  testing of  the  test welds according to this specification.  COMPANY approval  of welding  procedure  qualifications  is 

Specification for Fabrication of Pipeline End Manifold  11 of 23 

Page 12: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

required  before  the  start  of  any  production welding.  COMPANY  shall  witness  and  approve  the qualification  of  the  welding  specification  and mechanical tests.  5.4.10  Welders Qualification  COMPANY shall witness and approve the Welder Performance Qualification Tests.  Each  welder  shall  pass  a Welder  Qualification Test using the qualified Procedure  for the weld that  the welder will perform.   Test welds  shall meet  the  required  minimum  standards  of acceptability  for  visual  examination,  100% radiographic  examination  and  mechanical testing by the applicable code.    No welder  shall perform  any phase of welding which that welder has not been tested, qualified and  approved  by  the  COMPANY.    Welder qualification  shall  lapse  after  three  months without production welding experience.  All welders will be assigned unique identification numbers  when  qualified.    If  qualified  welders leave  the  Project,  their  numbers  shall  not  be reassigned.  5.4.11  CONTRACTOR Equipment and Supplies  CONTRACTOR shall provide all required welding machines,  line‐up  clamps,  beveling  machines, contour  cutting  machines,  welding  electrodes and  all  other  equipment,  supplies  and consumables  used  in  connection  with  the welding activities.  5.4.12  Equipment  

All welding equipment shall be  in good working order  and  capable  of  producing  welds  of  the required  quality.    Any  equipment  which  does not meet these requirements shall be replaced.  Prior  to  the  start  of  production  welding CONTRACTOR  shall  check  and  calibrate  all welding machine volt and amp meters to within 1% of the reference standard.  During  production  welding,  the  CONTRACTOR shall  check  voltage  amperage  readings  by independent  instrumentation  at  least once per shift and when any inaccuracy is suspected.  5.4.13  Consumables  All  welding  consumables  used  in  production welding  shall  be  qualified  to AWS D  1.1.    Test results shall be presented  to  the COMPANY  for evaluation and approval.  All  welding  consumables  shall  be  supplied  in hermetically  sealed  containers  and  stored according to Section 5.4.14 on Electrode Storage in this specification.  The  CONTRACTOR  shall  be  responsible  for maintaining control and identification of welding consumables and shall ensure that they are kept clean  and  free  from  grease,  oil,  dirt,  rust  and other  contaminates.   All  unidentified  damaged or  rusty  filler  materials  shall  be  discarded.  Welding  consumables which  are wet  or moist shall also be discarded.  5.4.14  Electrode Storage  The  following  are  electrode  storage requirements for different conditions:  • Hermetically  sealed  containers  indoors, out 

of weather and off ground; 

Specification for Fabrication of Pipeline End Manifold  12 of 23 

Page 13: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

• Opened  Containers  ‐  200  degrees  F minimum/300  degrees  F  maximum  or  as recommended by Manufacturer; 

• Electrodes withdrawn  from use  ‐  after  two hours  must  be  discarded  to  prevent  the problem of mixing good and bad electrodes; 

• SMAW  electrodes  shall  be  properly  stored according  to  manufacturers  instructions after opening.  Heaters used for storage shall have a thermometer; 

• General  storage  of  consumables  shall  be maintained  to  prevent  damage  to  the consumable  and  shall  be maintained  clean and dry. 

 5.4.15  Equipment Settings  Procedures  and welders  shall  be  approved  by COMPANY before starting any welding.   During welding, welding speeds shall not vary by more than  plus  or minus  twenty  (±  20%)  percent  in the  Procedure  Qualification  Tests,  and  the voltage  and  amperage  shall  not  vary  from  the settings  approved  for  the  Procedure qualification by more than plus or minus twenty (± 20%) percent.  5.4.16  Grounding Clamps  Grounding  clamps  shall  be made  of  steel  and shall have solid contact with the pipe to prevent the possibility of  arc burns.   Copper or  copper alloys  are  prohibited.    Grounding  clamps  shall not be welded to structure.  5.4.17  Retest of Welds  At  COMPANY  discretion,  additional  welds  for test  purposes  shall  be  cut  out  for  further examination.    For  welds  proven  to  be satisfactory,  CONTRACTOR  shall  be  reimbursed 

by COMPANY according to the Price Schedule of the CONTRACT.  5.4.18  Frequency of Weld Defects  Frequent weld defects of a similar nature, which occur in spite of good welder technique, shall be sufficient  cause  for  CONTRACTOR  and COMPANY to review the welding equipment and electrodes to determine the corrective steps to be taken.  5.4.19  Weather  All welding shall be done  in‐doors  in a covered fabrication shop.  5.4.20  Clean Sled Components  CONTRACTOR  shall  clean  out  the  sled components before closing the ends.  5.4.21  Weld Repairs  Weld  repairs  shall  be  performed  using procedures  and welders  qualified  according  to this specification.  Repairs  of  weld  defects  shall  not  be  made without the knowledge and concurrence of the COMPANY.  The  repair  weld  preparation  shall  be  smooth, with  a  regular  contour,  and  shall be  free  from rust, grease, oil, or other extraneous material.  The  applied  pre‐heat  shall  be  150  degrees  F minimum.  Repair  welds  to  circumferential  weld  seams, when approved, shall be separated by at least 6‐inches. 

Specification for Fabrication of Pipeline End Manifold  13 of 23 

Page 14: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

   Arc  air  gouging  shall  be  allowed  on structural components only.  The COMPANY shall witness the  inspection and NDE of all repair welds.  5.4.22  Arc Burns  All arc burns  shall be  removed by grinding and suitably etched to ensure that all evidence of arc strikes are removed.    5.4.23  Daily Weld Log  The  NDE  contractor  shall  submit  a  weld identification  procedure,  a  radiographic  record log and film for approval by the COMPANY prior to use.  Each weld  shall  be  numbered  consecutively  in accordance  with  the  procedure.    The CONTRACTOR  shall  record  the  identification  of each pipe  joint and weld number  in a daily  log.  This  daily  log  shall  have  the  daily  welds inspected,  the  name  of  the  inspector,  the identification of the welders and the portion of the weld performed.   Steel die stamps shall not be used for marking production welds.  The  radiographic  record  log  and  film  shall  be traceable to a specific weld,  location, welder or welders and shall include the results of all of the radiographic,  ultrasonic  or  other  inspections performed.  Daily Weld Log shall be kept during the work and becomes  part  of  COMPANY  project  records.  This  log  shall  include  but  is  not  limited  to  the following:  • Drawings showing location of each weld; 

• Identification  of  each  element  welded, grade, thickness and width; 

• Identification number of each weld; • Welding procedure used for each weld; • Welder(s)  identification  and  the  portion 

welded; • Date of each weld completion; • Inspector,  date  of  weld  inspection  and 

results; • Defects  found,  weld  repair  and  date 

repaired.  5.4.24  Documentation  Thirty  (30)  days  prior  to  start  of  production welding,  the  CONTRACTOR  shall  provide  the COMPANY with welding document record.  This record shall contain as a minimum the following information:  • Procedure Qualifications Records (PQR); • Welder Performance Qualifications (WPQ); • Quality Control Records.  5.5  Welding Flowlines   All flowline welding and NDE shall be according to COMPANY Specifications 2136600‐SP‐012.  5.6  Welding of Stainless Steel   5.6.1  General  Welding of stainless steel tubing shall meet the requirements  in  this  specification.  CONTRACTOR  shall  submit  to  COMPANY  for approval written procedures as required by the relevant  clauses  in  this  specification  to  the COMPANY for approval a minimum of forty‐five (45) days prior to flowline bundle fabrication. 

Specification for Fabrication of Pipeline End Manifold  14 of 23 

Page 15: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

 5.6.2  Qualification Tests  The  qualification  tests  shall  be  according  to ASME  IX  for welder performance.    In  addition, one  microscopic  section  for  each  position welded shall be done.  CONTRACTOR shall carry out welding procedure qualification test utilizing a COMPANY approved testing laboratory.  CONTRACTOR shall furnish X‐ray, mechanical test results and micro sections.  The  welding  procedure  qualification  shall  be carried  out  before  the  beginning  of  the  field work.    Duplex  stainless  steel  shall  require additional  tests  including  ferrite  count  in  the HAZ of tube, fitting and weld areas (allowable is 35% to 65%) and three (3) burst test to failure.  5.6.3  Radiography  CONTRACTOR  shall  submit  to  COMPANY,  for approval,  written  inspection  and  non‐destructive  examination  procedures  thirty  (30) days prior to start‐up of production welding.  All NDE field inspection shall be in accordance with the approved procedures.  The radiography shall meet the requirements of ASME B31.3 and include 100% of the weld.  5.6.4  Repairs  Weld repairs shall not be allowed.  Welds which fail radiographic requirements shall be removed entirely.  5.6.5  Duplex Tubing  Duplex stainless steel tubing shall be controlled to a ferrite count of 35% to 60%.  

5.7  Structural Welding   Structural Welding shall meet the requirements as  specified  in  the  latest  edition  of  AWS  D1.1 Code.    NDE  is  according  to  NDE  of  sled structures, SP‐065.  5.7.1  Preheat  Preheating  for  welding  shall  be  applied according  to  the  requirements  of  AWS  D  1.1 Code.  Whenever  necessary,  preheating  shall  be performed  by  electric  resistance  or  induction equipment or with  special  shaped gas burners.  Hand‐cutting  torches  shall  not  be  used  for preheating.    Preheating  is  also  required when the ambient temperature falls to 41° F or lower.  When  preheating  is  required,  the  heated material  shall  be  kept  at  the  required temperature until  the weld  is  completed.   The temperature  shall  be  measured  by  means  of thermo‐crayons or equal.  5.7.2  Seal Welding  All  structural welding  shall be  seal welded.   All sharp  corners  shall  be  suitable  removed  to ensure proper coating application.  5.8  Welders Qualification   Welders  qualified  position  is  6G  or  6GR  for structural as applicable.  5.9  Non‐Destructive Examination   All  Non‐Destructive  Examination  shall  be according to COMPANY Specifications SP‐018.  

Specification for Fabrication of Pipeline End Manifold  15 of 23 

Page 16: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

5.10  Protective Coatings   CONTRACTOR  shall  submit  to  COMPANY,  for approval,  cleaning,  surface  preparation  and coating procedures prior to start of work.  All  of  the  external  structural  surfaces  of  the PLEMs and porches shall be cleaned and coated with a  three coat epoxy coating  system except for  the  neoprene  coated  flowlines  and  the abrasion  coated bottom half of  the  sleds.   The finished  coating  shall  be  a  non‐glossy  yellow color.  5.10.1  Surface Preparation  Surfaces shall be  free  from oil, grease, dirt and other  foreign  matter  before  blasting.    Once clean, the surface shall be blasted to near white metal (SA 3.0) according to SSPC‐SP‐5 with a 1.5 to 2.5 mil anchor profile, and shall be verified by COMPANY.  Any  portion  of  the  fabrication  to  be  blast cleaned, including the drilling of bolt holes, shall be  complete  and  in  final  condition  before blasting is started.  Blasting procedure, schedule and equipment shall be approved by COMPANY.  Blast  cleaned  surfaces  shall  be  coated  with primer  immediately  after  blast  cleaning.    No blasting  shall  be  done  between  sunset  and sunrise.   No  acid washes,  cleaning  solutions or rust  inhibitors  shall  be  used  on metal  surfaces after blast cleaning.   Blast cleaning shall not be done  on  moist  surfaces  or  those  that  may become moist before the application of primer.    The maximum relative humidity shall be 

less than eight five (85) percent, and the metal  surface  temperature must  be  at least +10 degrees F above dew point. 

 No blast cleaning shall be done near surface coating activities or near other surfaces sensitive to dust and particle contamination. 

 5.10.2  Epoxy Coating Systems  External  protective  coatings  shall  be manufactured by International Paint, and are as follows:  DRY FILM THICKNESS Prime Coat International Intergard FP   5.0 ‐  7.0 mils prime coat  Second Coat International Intergard FP   5.0 ‐  7.0 mils second coat  

TOTAL: 10.0 ‐14.0 mils  See Appendix D for Coating Data Sheet  5.10.3  Paint Coating Application  CONTRACTOR's equipment for spray application shall be  inspected  and approved by COMPANY before  application.    The  paint  manufacturers recommendations  for  the  selection  and  use  of paint  spray  equipment  shall  be  followed.  CONTRACTOR  shall  apply  each  of  the  epoxy coats following the manufacturers specifications for application and repair.  The pressure gauges shall be in working order.  All surface defects including cracks, laminations, deep  pitting,  and  weld  splatter  that  would interfere with  the  coating  application  shall  be removed.    All  fins,  saw  cuts,  barbs  and  sharp edges  shall  be  removed.    Where  extensive 

Specification for Fabrication of Pipeline End Manifold  16 of 23 

Page 17: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

grinding  is  required,  the  dressed  area  shall  be reblasted to remove all rust.  Coating application  shall be  in accordance with manufacturer’s recommended practices.  Each  coat  shall  be  applied  uniformly  over  the entire surface.   Skips, runs, sags and drops shall be  avoided.   On  beams  and  irregular  surfaces and shapes, edges shall be coated  first with an additional pass made  later.   Each  coat  shall be allowed  to  dry  for  the  time  specified  by  the manufacturer.  Specified  film  thickness  for  coating  materials shall  be  achieved.    Film  thickness  shall  be checked with calibrated gauges.  All  installed  equipment  and  facilities  shall  be protected  from  overspray  from  the  coating operations.    Threaded  surfaces  shall  be  sealed with  grease  before  the  application  of  epoxy coatings.  Coatings  shall  be  free  of  pin  holes,  voids, bubbles and other holidays.  The defects shall be repaired  per  coating  manufacturer recommended practices..  Precautions  shall  be  taken  to  prevent  the deposit  of  dust,  moisture  and  other  foreign matters on  the  surface of  the  coating.    If  such contaminants  occur,  the  surface  area  shall  be reblasted and coated again.  When coatings are applied by brushing, brushes shall be of style and quality for application of the material. 

6.0  PRESSURE TESTING 

The  pressure  testing  procedures  shall  be prepared  by  the  CONTRACTOR  for  COMPANY approval.    The  flowlines  on  the  PLEM  shall  be 

hydrostatically pressure tested for a minimum of two  (2) continuous hours.   The hydrostatic  test shall be witnessed by the COMPANY.  All  the  flowlines  and  control  lines  shall  be cleaned,  dried  and  capped.    (The  control  lines shall be cleaned to Class "6" of NAS 1638).  Some  of  the  structural members  of  the  sleds shall be  tested with  compressed  air  to 150 psi pressure  for a minimum period of 2 hours.   All welds shall be soaped  to check  for  leaks  in  the presence of COMPANY. 

7.0  PLEM ACCEPTANCE TESTING 

7.1  General  CONTRACTOR shall check and test the fabricated units  including  the  mechanical  components.  CONTRACTOR  shall  prepare  test  procedures  to achieve  the  test  requirements  of  this specification, for COMPANY approval.  The  results of  the  tests and pre‐commissioning report shall be documented and copies given to the COMPANY within  two weeks after the  final pre‐commissioning test.  7.2  Sled Testing   The  minimum  requirements  for  checking  and testing of the PLEM are as follows:  7.2.1  Detailed Dimensional Survey  CONTRACTOR  shall  prepare  a  report  of  the  as built dimensions of the PLEM.  Special attention shall  be  given  to  the  position  of  the  flowline connector  hubs.  Measurement  accuracy required  is 1/8‐inch  for piping and 1/4‐inch  for the structural members.  

Specification for Fabrication of Pipeline End Manifold  17 of 23 

Page 18: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

7.2.2  Sled Dry Weight and Center of Gravity  CONTRACTOR  shall  determine  the  dry  weight and  the  center  of  gravity  of  the  PLEM.  Measurement  accuracy  required  is  the weight within  200  lbs.  and  the  Center  of  Gravity  to within 1/2‐inch.  7.3  Submerged Weight Determination  The  PLEM  shall  be  completely  submerged  in water to determine the submerged weight to an accuracy  of  200  lbs.   All  of  the water  shall  be drained from the units after the submerged test.  CONTRACTOR shall record temperature, air and coater, at the start and end of weighing and shall provide  water  sample(s)  to  determine  water density.  

8.0  TRANSPORTATION 

 The  PLEM  shall  be  sent  to  the  COMPANY’s fabrication  facility  for  assembly  and  launch purposes.  There may be road and marine access to the site.  CONTRACTOR,  as  part  of  the  fabrication contract,  shall  provide  load  out  crane  support, for  lifting,  tie‐down materials and  labor  for  the PLEMs on COMPANY provided transportation. 

9.0  DOCUMENTS  ON  COMPLETION  OF FABRICATION 

The Work is not considered to be complete until all of the required documents in this section are furnished  to  the  satisfaction of  the COMPANY.  Within  thirty  (30) days  following  completion of the  fabrication,  the  CONTRACTOR  shall  submit the following documentation to the COMPANY.  

• Complete "As Built Drawings" of the sleds; • Dimensional control and survey reports; • Results  of  the  day  weight  and  center  of 

gravity measurement; • Records of the hydrostatic tests; • Results  of  the  submerged  weight 

measurements; • Ultrasonic testing reports of plate material; • Post weld heat treatment reports; • Structural Steel Plate mill certificates; • Other Components mill certificates; • Change order requests and acceptance; • Non‐conformance reports; • Information  on  tie‐down,  transport  and 

storage of fabricated units; • Part lists with certificate numbers; • Information on the lubricants used; • Operating  and  maintenance  manual  with 

technical  specifications  and  other information. 

 9.1  As‐Built Drawings   CONTRACTOR shall prepare "As‐Built Drawings" showing  all  of  the  deviations,  changes  and revisions  from  the  "Approved  for  Construction Drawings".    CONTRACTOR  shall  provide  one complete  set  of  reproducible  drawings  to COMPANY.  9.2  Materials  COMPANY shall provide certain materials to the CONTRACTOR for the Work.  CONTRACTOR shall furnish  a  complete  accounting  of  the material used, unused and waste.   The documents  shall include  the  variations and  revisions  in material lists.  

Specification for Fabrication of Pipeline End Manifold  18 of 23 

Page 19: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

Specification for Fabrication of Pipeline End Manifold  19 of 23 

COMPANY shall arrange  for  the surplus unused material  to  be  transported  to  COMPANY warehouse facilities.  9.3  Weekly Progress Reports   The Weekly  Progress  Report will  be  in  a  form and  level  of  detail  as  agreed  between CONTRACTOR  and  COMPANY,  including manpower  and  equipment  as well  as weather and downtime.  The Weekly  Progress  Report  prepared  by  the CONTRACTOR  shall be  forwarded  to COMPANY on the first day of the following week.  9.4  Minutes of Meetings   The  CONTRACTOR  shall  prepare  and  distribute minutes  of  project  meetings  as  well  as  of meetings  with  vendors  and  subcontractors  on the day after  the meeting.   CONTRACTOR  shall 

prepare and distribute  letters confirming verbal instruction from the COMPANY.  9.5  Accident Reports   The CONTRACTOR shall prepare and provide to the COMPANY detailed  reports of all accidents with  extent  of  damage,  cause,  results  and disposition in an acceptable form to insurers and law enforcement agencies.  9.6  Notice of Work Completion   The  CONTRACTOR  shall  provide  verification documents that all material, subcontractors and services  with  any  liens  and  claims  have  been satisfied by all parties that were connected with the Work.  These  records  must  be  provided  to  the COMPANY  and  reviewed  before  a  Notice  of Work  Completion  may  be  issued  to  the CONTRACTOR.

 

Page 20: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

Appendix A  

SUMMARY OF CONTRACTOR DELIVERABLE DOCUMENTS 

Specification for Fabrication of Pipeline End Manifold  20 of 23 

Page 21: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

ITEM  SECTION  DESCRIPTION  REQUIRED BY  1.  4  Work Plan  45 days prior to start  2.  4.1  Quality Assurance Program  45 days prior to start  3.  5.1.1  Material Lists and Mill Test  Before start of fabrication  4.  5.4.6  Welding Procedure Specifications  45 days prior to start  5.  5.4.25  Procedure Qualif. Records  30 days prior to start of 

Welder Performance Qualif.  production welding  6.  5.6.1  Welding Procedure Specifications  7.  5.6.3  Inspection and NDE Procedures  8.  5.10  Coating Procedures  9.  7.1  Test and Precommissioning Reports  10.  9  Document on Completion of  30 days after completion 

Fabrication  11.  9.1  As Built Drawings  30 days after work completion  12.  9.3  Weekly Progress Reports  Day after  13.  9.4  Minutes of Meetings  Day after  14.  9.5  Accident Reports  15.  9.6  Verification Documents  

Specification for Fabrication of Pipeline End Manifold  21 of 23 

Page 22: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

Appendix B  

LIST OF COMPANY PROVIDED MATERIALS AND SERVICES (Check complete list in CONTRACT) 

Specification for Fabrication of Pipeline End Manifold  22 of 23 

Page 23: Specification for Fabrication of Pipeline End Manifoldengineering-experts.com/specs/fabrication/Specification_for... · Specification for Fabrication of Pipeline End Manifold 1 of

 LIST OF COMPANY PROVIDED MATERIALS AND SERVICES 

  1. Buoyancy Modules for Sleds 2. Line Pipe 18 “OD x 1.0” WT X‐60, 16 “OD x 0.812” WT X‐60, 14 “OD x 0.688” WT X‐60 and 12.75 

“OD x 0.562” WT X‐60. 3. Bends 4. Valves 5. Piggable Wyes 6. Swivels 

Specification for Fabrication of Pipeline End Manifold  23 of 23