Special Provisions Blank Master  · Web viewproject, for the duration of the construction project...

34
SP XXXX-XX Insert Date This “sample” set of Signal System Special Provisions will require editing (add, delete, modify, update, etc.) prior to use on a specific project. Some of the paragraphs included in these special provisions are project specific and may not be required on every project. Use the language when appropriate based on the plan and as directed in RED text. All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting. DIVISION SS Table of Contents SS-1 (2565) REVISE SIGNAL SYSTEM 1 SS-1.1 GENERAL................................................................ SS-1.2 MATERIALS.............................................................. SS-1.3 CONSTRUCTION REQUIREMENTS............................................. SS-1.4 MEASUREMENT AND PAYMENT............................................... SS-2 (2565) EMERGENCY VEHICLE PREEMPTION SYSTEM...........................30 SS-2.1 SS-3.1 GENERAL....................................................... SS-2.2 SS-3.2 MATERIALS..................................................... SS-2.3 SS-3.3 CONSTRUCTION REQUIREMENTS..................................... SS-1 (2565) REVISE SIGNAL SYSTEM This work consists of removing items of the existing traffic control signal system; furnishing and installing materials and electrical equipment; and installing Department furnished materials as specified herein, all to provide a complete operating revise signal system at the intersection of T.H. ___ and __________ in ________, _______ County in accordance with the applicable provisions of MnDOT 2565; with the current edition of the National Electrical Code; with the Plans; and as follows: --- OR --- This work consists of removing and salvaging two existing traffic control signal systems; furnishing and installing materials and electrical equipment; and installing Department furnished materials as specified herein, all to provide two complete operating new hardwire interconnected coordinated full-traffic-actuated traffic control signal systems as follows: SYSTEM "A" - at the intersection of ______ (______) and ______ in ________, _______ County, and SYSTEM "B" - at the intersection of ______ (______) and ______ in ________, _______ County, 1-SS

Transcript of Special Provisions Blank Master  · Web viewproject, for the duration of the construction project...

Page 1: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

This “sample” set of Signal System Special Provisions will require editing (add, delete, modify, update, etc.) prior to use on a specific project. Some of the paragraphs included in these special provisions are project specific and may not be required on every project. Use the language when appropriate based on the plan and as directed in RED text.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

DIVISION SSTable of Contents

SS-1 (2565) REVISE SIGNAL SYSTEM 1SS-1.1 GENERAL.........................................................................................................................................................SS-1.2 MATERIALS.....................................................................................................................................................SS-1.3 CONSTRUCTION REQUIREMENTS.................................................................................................................SS-1.4 MEASUREMENT AND PAYMENT...................................................................................................................

SS-2 (2565) EMERGENCY VEHICLE PREEMPTION SYSTEM.............................................................................30SS-2.1 SS-3.1 GENERAL...........................................................................................................................................SS-2.2 SS-3.2 MATERIALS........................................................................................................................................SS-2.3 SS-3.3 CONSTRUCTION REQUIREMENTS......................................................................................................

SS-1 (2565) REVISE SIGNAL SYSTEMThis work consists of removing items of the existing traffic control signal system; furnishing and

installing materials and electrical equipment; and installing Department furnished materials as specified herein, all to provide a complete operating revise signal system at the intersection of T.H. ___ and __________ in ________, _______ County in accordance with the applicable provisions of MnDOT 2565; with the current edition of the National Electrical Code; with the Plans; and as follows:

--- OR ---

This work consists of removing and salvaging two existing traffic control signal systems; furnishing and installing materials and electrical equipment; and installing Department furnished materials as specified herein, all to provide two complete operating new hardwire interconnected coordinated full-traffic-actuated traffic control signal systems as follows:

SYSTEM "A" - at the intersection of ______ (______) and ______ in ________, _______ County,

and

SYSTEM "B" - at the intersection of ______ (______) and ______ in ________, _______ County,

In accordance with the applicable provisions of MnDOT 2565; with the current edition of the

National Electrical Code; with the Plans; and as follows:

2565 ABBREVIATIONS

GLOSSARY OF ACRONYMS AND ABBREVIATIONS

Acronyms and abbreviation used in the Contract to represent full text in accordance with 1102 “Abbreviations and Measurement Units” and as shown in Table 2545-1:

1-SS

Table 2565-1Acronyms and Abbreviations Used

Acronym or Short Form Full Name or MeaningAPL Approved/Qualified Products List

Page 2: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

SS-1.1 GENERAL

A Revise Existing Traffic Control Signal System Revise the existing traffic control signal system in accordance with the Plans and with the

following to provide a complete operating revise signal system:

(1) Remove and dispose of items of the existing traffic control signal system not being reused in the revise signal system as required by the Plans and these Special Provisions.

(2) Incorporate into the revise signal system all in place items of the existing traffic control signal system as indicated in the Plans.

(3) Install Department furnished traffic materials as specified herein.(4) Provide and install new items as required by the Plans which includes, but is not limited

to the following:

(a) Concrete foundations(b) Mast arm pole standards(c) Signal service cabinet type: SSB(d) LED vehicle signal indications(e) LED pedestrian signal indications(f) Light emitting diode (LED) units for both new and in place vehicle signal

indications(g) Conduit and conduit fittings(h) Luminaires and luminaire extensions(i) Loop detectors(j) Traffic control signal electrical cables and conductors(k) Bonding and grounding materials

(5) Provide and install insulated spade lugs on conductors required to be terminated.(6) Provide and install new labels to identify cables and conductors as required by the field

wiring diagram.(7) Terminate all cables and conductors as required to provide an operational revise signal

system to the satisfaction of the Engineer.

Ensure Division S Special Provisions “As-Builts” are included in the Division S Special Provisions.This would include the pay item 2011.601.After the July 2015 Project letting date the As-Builts verbiage should automatically be included in Division S Special Provisions by MnDOT’s Project Management & Technical Support Office.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

SS-1.2 MATERIALS

A Department Provided MaterialsThe Department provides to the Contractor (at no expense to the Contractor) the following materials and electrical equipment for the Contractor to install:

(1) One (1) traffic control signal cabinet each complete with actuated controller unit and all required signal control equipment.

(2) Four (4) sets of anchor rods, nuts, and washers to mount the Department provided traffic control signal cabinet (one set = one anchor rod, nut, and washer).

2-SS

Page 3: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

(3) One (1) 4-section rubber gasket to be installed between the bottom of each traffic control signal cabinet and the concrete foundation.

(The following language is to be used for required warning stickers on the backside of sign panels being installed on the signal system project. See additional verbiage under construction requirements. The Specification Writer must include the appropriate contact person and phone number to the following paragraph).

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(4) Warning stickers on new sign panels shall be in accordance with 2564.3 H. The quantity required must be coordinated with the Engineer.

Add the section below if video detection is going to be used.There should be companion verbiage in the construction requirements section below also. The video detection system should be state supplied. The detection systems are on State contract. The traffic signal control public interest finding (PIF) covers this type of detection so State supplying it should not be a problem.The Auto scope Vision uses 4 conductor 18 AWG microwave and sonic detector cable 3815.2 C.14The Gridsmart system uses an Ethernet cable with power over Ethernet. Ethernet Cable (Outside Plant) 3815.2 C.6.dThe Iteris Vantage Next system uses an Ethernet cable with power over Ethernet. Ethernet Cable (Outside Plant) 3815.2 C.6.d.The video detection system to be installed and used at the intersection should be decided at the signal design phase so the correct cable can be call for and shown on the plan. Either Cat 5 E or 4/C 18 AWGUse the language when appropriate based on the plan and as directed in RED text.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(5) Video Detection

B Contractor Provided Equipment for Traffic Control Signal Cabinets Deliver Contractor provided equipment for integration into the State provided traffic control

signal cabinet at least 30 business days in advance of needing the traffic control signal cabinet on the project to the following address:

MnDOT Electrical Services Section (ESS)6000 Minnehaha AvenueSt. Paul, MN. 55111- 4014

Contractor provided equipment when specified includes:

(1) EVP phase selectors(2) APS Central control units(3) Video image processors

To ensure integration into the correct signal cabinet, before delivery to ESS label the Contractor provided equipment packaging with the following:

(1) Assigned Traffic Engineering (TE) Number,(2) State Project Number,(3) Contractor name, and(4) Contact name and phone number.

Notify ESS at least 3 business days in advance before delivering Contractor provided equipment by contacting the following in the order listed until notification has been received:

Electronic Maintenance Supervisor 651 366 5759

3-SS

Page 4: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

Stockroom 651 366 5720Transportation Program Supervisor 651 366 5753

Have the TE Number on hand before calling ESS.

C Materials Provide materials in accordance with 2565.2A and as follows.

D Rodent Intrusion BarrierRodent intrusion barrier listed on MnDOT’s Approved Products List for Signals may be used

instead of stainless steel woven wire cloth specified in 2565.2.DD for traffic signal pole transformer bases Standard Plate No. 8121.

E Arc-Flash Hazard Warning LabelsProvide 4 in H x 6 in W vinyl or polyester labels meeting the following:

(1) White background,(2) Orange background behind the WARNING text,(3) Black text,(4) Self-adhesive,(5) Machine printed letters and numbers, and(6) Water-resistant.

Figure 1 below is for information and reference only.

If the district is going to use the 5 foot mast arm extension include the verbiage below. The most likely scenario for this products use is flashing Yellow arrow. The FYA sign can be mounted on this extension.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

4-SS

Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1

Page 5: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

F Mast Arm Pole Standards and LuminairesProvide mast arm poles and LED luminaires in accordance with the provisions of MnDOT 2565,

3810, and 3831, and as follows:

(1) Mast Arm Extension With Flange Brace(2) Provide and install mast arm extensions with flange brace as detailed in the plans.(3) MnDOT approved mast are extension with flange brace are listed on MnDOT’s

Approved/Qualified Products List for Signals:

http://www.dot.state.mn.us/products/index.html

G Pedestal Slipfitter Collars and Pedestal CapsIf you are going to replace pedestal mounted signal heads with bracketing use the following language for a slipfitter collar

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(1) Pedestal Slipfitter Collars:

Provide pedestal slipfitter collars as detailed in accordance with MnDOT 3832.2C8 and Standard Plate 8111 atop each pedestal shaft when a pedestrian signal indication is installed on the top of the pedestal shaft or when signal head bracketing is used.

If you are going to replace pedestal mounted signal heads and no longer use signal bracketing but rather use straight mount plumbizers than use the following paragraph instead of slipfitter collars

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(2) Pedestal Cap:

Provide aluminum pedestal caps in accordance with 3832.2C.7 atop each pedestal shaft when straight mount plumbizers are used for signal and pedestrian head mounting.

The following language needs to be included if you are designing a signal system with flashing yellow arrow (FYA) with a combined thru and left turn lane. An additional application would be HAWK Pedestrian type ped crossing.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

H Cluster Head AdaptorProvide Cluster head adaptors at locations as indicated in the plan.

Use MnDOT approved cluster head adaptors listed on MnDOT’s Approved/Qualified Products List for Signals:

http://www.dot.state.mn.us/products/index.htmlThe following language needs to be included if you are designing a signal system with flashing yellow arrow (FYA) with a combined thru and left turn lane. This indication is only intended to be used in this application.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

I Bi Modal Green and Yellow Arrow Signal IndicationsProvide green and yellow bi-modal signal indications at locations as indicated in the plan.

Use MnDOT approved bi-modal signal indications listed on MnDOT’s Approved/Qualified Products List for Signals:

5-SS

Page 6: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

http://www.dot.state.mn.us/products/index.html

J Grease Filled Wire NutsUse NRTL listed grease filled wire nuts meeting the following requirements to insulate and seal

individual splices of signal control cable:

(1) Pre-filled twist-on wire connector(2) Silicone based sealant(3) UL 486C listed (4) UL 486D listed for direct burial(5) UL 94V-2 Flame Rating(6) CSA-C22.2 NO. 188 listed(7) CSA-C22.2 NO. 198.2 listed for direct burial(8) RoHS Compliant(9) Sized in accordance with the intended conductors being spliced.

K Accessible Pedestrian Signals (APS)(Audible Pedestrian Push Button Units and Associated Traffic Control Signal Cabinet Equipment)

Provide Accessible Pedestrian Signals in accordance with MnDOT 3833 and as follows:

The APS manufacturer must provide the required voice messages in each button as defined below. Additionally the APS manufacturer must supply backup copies of the voice messages to the Electrical Services Section on one of the following media types:

Compact Disk

USB flash drive.

Deliver all Accessible Pedestrian Signals (APS) components, except push button units, to MnDOT’s Electrical Services Section for installation into the department provided traffic control signal cabinet. Deliver the components being installed in the traffic control signal cabinet to the above location at least 30 business days in advance of when the department provided traffic control signal cabinet is required on the job site.

Ensure that the order form below is presented to the Accessible Pedestrian Signal (APS) manufacturer so the appropriate Braille message is added to the pedestrian information sign and the correct voice messages are programmed in the pedestrian push buttons.

The following order form must be filled out by the special provisions writer before inclusion in the final set of special provisions. The order form should be left as separate pages so they can be removed.

All RED text must be removed from the special provisions prior to the Special Provisions being submitted for project letting.

 Accessible Pedestrian Signal (APS)

ORDER FORM(Fill out one form per intersection)

Intersection:System I.D. ___________ T.E. No. ___________ Total Number of Pedestrian Push Buttons _____ Field Wiring Interface Board: One needed for each intersection Qty: 1

CCU (Central Control Unit): One needed for each intersection Qty: 1

6-SS

Page 7: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

Push Button and Sign Braille InformationButton Arrow Direction R/L Street Name

(Street Being Crossed)PB2-1 PB2-1PB2-2 PB2-2PB2-3 PB2-3PB2-4 PB2-4PB4-1 PB4-1PB4-2 PB4-2PB4-3 PB4-3PB4-4 PB4-4PB6-1 PB6-1PB6-2 PB6-2PB6-3 PB6-3PB6-4 PB6-4PB8-1 PB8-1PB8-2 PB8-2PB8-3 PB8-3PB8-4 PB8-4

Custom Voice Message Details

Voice on Location and Walk Message(s) Please give phonetic pronunciation on difficult street names so that the message will be recorded correctly. *Note that unless Street, Drive, Avenue etc.…are absolutely necessary for intersection identification, it is recommended to not include them in the verbal message. 

7-SS

Page 8: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

8-SS

PB2-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB2-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB2-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB2-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 9: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

9-SS

PB4-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB4-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB4-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB4-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 10: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

10-SS

PB6-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB6-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB6-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB6-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 11: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

11-SS

PB8-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB8-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB8-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB8-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 12: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

Walk Interval MessagesModel message for the walk interval, applicable to most intersections.“Howard. Walk sign is on to cross Howard.”

Pushbutton Informational MessagesModel message for pushbutton intersection identification information.“Wait to cross Howard at Grand.”

All RED text must be removed from the special provisions prior to the Special Provisions being submitted for project letting.

Include the following if the District intends to use pedestal shafts to mount APS buttons with Signal or Pedestrian Heads installed above.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

L Accessible Pedestrian Signal (APS) Pushbutton Mounting SpacerProvide and install MnDOT approved Accessible Pedestrian Signal (APS) Pushbutton Mounting

Spacers as specified herein and in the Plan.

MnDOT approved Accessible Pedestrian Signal (APS) Pushbutton Mounting Spacers are listed on MnDOT’s Approved/Qualified Products List for Signals:

http://www.dot.state.mn.us/products/index.html

M Equipment PadProvide an equipment pad as detailed in the Plans and specified in these Special Provisions.

The equipment pad contains the following:

Traffic control signal cabinet and control equipment.

Traffic control signal cabinet, anchor rods, nuts and washers and associated internal control equipment to be provided by the Department and installed by the Contractor.

N Signal Service Cabinet.Signal service cabinet Type SSB to be provided and installed by the Contractor. SSB cabinets will

be supplied from the manufacturer with anchor rods, nuts and washers used for attaching the service cabinet to the equipment pad.

O Signal Service Cabinet, Type SSB (with Battery Back-up Equipment) Use this paragraph if the District wants a full blown SSB cabinet with a battery backup system. The spec writer needs to use this or the other paragraph for an SSB Service cabinet.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

Provide a signal service cabinet in accordance with MnDOT 3837.2A.7 and as follows:

Type SSB with battery back-up equipment which includes an inverter, batteries, bypass switch and external strobe.

P Signal Service Cabinet, Type SSB (without Battery Back-up Equipment) Use this paragraph if the District wants a SSB cabinet without batteries, inverter and bypass switch. The SSB service cabinet will not have any back up capabilities. The backup system can be added at a later date to the standard SSB cabinet that would be provided using this paragraph. The spec writer needs to use this or the other paragraph for an SSB Service cabinet.

12-SS

Page 13: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

Provide a signal service cabinet in accordance with MnDOT 3837.2A.7 and as follows:

Type SSB without battery backup equipment. Do not provide an inverter, batteries, bypass switch or external strobe.

Q Advance Warning Flashers (AWF)Traffic control signal pedestal shafts and pedestal bases must be in accordance with the

applicable provisions of MnDOT Standard Plate 8122, 8129, MnDOT 2565, 3832, and detailed in the Plan.

Provide all materials and electrical equipment to provide four (4) complete operating advance warning flashers (Signal Base No.'s __, __, __, and __) at the locations indicated in the Plans in accordance with the "ADVANCE WARNING FLASHER DETAILS" in the Plans and with the following:

Change the bolded aluminum to steel below if the signal system is going to be painted. In either case remove the bolded option from the text.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(1) Traffic control signal pedestals in accordance it 3832.(2) Flashing Beacon Assemblies as follows:

(a) 12 inch, polycarbonate vehicle signal heads for flashing beacon assemblies in accordance with 3834.

(b) 12 inch "Yellow" signal indications in accordance with MnDOT 3834 and as follows:

(c) Affix to the back of each "yellow" flasher indication a permanent label indicating the date of installation in accordance with 2565.3L.6 and to the satisfaction of the Engineer.

(d) Each flashing beacon assembly must include a cut away visor and background shield as indicated on the detail in the Plan.

(e) Attach flasher beacons as detailed in the Plans to the satisfaction of the Engineer.

(3) Flashing Beacon Assembly Bracketing

Provide aluminum flashing beacon assembly bracketing with anodic coating as per MIL-A-8625C for Type II, Class I Coating.

(4) Wiring at Each Advance Warning Flasher:

Provide a 4/c 14 AWG signal control cable in accordance MnDOT 3815.2 between the terminal block or pole base connector in the pedestal base and each flashing beacon atop the advance warning flasher assembly.

(5) Advance Warning Flasher Signs:

Provide and install W3-X4 (PREPARE TO STOP WHEN FLASHING) signs in accordance with 2564.

Mount each sign as detailed in the Plan to the satisfaction of the Engineer.

13-SS

Page 14: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

SS-1.3 CONSTRUCTION REQUIREMENTS

A Conduit UndergroundPlace conduit underground in accordance with 2565.3.D.2.b “Underground” and as follows:

Place conduit at least 24 in below roadway

The following paragraph needs to be modified to give contractor specific location to deliver the pallet back to MnDOT.

All RED text must be removed from the special provisions prior to the Special Provisions being submitted for project letting.

B Pick Up Department Provided Materials Pick up materials and electrical equipment from:

MnDOT’s Electrical Services Section,6000 Minnehaha Avenue,St. Paul, MN. 55111- 4014.

Follow these requirements:

(1) Request from the Electrical Services Section the materials and electrical equipment listed in (A) above.

(2) Direct MnDOT’s Electrical Services Section to the T.E. Request No. ______. (3) Request Department provided materials at least 30 business days in advance of needing

the material on the project. (4) Notify MnDOT’s Electrical Services Section at least 3 business days in advance of

intention to pick up materials and electrical equipment. Contact:

Electronic Maintenance Supervisor 651 366 5759Stockroom 651 366 5720Transportation Program Supervisor 651 366 5753

(5) Pick up the Department provided materials and electrical equipment at the above specified location and transport them to the job site

(6) Secure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip and be damaged

Notify the Engineer in advance of contacting MnDOT’s Electrical Services Section.

C Installation of Department Provided MaterialsInstall the Department provided traffic control signal cabinets each complete with actuated

controller unit and all required signal control equipment.

Provide and install all additional materials and electrical equipment for a complete operating traffic control signal cabinet installation which includes, but is not limited to:

(1) A cabinet concrete foundation as part of the equipment pad concrete foundation using Department provided anchor rods, nuts, and washers.

(2) Bonding and grounding materials and connections.(3) Make all field conductor connections in each traffic control signal cabinet as directed by

the Engineer to make each traffic control signal system operational.

Protect the Department provided cabinet pallet from damage and return the pallet to MnDOT Central Electrical Inventory Center at the address specified herein, or the District Headquarters.

14-SS

Page 15: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

Add the text below if the signal system has video detection.There should be companion verbiage in the materials section above also. Use the language when appropriate based on the plan and as directed in RED text. All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

D Video Detection Systems Construction RequirementsInstall traffic signal high definition video detection systems at the locations shown on

the Plan and the following:

(1) Aim each camera for optimal field of view and detector placement at each specific approach,

(2) Install continuous unspliced Cat 5 E cable, or microwave and sonic detector cable(3) Zoom and focus the cameras to provide proper imaging of the approaches(4) Program video image detection zones as shown on the Plan, and(5) Verify with MnDOT’s district traffic office:

(1) Aim each camera for optimal field of view and detector placement at each specific approach,

(2) Detection zones are working correctly, and(a) Live video images show the detection zones properly overlaid and operating

(3) Remove, reinstall, and aim cameras for optimal field of view and proper detector overlay placement when different stages of the project require intersection configuration changes.

E SplicingUse grease filled wire nuts for splicing signal control cable.

F Rodent Intrusion BarrierInstall rodent intrusion barrier in accordance with 2545.3W.

Rodent intrusion barrier listed on MnDOT’s Approved Products List may be installed instead of stainless steel woven wire cloth as specified in 2545.3.W for traffic signal pole transformer bases Standard Plate No. 8121.

Install the MnDOT APL barrier in accordance with the manufacturer’s installation instructions. Fill gaps between the barrier and base plate, and between the barrier and the foundation with 100% silicone sealant.

G Arc-Flash Hazard Warning LabelingCalculate available fault current in accordance with 2545.3X and 2565.3 CC.

Establish available fault current and apply the appropriate label as follows.

Use the current edition of NFPA 70E “Standard for Electrical Safety in the Workplace” to determine the required PPE category and personal protective equipment.

If the available fault current is ≤ 25,000 amps then provide a label with the following information shown in Example 1.

15-SS

Page 16: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

If the available fault current is ˃ 25,000 amps:

Determine PPE requirements in accordance with the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Provide a label with the following information shown in Example 2. Fill in the ___ (blank) with the required arc-flash PPE category and arc-flash boundary distance

Install labels on the front of the dead front door of the electric service cabinet at eye level.

H Maintenance of Existing Electrical Systems

Maintain and keep in operation new and existing electrical systems in accordance with 2565.3B and as follows:

The Contractor is responsible for locating underground facilities of existing traffic control signal systems including temporary, and newly constructed signal systems within the limits of the construction

16-SS

Example 1

Warning Arc Flash HazardAppropriate PPE RequiredArc Flash Boundary 19 inches Arc Flash PPE Category ____1____Working Distance 18 Inches Arc Flash Personal Protection Equipment (PPE)

List required clothing, Min Arc Rating of 4 cal/cm², and protective equipment in accordance with the PPE Table from the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Equipment ID

Example 2

Warning Arc Flash HazardAppropriate PPE RequiredArc Flash Boundary ____Feet Arc Flash PPE Category ________Working Distance 18 Inches Arc Flash Personal Protection Equipment (PPE)

List required clothing, Min Arc Rating of ___ cal/cm², and protective equipment in accordance with the PPE Table from the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Equipment ID

Page 17: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

project, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with Minnesota State Statute 216D.

The responsibility for locating underground traffic control signal system facilities shall be transferred to the Contractor on the project start date as shown on the proposal.

MnDOT’s locating group will provide an initial locate of the underground traffic control signal system facilities within the project limits at the request of the Contractor at the start of the project. The request for the initial locate must be submitted to MnDOT’s Locating Office a minimum of 4 business days prior to the project start date.

Locate requests that are within the construction project limits will continue to be received by MnDOT’s Locating Office. These locate tickets will be forwarded to the Contractor’s representative responsible for coordinating locate requests within the projects limits. The locate tickets will be forwarded via e mail or fax. Confirmation of receipt of the locate ticket must be sent by the Contractors representative back to MnDOT’s locating office within 2 hours of MnDOT’s sending the Contractor’s representative the locate request.

The Contractor responsible for locating underground traffic control signal system facilities will repair damage as the result of improperly located or unmarked underground traffic control signal system facilities within the project limits.

The repair the damaged underground traffic control signal system facilities in accordance with 2545.3A, 2565.3B and RTMC design and construction requirements.

Until final written acceptance of the project by the Engineer (MnDOT 1716), locate underground traffic control signal facilities as required in this section. This Work is included in the Pay Item Traffic Control Signal System.

It is the Contractor’s responsibility to notify MnDOT’s Locating Office to provide contact information and establish the contractor has assumed responsibility for locating MnDOT’s underground traffic control signal system facilities within the project limits. The form in this section is filled out by the Contractor’s representative and provided to the Engineer at the pre-construction meeting. A copy of the completed form sent to the following:

Electrical Services Dispatch Phone: (651)366-5750Fax: (651)366-5742E mail: [email protected] Minnehaha Ave. St. Paul, MN 55111-4014andLocating Supervisor Phone: (651)755-9061Fax: (651)366-5742E mail: [email protected] Minnehaha Ave. St. Paul, MN 55111-4014

(The following Section should be filled out by the specification writer to direct the contractor and project engineer to the correct person in the District.All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

MnDOT District Signal Operations Name: _______________Phone: _______________

17-SS

Page 18: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

Fax: _________________E mail: _______________Address: ______________

(The following Section should be left on its own page so the contractor can remove it and use the blank page)All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

18-SS

Page 19: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

19-SS

Locating Responsibility FormJob S.P. Number __________________________________

Job Type __________________________________

Start Date __________________________________

End Date __________________________________

T.H. __________________________________

Location __________________________________

Lighting/ Signal Inspector __________________________________

Contractor __________________________________

Contractor (24 Hour Contact) __________________________________

Project Manager __________________________________

Phone Number __________________________________

Fax Number __________________________________

Email __________________________________

Electrician __________________________________

Phone Number __________________________________

Locator Area __________________________________

Project Engineer __________________________________

Phone Number __________________________________

Chief Inspector __________________________________

Phone Number __________________________________

Weekly Meeting __________________________________

Page 20: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

During any periods of authorized work suspension, the contractor is responsible for maintenance of the existing, temporary, and newly constructed traffic control signal systems.

Provide to the Department contact information with the names and telephone numbers for 24 hours a day, 7 days a week maintenance as defined above.

This Work is included in the Unit Prices of the Pay Items that are part of the Traffic Control Signal System.

I Anchor Rod Tightening (Signals)The second paragraph of 25653O “Traffic Signal Mast Arm Pole Installation” is deleted and

replaced with the following.

Install poles and tighten anchor rods in accordance with the MnDOT Anchor Rod Tightening Handbook- New Installation Procedures and the MnDOT Anchor Rod Tightening Form.

Complete a MnDOT Anchor Rod Tightening Form for each traffic signal mast arm pole installed on the Project. Submit the completed forms to the Engineer.

For traffic signal mast arm poles installed on PA pole foundations use a Hytorc Stealth 4 low profile hydraulic torque wrench with digital pendant and working digital torque read out in foot pounds to tighten the top nuts to the required torque values.

A Hytorc Stealth 4 hydraulic torque wrench may be obtained from:Glenn Lickness Hytorc MN- Sales & Rental Bolting Specialist [email protected] Bridgepoint way South St. Paul, MN 55075Or use a low profile hydraulic torque wrench with digital pendant and working digital torque read

out in foot pounds to tighten the top nuts to the required torque values. Ensure the wrench fits between the PA base sidewall and the top nuts.

Obtain Engineer’s approval of the wrench and provide proof of calibration performed within the last 12 months from an accredited calibration service before installing signal mast arm poles.

For PA transformer bases, when leveling the leveling nuts use a standoff distance of at least ½ inch and not more than 1 inch. Standoff distance is the clear space between the bottom of the leveling nut and the top of the concrete foundation.

Use fixed size wrenches for turning leveling nuts. Do not use pipe wrenches.

Immediately after standing the pole on the foundation complete the entire pole installation process. The pole installation process is from the time the pole is set on the foundation to the re-tightening to 100% torque final step of the Anchor Rod Tightening Handbook- New Installation Procedures. Do not stop midway through the installation process. Do not stand poles on foundations without completion of final anchor rod re-tightening step. If equipment downtime is a concern during the tightening of anchor rods to complete the entire pole installation process, then provide one crew for installing the pole and another crew for anchor rod tightening.

Keep the form on the next page on a separate page so the contractor can remove it from the special provisions and use it in the field.

20-SS

Page 21: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

21-SS

Page 22: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

22-SS

Page 23: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

If the district is going to use the 5 foot mast arm extension include the verbiage below. The most likely scenario for this products use is flashing Yellow arrow. The FYA sign can be mounted on this extension.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

J Mast Arm Extension with Flange BraceInstall the mast arm extension and flange brace according to manufacturer’s installation instructions.Cut mast arm extension to length to center the signal head on the driving lane.The following language needs to be included if “pole base connectors” are being used as conductor termination devices. The District must use either Pole Base Connectors or Terminal Bocks but not both.All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.The following language needs to be included if “terminal blocks” are being used as conductor termination devices. The District must use either Pole Base Connectors or Terminal Bocks but not both.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

K Electric Service Information FormFill out the electric service information form for traffic control signal systems included elsewhere

in these Special Provisions.

Provide to the Engineer, prior to final acceptance of the project, four (4) copies of the electric service information form for traffic control signal systems and the Engineer will distribute the copies as follows:

MnDOT Electrical Services Section.MnDOT Traffic Electrical Systems Engineer.MnDOT District Traffic Engineer.City of _________ or County of________.

The Contractor provided "electrical service information form for traffic control signal systems" and available fault current calculations and labeling are considered incidental work.

(The following form should be left on its own page so it can be removed from the special provisions and used by the contractor) See the next page of this document

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

23-SS

Page 24: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

24-SS

Page 25: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

L Pedestal Reinforcing Collar (Wind Collar) InstallationWhere the pedestal reinforcing collar is utilized, clamp each reinforcing collar around the top of

the pedestal base by using two (2) 5/16" Socket Head Bolts per section (see figure below).

Each section must have a 5/16" pilot hole for drilling into base. Drive a 5/16" x ¾" Roll Pin through the collar into the base (flush to allow ¼" penetration into the base) to prevent the pedestal shaft from turning in the pedestal base.

M Install Salvaged Mast Arm Mounted SignsSalvage and re-install mast arm mounted sign panels on the traffic control signal mast arms

where indicated in the Plans and as directed by the Engineer. If required by the Engineer, provide new mounting brackets and mounting hardware for each salvaged sign panel. Mount salvaged signs at the location on the mast arm as specified in the Plans and to the satisfaction of the Engineer

Installing the salvaged mast arm mounted sign panels and all required mounting brackets and mounting hardware is considered incidental work to the REVISE SIGNAL SYSTEM and no direct compensation will be made therefor.

Include the following if the District intends to use pedestal shafts to mount APS buttons with Signal or Pedestrian Heads installed above.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

N Accessible Pedestrian Signal (APS) Pushbutton Mounting SpacerProvide 3 Accessible Pedestrian Signal (APS) Pushbutton Mounting Spacers in accordance with

3833 at each location where an APS button is installed on a pedestal shaft containing signal or pedestrian heads above.

Two spacers are used as APS button standoffs and the third shall act as a wire way for the APS button.

O Equipment Pad Concrete FoundationProvide the equipment pad in accordance with 2565.3F.3 and as detailed in the Plans at the

location staked by the Engineer.

The anchor rods must project above the concrete foundation to accommodate the13 mm (1/2 inch) thick gasket.

Install the Department provided rubber gasket sections between the bottom of each cabinet base and the concrete foundation. Leave one ½ inch (13 mm) gap in the gasket to ensure proper water drainage.

25-SS

Page 26: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

Install the cabinet concrete foundation for the signal service cabinet type SSB as part of the equipment pad concrete foundation using anchor rods, nuts, and washers supplied by the SSB cabinet manufacturer. The anchor rods must project above the concrete foundation to accommodate 1/2 inch (13 mm) thick gasket.

Install the cabinet manufacturer supplied rubber gasket sections between the bottom of each cabinet base and the concrete foundation. The Contractor must leave one 1/2 inch (13 mm) gap in the gasket to ensure proper water drainage.

(The following language is to be used for required warning stickers on the backside of sign panels being installed on the revised signal system project. The Specification Writer must include the appropriate contact person and phone number to the following paragraph).

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

P Sign Panel Warning StickersInstall Department furnished warning stickers on new sign panels in accordance with MnDOT

2564.3H. Provide 30 days advance notice to___________________ at ___-___-____ prior to picking up the Department furnished warning stickers.

Remove and Dispose of Conduit

Except under roadway surfaces, remove and dispose of the existing traffic control signal system underground conduit, unless otherwise specified in Contract Documents or directed by the Engineer.

Abandon the existing conduit under roadway surfaces, unless otherwise specified in Contract Documents or directed by the Engineer.

Q Remove and Salvage Traffic Control Signal Cabinet and EquipmentTo ensure proper care and prevent damage during removal, handling and shipping of control

signal cabinets and equipment, provide in order the following:

(1) De-energize the traffic control cabinet and equipment (2) Disconnect the power conductors (3) Unplug and remove removable control equipment including the controller unit, detector

amplifier units, conflict monitor, and load switches from the cabinet. (4) Package and secure the removed control equipment in a method and manner that

prevents damage to the equipment during handling and shipping (5) Coil together the connecting harnesses of the removed equipment (6) Fasten and secure the harnesses to a cabinet shelf in a method and manner that

prevents the harnesses from being damaged when closing the cabinet door and from falling through the bottom of the cabinet during removal, handling and shipping

(7) Secure the cabinet in an upright position when removing, handling and shipping

R Remove and Salvage Battery Backup Service (SSB) Cabinet and EquipmentTo ensure proper care and prevent damage during removal, handling and shipping of control

signal cabinets and equipment, provide in order the following:

(1) De-energize the SSB cabinet and equipment (2) Disconnect the power conductors (3) Remove the batteries and uninterrupted power supply (UPS) from the cabinet(4) Package and secure the removed batteries and UPS in method and manner that

prevents damage to the equipment during handling and shipping (5) Coil together the harnesses

26-SS

Page 27: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

(6) Fasten and secure the harnesses to a cabinet shelf in a method and manner that prevents the harnesses from being damaged

(7) Secure the cabinet in an upright position when removing, handling and shipping

S Remove and Dispose Miscellaneous StructuresRemove and dispose of miscellaneous structures including mast arm poles, traffic signal

pedestals, and APS push button stations as follows:

(1) Destroy miscellaneous structures including pole shafts, transformer bases, mast arms, and luminaire extensions to the satisfaction of Engineer.

(2) Handle, transport, and dispose of miscellaneous structures containing lead based paint in accordance with Occupational Safety & Health Administration (OSHA) and the Minnesota Pollution Control Agency (MPCA) regulations.

(3) Read, certify understanding, and agree to abide to the requirements in OSHA 29 CFR 1926.62 and Minnesota Rules Chapter 5206, 7025, 7035, 7045 relating to the removal and disposal of lead base painted miscellaneous structures as hazardous waste.

(4) Submit to the Engineer a completed “Contractor Certification of Disposal" form included in the Method of Measurement and Basis of Payment Section.

Ensure Division S Special Provisions “As-Builts” are included in the Division S Special Provisions.This would include the pay item 2011.601.After the July 2015 Project letting date the As-Builts verbiage should automatically be included in Division S Special Provisions by MnDOT’s Project Management & Technical Support Office.The District needs to include the verbiage below to trigger installation of Divisions S Special Provisions.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

T As Built Drawings and GPS CoordinatesAs Built drawings and GPS coordinates in accordance with Division S Special Provisions “AS-

Builts” including Pay Item No. 2011.601 (As-builts).

U Structures Containing Lead Based PaintHandle, transport, and dispose of miscellaneous structures containing lead based paint in

accordance with Occupational Safety & Health Administration (OSHA) and the Minnesota Pollution Control Agency (MPCA) regulations and the following.

(1) Read, certify understanding, and agree to abide to the requirements in OSHA 29 CFR 1926.62 and Minnesota Rules Chapter 5206, 7025, 7035, 7045 relating to the removal and disposal of lead base painted miscellaneous structures as hazardous waste.

(2) Submit to the Engineer a completed “Contractor Certification of Disposal" form included in this section.

(3) Submit to the Engineer a copy of the “Tipping Receipt” from the scrap yard or recycler.

The form below is provided as an example. The actual form must be downloaded by the contractor. Keep the form on the next two pages in the document.All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

27-SS

Page 28: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

28-SS

Page 29: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

The Office of Environmental Stewardship sets the policy and procedures for regulated materials management.

The contractor must follow the links below to obtain the current work order form and the list of approved waste contractors.

http://www.dot.state.mn.us/environment/regulatedmaterials/wastemgmt.html

Hazardous Waste Work Order Form (Word)

MnDOT approved list of waste contractors (Word)

SS-1.4 MEASUREMENT AND PAYMENT

A MeasurementRemoving items of the existing traffic control signal system; furnishing and installing materials

and electrical equipment; and installing Department furnished materials as specified herein, all to provide a complete operating revise signal system at the intersection of T.H. ___ and _______ in ______, ________ County as contained in these Special Provisions and in the Plans will be measured as an integral unit complete in place PAYMENT

B PaymentRemoving items of the existing traffic control signal system; furnishing and installing materials

and electrical equipment; and installing Department furnished materials as specified herein, all to provide a complete operating revise signal system at the intersection of T.H. ___ and _______ in ______, ________ County as contained in these Special Provisions and in the Plans will be paid for under Item No. 2565.616 (REVISE SIGNAL SYSTEM) at the Contract price per SYSTEM, which price will be compensation in full for all costs incidental thereto.

SS-2 (2565) EMERGENCY VEHICLE PREEMPTION SYSTEMThis work consists of furnishing and installing emergency vehicle preemption (EVP) system at the

intersection of ______ (______) and ______ in ________, _______ County in accordance with the applicable provisions of MnDOT 2565; with the Plans; and as follows:

SS-2.1 SS-3.1 GENERAL(None)

SS-2.2 SS-3.2 MATERIALSProvide Emergency Vehicle Preemption (EVP) equipment in accordance with MnDOT 2565 and

3814. Phase selectors (or other EVP equipment to be installed in the traffic control signal cabinet) will be installed in the Department furnished cabinet by MnDOT personnel.

Deliver all EVP phase selectors or other required EVP equipment to be installed in the traffic control signal cabinet to the Department at MnDOT’s Electrical Services Section for installation into the Department furnished traffic control signal cabinet. Provide the equipment at least 30 business days in advance of when the Department furnished traffic control signal cabinet is required on the job site.

SS-2.3 SS-3.3 CONSTRUCTION REQUIREMENTSPlace in accordance with 2565.3.

A SS-3.3 MEASUREMENTFurnishing and installing emergency vehicle preemption (EVP) system at the intersection of T.H.

___ and ______ in ________, _______ County as specified herein is measured as an integral unit complete in place and operating

29-SS

Page 30: Special Provisions Blank Master  · Web viewproject, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with

SP XXXX-XXInsert Date

B SS-3.4 PAYMENTEVP systems are paid for under Item No. 2565.501 [EMERGENCY VEHICLE PREEMPTION (EVP)

SYSTEM] at the Contract price per LUMP SUM, which price is compensation in full for all costs in

30-SS