Southwest LRT Project Craig Lamothe, AICP Senior Project Manager 2011 MN State Planning Conference September 29, 2011

Transcript of Southwest LRT Project - Planners Conference Light Rail... · Southwest LRT Project Craig Lamothe,...

Southwest LRT Project

Craig Lamothe, AICP

Senior Project Manager

2011 MN State Planning Conference

September 29, 2011

1) Twin Cities Transit System Profile

2) Previous Regional New Starts Projects

a) Hiawatha LRT

b) Northstar Commuter Rail

c) Central Corridor LRT

3) Federal New Starts Program Primer

4) Southwest LRT Project

a) Alternative Analysis Phase Recap

b) Preliminary Engineering Phase Preview

2

Today’s Topics

3

Twin Cities Ridership

80

82

84

86

88

90

92

94

96

2006 2007 2008 2009 2010

Mil

lio

ns

4

Metro Transit Ridership (2010)

Express9,243,906

Suburban Local

1,570,446

Local56,068,009

LRT10,455,860

Commuter Rail710,426

5

Peer Comparison: 2009 System Ridership

6

Peer Comparison: Ridership per Capita

0

20

40

60

80

100

120

Rid

es p

er

Cap

ita

• Buses

– Artic Buses: 163

– Standard 40’ Buses: 735

– Hybrid Buses: 97

• Light Rail

– 27 cars

• Commuter Rail

– 18 Passenger Cars

– 6 Locomotives

7

Metro Transit Fleet

8

2030 Transitway System

• 12 miles

• 19 Stations

• Project Cost: $715.3 million

• 2011 Annual Operating Budget:

$26.7 million

• Avg. Weekday Ridership (Aug ‘11):

35,069

• 2010 Total Annual Ridership:

10,500,000

9

Hiawatha LRT (Blue Line)

• 40 miles

• 6 stations

• Project Cost: $320 million

• 2011 Annual Operating Budget:

$17.0 million

• Avg. Weekday Ridership (Aug. ‘11)

2,696

• 2010 Total Annual Ridership:

710,400

10

Northstar Commuter Rail

• 11 miles

• 18 new stations

• $957 million

• 2015 Est. Operating

budget: $25.4 million

• Projected weekday

ridership: Over 40,000

by 2030

11

Central Corridor LRT (Green Line)

12

New Starts Overview

Full Funding

Grant Agreement

Alternatives Analysis

Final DesignCommitment of Non-Federal Funding,

Construction Plans, ROW Acquisition,

Before-After Data Collection Plan,

FTA Evaluation for FFGA,

Begin Negotiations

Pro

jMgm

t O

ver-

sig

ht

Construction

Preliminary EngineeringComplete NEPA Process

Refinement of Financial Plan

Select LPA,

MPO Action

PMP

FTA Decision on entry

into PE

FTA Decision

on entry into FD

Systems Planning

• Evaluate the mode and alignment options for

a particular corridor

• Benefits, costs and impacts of transportation

options

• Complete with the selection of the locally

preferred alternative (LPA) and adoption of

the LPA into the region’s long range

transportation plan

13

Alternatives Analysis (AA) Phase

• Consider design options to refine LPA and

complete the NEPA process

• Hone the estimates of project cost, benefits,

impacts and schedule

• Finalize management plans

• Demonstrate technical capabilities to

develop the project

• Commit local funding sources

14

Preliminary Engineering (PE) Phase

• Prepare final construction plans, contract

packages, detailed specifications and bid

documents

15

Final Design (FD) Phase

16

New Starts Evaluation Process

17

Peer “New Starts” Projects

Orlando, FLHonolulu, HI

New York, NY

St. Paul- MinneapolisP

N

Pending FFGA

New FFGA

E Existing FFGAJuly 2011 Status

San Francisco

Houston, TX

Denver, CO

Salt Lake City, UT

Dallas, TX

Seattle, WA

E

EEN. Virginia-Dulles, VA

E

E

N

P

Hartford, CT

E

E

P

Sacramento, CA

P

P

San Jose, CA

N

N Portland, OR

P

P

E

E

E

18

Peer “New Starts” PE Projects

Vancouver, WA

Portland, OR

Sacramento, CA

Los Angeles, CA

Los Angeles, CA

Honolulu, HIHouston, TX

Charlotte, NC

Pawtucket, RI

San Jose, CA

Salt Lake City, UT

Minneapolis,- St. Paul, MN

September 2011 Status

Alternatives Analysis

LPA Selected

LPA Amended into TPP

MC requests to Enter PE

FTA approves Entry into PE

19

SWLRT: Historical Timeline

2005 - 2009

Nov. 4, 2009

May 26, 2010

Aug. 31, 2010

Sept. 2, 2011

• Transit Technology Review

• Identification of Alignments and Stations

• Initial Set of Alternatives

– No Build

– Enhanced Bus

– Build Alternatives (BRT & LRT)

20

SWLRT: AA Phase

• 15 miles

• 17 new stations

• Est. Project Cost:

$1.25 billion

21

SWLRT: Locally Preferred Alternative (LPA)

22

SWLRT: Project Budget

30%

10%

10%

50%CTIB

HCRRA

State

FTA

$30.6M in Local Funds Committed to Date

$625 million

$375 million

$125 million

$125 million

23

SWLRT: Anticipated Schedule

Preliminary Engineering

Final Design

Construction

Revenue Operations

2011 - 2013

2013 - 2014

2014 - 2017

2018

• Procurement of Engineering Services

• Complete 30% Design

• Procurement of Environmental Services

• Complete Final Environmental Impact Statement

• Establishment of a Project Office

• Secure Municipal Consent from 5 Cities

24

SWLRT: PE Phase

http://www.metrocouncil.org/transportation/SW/SouthwestLRT.htm

• Mark Fuhrmann, Program Director – New Starts Rail Projects

651-602-1942

[email protected]

• Chris Weyer, Project Director - Southwest LRT

651-602-1932

[email protected]

For Further Information and Updates