Spacecraft development - Lund Observatory · Spacecraft development Gaia program history Program...
Transcript of Spacecraft development - Lund Observatory · Spacecraft development Gaia program history Program...
Spacecraft development
Gaia program historyProgram overviewPayload optimisationProject organisationIndustrial team build upSubcontractor selectionOverall developmentSpecification treeAssembly, Integration and verificationAvionic modelMechanical and Electrical integrationTests
Gaia: a long story
Gaia is in the air since astrometry from space has demonstrated its viability with Hipparcos (1989 launch)
– Roemer mission by Hoeg & al in 1992
Industry is involved in Gaia definition from the beginning– First industrial studies funded by ESA around mid 90’s
– Nearly 10 years of advanced studies needed to issue a concept• Fulfilling as much as possible the science needs
• Technically and programmatically affordable
– Final concept settled in 2004
– Detailed definition and development started in 2006.
Gaia is to be ready for launch in 2011
Gaia programme overview
1995 – 2004: Phases O/A: Feasibility and Definition studies– Designing a valuable and affordable mission
– Iterations « as long as necessary » by a small industrial team, GST and ESA
– Technological support studies (TDA) launched in parallel of system studies
2005: Industrial competition to design & develop the spacecraft– Intensive period for
• ESA to issue Invitation to Tender
• Then for industry to reach a design/development maturity sufficient to commit on performances, cost and schedule
• And finally for ESA to select a Prime industrial
2006-2007: Phase B: Detailed design and team build up– Spacecraft design is tentatively frozen, building blocks are specified
– The industrial team is built up through competitive process
– The spacecraft performances are refined, with feed back form industrial team
– The Payload is optimised with GST support
2008 – 2011: Phase C/D: The spacecraft is developed, assembled, tested and qualified before delivery to ESA
Payload Optimisation with GST support
Although the schedule for the industrial team build-up and for the satellite development is extremely tight, Payload parameters are still optimised during phase B with the support of GST, after System Requirement Review
Main topics that deserved some optimisation– Photometric instrument: prism dispersions, red and blue band
definition,
– Radial velocity instrument: spectral resolution, star density, HR/LR modes,
– Windowing, sampling strategy, on-board processing algorithms
– Data priority management
– Scenario for scan law & modified scan law
Prime project organisation
spacecraft architects & coordinators
Mechanical & thermal engineering support Electrical & dynamics engineering support
Secretary & Documentation : C. Deblock
Configuration : JJ. Bouisset
Contract officer: J.A. VatinelSubcontracts: S. Peden
Project control: M. Mamy / I. BraultSchedule control: C. Buge
Product Assurance APM: D. Herbin
Industrial Devel’nt& AIT APM
M. Pendaries
System engineering& verification APM
F. Faye
Payload ModuleAPM
P. Charvet
CSWAPM
P. Humbert
Mechanical packageprocurement APM
C. Lebranchu
• Mechanical, thermal & propulsion C. Lebranchu• Launcher interface C. Lebranchu• Electrical systems & EMC G. Rougier• Performance verification & calibration E. Ecale• Dynamics & pointing E. Ecale
• Operations & Database X. Moisson• System datation X. Moisson• Data management & On-board software P. Humbert• AIT & GSE architecture engineering C. Gabilan
• Mechanical engineering F. Vogel• Thermal engineering U. Rauscher
• Electrical, RF & EMC enginnering A. Dyne• Dynamics & pointing enginneering T. Colegrove
Support to ESA for Science & Mission Performance expert: F. Safa
Electrical packageprocurement APM
P. Lelong
GAIA SpacecraftProject ManagerV. Poinsignon
spacecraft architects & coordinators
Mechanical & thermal engineering support Electrical & dynamics engineering support
Secretary & Documentation : C. Deblock
Configuration : JJ. Bouisset
Contract officer: J.A. VatinelSubcontracts: S. Peden
Project control: M. Mamy / I. BraultSchedule control: C. Buge
Product Assurance APM: D. Herbin
Industrial Devel’nt& AIT APM
M. Pendaries
System engineering& verification APM
F. Faye
Payload ModuleAPM
P. Charvet
CSWAPM
P. Humbert
Mechanical packageprocurement APM
C. Lebranchu
• Mechanical, thermal & propulsion C. Lebranchu• Launcher interface C. Lebranchu• Electrical systems & EMC G. Rougier• Performance verification & calibration E. Ecale• Dynamics & pointing E. Ecale
• Operations & Database X. Moisson• System datation X. Moisson• Data management & On-board software P. Humbert• AIT & GSE architecture engineering C. Gabilan
• Mechanical engineering F. Vogel• Thermal engineering U. Rauscher
• Electrical, RF & EMC enginnering A. Dyne• Dynamics & pointing enginneering T. Colegrove
Support to ESA for Science & Mission Performance expert: F. Safa
Electrical packageprocurement APM
P. Lelong
GAIA SpacecraftProject ManagerV. Poinsignon
Contract officer: J.A. VatinelSubcontracts: S. Peden
Project control: M. Mamy / I. BraultSchedule control: C. Buge
Product Assurance APM: D. Herbin
Industrial Devel’nt& AIT APM
M. Pendaries
System engineering& verification APM
F. Faye
Payload ModuleAPM
P. Charvet
CSWAPM
P. Humbert
Mechanical packageprocurement APM
C. Lebranchu
• Mechanical, thermal & propulsion C. Lebranchu• Launcher interface C. Lebranchu• Electrical systems & EMC G. Rougier• Performance verification & calibration E. Ecale• Dynamics & pointing E. Ecale
• Operations & Database X. Moisson• System datation X. Moisson• Data management & On-board software P. Humbert• AIT & GSE architecture engineering C. Gabilan
• Mechanical engineering F. Vogel• Thermal engineering U. Rauscher
• Electrical, RF & EMC enginnering A. Dyne• Dynamics & pointing enginneering T. Colegrove
Support to ESA for Science & Mission Performance expert: F. Safa
Electrical packageprocurement APM
P. Lelong
GAIA SpacecraftProject ManagerV. Poinsignon
Industrial team build-up
Right from the beginning of phase B2, the Core team is in place to organise the selection of the subcontractors for the complementary activities
Within the Core team, the responsibilities are assigned for the establishment of the rest of the industrial team
The list of items to be subcontracted is defined – more than 80 items
All fields of work are covered– Support tasks, AIT, sub-systems, equipments, software, GSE’s
The method of procurement– Open competition
The selection process– ESA Best Practices
– Confidentiality
– Fairness of competition
The industrial team build-up is a continuous process all along phase B2– Gradual release of ITTs
– Selection of subcontractorsmade by ESA and the spacecraft prime contractor on technical, cost, schedule, risk, and geo-return grounds
At the end of phase B2, the industrial team is complete and at work
Overall development
Development cycles
The specification tree
MRDAIV
requirementsPA
requirementsManagementrequirements
OIRDSGICDvol 1
SGICDvol 2
SRS GDIR
PLM spec E-SVM spec MSVM spec
ROOTSW URD
SYSTEMSW URD
PLM SWURD
AOCSSW URD
MMUSW URD
DMS SWURD
OperabilitySW URD
FPAspec
MPSspec
CPSspec
DSAspec
ESVMeqptspec
MSVMeqpt spec
MPS SWURD
TCS SWURD
FPAeqptspec
PLMeqptspec
CDMS, Power,TTC SW URD
GenericTMTC ICD
PL TCSSW URD
Doors links
Doors links
Doors links
Doors links
Doors links
Level 1 (ESA documents)
Level 2 (Spacecraft and SW URDs approv
Level 2 (Modules - same level as S/C but
Level 3 (Subsystems)
Level 4 (Equipments)
Assembly, Integration and Verification
The overall development covers– Design/ Development/ Manufacturing/ Assembly/ Integration/ Validation
– At unit, subsystem, module and spacecraft level
Almost all project people contribute to verification, to demonstrate that the spacecraft will fulfil its mission and meet the associated performance specifications – System and subsystem engineering teams
– Equipment unit procurement teams
– Product assurance teams
– Assembly, integration and test teams
– Instrument teams, for instrument, spacecraft, and system performance level
Verification can be performed by – Design Review
– Analyses
– Simulations or tests (or any combination of the above)• involving software models or physical development models
Verification by analysis or simulation
Ex: Pointing performances
Ex: Number of transit over the celestial sphere over 5 years
Avionics Model AVM
Mars ExpressAstrium Toulouse,
2001 to 2003
Gaia AVMAll electronic units engineering models on a table for functional tests
Mechanical and electrical integration
Mars ExpressAlenia Turin,
Jan-Sept 2002
Gaia assembly trees
Mechanical environment tests
Mars ExpressSine tests, Intespace, Dec 2002
Acoustic tests, Intespace, Jan 2003
Thermal environment tests, in vacuum chamber
PUMPING COOLING
RECOVERY
Thermal Validation
BalanceThermal
ValidationBalance Heating up Plateau Cooling down Plateau
Depressurise & set-up the initial
condition
TMM transient validation
OPS COLD
TMM Correlation OPS HOT
TMM Correlation Safe Mode
Heater validation.Coldest
Environment.
Set up the TV HOT
environment transient
Functional Tests at high temperature
Set up the TV COLD
environment transient
Functional Tests at low temperature
Return to Ambiant Press.
& Temp.
10130 hPa 10130 hPa CHAMBER PRESSURE < 10-5 hPa < 10-5 hPa < 10-5 hPa < 10-5 hPa < 10-5 hPa < 10-5 hPa < 10-5 hPa < 10-5 hPa
SOLAR FLUX OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
TTA & SA DUMMY Simulated Simulated Simulated Simulated Simulated Simulated Simulated SimulatedTEMPERATURE Not controled solar flux solar flux solar flux solar flux solar flux solar flux solar flux solar flux Not controled
(1280 W/m²) (1400 W/m²) (1280 W/m²) (1280 W/m²) (1430 W/m²) (1430 W/m²) (1100 W/m²) (1100 W/m²)
SVMTEMPERATURE Ambient (20°C) Ambient (20°C)
PROFILE
CONFIGURATION S/C LAM FOM (LGA) SOM (PAA) Specific Specific LAMAOCS SBM IGM (CPS) NM (MPS) thermal conf thermal conf SBM
PDHS OFF ON ON OFF OFF OFFCDU OFF ON OFF OFF
PLM Ambient (20°C) Ambient (20°C)TEMPERATURE
PROFILE-120°C
Specific ISST Specific ISST Specific ISST Specific ISST
OBJECTIVE
OPERATION
PHASE
TITRE
TB
SAFE COLDHOT
PLATEAUCOLD
PLATEAU
TV
Sub Phases
Mars ExpressThermal vacuum
with Sun simulation Intespace, Oct 2002
Gaia spacecraft test set up and
sequence
Gaia Payload Module in cryochamber in Liege
EMC environment tests
Conducted EMC, S/C openedTorino, Aug 2002
Marsis radar antenna Mock up characterisation,Intespace, Nov. 2002
Radiated EMC & RFCFlight configuration,Intespace, Jan 2003
Gaia,RF Auto compatibility
Gaia,/SoyuzRF Compatibility
Physical measurements
Mars ExpressMass, CoG, InertiasIntespace, Jan 2003
Gaia on its horizontal lifting device
Deployment tests
Beagle 2 QM ejection, Intespace, Nov 2002
Gaia DSA deployment ring
Gaia DSA mock up (ESA TDA)
Satelliteunder test
End to EndStimulator
PLMSVM
CDMU + EIU PDHU VPUTRSP/RFDU
PAA
CDUClks
End toend
FPAopticalstimul.
7 SpWSpW 7 SpWTC/TM HK+S
CDUEGSE
RF EGSE
RF
TM
S +
HK
TM S
PLM EGSEn°2
1
End to
end
OpticalstimulEGSE
Video TMHK + S
FPA
UmbilicalEGSE
TM/TC EGSE Trigger
Video TMHK + S
Video TM S
Dynamic FPAsimulator
- Sky simulation - SC motion simulation
Sky sim.files
7 S
pW
Scanning star simulator used for the GAIA FPA Technology Development
Test set up
From star signal acquisition until RF telemetry to ground
End to end functional test
Spacecraft design
Design approachMechanicalPropulsionThermalFunctionalDynamic and controlElectricalCommunicationsSoftwareFDIRTimingData Management
Spacecraft design approach
Although Gaia is unique by essence, the spacecraft design approach remains classical
No universal rules, but guidelines– Analysis and understanding of system requirements
– Split in elementary spacecraft functions
– Identification of critical items
– Reference to past experience
– Identification of system design option to assess (trade off approach)
– Favour the simplest solutions when applicable
– Consider « non technical » constraints in the background
• Cost / Schedule
• Geo return
– Iterative approach
Initial spacecraft sizing
Mission budgetary envelop and political constraints define the potential launcher
– ESA science missions: Soyuz Fregat is the current workhorse
Achievable spacecraft dry masses are deduced from launcher capability and required orbit manoeuvres– Soyuz-Fregat: 2.1 tons in direct insertion toward L2
– Insertion around L2 (Lissajous orbit) • 150 to 200 m/s needed for Gaia
First element to draw out is the instrument
Then preliminary allocation is made for other spacecraft functions
– A first idea of a possible spacecraft configuration is needed as soon as possible.
– It allows to get a first idea on system budgets and critical items
Spacecraft configuration build up
One of the very first activity in spacecraft conception is to draw out a configuration, with:
– An instrumental concept
– Overall shape, size and geometry (thus mass)
– Articulation concept
– Field of view, aerials and appendages • Payload instruments first
• Then antennas, thrusters, solar arrays, attitude sensors
Then a structural concept is issued– Interfacing with launcher (volume, physical connections and load path)
– Supporting the instrument
– Housing all servitude functions
And a 3-D model of the spacecraft pops up with all its elements– Necessary to evaluate mission performances and budgets
Mechanical architecture
Design approach1st step: identification of sizing elements• Support the large instrument
• Support the service electronics, the propulsion systems, the solar arrays
• Compatibility with launcher– Class of launcher defines the allowable volume and mass for the spacecraft
2nd step: Defining a mechanical architecture• Looking for instrument isostatic mounting to avoid distortion
• Looking for symmetry to avoid distortion
• Providing efficient load paths during launch
• Pre-sizing the structure (decoupling 1st eigenfrequencies wrt. launcher)
• Verifying balancing on the launcher
3rd step: specifying mechanical environment for units• Worst case worst place for everybody to initiate the process
• Conditions refined/decreased once accommodation exercise completed
Gaia mechanical architecture
Decoupling payload module/service module
Interface with launcher via a ring and a clamp band system
Central cone as main load path
Central Cone
Propulsion system
Design approach1st step: staging optimisation between launcher and spacecraft
» Gaia: launcher ensures the insertion into transfer orbit to L2
» Lisa Pathfinder: spacecraft/cruise stage composite inserted on a transfer orbit
» Bepi Colombo: multi stage spacecraft for Earth escape, cruise and insertion around Mercury
2nd step: selection of propulsion system• Analyse of orbit manœuvres and associated velocity increments
• Selection of the propulsion techniques» High thrust/medium efficiency (chemical) or low thrust/high efficiency (electrical)
» Cold gas, liquid or solid
» For the liquid system, selection between Hydrazine (Isp 220 s), bipropellant (Isp 300 s) or dual mode
3rd step: Propulsion architecture definition• Tank sizing• Thrusters configuration and capacity (in connection with AOCS)• Pressurisation and isolation circuit definition
4th step: Propulsion thermal control definition
Gaia chemical (NTO/MMH) propulsion system
Thermal architecture
Design approach1st step• Characterisation of the various mission phases
• Characterisation of the space environment through these different phases– Viewing factors wrt. Sun and planets
2nd step• Definition of sink temperatures
• Heat rejection budget for each spacecraft faces through the different phases
3rd step • Internal layout accounted for
• Thermal path definitions (conducted or radiated, no convection)
4th step• Architecture definition, control principle elaboration, material selection
• Radiators, heaters and heating power sizing
• Temperature map prediction
Gaia thermal architecture
DSA stowed and deployed
Functional architecture
Design approach1st step: centralised or decentralised • Weight of tradition (ESA science programs decentralised until Gaia)
• SW flexibility, CPU loads, modes and operations complexity
• Failure tolerance, hot/warm/cold redundancy
• Mass, power constraints
2nd step: looking for heritage• Mars Express: Rosetta, Mars Express, Venus Express, Telecom, Earth observation
3rd step: traffic and link budget establishment• Evaluate volume of data exchanged (on board, with ground)
• Define physical supports (data bus, point to point links)
• List the interfaces, standardise as far as possible
4th step: establish performance budgets• Define protocols• Establish CPU, memory and bus occupation budgets
Gaia functional architecture
CDU
Solar arrays
DeployableSunshieldAssembly
Chemical propulsion
STRE
Phased ArrayAntenna
SSPA
SSPA
SSPA
PowerConditioning
&Distribution
Unit
Battery
HeatersThermalsensors
VPU
VPU
VPU
VPU
VPU
VPU
VPU
VPU
VPU
VPU
PayloadData
HandlingUnit
28 Vtousers
VPU
VPU
VPU
VPU
VPU
VPU
VPU
Focal Plane Assembly
Payload Module
Electrical SVM
Mechanical SVM
Micropropulsion
ClockDistribution
Unit
SVM MIL-STD 1553B bus
Payload MIL-STD 1553 bus
SpW
SpW
SpW
SpW
SpW
SpW
SpW
SpW SpW
Tim
ing
Tim
ing
Pyropulses
STRE
I/O’s
STRESTRE
MicroPropuslionAssembly
BAM & WFSsource
electronics
M2 mirrorsmechanism
drive electronics
BasicAngle
Monitor
WaveFront
Sensor
M2mech
M’2mech
BAM & WFSsource
electronics
M2 mirrorsmechanism
drive electronics
ElectricalInterface
Unit
GyrosGyros
TRSP
X-Rx
X-Tx
TransponderTransponder
X-Rx
X-Tx
FineSun
Sensor
FineSun
Sensor
FineSun
Sensor
StarTracker
Gyros
STRE
MicroPropulsion
Elect.
LVDS
Structure SVM
SVM ThermalPassive Hardware
Thermal tent
Structure optical assembly
PLM Thermal Passive Hardware
Launch bipods
PkW
Control andData
ManagementUnit
Low GainAntennasystem
Electrical SVM units
CDMS units
AOCS units
Electrical power units
TT&C units
Redundant unit
PLM units
PLM units on PLM
LEGEND
Internally redunded unit
PLM units on SVM
Mechanical SVM units
Micropropulsion units
Chemical propulsion units
Solar arrays
DSA, thermal items
Links
Timing & datation
SVM MIL-STD 1553 bus
PLM MIL-STD 1553 bus
Space Wire/Packet Wire
RF signal
Dynamic and control
Design approach1st step• Considering the required attitude profiles and disturbing torque assessments:
– Selection of control concept: passive or active, spinned or 3 axis controlled
– Gaia: slow rotation with precession: 3 axes control
• Considering the spacecraft configuration and the disturbing torque assessment– Selection of the control (thrusters, micro thrusters, reaction wheels, control momentum gyros…)
– Gaia: ultimate stability required: micro thrusters
2nd step• Selection of sensors• Actuator sizing and control bandwidth definition• Gaia
– Hybridizing instrument (stability) and star tracker (inertial attitude) in normal mode
– Fine sun sensor and gyros for initial acquisition and safe mode
– Hybridizing high accuracy gyros/ start tracker for intermediate mode.
3rd step• AOCS modes definition, associated control laws• Definition of failure modes and associated recovery procedures• Pointing budget elaboration, resources budgets (propellant, processing…)
Gaia AOCS
Gyros
Astro
Sun sensors
Star trackers
Micro propulsionChemical propulsion
Gaia AOCS
Electrical architecture
Design approach1st step: preliminary resource sizing• Estimate power requirement per phase
• Battery sizing» Energy needs (launch phase, eclipses, manœuvres, peak power….)
» Select battery technology (function of cycling, required capacity)
• Solar array sizing» Considering power profiles, battery charging, attitude wrt. Sun
» Select solar cell technology (deep space probe or not, temperature range)
2nd step: selection of a power topology• Conditioning and regulation principle
• Bus voltages
• Line protection
3rd step• Define electrical interfaces• Establish power budgets
Gaia power system
Li-ion battery
Solar array
Power Conditioning and Distribution Unit
• Triple Junction GaAs cells on solar arrays• Lithium ion batteries based on standard Sony cells• 28 V regulated and maximum power point tracker to minimise instability
CommunicationsDesign approach
1st step: Selection of frequency • Imposed by regulation agency (ITU),
• Function of mission type and orbit
• Gaia from L2: X band (8 GHz) TM/TC , 10 MHz max TM bandwidth
2nd step; Definition of communication scenarios• Gaia:
» Cebreros 35 m ESA station 8 hour/day outside galactic plane scans
» Cebreros and New Norcia 35 m ESA stations during galactic plane scans
3rd step: resources sizing (iterative)• Ground/spacecraft link capabilities: preliminary link budgets as function of distance, antenna
geometry, memory capability, data availability requirement, protocol
• Antenna, amplifiers, transponders selection in iteration with spacecraft configuration, power resources and thermal control capabilities
4th step: on board architecture definition: • Interconnection schemes
• Redundancy, reconfiguration,
• Detailed link budgets, system budgets
Gaia Communication system
Choked horn LGA
PAA radiating cone
Phased Array Antenna electronics
X band transponder
- X LGA-1
RF Splitter 2:7
PAA
TC
TM
TRSP-1
RTDiscreteTM/TC
X-BandRx
X-BandTx
RTDiscreteTM/TC
TC
TM
TRSP-2
X-BandRx
X-BandTx
TT&C
RT-A
DiscreteTM/TC
RT-B
DC/DCCV B
DC/DCCV A
EPIC A
10 Ms/s10Ms/s
Discrete
- X LGA-2
DC/DCCV
DC/DCCV
TM/TC
28V
+ X LGA
RFswitch
RFswitch
DiscreteTM/TC
SHPHK TM
BM 1
SSPA Qua
dri-M
odu
le 1
BM 2
SSPA Quad
ri-M
odu
le 2
BM 3
SSPA Qua
dri-M
odule 3
BM 4
SSPA Qua
dri-M
odu
le 4
BM 5
SSPA Q
uadri-M
odule 5
BM 6
SSPA Quad
ri-M
odu
le 6
BM 7
SSPA Quad
ri-M
odu
le 7
EPIC B
Controlfunction
B
Controlfunction
A
4ks/s
C
C
C
C
CC
CC
4ks/s
28V28V 28V
DiscreteTM/TC
DiscreteTM/TC
DiscreteTM/TC
SVM MIL-STD-1553B Bus N
SVM MIL-STD-1553B Bus R
Central software
In charge of spacecraft managementHW / SW interface, data acquisition and processing
AOCSSensors, Actuators, Control laws, mode management
Data managementData handling (services, mailboxes, priorities, events, interruptions,…)
Bus management (PLM and SVM 1553 buses, SpaceWire bus)
Mission Time Line
TM generation, TC acknowledge and processing, tasks scheduling
Dump / Patch
ThermalThermal control loops management
ElectricalLCL management, Pyro sequences
CommunicationsEarth ephemeris for PAA beam orientation
Monitoring Detect the failure
Isolate the suspected units
Reconfigure on safe configurations
Gaia software layered architecture
Failure Detection Isolation & Recovery
Hierarchical FDIR: the spacecraft detects autonomously on board failures and tries to continue its mission or place itself in safe mode through a gradual recovery process.
Groundcommands
Unf
ore
see
n e
ven
t
Level1
OK
OK
OK
OK
NO
K
NO
K
NO
K
NO
K
Redundantprocessor & units
Nominal Processor& redundant units
Redundant PM& nominal units
Last chanceconfiguration
Science continued
SpacecraftSafe Mode
(SSM):mission
interrupted
On boardMission Time Line
Spacecrafttelemetry
Gro
und
sta
tion
pa
ss
Nominal autonomy Nominal autonomyAutonomous hierarchical FDIR
Gro
und
sta
tion
pa
ss
Gro
und
sta
tion
pa
ss
Localreconfiguration
Level2
Level3
Level4
Specific on Gaia: Timing architecture
PPSRegister
OBTRegister
OBT
XO1553 I/F
SynchroUnit
PpsTo
CDMU
SCET
PEM 1 PEM #7
Time CodeGenerator
VPU #i
IM #i
TDI1
TDI2
TDI3
20 MHz
OBS
Latch signal
Time Strobe
TFG
MasterClock
Delivery of TDI and master clocks to the video chain, all of them being derived from the Hydrogen Maser (RACM)
Time correlation with ground time scale (UTC) thanks to Time strobe generated by the CDMU
PAA
Science data management architecture
A long way from Focal Plane to SOC and DPAC…
Kourou, French Guyana
Baikonur, Kazakhstan
Launch Campaign
Departure to launch site
The S/C shall fit in its container that shall fit within Antonov airplane
Final preparation
Propellant fueling
Installation on launcher, encapsulation, transport
Soyouz in Kourou(From Arianespace documents)
Babysitting on launch pad
Launch
And spacecraft operations are starting in ESOC
Gaia configuration: 1998
Science Mission Requirements
Two Astro viewing directions
Hipparcos scan law, sun-spin axis angle ξ > 45 deg,
Scan rate > 60 arcsec/s, precession period fixed @ 70 days
Astro detector operating temperature < 170 K
Astrometric accuracy ~ 10 µas for V > 15, limiting magnitude V ~ 20,
RVS spectral range 849 nm – 874 nm, resolution > 0.075 nm with a goal at 0.0375 nm per pixel
5 spectral broadband filters in astro fields (Broadband Photometer), 11 Medium Band filters in RVS telescope field (Medium Band Photometer)
Lissajous orbit about L2No eclipse for 5-6 years
Sun-Satellite-Earth angle < 10°
SUNSatelliteSpin axis
55°
Astrometric InstrumentLine of Sight 1
Astrometric InstrumentLine of Sight 2
Precession of the spinaxis in 72 days
GAIA
ConsecutiveGreat Circles
Basic Angle
Gaia configuration : 1998
Sunshield φ 9.5MSolar array(Rear face MLI covered) Spectrometric instrument
entrance aperture
Astrometric instrumentsentrance aperture
TT&C antenna
Star sensor
PLM Thermal cover
Optical cover
& baffle
Sunshield φ 9.5MSolar array(Rear face MLI covered) Spectrometric instrument
entrance aperture
Astrometric instrumentsentrance aperture
TT&C antenna
Star sensor
PLM Thermal cover
Optical cover
& baffle
Science telemetry
Antenna
TT&C antenna
10 N thruster
Solar array
Sunshield φ 9.5M
Propulsion subsystem
Science telemetry
Antenna
TT&C antenna
10 N thruster
Solar arraySolar array
Sunshield φ 9.5M
Propulsion subsystem
Satellite dry mass (incl. margin) = 2035 kgPropellant mass = 1010 kgTotal launch mass with margins = 3150 kgSatellite power budget (observation) = 2475 WLauncher: Ariane V
General Approach
Required performance
Optical quality: overall WFE < λ/14 rms
Basic angle variations/monitoring over 1 revolution (3 hours): ~ 1 µas
Minimum active control & mechanisms by taking full benefit of L2 orbit stable environment:
Sun shield/solar panels protects the payload from sun radiation.
Radiative & conductive de-coupling from SVM
Athermal design, by using of a single material, homogeneous & isotropic, for optics and major structural parts,
No mechanism in nm or pm range
Monolithic mirrors and refocusing mechanism (few µm accuracy).
Basic angle monitoring in orbit
Zerodur: Good optical properties, very low CTE @ RT (degrades in cold), but poor structural properties & lightweighting capability,
CFRP: Good structural properties & lightweighting capability but poor optical properties,
C-C (Aérospatiale data): Good structural properties, very low CTE but poor optical properties & low thermal conductivity
SiC: Good structural properties, very good lightweighting capability, low CTE (improves in cold, 0.5 @ 100 K) & good optical properties. Selected for Gaia design.
Parameter Zerodur Carbon-Carbon (C-C) Silicon Carbide (SiC) CFRPYoung Modulus E (GPa) 90 60 420 117Density ρ (g/cm3) 2.53 1.56 3.15 1.65Ultimate tens. strength (MPa) 20 190 350 240CTE α (µm/m/K) 0.05 -0.1 2 0.46Thermal conductivity λ (W/m/K) 1.5 7 190 37Lightweighting ratio E/ρ 35 38 130 71Thermal distortion ratio α/λ (x 100) 3.4 1.4 1 1Polishing yes no yes noCoating yes yes yes yes
Note: Values given at room temperature
Material selection
SiC Technology Maturity
Demonstrator telescopeΦ200 mm, WFE < 20 nm,Tested –100°C to +60°C
OSIRIS TMA telescope, 12 kgΦ 90 mm, WFE < 20 nm,
Trange -100°C to 70°C, will fly on Rosetta
Sofia secondary reflector, 1.9 kgΦ 352 mm, WFE < 50 nm
Rocsat2 telescope, 75 kgΦ 630 mm, WFE < 40 nm
Herschel demonstration reflectorΦ 1350 mm, made of 9 brazed segments
WFE < 4 µm, tested @ 110 K
Herschel Full scale petal, 1500 mm
SiC Technology Maturity
Herschel SiC telescope diameter is 3.5 m, mass 300 kg
Reflector and telescope structure are made of SiC
Operating temperature ~ 80 K
Delivery to ESA early 2005
All facilities used for Herschel are applicable to Gaia
Major features of the study design
Use of large aperture independent telescopes. No need for high accuracy mechanisms (nanometric positioning accuracy required for the case of an interferometer)
Common telescope for ARVI & narrow-band photometry (Arvi Photometer Telescope).
Feasible detectors, pixel dimensions > 9 µm,
Short term basic angle stability ensured by the use of Silicon Carbide for both the reflectors and the structure,
Implementation of a device capable of monitoring basic angle variations with an accuracy compatible with Gaia needs
ARVI (Auxiliary Radial Velocity Instrument) located on the symmetry axis
Design compatible with Ariane V launcher and ESA assigned cornerstone budget
Optical assembly configuration
ASTRO-1 secondary mirror
ASTRO-2 primary mirror
Basic anglemonitoring device
ASTRO-1 focal plane
ASTRO-1 primary mirror ASTRO-1 tertiary mirror
Optical assembly configuration
Astro Beam (1/4)
Astro Beam (2/4)
Astro Beam (3/4)
Astro Beam (4/4)
SPECTRO Tertiary Mirror
SPECTRO Secondary Mirror
SPECTRO Focal Plane
SPECTRO Primary Mirror
APT instrument
APT Beam (1/4)
APT Beam (2/4)
APT Beam (3/4)
APT Beam (4/4)
Dimensions compatible with Ariane 5 fairing
Payload accommodation
Optical bench design
The design of the torus is established in order to ease manufacturing and AIT activities
– the internal reinforcement will be chosen with respect to the equipment location in order to decrease the mass
150 mm300 mm
thickness 5 mm
GAIA Concept& Technology Study
Focal Plane & Electronics Accommodation
The Focal Plane Units are mounted on the PLM torus with a specific thermal insulation
The Video Processing Units are mounted on the SVM structure
FP active face
MLI +
permaglass wachers
MLI
torus
radiator
SPACEPLM CAVITY
SVM closure panel
torus
VPU
support +
radiator
Secondary structure design
The shape of the tent is optimised in order to stay under the protection of the sun shield and it has no connection with the PLM to improve stability
MLI
carbon truss
The tent is made of carbon truss supporting MLI on both faces
GAIA mechanical model
GAIA mechanical analysis
First lateral mode First axial mode
Electrical Architecture
FPAASTRO-1
FPASPECTRO
FPAASTRO-2
Video Processing Units (VPU)ASTRO-1
Video Processing Unit (VPU)RVS / NBP
Video Processing Units (VPU)ASTRO-2
Payload Data
Handling Elec.
(PDHE)
Solid State Recorder
(SSR)
High Rate Telemetry Formatter (HRTF)
Science TM Comm's
Link
PowerDistrib. Unit
Thermal Control & Mechan. Drive Elec
Central Data Management Unit
(CDMU)
Syncro /Time tag
PLM SVM
Science Data Acquisition / Processing / Transmission
SVM General Services
Payload equipment
Data
Data
Data
Comd / Contl Bus(1553, OBDH, ...)
1
© Astrium76
Gaia Configuration : 2002
PLM
SVM
Sunshield
PLM
SVM
Sunshield
Gaia configuration : 2002
PLM
SVM
Sunshield
PLM
SVM
Sunshield
Satellite dry mass (incl. margin) = 1150 kgPropellant mass = 250 kgTotal launch mass with margins = 1500 kgSatellite power budget (observation) = 1500 WLauncher: Soyuz Fregat
2002 Study concept and objectives
Study requirements & objectives, mainly to reduce the overall cost :– Soyuz-Fregat evaluation against Ariane 5 Reduce mass and size– Re-open basic trade-offs (Solar array / sunshield; payload telemetry antenna)– Update and Optimize of the development & validation approach– Update the technology planning– Optimize the industrial management approach
Study assumptions :– Same science requirements as for the Concept & Technology Study of 1998;– Re-use of up-to-date service modules strongly recommended– Transfer to L2 performed by launcher
GENERAL PARAMETERS
Previous Design New Design
Observing time L L = 4 years L = 5 years
Scan rate ω 120 arcsec/s 60 arcsec/s
Precession period ωp 70 days 70 days
Rotation axis 55° from sun direction 50° +/- 0.1° from sun
direction
Star population V < 20
Average value
« Worst case »
Ns = 14300 stars/deg²
155 000 stars/deg²
Same assumptions
Total number of observed stars ~ 1 billion ~ 1 billion
2002 Payload Optimisation
Reduce mass and size for being compatible with Soyouz launcher
Total launch mass ~ 2270 kg (A5) : mass objective < 1500 kg ( - 34%)
Reduce the PLM mass ~ 900 kg:Astro focal plane assemblies ~ 168 kg (with video electronics)
mass decrease obtained by reducing the number of CCDs
Optics with their mounts ~ 270 kg :
mass decrease is obtained by reducing the reflector sizes
Structure ~ 290 kg
structure mass decrease is a consequence of size and supported mass reduction
Mass reduction objective is in conflict with accuracy requirement.
Design improvement is mandatory for Soyouz compatibility.
Reduce overall complexity and cost– Try to harmonise CCD definitions
– Minimise hardware tests
– Suppression of mechanisms whenever possible
2002 Design Features
Astrometric Instrument– Superimpose the two focal planes, by making use of a focal plane combiner
located close to the exit pupil
– Increase the overall optical path length for practically suppressing optical distortion
– Enlarge CCDs along scan (~ 60 mm x 45 mm)
– Passive cooling of the FPA detectors down to 160 K – 170 K (radiation)
Spectrometric Instrument– Along scan dispersion for RVS
– Suppression of RVS mechanism
– RVS spectral resolution improved by a factor 2
– Medium Band Photometry improved
2002 Astrometric Instrument Configuration
M1
M2
M3
M4(1/2 focal plane
combiner)
M5, M6(common reflectors)
Astro focal plane
FPA radiator
6 mirrors in totalM4, M5 and M6 connected or common to both pathsFocal plane common to both paths
2002 Spectrometer baseline
Along scan disp. - Horizontal telescope Scale: 0.10 AsF 11-Mar-02
255.10 MM
Scan axis
Needs more optimisation to :Try to reduce diameters / mass / number of lenses
Get more realistic air gaps and lens thicknesses
M1
M2
RVS – MBP not shown
M3
13 lenses for the RTVS optic
2002 RVS Telescope accommodation
M1M2
MBP & RVSM3
2002 PLM mechanical analyses
A Finite Element Model of the PLM is constructed for a preliminary verification of the mechanical design
2002 FEM results: PLM eigenfrequencies
1st mode: f > 31 Hz (lateral) 1st axial mode (local): f = 54.5 Hz (lateral)
Frequency requirements on PLMf > 20 Hz, in lateral
f > 45 Hz, in longitudinal
Frequency requirements are met with a good margin
2002 FEM results: stress analysis
Stress levels are compatible with silicon carbide strength
Stress distribution 20g axial
Stress distribution 15g lateral
Stress analysis has been made for the following quasi static loads:
20 g in longitudinal direction
15 g in lateral direction.
PLM / SVM mechanical interface
The upper floor of SVM is a stiff and stable plate with following functions:
Support the in-plane forces due to the iso-static device of the optical bench
Transmit the lateral loads to the SVM central tube
Support the PLM thermal tent
Offer a high stability during the 6h period• No dissipating equipment on this plate• Thermal insulation from SVM and PLM• Stable CFRP structure
Finite Element Model
Rough model : used for a first estimate of stiffness and strength
Detailed model : used to analyse the global satellite behaviour
Modal analysis results
Lateral mode Y
Axial mode X
Lateral mode Z
Modal analysis results
Lateral mode3 Y=27.26 Hz
Lateral mode4 Z=27.56 Hz
Recommended technology developments
The sunshield TRP shall be oriented towards a dedicated system – without solar array – and assess the feasibility of deployment and its compatibility with the shield cover itself
The FPA electronics and video processing units must be studied on technical and industrial points of view. A dedicated TRP is recommended on these subjects.
The CCDs
The Micro propulsion technology selection
3
© Astrium92
Gaia configuration: 2005
Satellite dry mass (incl. margin) = 1400 kgPropellant mass (incl. Cold gas) = 280 kgTotal launch mass with margins = 1830 kgSatellite power budget (observation) = 1700 WLauncher: Soyuz Fregat
Gaia configuration: 2005
Key figures and order of magnitude
Primary mirrors: 1.45 m x 0.5 m
Focal length: 35 m
Pixel: 59 x 177 mas (10 μas 1/6000 pixel)
1 μas rotation M1 < 10 picometers at the edge
Focal plane: 420 x 850 mm
About 100 CCD, ~ 1 Gpixel
Star on CCD: mean: 150, peak: 36000 (magnitude 20)
Stellar flux: 20 000 e-/s @ V=15 200 e-/s @ V=20
Sample datation accuracy: 15 ns
Tore (3 m dia) thermal stability required some tens of μK
Rate measurement error < 0,9 mas/s
Rate pointing error < 5 mas
Attitude High Frequency Disturbance < 3.4 μas
2005 PLM design
M1
M3
M2
Common FPA
Common folding mirrors
M1
M3
M2
M1
M3
M2
M4 M’4
2 Three Mirror Anastigmat telescopes M1-M3
Intermediate image used for field discrimination
Beam combiner at their exit pupil => common FPA
Full silicon carbide architecture
Passive thermal design
Decoupling by release of launch bipods
2005 PLM design
RVSdetectors
Red & blue photometerdetectors
Astrometricfield
Sky mapper
BAM & WFS
M4/M’4beam combiner
Photometerprisms
RVS gratingand afocal
field corrector
M5 & M6fold mirrors
RVSdetectors
Red & blue photometerdetectors
Astrometricfield
Sky mapper
BAM & WFS
M4/M’4beam combiner
Photometerprisms
RVS gratingand afocal
field corrector
M5 & M6fold mirrors
Focal Plane Assembly
A cold part at 160K for limiting CCD sensitivity to radiations
A warm part for electronics
Bipods for mechanical mounting & thermal decoupling wrt optical bench
Photometer prisms
CCD radiator& shielding
Electronics radiatorFPA bipods
ElectronicsRadial VelocitySpectrometer CCDs
Astro FieldCCDs
Blue & RedPhotometer
CCDs
Star MapperCCDs
WFSOptics& CCD
BAM CCD
0.4
20
m
0.930 m
row 1
row 2
row 3
row 4
row 5
row 6
row 7
WF
S2
AF
1
AF
2
AF
3
AF
4
AF
5
AF
6
AF
7
AF
8
AF
9
BP
AS
M1
AS
M2
RP
WF
S1
BA
M-N
BA
M-R
RV
S1
RV
S2
RV
S3
Service Module Design
3
© Astrium98
Gaia Configuration: 2007
Gaia configuration evolution: 2007
Satellite dry mass (incl. margin) = 1620 kgPropellant mass (incl cold gas) = 350 kgTotal launch mass with margins = 2050 kgSatellite power budget (observatiuon) = 1750 WLauncher: Soyuz Fregat
Gaia: key figures and order of magnitude
Primary mirrors: 1.45 m x 0.5 m
Focal length: 35 m
Pixel: 59 x 177 mas (10 μas 1/6000 pixel)
1 μas rotation M1 < 10 picometers at the edge
Focal plane: 420 x 850 mm
About 100 CCD, ~ 1 Gpixel
Star on CCD: mean: 150, peak: 36000 (magnitude 20)
Stellar flux: 20 000 e-/s @ V=15 200 e-/s @ V=20
Sample datation accuracy: 50 ns
Tore (3 m diameter) thermal stability required some tens of μK
Rate measurement error < 0,9 mas/s
Rate pointing error < 5 mas
Attitude High Frequency Disturbance < 3.4 μas
S/C launch mass 2.1 tons
Solar Array capability 1.9 kW
Mass memory capability 1 Tb
S/C Height 3 m
Deployed Sunshield ø = 10 m
The solar array has fixed panels and deployed panels mounted on the sunshield
The CFRP SVM structure is mainly made of lower & upper floors, a central tube including the LV/IF ring, radial panels and a DSA ring
Bi-propellant propulsion system with 8 x 10 N thrusters for orbit correction
Cold gas micro-propulsion to perform stable attitude control
[1μN – 500μN] thrust range
The mechanical SVM
The harness provides electrical connection between units for power and data management
Thermal Tent Structure (TTS)
Thermal Tent Hardware (TTW)
Deployable Sunshield Assembly (DSA)
Solar Arrays
Structure
Chemical Propulsion System (CPS)
Micro Propulsion System (MPS)
Harness
The thermal tent provides a stable thermal environment and protects against micro-meteoroids ; it has large cut-outs for the instruments FoV and the FPA
The 10 m dia. sunshield is deployed in orbit to keep the PLM in the shade of the sun ; it has to be very flat and uniform, with an overall 0.2 deg flatness requirement
The electrical SVM
The electronic units are accommodated orthoradially
in the SVM cavitiesVery stable power dissipation and avoidance of conductive thermal paths minimises thermoelastic
distortion
AOCS3-axis controlStar trackers/gyro/sun sensorsASTRO instrument in the loop for accurate pointingThrusters and micro-thrusters for attitude control
X-band TT&CThree omni directional LGAPhased Array Antenna with up to 28 SSPA
– No mobile parts, electronically steered beam– TM only, 4.8 to 8.5 Mbps
Two X band TRSP
Power73 Ah Lithium batteryPower conditioning and distribution unit
– 28 V regulated main bus– MPPT regulation of 1.9 kW solar
arrays– Protected power lines to users
Data managementCommand & data management unit
– ERC 32 processor (N+R)– 8 Gb memory for mission management
Electrical Interface Unit– I/O customised with SVM and PLM units
The PLM
All SiC structure and mirrors for the optical bench, very high thermo-mechanical stability required for TDI and basic angle
A large focal plane with ~ 1 billion pixels.CCD passively cooled to 165 K
PLM electronic units accommodated in the SVM (PDHU, VPU, CDU)
Payload configuration
Torus design
FPA design
Satellite configuration evolution summary
A priori very different, but in fact implementing comparable principle
Thank you
Xavier [email protected]