SOUTHERN REGIONAL POWER COMMITTEE - Karnataka · third line which would evacuate power from...
Transcript of SOUTHERN REGIONAL POWER COMMITTEE - Karnataka · third line which would evacuate power from...
Minutes of the 31st SRPC Meeting held on 25th February 2017
CONTENTS
1. INTRODUCTION............................................................................................................................................... 4
2. CONFIRMATION OF THE MINUTES OF THE 30th SRPC MEETING .................................................................... 7
3. MEMBERSHIP TO RPC ..................................................................................................................................... 7
4. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT (PROTECTION)
AMENDMENT RULES, 2015............................................................................................................................. 8
5. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION – TASK FORCE ...................................................... 10
6. FLEXIBILITY IN UTILIZATION OF DOMESTIC COAL FOR REDUCING COST OF POWER GENERATION ............ 11
7 ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY ..................................................................... 12
8 CONGESTION RELATED ISSUES ..................................................................................................................... 14
9 COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014 – IN RESPECT OF LVRT AND
OTHER PROVISIONS OF CEA/CERC REGULATIONS ....................................................................................... 17
10 INCLUSION OF DRAWAL OF MAHE IN REA ................................................................................................... 18
11 ISSUES IN RESPECT OF NPCIL/BHAVINI ......................................................................................................... 19
12 LOW VOLTAGES ............................................................................................................................................ 24
13 RELIABLE ALTERNATE AUXILIARY SUPPLY AT HVDC, BHADRAVATHI ........................................................... 24
14 DC FOR NTECL, VALLUR DURING VARDHA CYCLONE ................................................................................... 25
15 OUTAGE PLAN OF CENTRAL GENERATING STATIONS .................................................................................. 26
16 EXPERIENCES FROM VARDAH CYCLONE ....................................................................................................... 29
17 STATUS OF GENERATION IN ISGS ................................................................................................................. 31
18 REVIEW OF ULDC / SCADA/COMMUNICATION ............................................................................................ 33
19 URTDSM (PMU) PROJECT IN SOUTHERN REGION ........................................................................................ 36
20 SCHEDULING OF WIND & SOLAR GENERATING PROJECTS HAVING CAPACITY OF 500 MW AND ABOVE ... 39
21 ISSUES IN RESPECT OF CONNECTIVITY/LTA/LILO/INFIRM POWER ............................................................... 40
22 TTC/ATC ........................................................................................................................................................ 41
23 UPCOMING TRANSMISSION SYSTEM ........................................................................................................... 47
24 UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH TRANSMISSION NETWORK ........ 60
25 NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP ................................................................ 65
26 NEW PROJECTS OF STATE SECTOR & IPP ...................................................................................................... 67
27 METHODOLOGY FOR CERTIFICATION OF INTRA-STATE TRANSMISSION LINE ............................................. 68
28 EMERGENCY RESTORATION SYSTEM (ERS) .................................................................................................. 69
29 PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR .............................................................. 71
30 OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS ....................................................... 77
Minutes of the 31st SRPC Meeting held on 25th February 2017
31 NON-AVAILING OF OCC APPROVED SHUTDOWN ......................................................................................... 78
32 GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS .................................................................. 79
33 STATUS OF PHASE I AND PHASE II OF PROTECTION AUDIT RECOMMENDATIONS ...................................... 80
34 SPARE ICT AND REACTOR PLACEMENT AND USAGE PROCEDURE ............................................................... 81
35 IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION .............................................................................. 81
36 SHARING OF TRANSMISSION CHARGES OF TRANSMISSION ASSETS OF NATIONAL IMPORTANCE ............. 94
37 THOROUGH REVIEW OF ALL THE DRAWAL POINTS OF STATES FOR DRAWAL COMPUTATIONS ................. 95
38 IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT SYSTEM (PMS) FOR SOUTHERN
REGION ......................................................................................................................................................... 96
39 POWER SYSTEM ANALYSIS GROUP (PSAG-17) MEETING HELD ON 3rd & 4th OCTOBER 2016 AT NTPC-
SIMHADRI STPS, KALPAKA SS AND HNPCL TPS ............................................................................................. 96
40 AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE TRANSMISSION LINES OF SOUTHERN
REGION ......................................................................................................................................................... 97
41 STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY RESOURCES INTO THE GRID ......... 98
42 SPECIAL MEETING WITH M/S KPCL HELD ON 27.10.2016 AT SRPC, BENGALURU ....................................... 98
43 IMPLEMENTATION OF LINE DIFFERENTIAL PROTECTION (LDP) ................................................................... 99
44 PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS ..................................................... 100
45 7th MEETING OF NATIONAL RELIABILITY COUNCIL FOR ELECTRICITY HELD ON 07.12.2016 AT NRPC, NEW
DELHI ........................................................................................................................................................... 100
46 SRPC REPORT ON “EFFECT OF DELAYED CLEARANCE OF FAULT ON TRANSMISSION SYSTEM” ................. 100
47 PROTECTION AUDIT OF 400 KV ALUNDUR SS OF PGCIL (SR-II) AND 230 KV ALUNDUR S/S OF TANTRANSCO101
48 SPECIAL MEETING ON NEYVELI GRID DISTURBANCE .................................................................................. 101
49 PENDING IMPLEMENTATION OF RECOMMENDATIONS OF PROTECTION COORDINATION SUB-COMMITTEE
(PCSC) OF SRPC ........................................................................................................................................... 102
50 COMMERCIAL COMMITTEE ISSUES ............................................................................................................ 102
51 ISSUES IN BILLING OF GENERATING STATIONS OWNED BY NTPC (TARIFF PERIOD 2014-19) .................... 104
52 TPCIL REQUEST TO EXEMPT DEVIATION CHARGES .................................................................................... 104
53 SCHEDULING OF NTPC RAMAGUNDAM SOLAR POWER PLANT (10 MW) .................................................. 105
54 SCHEDULING OF UNITS BELOW TECHNICAL MINIMUM AND OTHER ISSUES ............................................ 105
55 MONITORING OF SCHEMES FUNDED FROM PSDF ..................................................................................... 106
56 SALE OF URS POWER BY NLC STAGE-II ....................................................................................................... 106
57 SCHEDULING OF KAMUTHI SOLAR PARK .................................................................................................... 106
58 SETTLEMENT FOR THE PERIOD PRIOR TO BIFURCATION OF AP AND TELANGANA ................................... 107
59 AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM ........................................................................ 107
Minutes of the 31st SRPC Meeting held on 25th February 2017
60 GRID OPERATION ........................................................................................................................................ 108
61 RELIABLE COMMUNIACTION SCHEME UNDER CENTRAL SECTOR FOR SOUTHERN REGION ..................... 119
62 OPGW LINKS ON LINES CONSIDERING LILO IN FUTURE ............................................................................. 119
63 ALLOCATION OF 6 FIBRES FROM THE 18 FIBRES AVAILABLE AS SPARE ..................................................... 120
64 FINAL LIST OF OPGW LINKS UNDER FIBRE EXPANSION PROJECT OF SOUTHERN REGION ......................... 120
65 OPGW STRINGING ON KPTCL LINES............................................................................................................ 121
66 REIMBURSEMENT OF SRPC EXPENDITURE ................................................................................................. 121
67 APPOINTMENT OF CONSULTANTS ............................................................................................................. 121
68 DATE & VENUE OF THE NEXT SRPC MEETING ............................................................................................ 121
69 CONCLUSION .............................................................................................................................................. 121
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 4
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
MINUTES OF THE 31st SRPC MEETING HELD ON 25
th FEBRUARY 2017 AT
BENGALURU
1. INTRODUCTION
1.1 The 31st Meeting of Southern Regional Power Committee (SRPC) was held on 25
th
February 2017 at Bengaluru. The list of participants is given at Annexure-I.
1.2 KPTCL welcomed the Members, Directors and participants to the 31st Meeting of SRPC. A
video was presented on „Invest Karnataka‟; some of the highlights of which are given
below:
Sivasamudram (4.2 MW) was the first hydro station in Asia commissioned in 1902 for
enabling gold mining at Kolar. The power was extended to Kolar through then longest
transmission line of 147 kms.
Karnataka was the first state to set up professionally managed entity at state level
(KPCL) to plan, construct, operate and maintain power generation. Since 1976, KPCL
has installed capacity of around 6,500 MW of thermal, hydro, solar and wind energy.
56% of which is hydel energy. Around 9,500 MW is in the pipe line to be
commissioned in the future.
MNRE sanctioned National Training Centre for Solar Technology to KPCL in 2011.
Functions of transmission and distribution of erstwhile KEB were carved out in 1999.
Shortly afterwards, KERC was set up to regulate all aspects of electricity sector in a
transparent manner.
KPTCL was further unbundled in 2002 and four independent Discoms were formed,
which was later made into five Discoms.
PCKL was incorporated in 2007 to further augment power supply procurement.
KPTCL has reduced losses to one of the lowest in the country at 3.66 %.
KPTCL was first in the country to commission largest SCADA network to
professionally operate and control transmission network.
KPTCL switched to compact substations and was the first state in India to use covered
conductors.
KPTCL was awarded best „Transmission Utility‟ in the country by CBIP.
KPTCL / Escoms have been responsible for electrifying nearly 100 % of the habitats
in Karnataka. By 2020, all the households in Karnataka would be electrified.
Bescom was chosen to host the Pilot Project for Smart Grid. Distribution Automation
System (DAS) has been implemented in Bescom.
CESC earned first prize towards National Energy Conservation.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 5
KREDL is responsible for generating clean, green and renewable energy through wind
and solar projects. Government of Karnataka has revised its Solar Policy for 2014-
2021. Idea was to empower farmers through „Surya Raitha‟ and solar pump schemes.
Encouraging roof top solar and easy buyback polices are examples of the progress.
State is developing the worlds‟ largest solar park of 2,000 MW by 2017.
Hon‟ble Prime Minister of India had conferred the award for „Excellence in
Renewable Sector‟ to Karnataka.
By 2020, 8 crore population would be supplied 24x7 power in Karnataka.
1.3 Shri Jawaid Akhtar, MD, KPTCL extended a hearty welcome to all the delegates to the
meeting. At the outset, he welcomed Dr M Saikumar, Chairman, TNEB & Chairperson,
SRPC for making it convenient to attend this meeting despite his busy schedule. He made
a special mention of Shri S R Bhat, MS, SRPC who has been ably handling the issues of
SRPC. He welcomed all the Chairpersons, Managing Directors, Directors and CEOs to the
meeting.
On grid side, he informed that Karnataka had witnessed record energy consumption and
demand on 23.02.2017. However on the previous day, Karnataka had touched demand of
10,242 MW and energy consumption of 221.49 MU which were maximum till date. Major
evacuation system which was being undertaken since last two years consisted of six lines.
Out of three lines at 400 kV, one line (Bellary PS-Kelagina Kanive, Chitradurga District),
had been commissioned in the month of February 2017. The line from Kelagina Kanive to
Vasanthanarasapura would be completed within 10 days. Works in difficult areas of
Tumkur was over and the left out works were to be completed in Chitradurga District. The
third line which would evacuate power from KPCL‟s Yeramarus units would be ready by
April 2017. Out of three 220 kV lines, Vasanthanarasapura - Anthranasahalli and other
line from Vasanthanarasapura - Madhugiri would be completed within 15-20 days since
only couple of issues remain to be settled. Madhugiri-Pavagada line was expected before
March 2017. KPTCL had been able to complete more than 12-13 major works pending
since past 5-10 years. Most of these works were in and around Bengaluru and they were
trying to strengthen internal transmission lines within Karnataka, specifically around
Bengaluru.
1.4 Shri S R Bhat, MS, SRPC extended a special welcome to Dr M Saikumar, Chairman, TNEB &
Chairperson, SRPC. He also welcomed other SRPC members to the Meeting. He thanked MD,
KPTCL and his team for the excellent arrangements made for conduct of the Meeting.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 6
1.5 SRPC welcomed the following new Members to SRPC:
i. Shri R K Verma, Member (GO & D), CEA
ii. Shri H Nagesh, Director (T), KPTCL
iii. Dr K Ellangovan, CMD, KSEBL
iv. Ms M A Helen, Director (Distribution), TANGEDCO
v. Shri A K Gupta, Director (Commercial), NTPC
vi. Shri Siva Rama Krishnan M, CEO, NTECL
vii. Shri K V S Baba, CEO, POSOCO
viii. Shri N Ramesh, CEO, IL & FS
ix. Shri P Panduranga Rao, CEO, LKPPL
1.6 SRPC placed on record the excellent services rendered by the following outgoing Members:
i. Shri Paul Antony, CMD, KSEBL
ii. Shri T K Barai, Member (GO & D), CEA
iii. Shri S Sumanth, Director (Transmission), KPTCL
iv. Shri M Pandi, Director (Distribution), TANGEDCO
v. Shri U P Pani, Director (Commercial), NTPC
vi. Shri Thomas Joseph, CEO, NTECL
vii. Shri S K Soonee, CEO, POSOCO
1.7 Dr M Saikumar, Chairperson, SRPC & Chairman, TNEB at the outset thanked MD, KPTCL
for the excellent arrangements. He added that it was noted that TCC had a good Meeting on
the previous day. There were a couple of issues which need to be deliberated such as
integration of renewable energy. As was well known Tamil Nadu has considerable amount of
renewable. The associated problems being faced in this regard should be studied. The lessons
from the same should be shared and implemented in other places. Intra-day as well as inter-day
variations of wind were very high. There were cases where wind was 3,000 MW in the
morning, dropping to about 600 MW in the afternoon while completely disappearing in the
evening. At times even thermal plants had been backed down anticipating availability of 3,000
MW of wind but compulsory load shedding had to be subsequently resorted in peak hours.
This was happening as a matter of routine and thus planning was rather difficult. Some
resources were required which could quickly back down or ramp up. Karnataka and Andhra
Pradesh were also moving ahead in large scale renewable integration and it was reported that
Solar Energy Corporation was going in a big way for development in the country. It was to be
seen how such large scale integration would take place and also transmission requirements
needs to be provided in a timely manner. TN had been seeking green corridor for transfer of
renewable energy to other states. Assuming that all investments in Andhra Pradesh, Karnataka
and Tamil Nadu come up, it was to be assessed whether there would be a corridor to export.
Earlier only one state was getting affected, but now with large scale renewable integration in
number of states, the issues were getting magnified. All Constituents were proud about the
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 7
coming up of KKNPP units. However, one issue required to be sorted pertained to schedule
planning of large nuclear units like Kudankulam. In absence of backing down, there were
issues since more than 50 % power was allocated to Tamil Nadu. Second unit of KKNPP was
yet to be stabilized. Since power contracts were based on projected availability of KKNPP
units, any tripping of units/prolonged outages put the planning process in disarray.
1.8 The Agenda was taken up for discussions.
2. CONFIRMATION OF THE MINUTES OF THE 30th
SRPC MEETING
2.1 Minutes of the 30th
Meeting of SRPC held on 27th
August 2016 at Chennai had been
circulated vide letter dated 19th
October 2016.
2.2 Minutes of the Meeting were confirmed.
3. MEMBERSHIP TO RPC
3.1 Special Invitee /Membership status to M/s PTC in RPCs
3.1.1 In the 5th
Meeting of NPC held on 08th
April 2016, after deliberations, it had been agreed
that the issue of membership for Traders would be deliberated in respective RPCs and
outcome thereof would be communicated to CEA for taking up the matter with MoP.
3.1.2 In its 30th
Meeting, SRPC had concluded that the proposal to include M/s PTC as SRPC
Member could be deferred. Presently, composition as stipulated in the MoP Resolution
could be continued.
3.1.3 In the 6th
Meeting of NPC held on 19th
December 2016 (MoM dated 12.01.2017 available
on CEA website) the following had been noted:
Chief Engineer (GM), informed that as per the proposed amendment taken up with
MoP by CEA, a representative of each of nodal agency appointed by Government of
India for cross border power transaction with the countries having electrical
interconnection with the region also included as members of respective RPCs
irrespective of the trading volume. In such case PTC could be retained as a member of
ERPC. All other RPCs trader membership would be as per the present practice being
followed.
Member (GO&D) stated that since the matter would be sorted out by the proposed
amendment taken up by GM Division with MoP, further deliberation on the issue by
NPC was not required.
Chairperson, NPC observed that presently ER & NER were the regions involved in
cross border transaction of power. MoP may take a call on the proposed amendment in
the Resolutions of RPC for including traders who are involved in cross border trading
as members of respective RPCs.
NPC decided to await the outcome of proposed amendment of resolution by MoP.
3.1.4 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 8
3.2 Membership of IPPs in RPCs
3.2.1 In the 5th
Meeting of NPC held on 08th
April 2016, the following had been noted:
WRPC had proposed to enhanced the limit of 1,000 MW to 2,000 MW for
membership of IPP in RPCs. NRPC had suggested that instead of allowing them RPC
membership IPPs might be included in subcommittee like TCC/OCC.
NPC had suggested that this issue be deliberated first in respective RPCs and after
evolving a common view, same would be referred to MoP for amendment in
Resolution.
3.2.2 In its 30th
Meeting, SRPC had concluded that the present eligibility of 1,000 MW as
stipulated in the MoP Resolution could be continued in respect of Southern Region.
3.2.3 In the 6th
Meeting of NPC held on 19.12.2016 (MoM dated 12.01.2017 available on CEA
website) the following had been noted:
Member (GO&D) pointed out that MoP has issued individual Resolutions for each
RPC. Resolution in respect of WRPC could be proposed for amendment regarding
membership of IPPs.
After deliberation it was decided that GM Division, CEA would take up with MoP for
amendment in Resolution of WRPC in respect of eligibility condition of IPPs
membership in WRPC.
3.2.4 SRPC noted the above.
3.3 Representation from Power System Wing in RPC Meetings
3.3.1 In the 6th
Meeting of NPC held on 19th
December 2016 (MoM dated 12.01.2017 available on
CEA website) it was noted that in order to have fruitful deliberation on transmission system
related issues/schemes in TCC/RPC Meetings, Grid Management Division, CEA had
proposed that RPCs may invite Chief Engineer (PSP&A-I) / Chief Engineer (PSP& A-II),
CEA depending upon the region being dealt with, in respective TCC/RPC Meetings as a
“Special Invitee” on regular basis. It had been agreed that this proposal would be deliberated
in respective RPCs and outcome thereof communicated to NPC Secretariat.
3.3.2 TCC deliberations
It was opined that transmission related issues were being deliberated threadbare in the
Meetings of Standing Committee on Power System Planning. Further, the number of
participants was also required to be contained.
After deliberations, TCC had recommended that Chief Engineer (PSP&A-II) may be called
as a “Special Invitee” on a case to case basis as per any requirement.
3.3.3 SRPC noted the above.
4. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER
ENVIRONMENT (PROTECTION) AMENDMENT RULES, 2015
4.1 Revised water consumption and emission norms for existing as well as new thermal units (to
be installed from 01.01.2017 onwards) as per Environment (Protection) Amendment Rules,
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 9
2015 were notified by Ministry of Environment, Forest & Climate Change (MOEF & CC)
(Gazette Notification dated 07.12.2015). MOEF guidelines had classified thermal generators
into three categories with different norms. The three classes were - prior to 31st December
2003, 1st Jan 2004 to 31
st December 2016 and beyond 1
st January 2017. Existing as well as
new plants were required to meet standards by the stipulated time lines. Preparedness and
action plan in order to comply with revised norms had been discussed in SRPC and the
Subcommittee Meetings.
4.2 CEA, New Delhi vide letter dated 22.12.2016 (Annexure-II) had intimated that a
Committee headed by Chairperson, CEA had been constituted by Ministry of Power; Govt. of
India for preparing a phasing plan for implementation of new environmental norms issued in
December 2015 by MOEF &CC with regard to SPM, SOx & NOx emissions. 1st & 2
nd
Meetings of this Committee were conducted on 21st October 2016 and 13
th December 2016
respectively, wherein the following decisions had been taken:-
Region-wise lists to be prepared by CEA identifying thermal units for ESP up gradation
& installation of FGD. Lists in respect of Southern Region had been prepared and
enclosed at Annexure-1 to Annexure-4 of CEA‟s letter.
Concerned RPC to prepare phasing plan for above identified units for ESP up gradation
and FGD installation in consultation with concerned Power Utilities, SLDC &
POSOCO. RPCs were requested to complete above exercise within 1 month time and
furnish the same for inclusion in Report of the Committee.
Installation of low NOx burners in all coal based thermal units was discussed by the
Committee. It was brought to the notice of Committee, that all new units installed after
2004 onwards had low NOx burners/system. However, older units may not have low
NOx burners/system. Committee had recommended taking up installation of low NOx
system in these coals based thermal units during next over-hauling period positively.
Technical feasible options available for reducing NOx emissions were mentioned in the
letter/MOM.
4.3 Accordingly, a Meeting was conducted on 12th
January 2017 at SRPC, Bengaluru to
deliberate on status and also firm up Phasing Plan. (Minutes of the Meeting are available on
SRPC website). In the Meeting, Phasing Plan for FGD installation etc was firmed up. Other
issues in respect of the revised norms were also deliberated.
4.4 CMD, TANGEDCO vide letter dated 18.02.2017 (Annexure-III) had sought time extension of
two years for all the four units of MTPS-I to comply with the new environmental norms for
the desired SPM levels.
4.5 TCC deliberations
MS, SRPC had appraised TCC of the issues with regard to FGD installation, ESP up
gradation and low NOx burners/system. Schedule of FGD installation had been
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 10
communicated to CEA and was to be completed in the time frame of 2019-21. Installation
of low NOx system in coal based thermal units was to be carried out during next over-
hauling period positively. As noted earlier, there was no compulsion on phasing out of
units, provided revised environment norms were met. For seeking extension, CEA had
sought phasing plan for FGD installation which would be put up further to MoP.
Concerned generators had been requested to kindly initiate necessary action in this regard.
TCC had noted the requirements for necessary compliance.
TCC had suggested that some funding either from PSDF or any other fund could be
arranged from GoI to meet stipulated revised environment norms. Chairperson, SRPC
could be kindly requested to take up the matter with GoI.
4.6 SRPC deliberations
4.7 Chairperson, SRPC stated that most likely none of the entities may be in a position to meet
time frame for compliance of new environment norms. The issue had been taken up for TN
units with GoI, but response had not been very encouraging. Cost of Rs.1 to 1.5 crore per MW
to take up the works was also quite exorbitant. He added that all entities could suitably take
the request for time extension with the concerned Authorities.
4.8 It was agreed that Chairperson, SRPC would take up the issue with GoI for funding to meet
stipulated revised environmental norms.
5. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION – TASK FORCE
5.1 In the 29th
Meeting of SRPC, it had been agreed that a Task Force at TCC level could flag
issues and come out with Terms of Reference and possibly get it examined through a
Consultant. TCC in its 29th
Meeting recommended the TOR for renewable integration as
finalized in the Special TCC Meeting held on 02nd
August 2016 for approval of SRPC.
5.2 In the 30th
Meeting, SRPC had agreed to form a Working Group of Members from each of the
states, SRLDC and SRPC Secretariat to take forward the TOR by engaging a Consultant.
Constituent states of SRPC had agreed to share the financial commitment equally. It was
agreed that details would be put up to SRPC in the next Meeting.
5.3 Working Group of Members from each of the states, SRLDC and SRPC Secretariat had met
on 17.11.2016 and the TOR finalized is at Annexure-IV. As can be kindly appreciated there
are a number of reports/studies undertaken or being taken up in this field. It was thus felt
prudent to fine tune the TOR in discussion with experts/staff of POSOCO etc., to avoid any
possible duplication in the proposed study.
5.4 TCC deliberations
NLDC had informed that some reports on the subject were already available (links
available at Annexure-V). Available study material could thus be used to the extent
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 11
possible to cut down on cost of proposed study.
SRPC had informed that as per preliminary assessment, the cost could be around Rs.3.50
crores. SRPC Secretariat was also trying to fine tune the TOR in consultation with
experts/staff of CERC & POSOCO.
TANTRANSCO had suggested that this study/report could be funded by RE developers,
especially since objective was to facilitate RE integration smoothly, safely and securely
into the grid.
TCC had requested TANTRANSCO/TANGEDCO to use their good offices and take up the
matter with RE Developer Associations. TANTRANSCO/TANGEDCO had agreed to take
up the matter with the RE Developer Associations for possible funding of the consultancy.
5.5 SRPC noted the above.
6. FLEXIBILITY IN UTILIZATION OF DOMESTIC COAL FOR REDUCING COST OF
POWER GENERATION
6.1 MoP vide letter dated 10.06.2016 had informed that on 4th
May 2016, Cabinet had approved
proposal of Ministry of Power for flexibility in utilization of domestic coal for reducing cost
of power generation. Presently, share of generation from coal based power plants was about
78 % of the total generation in the country. These coal based power plants are supplied coal
against plant specific Fuel Supply Agreement (FSA). There are some power plants which
generate cheaper power than others. There was scope for utilization of coal in such power
plants to achieve overall reduction in cost of generation.
6.2 In this regard, approved mechanism for allowing flexibility in utilization of domestic coal
amongst power generating stations to reduce the cost of power generation was deliberated in
the 29th
TCC/30th
SRPC Meetings. The following had been noted in the Meeting:
TANGEDCO had stated as per computations, in Case-1 (use of coal aggregated with the
state in its own State GS), the cost is reducing. Ib valley coal (2,000 kM) linked to Mettur
could be utilized in North Chennai St-II. Presently computations for Case-2 (use of coal
aggregated with one state in GS to other state‟s utilities) would be difficult to assess.
Case-3 (use of coal aggregated with state in CGS and vice versa) could also be utilized
by TANGEDCO as in some earlier cases NTECL & NTPL were requiring coal.
CEA had informed that certain apprehensions were envisaged during the formulation of
this methodology. The methodology could be utilized only if there are some financial
benefits. Sample computations were carried out in consultation with NTPC; and the
estimated benefit for NTPC for one year was around Rs 760-900 Crores on internal
optimization only. Sample computations for Koradi (MAHAGENCO) had also shown
substantial saving (around 39 paise/unit in variable cost). The three Ministries i.e Power,
Coal and Railways had come together for implementation of the scheme. There would be
no rebooking charges by the Railways during diversion of coal under this scheme. Case
2 & 3 could be utilized which would a learning experience and subsequently Case 4
could be initiated in a transparent manner.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 12
NTPC had clarified that the scheme had been implemented for intra-state GENCO
stations and between NTPC and GENCO stations also. After experience, MoP may open
the scheme for IPPs. The whole essence of the scheme was to minimize the cost of
power. Within NTPC, coal could be transferred within various stations, maximizing
generation at pit head stations while non pit head stations could possibly be run on partial
loading, for maintaining spinning reserve and taken for reserve shut down as per system
requirement.
After deliberations, SRPC had suggested that states/generators may approach
CEA/CERC/SERC in line with the methodology with sample computations to utilize the
scheme for reducing cost of power.
6.3 Subsequently, CEA had informed that a web portal „Coal Mitra‟ had been created on 23rd
December 2016. Through this, traders could find suitable case / options for Coal transfer.
6.4 MoP vide letter dated 20.02.2017 (Annexure-VI) had released the Methodology for use of
Coal by State in Private Generating Stations (IPPS).
6.5 TCC deliberations
MS, SRPC had appraised TCC about „Coal Mitra‟ Portal (http://www.coal-mitra.com).
Certain details such as variable cost, fixed cost, linkage, nodal officers, calculator etc was
already available on the portal.
NTPC had informed that the scheme had been implemented among some NTPC stations
and informed that Moudha was a success story. Gujarat Government was also in touch with
NTPC for possible coal swapping. NTECL had informed that proposal was still under
discussion stage.
TANGEDCO had informed that they were utilizing the scheme among few of its state
generators.
TCC had requested the generators to examine the options to avail the benefits under the
scheme.
6.6 SRPC noted the above.
7 ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY
7.1 In the 29th
Meeting of SRPC it had been noted that in the matter of Roadmap to
operationalize Reserves in the country, Hon‟ble CERC vide Order dated 13.10.2015 on
Petition No. 11/SM/2015 had directed as follows:
(b) The Commission reiterates the need for mandating Primary Reserves as well as Automatic
Generation Control (AGC) for enabling Secondary Reserves.
(i) All generating stations that are regional entities must plan to operationalise AGC along
with reliable telemetry and communication by 1st April, 2017. This would entail a one-
time expense for the generators to install requisite software and firmware, which could
be compensated for. Communication infrastructure must be planned by the CTU and
developed in parallel, in a cost-effective manner.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 13
(ii) On the other hand, National/Regional/State Load Dispatch Centres
(NLDC/RLDCs/SLDCs) would need technical upgrades as well as operational
procedures to be able to send automated signals to these generators. NLDC /RLDCs and
SLDCs should plan to be ready with requisite software and procedures by the same date.
(iii) The Central Commission advises the State Commissions to issue orders for intra-state
generators in line with this timeline as AGC is essential for reliable operation of India‟s
large inter-connected grid.
(c) To start with, a regulated framework in line with the Ancillary Services Regulations
would need be evolved for identification and utilizing of spinning reserves and
implemented with effect from 1st April, 2016. This framework may continue till 31
st
March, 2017.
……………
(d) In the long term, however, a market based framework is required for efficient provision
of secondary reserves from all generators across the country. For this, NLDC/POSOCO
is directed to commission a detailed study through a consultant and suggest a proposal to
the Commission for implementation by 1st April, 2017, giving due consideration to the
experience gained in the implementation of Spinning Reserves w.e.f. 1st April, 2016.
7.2 In earlier Meetings the following had been noted:
NLDC had informed that AGC issues were being looked into by the Expert Committee of
Members. They had sought some more time from Hon‟ble CERC for operationalizing the
reserves since many other issues such as telemetry etc., were to be addressed. NTPC was
responding positively and the process of transmitting signals to the station as a pilot
project was being contemplated in each region. Changes in generators side controls were
required and NTPC was taking a lead in it.
SRLDC had informed that a Pilot Project had been taken up through M/s Siemens and
NTPC. Action was being taken for the detailed report of NLDC through Consultant and
in a couple of months, the report would be submitted. Feedback on Ancillary services had
been given to Hon‟ble CERC. ACE would soon be posted on website for the benefit of
all entities. POSOCO would also be conducting a workshop on AGC issues.
After deliberations, it was noted that NLDC/SRLDC would conduct workshops as part of
capacity building exercise and also display ACE on its website.
7.3 Subsequently, POSOCO had conducted the Workshop on AGC followed by feedback on
Ancillary Services implementation on 03rd
October 2016. Hon‟ble CERC had sought
comments on draft 5th
amendment to IEGC in which, creation of spinning reserve had been
proposed. The Final amendment in this regard was awaited.
7.4 TCC deliberations
NLDC had informed that a workshop on AGC was organized on 19th
/20th
Jan 2016. The
issue was further discussed in the FOLD Meeting held on 02.03.2016. It was discussed
in the Stake holders Meeting held on 15.03.2016 where all generators had participated.
NTPC, Dadri Stage-II was decided for Pilot Project keeping in view the high variable
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 14
cost, load center plant and since it is easy and economical to keep spinning reserve. LOA
for Dadri Pilot Project has been placed on 18th
Jan 2017 with time schedule of 4 months.
Other technical specifications, check list and consolidated rules for PLC Algorithm are
enclosed at Annexure-VII. Since this had commercial implications, the issue was being
discussed with NTPC, Dadri and Hon‟ble CERC would be approached for appropriate
orders. Though date for implementation was 01.04.2017, but being a new project,
Hon‟ble CERC had been approached appraising all the difficulties. It had therefore been
suggested that Pilot project would be taken up first and after getting experience and
submitting the report comprehensive AGC installation could be taken up.
To gain experience in SR, it was agreed that Pilot Project in SR for Simhadri St-II and N
P Kunta would be taken up.
In respect of N P Kunta, it was noted that POSOCO would get in touch with NTPC NP
Kunta for technical compliance to meet AGC requirements. For all plants, control
signals would be centrally transmitted from NLDC to the AGC software.
APTRANSCO had pointed out that subsequently, the matter would also be required to be
referred to APERC since it had commercial implications and RE had “must run” status.
MS, SRPC had informed that Hon‟ble CERC in its Order in respect of Petition No.
65/MP/2014 dated 13.2.2017 had stated the following:
„A detailed analysis of RRAS operation for the past 6 months has been submitted by the
NLDC in November, 2016 and the same is under consideration of the Commission. Based
on the experience gained from RRAS operations, POSOCO is expected to submit a
detailed procedure for implementation of Spinning Reserve of about 3,600 MW as per the
recommendation of the Committee on Spinning Reserve. Hence, in our view, there is no
requirement to engage an international consultant to study and recommend the road map
for introduction of constant frequency operation/secondary control.‟
7.5 SRPC noted the above.
8 CONGESTION RELATED ISSUES
8.1 NLDC had applied congestion charges on 14th
December 2016 for the 77-80 blocks. NLC
TS-II, NLC TS-I Expn, KKNPP, NTPL, NTECL and NTPC Stations (copy of letters
enclosed as Annexure-VIII) had informed that some of the notices such as Congestion
„Warning Notice‟, „Notice for Application of Congestion Charge‟ or „Notice for
Withdrawal of Congestion Charge‟ in line with Congestion Regulation / Procedure had not
been received by them in real time.
8.2 Clause 5.3, 5.6 and 6.5 of Detailed Procedure for Relieving Congestion in Real Time
Operation state as follows:
„5.3 Whenever actual flow on inter/intra regional link/corridor exceeds ATC and security
criteria as mentioned in clause 5.2 above are violated RLDC, NLDC may issue a
warning notice. In case, SLDC observes congestion within the intra State grid, it
shall inform the respective RLDC which in turn shall inform the NLDC. The notice
for congestion shall be communicated to all the Regional entities telephonically or
through fax/voice message/e-mail and through postings on website and making the
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 15
same available on the common screen at NLDC/RLDCs/SLDCs. The format of the
notice is enclosed as Format III.
…………………………………………
5.6 If violation of TTC limits persists for 2 time-blocks not counting the time-block in
which warning notice was issued by RLDC and no affirmative action is taken by
defaulting agency, NLDC/RLDC(s) shall issue a notice for application of congestion
charge. This notice shall be communicated to all the concerned Regional entities
telephonically or through fax message and through postings on website and the same
shall also be made available at the common screen at NLDC/RLDCs/SLDCs. The
format is enclosed as Format IV.
………………………………
6.5 Congestion charge shall be withdrawn after the power flow on the affected
transmission link/corridor has come down to the ATC and remains at this level for
one time block. NLDC/RLDC shall communicate to all the concerned Regional
entities telephonically or through fax message/e-mail and through postings on
website and making available the same on common screen available at
NLDC/RLDCs/SLDCs for lifting of congestion charge. The format of the notice is
enclosed as Format V.‟
8.3 Issue had come up for deliberation in the 127th
Meeting of OCC wherein Regional entities
had stated that Congestion charges should be waived off keeping in view the fact that a
number of entities had not received all relevant messages. KSEBL vide letter dated
21.01.2017 (Annexure-IX) had suggested for withdrawal of Congestion charges keeping in
view grounds mentioned in the letter.
8.4 SRPC Secretariat vide letter dated 30.12.2016 (Annexure-X) addressed to NLDC had sought
certain clarifications, as given below:
Criteria for declaring a region as upstream or downstream
ER schedule practicability
Total import capability Vs Congestion in a Corridor
Availability of Format III, IV and V at NLDC/SRLDC Website.
RRAS up during congestion for SR import
Tamil Nadu had not recovered from „Vardha‟ cyclone
8.5 TCC deliberations
NLDC had stated that whenever congestion charge is imposed, information is passed on
through mails and also by putting on website. Same procedure was also being followed in
other regions but there had been no such concern reported regarding receiving of messages
etc. Now, Formats had also been made available on NLDC website which could be
retrieved subsequently.
It was noted that issues such as under drawal in WR, over injection in WR, permitting
infirm injection, kicking in Ancillary up, impractical scheduling on ER-SR link and kicking
in congestion only for SR were some of the issues which need to be further deliberated. It
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 16
was also noted that only when messages were not being received by the entities, waiving
was being suggested. All other payments as per congestion account were being honored.
SRDLC/NLDC had pointed out that there was no provision for waiving off congestion
charges.
TCC recommended to waive off the congestion charges from 77 to 80 blocks on 14th
Dec.
2016 keeping in view the fact that applicable congestion notices had not been received by
generators/SLDC‟s in line with provision of CERC approved Congestion Procedure.
8.6 SRPC concurred with the recommendations of TCC.
8.7 Settlement of waived off congestion charge for the period 01.06.2015 to 07.06.2015
8.7.1 In the 28th
Meeting of SRPC held at Goa on 10.10.2015, it had been agreed to waive off
congestion charges for first week (01.6.2015 to 07.06.2015) of June 2015 as a special case.
It had been agreed that if charges are refunded by the receivable entity, it could be given
back to the entities, which made payments; else it would be adjusted in the future
congestion accounts.
8.7.2 In the 32nd
CC Meeting, SRLDC had requested the constituents to repay the congestion
charges amount to the Pool, so that the amount would be returned to the utilities that paid
the congestion charges. Otherwise, it may take considerable time to settle/adjust/repay the
congestion charges paid during 1st week of June 2015. CC forum suggested that the utilities
may consider paying back the amount received by them, as congestion charges for the
week 01.6.2015 to 07.06.2015, to the congestion pool account to enable
refunding/adjustment to the constituents, who paid congestion charges for that week.
8.7.3 TCC deliberations
KPTCL had informed that they had made the payment on 21.02.2017 to the congestion
pool account.
Status update is as given below:
S.NO Constituent Amount to be
returned to Pool
(Rs)
Status
1 Telangana 35,14,602 Paid
2 Karnataka 84,29,984 Paid
3 Goa 2,48,607 Paid
4 Kerala 67,72,148 Paid
5 NLC TPS-II (Expn.)-I
(Infirm) 1,43,979
Paid
6 NLC TPS-II (Expn.) 52,716 Paid
7 ILFS (Infirm) 69,126 Paid
SRLDC had informed that amount received from Karnataka had already been disbursed
(the statement in this regard is enclosed at Annexure- XI).
8.7.4 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 17
9 COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014 –
IN RESPECT OF LVRT AND OTHER PROVISIONS OF CEA/CERC
REGULATIONS
9.1 Three Meetings had been conducted so far in compliance of Order of Hon‟ble CERC
(Petition No.420/MP/2014) in respect of LVRT and other provisions of CEA/CERC
Regulations. Hon‟ble Commission had specified time lines for a number of actionable points
for various entities.
9.2 Quarterly reports for the period January-March 2016 and April-June 2016 of the SR
constituents jointly validated by SRLDC/SRPC Secretariat had been communicated to
Hon‟ble CERC with regard to monitoring of the installation and performance of LVRT
installed on existing WTGs as per the directives of Hon‟ble CERC.
9.3 CEA had issued draft second amendment in CEA (Technical Standards for connectivity to the
Grid) Regulations and comments had been sought till 31.01.2017. This amendment seeks to
introduce/review the following provisions in the existing regulations:
a) Introduction of Frequency range with provision to include frequency response by
Wind & Solar power stations
b) Introduce applicability of LVRT to Solar Generating stations.
c) Change applicability of LVRT to Wind generating units/stations at all voltage levels
in place of 66 kV level & above.
d) Introduction of HVRT facility in Solar & Wind Generating units/stations
e) Specifying Ramp Up & Ramp Down rates for Solar & Wind Generating units/stations
f) Introduction of Voltage Regulation services for Solar & Wind Generating stations
g) Introduction of Short Circuit Ratio (SCR) for Renewable generating units/stations
h) Review of Reactive Power control capability of Renewable generating units/station
i) Review of limits of Harmonics
j) Review of limits of introduction of a new technology
k) Compliance Monitoring of CEA Regulations
The final amendment was awaited.
9.4 Quarterly report for the period July-September 2016 and October-December 2016 had been
communicated to Hon‟ble CERC.
9.5 SRLDC vide letter dated 07.02.2017 (Annexure-XII) had proposed the issue for discussion.
9.6 TCC deliberations
SRLDC had stated that new wind and solar units need to comply with LVRT/HVRT
provisions and STU/SLDC was to ensure necessary compliance. Required mechanism
needs to be in place for this purpose.
TCC had noted that it may be prudent to await second Amendment in CEA Connectivity
Regulations to move forward on the issue.
9.7 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 18
10 INCLUSION OF DRAWAL OF MAHE IN REA
10.1 In the 32nd
Meeting of CCM it had been decided that Mahe Region of UT of Puducherry
power drawl would be included in the REA of Southern Region from 7th
Nov 2016. KSEBL
vide letter dated 24.10.2016 (Annexure-XIII) addressed to PED had stated that KSEBL
would charge transmission charges for the intervening transmission facility at the rate as
determined by the KESERC, i.e. at the rate of 26 paise/kWh and also the losses in the
transmission system has to be taken into account. Further, it is also stated that a TSA needs to
be executed between KSEBL and PED. The matter had been taken up by SRPC (Annexure-
XIV) with KSEBL. Drawal by PED could not be included in REA from 7.11.2016. KSEBL
vide letter 24.12.2016 (Annexure-XV) communicated the following:
Willingness to allow UT of Puducherry to draw Central share to Mahe through REA at
transmission charges paid by KSEBL to other states but subject to approval of YTC by
Hon‟ble CERC.
CE, Tr (North) had been authorized to initiate necessary action to terminate the EHT
Agreement with UT of Puducherry after settlement of all dues/ arrears payable by UT
of Puducherry, on switch over of drawal of power to Mahe under REA.
They would be approaching SRPC for certification of the intra state lines of KSEBL
carrying power to Mahe as ISTS lines in terms of para 2.1.3 of Annexure-1 of Third
amendment of CERC Regulation.
10.2 UT of Puducherry vide letter dated 03.01.2017 (Annexure-XVI) had requested SRPC to
examine the above decisions made by KSEBL and advise accordingly. This issue had been
included as an agenda item in the 33rd
CCM. In the 33rd
CCM held on 31st January 2017,
Puducherry ED was requested by KSEBL to clear certain accumulated dues.
10.3 Secretary (Power), Puducherry vide letter date 07.02.2017 (Annexure-XVII) had proposed
to take up the matter in the ensuing 30th
TCC & 31st SRPC so as to get a consensus on the
issue and bring out the inclusion of Mahe region of UT of Puducherry power drawl in REA
at the earliest without any furtherance on the issue.
10.4 KSEBL vide letter 31.01.2017 (Annexure-XVIII) had stated that matter regarding
certification of intra-state lines of KSEBL carrying power to Mahe as ISTS lines be
discussed.
10.5 TCC deliberations
KSEBL had stated that the proposal of Puducherry was under consideration and further
details would be communicated in the SRPC Meeting.
10.6 SRPC deliberations
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 19
10.7 CMD, KSEBL agreed with the SRPC Secretariat proposal in principle since it was in line
with the common philosophy being followed in SR for the beneficiaries. However it was
informed that formal approval of the Board would be obtained and subsequently
communicated.
11 ISSUES IN RESPECT OF NPCIL/BHAVINI
11.1 Delay in revision of DC and schedule of NPCIL units
Issue regarding delay in revision of DC and schedule of NPCIL units had been raised on
several occasions earlier. In the Special Meeting held on 25th
November 2016 after
deliberations, it had been agreed that NPCIL units would immediately inform SRLDC about
any tripping/synchronization in compliance of IEGC provisions and would also revise
DC/GS immediately. Changes in DC/GS would be communicated to SRLDC within
stipulated time frames. Necessary system/procedure would be put in place to ensure full
compliance. A workshop on grid aspect for NPCIL stations was also conducted by SRLDC
on 23rd
January 2017 at MAPS.
11.1.1 TCC deliberations
Station Director, MAPS (on behalf of all NPCIL units of SR) had informed that
implications had been noted by NPCIL stations of SR during the Special Meeting and
also further in the workshop conducted on 23rd
January 2017. Suitable instructions had
been communicated to all NPCIL stations of SR to take care of this aspect in future.
11.1.2 SRPC noted the above.
11.2 Black start mock drill for Nuclear Power Plants
In the Special Meeting held on 25.11.2016 and subsequent OCC Meetings, the following had
been noted:
KGS & MAPS had informed that during contingency, the units would go on house load
and they would be able to sustain for 6-7 hrs and subsequently, the reactor would poison
out. It would then take 36-38 hrs for revival. Subsequently, MAPS had informed that
they could operate on house loads only for two hrs. Success of going on house load was
very high but in the recent Vardha cyclone, Unit at MAPS did not go on house load.
Exact information was required to be suitably incorporated in the BSRP document and to
assess the need for black start mock drill for KGS and MAPS.
KKNPP had informed that their reactor does not have limitation of reactor poisoning and
the units could be brought back in short duration. During complete Black out around 50-
70 MW may be required per unit to meet the auxiliary consumption. SRLDC had
informed that procedure for extending supply to KKNPP during Black Out was in place.
It had been agreed that KKNPP would work out internal procedure to avail startup power.
Subsequently, mock drill would be planned and carried out in coordination with SRLDC
and TNSLDC.
SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion:
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 20
11.2.1 TCC deliberations
Station Director, MAPS had informed that low frequency set points would be retained.
High frequency set points for house load operation would be examined.
MAPS had agreed that during house load operation, it would synchronize even with
availability of single evacuation line. As per AERB guidelines, two sources are
required for synchronizing to the grid after criticality.
MAPS had agreed to look into the mock exercise during black start.
11.2.2 SRPC deliberations
SRPC noted the above.
SD, MAPS stated that 400 MW of power could not be evacuated through a single
evacuation line and hence TCC deliberations to be comprehended accordingly.
11.3 A/R for MAPS/BHAVINI lines
In the Special Meeting held on 25.11.2016, MAPS had informed that since line CVT‟s
are a pre-requisite for A/R, and replacement of 15 line CVT‟s were being taken up for
commissioning, A/R would be commissioned/ enabled alongside Y-ph line CVT‟s
replacement, and assured that A/R would be put into service in six (6) months time
(i.e., by May, 2017). They were in touch with TANTRANSCO, and had been assured
that 15 CVTs would be made available to them (as per mutually agreed terms and
conditions). Subsequently MAPS had informed that it is planned to get CVTs from M/s
TANTRANSCO by the end of February 2017 and implement the A/R for all the lines
emanating from MAPS by July 2017.
BHAVINI had informed that A/R would be enabled by January 2017.
SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion.
11.3.1 TCC deliberations
TANTRASCO had agreed to spare 4 numbers of CVTs to MAPS immediately.
Station Director, MAPS had informed that they required 15 numbers of CVTs and
requested TANTRANSCO to spare them. As committed earlier, they would comply
with CERC order in respect of providing of CVTs and would enable A/R by July 2017.
Parallely they had initiated action to purchase the CVTs. In respect of BHAVINI, the
requirement would be communicated for needful.
11.3.2 SRPC deliberations
SRPC noted the above.
SD, MAPS again requested TANTRANSCO to kindly spare 15 CVTs so that the entire
work could be completed.
11.4 Status of 2 x 125 MVAR reactors at Kaiga GS
It had been noted that KGS / NPCIL would interact with SR-II PGCIL at the earliest
and come out with a detailed action plan by December 2016.
There was urgent need of reactor at KGS, and PGCIL could be requested by KGS for
diversion or providing spare reactor for KGS.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 21
11.4.1 TCC deliberations
Station Director, MAPS had informed that financial sanction had been received in
this regard. Initially they would provide additional reactor and subsequently replace
existing reactor with 125 MVAR reactor. It could take around 2 years time for
commissioning of the reactors.
SRLDC had suggested that Kaiga GS could approach PGCIL to possibly utilize the
50 MVAR spare reactor available at Narendra.
11.4.2 SRPC deliberations
PGCIL stated that they would not be able to spare the reactor.
11.5 Reactive requirement for KKNPP Phase-II unit
NPCIL had informed that they had taken up the issue with CTU (through email) and
reply was awaited.
SRPC & SRLDC had stated that the limitation of no absorption by Stage-2 units needs
to be taken up formally with CTU and details communicated to SRPC/SRLDC.
11.5.1 TCC deliberations
CTU had informed that NPCIL had not approached them on the above issue.
NPCIL was again requested to communicate MVAR absorption limitation to CTU at
the earliest.
It was noted that 2 bus reactors at KKNPP-I were under prolonged outage. SD,
MAPS had assured that the issues would be communicated to KKNPP for further
needful.
11.5.2 SRPC noted the above.
11.6 Planned maintenance of NPCIL Units
Keeping in view peak load period of SR, NPCIL had been earlier suggested to avoid
planning their shutdowns during the months of January to April each year. However,
it has been observed that one or two shutdowns invariably are availed during the
months of January to April each year. This year too shutdown of KGS unit-2 was
planned during December 2016 but subsequently rescheduled by KGS to February-
March 2017. SRPC Secretariat letter dated 06.12.2016 in this regard is at Annexure-
XIX. MAPS unit-1 shutdown which was planned for 29.11.2016 to 12.01.2017 had
been rescheduled to March 2017.
NPCIL needed to kindly plan unit maintenance during the period May to December
each year.
11.6.1 TCC deliberations
Station Director, MAPS had stated that maintenance of NPCIL units depended on
technical specifications and surveillance tests etc. A letter had been addressed to AERB
to permit extension of MAPS unit shutdown to 18.03.2017 and by that time Kaiga unit
would come back. To the extent possible, shutdowns would be planned during the
period May to December each year.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 22
11.6.2 SRPC deliberations
SRPC suggested NPCIL to plan shutdowns during May-December each year.
11.7 MVAR absorption at KGS
Issue of MVAR absorption had been discussed in the Special Meeting held on 25.11.2016
and the following noted:
KGS had informed that after unit-III generator core failure, generation was being
maintained at around 190 MW (to restrict the temperature). Core heating was being
observed in unit-IV also and therefore, they were restricting the MVAR absorption.
As a long term measure, they were planning to replace the generator itself.
Report of OEM about Unit III & IV Generator, clearly elaborating technical issues,
precautions etc needed to be furnished to SRPC/SRLDC. SRLDC vide letter dated
07.02.2017 (refer Annexure-XII) had proposed the issue for discussion.
SRPC/SRLDC/KPTCL had expressed concern and pointed out that KPCL/KPTCL had
completed the identified steps in the adjoining areas of KGS. KGS needs to be
proactive and commissioning of the 2 x 125 MVAR reactors needs to be expedited.
Other units should support the grid with MVAR absorption to possible capability.
11.7.1 TCC deliberations
SRLDC had expressed concern and stated that even Unit-IV was not absorbing
adequate MVAR , though the problem was with regard to Unit-III.
Station Director, MAPS had stated that both units were of same make and had similar
features and therefore, the MVAR absorption was being restricted. Report of OEM (on
restricting MVAR absorptions) would be shared.
11.7.2 SRPC noted the above.
11.8 Pending Protection issues specific to MAPS
Compliance of recommendations of PSAG-14 & PCSC-54 Meetings:
MAPS had been asked to furnish a report bringing out clearly actions taken w.r.t. the
recommendations given by PCSC forum in their 54th
Meeting held on 26.05.2016.
MAPS vide their mail dated 06.12.2016 sent compliance status, in which all
pending except A/R had been complied.
TANTRANSCO to kindly furnish status update on changing of porcelain insulators
with polymer insulators for each of the MAPS evacuation lines.
TANTRANSCO vide their letter dated 25.01.2016 informed that the long rod
insulation in 159 cut points out of 688 towers had already been replaced. On
23.12.2015 & 01.01.2016, replacement of insulators was made at 2 locations on
the 230KV Kalpakkam - S.P.Koil and on 05.01.2016 & 07.01.2016, replacement
work carried out on 230KV Kalpakkam - Acharapakkam feeder at 2 locations.
As about 2000 Nos. of insulators are to be replaced on all the 230 kV Feeders
emanating from MAPS to Kalpakkam, further replacement will be made after
procurement of insulators. TANTRANSCO vide their mail dated 22.02.2017
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 23
informed that so far 170 nos. of porcelain disc insulators had been replaced by
Polymer/ Long rod insulators by 20.02.2017
11.8.1 TCC deliberations
Station Director, MAPS had informed that around 50 % replacement of insulators with
Polymer had been carried out on MAPS evacuation lines. Some of the replacements
had been carried out using hot line techniques. Some of the tower base was corroding
and TANTRANSCO was requested to look into this aspect especially on SP Koil line.
TANTRANSCO had informed that insulator replacement was being taken up and
would be completed in couple of months.
It was noted that in addition to the insulators replacement, coping/
strengthening/replacement of towers may need to be carried out by TANTRANSCO.
11.8.2 SRPC deliberations
SRPC noted the above.
TANTRANSCO agreed to take up the insulator replacement, coping /strengthening
/replacement of towers for MAPS evacuation lines and towers affected by Vardha
cyclone.
Status of providing Line CVT‟s in the Y phase of all feeders except SP Koil-2
MAPS representative had assured that said line CVT‟s erection & commissioning and
putting them into service would be completed in six to eight months, i.e., by July, 2017.
11.8.3 TCC deliberations
SD, MAPS had informed that the CVTs would be commissioned by July 2017.
11.8.4 SRPC noted the above.
11.9 Pending Protection issues specific to KGS
It had been decided that KGS would comply with all pending recommendations of
PCSC Meetings (47/II/7 & 57/I/1) in a week‟s time, and furnish a compliance report to
SRPC Secretariat.
KGS vide their mail dated 03.12.2016 had furnished compliance.
11.10 Monitoring of forced outage of 230 kV lines emanating from Nuclear Power Plants
Considering the security & importance of nuclear power plants, it was also decided that
SRLDC would monitor the trippings of all 220/ 230 kV transmission lines emanating
from all Nuclear Power Plants (viz., MAPS, KGS, Kudankulam NPP and BHAVINI
[from synchronization])
11.11 Metering Issues
11.11.1 TCC deliberations
SRLDC had expressed concern on persistent metering and data submission issues from
NPCIL units. For example Kaiga ICT data is not available since more than one year.
SD, MAPS had assured that concern in this regard would be communicated to all SR
NPCIL stations.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 24
12 LOW VOLTAGES
12.1 SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion. Other issues with KPTCL/BESCOM were being deliberated in the OCCM.
12.2 Status of UVR implementation as finalized in the Special Meeting on Low Voltages held on
18th
April 2016 at SRPC, Bengaluru is given below please:
State Location identified
for implementation
Status of
implementation
Remarks
KPTCL Somanahalli 1st stage of 100 MW
implemented at
Somanahalli,
Nelamangala and
Hoody. Details of
2nd
Stage of 100
MW at Somanahalli
had been received.
Details for
Nelamangala and
Hoody were to be
received from
BESCOM.
In the 30th
SRPC
Meeting, KPTCL
had assured that UV
Relays at
recommended
locations would be
made operational
within three months
(by November
2016).
Nelamangala
Hoody
Bidadi It was agreed to drop
the Bidadi UVR
KSEBL Trichur Both the stages implemented
Palakkad
Kochi
TANTRANSCO Udumalpet Both stages implemented and in operation
from 30.11.2016.
Salem Both stages implemented.
Hosur
12.3 SRPC noted the above.
13 RELIABLE ALTERNATE AUXILIARY SUPPLY AT HVDC, BHADRAVATHI
13.1 Southern Region has a TTC/ATC of around 4,000/3,250 MW from WR. Out of this around
1,000 MW TTC/ATC is available through HVDC, Bhadravathi. Earlier Bhadravathi HVDC
station of PGCIL was having two feeders from MSEDCL (Maharashtra) and a back up DG.
The supply from MSEDCL had a number of voltage fluctuations and HVDC poles had
tripped on several occasions. There were some issues in the auto pick up/delayed pick up of
DG at PGCIL SS also. SR had been raising these issues since a long period. Subsequently,
PGCIL had gone for a 315 MVA ICT, the tertiary of which was used as alternate auxiliary
supply for PGCIL SS. After commissioning of this ICT, auxiliary supply reliability had
improved considerably.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 25
13.2 In respect of Petition No.56/TT/2015 (dated 29.7.2016 ) Hon‟ble CERC had not approved
the 315 MVA ICT which was proposed to be used as an alternate supply to MSETCL and
had directed to remove the ICT as it is catering only 2 MVA load of HVDC, Bhadravathi. If
the ICT is removed, reliable uninterrupted supply to meet the auxiliary would be affected
and there could be more trippings of HVDC, Bhadravathi poles. Any tripping of poles leads
to diversion of power through other AC links (Sholapur-Raichur, Kolhapur-Kudgi etc) along
with all associated AC links in WR. Sometimes, it could lead to triggering of SPS affecting
the WR generators/SR loads. SR being an importing region is affected by such events.
13.3 In view of the above, WRPC had been requested to kindly consider the following:
Alternate EHV supply from MSETCL could be considered for reliable auxiliary supply
to HVDC, Bhadravathi.
MSETCL may be requested to have connectivity at 220 kV level from this ICT, if it fits
in their perspective plan. This would avoid shifting of this 315 MVA ICT.
PGCIL may be again requested to strengthen their auto pick up of DG which would
avoid tripping of the HVDC poles during any voltage fluctuation in MSEDCL feeders.
Any other option which could ensure reliable auxiliary supply to the HVDC,
Bhadravathi SS.
13.4 SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion.
13.5 TCC deliberations
MS, SRPC had brought to notice contents of Order dated 17.01.2017 of Hon‟ble CERC
in respect of Petition No 245/MP/2016. It had been suggested that the same could be
kindly examined by PGCIL
PGCIL had informed that they would provide ICT at Bhadravathi at their own cost.
13.6 SRPC noted the above.
14 DC FOR NTECL, VALLUR DURING VARDHA CYCLONE
14.1 NTECL-Vallur vide letter dated 28-12-2016 (Annexure-XX) had requested that, DC
during the period of shutdown of plant owing to Cyclone-Vardha, be allowed considering
declared capacity of 1,380 MW, which was prevailing, prior to the cyclone. It was stated
that the generation had been reduced due to “Force Majeure” conditions.
14.2 After deliberations in the 33rd
Meeting of Commercial Sub Committee, it had been decided
to put up the following for the approval of SRPC in the forthcoming Meeting:
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 26
Sequence of tripping of units is as follows:
Element
Tripping Time Restoration Time
Time Date Time Date
400 kV Vallur- NCTPC -1 1:05 12-12-2016 22:05 12-12-2016
400 kV Vallur- NCTPC -2 14:20 12-12-2016 16:05 14-12-2016
400 kV Vallur- Almathy -1 14:20 12-12-2016 11:09 14-12-2016
400 kV Vallur- Almathy -2 13:51 12-12-2016 12:35 13-12-2016
400 kV Vallur- Kalvindapattu -1 11:59 12-12-2016 15:43 13-12-2016
400 kV Vallur- Kalvindapattu -2 11:53 12-12-2016 14:45 14-12-2016
Vallur#1 11:09 12-12-2016 20:32 16-12-2016
Vallur#2 13:00 12-12-2016 1:34 15-12-2016
Vallur#3 9:36 12-12-2016 2:49 16-12-2016
DC may be allowed considering average DC for the past 7 days (with due consideration
of normal operation days). It may be allowed from the time block when first unit
tripped, i.e. Unit #3, from 09:36 hrs on 12.12.2016. DC may be allowed till 8 hrs from
time of restoration of last 400 kV transmission line (400 kV Vallur - Kalivandapattu
Line-2), which was at 14:45 hrs on 14.12.2016, i.e., up to 22:45 hrs on 14.12.2016.
NTECL-Vallur had stated that they could not come back on 14.12.2016, since port
clearance was not received to operate coal conveyer system till 15.12.2016.
It had been recommended that DC be revised to 1,250 MW as taking average of last 7
days (05.12.2016 to 11.12.2016). NTECL requested to consider the average DC
omitting the time blocks where unit tripped due to Steam leak turbine piping. The unit
was under outage from 18:38 hrs of 5th
Dec 2016 to 08:07 hrs 6th
Dec 2016.
Average DC works out to be 1,280 MW for the week starting from 5th
Dec 2016 to 11th
Dec 2016 excluding blocks from 18:45 on 5th
Dec 2016 to 08:15 of 6th
Dec 2016.
Commercial Committee recommended for Deemed DC of 1,280 MW from 09:30 of
12th
Dec 2016 to 22:45 of 14th
Dec 2016
14.3 TCC deliberations
TCC recommended for approval of SRPC, Deemed DC of 1,280 MW from 09:30 of 12th
Dec 2016 to 22:45 of 14th
Dec 2016 for NTECL in view of Vardha Cyclone. However, this
would not be cited as a precedence for any future cases.
14.4 SRPC deliberations
SRPC approved the recommendations of TCC.
15 OUTAGE PLAN OF CENTRAL GENERATING STATIONS
15.1 APTRANSCOs suggestion on outage plan of CGS units
15.1.1 APTRANSCO vide letter dated 28.11.2016 (Annexure-XXI) had submitted the following:
Requested to take up with all Central Generating Stations of SR to complete the
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 27
overhauls of their units during July 2017 to September 2017, when wind potential is
expected to be higher during July to September.
Ensure full availability during the months January 2017 to June 2017.
Arrange to reschedule overhaul program of all CGS units during July 2017 to Sept
2017 and bring back the units on bar as per schedule.
15.1.2 The following had been noted in the 126th
Meeting of OCC:
NTPC/NLC had pointed out difficulty in carrying out maintenance during July –
September only due to contractual, availability of trained manpower, all India schedule
(NTPC), mining issues (NLC), simultaneous outages in same station, number of units
to be taken up for maintenance etc. Even 6 months were difficult to complete all the
maintenance.
SRPC/SRLDC had also endorsed views of generators and stated that 6 months were
required to complete the maintenance in phased manner between June to December.
The outages were being maximized during July to September. With higher ingress of
renewable more units would be required for hot/warm/cold standby to take care of
intermittency and variability. The peak demand was not substantially falling in July to
September compared to other months and for energy security optimal number of units
was needed as reserves.
After deliberations, it had been agreed that maintenance of thermal/nuclear stations
would be continued to be planned during June to December each year, maintenance
would be maximized during July-September while in October it would be optimally
minimized.
15.1.3 TCC deliberations
TCC had agreed that maintenance of thermal / nuclear units could be continued to be
planned during June-December each year. Maintenance would be maximized during
July-September by all generators while in October, it would be optimally minimized.
15.31.4 SRPC noted the above.
15.2 Information of unit revival of ISG stations /URS details
15.2.1 In the 126th
Meeting of OCC, TSTRANSCO had expressed that information on units likely
to revive up to next day needs to be made available by 10‟O‟ clock each day. It leads to
appreciable commercial loss since the power purchase gets affected due to lack of
information of unit revival. Issues on the information in respect of URS details in different
heads were also raised.
15.2.2 It had been noted that all generators need to diligently report the revival times which could
be incorporated in SRLDC report. SRLDC was requested to look into the possibility of
putting the URS details in different heads keeping in view the URS/scheduling which could
commence on D-2 day as proposed in IEGC amendment.
15.2.3 TCC deliberations
MS, SRPC had informed that it was noted that all generators need to diligently report
revival times which could be incorporated in the SRLDC report, since this had an impact
on power purchases.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 28
TCC had suggested that generators may kindly inform revival times diligently to SRLDC
/ SLDC as applicable.
15.2.4 SRPC noted the above.
15.3 Deferment of approved outage plan for ISGS Units
15.3.1 In the 125th
OCCM, the following had been noted:
NTPC had expressed concern that unit maintenance was being planned diligently after
considering various factors by SRPC Secretariat. The schedule is getting affected due
to request of one of the constituent states. Lot of effort goes into planning and
preparation of unit outages and one rescheduling has a cascading affect on planned
maintenance of other units. There were contractual obligations and rescheduling leads
to intangible loss and stress to NTPC. For example, Simhadri unit went on forced
outage on two occasions as the planned outage was not approved. Number of unit
maintenance pile up towards Oct- Dec affecting the availability. The unit maintenance
gets rescheduled to periods where other states are facing deficit. The window to carry
out maintenance was also very small.
TANTRANSCO had expressed concern that number of maintenance was getting
accumulated and number of 500 MW units outage was getting overlapped.
SRPC had informed that outages are generally planned during June-Dec each year;
overlapping of more than two 500 MW is avoided. With the wind generation peaking
during June-September the outages is maximized during that period. The outages
quantum is computed on weekly basis and the outages are staggered to even out the
quantum during the agreed period. Rescheduling by one constituent completely upsets
the applecart. It has been observed in past that number of rescheduling was due to lack
of preparation and inadequate follow-up with OEM by generators.
After deliberations, it had been agreed that maintenance schedule would be adhered to
by all generators and states. Any request for rescheduling would be conceded only if
majority of states (3 out of 5) approve it, or else on directive of Higher Bodies like MoP
etc. Generators had been requested to be in touch with their maintenance agencies and
have periodical review Meetings to ensure that maintenance is carried out as per
programme. It was also desired by the forum that maintenance of nuclear units should
also be planned during June-Dec each year.
15.3.2 TCC deliberations
MS, SRPC had appraised about instances of rescheduling of outages of some ISGS units
at the request of one or two of the constituents. This was hampering maintenance
preparation of stations and at times outage was getting rescheduled to high demand
period of other constituents.
After deliberations, TCC had agreed on the recommendation finalized in the OCC forum.
Any request for rescheduling would be conceded only if majority of states (3 out of 5)
approve it, or else on directive of Higher Bodies like MoP etc.
15.3.3 SRPC deliberations
15.3.4 Chairperson, SRPC observed that majority decision (3 out of 5) could affect states with
major share in the station.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 29
15.3.5 After deliberations, SRPC concurred that if states having cumulative share of more than 50
% agreed for deferment, then alone the same could be agreed in contingency, or else on
directive of Higher Bodies like MoP etc.
16 EXPERIENCES FROM VARDAH CYCLONE
16.1 Vardha cyclone had struck Chennai and surrounding areas on 12th
December 2016. Its impact
on the grid and subsequent revival activities had been deliberated in detail in the OCC
Meetings. Some of the issues which require kind attention are given below:
SRLDC would firm up need for SAT Phone at critical sub stations/generating stations
specifically in coastal areas of AP/TN/ Puducherry. Other critical stations would also
be covered. SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed
the issue for discussion.
Reason for MAPS unit not going on House Load – MAPS needed to assess and revert
back.
Tripping of Almathy-Vallur lines on O/V (though the voltages were not high) –
TANTRANSCO/NTECL to revert back.
Adequacy of DG capacity at Almathy – TANTRANSCO to revert back. DG adequacy
needs to be assessed for all critical Substations/generating stations -TANTRANSCO/
TANGEDCO/TNSLDC/PGCIL/NTECL/MAPS to revert back.
Adequate manpower availability at SLDC/critical substations/generating stations in
anticipation to cyclone- TANTRANSCO/TANGEDCO/ TNSLDC/PGCIL/ NTECL/
MAPS to revert back.
Black Start Restoration Procedure needs to be reviewed/modified after case study -
NTECL/NCTPS/MAPS- SRLDC to revert back.
Any alternate means of SCADA data/voice communication availability during
contingencies –PGCIL/STUs to revert back.
TANTRANSCO to present detailed report - details of incident, problems encountered,
suggest improvements which could be adopted by all etc.
Readiness of ERS and other trained personnel/material which would be required for
restoration.
16.2 TCC deliberations
TANTRANSCO presented salient features in respect of Vardha Cyclone and also on the
restoration measures :
TNEB had met an all time high demand of 15,343 MW, thereby making Tamil Nadu as
second largest power consumption state in the Country. In and around Chennai, power
was being transmitted from generating stations through 400 KV and 230 KV EHT
feeders and distributed to the consumers through downstream lines.
On December 11th
2016, Indian Metrological Department, Chennai had issued an
emergency alert that Vardha cyclone would hit in and around Chennai, Kanchipuram
and Thiruvallur District of Tamil Nadu. Immediately under the guidance of Hon‟ble
Minister for Electricity of Tamil Nadu, an emergency Meeting was convened by CMD,
TNEB along with top Officials to discuss in detail about preventive steps taken to meet
out the emergency condition.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 30
Men and materials were rushed to Chennai and placed at vital spots for quick
deployment at the shortest notice.
On December 12th
2016, Vardha cyclone struck Chennai and sub urban area causing
massive damages to the power industry.
As a result, 54 EHT towers, 296 Substations, 1835, 11 KV feeders, 32,100 Poles and
800 Distribution transformer collapsed.
Due to this 230 KV EHT feeders connecting Chennai through 10 transmission paths
snapped one after another, resulting in outage of all generating stations in and around
Chennai.
However, due to precaution measures taken by TNEB, there was no loss of life due to
electricity. To overcome this blackout, power was generated from the nearby Basin
Bridge Gas Turbine Power stations and 12 MW of power was evacuated immediately
through 110 KV EHT line to stabilize the grid. Immediately, supply was restored to
General Hospital, Secretariat and High court of Madras, Metro Water and Koyambedu
Bus Terminus. Further, healthiness of feeders was ascertained and supply was extended
step by step. Around 10:00 pm, 50 MW of load was met.
On December 13th
2016 around 3:00 am supply was extended to Chennai Airport and
flight service were resumed.
All EHT lines works were established by mobilizing gangs and healthy feeders were
restored in Chennai and resuming supply to Chennai was done step by step.
Due to the devastating effect of cyclone “Vardha” heavy wind had caused uprooting of
trees which fell on electrical infrastructure and caused extensive damages to electrical
poles, distribution transformers and conductors in Chennai, Thiruvallur &
Kanchipuram districts. Since the damages were very heavy and as it could not be
managed with the existing staff working in affected districts, workers from other
districts, labourers other than EB staff and 1,125 workers from Andhra Pradesh totaling
around 15,300 were deployed in restoration works and supply was restored at the
earliest though the damages were very severe.
Hon‟ble Minister for Electricity of Tamil Nadu, CMD of TNEB reviewed the
restoration activities with top officials on daily basis round the clock.
In order to replace the damaged poles apart from the stock of 32,000 poles, 10,000
additional poles were taken from Andhra Pradesh. 42,000 poles were transported and
restoration activities undertaken on war footing.
Labourers worked tirelessly round the clock to restore the damaged towers, poles and
electrical infrastructure towards restoration of power supply.
Due to dedication of Staff and Officers of TNEB and due to their extra ordinarily quick
response, power supply was put back on rails within very short span of time.
SRLDC had informed that communication was a major issue during the period.
PGCIL had informed that post Hud Hud cyclone and Srinagar floods, GoI had taken the
issue of reliable communication seriously and 6-7 Meetings have been held in this regard.
A Committee to look into reliable communication aspects had been formed.
After deliberations, the following was agreed:
An Expert Committee comprising of Communication Engineers including
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 31
representation from LD & C, PGCIL would study communication requirements for
ensuring data/voice to RLDC/SLDC during Natural Disasters.
DG Capacity requirement along with load would be studied by the entities and
compliance report would be submitted.
Coping and towers strengthening/replacement could be carried out by TANTRANSCO
(and other utilities) as per requirement.
16.3 SRPC deliberations
SRPC noted the above.
ED (LD & C), PGCIL stated that representation from CEA would add value to the
Committee.
It was agreed that CEA would also be requested to represent in the Committee.
17 STATUS OF GENERATION IN ISGS
17.1 Issue regarding low generation at NLC TS-II Expansion, NTECL and NTPL had been
deliberated in the earlier Meetings of SRPC and subcommittee Meetings in which, the
following had been noted:
NTECL vide letter dated 10.11.2016 (Annexure-XXII) addressed to MCL had
submitted that realization of ACQ till date was only 69.8% of the pro-rate ACQ
resulting in drop in the ground stock and dependence on imported coal. Average rake
realization was only 2.77 rakes/day against the sanctioned programme of 4.4 rakes/day
for November 2016. The plant had been pro-actively taking many actions to overcome
the railway logistic bottlenecks in supply of coal like both Paradip & Dhamra Ports
have been engaged for coal receipt through Indian Railways and dispatch through sea
route, Panamax class vessels have been engaged to improve the coal off take and
manual uploading and intra Port transport facility maintained at Paradip to facilitate
receipt of BoxN type wagons from Talcher and Ib Valley. Subsequently, MS, SRPC
vide letter dt.16.11.2016 (Annexure-XXIII) had taken up the issue with MCL with a
request for increased dispatch of coal against FSA for NTECL to meet load demand in
Southern Grid. MCL vide letter dated 05.12.2016 (Annexure-XXIV) had pointed out
the issues with Railways/Ports and requested NTECL to impress upon various
Railways and Port Authorities to work on the constraints being faced and maximize
movement. In addition to the present movement, routes of Talcher-Paradip Port, Ib-
Dhamra Port and Ib-Paradip Port, it was suggested that NTECL should also explore
movement through Ib-Vizag Port, which would certainly be helpful for augmenting
coal movement further and especially when there was any constraint or congestion at
the other ports. TANGEDCO was already using this route gainfully. As per FSA, 5%
of ACQ is offered to all Power Houses on RCR mode and 5% of ACQ against import
component. NTECL may avail this coal under the respective dispensations to add up to
the existing materialization. NTECL vide letters dated 28.12.2016 & 21.01.2017
(Annexure-XXV) had taken up the issue of reporting of coal stock with CEA.
NLC had informed that they had narrowed down the issues which were related to
refractory etc and had carried out necessary modifications. They had achieved PLF of
49% in TS II Expn during July 2016. All issues were getting resolved and PLF of
around 75-80% was anticipated in the coming months.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 32
17.2 Level of generation of some ISG stations is given below:
17.3 TCC deliberations
NTECL had informed that coal stock had been improved to 2.75 LT. They were making
all efforts to increase to 6-7 LT. Main issues were low coal supply at Talcher, availability
of rakes by railways at Talcher and Ib to transport coal to Paradip and Damra ports.
Coal was being supplemented from ECL/CCL. Imported coal supply would be stopped
shortly.
NLC had informed that refractory issue at TS-II expansion was being narrowed down and
that PLF would improve from March 2017 onwards.
TSTRANSCO had expressed concern on frequent force outages at NTPL. NTPL had
informed that due to entry of sea water into the boiler, the tubes were corroded. The
rectification was planned during April 2017 and July 2017 (U1/U2) respectively.
SD, MAPS had informed that as per request they were envisaging running the KKNPP
Unit-I on partial load up to 15th
April 2017, based on fuel availability.
TANTRANSCO had enquired whether NPCIL units (specifically KKNPP) can run on
flexible generation (generation levels could be controlled in a day). SD, MAPS had
informed that NPCIL units were base load stations and flexible generation levels may not
be possible.
17.3.1 SRPC deliberations
17.4 SRPC noted the above.
17.5 Chairperson, SRPC observed that refueling of KKNPP units should be availed during lean
season and to avoid peak demand periods.
17.6 SD, MAPS informed that periodic refueling was to be taken up as per design. Unit-1 was
running continuously from February 2016 to November 2016. Unit-2 would be available to
full capacity after its COD. Proposed Generation schedule would be furnished for both the
units.
17.7 MCL representative stated that NTECL was being given additional coal from ECL & CCL
and supply from MCL would also be improved. On a query, he informed that there were no
coal supply issues at Ib, however rake issues persisted. Since coal stock at NTECL was
under critical category, MCL headquarters / CIL were taking necessary initiatives to
augment coal stock from other subsidiaries.
Station Aug’16 Sep’16 Oct’16 Nov’16 Dec’ 16 Jan’17
NTECL,
Vallur
Generation
in MU
893.17 859.46 709.30 797.95 788.38 880.32
PLF 80.03 79.58 63.56 73.88 70.64 78.88
NTPL,
Tuticorin
Generation
in MU
497.52 592.18 521.66 583.11 471.95 573.35
PLF 66.87 82.25 70.12 80.99 63.43 77.06
NLC TS II
Exp
Generation
in MU
61.10 156.85 85.53 23.20 157.11 164.21
PLF 16.43 43.57 22.99 6.44 42.23 44.14
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 33
17.8 Chairperson, SRPC stated that Coal stock of 4 days at NTECL was not comforting and
being a critical station, NTECL should have atleast 10 days of coal stock.
17.9 MD, KPCL pointed out that coal stocks position for KPCL stations at Raichur and Bellary
TPS was only for 3-4 days and had depleted considerably from earlier level of 20 days.
Coal movement from WCL and MCL had been patchy and issues at Talcher had already
been brought out. All bills of Coal companies had been cleared. Railways were suggesting
that they go for all RR route instead of RSR route.
17.10 MCL representative stated that there were no coal supply issues in respect of KPCL but
supply of rakes was not as required. They had taken up the issue with Railways and at
higher level with Director (Traffic), Railway Board to augment supply of rakes. They are
trying allotment of around 36-37 rakes to Ib Valley. Weekly, subgroup meeting was being
held in Delhi in which Railway (Joint Secretary Level), MoP and CEA officials were
deliberating coal stock/supply issues for critical and subcritical stations.
17.11 Chairperson, SRPC suggested that he would work out a joint meeting with Chairman, Coal
India, in which KPCL and NTECL coal issues could also be deliberated. Ideally, coal
stock should be maintained for around 15 days.
17.12 APGENCO confirmed that there were no coal related issues being faced by them presently.
They were having a coal stock of around one week.
17.13 It was agreed that a Meeting would be held at Hyderabad with participation of Coal India.
18 REVIEW OF ULDC / SCADA/COMMUNICATION
18.1 A Special Meeting had been conducted on 07th
February 2017 to deliberate on pending
SCADA/Communication issues (MoM available on SRPC website). Status of pending
items is as follows:
Issue Action Plan
1 Meeting with M/s
ALSTOM regarding
AMC issues, punch
points
Meeting was held on 16.11.2016 with M/s Alstom
and constituents and M/s Alstom had agreed to
liquidate all pending points except balance Training
modules by end of December 16. Approval for
recovery towards short supply of software has been
obtained by SRLDC while recovery proposal against
the contract of State constituents is under approval.
30th
TCC: SR-II, PGCIL informed that the rates for the unresolved points had
been firmed up and the recovery would be finalized. Only training was left which
would be closed by M/s Alstom and the same was scheduled in March 2017.
AP, TS & KER requested PGCIL to substantiate reasons for delay in completion
of new SCADA by M/s Alstom which had lead to the extension of the AMC by M/s
GE.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 34
2 ICCP link between
RTAMC and SRLDC
ICCP link from RTAMC to SRLDC had been
established and database tables and ICCP association
was being carried out by RTAMC. This data can
form an alternate data set for all SR1 and SR2 data,
especially when data is unavailable or there is a
discrepancy.
3 KPTCL to Back up
SRLDC ICCP link
Link established and tested. ICCP association is
being made.
4 Data discrepancies in
ISGS/IPP/PGCIL/STUs
Sufficient number of Transducer spares needs to be
maintained as per usage/ replenishment.
To be addressed at the earliest. The schedule is given
in the MoM (07.02.2017).
30th
TCC: Sufficient number of spares needs to be maintained as per
usage/replenishment.
5 Replacement of
Transducer at NTPC
Ramagundam
NTPC confirmed that Transducer replacement work
would be completed latest by March 2017.
6 Providing additional
RTU at NTPC Talcher
RTU procurement is under progress and the same
would be completed by March 2017
7 Protection coupler
replacement for
Kayamkulam
Transmission system
SR-II informed that the expenditure on Protection
Coupler for Kayamkulam Transmission System needs
to be borne by respective beneficiaries.
8 Training on RTU
Maintenance
Training was completed 18.11.2016 at
Yelahanka/Hosur for all CGS and Regional entities of
SR.
9 Sparing of fibers in
TANTRANSCO links by
TANTRANSCO
SR II informed that consent was received from
TANTRANSCO.
10 NTECL fiber channel
connectivity
NTECL, SR-II & SRLDC would jointly coordinate
on 10.02.2017 for Vallur data integration at SRLDC.
SRLDC stated that they would ensure M/s Alstom
and SRLDC representative presence at
Sriperumbudur for end to end checking of DCPC.
SR-II would be ensuring presence of M/s Tejas at
NTECL.
11 OPGW stringing on
balance portion of
KPTCL lines
Forum suggested coordination between KPTCL and
PGCIL could be continued and pending works could
be completed to ensure path redundancy and
reliability to SRLDC.
12 Establishing E1 Link
between Backup SRLDC
to Backup NLDC
Link had been established on 05.12.2016 and
informed to SRLDC. Redundancy w.r.t SRLDC
control center hence is established. Back up Control
Center functionality was successfully completed on
31st January 2017.
13 Communication
Diagram/Connectivity
SR-I and SR-II informed that the Updated
Communication diagram / path for all RTU/DCPC
connectivity to SRLDC incorporating the latest
changes would be provided by end of February 2017.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 35
SRPC noted the above.
14 Migration of SCADA
periphery in line with
SEM
Kerala SEM based drawal was checked by both
SRLDC and Kerala and was found satisfactory. The
same will be implemented in February 2017.
APTRANSCO, TSTRANSCO and PGCIL agreed to
attend to the issues at the earliest. Action plan would
be communicated to SRLDC/SRPC.
30th
TCC: AP & TS would migrate to SEM based drawals by 15.03.2017.
15 RTU data issue and
drawal differences w.r.t
APTRANSCO
SR-I and SR-II agreed to attend the issue on priority
and rectify as soon as possible. Daily verification for
drawal checking of states would be resumed at 11:00
hrs. Issues in drawls, if any, would be raised then and
will be rectified by concerned parties.
30th
TCC: PGCIL would rectify the data hanging issues for Raichur-Kurnool,
Kurnool-Thiruvalam and Chittoor-Thiruvalam by 15.03.2017. PGCIL would
replace the terminal equipment, if required.
Validation of drawal at 11 hrs to be continued.
16 SCADA Data failure
Protocol
RTU not reporting/data failure would be
communicated to the concerned entity/user with a
copy to PGCIL. User would take lead role in getting
the issue resolved. User/SRLDC would ensure
necessary verification at their ends as explained in the
training. Parallely, PGCIL would look into
communication issues. User/SRLDC would appraise
PGCIL about the verification at their end for PGCIL to
sort out the communication issues.
Official email ID for SCADA issues to be created for
each entity/User involved for easier communication
and proper delivery of information. All
correspondences regarding any SCADA issue to be
made through this mail ID only. Details to be
communicated to SRLDC/SRPC within a weeks‟ time.
17 Non-availability of
RGMO status /
Inconsistency in RGMO
data reporting to SRLDC
Generating stations and SLDCs agreed to look into the
issue and it was agreed that the issues would be
rectified by end of 15th
March 2017.
18 Integration of new
elements in
SRLDC/SLDC SCADA
All the concerned were requested to strictly adhere to
the time schedules
19 Issues with Orange
Exchange
A separate Meeting would be conducted by PGCIL by
end of Feb 2017 to resolve those issues. All
constituents were requested to communicate the
agenda point to PGCIL/SRLDC/SRPC to discuss the
hot line speech communication provided by Orange
Exchange.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 36
18.2 Video Conferencing facility at SLDCs
Status update is as follows:
AP TN PUDU
Will provide the facility
in new SLDC at
Vijayawada by
March/April 2017.
VC facility between
SLDC (Chennai) and
SRLDC was established
on 19.01.2017. VC
between SLDC, SRLDC
and sub-SLDCs at
Madurai and Erode is
being tested.
Puducherry informed that
Budget for 2016-17 had
been approved but funds for
VC were not allocated due
to paucity of funds. They
would take up VC in the
next financial year 2017-18.
19 URTDSM (PMU) PROJECT IN SOUTHERN REGION
19.1 Hon‟ble CERC in its Order dated 16.09.2016 in the matter of „Approval …….. for grant of
regulatory approval for execution of Unified Real Time Dynamic State Measurement
(URTDSM) Phase-II‟ had stated
„22. It is noticed that URTDSM scheme was approved with the purpose to improve the
visibility and security and to mitigate the probability of grid failure. By considering the
present progress of the Phase-I, the petitioner does not seem to have made adequate efforts
to complete the phase-I of the scheme. The implementation period for phase-I was 2014-15.
However, it is still under implementation. We express our unhappiness with the progress of
Phase I of URTDSM scheme to be implemented by the petitioner. We direct the petitioner to
expedite the work of Phase-I of the scheme so that it may be completed by November 2016 as
submitted by the petitioner. Since substantial progress has not been achieved by the
petitioner in phase-I, it may not be appropriate to grant regulatory approval for
implementation of Phase-II of the scheme at this stage. Accordingly, the petitioner is granted
liberty to submit the fresh proposal for grant of regulatory approval for Phase-II of the
scheme in consultation with CEA after implementation of Phase-I scheme, which would be
considered in accordance with law.‟
19.2 Following is the status update in respect of URTDSM Phase-I as discussed in the Meeting
conducted on 07th
February 2017:
Sl. No. Issue Status/Remarks
1 Updated details of Nodal
Officers:
Whats App group in name of Southern Region
WAMS has been created on 03.11.2016. This
Group will look into dispatch, installation and
commissioning issues under URTDSM Project.
The above group would be functional during the
maintenance phase also.
2 Status of URTDSM
Project(SR Portion)
PMUs to be installed in SR as per URTDSM
Project Package–II had further increased from 240
to 264 on account of commissioning of certain
new stations and additional feeders. (As per LOA-
212)
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 37
Status
Total
Envisaged
Survey
completed
S/S PMU
SS PMU Installed
SR
I
120
Pending in
Hyderabad,
Khammam
and Vemagiri.
PMU quantity
would be
finalized by
end of Feb
2017
18
74
SR
II
41 144 Completed 28 91
Remaining 52 PMUs as per revised BOQ (out
of 264) would be supplied once rate
negotiation with M/s GE is completed.
Currently a Committee is formed by LD&C
PGCIL for rate finalization as extra PMUs are
exceeding the overall quantity variation of SR
& WR limit of 15 % as per original LOA.
Forum requested Project Coordinator/PGCIL to
freeze the total number of PMUs for SR at the
earliest in the interest of faster execution of
project as in the previous Meeting the number
of PMUs had been revised to 240 from 212(as
per LOA). Additional requirement could be
covered in Phase II.
Forum expressed concern that project was
getting delayed and requested PGCIL / GE to
share monthly project execution plan up to
Sep 2017 and monthly progress (
installation and integration to Control
Centre) status by end of every month.
30th
TCC: PGCIL informed that Control Centre hardware has reached Mumbai
and FAT would be completed by March 2017 while SAT would be completed by
April/May 2017. This project would be completed by September 2017.
TCC suggested that Phase-I of the URTDSM project needs to be completed at the
earliest.
PGCIL requested the entities to work out and intimate requirement for Phase-II of
the URTDSM project. They were planning to approach Hon‟ble CERC in April
2017 again.
3 Contractual amendment
Negotiation is under progress with GE T&D.
Amendment is expected to be released in
April’2017 (last Meeting agreed for January 2017)
and system expected to be commissioned by Sep
2017.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 38
4 Requirement of Auxiliary
Power Supply System (APS)
as per revised BOQ
(excluding input ACDB and
one battery bank of the
proposed two battery banks).
SRLDC had already intimated to SR-II vide
letter dated 12.12.16
APTRANSCO, TSTRANSCO and
TANTRANSCO confirmed the requirement of
Auxiliary Power Supply System, a letter
confirming the same would be furnished to SR-
II within a weeks‟ time.
SR-II informed that once all constituents
finalized the APS System requirement by 15th
February 2017, the revised BOQ of APS would
be furnished by LD&C, PGCIL.
It was noted that KSEBL and KPTCL had
already confirmed in the previous review
Meetings that they do not require APS System.
APS System was expected to be delivered
during the month of May 2017. All constituents
were requested to make site ready for APS
System installation to avoid further delay.
5 Capacity of Battery & charger KSEBL suggested to have clear SAT procedure
with current limiting and constant voltage
charging as stipulated by OEM of VRLA
battery set.
6 Responsibilities under Entities SR-II confirmed that dismantling of panels and
any civil works etc required to prepare site for
installing APS System was not under the scope
of the Project and thus was in the scope of
respective constituents.
Supply, erection & commissioning of UPS,
ACDB Input & Output panels, Battery Bank
and associated cabling works for establishing
APS system was under the scope of the Project.
Air Conditioning System was required and
constituents were to make necessary
arrangements.
7 Redundancy for PMUs PGCIL confirmed that all PMUs are provided
with redundant communication path and
schematic diagram of communication flow had
been shared with the constituents.
8 SAT procedure Draft SAT procedure had been circulated
among all constituents. SAT in SR earlier
planned for January 2017 was postponed to
April 2017.
9 SR Region Training
Training had been firmed up by M/s GE and
will be conducted in two batches starting from
27th
February 2017. The details of module have
been communicated to all. Training would be in
two phases and it would cover both operation
and maintenance aspects.
10 Availability of necessary
communication ports for
All constituents to make available necessary
communication ports for connection of servers
under URTDSM project by 20.02.2017 as
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 39
connection of servers under
URTDSM
decided in the last Meeting.
11 Training on Application part PGCIL (LD & C) had stated that requirement of
Training on Application part would be
communicated to the Management
30th
TCC: PGCIL informed that out of six analytics, three analytics prototype were
under trial operation at WRLDC and also in Gujarat system. PMUs in Gujarat
were to be integrated with the PMUs of URTDSM project and analytics could be
uploaded for trial operation at Gujarat SLDC also.
31st SRPC: PGCIL informed that three analytics prototype were under testing at
Delhi and in March 2017, they would put be under trial operation in WRLDC.
Gujarat had commissioned 110 PMUs on their own and they were to be integrated
with URTDSM project and analytic test could be taken up subsequently.
12 Update the Drawings Constituents‟ requested PGCIL to update the
Drawings with changes done in the
CT/PT/Status wiring for the PMU system and
submit as built drawing.
13 Completion of the
commissioning activity at
each site.
M/s Alstom and PGCIL representatives were
requested by constituents to certify the
completion of the commissioning activity at
each site.
14 Mandatory spares PGCIL had agreed to furnish the details about
the mandatory spares supplied at each site.
19.3 SRPC noted the above.
20 SCHEDULING OF WIND & SOLAR GENERATING PROJECTS HAVING
CAPACITY OF 500 MW AND ABOVE
20.1 Hon‟ble CERC vide amendment dated 7th
August, 2015 (Indian Electricity Grid Code - Third
Amendment) Regulations, 2015, which came into effect from 1st November, 2015 had
amended the following:
Amendment of Regulation 6.4 (2) of Part 6 of Principal Regulations which is read as:
“The Following generating stations shall come under the respective Regional ISTS
control area and hence the respective RLDC shall coordinate the scheduling of the
following generating Stations:
b) Ultra-Mega Power projects including projects based on wind and solar resources and
having capacity of 500 MW and above”
20.2 It had been requested that details of upcoming wind and solar projects with installed capacity
of more than 500 MW may kindly be intimated to SRPC.
20.3 TCC deliberations
MS, SRPC had requested constituents to share the details of wind and solar projects
having installed capacity more than 500 MW which would assist in ensuring technical /
commercial requirement as per CEA/CERC Regulations and also seamless integration
and accounting by SRLDC / SRPC.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 40
APTRANSCO had expressed concern that if the scheduling responsibility is shifted to
SRLDC, it would be difficult for APSLDC to manage DSM deviations considering intra-
day and seasonal variations of load and RE injection. During the months of July to
August, availability could be around 12,000 MW while demand would vary from 5,500
to 7,000 MW. About 1,600 MW of overhauls were planned and thus even after backing
down there could be need for some curtailment of RE also as a last resort.
TCC had observed that the requirement emerged from CERC Regulations and
APTRANSCO could appropriately take up the issue.
20.3.1 SRPC deliberations
20.4 APTRANSCO again expressed concern over scheduling responsibility being shifted to
SRLDC for RE projects (more than 500 MW) since during any contingency, they would not
have any control over these generators. STU connected generators need to be scheduled by
respective SLDCs. It required 45 minutes to make correction in schedules as per Regulations
in place and during this period; grid security could get endangered besides state getting
commercially penalized also.
20.5 Chairperson, SRPC stated that any load/generation management would require to be carried
out by Discoms. Being regulatory associated; the issue had to be dealt appropriately.
20.6 APTRANSCO was suggested to approach appropriate Commission on the issue, if deemed
fit.
21 ISSUES IN RESPECT OF CONNECTIVITY/LTA/LILO/INFIRM POWER
21.1 Hon‟ble CERC in its Order dated 28.09.2016 in respect of NLDC Petition No. 30/MP/2014
had passed the following Order:
„(a) CTU is responsible for planning and coordination with regard to inter-State
transmission system in consultation with all concerned as mentioned in Section 38 (2) of
the Act for development of efficient, conducted and economical system of development of
transmission system for smooth flow of electricity from the generating station to the load
centre. CTU is also responsible for providing non-discriminatory open access to the inter-
State Transmission System for use by any licensee or generator or consumer (subject to
permission by the State Commission). Therefore, while planning and developing the inter-
State Transmission System, CTU is required to take into consideration the applications for
connectivity and LTA received in accordance with Connectivity Regulations.
(b) CTU shall plan the inter-State Transmission System after carrying out the system
studies in accordance with CEA Connectivity Regulations. If on the results of the study it
appears to the CTU that connectivity is required to be granted by looping in and looping
out the existing or proposed transmission line, CTU shall include such LILO as part of the
coordinated planning and development of the inter-State Transmission System.
(c) Injection of infirm power and/or drawl of start-up power may be allowed in the interim
arrangement through LILO by RLDCs in accordance with the relevant provisions of the
Connectivity Regulations and Grid Code, keeping in view the grid security. If more than
one generator is injecting infirm power or drawing start-up power within the same
timeframe, then the concerned RLDC shall finalize schedule after discussing the same in
the Regional Power Committee in order to ensure that such unscheduled inter-changes on
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 41
account of injection of infirm power/ drawl of start-up power do not endanger grid
security.
(d) Injection of firm power shall not be allowed as a matter of principle. In exceptional
cases where the dedicated transmission line executed by the generator/ CTU/ inter-State
transmission licensee is unlikely to be commissioned matching with the COD of the
generating station or a unit thereof, concerned generator/ CTU/ inter-State licensee shall
be required to approach the RPC of the respective region three months prior to the
anticipated COD of the generating station for continuation of the LILO arrangements for
injection of firm power. The RPC in consultation with CTU after considering the proposal
in the light of the relevant factors can permit injection of firm power for a period of three
months which can be extended for another period of maximum three months. If the
dedicated transmission line is not commissioned within the period granted by the RPC,
then interchange of firm power shall not be permitted by the RLDC concerned on interim
LILO arrangement.
(e) CTU shall take up all the existing cases of connectivity on interim LILO with the
RPC of respective regions within a period of one month from the date of issue of this
order for review and decision on disconnection of the interim arrangements through
LILO. All such interim arrangements through LILO shall be disconnected within a
period of three months of the issue of this order unless the RPC grants extension for
continuation of LILO keeping in view of all relevant factors.
(f) As far as practicable, intra-State generating stations should not be granted interim
connectivity to ISTS for drawing start-up power or injecting infirm power. Only in
exceptional case, interim connectivity to intra-State generating stations may be granted on
the basis of explicit recommendations by the concerned STU.
(g) CTU shall review all cases where LTA taken by the generators have not been
operationalized on account of non-commissioning of the dedicated transmission line or
some of the system strengthening lines, even though the generators have been permitted to
inject firm power on short term basis. Based on the review, CTU shall operationalize the
part/full LTA in respect of the transmission lines which have been commissioned and raise
bills for transmission charges on the generators concerned.‟
21.2 SRPC noted the above.
22 TTC/ATC
22.1 In earlier Meetings the following had been noted:
In the 4th
Meeting of NPC held on 10th
December 2015 (MoM dated 1.1.2016), it had been
decided that to begin with, power system study for assessment of operational limits /
power transfer capability for each state would be done by the concerned RLDC in
association with concerned SLDC. Monthly TTC/ATC would be uploaded by SLDCs in
their respective websites and also communicated to concerned RLDC & NLDC
subsequently.
Converged PSSE base cases to be furnished to SRLDC.
SRLDC had stated that intra-state TTC/ ATC computations could also help in transfer of
power among SR-Constituents and they would render full assistance in this regard. For
instance, TN power could be sold to Telangana during the months of June-September.
There were constraints in WR and ER towards NR but there were no constraints in SR.
Constituents had been requested to nominate officials to coordinate with SRLDC to
identify these trading possibilities so that it would be commercially beneficial to all. All
states need to host ATC/TTC computations on their websites
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 42
CEA had stated that intra-state ATC/ TTC computations were very much essential to
implement GoI initiative of Discovery of Efficient Electricity Price (DEEP). In DEEP
platform, certain transactions were cleared but could not be materialized due to TTC/ATC
limitations. States need to furnish ATC/TTC computations, long term, medium term and
short power purchase agreement/plans and procurement through this platform. This would
help in reducing the cost of power purchase and uphold transparency. ATC/TTC
computations transparency has been achieved at CTU/RLDC level and same has to be
achieved at state level to ensure that all are on same platform.
Director (G & TM), APTRANSCO had assured that despite manpower shortage, they
would nominate some officials to get trained for ATC/TTC computations.
22.2 The following is the status in this regard:
State 5
months
LGB
Converged
PSSE Base
case
ATC/TTC
Computation
furnished to
SRLDC
ATC/TTC
Computation
posted on SLDC
website
Nodal
Officer
Status
Study
Group
AP Yes No No No No No
TS Yes Yes No No Yes Yes
KAR Yes Yes No No No Yes
TN Yes Yes No No Yes Yes
KER Yes Yes No No Yes Yes
Pudu NA No No No Yes No
22.3 TCC deliberations
SRLDC & SRPC had expressed concern that number of activities as enumerated in the
Table above were yet to be complied by entities. All concerned entities had been kindly
requested to initiate action to comply with the above.
22.3.1 SRPC deliberations
22.4 SRPC suggested for concerted action from the concerned for compliance of the above.
Nodal Officers details, wherever pending , was to be communicated to SRLDC & SRPC
by 15th
March 2017.
22.5 Revision of TTC between S1-S2 and formation of S1-(S2&S3)
22.5.1 The following issues had been raised in this regard:
TTC between S1-S2 got revised from 7,382 MW to 5,426 MW for the months of
December 2016 vide revision No.1 issued on 29th
November 2016. Reason for revision
was mentioned as limiting constraints getting shifted from (N-1) contingency for 400
kV Hiriyur-Nelamangala D/C to (N-1) contingency of 400 kV Udumalpet-Palakkad
D/C
KSEBL had stated that declaring Kerala as separate control area (S3) needs to be
deliberated in RPC forum.
No of correspondence had been exchanged by KSEBL, TANTRANSCO, SRLDC,
NLDC & SRPC secretariat (copies attached with OCCM) on this issue.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 43
NLDC on 30.12.2016 had formed S1 – (S2&S3) with TTC of 6,720 MW & S3 with
TTC of 2,900 MW.
TANTRANSCO vide letter dated 05.01.2017 (Annexure-XXVI) had raised certain
observations on the above and had stated that split bus arrangement should not hamper
the existing load pattern in TANTRANSCO network. It was suggested to provide
necessary SPS arrangement to restrict the overloading of feeders at Meywdai,
Checkanoorani and Tirnulveli 400 kV SS. A special system study Meeting was
requested to be convened in this regard. SRPC vide letter dated 06.01.2017 (Annexure-
XXVII) had furnished the clarifications to TANTRANSCO.
KSEBL vide letter dated 03.01.2017 (Annexure-XXVIII) had raised certain
observations in respect of PSSE base case for January 2017 and requested that TTC
declaration may be revised by the removing creation of S3. SRLDC clarification vide
their mail dated 05.01.2017 is given at Annexure-XXIX.
NLDC vide letter dated 23.01.2017 (Annexure-XXX) had informed about
operationalization of new bid area S3 wef 24.01.2017 for delivery date 25.01.2017.
KSEBL vide letter dated 31.01.2017 (refer Annexure-XVIII) had stated that formation
of S3 bid area and issues relating to partial commissioning of assets be discussed. The
proposed formation of S3 area has been proposed to be reviewed.
22.5.2 TCC deliberations
22.5.3 It was noted that a Meeting had been conducted on 17th
February 2017 to finalize SPS to
contain possible over loading of upstream elements of 220 kV Idukki-Udumalpet and
Sabarigiri-Theni lines due to split grid operation in Kerala system (MoM available on
SRPC website). SRPC Secretariat had thanked both TANTRANSCO and KSEBL for
coming to a mutual consensus on the issue of SPS.
22.5.4 SRPC noted the above.
22.6 Revision of TTC/ Curtailment to Southern Region
22.6.1 KSEBL vide letter dated 21.01.2017 (refer Annexure-IX) had expressed concern over
conservative approach for the determination of ATC-TTC of the region and downward
revision of TTC imposing restriction on import by KSEBL. Commercial impact on
additional purchases on account of such curtailment of Rs 7.50/unit. KSEBL had
requested that any curtailment of corridor was to be judiciously done by POSOCO; any
work has to be completed in the minimum possible time by PGCIL and the revival has to
be declared realistically so as to facilitate minimization of curtailment.
22.6.2 SRPC Secretariat vide letter dated 24.11.2016 (Annexure-XXXI) had invited attention
of NLDC to CEA‟s letter dated 22.11.2016 and deliberations in the 40th
Standing
Committee Meeting of SR held on 19.11.2016, wherein, it was agreed that the loading
limit of Raichur-Sholapur 765 kV 2xS/C can be enhanced from 2,500 MW to 2,750 MW
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 44
(under N-1 condition). Studies indicate that TTC to SR could be enhanced by 400 MW
i.e. from 6,650 MW to 7,050 MW.
22.6.3 Subsequently, it was noted that the TTC had been increased for 7 hours a day while
LTA/MTOA had increased from 3250 MW to 3384 MW for 24 hours.
22.6.4 KSEBL vide letter dated 31.01.2017 (refer Annexure-XVIII) had stated that POSOCO
may follow approved procedure for computation of TTC. KSEBL had stated that
POSOCO is curtailing TTC heavily when shutdown is availed on bus bars of Sub-station.
Similarly, S1-S2 ATC is seen reduced when one ICT is taken for shutdown without
considering the fact that 220 kV distribution may be possible even otherwise, without
affecting 400 kV line flows.
22.6.5 KSEBL vide letter dated 23.02.2017 (Annexure-XXXII) had stated that 500 MW
additionally created on Talcher-Kolar HVDC link with capital inclusion earlier is kept as
reserve to control the flow on AC lines. It was suggested to release of 500 MW for 10 hrs
which may be considered in ATC/TTC computations.
22.6.6 TCC deliberations
It was noted that with commissioning of Angul- Srikakulam- Vemagiri corridor, the net
increase in TTC was only around 200 MW (+800 MW on ER-SR and - 600 MW on
WR-SR). Taking SPS into consideration for TTC computations is supported by
provisions of IEGC as well as by CAC‟s recommendations approved by Hon‟ble
CERC. SPS logic presently configured for tripping of Aurangabad-Sholapur D/C lines
could be modified to tripping of S/C line and TTC could be computed accordingly.
After deliberations, the following was noted:
NLDC was suggested to revive TTC/ATC of 500 MW for 10 hours on Talcher-Kolar
HVDC which had been earlier operational (prior to commissioning of Raichur-
Sholapur link).
It was observed that constraint for import of power from NEW grid would be
Vemagiri- Gazuwaka line with the worst credible contingency of N-1 of 765 kV
Aurangabad-Sholapur line. TCC suggested NLDC to consider the SPS on 765 kV
Aurangabad-Sholapur D/C line (could be modified for tripping of one circuit of
Aurangabad-Sholapur) while selecting the worst credible contingency for assessing
TTC to SR.
Regarding, KSEBL issue it was noted that issue regarding curtailment of TTC due to
shutdown of bus had been taken up by SRPC Secretariat with NRCE. Other specific
issue of TTC curtailment for ICT shutdown etc could be deliberated in the
subcommittee Meetings.
22.6.7 SRPC deliberations
22.6.8 CMD, KSEBL stated that Kerala was undergoing severe drought and thus 10 hrs of
additional ATC on Talcher-Kolar HVDC link was needed to be released urgently. It
would be very useful for them during the summer.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 45
22.6.9 NLDC stated that this 500 MW capacity was being used to control the flows.
22.6.10 MS, SRPC noted that now there were three links in parallel with the HVDC link and
thus sensitivity on Raichur-Sholapur link with Talcher- Kolar HVDC flow change had
thus naturally decreased compared to earlier.
22.6.11 SRPC suggested NLDC to study the proposals of TCC. NLDC stated that they would
examine the proposals and revert back.
22.7 Planned shutdown of Talcher-Kolar HVDC link
22.7.1 In the 128th
OCC, the shutdown of Talcher-Kolar HVDC link had been agreed from 4th
-8th
March 2017.
22.7.2 TCC deliberations
In the Meeting, SRTS-II, PGCIL had informed that on account of non-availability of
experts /OEM from Germany, the shutdown was now planned during 6th
-11th
March
2017. Shutdown was critical in nature and was to be attended immediately as explained
in the sub-committee Meetings.
In view of non-convergence on the matter, it was agreed to deliberate the proposed
outage further in the SRPC Meeting.
TCC had categorically pointed out that in future at least PGCIL / Transmission Licensees
(of critical inter-regional and intra-regional links) should plan and complete maintenance
during June to December (in contingency only could be extended up to 20th
January) each
year so as to ensure that elements affecting TTC/ATC of SR, S1-S2 & S3 are available
during the peak months of February to April each year.
22.7.3 SRPC deliberations
22.7.4 GM, SR-II, PGCIL appraised SRPC of the requirement of the critical shutdown during this
period. The work involved insulator replacement in three regions, OLTC capital overhaul
and pole related works at both Talcher and Kolar ends. During day time, both poles would
be out since both the lines will be out. During night time, they would be bringing back one
of the poles except on two nights when both poles would be out.
22.7.5 SRPC stated that PGCIL should endeavour to bring one of the poles during evening peak
hours from 1730 hrs on each day.
22.7.6 CMD, KSEBL stated that March was a critical month for them being exam period and
shutdown of this nature needed to be avoided in future.
22.7.7 ED, SR-II, PGCIL informed that they had tied up with M/s Siemens this year with limited
leverage and the condition of the link was critical. From next year onwards, shutdown
would be taken up before December/20th
January.
22.7.8 APTRANSCO opined that it would be prudent to go for planned shutdown rather than face
any forced shutdown.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 46
22.7.9 SRPC concurred for the shut down as a special case. It also concluded that a TCC
recommendation as given below was to be complied in future:
PGCIL / Transmission Licensees (of critical inter-regional and intra-regional links) should
plan and complete their maintenance during June to December (in contingency only could
be extended up to 20th
January) each year to ensure that the elements affecting TTC/ATC of
SR, S1-S2 & S3 are available during the peak months of February to April each year.
22.8 Furnishing of Tripping files (FIR/DR/EL/TR) for forced outage of Inter-Regional
Grid-Elements
22.8.1 Since healthy working condition of grid elements and fail-proof operation of protection
systems in place are sine qua non of secure and integrated operation of grid, it is but
essential that a close vigil is maintained on the trippings of grid elements. To facilitate
this, whenever tripping of any grid element takes place, relevant tripping files
(FIR/DR/EL/TR) are being sought from concerned Constituents to carry out systematic
tripping analysis and identify suitable remedial measures to be taken to avoid recurrence
of such events in future.
22.8.2 Timely submission of tripping files is mandated by Regulation 5.2 (r) of IEGC, as per
which all Users, Utilities, STU/ SLDC and CTU are required to furnish for analysis
purpose the relevant information relating to tripping events in their system along with
Disturbance Recorder (DR) and Event Logger (EL) to RLDC/ RPC within 24 hrs of
occurrence of the same. No User, SLDC/STU or CTU shall block any data/information
required by the RLDC and RPC for maintaining reliability and security of the grid and
for analysis of an event.
22.8.3 Though this has been religiously pursued for all kinds of forced trippings, instances of
delayed or non-furnishing of sought tripping details have been witnessed more frequently
in case of trippings involving inter-regional grid elements, owing to their being in
different operational jurisdiction.
22.8.4 This particular issue of timely reporting of inter-regional grid elements had also been
discussed in the 11th
Meeting of Protection System Analysis Group (PSAG-11) of SRPC
held on 24.01.2015 at HVDC, Bhadravathi, when the following was agreed upon:
Reporting of events of tripping by Bhadravathi
SRLDC is maintaining a web portal for submission of DR/EL/TR of any
tripping/event by the utilities of SR. SRLDC will provide user Ids for WRTS-I
and Bhadravathi S/S to post the DR/EL/TR of any tripping at Bhadravathi &
POWERGRID Stations of WR – SR links within 24 hours on this web portal.
SRLDC will also share the web application package with WRLDC to facilitate
creation of similar web portal to get the details of any event by WRLDC.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 47
22.8.5 Subsequent to this Meeting, User-ID‟s and Password‟s had been provided to WRTS-I and
Bhadravathi S/S by SRLDC for uploading required tripping files. However, timely
furnishing of required information necessitated by tripping of WR-SR links was observed
to be not satisfactory in majority of the cases. Recent trippings of HVDC Bhadravathi
Pole-1 on 02.12.2016 and 19.12.2016 are a case in point. PGCIL was therefore kindly
requested to ensure compliance of above mechanism by WRTS.
22.8.6 Similarly, in view of newly commissioned/ upcoming links of SR-ER, PGCIL was also
requested to ensure posting of tripping files (FIR/DR/EL/TR) by their ER counterparts of
any tripping of SR-ER links within 24-hr on SRLDC web portal, for which separate
User-ID and Password would be given.
22.8.7 TCC deliberations
MS, SRPC had appraised TCC of the requirement to have tripping files of WR and ER
contiguous S/S which assisted in analysis of events in the Meetings of PCSC. PGCIL
was requested to take up the issue suitably with WRTS & ERTS for uploading relevant
tripping files on SRLDC web portal.
PGCIL had assured that they would take up with WR and ER counterparts to comply
with Regulation 5.2 (r) of IEGC in furnishing relevant tripping files (FIR/DR/EL/TR)
relating to trippings of SR-ER and SR-WR links in SRLDC web-portal. SRLDC was
requested to kindly provide User-ID and Password to ERTS-I, PGCIL for uploading the
required tripping files.
22.8.8 SRPC noted the above.
23 UPCOMING TRANSMISSION SYSTEM
23.1 In the 30th
Meeting of SRPC, it was noted that a Committee for finalization of compensation
in regard to Right of Way (RoW) for transmission lines in urban areas had been constituted
by MoP vide OM dated 11.08.2016. Principal Secretaries of Karnataka and Kerala from
Southern Region were also Members of this Committee.
23.2 Pending transmission elements in WR and SR for proper utilization of 765 kV Raichur-
Sholapur line (Out of planned 18 elements)
23.2.1 Updated status of pending transmission elements in WR and SR for proper utilization of
765 kV Raichur - Sholapur lines (out of planned 18 elements) is furnished below please:
Sl.
No
Name of
Transmission
Element
Exe.
Agency
Sch.
CoD
Expected
date
Remarks
1 400 kV Gooty-
Tumkur D/C line
PGCIL June
2014 Commissio
ned on
01.12.2015
Power flow of around 550
MW observed with temporary
reconfiguration at Bidadi SS.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 48
23.2.2 In the earlier Meetings, following had been noted:
SR-II, PGCIL had informed that there was not much progress in three districts, Bengaluru
Urban, Bengaluru Rural and Tumkur. Only 5 km of stringing work was pending in
Tumkur-Yelahanka line.
KPTCL had informed that Govt of Karnataka was seized of the issue. Recently, Hon‟ble
Chief Minister had reviewed the matter and directed the concerned to deploy police force,
wherever required. With directives from the top, they were hopeful that issues would be
resolved at an early date. KPTCL had informed that Additional Chief Secretary had also
intervened in this matter.
PGCIL had informed that in recent orders, Hon‟ble CERC had directed that transmission
charges are to be paid by state utilities, in case downstream network is not ready. In the
recent Grid Code Amendment, the Commission has stated that there has to be an
Implementation Agreement between the respective state and PGCIL. Firm dates for
downstream evacuation system at Madhugiri and Yelahanka needs to be confirmed by
KPTCL for proper coordination.
23.2.3 Hon‟ble Commission in its ROP dated 15.12.2016 in respect of Petition No 54/MP/2016,
IA No 48/2016 & 403/TT/2014 had stated
„3. The Commission observed that comments sought vide letters dated 7.11.2016 and
28.11.2016 from CEA have not been received. The Commission directed the staff of
the Commission to study the comments furnished by SRLDC and to seek the comments
from SRPC on the PGCIL‟s contention that Gooty-Madhugiri 400 kV D/C line along
with the associated bays is system strengthening scheme and it is not merely to serve
the distribution companies of Karnataka and whether the line could be utilized
effectively with the commissioning of Madhugiri-Bidadi line in the absence of
downstream system of Karnataka.
4. Subject to the above, the Commission reserved the order on the issue of
"maintainability".‟
SRPC Secretariat had furnished comments as directed by Hon‟ble CERC.
23.2.4 SRTS-II, PGCIL vide letter dated 24.11.2016 (Annexure-XXXIII) addressed to KPTCL
had informed that with the administrative support of Karnataka State Government, the
ROW issue of 400 kV Nelamangala-Hoody LILO at 400 kV Yelahanka Station was
resolved. It was requested that the 220 kV evacuation system of KPTCL at Yelahanka SS
may kindly be expedited so as to facilitate the evacuation power through the 220 kV
downstream systems.
2 400/220 kV , 2 x
500 MVA, 63
MVAR Reactor
Tumkur S/S
PGCIL June
2014 Commissio
ned on
01.12.2015
Downstream network not
available
3 400 kV Tumkur-
Yelahanka D/C
line
PGCIL June
2014
Severe RoW problem. 400 kV
Yelahanka S/S is ready.
30th
TCC: SR-II informed that in the recent Meeting held on
18.02.2017 with Secretary, Power and Chief Secretary, GoK,
police protection was assured to carry out the works.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 49
23.2.5 Status of downstream at Madhugiri and Yelahanka is given below:
23.3 Upcoming inter-regional transmission schemes
23.3.1 KSEBL vide letter dated 31.01.2017 (refer Annexure-XVIII) had proposed to review the
status of upcoming transmission systems. It was stated that early commissioning of 765
kV Wardha - Nizamabad line and Angul – Srikakulam lines with associated lines is
urgently required to meet the power requirement. However, commissioning of above lines
and enhancement of ATC has not materialized till date resulting in alarming situation.
23.3.2 Updated status is furnished below please:
S S.No. Transmission Element Remarks
a) 765 kV Wardha – Nizamabad-
Hyderabad D/C line
Original Schedule by May 2018.
PGCIL trying to complete by June
2017.
30th
TCC:
PGCIL had informed that by March 2017, Wardha - Nizamabad and
Dichipally – Dichipally (HTLS) lines would be completed. Nizamabad-
Maheshwaram (Hyderabad) section would be completed by June 2017.
TSTRANSCO confirmed that they would be bringing up the
downstream system in the same timeframe.
PGCIL stated that the Tariff for the above elements should be allowed
as and when the elements come up.
TCC recommended the same for the approval of SRPC.
31st SRPC :
SRPC agreed that Tariff for above elements would be allowed as and
when the elements come up.
Sl.
No
Name of
Transmission
Element
Exe.
Agency
Sch. CoD Expected
date
Remarks
Tumkur downstream
1 220 kV Tumkur –
Antharasana Halli
D/C
KPTCL Tenders for
the above
line had been
placed on
18.03.15 and
it would take
18 months
for
completion
30th
TCC
update :
March 2017
2 220 kV Tumkur
(400 kV) S/S – 220
kV Tumkur S/S
D/C
KPTCL 30th
TCC
update :
March 2017
Yelahanka downstream
1 220 kV Yelahanka
(400/220 kV) S/S-
220 kV Yelahanka
S/S D/C Cable – 5
kM
KPTCL (5.875 kM) 30th
TCC
update :
December
2017
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 50
b) WR-SR 6000 MW HVDC Bipole Link
[Raigarh (Chhatisgarh) - Pugalur-
Trichur (TN/KER)]
Nov’ 2019
30th
TCC:
PGCIL had informed that package for the terminal at both ends had been
awarded. Package for the line is expected to be awarded during March 2017.
c) 765 kV Angul - Srikakulam PS D/C
line
765 kV Angul-Srikakulam D/C:
COD from 01.02.2017
765 kV Srikakulam-Vemagiri
(PVTL) D/C: COD from
01.02.2017
1500 MVA ICT-I at Vemagiri:
COD from 01.02.2017
240 MVAR Bus Reactor I & II at
Vemagiri PS: COD from
01.02.2017.
LILO of 400 kV Gazuwaka-
Vijayawada S/C at Vemagiri PS:
COD from 01.02.2017.
80 MVAR Bus Reactor at Vemagiri
PS: COD from 01.02.2017.
240 MVAR Line Reactor at
Vemagiri and Srikakulam PS for
both circuits of Srikakulam PS –
Vemagiri PS 765 kV D/C line:
COD from 01.02.2017.
Other associated elements by
Jun’2017-Dec’ 2019
30th
TCC:
TCC noted the above.
d) Additional inter-Regional AC link for
import to Southern Region, i.e.,
Warora - Warangal - Hyderabad-
Kurnool 765 kV link
TBCB, PFCCL- BPC Schedule was 40 months from the
transfer of SPV (around mid-
2019).
Discussed in 36th
Meeting of
Empowered Committee scheduled
for 26.07.16
Hon‟ble CERC in its Order dated
29.09.2016 in respect of Petition
No 111/TL/2016 had granted
Transmission License to Warora-
Kurnool Transmission Limited
(WKTL).
29th
TCC:
M/s Essel Infra has been selected through TBCB. SPV was transferred on
06.07.2016 with a schedule of 40 months.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 51
e) System strengthening within SR for
transmitting power beyond Vemagiri
TBCB- RECTPCL-BPC–Some
scope of work/ reactive
compensation modified.
The project has been awarded to
PGCIL under TBCB, and was
expected by April 2019.
30th
TCC:
All associated transmission system is scheduled to be completed by April
2019. The dispersal of power from Kadapa - Madhugiri needs to be
expedited/ensured.
23.3.3 SRPC noted the above.
23.3.4 Updated detailed status of upcoming inter regional scheme is furnished at Annexure-
XXXIV.
23.4 Status of various Associated Transmission Systems (ATS) of upcoming generators
23.4.1 Common System Associated with NTPL / Costal Energen Private Ltd / Ind-Barath
Power Ltd, Tuticorin Area
Updated status of associated links is furnished below:
Transmission
Elements
Line
Lengt
h
(ckm)
Impleme
nting
Agency
Sch
COD
Ant
COD/
Act
COD
Constraints/
Remarks
765 kV D/C Tuticorin
PS - Salem PS line
(Dharmapuri) (initially
charged at 400 kV)
731 PGCIL Dec'14 COD from 13.11.2016
400 kV D/C Salem PS
– Salem line
120 PGCIL COD from 23.10.2016
765 kV S/C Salem PS
(Dharmapuri) -
Madhugiri P S line
(initially charged at
400 kV)
245 PGCIL Dec'14 March-
17 29
th TCC update:
Severe ROW
problems in
Karnataka. Critical.
Covered under
PRAGATI.
765/400 kV Salem PS
(initially charged at
400 kV)
PGCIL COD from 13.11.2016
400 kV D/C Coastal
Energen – Tuticorin
PS
54 Coastal
Energen
Ckt I charged on 29.10.2016
Ckt II charged on 27.10.2016
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 52
23.4.2 Transmission system associated with IPPs (IL&FS) of Nagapattinam/Cuddalore Area
Updated status of associated links is furnished below please:
(i) Transmission system associated with IPPs of Nagapattinam/Cuddalore Area–
Package A
Transmission
elements
Line
Length
(ckm)
Imp. Agency Sch
COD
Ant.
COD
Constraints/
Remarks
Nagapattinam PS-
Salem New
765 kV D/C line
406 Power grid
Nagapattina
m-
Madhugiri
Transmission
Company
Limited
(PNMTCL)
(A subsidiary
of PGCIL)
Mar‟
15 COD from 21.10.2016
Salem New –
Madhugiri 765
kV S/c line.
219 30th
TCC:
June
2017
Severe RoW issues
being faced in
Karnataka.
(ii)Transmission System Associated with Contingency plan for Evacuation of Power
from IL&FS (2x600MW)
Following may please be noted in this regard:
It was noted that some stringing/ upgradation was pending within NLC Complex.
These works had been envisaged as a contingency evacuation for IL&FS.
SR-II, PGCIL had informed that they would be taking up work during shutdown of one
of the units at NLC TS-I Exp. There may be one day requirement of shutdown of both
the units at NLC TS-I Exp.
A Meeting was held regarding Transmission System Associated with IPPs
Naggipattnam/Cudalure Area package A held on 15.09.2016 in CEA. The minutes are
enclosed as Annexure-XXXV.
23.4.2.1 TCC deliberations
It was noted that Hon‟ble CERC in its order dated 07.02.2017 in respect of Petition
No.222/TT/2016, in respect of TANGEDCO issues had directed Chief (Engineering),
CERC to look into issues raised by TANGEDCO with reference to various applicable
regulations and submit a report within a month.
23.4.2.1 SRPC noted the above.
23.4.3 Evacuation of Power from HNPCL (1,040 MW) Power Plant (i) Updated status of associated links under APTRANSCO‟s scope is furnished below:
Transmission
Elements
Line
Length
(ckm)/M
VA cap.
Implementing
Agency
Target
Date
Target
date
completio
n
Constraints/
Remarks
Startup Power Line
from M/s. HNPCL
TPP to 400/220 kV
Kalpakka SS
7 APTRANSCO Commissi
oned on
07.02.14
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 53
400 kV TM D/C
Line from HNPCL
- Kamavarapukota
S/S (Lot-I, II &
III)
200 APTRANSCO Jul „15 30th
TCC:
June 17
Purchase Order
issued on
03.11.2015.
400 kV TM D/C
Line from
Kamavarapukota
S/S - Vemagiri 400
kV S/S
185 APTRANSCO 30th
TCC:
June 17
All the
foundations, tower
erections and
stringing works are
completed.
400 kV TM D/C
Line from
Kamavarapukota
S/S - 400 kV
Chinna Korukondi
S/S
179 APTRANSCO Sept.
„15 30
th TCC:
June 17
Test charged on
20.10.2016
Kamavarapukota
Substation
2x315
APTRANSCO Mar
„16 30
th TCC:
Mar 17
2 Nos. of 400 KV
Bay Extensions at
existing 400/220
KV Kalpaka S/S of
HNPCL
APTRANSCO Commissi
oned on
18.11.13
(ii) Updated status of associated links under TSTRANSCO‟s scope is furnished below:
Transmission
Elements
Line
Length
(ckm)/M
VA cap.
Implemen
ting
Agency
Target
Date
Target
date
completi
on
Constraints/
Remarks
400 kV TM D/C Line
from Chinna Korukondi
- 400 kV Suryapet S/S
170 TSTRAN
SCO
30th
TCC:
Charged
Suryapet S/S -
Nandiwanaparthi S/S
400 kV Quad D/C Line
240 TSTRAN
SCO
Mar‟15 Test
charged
on
28.07.16
400 kV Quad D/C Line
from Nandiwanaparthi
S/S - Shankarapally S/S
222 TSTRAN
SCO
Mar‟15 30th
TCC:
Charged
Suryapet Substation
400/230/132 & 2 Nos.
of 400 KV Bay
Extensions at 400 KV
Shankarapalli S/S
2x315
TSTRAN
SCO
30th
TCC:
ICT-I
Charged
ICT-II by
Mar 17
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 54
23.4.4 Transmission system of KPTCL for evacuation of power from Yermarus TPS (2x800
MW)
Updated status of associated links is furnished below:
Transmission elements Imp.
Agency
Line
Length
(ckm)/
MVA
cap.
Sch. COD Constraints/ Remarks
Bellary 400 kV PS near
„BTPS‟
JSWEL
(KPTCL
)
30th
TCC:
Mar 17
Completed
Gulbarga 400/220 kV
substation
KPTCL 2x500 Land acquired. Geo tech
survey work will be
awarded within a week.
Bill of Materials
prepared and estimate to
be prepared.
Yermarus TPS - Gulbarga
400 kV D/C line (QM)
KPTCL Detailed survey
completed.
Estimate is being
prepared.
400 kV SS at
Chikkanayakanahalli (C.N
Halli) near “Loop in Loop
Out” (LILO) point on the
Nelamangala – Talaguppa
400 kV lines to Hassan.
KPTCL 2x500
MVA
In 39th
SCPSPSR a
step down
SS with 2 x
500 MVA,
400/220 kV
ICTs was
agreed.
30th
TCC:
Land yet to be identified.
Alternate site at
Bindikere is under
consideration
LILO of both the circuits of
Nelamangala – Talaguppa
400 kV lines to the proposed
pooling station near CN
Halli.
KPTCL Linked with CN Hally
station
Termination of 400 kV D/C
line feeding 400/220 KV
station at Hassan from
Nelamangala – Talaguppa
line at CN Halli 400 kV
pooling station.
KPTCL After CN Halli land
identification, survey
would be taken up.
Yermarus TPS - Bellary
Pooling Station 400 kV D/C
line with quad moose
conductor
KPTCL 285
(400 kV
MC Line
(5.138
Kms) and
400 kV
DC line
(137.355
Km)
Expected by
Aug‟17
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 55
totally for
a route
length of
142.493
Kms)
Bellary Pooling Station -
C.N.Hally 400 kV D/C line
with quad moose conductor
KPTCL 360 Survey
using MST
conducted
and reports
submitted to
zonal office
vide ltr no
:1682-83
Dt:30.06.15
and the
same is
submitted
for approval
to
CEE(P&C)
vide letter
no. 2504-06
dt 7.7.2015
29th
TCC update:
Part of the work from
Rampura-Jagalur 65 kM
had been awarded.
Bellary PS to Madhugiri
line (765/400kV V.N.Pura
substation (PGCIL)
a) Madhugiri to Rampura
limits): 400kV DC line
with Quad Moose ACSR
(188.74 Kms)
b) Bellary pooling Stn 400
kV to Rampura limits
(KelaginaKanavi): (43.018
Kms)
KPTCL
Under
Executio
n by KECIL
By
Kalpatar
u PTL
377
86
Earlier
schedule:
22-Dec-16
30th
TCC
update:
Mar‟17
Earlier
schedule:
24-Apr-17
30th
TCC:
Completed
Bellary TPS – Bellary
Pooling Station 400 kV D/C
line with quad moose
conductor
KPTCL 10 In 39th
SCPSPSR it was
agreed to drop the
proposal.
Dropped
De-link 400 kV S/C line
running between RTPS-
BTPS-JSW-Guttur with
JSW Bus
KPTCL
Nov‟16 Agreed in 39th
SCPSPSR
400 kV M/C line from
JSW to BPS is under
progress, once this is
commissioned the link
between JSW & BPS will
be delinked.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 56
23.4.5 Transmission System required for evacuation of power from Kudgi TPS (3x800 MW
in Phase-I) of NTPC Limited
Updated status is furnished below:
Following had been noted in earlier Meetings:
Three 220 kV D/C lines were planned evacuation lines at 220 kV level to Vajramatti,
Basavana Bagewadi and Bijapur. The Vajramatti line had just been awarded and could
take about 1 year. There were some RoW issues in that area. Construction from B
Bagewadi and Bijapur ends had already commenced and about 50 % of the lines are
completed
23.4.6 Transmission System for evacuation of power from Singareni Collieries Generating
Project (2 x 600 MW)
Following is the status update:
JSW TPS – Bellary Pooling
Station 400 kV D/C line
with quad moose conductor
KPTCL 30th
TCC:
Completed
Additional JSW TPS –
Bellary Pooling Station 400
kV D/C line with quad
moose conductor
Agreed in 39th
SCPSPSR
400 kV BTPS-Guttur D/C
line (QM)
Agreed in 39th
SCPSPSR
Transmission
Elements
Imp. Agency Schedul
ed CoD
Revised
Target
Date
Constraints/ Remarks
400 kV Kudgi TPS –
Kudgi (PG) 2xD/C
Line
M/s Kudgi
Transmission
Limited
(L&T
Infrastructure
Development
Projects Ltd.)
Feb-15 2015-16
One D/C line Kudgi TPS –
Kudgi (PG) declared on
deemed CoD from 04.08.15
Kudgi (PG)-Tumkur
765 kV D/C Line
Dec - 15 Trial operation completed on 23.09.2016
Tumkur - Bidadi 400
kV D/C (quad) Line
Trial operation completed on 24.08.2016
400/220 kV ICT 2 at
NTPC Kudgi
Switchyard
NTPC Charged on 06.09.2016
400 kV Bus Reactor -2 NTPC Charged on 21.09.2016
Transmission
elements
Length
(ckm/MVA
capacity)
Imp. Agency
Sche
duled
CoD
Target
date of
Completi
on
Constraints/
Remarks
1. 400 kV Singareni- Gajwel in two parts
a) 400 kV Jaipur
(Singareni) -
149.636
TSTRANSCO
Comp
leted
Charged
in Nov 15
Reactor also
commissioned
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 57
23.4.7 Transmission System for Rayalaseema TPS (600 MW)
Following is the status update:
23.5 Status of upcoming links having impact on S1-S2
Following is the updated status:
Sl.
No.
Transmission
Element Schedule
Expected
Commissio
ning Date
Remarks
1 400 kV
Somanahalli-
Dharmapuri PS
Jun‟15 June 2017 Severe RoW problems being faced in
Karnataka. Critical issues related
compensation not yet resolved.
Rangampet D/C
(Quad)
b) 400 kV
Rangampet- Gajwel
D/C (Quad)
174.852
TSTRANSCO
Comp
leted
Commissi
oned on
13.11.201
5
2. 400 kV Singareni-Nirmal in two parts
a) STPP, Jaipur –
Jagityal
142 TSTRANSCO 30th
TCC:
June‟ 17
Works Awarded
on Nov‟15.
b) Jagityal - Nirmal 148 TSTRANSCO Feb
17
30th
TCC:
June‟ 17
Works Awarded
on Oct‟15.
Transmission
elements
Length
(ckm/M
VA
capacity)
Imp. Agency
Schedule
d CoD
Target date
of
Completion
Constraints/
Remarks
RTPP (Stage - IV)
- Chittoor TM D/C
Line
(a). RTPP - Pedda
Jamgam Palli
(P.J.Palli)
(b). P.J. Palli-
Chittoor
(c) 220 kV
Muddanur(RTPP)-
Chinakampally 3
& 4
432
216
212
121
APTRANSCO
30th
TCC:
Mar‟17
30th
TCC:
Mar‟ 17
Commissioned
on 16.06.2016
400/220 kV,
Kalikiri S/S
2 x 315
MVA
APTRANSCO Sep‟17 30th
TCC:
2018-19
PO is placed in
Nov-15.
LILO of both
circuits of
Rayalseema IV-
Chittoor 400 kV
D/C line at Kalikiri
81
APTRANSCO
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 58
2
400 kV
Mangalore
(UPCL ) -
Kasargode-
Kozhikode
In the 39th
SCPSPSR, it was noted that
the process of implementation of 400
kV UPCL-Kasargode-Kozhikode line in
TBCB or regulated tariff in compressed
time schedule will be initiated as
applicable.
23.5.1 In earlier Meetings the following had been noted:
PGCIL had informed that regarding 400 kV Dharmapuri - Somanahalli line, DC
(Urban) had ordered compensation of 100 % of fair value for tower footing and 55 %
for line corridor. With this, cost of 30 kM line was working out to as high as Rs 90
crore. SR-II, PGCIL had informed that ROW issues for 400 kV Somanahalli -
Dharmapuri PS were yet to be resolved and it would take around two months to
complete the work once the ROW issues are resolved.
23.5.2 TCC deliberations
Shutdown was approved from 20.02.2017 to 20.03.2017 for Hosur-Somanahalli for
stringing of 400 kV Dharmapuri – Somanahalli line. However, this shutdown could
not be availed on account of ROW issues. Status of this line was also discussed in
the Meeting of Secretary, Power with Chief Secretary, GoK.
23.6 Critical Intra-regional transmission elements
Following is the status update:
Sl.
No. Transmission Element Expected CoD Remarks
1 765 kV Salem- Tumkur
By PGCIL (219 ckm)
Through TBCB
30th
TCC:
June 2017
30th
TCC:
Severe RoW being faced in
Karnataka.
2 400 kV Edamon-Kochi
(297 ckm)
30th
TCC:
Aug‟18
Being monitored under
PRAGATI
23.6.1 TCC deliberations
KSEBL had informed that the compensation would be paid from 01.03.2017 onwards.
SR-II, PGCIL had informed that a new contract would be awarded by March 2017 with
likely schedule of 18 months. Works would commence once compensation issues are
settled.
23.6.2 SRPC deliberations
23.6.2 CMD, KSEBL confirmed that the compensation disbursement was planned from 1st March
2017 onwards and ROW of around 10 kms in phases would be handed over to PGCIL to
take up the works. With disbursement, the resistance was likely to come down. From 1st
April 2017, PGCIL was likely to commence works.
23.7 400 kV Trichur-Kozhikode line (Madakkathara-Areakode)
In the 39th
SCPSPSR it had been noted that Madakkathara-Areakode (Kozhikode) -
Kasaragode 400 kV D/C link may be taken up by KSEBL.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 59
23.8 Requirement of additional ICT at 400 kV sub-station at Kozhikode
23.8.1 In the 39th
SCPSPSR, 1 x 500 MVA ICT at Areakode (Kozhikode) substation was agreed.
Subsequently, KSEBL vide letter dated 20.02.2016 had stated that PGCIL may take
necessary steps to provide additional ICT at 400 kV substation at Kozhikode temporarily
by using spare 315 MVA ICT till 500 MVA ICT is available. KSEBL had informed that
PGCIL had given an estimate of Rs.3 Crores for which approval was required. They
would intimate their decision within a week‟s time.
23.8.2 PGCIL had informed that 500 MVA Transformer approved in the Standing Committee
was under NIT with a schedule of one year.
23.8.3 Subsequently, KSEBL had approved PGCIL‟s proposal.
23.8.4 TCC deliberations
KSEBL had informed that 3rd
ICT of 315 MVA was likely to be commissioned by first
week of March 2017.
KPTCL had stated that KSEBL was continuing to draw 50-80 MW on Kadakola -
Kaniampetta line. Thus, upstream lines were getting over loaded and affecting essential
loads. KSEBL had stated that after commissioning of 3rd
ICT at Kozhikode, the loading
on this line would get reduced.
23.8.5 SRPC deliberations
23.8.6 CMD, KSEBL stated that 3rd
ICT was expected by 5th
/6th
March 2017. This would provide
relief to northern parts of Kerala.
23.9 NLDC vide letter dated 20th
January 2017 (available in NLDC website) had highlighted
following transmission constraints in Operational Feedback for the quarter October-
December 2016 in respect of SR:
Transmission Line constraints:
400 kV Nellore Pooling Station -Nellore D/C line
400 kV Gooty-Nelamangala line & 400 kV Gooty- Somanahalli line. Loading on
these lines have been partially relieved after 400 kV Tumkur-Bidadi-Nelamangala
rearrangement.
400 kV Udumalpet- Palakkad D/C line
400 kV Hiriyur-Nelamangala D/C line
220 kV Bangalore Metro Network
Overloading of 220 kV Shoolagiri-Hosur(TN)-Yerrandahalli-Somanahalli S/C line
220 kV Sharavathy-Shimoga lines (3 nos) and 220 kV Sharavathy-Talaguppa (3 nos)
Constraints for Rayalaseema TPS Generation Evacuation – 30th
TCC: it was noted
that the constraints has been removed which was confirmed by SRLDC.
Transformation Capacity at 400/220 kV Kozhikode SS
Constraints in Chennai 230 kV System
Overloaded 220 kV Lines in Tamil Nadu
Constraints in 230 kV evacuation lines of MTPS and Kundah complex
Constraints in wind evacuation
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 60
ICT Constraints
400/220 kV 2 x 315 MVA ICTs at Gazuwaka – 30th
TCC: APTRANSCO expressed
concern on the overloading of the ICTs. SR-I, PGCIL informed that it could be
replaced with 2 x 500 MVA ICTs.
31st SRPC: It was noted that the requirement needs to be ratified in the Standing
Committee. SRPC approved in principle for 2x500 MVA ICTs in place of existing
ICTs. PGCIL was suggested to take up the issue in the Standing Committee for
ratification.
400/220 kV 2 x 315 MVA ICTs at Vemagiri
400/220 kV 3 x 500 MVA ICTs at Nelamangala
400/220 kV 3 x 500 MVA ICTs at Somanahalli
400/220 kV 3 x 500 MVA ICTs at Hoody
400/220 kV 2 x 315 MVA ICTs at Guttur
400/220 kV 2 x 315 MVA ICTs at Hiriyur
400/220 kV 2 x 315 MVA ICTs at Narendra
400/230 kV 2 x 315 MVA ICTs at Pugalur
400/230 kV 2 x 315 MVA ICTs at Trichy
400/230 kV 2 x 315MVA ICTs at Madurai
400/230 kV 2 x 315MVA ICTs at Thiruvalam
400/220 kV 2 x 315 MVA ICTs at Kozhikode
Respective entities were requested to kindly identify and implement short term and long term
measures to overcome these constraints in a time bound manner.
23.10 40th
Standing Committee on Power System Planning for Southern Region
CEA had issued Minutes of the 40th
SCPSPSR (MoM available at CEA website) held on
19th
November 2016.
23.11 SRPC noted the above.
24 UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH
TRANSMISSION NETWORK
24.1 Status update of the upcoming evacuation schemes in Southern Region for renewable as
given below is furnished at Annexure-XXXVI:
S.No. State Project Type of
Renewable
Project
Capacity
in MW
1 TS Gattu Solar Park Solar 500
2 AP N.P. Kunta Solar Park Project Solar 1500
3 AP Ghani/ Panyam Solar Project Solar 1000
4 AP Aspiri Wind Project Wind 1000
5 AP Suzlon Power Project Wind 300
6 AP Various, at Uravakonda area Wind 1361
7 AP Various, at Kondapuram area Wind 1109
8 AP Various, at Hindupur area Wind 680
9 AP Mailavaram dist. Kadapa Solar 1000
10 AP Talaricheruvu Dist Ananthpur Solar 500
11 KA Tumkur(Pavagada) Ultra Mega Solar
Park
Solar 2000
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 61
12 KA Gadag Wind Project Wind 80
13 KA Dhoni Wind Project Wind 587
14 KA Harti Wind Project Wind 244
15 KA Gadag Wind Project Wind 90
16 KA Gadag Wind Project Wind 197
17 KA Jagalur Wind Project Wind 177
18 KA Thalak Wind Project Wind 250
19 KA Thalak Solar Project Solar 200
20 KA Guttur Wind Project Wind 518
21 KA Davanagere and Chitradurga Wind 60
22 KA Davanagere and Chitradurga connected Wind
(proposed)
406
23 KA Athani Wind Wind 240
24 KA Chikkodi Wind 92
25 KA Chikkodi, Ghatprabha, Belgaum Wind 110
26 KA Chikkodi, Ghatprabha, Belgaum Wind 418
27 KA Atria Hydel Hydel 12
28 KA Cauvery Hydro Hydro 3
29 KA Pioneer Power Hydro 24.75
30 KA Pioneer Power Hydro 24.75
31 TN Mytrah Energy (India) Wind 300
32 TN Samimeru Wind farms Wind 48.5
33 TN SISL Green Infra Wind 48.5
34 TN Samiran Udaipur Wind farms Wind 48.5
35 TN Shivam Filaments Wind 48.5
36 TN R.S. India Global Energy Wind 480
37 TN Suzlon Power Infrastructure Wind 1000
38 TN Suzlon Power Infrastructure Wind 350
39 TN Vestas Wind Technology India Wind 150
40 TN Wind Projects at Samugarengapuram Wind 600
41 TN Kamuthi Solar Park Solar 1000
42 KER Kottathara Project Wind 80
43 KER Vettathur Project Wind 80
44 KER Kuyilimala Wind Project Wind 14.25
45 KER Kasargode Solar Project Solar 200
Data not present in draft NEP
Vol.2(Trans.)
46 AP Gamesa Renewable Pvt. Ltd.(Kurnool) Wind 350
47 AP Gamesa Renewable Pvt. Ltd.(Dhone) Wind 300
48 AP Galiveedu, Kadapa Solar 500
49 KA Ostro Dakshin Power Pvt. Ltd. Wind 300
50 KA Orange Ashok Wind Power Wind 250
51 KA Renew Wind Energy (TN) Pvt. Ltd.
(Koppal)
Wind 400
52 TN Inox Wind Infrastructure Services Ltd Wind 500
53 TN Vagarai Suzlon wind farms Wind 200
54 TN Regen Wind Farm (Vagarai) Wind 600 or 384
55 TN Renew Power Ventures Pvt. Ltd.(Karur) Wind 400
56 TN Orange Sironj Wind Power Pvt. Ltd. Wind 200
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 62
57 TN Ostro Alpha Wind Pvt. Ltd. Wind 400
58 TN BLP Energy Pvt. Ltd. Wind 250
59 TN Greenmint Power Pvt. Ltd. Wind 200
60 TN Gamesa Renewable Pvt. Ltd.
(Thoothukudi)
Wind 400
61 TN Sitac Kabini Renewables Pvt. Ltd. Wind 250
62 TN Gamesa Renewable Pvt. Ltd. (Karur) Wind 200
63 TN Green Infra Wind Energy Ltd. (Tirpur) Wind 250
64 TS Enerfra Projects (India) Pvt. Ltd. Wind 300
24.2 KSEBL vide letter dated 23.02.2017 (refer Annexure-XXXII) had informed that in the LTA
Meeting of SR constituents held on 21.02.2017 regarding connectivity of IPPs (Wind), it was
deliberated that CTU has to build additional substations for giving connectivity as per the
connectivity application of the Wind IPPs. None of the wind developers are willing to get
connected to STU, reported to be in view of the exemption of open access charges. It was
also noted that the requirement projected by the wind developers was with (N-1) security in
some cases. This would necessitate more number of bays in the 400 kV S/s, CEA had
suggested some of the links with one circuit instead of double circuit. CTU had pointed out
that some of the existing 400 kV S/s do not have expandability and proposed new substations
near the existing 400 kV S/s for providing connectivity to the grid. The scope of the wind
developer being limited to the 220 kV line from the generation point to the 400 kV S/s up to
the 220 kV bay, the balance of expenditure is impending on the LTA holders. In some of the
cases discussed, it was evident that injection of power is likely to cause transmission
constraints. To a query, CTU and CEA opined that the system strengthening can be
considered when such applicants apply for LTA. The probability of achieving the generation
now proposed by them is also to be considered. The approach of wind generation to leave the
STU connectivity to ISTS connectivity and passing over the additional expenditure to the
existing LTA holders was proposed to be deliberated in the SRPC forum.
24.3 TCC deliberations
MS, SRPC had informed that RE schemes are getting modified at times while some are
getting dropped also. It was suggested that the RE Projects/evacuation schemes may
kindly be reviewed and updated status be communicated. It was observed that timely
progress on these schemes needs to be communicated to SRPC Secretariat, being a
critical issue monitored by various bodies.
TCC had suggested that concerned entities to furnish the updated status to SRPC
secretariat in a time bound manner.
23.4 SRPC deliberations
24.5 SRPC noted the above.
24.6 ED, SR-I, PGCIL stated that RE evacuation was planned and executed under critical/tough
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 63
conditions and compressed time lines based on committed dates by RE generators. For
example, at NP Kunta, NTPC had stated that project would come in three phases and works
were awarded for all the three phases matching with the time schedule given by them.
However, matching activities at NP Kunta (NTPC) end was not being observed and PGCIL
should not get penalized/affected in any manner on account of delay at generation end.
24.7 Transmission System associated for Tumkur Ultra Mega Solar Park (2000 MW)
Transmission
Elements
Line Length
(ckm)/
MVA/MVAr
Capacity
Implem
enting
Agency
Sch
COD
Ant
COD/
Act COD
Constraints/ Remarks
A. Transmission system for connectivity by September 2017
400/220 KV Tumkur
(Pavagada) Pooling
Station
1 x 500 MVA
Oct 18 PGCIL
trying to
commissi
on the
system
matching
with
generatio
n
LILO of 400kV Gooty
–Tumkur
(Vasantnarsapur) D/C
at Tumkur (Pavagada)
PS
5
PGCIL Oct 18 Award placed in
Jun‟16. Survey had
been completed.
220 kV Line Bays (8
nos) at 400/220 kV
Tumkur (Pavagada) PS
for solar
interconnection
Oct 18 8 No. of Line Bays
required
Bus Reactor at Tumkur
(Pavagada) pooling
Station
1 x 125
MVAR
Oct 18
B. Phase-I : Transmission system for LTA Tumkur Ultra Mega Solar Park (1000 MW) by
September 2017
Tumkur PS - Hiriyur
400 kV D/C line (as
part of
Tumkur(Pavagada)
Pooling Station -
Mysore line)
218
PGCIL Oct 18 PGCIL
trying to
commissi
on the
system
matching
with
generatio
n
For 400kV Tumkur –
Mysore line section
routed via Hiryur S/s.
Award placed in
Jun‟16.
LILO of 400kV Bellary
Pool – Tumkur
(Vasantnarsapur) D/C
(Quad)(both
circuits)[KPTCL line]
at Tumkur (Pavagada)
Pooling station*
110
PGCIL Oct 18 *KPTCL would
complete Bellary
pooling station –
Tumkur
(Vasantnarsapur) line
D/C (Quad) by
December- 2016.
Award placed in
Jun‟16.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 64
Augmentation of
400/220 KV Tumkur
(Pavagada) Pooling
Station
2 x 500 MVA
Oct 18 Award placed in
Apr‟16
C. Phase-II : Transmission system for LTA Tumkur Ultra Mega Solar Park (1000 MW) by
September 2018
Hiriyur–Mysore 400
kV D/C line
190
Oct 18 One ckt would be
connected with one ckt
of Tumkur-Hiriyur to
make Tumkur-Mysore
direct line
Fixed series Capacitor
(40%) on 400 kV
Tumkur (Pavagada) -
Tumkur
(Vasantnarsapur) D/C
(Quad) line at Tumkur
(Pavagada) Pooling
Station end
Augmentation of
transformer at 400/220
kV Tumkur PS
2 x 500 MVA
2nd
Bus Reactor at
Tumkur (Pavgada) PS
1 x 125
MVAR
Third 400/220 kV
MVA transformer at
Tumkur
(Vasantnarsapur)
1 x 500 MVA
Switchable Line
Reactor(LR) at Mysore
end of Hiriyur-Mysore
D/C for each circuit
1 x 80
MVAR
D. Additional ATS for Tumkur(Pavagada), to match with the commissioning of Devanahalli
SS of KPTCL
400 kV Tumkur
(Pavagada) -
Devanahalli (KPTCL)
D/C (Quad) line with
some portion on multi
circuit towers
125 KPTCL would
complete establishment
of 400/220 kV
substation at
Devanahalli including
inter-linking 400 kV
and 220 kV lines
before Phase-II at Ultra
Mega Solar Power
Park.
24.7.1 In earlier Meetings, the following had been noted:
SR-II, PGCIL had informed that they were focusing on completing the Pavagada SS and
LILO of Gooty-Tumkur line at Pavagada SS. As per Investment Approval scheduled
date of LILO of Gooty-Tumkur at Pavagada and Pavagada SS was Oct 2018 but PGCIL
was expediting to advance the commissioning.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 65
It was noted that Tumkur Ultra Mega Solar Park Phase-I (1,000 MW) was expected by
April 2017.
24.7.2 TCC deliberations
KPTCL had informed that 500 MW would be coming up by June 2017. Second module
of 500 MW was expected by September 2017. The project was scheduled to be
completed by September 2018.
PGCIL had informed that evacuation would be ensured matching with generation
modules coming up.
24.7.3 SRPC noted the above.
25 NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP
25.1 Krishnapatnam UMPP (6x660 MW)
25.1.1 Following had been noted in earlier Meetings of SRPC:
The matter is sub-judice in High Court of Delhi.
APTRANSCO & APGENCO had informed that APSPDCL was the lead procurer. Over
a period of time this project was non-starter and it was unlikely to start in future also.
Except land leveling no work had been undertaken. CAPL had made presentation to the
procurers for exit from the project. Hon‟ble High Court had posted the case on 22nd
April 2016 and project was being constantly monitored. Even in the last procurer‟s
Meeting, CAPL was suggested to come out with a reasonable proposal.
Progress of Krishnapatnam UMPP had been uploaded in MoP website with the
observation „The project was handed over to Reliance Power Ltd. on 29.01.2008. The
developer has stopped work at site, citing new regulation of pricing in Indonesia. Lead
Procurer namely Andhra Pradesh South Power Distribution Company (APSPDCL) has
issued termination notice to Coastal Andhra Power Ltd (CAPL). The case is subjudice
in division bench, Delhi High Court.‟
25.1.2 TCC deliberations
APTRANSCO had informed that in the last Procurers Meeting, lead procurer
(APSPDCL) had been suggested to obtain legal opinion on APTEL Order and ongoing
legal proceedings. APTRANSCO had requested consent of other procurers to seek legal
opinion.
25.1.3 SRPC noted the above.
25.2 Cheyyur UMPP (4,000MW)
25.2.1 In earlier Meetings, the following had been noted:
CTU had informed that this project had been identified under „Plug and Play Mode‟ and
new bids would be called.
Progress of Cheyyur UMPP has been uploaded in MoP website with the observation „The
site at Cheyyur in Kanchipuram District in Tamil Nadu has been identified along with
captive port at Panaiyur village. Request for Qualification (RfQ) and Request for Proposal
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 66
(RfP) issued in 2013 were withdrawn. Fresh RfQ and RfP are to be issued after the
finalization of Standard Bidding Documents.‟
TANGEDCO had informed that land acquisition was over. In case the bidding process is
getting delayed they were willing to take the project by themselves.
25.2 Schedule of synchronizing/commissioning of the new projects of NTPC, NLC, NPCIL,
and BHAVINI & UMPP is furnished below:
Station Unit
Installed
Capacity
MW
Scheduled date of
synchronizing /
commissioning
Remarks
NTPC
Kudgi TPS
Stage-I
I,II,
III
3 x 800=
2400 Unit-I Synchronized and
achieved full load on
25.12.2016.
CoD by April/May
17.
Unit-II
Synchronization by
Feb‟17. CoD by
Aug‟17
Unit–III Synchronization by
May 17. CoD by
Nov‟17
On a query, NTPC
confirmed that full DC
would be ensured and there
were no constraints.
Telangana STPP
Phase I
2 x 800 U-I CoD May 2020
U-2 CoD Nov 2020
Pudimadaka AP 4 x 1000 52 Months from Zero
Date
85% share to AP.
Zero date yet to be finalized.
AP requested NTPC to firm
up the zero date at the
earliest.
AP informed evacuation
system would be developed
by PGCIL
30th
TCC: NTPC informed that the domestic coal was yet to be tied up.
APTRANSCO informed that they would apply for LTA with CTU after the
coal linkage is firmed up.
NLC
New Thermal
Power Project
I 500 April 2018 CTU had informed that for
evacuation LILO of Neyveli -
Puducherry and 400 kV D/C to
Araliyur lines are planned. NLC
had applied for LTA of 340 MW
which could be managed with the
LILO of Neyveli – Puducherry.
Balance 600 MW would be
catered by 230 kV system of
TANTRANSCO. Araliyur S/S
II 500 April 2018
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 67
was being developed by
TANTRASCO and was expected
by June 2018
NPCIL
Kudankulam St-I II 1000 COD: By March
2017
Unit-II: First synchronized to
grid at 11:16 hrs of
29.08.2016. Scheduling
started from 14.10.2016.
BHAVINI
Kalpakkam
(PFBR)
I 500 Synchronization by
March 2017
COD by Sep 2017
UMPP
Krishnapatnam 3960
(6 x 660)
APEPDCL and PCKL had
taken steps with their legal
counsel to expedite the
hearing before Honorable
High Court of Delhi
Cheyyur 4000 New bids would be called
26 NEW PROJECTS OF STATE SECTOR & IPP
26.1 Updated status of new projects of State sector is furnished below:
Sl
No
Name of project Located
in
Capacity
in MW
Commissioning Schedule
/Remarks
1 Rayalaseema TPS ST-
IV
AP 1 x 600 Synchronization by June 2017
COD by Dec 2017
2 Dr. NTTPS,
Vijayawada
AP 1 x 800 2017-18
3 Krishnapatnam Stage II
(U3)
AP 1 x 800
4 Polaki AP 4000 (5 x
800 MW)
5 Bellary TPS U-3 KAR 1 x 700 Achieved full load on
01.03.2016. COD on 16.09.2016
6 Yermarus TPS KAR 2 x 800 Unit-I: FL achieved on
29.03.2016. Unit II: COD by
2016-17
7 Edlapur KAR 1 x 800
8 North Chennai Stage
III
TN 1 x 800 2019-20
9 North Chennai Stage
IV
TN 2 x 800 Beyond 2019-20
10 Ennore TPS Exp TN 1 x 660 2018
11 Ennore replacement TN 1 x 660 2018
12 Udangudi Stage I TN 2 x 660 2019-20
13 Uppur TPP (TBCB) TN 2 x 800 2019-20
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 68
14 Singareni Telangana 2 x 600 Unit I: CoD from 25.09.2016
Unit II: CoD from 02.12.2016
15 Manuguru PPP Telangana 4 x 270 U1 : 20.03.2017
U2: 20.05.2017
U3: 20.09.2017
U4:20.09.2017
16 Kakatiya TPP Stage III Telangana 1 x 800 2017-18
17 Kothagudem TPS
Phase VII
Telangana 1 x 800
18 Damaracherla
(Yadadri)
Telangana 2 x 600 +
4 x 800
2018-19
26.2 Updated status of new projects of IPPs is furnished below:
Sl
No.
Name of project Located
in
Capacity
in MW
Commissioning Schedule
/Remarks
1 Meenakshi PH-II AP 2 x 350 2017-18
Untied: 640 MW
2 East Coast Energy
Thermal
AP 2 x 660
2017-18
AP : 300 MW
3 Thermal Powertech
(TPCIL) Unit-III
AP 1 x 660
2017-18
4 SGPL (NCC)
Krishnapatnam
AP 2 x 660
Unit I : CoD from 17.11.2016
Unit II: Syn. by June 2017
AP: 500 MW (firmed up PPA to
be signed).
5 Godhna TPP, Janjir –
Champa Dist,
Chhattisgarh
For
KAR
2 x 800 2017-18
27 METHODOLOGY FOR CERTIFICATION OF INTRA-STATE TRANSMISSION
LINE
27.1 APTRANSCO vide letter dated 09.12.2016 (Annexure-XXXVII) had requested SRPC to
certify certain intra state lines so that the same could be considered for inclusion in POC
charges.
27.2 Clause 2.1.3 of Annexure –I CERC Third Amendment of Sharing of inter-State
Transmission Charges and Losses Regulations 2015 states as follows:
“Certification of non-ISTS lines carrying inter-State power, which were not approved by
the RPCs on the date of notification of the Central Electricity Regulatory Commission
(Sharing of Transmission Charges and Losses) Regulations, 2009, shall be done on the
basis of load flow studies. For this purpose, STU shall put up proposal to the respective
RPC Secretariat for approval. RPC Secretariat, in consultation with RLDC, using WebNet
Software would examine the proposal. The results of the load flow studies and
participation factor indicating flow of Inter State power on these lines shall be used to
compute the percentage of usage of these lines as inter State transmission. The software in
the considered scenario will give percentage of usage of these lines by home State and
other than home State. For testing the usage, tariff of similar ISTS line may be used. The
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 69
tariff of the line will also be allocated by software to the home State and other than home
State. Based on percentage usage of ISTS in base case, RPC will approve whether the
particular State line is being used as ISTS or not. Concerned STU will submit asset-wise
tariff. If asset wise tariff is not available, STU will file petition before the Commission for
approval of tariff of such lines. The tariff in respect of these lines shall be computed based
on Approved ARR and it shall be allocated to lines of different voltage levels and
configurations on the basis of methodology which is being done for ISTS lines.”
27.3 It was proposed to evolve a methodology for SRPC certification of intra state lines, carrying
power to other states, to be applicable to all the utilities, with consensus on the same.
Methodology prepared by SRPC is enclosed as Annexure-XXXVIII please.
27.4 This matter had been discussed in the 33rd
Meeting of Commercial Sub Committee held on
31st January 2017. After discussions, the Commercial Sub Committee had recommended the
methodology prepared by SRPC for approval. This methodology was put up for approval.
27.5 TCC deliberations
APTRANSCO had stated that the methodology had not been agreed by APTRANSCO in
Commercial Committee Meeting. SOR to 3rd
Amendment of Sharing Regulations
suggested that lines carrying 10 % interstate power could be considered to be included in
PoC computations.
TSTRANSCO had stated that there are no standards in place presently to decide on any
percentage.
TCC had concurred with the recommendations of Commercial Committee and placed the
same before SRPC for approval. It was agreed that 50% criteria would be reviewed later
after experience/feedback is available on the issue.
27.6 SRPC deliberations
27.7 APTRANSCO stated that 50% criteria seem to be on the higher side and requested for a
review.
27.8 SRPC approved the recommendation of TCC. It was agreed that 50% criteria would be
reviewed later after experience/feedback is available on the issue.
28 EMERGENCY RESTORATION SYSTEM (ERS)
28.1 Requirement of ERS had been outlined in MoP letter dated 05.12.2014. CEA vide letter
dt.18.04.2016 had sought updated status on the ERS which was communicated to the States.
Status update is given below:
Transmission
Utility
Requirement
as per MoP
Existing Status/Remarks
APTRANSCO 3 Nos. ERS I – Placed at Nellore
ERS II – Placed at Vizag
ERS III – Submitted for approval for
PSDF funding
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 70
TSTRANSCO 1 No. To be retendered
KPTCL 2 No. 2 Nos.
KSEBL 1 No. Tenders to be floated
TANTRANSCO 2 Nos Under consideration
PED Nil
PGCIL 4 Nos. ( 2
Nos.
additional)
2 Nos (SR
I & SR II
was having
1 No. each)
Inspection completed-Would be
dispatched. Would be kept at Vizag
and Chennai. Expected by June 2017.
765 kV ERS (one each for SR-I and
SR-II) order would be placed in March
with a delivery schedule of 15 months.
28.2 In earlier Meetings the following had been noted:
CEA had informed that it has been decided that all Transmission Licensees (irrespective of
ownership) would maintain ERS as mandated in CEA Regulations. All ERS locations
should be available at RLDC website to ensure availability of ERS at particular location in
a timely manner. As per National Disaster Management System, one should be able to
deploy these ERS within two days. Even single line owners (TBCB) had been directed to
have ERS and there was an Order of CERC in this regard also.
Chairperson, SRPC had observed that Andhra Pradesh and Tamil Nadu need to have higher
number of ERS since their coastal belt was more prone to cyclones. During floods in
Chennai, PGCIL ERS had come in very handy.
TANTRANSCO had enquired about status of ERS S/S which had been approved earlier by
SRPC. Chairperson, SRPC had stated that as per Disaster Management plan, ERS SS may
also be required. This was basically required to run some essential services.
PGCIL had informed that that they had taken up tendering but there was no response, ERS
S/S has been dropped. The cost was exorbitantly high (around Rs 400 crores). ERS SS was
available up to 220 kV, but 400 kV ERS was too bulky and transportation was a problem.
They were still trying for a smaller transformer of 100/160 MVA with minimum breakers
instead of 315/500 MVA.
Chairperson, SRPC had suggested that PGCIL should go for smaller capacity transformers
to meet the objectives.
28.3 SRPC deliberations
28.4 Chairman, TNEB stated that actual usage of ERS during the Vardha Cyclone period had
been assessed. Water borne/swamps were some areas where ERS was specially required,
however ERS technology was having limitations in such areas. In many places, restoration
of tower was faster than shifting to ERS.
28.5 APTRANSCO stated that ERS had helped them significantly during the Hud Hud cyclone.
28.6 It was noted that Ministry of Power had itself specified state wise ERS requirements. States
were suggested that they could consider taking up ERS procurement through PSDF
funding.
28.7 Chairperson, SRPC stated that one or two ERS S/S at lower capacity/voltage level as
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 71
deliberated in the earlier Meeting may be required.
28.8 ED, PGCIL stated that they were examining feasibility of ERS S/S technically/
commercially.
29 PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
29.1 Status of implementation of Bus / Line Reactors / Dynamic Compensation approved in the
Standing Committee / SRPC pending for commissioning by the SR constituents is
furnished below:
Entity Bus Name Status Remarks
KPTCL
Hoody Reactor erected on
platform June 2017
Nelamangala Reactor erected on
platform June 2017
Entity Bus Name
Capacit
y in
MVAR
Approved
in Type Remarks
PGCIL
Vijayawada 2x125
20th
SRPC/
34th
SC Bus
1st : commissioned in
June 2016
2nd
: March 2017
Nagarjuna
Sagar 125
21st SRPC/
34th
SC Bus March 2017
Narendra 125 21
st SRPC/
34th
SC Bus
Commissioned on
23.01.2017
Hyderabad 125 21
st SRPC
PGCIL informed that it is
dropped
Gooty 125 22
nd SRPC
/ 36th
SC Bus March 2017
Hassan 125
36th
SC
Bus Commissioned on
18.12.2016
Khammam 125 Bus March 2017
Kudgi PG 125 Bus Commissioned on
30.12.2016
Trivandrum 125 Bus Commissioned on
24.01.2017
Nellore
(Existing) 125 Bus March 2017
Yelahanka 2x63 Bus Deferred as per 40
SCPSSR
Nellore PS
on NPS-
Gooty Line
2 x 63
(37th
SC) Line March 2017
Kudgi PG–
Tumkur
D/C at each
end
4 x 63 Line
Reactors commissioned
with line in December
2016
Cuddapah 50 to 125 39th
SC Yet to be awarded
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 72
Thiruvalam
765 kV 2 x 240 39
th SC
Commissioned with
Kurnool lines.
APTRANSCO
Vemagiri 125
36th
SC
Bus PO has been placed on
18.06.2016. Expected by
August 2017
Kurnool 125 Bus
Kalpakka 125 Bus
Chittoor 125 39th
SC To be taken up
Vijayawada 125 39th
SC
APTRANSCO/
APGENCO
VTPS Stage
IV 125 39
th SC
APGENCO informed
that reactor was coming
up with 800 MW unit.
APGENCO was
suggested to take up
independently
KPTCL Davangere 125 39
th SC KPTCL informed that
they are taking it up Talguppa 125 39th
SC
TANTRANSC
O
Almathy 125 39th
SC
Diversion order has been
issued from Kanarpetty
400 kV S/s.
Kayathar 125 39th
SC
Administrative Approval
accorded and being
taken up
TANTRANS
CO/
TANGEDCO
Mettur 125 39th
SC
Commissioning of
Palawadi 400 KV S/s is
expected in near future
and the MTPS –
Thiruvalam line will be
LILOed at Palvadi 400
kV S/s would be
completed in 2 months
and length of the line
will get reduced
considerably.
TSTRANSC
O
Mamidipalli 125
36th
SC
Bus Sanction of funding
from PSDF is received
for 5 Nos of 125 MVAR
reactors from MoP on
05.09.2016 and works
are in progress.
Expected to be
commissioned by June
2017.
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob
Nagar 125 Bus
Malkaram 125
Bus
TSTRANSC
O/
TSGENCO
Srisailam
LB 125
39th
SC
Erection of GIS with
Bus reactor is not
suggestible due to
financial implications
and space constraint in
400 kV GIS of
SLBHES. Hence, the
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 73
erection of Bus reactors
shall be examined at
other end.
NPCIL Kaiga 2 x 125
Bus
KGS informed that
financial sanction is
received and works
would be completed in 2
years
UPCL Udupi 2 x 125
39th
SC
KPTCL informed that
the line is planned to be
LILOed at Drinking
water substation at
Yettinahole between
UPCL and Hassan.
Subsequently the studies
would be put up to
Standing Committee.
29.2 Concerned entities were requested to kindly expedite commissioning of reactors.
29.3 NGR bypass of reactors
29.3.1 Need for convertible line reactors which can be used as bus reactors had been highlighted
by SRLDC in various OCC Meetings. It had been noted that this aspect had not been
considered during planning/design stage itself and subsequently only, works were being
taken up. It had been suggested that provision to convert the line reactor as Bus reactor
could be made during the planning/designing stage itself to take care of variations during
peak/off peak, seasonal variations, RE integration etc.
29.3.2 SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion.
29.3.3 In SR, NGR bypass of 400 kV Nellore-Thiruvalam I & II, Thiruvalam-Kurnool I & II and
Kozhikode-Mysore I & II line reactors was scheduled for 2017-18. PGCIL had informed
that earlier as per norms 765 kV bypass arrangement was being carried out by breakers and
by isolators at 400 kV.
29.3.4 TCC deliberations
PGCIL informed that new Line Reactors were coming up with provision to be
convertible as Bus Reactors. For existing line reactors, NGR bypass works of Nellore-
Thiruvalam I & II, Thiruvalam-Kurnool I & II and Kozhikode-Mysore I & II would be
completed by August 2017.
29.3.5 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 74
29.4 Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA /
KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR) Remarks
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125 Tendering
Completed.
P.O. would
be placed
by June
2017 with
a schedule
of 24
months
Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
29.4.1 PSDF– Installation of STATCOM by Power grid in Southern Region
The following had been noted in earlier Meeting:
SRPC had approved TCC recommendation of the proposal for funding through PSDF.
PGCIL could take up the project by itself in case proposal was not approved through
PSDF. However, all efforts should be made by PGCIL for PSDF funding.
KPTCL had suggested that one STATCOM could be shifted to any 400 kV SS of
Bengaluru. KPTCL was suggested to kindly take up the matter with the Standing
Committee on Power System Planning.
SRPC had suggested that a new study on STATCOM requirement could be carried out
and feedback provided to the Standing Committee. KPTCL‟s request could also be
considered in the Standing Committee.
29.4.2 TCC deliberations
PGCIL informed that 90% PSDF funding for STATCOM was envisaged.
NPC informed that the approval of SRPC has not been communicated by PGCIL to
PSDF Appraisal Committee. PGCIL was requested to take necessary action in this
regard.
29.4.3 SRPC noted the above.
29.5 Reactive Power Planning
29.5.1 Status of Capacitor installation in Transco/Discoms is given below:
Utility Reactive Power Planning Voltage
level
Remarks
APTRANSC
O
Kadapa: 86.4 MVAR
Vijayawada: 172.8 MVAR
Visakhapatnam: 158.4
MVAR
On 33 kV
side
50.4 MVAR commissioned
50.4 MVAR commissioned
28.8 MVAR commissioned
APSPDCL 72 MVAR 18 MVAR commissioned
APEPDCL 218 MVAR
TSNPDCL 123 x 2 MVAR 123 x 2 MVAR and 118 x 1
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 75
118 x 1 MVAR MVAR capacitors had been
commissioned.
TSSPDCL 221 x 2 MVAR 11 kV 221 x 2 MVAR commissioned.
KPTCL Bengaluru Tr. Zone:708.8
MVAR
12.1 kV No update
Bagalkot Tr. Zone :258.1
MVAR
12.1 kV Material supplied. Erection
completed/under progress.
Hassan Tr. Zone : 150.8
MVAR
Material supplied. Erection
completed/under progress. Due
to space constraints 2*2.9
MVAR Capacitor Bank at
Belur, diverted from Belur to
Javgal 110kV Substation
Mysore Tr. Zone :60.9
MVAR
1x2.9 MVAR at Davanur S/s
commissioned on 26.10.2016
and 2x2.9 MVAR at Kikkeri
commissioned on 26.10.2016
Gulbarga Tr. Zone :98.60
MVAR
No update
Tumkur Tr. Zone :281.3
MVAR
12.1 kV 40.6 MVAR commissioned.
34.8 MVAR cable laying,
termination and testing and
commissioning works
completed. EI approval
awaited. At Haluvagalu due to
space problem, 2 nos of
capacitor banks are diverted to
JG Halli & Hariyabbe MUSS.
KSEBL
360 MVAR
66 kV Have done reactive
compensation study 360
MVAR is planned. Works will
be started shortly.
11kV
TANGEDCO 34 x 2.4 MVAR 11 kV 8 x 2.4 MVAR installed.
Balance works are under
progress
35 x 2.4 MVAR 11 kV Additional – Administrative
approval accorded. Tender to
be floated
16 x 2.4 MVAR 22 kV 8 x 2.4 MVAR installed.
Balance works are under
progress
51 x 2.4 MVAR 22 kV Additional – Administrative
approval accorded. Tender to
be plotted.
13 x 24 MAVR 110 kV BOQ approved by Board.
Tender opened. Techno
Commercial evaluation under
progress.
822 MVAR capacitors at
Distribution level had
Balance 109 MVAR will be
commissioned before 31.03.2017.
However for further enhancement
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 76
been commissioned out of
931 MVAR capacitors
planned.
of Reactive Power, Capacitor bank
provisions have to be arranged by
Planning/Transmission wings.
29.5.2 PSDF – Funding of the schemes of the state utilities for installation of capacitors in
the state network at transmission / distribution network
29.5.2.1 MS, Appraisal Committee & ED, NLDC vide letter dated 22.06.2016 had referred to the
schemes of state utilities for installation of capacitors in the State Network at
transmission/distribution network for funding from PSDF. The matter was deliberated by
the Appraisal Committee during the Meeting held on 31.05.2016 wherein, it was decided
that assessment of capacitor requirement may be carried out at regional level by engaging
expert agency like CPRI. In the 30th
Meeting, SRPC had approved TCC recommendation
that a regional proposal for capacitors installation would be put up for PSDF funding.
The Study would be conducted by CPRI.
29.5.2.2 A Meeting in this regard was conducted on 29th
November 2016 (MoM available on
SRPC website), wherein, the following had been agreed:
„Each state would furnish the converged PSSE base case for the Low Voltage/High
Demand scenario for its control area. LGB, Tap positions and assumptions for the
base case would also be furnished. STU would prepare the base case in consultation
with the DISCOMs. These details would be positively furnished to SRPC/SRLDC by
15th
December 2016. After validation by SRLDC/SRPC the details would be
communicated to CPRI.‟
29.5.2.3 TN had furnished the details while the details from other states were awaited. Further
each state in the region would need to contribute Rs 5 lakhs for the study to be conducted
by CPRI.
29.5.2.4 TCC deliberations
MS, SRPC had stated that a comprehensive proposal (STU & Discom) was to be
furnished. This was getting delayed on account of various reasons. PSDF Appraisal
Committee had sought for a vetted regional proposal which would enable PSDF
funding. As agreed in the 30th
SRPC, CPRI was willing to take up the study. The matter
needs to be urgently expedited.
After deliberations the following was agreed:
All states agreed to positively furnish a comprehensive proposal of STU/DISCOMs
by 15th
March 2017.
All states agreed to make the payment of Rs. 5 Lakhs each due to CPRI for the study.
29.5.2.5 SRPC deliberations
29.5.2.6 NLDC was requested to consider individual proposals since comprehensive proposal was
taking some time due to delay due to various reasons.
29.5.2.7 NLDC stated that WRPC, ERPC and SRPC had been requested to submit a regional
proposal. The proposal from WRPC had been received recently.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 77
29.5.2.8 Chairperson, SRPC stated that in the recent meeting with MoP, it was noted that they
were willing to approve proposals expeditiously. Proposals needed to be submitted
immediately to avail the funding.
29.5.2.9 SRPC noted that data would be submitted by 15th
March 2017 and payment to CPRI
would also be expedited.
30 OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS
30.1 In CCM Meetings, the following had been noted:
Puducherry vide letter dated 09.12.2016 informed that they had received Rs 54,366/- from
GUVNL and balance amount of Rs 48,355/- only to be paid by GUVNL.
Pending payments between WR& SR Constituents as on 10.01.2017 are as follows:
State Receivable from Payable to
Entity Rs Entity Rs
Andhra Pradesh
/ Telangana
MPPMCL 1,21,76,270
*
MPPMCL Nil
Karnataka MPPMCL 13,27,208 CSPDCL 73,72,176
GUVNL 9,40,320
Kerala MPPMCL 1,21,47,260
CSPDCL 7,05,279
GUVNL 4,98,019
Tamil Nadu MPPMCL 1,17,17,268 CSPDCL 92,77,878
Puducherry GUVNL 48, 355 GUVNL Nil
* In the recent Meeting of SR-WR held on 09.11.2016 at WRPC, Mumbai, MPPMCL
informed that MPPMCL has to receive payment from APTRANSCO and the details
would be shared with APTRANSCO/SRPC Secretariat.
30.2 SRPC noted the above
30.3 Payable amount by PGCIL (WRTS / SRTS) to SR Constituents (as on 10.01.2017)
State/UT Amount
(Rs)
Received(Rs) Paid by SRTS II
on 01.04.2016
(Rs)
Balance to
receive (Rs)
Andhra Pradesh
& Telangana
47,05,447 3,69,848 10,16,847 33,18,752
Karnataka 49,79,733 3,91,407 10,76,120 35,12,206
Kerala 27,58,402 2,16,811 5,96,091 19,45,500
Tamil Nadu 47,21,994 3,71,149 10,20,423 33,30,422
Puducherry 9,24,035 72,629 1,99,684 6,51,722
Total 1,80,89,611 14,21,844 39,09,165 1,27,58,602
SR constituents had been requested to take up pending payment issue with concerned
WR utility directly, with a copy to SRPC / WRPC Secretariat.
30.4 TCC deliberations
SR-II PGCIL informed that an amount of Rs. 13,38,631 had been received from
Chhattisgarh and the amount would be dispersed.
30.5 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 78
31 NON-AVAILING OF OCC APPROVED SHUTDOWN
31.1 In OCC Meetings, it had been noted with concern that at times entities were not availing the
OCC approved shut downs as per schedule. Details of availed outages against OCC
approved shut downs (furnished by SRLDC) are given below:
31.2 SRPC deliberations
SRPC suggested for better compliance in this regard.
31.3 Rescheduling / Deferment of OCC approved outages having impact on TTC/ATC
31.3.1 In the 127th
Meeting of OCC, it had been noted that Raichur Bus-1&2 shutdowns were
rescheduled to coordinate with shutdowns of transmission elements in WR (Aurangabad-
Sholapur and Wardha Bus-1). There was lack of correct and timely information which was
required for adequate power purchase requirements by states. The issue has also been taken
up WRPC. However, the following merit attention:
Shutdowns need to be planned more diligently well in advance and approved in WRPC
& SRPC (in future ERPC also) OCCs.
Change in date should not be encouraged and avoided. Any change in date affects the
power procurement of SR entities which is generally on a day ahead basis (it may
become to D-2 with the new IEGC amendment).
Entity Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17
Availed % with respect to the OCC approved outages
AP TRANSCO 47 66 63 62 29 34.5
KPTCL 40 8 0 20 33 66.7
KSEBL NIL NIL 100 0 0 50
TANTRANSCO 48 36 48 52 28 40.9
TSTRANSCO 43 80 44 73 29 42.9
PGCIL, SR1 80 55 100 33 38 47.6
PGCIL, SR2 52 33 65 23 25 57.1
NTPC 100 33 0 0 100 50
NLC 100 NIL 100 67 0 50
NTECL NIL NIL 100 NIL NIL NIL
NPCIL NIL NIL NIL NIL NIL NIL
KPCL NIL NIL NIL NIL 100 NIL
PNMTC NIL NIL NIL NIL NIL NIL
KTL NIL NIL NIL NIL NIL NIL
MEPL NIL NIL NIL NIL NIL NIL
TOTAL 55 47 56 48 41 46.9
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 79
Any deferments at the last minute leads to unnecessary costly power procurement and
also load generation balance issues.
Timing of revival of the units should be in line with the approved timings. Any delay
should be as far as possible avoided and the revised time schedule of the revival should
be informed well in advance (around 3-4 hrs).
31.3.2 KSEBL vide letter dated 21.01.2017 & 31.01.2017 (refer Annexure-IX & XVIII) had
expressed concern that the delay in completion of maintenance works on 28/29.12.2016
had resulted in a revenue loss of approximately Rs 160 lakhs to KSEBL. It was stated that
change in date of availing shut down and over stayal of shutdown works are matter of
concern. Also, non-availability of current information from SRLDC and NLDC control
rooms is also cause of worry.
31.3.3 TCC deliberations
KSEBL had expressed concern on rescheduling, lack of information to SRLDC/NLDC
by PGCIL and also delay in restoration during the above referred outages.
PGCIL had assured to take up the issue with other regions on adhering to schedule and
also timings.
31.3.4 SRPC noted the above.
31.4 Deferment of OCC approved outage
31.4.1 In the 125th
OCC Meeting, PGCIL had expressed concern that on several occasions, OCC
approved shutdowns were not being concurred in real time. Considerable effort and
money was frittered on account of such deferment etc.
31.4.2 After deliberations, it had been noted by OCC forum that entities should be allowed to
avail the OCC approved S/Ds on the approved dates itself. Considerable planning and
manpower is deployed to take up OCC approved S/Ds.
31.4.3 SRPC noted the above.
32 GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS
32.1 As per MoP order dated 16.07.2014, M/s Tractebel Engineering (TE) has been appointed as
the Consultant to conduct the study/ analysis of National Grid. The terms of reference of the
Consultant are as follows:
a) To Review the status of implementation of the recommendations of the Enquiry
Committee (Task-1).
b) Carrying out actual protection audit check for 10% (76 nos.) of 762 substations across
the country to address the gaps, in consultation and collaboration with states and all
stakeholders as per present and future requirements (Task-2).
32.2 Task-1 for SR-Constituents was already completed by the first week of September, 2015. The
draft report on Task-1 prepared by the Consultant was discussed in the third Grid Study
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 80
Committee (GSC) Meeting held on 18th
November, 2015. Subsequently, the feedback of the
SR-Constituents was furnished to the Consultant by the last week of November, 2015.
32.3 Under Task-2, 15 Stations from SR have been audited by the Consultant. The draft report on
Task-2 by the Consultant has been received. It may please be noted in this regard that based
on their audit, the Consultant has given certain general observations w.r.t. each station, and
the final set of recommendations will be provided by M/s Tractebel Engineering in their final
report on Task-2. A Meeting chaired by Member (GO&D), CEA is proposed to be held on
13th
February 2017 for finalizing this report.
32.4 Under GSC-Task 2 activities, Consultant, M/S Tractebel Engineering had conducted a five-
day training programme during 16-20 January, 2017 at SRPC Secretariat, Bengaluru on
protection system operation with specific focus on protection audit methodology and relay
setting calculations & coordination for SR-Constituents.
32.5 SRPC noted the above.
33 STATUS OF PHASE I AND PHASE II OF PROTECTION AUDIT
RECOMMENDATIONS
33.1 With reference to petitions filed by KSEB (88/MP/2016) and KPTCL (135/MP/2016) seeking
further time-extension for completing their respective Protection Audit Recommendations
(PAR), a review Meeting was convened by CERC Staff on 05th
October 2016 at SRPC
Secretariat, Bengaluru to ascertain status of implementation of Protection Audit
Recommendations (PAR) by various SR-Constituents. Based on inputs furnished by various
Constituents in the Meeting, detailed status along with probable timelines required for
completion of their respective PAR (Phase-I & Phase-II) had been worked out and furnished
to Hon‟ble CERC for taking a decision w.r.t. granting further time-extensions as sought by
various SR-Constituents.
33.2 Final Order of CERC disposing of above petitions was issued on 15.12.2016. In this Order,
Hon‟ble Commission, apart from granting last-chance time-extensions to various SR-
Constituents had also directed SRPC to monitor status of completion of PAR regularly in
PCSC Meetings and submit bi-monthly report to the Commission confirming the completion
of Phase-I and Phase-II of PAR of the Constituents of Southern Region.
33.3 Timelines given by Hon‟ble CERC, as per above Order dated 15.12.2016, to various
SR-Constituents for completion of their respective Phase-I and Phase-II works of Protection
Audit recommendations are given below:
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 81
33.4 Constituents were kindly requested to adhere strictly to time-lines given in the Order for
completing their respective pending PAR. IPPs for whom there are pending PAR [viz.,
Spectrum PGL, GMR Barge - Kakinada, Konaseema GPL, APGPCL Vijjeswaram Stage-I &
Stage-II), & LANCO-Kondapalli PL] were also requested to complete them.
33.5 SRPC noted the above.
34 SPARE ICT AND REACTOR PLACEMENT AND USAGE PROCEDURE
34.1 PGCIL had informed following status of spare ICTs and Reactors as agreed in earlier
Meetings:
Region Equipment Location
SR ICT Madurai (would be
reaching in Sep 2016) &
Hyderabad (was being
used at Sriperumbudur)
Reactor Vizag & Gooty (being
used at Somanhalli)
Status of Narendra reactor
35 IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION
35.1 Automatic Demand Management Schemes
35.1.1 In line with clause 5.4.2 (d) of IEGC, Automatic Demand Management Scheme was to
have been provided by all constituents by 1st
January 2011. SRLDC & SRPC Secretariat
Sl.
No.
Constituent Date for completion
of Phase-I activities
Date for completion
of Phase-II activities
1 APGENCO (Hydel) 31.12.2017 31.12.2017
2 APGENCO (Thermal) 30.07.2017 ---
3 APTRANSCO 31.03.2017 ---
4 TSGENCO (Hydel) 31.03.2017 31.03.2017
5 TSGENCO (Thermal) 31.03.2017 31.03.2017
6 TSTRANSCO
31.03.2017 31.03.2017
7 KPCL --- 31 30.11.2016
8 KPTCL 31.05.2017 31.05.2017
9 TANGEDCO 31.12.2017 31.12.2017
10 TANTRANSCO 31.12.2017 31.12.2017
11 KSEB 30.11.2016 31.12.2017
12 NPCIL (MAPS) 31.01.2017 ---
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 82
had pointed out that automated scheme was to be in place to meet Regulatory
requirements.
35.1.2 In earlier Meetings, the following had been noted:
AMDS logic was finalized as OD >250 MW or 20 % of Schedule, whichever lower, for
15 minutes when frequency < 49.8 Hz.
This setting (49.8 Hz) would be reviewed in 30th
TCC for subsequent enhancement to
49.9 Hz.
35.1.3 Number of incidents satisfying the existing logic and proposed logic is given in the Table.
It was recommended to migrate to IEGC limits of 49.9 Hz:
Month
Present settings Proposed settings as per IEGC
Frequency < 49.8 Hz for 15
Min. and OD = Min DSM
limit
Frequency < 49.9 Hz for 15
Min. and OD = Min DSM limit
No of instances
Meeting the
freq. limit
No of
instances
applicable
to states
No of
instances
Meeting
the freq.
limit
No of instances
applicable to states
AP KAR TN
Aug-16 NIL NIL 39 3 1 3
Sep-16 1 AP (1) 27 1 3 1
Oct-16 NIL NIL 20 1 0 5
Nov-16 NIL NIL 46 2 1 2
Dec-16 NIL NIL 56 9 0 10
Jan -17 NIL NIL 13 1 0 1
35.1.4 TCC deliberations
SRLDC & SRPC suggested that new set points at 49.9 Hz be adopted.
States pointed out that corrective action was already being taken by them as could be seen
that there were minimal incidents satisfying the proposed logic. Opportunity needs to
given to Operator to take corrective action rather than go for automatic load shedding and
existing set points were reasonable. Unnecessary interruptions to loads were not advisable
in the present scenario. In time of contingency, appropriate urgent action was being taken
by SLDCs.
TCC suggested that ADMS set points could be reviewed in the next Meeting of TCC.
35.1.5 SRPC noted the above.
35.2 UFR and df/dt reliefs
35.2.1 All States had implemented AUFR and df/dt schemes fully. SRPC vide letter dated
29.01.2016 had submitted status report duly certified by SRLDC and SRPC wrt
implementation of SCADA mapping of all constituents to Hon‟ble CERC in respect of
Order dated 27.11.2015 vide Petition No. 60/MP/2014. Details of recommended,
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 83
implemented, SCADA monitorable and actual relief being realized are shown in Table
below:
State AP TS KAR KER TN PUD SR
Recommended MW A 2782 2965 3539 1173 4176 103 14738
Implemented MW B 2782 2978 3559 1207 4544 116 15186
% B/A 100 100 101 103 109 113 103
SCADA
monitorable
MW C 1169 1898 3557 1184 3849 116 11773
% C/B 42 64 100 98 85 100 78
Average
Visible Relief
in November
2016
MW E 1179 1081 2575 1035 1979 81 7930
Wrt
monitorable %
E/C 101 46 72 87 51 70 65
Average
Visible Relief
in December
2016
MW F 1020 890 2363 1062 1717 76 5966
Wrt
monitorable %
F/C 87 38 66 90 45 66 49
Average
Visible Relief
in January
2017
MW
G
1108 1006 2640 1098 1661 76 7523
Wrt
monitorable %
G/C 95 43 74 93 43 66 62
35.2.2 In earlier Meeting, the following had been noted:
TANTRANSCO had informed that action had been taken for the provision of
MPLS/GPRS link and for suitable RTUs at 29 SS GCs connected for AUFR and df/dt
and the time line for completion was April 2017. Regarding monitoring of figures
connected in AUFR and df/dt, PO had been issued for procurement of transducers and
the data visibility would be improved by 31.01.2017.
SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion.
35.2.3 TCC deliberations
APTRANSCO had informed that 25 RTUs would be commissioned by May 2017 and
the visibility would get increased to 70 %. APTRANSCO was requested to initiate
action to improve visibility to 100 %.
TSTRANSCO had informed that 18 RTUs would be commissioned by March 2017
while balance 6 RTU‟s would be taken up later (Administrative Approval is for 24
RTUs). With 24 RTUs in position, the visibility would increase to 100 %.
TANTRANSCO had informed that 100% visibility would be ensured by June 2017.
35.2.4 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 84
35.2.5 In the 6th
Meeting of NPC held on 19.12. 2016 (MoM dated 12.01.2017 available on
CEA‟s website), issue of ensuring proper functioning of UFR and df/dt relays had been
deliberated and following was noted:
„After deliberations, it was decided that all RPCs Secretariat would furnish to NPC
Secretariat the procedure being followed by them to ensure healthiness of UFR & df/dt
relays. RPC Secretariat shall carry out periodic inspection, in line with the provisions
of IEGC.‟
35.2.6 Subsequently, SRPC Secretariat vide letter dated 16.01.2017 (Annexure-XXXIX) had
requested constituents to furnish details as sought by NPC. TSTRANSCO/
APTRANSCO/KSEBL/TANTRANSCO had furnished the details in this regard.
35.2.7 TCC deliberations
KPTCL was requested to kindly communicate the details.
35.3 Restricted Governor Mode of Operation (RGMO)/FGMO of Generating Units
35.3.1 RGMO response is being analyzed in Meetings of OCC. SLDCs were to analyze RGMO
instances posted by SRLDC for the generators in their control area and initiate suitable
action as per Order in respect of 84/MP/2015. Inadequate Response was to be taken up
with SERC (Petition No.302/MP/2013).
35.3.2 Performance of RGMO is being analyzed in the OCC forum. Summary for 5th
October
2016 instance is given in the Table below:
State
Hydro Thermal TOTAL
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
AP -8.7 -6.9 79% -180.5 -107.7 60% -189.2 -114.7 61%
TG -13.4 -14.0 104% -75.0 -43.1 57% -88.4 -57.1 65%
KAR -11.0 0.3 -2% -159.1 -8.5 5% -170.1 -8.3 5%
KER -14.1 -4.9 35% 0.0 0.0 -14.1 -4.9 35%
TN -2.3 0.7 -29% -133.9 -15.2 11% -136.2 -14.6 11%
CGS 0.0 0.0 -510.1 -92.2 18% -510.1 -92.2 18%
SR -49.6 -24.9 50% -1058.5 -266.8 25% -1108.0 -291.7 26%
35.3.3 SRLDC vide letters dated 18.10.2016 and 12.01.2017 (Annexure-XL) had furnished a
summary of RGMO performance of generating stations of SR during Q-2 (July –
September 2016) and Q-3 (October-December 2016) to Hon‟ble CERC.
35.3.4 Extension of RGMO status point to SRLDC/SLDC, is also being deliberated in the
Meetings of OCC and the concerned entities are kindly requested to complete the pending
works.
35.3.5 SRPC Secretariat vide letter dated 07.09.2016 & 02.02.2017 (Annexure-XLI) had taken
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 85
up issue of scheduling the units with NLDC. It was not understood whether all other
RLDCs were adopting the same scheduling practice for ISGS units for ensuring adequate
RGMO response. KSEBL vide letter dated 31.01.2017 (refer Annexure-XVIII) had
raised the issue of restricting the schedule of ISGS for RGMO performance. It has been
stated that SRLDC has not provided DC adopted by them for scheduling against actual
DC given by the generators. This has resulted in higher availability as per REA, whereas
such capacity is not available to the constituents. The Regional Energy Accounts from
January have been proposed to be revised using actual capacity made available to the
constituents.
35.3.6 NLDC vide letter dated 10.10.2016 (Annexure-XLII) had furnished a report on frequency
response characteristics (FRCs) region-wise and all India wise since 1st January 2015 to
2nd
September 2016. It is stated that duration of time when frequency remained within the
IEGC band is continuously improving as evident in average frequency profile curves.
Southern Region is exhibiting a better FRC than other regions. Ancillary Services had
been implemented w.e.f 12th
April 2016 leading to better tertiary control for frequency.
Frequency Variation Index (FVI) had shown continuous improvement and on 21.07.2016
best FVI of 0.024 was recorded. Average frequency on many days had been 50.0 Hz with
a standard deviation of 0.05 Hz. Though considerable efforts had been taken in this
direction, yet a lot of scope is left for improvement. On day to day basis, the sharp
frequency excursions at hourly boundary (significantly observed at 1300 and 1800 hours)
were also a cause of concern. Frequency plot of a typical day shows wide excursions to
50.20 Hz and above. These excursions had in many cases led to tripping of lines on
overvoltage creating insecure conditions. For further ramping up this exercise of
frequency smoothening, primary and secondary frequency controls are also necessary. As
per CERC order Date 13.10.2015, all generating stations that are regional entities must
plan to operationalize AGC along with reliable telemetry and communication and
communication by 01.04.2017. Efforts are already on in this direction so that secondary
control is available. Primary response through governor action is already expected to be
provided by generating units as per sections 5.2(f) to 5.2(i) of the IEGC. However, desired
response from generators was not received. It had been requested by NLDC that primary
response may kindly be ensured through governor response from generators in interest of
grid security and better frequency profile.
35.3.7 TCC deliberations
MS, SRPC had informed the following:
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 86
Hon‟ble CERC in its order in respect of Petition No. 383/MP/2014 (date of Order
15.02.2017) had mandated that FRC was to be monitored. Whenever any RGMO
incident is posted, the FRC should also get posted.
Hon‟ble CERC in its order in respect of Petition No. 65/MP/2014 had mandated
NTPC Ramagundam Units-1, 2 & 3 to go for Retrofit or adopt FGMO with MI.
TCC had suggested that generators take necessary steps to ensure desired Primary
Response. SLDCs need to monitor the performance of the generators and compute FRC
in its Control area. Pending status points (automatic) also need to be extended to
SLDC/SRLDC.
Regarding schedule restriction (for RGMO), SRLDC had stated that as per directive of
Hon‟ble CERC, they are restricting schedules and the Procedure has been well
deliberated in the forum.
On a query about whether the same Procedure for restricting the schedule was
implemented in other regions also, NLDC had informed that the Procedure had been
implemented in SR and they were endeavoring to implement in all the regions.
Constituent states had pointed out that they were losing on the fixed charges and
additional energy charges since more than one year.
After deliberations, TCC had recommended that the Procedure of restricting the
schedule for RGMO compliance by SRLDC should be kept in abeyance since SR
constituents were at a disadvantageous position compared to other regions.
RGMO/FGMO with MI response was mandatory for all the applicable generators in all
the regions. NLDC was suggested the follow a common procedure for all regions in the
country.
35.3.8 SRPC deliberations
35.3.9 SRLDC informed that all RLDCs/NLDC were taking up the issue of restricting schedule
for RGMO compliance in all regions. No decision could be taken against CERC Order.
Scheduling was being restricted to normative and the margin beyond 100 % was being
ensured for primary response.
35.3.10 SRPC noted the TCC recommendation (except NLDC/SRLDC). SRPC felt that there need
for harmonization of such requirements like RGMO, for all applicable units in all the
regions.
35.3.11 SRLDC/NLDC informed that aspect of restricting the schedule for RGMO compliance was
covered in the proposed IEGC amendment.
35.3.12 NLDC informed that a petition for primary response in the interest of grid security had
been filed before Hon‟ble CERC.
35.4 Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
35.4.1 Each SLDC was to create a mechanism and facilities to facilitate on-line demand
estimation of demand for daily operational purpose for each 15 minutes block by
01.01.2011. In this regard, following may kindly be noted as contained in Order dated 19th
December 2013 of Hon‟ble CERC in respect of Petition No. 249/250/251/MP/2012:
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 87
“We direct all STUs/SLDCs of the Northern Region, Southern Region and Eastern
Region to forecast their demand and make adequate arrangements to avoid dependence
on Unscheduled Interchange for Meeting their demand or for injecting short term
surplus power, irrespective of the frequency.”
Load Forecasting tool meeting the regulatory requirement was yet to be developed by all
utilities. The forecast was required for RRAS and Renewable Framework also.
35.4.2 The following had been noted in earlier Meetings:
TANTRANSCO had informed that forecast of NIWE and Wind Developers was having
a difference of 600 - 700 MW (equivalent to 3 thermal units). Demand estimation was
quite accurate and they were in the process of procuring the software and they would be
fully equipped before next summer.
CEA had informed that MoP was willing to give the task of load forecasting to CEA. In
this model, load forecasting data and weather inputs would be communicated to CEA
and CEA would furnish the forecast to the states.
It was agreed that a small group would be formed at SRLDC, and demand forecast
exercise would be undertaken for individual states in coordination with SLDCs. SRLDC
was entering into MoU with IMD and weather data would be integrated.
Parallely, all state entities agreed that CEA could carry out state-specific forecasting.
SLDC would submit necessary data to CEA. This would not involve any financial
commitment for the states.
35.4.3 Subsequently, CEA had informed that a Meeting in this regard was held in Oct 2016 and
consent of SR states was obtained. DFID UK collaboration was being implemented by
KPMG with CEA and was likely to begin in January 2017. Telangana State has been
selected for Pilot project in load forecasting and short term power procurement
optimization program. For this, active highest level of support of Telangana Power utilities
and its SLDC would be required and DFID/KPMG team would visit Hyderabad. This
project involves development of software tools and at a later stage, project implementation
for other states would be taken up by CEA.
35.4.4 SRPC noted the above.
35.5 Sudden Change in Demand/Frequency Excursion
35.5.1 In earlier Meetings, violation of Clause 5.2 (j) of the IEGC Regulations had been
highlighted. No user is to cause sudden variation in its load by more than 100 MW
without prior intimation to and consent of the RLDC. Similarly no user should reduce the
generating unit output by more than 100 MW without prior intimation to and consent of
the RLDC. Necessary action is sought in respect of demand and generation management
as well as power purchases, so that clause 5.2 (j) of IEGC Regulations is not violated.
35.5.2 Constituents had been requested to ensure necessary compliance.
35.5.3 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 88
35.6 Arranging of interruptible loads in four groups
35.6.1 As per IEGC, to maintain the frequency within stipulated band and also to ensure network
security, interruptible loads are to be arranged in four groups of loads. This was for the
purpose of scheduled power cuts/load shedding, loads for unscheduled load shedding,
loads to be shed through UF relays, df/dt relays and loads to be shed under any SPS
Scheme. These loads are to be grouped in such a manner that there was no overlapping
between different groups of loads.
35.6.2 Existing schemes were not Meeting Regulatory requirement fully and further action was
required in this regard. Constituents had been requested to ensure necessary compliance.
35.6.3 SRPC noted the above.
35.7 PSS Tuning
35.7.1 4th
Meeting of PSS tuning was held on 13th
January 2017 and MoM is available at SRPC
website. PSS Study group also analyzed the Step Response Test Reports for the generators
which had furnished the reports and recommendations had been finalized. It is kindly
requested that necessary action may kindly be taken as finalized in the 4th
Meeting of PSS.
35.7.2 SRT of following units had been analyzed in the 3rd
and 4th
Meetings of PSS and necessary
action had to be taken as per Recommendations:
Entity Generating Stations/Units
APGENCO Rayalaseema TPS U1 to U5; VTPS U1 to U4 & U7; SDSPP U1&U2;
Srisailam RB HEP U1 to U7
AP IPP
TSGENCO Nagarjunasagar HEP U2 to U8
KPCL Raichur TPS U1,2,3,5,6,7& 8; BTPS U1 to U3; Varahi UGPH HEP
U1,2 & 4; Nagjheri HEP U1,2,4 & 5; Sharavathy HEP U3,5,7,9 & 10
KAR IPPs UPCL U1 & U2; JSWEL U2 & U3
KSEBL
TANGEDCO MTPS St-I U1 to U4; NCTPS St-1 U2 & U3; Tuticorin TPS U4 & U5
(to be analyzed)
TN IPPs
CGS NTPC- Ramagundam U7; NTPC-Simhadri U1 to U4; NTPC-Talcher
STPS St-II U 3 to U6; NTECL-Vallur TPS U1 – U3; NLC-Neyveli
TPS II U4 to U7; NPCIL-KKNPP U1
ISTS connected IPPs TPCIL U1; Coastal Energen U2; IL & FS U1 &U2
For the following Units, PSS was to be tuned and SRT to be carried out:
Entity Generating Stations/Units
APGENCO VTPS U5 & U6; Lower Sileru HEP U2 to U4
AP IPPs HNPCL
TSGENCO Kothagudem TPS U7 & U8, Nagarjunasagar HEP U1, Srisailam LB HEP U1
to U6, Sinagareni Collieries U1 & U2
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 89
KPCL Raichur TPS U4; Yeramarus TPP; Varahi UGPH HEP U3; Nagjheri HEP U3
& U6; Sharavathy HEP U1,2,4,6 & 8
KAR IPPs JSWEL U1 & U4
KSEBL Idukki HEP U1 to U6
TANGEDCO NCTPS St-1 U1(14.702013); NCTPS St-II U1 & U2; Tuticorin TPS U1 to
U3; Mettur St-II TPS U1; Kadamparai HEP U1 to U4
TN IPPs STCMS
CGS NTPC-Ramagundam U1 to U6; NTPC-Kudgi; Neyveli TPS I U7 to U9; NLC-
Neyveli TPS I Exp. U1 & U2 (SRT report not submitted); NLC-Neyveli TPS
II U1 to U3; NLC-Neyveli TPS II Exp U1 & U2; (NLC & TN JV)NTPL U1
& U2; NPCIL- KGS U1 to U4; NPCIL-MAPS U1 & U2; NPCIL-KKNPP U2
ISTS
connected
IPPs
Simhapuri Energy Ltd (SEL) U1 to U4; MEPL U1 & U2; TPCIL U2; Coastal
Energen U1; Lanco Stage II & III; SGPL-Nellore
35.7.3 In the 6th
Meeting of NPC held on 19.12.2016 (MoM dated 12.01.2017 available on CEA
website), it had been decided that a small group comprising of representative of Protection
Sub- Committee of respective RPCs and NLDC, NTPC would be formed to finalize a
common procedure.
35.7.4 SRPC noted the above and suggested that generators take necessary steps as finalized in the
PSS Meetings.
35.8 Scheduling of Simhadri STPS Stage-I by SRLDC
35.8.1 APTRANSCO had filed a Petition before Hon‟ble CERC in this regard and the petition was
admitted on 7th
January 2016.
35.8.2 Hon‟ble CERC had reserved Order in the matter in respect of Petition No.291/MP/2015.
35.9 Instantaneous Scheme for Sudden Withdrawal of Wind
35.9.1 TANTRANSCO had implemented the SPS for sudden withdrawal of Wind generation at
Udumalpet and Kayathar area and the same was in operation with effect from 27.04.2016.
35.9.2 In the Special / OCC Meetings, SRLDC had opined that the scheme was required to be
extended to other stations and other states as higher capacity ( > 500 MW wind and solar
projects were coming up.
35.9.3 Constituents were suggested to study and discuss the same in OCC.
35.10 Energy Generation data Management from Renewable Energy Sources
Monthly generation data in respect of renewal energy sources is to be submitted to CEA
with a copy to SRPC.
35.10.1 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 90
35.11 Treatment of Bilateral short term and collective transaction in case of grid
disturbances
In the 6th
Meeting of NPC held on 19.12.2016 (MoM dated 12.01.2017 available on CEA
website), after deliberations, NPC had recommended for the accounting methodology to be
submitted to Hon‟ble CERC.
35.11.1 SRPC noted the above
35.12 Power swing blocking (PSB) setting in Distance relays
In the 5th
Meeting of NPC held on 08.04.2016, NPC while agreeing to NRPC's opinion to
have a uniform PSB setting across all regions, decided to maintain status quo in different
regions and await the report of the Consultant appointed for implementation of the
recommendations of the 'Task Force for Power System Analysis under contingencies'
before further deliberations in the matter.
35.12.1 SRPC noted the above
35.13 Other Issues requiring kind attention of TCC / SRPC
Following issues which are being followed up in the Meetings of Sub-Committees of
SRPC also merited kind attention:
220 kV Narketpalli-Chilakallu Circuit I (inter-state line between AP and TS) was
LILOed at Suryapet at TSTRANSCO without exchanging code from SRLDC. 230 kV
MAPS –Arni line was LILOed at Echur SS by TANTRANSCO on 08.08.2016 without
prior concurrence from SRLDC. Any reconfiguration on inter-state lines and lines
emanating from regional entities needs to be carried out only after approval from
SRLDC keeping in view the operational / commercial aspects involved.
TANTRANSCO to complete insulator replacement with polymer for Vallur-NCTPS
lines.
NTECL and PGCIL to coordinate and complete the insulator replacement for gantry
tower towards line at NTECL.
TSGENCO had communicated that after Meeting water requirement in the Tail Pond
project, OEM M/s.Hitachi would be taking up testing and commissioning of units for
Pump mode operation at Nagarjunasagar.
Nagarjunasagar Unit-4 was drawing more power (12 MW) due to uneven shutter gap of
guide vanes and water leakage through guide vanes. For Unit-6, air depression needs to
be carried out frequently. TSGENCO had informed that these would be rectified in next
overhaul.
TSGENCO had informed that in respect of condenser mode of operation for Srisailam
LB, it takes around 3-4 hrs to put all the units in condenser mode. TSGENCO had been
requested to revert back on technical feasibility to reduce this time.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 91
N-1 violation of Nelamangala, Vemagiri, Hoodi, Somanahalli, Madurai, Narendra,
Nunna, Kalvindapattu, Ramagundam, Pugalur, Kozhikode, Gazuwaka and Trichy ICTs
had been highlighted in the OCC Meetings.
High loading of Kolar-Hosur and Udumalpet-Palakkad line had been highlighted in the
OCC Meetings.
Chittoor ICT was under prolonged outage and APTRANSCO to take corrective action.
SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the A/R issues
for discussion.
A/R had been commissioned for Ambewadi-Ponda by KPTCL and enabling was
pending due to non-approval from Goa end. Ambewadi-Xeldam being operated in
radial mode but the provision for A/R to be ensured.
A/R for Nagjheri lines to be completed by KPTCL/KPCL.
A/R to be made available for Munirabad-Lingapur I&II and Munirabad-Kalyani by
KPTCL.
A/R to be made available for Warangal-Nagaram I&II, Warangal-Durshed and
Warangal-Bommakal by TSTRANSCO.
NTECL had under injected wrt the dispatch schedule during the period 31.12.2016 to
02.01.2017. The issue was deliberated in the 127th
OCCM.
Power grid Vizag Transmission Limited (PVTL) vide letter dated 27.12.2016
(Annexure-XLIII) had informed that they had declared COD of the Srikakulam-
Vemagiri 765 D/C Transmission Line. However, it was not considered for computation
of PoC charges was not considered by Validation Committee since the terminal
equipment was not ready and the subject system was not able to be used. Date of COD
of Vemagiri-Srikakulam 765 D/C line shall be intimated when the same is ready for use.
SGPL vide letter dated 23.12.2016 (Annexure-XLIV) had requested for enhancing the
net exportable capacity of SGPL units to 620 MW instead of 617 MW. The same would
be aligned with their connectivity grant by CTU of 1240 MW for two units. 620 MW
had been demonstrated during the trial run and was supported by the trial run data
submitted to SRLDC. The matter was under consideration of SRLDC.
SRPC Secretariat vide letter dated 24.11.2016 (Annexure-XLV) addressed to CTU had
sought certain clarifications regarding LTA operationalization in respect of M/s MEPL
whereas, LTA of 491 MW was granted to M/s SEL. CTUs reply in this regard is at
Annexure-XLVI. MEPL had filed Petition No. 312/MP/2015 which was listed for
08.01.2017.
6th set of Pollution measurement in SR were to be completed by 25.09.2016.
PGCIL and NTPC had filed a Petition No.42/RP/2016 and No.44/RP/2016 for review of
the Order dated 27.6.2016 in Petition No. 236/MP/2015 in respect of KTL Transmission
Lines. The Petition was heard on 19.01.2017 and has been listed for hearing on
28.02.2017.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 92
KTL had filed Petition (248/MP/2016) with IA No. 64/2016 before Hon‟ble CERC in
the matter of „Petition for set-aside the letter dated 5.12.2016 issued by Bangalore
Electricity Supply Company Limited (BESCOM).‟ In the ROP dated 03.01.2017
following was directed :
„4. As regards the prayer in the IA, the Commission directed the petitioner to give a
bank guarantee of Rs. 4.3 crore by 9.1.2017 in favour of BESCOM (or the amount as
may be calculated as liquidated damages by BESCOM for the delay) for a period of
six months. The Commission directed BESCOM not to encash the bank guarantee
without seeking permission of the Commission. Subject to the above, the Commission
directed BESCOM not to take any coercive action against the petitioner in terms of its
letter dated 5.12.2016. Accordingly, IA was disposed of……….
The petition shall be listed for hearing on 9.2.2017.‟
The petition was heard on 09.02.2017 and was listed for 23.03.2017
NTPC had filed Petition (51/RP/2016) before Hon‟ble CERC in the matter of „Review of
Commission‟s order dated 29.7.2016 in Petition No. 201/TT/2015 in the matter of
approval of transmission tariff for 4 nos. 400 kV Line bays at Narendra (New) for Kudgi
TPS-Narendra (New) 400 kV 2XD/C Quad lines, under "Sub-station Extension works
associated with transmission system required for evacuation of Power from Kudgi TPS
(3X800 MW in phase-I) of NTPC Limited" in Southern Region for 2014-19 tariff period
under Regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC
(Terms and Condition of Tariff) Regulations, 2014‟. Hon‟ble CERC had admitted the
Petition and was listed for 06.12.2016 and had stated
„7. The staff of the Commission is directed to provide a copy of the instant review
petition to CEA and request CEA to give its comments on the NTPC‟s contention that
the Kudgi-Narendra (new) line can be utilized for drawl by Karnataka through ICTs
by 25.11.2016.‟
The petition was heard on 24.01.2016 and hearing on the matter was closed.
CEPL had filed Petition (246/MP/2016) in the matter of „Petition seeking deferment of
Long Term Open Access and relinquishment of part allocation of Long Term Open
Access under the Bulk Power Transmission Agreement dated 24.02.2010 under
Regulation 18 read with Regulation 32 of the Central Electricity Regulatory
Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access
in inter-State Transmission and related matters) Regulations, 2009‟. The Petition was
admitted and was heard on 17.01.2017and is now listed for 28.02.2017.
TPCIL had filed Petition (240/MP/2016) in the matter of „Petition for seeking
declaration that no relinquishment charges are payable for termination of the Medium-
term Open Access, dated 6.10.2015, granted to the petitioner by Power Grid
Corporation of India Limited‟. The Petition was admitted and was heard on 17.01.2017
& 24.01.2017 and is now listed for 10.03.2017.
In the 125th
OCCM, NLC had informed that the construction works of the NNTPP are in
advanced stage and startup power of about 32.5 MW is required for trial operation of all
major equipments of the plant from February 2017.Connectivity of the plant with 400kV
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 93
system was granted by PGCIL vide intimation No.C/SEF/TA/C/S/11/17(R1) dt 18-11-
2013. Signing of Connection Agreement is in progress. The commissioning of the LILO
of 400 KV TPS-II – Pondicherry S/C Line at NNTPP Switchyard through which
connectivity is granted is scheduled to be completed on 31.03.2018 by PGCIL. In the
35th
Meeting of Standing Committee held on 04th
January 2013, as System
Strengthening, it was agreed for LILO of both circuits of 230 KV Neyveli TS-I –
Neyveli TS-II D/C line at NNTPS switchyard by NLC. These lines are owned by NLC
India Limited. Considering startup power requirement from February 2017, it is
proposed to avail startup power under DSM basis through the LILO of 230 KV lines
from TPS-II ISTS Switchyard and SEMs will be installed at all the locations for
computation of startup power drawn by NNTPP.
PGCIL vide their letter dated 01st August 2016 had informed works of Extensions of
230 kV Main and Transfer Buses in TANTRANSCO Switchyard at Checkanoorani 230
kV Station (Madurai SS) under SRSS-XXIII and Alunder 230 kV Station (Trichy SS)
under SRSS-XX are yet to be taken up by TANTRANSCO. PGCIL is expected to
commission ICT-3 at Madurai by September 2016 and at Trichy by December 2016.
TANTRANSCO had been requested to kindly expedite the aforesaid works. CTU had
stated that the issue of coordination and downstream network not being ready would
come into picture and charges would be required to borne as per Hon‟ble CERC‟s
Order. TNEB had assured of necessary action at their end. Subsequently, it was noted
that Madurai ICT was declared on COD from 31.12.2016.
Information regarding Cyber Security to be furnished to Chief Engineer, DPD, CEA,
New Delhi. Report on Physical Security, other Mock Drills for CMP, Mock Drill for
Black Start Restoration to be furnished to Chief Engineer, DMLF, CEA, New Delhi.
Copy of the report is to be sent to SRPC Secretariat by e-mail.
SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed to discuss
status review of System Protection using Optimization Technique– 30th
TCC: SRLDC
informed that they were planning a visit to Kolar along-with ABB Engineer with
participation and inputs from PGCIL Engineers. It was noted that the SPOT was only
in preliminary stage and SRLDC could bring the issue when a concrete technically
viable proposal is firmed up.
SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed to discuss
review of operation of Inter Regional and Intra Regional Links like Upper-Sileru-
Balimela etc - 30th
TCC: It was noted that the NLDC & other RLDCs could coordinate
to make these Inter Regional line operational. Other Intra-Regional lines need
concurrence of SLDCs and can be discussed in OCC.
KSEBL vide letter dated 17.02.2017 (Annexure-XLVII) had raised the issue of
replacement of PLCC protection coupler for Kayamkulam transmission system
maintained by PGCIL. 30th
TCC: PGCIL informed that PLCC protection coupler would
be replaced by them under their O&M head.
KSEBL vide letter dated 17.02.2017 (refer Annexure-XLVII) had raised the issue of
providing a Service Engineer at site for the maintenance of Fibre Optical Terminal
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 94
equipments at site: PGCIL stated that as per contract, the Service Engineer needs to be
available within certain time. KSEBL stated that on one of the occasion, it had taken
more than one day for the Engineer to respond and on few occasions, it was affecting
the VC connectivity. PGCIL agreed to look into the term and condition of Maintenance
Contract and M/s Tejas would be advised to adhere to it.
TSTRANSCO suggested a SPS for ICT tripping/loading at NTPC, Ramagundam. It was
agreed SRLDC & TSTRANSCO would study the scheme. The loads would be provided
by TSTRANSCO. NTPC, Ramagundam to extend cooperation for implementation of
the SPS. MS, SRPC suggested for augmentation as SPS would provide temporary relief
only. TSTRANSCO clarified that new substations are coming in that area which would
reduce the loadings of Ramagundam ICTs.
SRLDC stated that Point to Point Black Start mock exercise needs to be given more
importance and needs to be completed twice a year.
35.13.1 SRPC noted the above and suggested concerned entities to initiate action/corrective
action
36 SHARING OF TRANSMISSION CHARGES OF TRANSMISSION ASSETS OF
NATIONAL IMPORTANCE
36.1 The following had been deliberated in earlier Meetings:
Hon‟ble Commission in its Order in Petition No. 67/TT/2015 (Sharing of Transmission
charges) had stated the following in Para 30 in its Order dated 08.01.2016:
“Since, these assets are proposed to be considered as assets of national importance
and all the regions are proposed to bear the transmission charges, we consider it
necessary to hear the DICs of all the regions”.
KSEBL/TANTRANSCO had stated that the planning of this system had not been
deliberated in the Standing Committee of SR and SRPC Meetings. In the present scenario
the SR constituents were unlikely to reap any benefit from this HVDC links between NER
and NR.
Subsequently, Chairperson, SRPC vide letter dated 16.03.2016 had taken up the issue
with Chairperson, CERC.
In the ROP for date of order dt.03.03.2016, the following had been stated:
„…Accordingly, we direct that the transmission charges allowed in para 6 of this
order shall be provisionally recovered from DICs of all regions in accordance with
the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State
Transmission Charges and Losses) Regulations, 2010 as amended from time to time,
subject to the final decision of the Commission in the present petition. It is further
directed that any grant/assistance received from Government of India/PSDF Fund
shall be applied to reduce the cost of the assets and consequently, the transmission
charges of these assets. We direct PGCIL to pursue the matter in the right earnest
for early release of grant/assistance.‟
In the ROP for date of hearing 19.04.2016, the following had been stated:
„………..The Commission directed the respondents, who have not filed their reply, to
file reply as a last opportunity by 29.4.2016 and the petitioner to file rejoinder, if any,
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 95
by 6.5.2016. The Commission directed the parties to comply with the directions within
the timeline specified.
4. The Commission directed to list the matter on 31.5.2016 for final arguments.‟
In the ROP of Hon‟ble CERC for date of hearing 05.07.2016 it was noted that submissions
had been made by various entities like GRIDCO, KSEBL etc and final Order was awaited.
36.2 PGCIL had filed Petition (184/TT/2016) in respect of „Determination of transmission tariff for
asset ± 800kV Biswanath Chariali -Agra HVDC Pole-II (1500MW HVDC Terminal at
Biswanath Chariali and Agra) along with Earth Electrode line and Earth Electrode Station for
both Biswanath Chariali and Agra from anticipated CoD 1.9.2016 to 31.3.2019….”. Hon‟ble
CERC in its Order dated 27.12.2016 had stated
„6. Reply has been filed by Uttar Pradesh Power Corporation Limited (UPPCL),
Respondent No. 12, vide affidavit dated 17.10.2016, BSES Rajdhani Power Limited
(BRPL), Respondent No. 22, vide affidavit dated 3.11.2016 and Kerala State Electricity
Board (KSEB), Respondent No. 35, vide affidavit dated 22.11.2016. Issues raised by
respondents will be considered at the time of grant of final tariff. After carrying out
preliminary prudence check of the AFC claimed by the petitioner, we are inclined to grant
AFC for ±800kV Biswanath Chariyali-Agra HVDC Pole-II covered in the instant petition
in terms of proviso (i) of Regulation 7(7) of the 2014 Tariff Regulations as given in para 7
of this order for the years 2016-17 and 2017-18.
………………….
9. The petitioner is further directed to file the additional information sought vide RoP
dated 17.11.2016 with a copy to respondents by 30.12.2016. The parties are directed to
complete the pleadings by 10.2.2017.
10. The matter shall be listed on 21.2.2017 for final hearing.‟
36.2.1 SRPC deliberations
36.3 MS, SRPC informed that Hon‟ble CERC in Petition No.67/TT/2014 (date of order 07.02.2017)
had noted „……………..tariff allowed for the instant assets up to 31.3.2017 is extended for the
year 2017-18 under proviso (i) of Regulation 7(7) of the 2014 Tariff Regulations for inclusion
in the POC charges, subject to adjustment as provided under proviso (ia) of Regulation 7(7) of
the 2014 Tariff Regulations.‟
37 THOROUGH REVIEW OF ALL THE DRAWAL POINTS OF STATES FOR
DRAWAL COMPUTATIONS
SRPC vide letter dated 30.10.2015 had circulated revised methodology to identify the
node points and touch points in a node for Southern Region.
This methodology was noted in the 30th
SRPC Meeting and also in the 31st and 32
nd
CCM. As per deliberations of the 32nd
CCM, accounting based on Nodal points identified
for drawl was used for accounting of Energy in the Southern Region from 7th
November
2016 onwards.
37.1 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 96
38 IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT
SYSTEM (PMS) FOR SOUTHERN REGION
38.1 In the 26th
Meeting of SRPC held on 20th
December, 2014 at Visakhapatnam, SRPC had
approved the proposal to procure Protection Suite (Protection Management System) that
comprises Web based management software and protection setting calculation tool through
PSDF funding.
38.2 In this regard, steps have been initiated to procure Protection Suite through PSDF funding. A
total of 35 licenses would be procured for the Constituents of Southern Region. After
obtaining approval for PSDF funding, tendering process for executing Protection Management
Suite would be initiated. For evaluating the technical and financial bids that would be
received, a Committee comprising members from SR-Constituents would later be constituted
with approval from Chairperson, SRPC.
38.3 SRPC deliberations
38.4 It was noted that the Proposal of PMS for PSDF funding had been approved by the Monitoring
Committee and Sanction Order had also been received from MoP. Bidding documents were
under preparation.
39 POWER SYSTEM ANALYSIS GROUP (PSAG-17) MEETING HELD ON 3rd
& 4th
OCTOBER 2016 AT NTPC-SIMHADRI STPS, KALPAKA SS AND HNPCL TPS
39.1 On 6th
September, 2016, multiple trippings took place in Kalpaka – Gazuwaka – Hinduja
NPCL – Simhadri (KGHS) Corridor with Kalpaka as the epicentre. Though the triggering/
initiating cause was the failure of the Y-ph limb of Circuit Breaker (CB) of Bus Reactor -3
(BR-3) at 400/ 220 kV Kalpaka SS of APTRANSCO, certain anomalies had been observed in
the protection system operation that became manifest in the consequent multiple trippings in
the transmission network adjoining Kalpaka SS.
39.2 Keeping in view importance of KGHS Corridor and the gravity of the issues involved, a
PSAG-17 team comprising Officials from SRPC, SRLDC, KPTCL, KSEB, PGCIL (SRTS-I),
APTRANSCO, NTPC and HNPCL held their Meeting on 3rd
& 4th
October, 2016 at NTPC-
Simhadri STPS, Kalpaka SS and HNPCL TPS, and made field visits to their Control Rooms
& Switchyards.
39.3 Committee, after thoroughly analyzing various issues involved, had submitted following set of
recommendations to be complied with by APTRANSCO, NTPC-Simhadri, PGCIL (SR-I)
and HNPCL:
Revision of Bus Bar Protection (BBP) relay‟s settings & ascertaining reasons for
Breaker failure at Kalpaka SS of APTRANSCO.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 97
Measures to sort out development of sudden & steep Over Voltage on Simhadri –
Kalpaka lines 2 & 3 & 4 at Simhadri end.
Provision of external Auto-Reclose (A/R) relays on Kalpaka bound lines at Simhadri
STPS (Stage-I).
Distance protection settings (Zone-2 & Zone-4) for the lines emanating from Gajuwaka
- Kalpaka - Simhadri – HNPCL Corridor.
Provision of Line differential Protection on all 400 kV transmission lines
interconnecting Gazuwaka SS (PGCIL-STRS1), Simhadri STPS (NTPC), Kalpaka SS
(APTRANSCO), and Hinduja TPS (HNPCL).
Providing for proper substation maintenance equipment like DCRM, PPI test kit,
thermo-vision scanning camera at Kalpaka SS of APTRANSCO.
Provision of GPS/ Time synchronization facility in all 220 kV & above substations/
generation switchyards in Gazuwaka – Simhadri – Kalpaka Corridor.
39.4 Additionally, on request of NTPC-Simhadri, system studies pertaining to power evacuation
from Kalpaka – Gazuwaka – HNPCL – Simhadri (KGHS) Corridor were carried out and
presented. Also field visits to Control Room & Switchyard of NTPC-Simhadri STPS,
Kalpaka SS and HNPCL TPS had been undertaken to get first-hand information of the
adopted relay settings & protection practices being followed.
39.5 The compliance report is given at Annexure-XLVIII
39.6 TCC deliberations
APTRANSCO, PGCIL (SR-I), NTPC-Simhadri & HNPCL were requested to initiate steps
to comply with recommendations given, especially line differential protection, at the
earliest.
39.7 SRPC noted the above.
40 AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE
TRANSMISSION LINES OF SOUTHERN REGION
40.1 Majority of faults that occur on transmission lines are of transient nature; hence provision
of Auto-Reclosure certainly helps not only in preventing forced outage of the subject
transmission line, but also in averting cascade trippings, in some cases, of adjacent
transmission lines due to consequent over-loading.
40.2 Provision for Auto-Reclosure is also mandated by Regulation 43 (4) (c) of CEA Technical
Standards for Construction of Electrical Plants and Electric Lines, 2010, which has force of
law. Therefore, it is in the interest of grid security that all Constituents implement auto-
reclosure feature on all 220 kV & above transmission lines in their respective control areas.
Any exceptions to this needed to be properly justified.
40.3 This issue had been discussed in PCSCM-60 held on 22.12.2016, wherein the logics to be
used for implementing A/R was clarified. All Constituents, in whose 220 kV & above
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 98
network A/R had not yet been implemented, were requested to furnish an action plan for
providing the same by PCSC-61 Meeting schedule to be held on 27.01.2017.
40.4 SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed A/R issues for
discussion.
40.5 TCC deliberations
Status of implementation of A/R (excluding Radial feeders & Cables) as furnished by
SR-Constituents is given at Annexure-XLIX Action plan furnished by SR-Constituents
for implementing A/R on the transmission lines, where it is presently not in service is
given at Annexure-L.
APGENCO, APTRANSCO, TSGENCO, TSTRANSCO, NLCIL, NTPC-Ramagundam
and BHAVINI had not furnished the Action Plan for implementing Auto-Reclosure in
their 220 kV & above voltage level transmission lines.
TCC noted the following :
All above Constituents agreed to furnish the detailed Action Plan for implementing A/R
in their 220 kV & above voltage level transmission lines by next PCSC-62 Meeting
scheduled to be conducted on 15th
March 2017.
All SR-Constituents were kindly requested to take steps to implement A/R in their
respective networks at the earliest.
40.6 SRPC noted the above.
41 STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY
RESOURCES INTO THE GRID
41.1 The proposal had been approved by Monitoring Committee and sanction Order has been
issued by MoP. Bidding Documents have been floated through E Procurement mode. The
last date for receipt of bids is 2nd
March 2017. Nominations will be sought from utilities in
Southern Region for the study programme on integration of RES. Nominations from utilities
will also be sought to two Assessment Committees for this scheme. While one Assessment
Committee will carry out technical scrutiny of the proposals received, the second Assessment
Committee will carry out scrutiny of the commercial proposals.
41.2 SRPC deliberations
41.3 MS, SRPC informed that NIT had been floated. Technical/Price bids would be opened in first
week of March 2017. Nominations would be sought from utilities shortly in this regard.
42 SPECIAL MEETING WITH M/S KPCL HELD ON 27.10.2016 AT SRPC,
BENGALURU
42.1 A Special Meeting was conducted on 27th
October, 2016 at SRPC Secretariat, Bengaluru to
deliberate on the issues concerning hydro power stations (HPS) of M/s KPCL in the context
of Grid Disturbances (GD‟s) during August – October, 2016 that had led to complete outage
of few hydro power stations of M/s KPCL.
42.2 In the Meeting, apart from specific issues that had caused GD‟s at various hydro power
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 99
stations, general issues required to be given attention by KPCL to avoid recurrence of such
events in future were also discussed. Deliberations revolved around the following issues:
Ensuring proper protection setting of all newly commissioned & to-be-commissioned
relays.
Auto-Reclosure implementation on all 220 kV lines emanating from KPCL‟s generating
stations.
Providing for Double Main-Bus operation at all 220 kV HPS‟s of KPCL.
Provision of stand-alone Disturbance Recorder (DR) & stand-alone Event-Logger (EL)
at all HPSs of KPCL.
Station-specific recommendations covering 220 kV Nagjheri PH, 220 kV Kadra PH,
220 kV Sharavathy Tail Race PH, 220 kV Varahi UGPH and 220 kV Sharavathy PH.
Additionally, following running operational issues of KPCL were also discussed:
RGMO performance
RGMO status point extension to SLDC/SRLDC
PSS tuning related issues
CoD of Bellary TPS (Unit-III), and Yeramarus TPS (Unit-I)
Mock-Drill of Black-Start restoration
42.3 TCC deliberations
Compliance Status as furnished by M/s KPCL vide their letter dated 26.11.2016 is at
Annexure- LI. MS, SRPC had suggested KPCL to look into the recommendations of
providing for Double Main-Bus operation at all 220 kV HPSs of KPCL as a long term
measure.
43 IMPLEMENTATION OF LINE DIFFERENTIAL PROTECTION (LDP)
43.1 NPC vide letter No. 4/ MTGS/ NPC/ CEA/ 2016 dated 27.10.2016 had requested to discuss
implementation of Recommendation on Line Differential Protection of the Sub-Committee
on Relay/Protection under Task Force for Power System Analysis under contingencies
(Para14 in Section-6 of the report under Relay setting guidelines for Transmission lines).
43.2 In this regard, the issue was discussed by PCSC forum in their 59th
Meeting held on
22.11.2016. The deliberations focused on the logic to be followed for LDP implementation,
fit-cases for LDP implementation, and general guidelines for implementing LDP.
Application of System Studies to ascertain the fit-cases for implementing LDP was also
explained (Ref: MoM of PCSC-59 issued vide SRPC letter no: SRPC/ SE-III/ PCSC-59/
2016/ 7890 – 23 dated 08.12.2016)
43.3 Subsequently, the issue had been discussed in the 6th
Meeting of NPC held on 19.12.2016 at
Bengaluru, where it was decided that the same sub-group formed for PSS would also look
into various aspects of implementing LDP.
43.4 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 100
44 PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS
44.1 In recent times insulator tracking has been observed in Transmission lines and Substations
located in the coastal and polluted areas and SRPC vide letter dated 05th
May 2016 had
communicated to the concerned in this regard. Transmission Lines and Substations in the
most vulnerable terrain, coastal and polluted areas were to be categorized for monitoring to
ensure that Patrolling and Maintenance is being carried out as per Patrolling guidelines.
Format for furnishing details of schedule / Patrolling and Maintenance carried out of the
critical Transmission lines and Substations had been enclosed.
44.2 Concerned entities need to kindly initiate/continue necessary steps to ensure that Patrolling
and Maintenance is carried out regularly as per the Patrolling Guidelines.
44.3 SRPC noted the above and suggested to maintain sustained efforts in this direction.
45 7th
MEETING OF NATIONAL RELIABILITY COUNCIL FOR ELECTRICITY HELD
ON 07.12.2016 AT NRPC, NEW DELHI
45.1 In accordance with the decision taken in the 6th
Meeting of NRCE, two sub-groups had been
constituted to work on the following (Ref: MoM of NRCE-6 issued vide NPC letter
no:3/NRCE/NPC/CEA/2016/35-63 dated05.01.2016)
Sub-Group to finalize Protection and Communication Standards
Sub-Group for the purpose of determination of TTC/ATC/TRM and to suggest a clear-
cut methodology for calculation of ATC, TTC & TRM to POSOCO to comply with.
45.2 Previously all RPC‟s were represented in the second sub-group only. In the 7th
NRCE
Meeting, it was agreed to invite Members from all RPCs in the first sub-group Meetings
also as Special Invitees.
45.3 SRPC Secretariat vide letter dated 25.01.2017 (Annexure-LII) had taken up certain issues
in respect of TTC/ATC and congestion with NRCE.
45.4 SRPC noted the above.
46 SRPC REPORT ON “EFFECT OF DELAYED CLEARANCE OF FAULT ON
TRANSMISSION SYSTEM”
46.1 Hon‟ble CERC vide their Order dated 14.06.2016 in respect of petition no: 9/SM/2014 on
“Investigation of tower collapse and load crash in northern region on 30.05.2014” and petition
no: 10/SM/2015 on “Investigation of line outages due to tower collapse in northern region
during April-June, 2015” had noted that delayed clearance of faults is a serious issue and
directed RPC‟s to examine the cases of delayed clearance of faults on the transmission system
during last two years in respective region, and submit an analysis report on the same.
With respect to above, SRPC had considered the instances of delayed fault clearance that
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 101
occurred between April 2014 – May 2016 from SRLDC Database, and sought comments from
concerned SR-Constituents. Based on the inputs furnished by SR-Constituents, and available
regulations/ guidelines/ reports/ literature on the subject, a report had been compiled and
submitted to Hon‟ble CERC vide SRPC letter dated 14.12.2016. This report was included in
MoM of PCSC-60 issued vide SRPC letter dated 06.01.2017.
47 PROTECTION AUDIT OF 400 KV ALUNDUR SS OF PGCIL (SR-II) AND 230 KV
ALUNDUR S/S OF TANTRANSCO
47.1 Hon‟ble CERC vide Order dated 27.04.2015 in respect of Petition No.95/MP/2015 dated
09.04.2015 had directed SRPC to submit bi-monthly report of periodic protection audit
details to the Hon'ble Commission.
47.2 In this regard, for the period covering 01.11.2016 – 31.12.2016, the following substations had
been protection audited:
Sl
No
Name of the substation
audited
Date of
Protection
Audit
Audit Team
Composition
1 400 kV Alundur SS of PGCIL
(SR II)
16.12.2016 SRPC, SRLDC &
KPTCL
2 230 kV Alundur SS of
TANTRANSCO
17.12.2016 SRPC, SRLDC,
PGCIL & KPTCL
47.3 Remarks of the protection team given at Annexure-LIII were submitted to Hon‟ble CERC
vide SRPC letter dated 02.01.2017.
PGCIL (SR-II) and TANTRANSCO were requested to take suitable action to comply with
the remarks given.
47.4 In this regard, Compliance Status furnished by PGCIL (SR-II) is given at Annexure-LIV.
47.5 SRPC noted the above.
48 SPECIAL MEETING ON NEYVELI GRID DISTURBANCE
48.1 A Special Meeting had been conducted on 03rd
January 2017 in SRPC Secretariat,
Bengaluru with Officials of TANTRANSCO, NLCIL, Puducherry, ST-CMS and SRLDC
along with participation of KPTCL & KSEBL to deliberate on various issues involved in the
Neyveli Grid Disturbance that occurred on 25th
November, 2016.
48.2 Compliance status is given at Annexure-LV.
48.3 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 102
49 PENDING IMPLEMENTATION OF RECOMMENDATIONS OF PROTECTION
COORDINATION SUB-COMMITTEE (PCSC) OF SRPC
49.1 Recommendations given in various PCSC Meetings to SR-Constituents are being sent
regularly to the concerned Constituents for implementation. Update of the consolidated list
of pending PCSC recommendations (up to the 60th
Meeting) for implementation by SR-
Constituents is enclosed in the minutes of PCSC.
49.2 SRPC noted the above and suggested appropriate time bound action by the entities to close
all the issues.
50 COMMERCIAL COMMITTEE ISSUES
50.1 Following issues had been discussed in the CC Meetings and brought to the attention of
SRPC/TCC:
Audit of SR UI/Deviation Account &Reactive Energy Pool Account
Assessment of Metering requirement
CCM forum requested SRTS I, PGCIL, STUs, Generators and IPPs to submit the SEM
requirements and procurement plan for the power system elements as per CEA Metering
regulations for the upcoming projects to the SRLDC and SRPC Secretariat .
Non Availability of SEMs as per CEA metering regulations
In the 32nd
Meeting of CCM, SRTS II, PGCIL had stated that irrespective of the
ownership of the bay and line, the owner of the sub-station shall install the SEM at their
stations. Consolidated list of locations where SEMs are not available as per CEA Metering
Regulations is given below:
S.No Element Non availability of
SEM
To be installed by
1 MAPS: GTs (HV side) Stand By CTU/MAPS
2 Vallur : 400 kV NCTPS lines 1
& 2
Check NCTPS/CTU
3 400 kV UPCL-Hassan line
1&2
UPCL CTU/KPTCL/UPCL
4 400 kV Nelamangala-Hassan
line
Nelamangala CTU/KPTCL
5 400 kV Talaguppa-Hassan Line Talaguppa KPTCL
6 400 kV Guttur-Hiriyur lines
1&2
Both Guttur and Hiriyur CTU / KPTCL
7 Bonakaalu - Chillakallu lines
1&2
Bonakaalu end of 132
kV Line
TS
8 400kV Hiriyur-BTPS lines
1&2
Both Hiriyur and BTPS KPTCL
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 103
Non-compliance / pending issues as per 3rd
Meeting of Nodal Officers for SEM Data
Coordination and 32nd
CCM
Sl No Description 32nd
CCM deliberations Status
a Replacement of
SEMs at
Thiruvalam and
Theni
TANTRANSCO informed
that SEMs arrived at the site
and they were waiting for LC
to install the SEM.
The forum requested
TANTRANSCO to take up
with SRLDC to avail the LC
to replace the SEMs at the
earliest and inform SRPC.
TANTRANSCO
yet to install the
SEMs.
b Non receipt of
SEM data from
Kadra, Kodasalli,
Guttur and
Nelamangala.
KPTCL yet to install the
SEM.
KPTCL yet to
install the SEMs.
Approval of Metering Scheme for new Generation and Transmission scheme
All SR constituents had been requested to submit the Metering scheme to SRLDC / SRPC
with the requisite documents to get it approved in the CCM of SRPC.
Submission of C1-C4 formats for New Element Charging
As per the new NLDC procedure, complete C1-C4 format needs to be submitted, soon
after successful trial operation, to declare COD.
Failure to intimate new Bay charging details to SRLDC
All entities had been requested to inform SLDC/SRLDC and the other end utility (if
applicable) regarding the bay changing works etc, that affect commercial accounting
issues to have effective and correct accounting system.
Non-compliance/Pending Issues as per 3rd
Meeting of Nodal Officers for SEM Data
Coordination
It was noted that certain SEM issues raised were yet to be resolved.
50.2 SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed following issues
for discussion:
Replacement of defective meters/ high time drift (Say more than 10 minutes) meters and
action for attending the time drift in meters with time drift less than 10 minutes.
Reconciliation and confirmation of STOA transactions payments made, TDS deduction
etc to SRLDC by 10th
of following month.
50.3 KSEBL vide letter dated 31.01.2017 (refer Annexure-XVIII) had stated that there was
mismatch in the scheduled energy for the MTOA transaction between MPL and KSEBL for
the month of August 2016 in the REAs of SRPC and ERPC. On 1st August 2016 while
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 104
revision was carried out at SRLDC (Block 40 to 82), corresponding revision has not been
taken into account by ERPC. ERLDC has not issued any revision for these blocks. It has
been stated that energy account of ERPC needs to be corrected.
50.4 TCC deliberations
Regarding KSEBL issue (MTOA transaction in August 2016), SRLDC had informed that
the matter has been taken up with ERLDC.
KPTCL had informed that they had requested for 11 SEMs urgently from PGCIL. SR-II,
PGCIL informed that they had purchased spares SEMs for their use but 11 nos would be
provided to KPTCL.
TCC had noted the above issues and suggested concerned entities to take necessary steps
to close the issues.
50.5 SRPC noted the above.
51 ISSUES IN BILLING OF GENERATING STATIONS OWNED BY NTPC (TARIFF
PERIOD 2014-19)
51.1 KSEBL vide letter dated 31.01.2017 & 17.02.2017 (refer Annexure -XVIII & XLVII) had
stated that NTPC have adjusted the total moisture content of coal resulting in increase of
working capital and hence increase in AFC. Once the adjustment has been made by CERC
and working capital for the entire tariff period is fixed, further adjustment in working capital
cannot be allowed. NTPC cannot make further adjustments and claim different amount from
the beneficiaries. It is stated that claim of NTPC is not in line with the Regulations and
Orders of CERC.
51.2 TCC deliberations
KSEBL had stated that there was discrepancy in AFC computation as there was
duplication of the moisture content adjustment in the Tariff Orders.
NTPC had stated that adjustment of GCV for moisture content and billing is as per
CERC Order and CERC Regulations. It was mentioned in the Order of Tariff that „6.
Adjustment on account of coal received at the generating station for equilibrated basis
(Air dried) in the billed GCV Of Coal India‟ is „To be calculated by the petitioner
based on the adjustment formula‟ and „Rate of energy charge ex-bus‟ is „ to be revised
as per the figures at Sr. No. 6‟.
TCC had observed that NTPC computation appeared to be in line with CERC
Order/Regulations.
51.3 SRPC noted the above.
52 TPCIL REQUEST TO EXEMPT DEVIATION CHARGES
52.1 TPCIL vide letter dated 07.01.2016 had requested for to consider the event of 30.12.215 as
“force majeure” during CTU system outage (ISTS) and revise the deviation account for the
week 28.12.15 to 03.01.16.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 105
52.2 Issue was deliberated in the 31st CCM wherein it was noted a Working Group of NPC was
Meeting shortly to recommend the methodology for „Treatment of Bilateral short term and
collective transaction in case of grid disturbances‟. In the 6th
Meeting of NPC held on
19.12.2016, NPC had finalized the methodology and it would be put to CERC.
52.3 TPCIL had filed a Petition No.193/MP/2016 which was heard on 19.01.2017 and admitted.
The petition was listed for hearing on 16.03.2017.
52.4 SRPC noted the above.
53 SCHEDULING OF NTPC RAMAGUNDAM SOLAR POWER PLANT (10 MW)
53.1 A Special Meeting was held on 17th
November 2015, to facilitate scheduling by SRLDC
and identifies certain prerequisite criteria to be ensured by NTPC. The issue is being
followed up in the OCC Meetings.
53.2 The following had been noted in earlier Meetings:
NTPC had informed that any decision regarding scheduling domain would be as per
Regulations. For a small plant of 10 MW, it was not appearing feasible for two states
have a share in it. Concurrence from Andhra Pradesh and Telangana had been received
in this regard. Some power could be given to Andhra Pradesh from other NTPC Solar
plant (NP Kunta) while this plant could be dedicated solely to Telangana.
SRPC had stated that in that case, MoP may need to be approached for necessary
amendment with regard to unallocated power linked with this project.
53.3 SRLDC vide letter dated 07.02.2017 (refer Annexure-XII) had proposed the issue for
discussion:
53.4 TCC deliberations
NTPC informed that concurrence from AP and TS has been received and they would be
approaching MoP in this regard.
54 SCHEDULING OF UNITS BELOW TECHNICAL MINIMUM AND OTHER ISSUES
54.1 Issue of scheduling the units below technical minimum and other issues were deliberated in
detail in 29th
TCC/30th
SRPC Meetings. After deliberations, it was agreed that CEA‟s advice
would be sought for smoother facilitation of renewable integration.
54.2 SRPC Secretariat vide letter dated 29.08.2016 (Annexure-LVI) had taken up the issue with
CEA. Subsequently, CEA had informed that major issues were covered under Committee of
Merit Order Operation and Must Run Status for Renewable.
54.3 TCC deliberations
SRLDC had enquired about the action to be taken during this wind season.
It was noted that the Procedure on Technical Minimum/Compensation may come out
shortly.
54.4 SRPC noted the above.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 106
55 MONITORING OF SCHEMES FUNDED FROM PSDF
55.1 In the 6th
Meeting of NPC held on 19.12.2016 (MoM dated 12.01.2017 available on CEA
website) it was noted that in a Meeting held on 29.04.2016 chaired by Joint Secretary (OM),
MoP to review the status of implementation of the schemes funded from PSDF, it was felt
prudent that respective RPC Secretariat monitor the schemes approved in its region, in
addition to the Monitoring Group at Central level, as part of monthly Meetings, in view of
slow progress of the implementation of the schemes.
55.2 After deliberations, it was decided that NPC Secretariat would put up Agenda on monitoring
of schemes funded from PSDF for deliberation in the OCC Meetings of RPCs. RPCs agreed
to take up monitoring of schemes funded from PSDF in monthly OCC Meetings on regular
basis for updating the status of implementation.
55.3 In the 127th
OCC Meeting, NPC representative had appraised the OCC on monitoring
requirements. All concerned entities are kindly requested to ensure needful.
55.4 TCC deliberations
MS, SRPC had stated that the PSDF funded schemes were to be monitored in the OCC as
per the directive of MoP through CEA.
NPC had expressed concern that implementation of projects and disbursement was not as
desired. In respect of KPCL, the progress was slightly better. With regard to TN, for two
schemes, amount had been drawn only for one scheme. For Puducherry, the scheme had
been sanctioned in August 2015 while the agreement was still to be signed.
TSTRANSCO had stated that the first batch of sanction had a time period of one year
from the date of sanction. For the first batch scheme, 50 % works were over and they
required extension to complete the works. NPC had informed that as noted in the last
review Meeting, TSTRANSCO needed to approach NLDC for extension.
APTRANSCO had stated that all the required documents for disbursement of the
installment has been furnished to NLDC and the payment release needs to be expedited.
55.5 SRPC urged the agencies to take urgent steps to ensure needful.
56 SALE OF URS POWER BY NLC STAGE-II
56.1 In the 126th
OCC Meeting, TSTRANSCO had expressed concern that NLC was selling power
outside for a price less than variable charge (Rs.2.598/unit for the month of December 2016).
After giving consent, they were losing the chance to recall the surrendered power and selling
below variable price which was against the spirit of Tariff policy.
56.2 SRPC noted the above.
57 SCHEDULING OF KAMUTHI SOLAR PARK
57.1 Two Meetings had been convened on 03.11.2016 and 23.12.2016 at SRPC, Bengaluru to
discuss scheduling and dispatching responsibility in respect of Adani Solar Power Project at
Kamuthi in Tamil Nadu. Minutes of the two Meetings are available at SRPC website. In the
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 107
Meeting held on 23.12.2016, the following was concluded:
„After deliberation it was decided that M/s. AGEL would obtain legal advice and
submit the same to SRPC & SRLDC. Subsequently SRPC would refer the matter to CEA
for legal advice. Tamil Nadu was also requested to consider furnishing their inputs to
SRPC/CEA at the earliest.‟
57.2 Legal opinion from M/s AGEL had been received.
57.3 SRPC deliberations
57.4 It was noted that legal opinion of M/s AGEL and POSOCO had been referred to CEA.
58 SETTLEMENT FOR THE PERIOD PRIOR TO BIFURCATION OF AP AND
TELANGANA
58.1 A Meeting was held on 25.10.2016 At Hyderabad to deliberate the settlement of bills for the
period prior to AP and Telangana and other issues. Minutes of the Meeting are available on
SRPC website.
58.2 SRPC deliberations
58.3 It was noted that there were some issues in respect of PGCIL payments for AP and Telangana
and a separate meeting at Hyderabad would be arranged.
59 AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM
59.1 KSEBL vide letter dated 25th
September 2015 had stated that since all Southern states would
get benefitted with the early commissioning of Talcher-II transmission system, all SR
Constituents may jointly implead as a party in the Civil Appeal filed by TNEB before Hon‟ble
Supreme Court. In the 27th
TCC Meeting it was suggested that SR constituents may jointly
implead as a party in the Civil Appeal filed by TNEB in Honorable Supreme Court.
59.2 Hon‟ble Commission in its Order dated 05.11.2015 in respect of Petition No. 14/SM/2015, in
the matter of „Notice under Section 19 of the Electricity Act, 2003 for revocation of the inter-
State transmission licence granted to Talcher II Transmission Company Ltd.‟ had passed the
Order :
„13. In exercise of our power conferred under Section 19 (3) of the Act and Regulation 20
of the Transmission Licence Regulations notice is given to the licensee to show cause
within three months from the date of this order as to why the transmission licence granted
for the transmission project should not be revoked in terms of the provisions of Section 19
of the Electricity Act and Transmission Service Regulation as quoted above. If no response
is received within three months from the date of issue of the order, the licence shall be
deemed to have been revoked.‟
59.3 In the 29th
Meeting of SRPC, TANTRANSCO had stated that as discussed in earlier SRPC
Meeting, all constituents had been suggested to jointly implead but no action has been
taken. They were in the process of invoking the Bank Guarantee.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 108
59.4 SRPC deliberations
59.5 Director (D), TANGEDCO informed that after CERC‟s Order referred in the agenda, M/s
Reliance had approached APTEL. Revised cost submitted by the M/s Reliance is around
2.5 to 3 times the original cost. APTEL had advised Reliance to approach all the LTTCs for
seeking consent for Reliance to carry out the works at enhanced cost. Reliance had
convened a meeting but none of the LTTCs had attended and now they have taken up the
issue through letters. Next hearing in APTEL was scheduled in 1st week of April 2017.
59.6 Director (T&SO), KSEBL suggested for Joint Study to assess requirement of Talcher II
augmentation system in the present scenario.
60 GRID OPERATION
Salient Achievements
11.4 BUs Wind energy was evacuated in Tamil Nadu in 2016 with considerable
efforts of TANGEDCO, TANTRANSCO & SRLDC.
Efforts of TANTRANSCO, TANGEDCO, NTECL, PGCIL, SRLDC & SR
constituents during Vardha cyclone and system revival.
Workshop on AGC followed by feedback / suggestion session on Ancillary Services
Implementation was conducted by NLDC on 03.10.2016.
Workshop on PoC was conducted by SRPC and SRLDC on 14.12.2016 for better
understanding of PoC concepts, need for data validation, demand forecast, internal
generation, net load, truncation etc.
AP crossed 3,000 MW of combined wind and solar installed capacity as on
30.11.2016 and the deviation limit was increased to 250 MW from 200 MW w.e.f.
01.12.2016.
Telangana crossed 1,000 MW of combined wind and solar installed capacity as on
31.12.2016 and the deviation limit was increased to 200 MW from 150 MW w.e.f.
01.01.2017.
Efforts of TSGENCO, TSSLDC and SRLDC for successfully completing the MVAR
testing at Nagarjunasagar on 17.09.2016.
Workshop was conducted by SRLDC at MAPS for NPCIL stations on grid aspects on
23.01.2017.
POSOCO was created as an separate entity with effect from 03.01.2017.
BSRP workshop for TN was completed on19.12.2016 by SRLDC
Reactive power document of SR 2016 released on 30.12.2016 by SRLDC
Black start restoration procedure of SR 2017 released on 30.12.2016 by SRLDC
60.1 Grid Events/ Highlights during August 2016
Andhra Pradesh met a demand of 8270 MW on 23.08.2016 which was maximum till date
Telangana met a demand of 8405 MW on 12.08.2016 which was maximum till date
Southern Region witnessed highest ever wind power generation in August 2016 (153.9 MU
on 16.08.2016).
Andhra Pradesh wind generation met a maximum of 24.08 MU on 03.08.2016.
Karnataka wind generation met a maximum of 39.72 MU on 03.08.2016.
Tamil Nadu wind generation met a maximum of 4906 MW on 29.08.2016 at 16:00 hours.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 109
Tamil Nadu wind generation met a maximum of 97.35 MU on 16.08.2016.
Tamil Nadu solar met a maximum of 863 MW on 28.08.2016 at 12:00 hours.
Tamil Nadu solar generation met a maximum of 5.647 MU on 11.08.2016.
KKNPP Unit II of NPCIL was synchronized to Grid on 29.08.2016.
Bidadi-Tumkur (TBCB) line was connected to Bidadi and Nelamangala (by opening of
Bidadi - Nelamangala line) as temporary rearrangement and made operational (trial
operation completed on 24.08.2016).
Kudgi ICT II was charged on 06.09.2016 by NTPC.
Unit II of HNPCL in Andhra Pradesh, of installed capacity 520 MW was declared COD
from 00:00 hours of 03.07.2016.
2nd Circuit stringing on 220 kV Garividi – Tekkali feeder in Srikakulam Dist of 92 ckm was
commissioned on 12.08.2016 by APTRANSCO.
230/132kV, 100 MVA capacity transformer at 220 kV SS at Kosagi was commissioned on
22.08.2016 by TSTRANSCO.
SR II, Power grid vide letter dated 31.08.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under Transmission System
associated with “System strengthening – XX Southern Region Grid” have been put under
Commercial Operation w.e.f 00:00 hrs of 31st August 2016 in terms of Clause 4 of CERC
(Terms and Conditions of Tariff Regulations 2014):
1 x 125 MVA, 400/220/33 kV ICT at Somanahalli Substation along with associated
bays and equipments.
CEA vide letter dated 9th
September 2016 had enclosed MoP letter dated 7th
September
2016. MoP has withdrawn 50 MW unallocated power of Andhra Pradesh from KKNPP
first Unit and the power is added to the Southern Regional pool of unallocated power for
utilization by the states /UTs. The revised allocation (Firm + Unallocated) in percentage
from Central Generating Stations (CGS) of SR to the beneficiaries were implemented from
00:00 hrs of 14th
September 2016 till further orders.
60.2 Grid Events/Highlights during September 2016
TSTRANSCO met a demand of 8444 MW on 09.09.2016 which was maximum till date .
TSTRANSCO had a Maximum wind generation of 87 MW & 1.36 MU on 18.09.2016
which is till date maximum.
TSTRANSCO had a Maximum Solar generation of 483 MW on 29.09.2016 which is till
date maximum.
TSTRANSCO had a Maximum wind generation of 3.37 MU on 08.09.2016 which is till
date maximum.
220/33 kV SS at Singotam in Mehaboobnagar Dist of capacity of 31.5 MVA was
commissioned on 02.09.2016 by TSTRANSCO.
220/132 kV SS at Nagole in R.R. Dist of capacity of 100 MVA was commissioned on
25.09.2016 by TSTRANSCO.
220/132 kV features at 132 Sitapuram Sub Station in Nalgonda Dist capacity of 160 MVA
was commissioned on 19.09.2016 by TSTRANSCO.
220 kV LILO from 220 kV Wanaparthy-Regimanugadda line to proposed 220/132 kV SS
Singotam in Mehaboobnagar Dist of 10.4 ckm was commissioned on 02.09.2016 by
TSTRANSCO
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 110
220 kV D/C line from Puluchintala Hydro Electric station switchyard to Sitapuram
switching station in Nalgonda Dist of 15.74 ckm was commissioned on 19.09.2016 by
TSTRANSCO.
220 kV line from Ghanapur to Nagole SS in R.R. Dist of 40.38 ckm was commissioned on
25.09.2016 by TSTRANSCO.
400 kV Kamuthi – Karaikudi line was commissioned on 08.09.2016 at 15:58 hrs by
TANTRANSCO.
GMR Vemagiri Bus Reactor in AP was commissioned on 11.09.2016 at 16:38 hrs.
GT II at SGPL was commissioned on 16.09.2016 at 17:25 hrs by SGPL.
Kamuthi ICT IV was commissioned on 19.09.2016 at 18:23 hrs by TANTRANSCO.
125 MVA Bus Reactor II at NTPC Kudgi was commissioned on 21.09.2016 at 17:01 hrs
by NTPC.
400 kV Salem – Dharmapuri- 1 was commissioned on 21.09.2016 at 16:35 hrs.
400 kV Salem – Dharmapuri- 2 was commissioned on 21.09.2016 at 18:10 hrs.
400 kV Kudgi – Tumkur – 1 &2 Trial operation completed on 23.09.2016.
SR II, Power grid vide letter dated 23.09.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under Transmission System
associated with “System strengthening – XX Southern Region Grid” have been put under
Commercial Operation w.e.f 00:00 hrs of 23rd
September 2016 in terms of Clause 4 of
CERC (Terms and Conditions of Tariff Regulations 2014):
1 x 500 MVA, 400/220/33 kV ICT at Mysore Substation along with associated bays
and equipments.
60.3 Grid Events/Highlights during October 2016
1.5 MW of windmill capacity (Private sector) was added in Tamil Nadu during October
2016.
220 kV SS Nellore in SPSR Nellore Dist of 2 x 160 + 1 x 100 existing MVA was
commissioned on 02.10.2016 by APTRANSCO with augmented capacity of 3 x 160
220 kV SS Chittoor in Chittoor Dist of 3 x 100 existing MVA was commissioned on
05.10.2016 by APTRANSCO with augmented capacity of 2 x 100 + 1 x 160 MVA.
220 kV D/C 42 Ckm LILO line from Miryalagudda – Kammam ckt-I @ the proposed
400/220/132 Suryapet SS in Nalgonda Dist was commissioned on 07.10.2016 by
TSTRANSCO.
220 kV D/C 48 Ckm LILO line from Miryalagudda – Kammam ckt-II @ the proposed
400/220/132 Suryapet SS in Nalgonda Dist of was commissioned on 07.10.2016 by
TSTRANSCO.
400 kV Nagapattinam-Dharmapuri -1 was commissioned on 21.10.2016 at 21:57 hrs.
400 kV Nagapattinam-Dharmapuri -2 was commissioned on 21.10.2016 at 21:05 hrs.
400 kV Coastal-Tuticorin Pooling Station-1 was commissioned on 29.10.2016 at 21:32
hrs by CEPL.
400kV Coastal-Tuticorin Pooling Station 2 was commissioned on 27.10.2016 at 16:57
hrs by CEPL.
SR II, Power grid vide letter dated 24.09.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Sub Station
Extension works associated with transmission required for evacuation of power from
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 111
Kudgi TPS (3 X 800MW in phase-I) of NTPC Limited” have been put under
Commercial Operation w.e.f 00:00 hrs of 24th
September 2016 in terms of Clause 4 of
CERC (Terms and Conditions of Tariff Regulations 2014).
2 Nos 400kV Line bays at Narendra (New), 2 Nos 400 kV Line bays at
Madhugiri (Tumkur), 2 x 63 MVAR (fixed) line reactors (with 600 ohm
NGRs) at Narendra (New) & 2 x 63MVAR (fixed) line reactors (with 600 ohm
NGRs) at Madhugiri (Tumkur) for Narendra (New) – Madhugiri (Tumkur) 765
kV D/c line (initially charged at 400kV).
Declaration of Commercial Operation date of Nagapattinam Pooling Section-Salem
765 kV D/C line under “Transmission system associated with IPPs of
Nagapattinam/Cuddalore Area-Package-A”
Power grid NM Transmission LTD vide letter dated 23.10.2016 had informed that on
successful completion of twenty four (24) hours of connection with the interconnection
facilities the following element is put under commercial operation w.e.f. 00:00 hours of
23rd
October 2016 and accordingly POWERGRID NM Transmission Limited (Formerly
Nagattinam Madhugiri Transmission Company Limited) is entitled for all benefits
envisaged in the aforesaid TSA.
Nagapattinam Pooling Station-Salem 765 kV D/C line (initially charged at 400
kV).
Salem-Madhugiri 765kV S/C transmission line of the project is under construction
and the COD shall be declared separately.
SR II, Power grid vide letter dated 23.10.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Transmission
system associated with Coastal Energen Private Limited & Ind-Bharat Power (Madras)
Limited LTOA Generation Projects in Tuticorin Area – Part-B” have been put under
Commercial Operation w.e.f 00:00 hrs of 23rd
October 2016 in terms of Clause 4 of
CERC (Terms and Conditions of Tariff Regulations 2014).
400 kV Salem Pooling station (Dharmapuri) – Salem 400kV D/C line along with
new 765 kV/400kV Pooling Station at Salem (Dharmapuri) (initially charged at
400 kV) and Bay Extensions at Salem 400/220 kV existing Substation.
SR II, Power grid vide letter dated 23.10.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Common
Transmission Scheme associated with ISGS Projects in Nagapattinam/Cuddalore area
of Tamil Nadu Part-A1(b)” in Southern region have been put under commercial
operation w.e.f 00:00 hrs of 23rd
October 2016 in terms of Clause 4 of CERC (Terms
and Conditions of Tariff Regulations 2014).
2 Nos 400kV bays each at Nagapattinam pooling station and Salem New
(Dharmapuri) for terminating Nagapattinam Pooling Station-Salem New
(Dharmapuri) 765 kV D/C Line (Initially charged at 400 kV) being
implemented under tariff based bidding and 1no. 63 MVAR line reactor at
Nagapattinam Pooling Station and Salem New (Dharmapuri) each for both
circuits of Nagapattinam Pooling Station – Salem New (Dharmapuri) 765kV
D/C Line (Initially charged at 400kV).
SR II, Power grid vide letter dated 13.11.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Transmission
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 112
system associated with Coastal Energen Private Limited & Ind-Bharat Power (Madras)
Limited LTOA Generation Projects in Tuticorin Area – Part-B” have been put under
Commercial Operation w.e.f 00:00 hrs of 13th
November 2016 in terms of Clause 4 of
CERC (Terms and Conditions of Tariff Regulations 2014).
Tuticorin Pooling station – Salem Pooling station 765 kV D/C line (initially
charged at 400kV) along with bay extensions at Salem Pooling Station and
Tuticorin pooling station and 80 MVAR Line Reactors at each end of both
circuits of Tuticorin Pooling station – Salem Pooling Station 765kV D/C line
(Initially charged at 400kV).
60.4 Grid Events/Highlights during November 2016
6.5 MW of windmill capacity (Private sector) was added in Tamil Nadu during
November 2016.
220 kV DC/SC line from Shapuram to Subbarayanpalli in Ananthapur Dist of 9.85 ckm
was commissioned on 04.11.2016 by APTRANSCO.
220 kV DC/SC line from Boksampalli to Shapuram Switching Station in Ananthapur
Dist of 7.32 ckm was commissioned on 04.11.2016 by APTRANSCO
220/132/33 kV Boksampalli SS in Ananthapur Dist with 163 MVA capacity was
commissioned on 04.11.2016 by APTRANSCO.
220/33 kV Subbarayunpallin SS in Ananthapur Dist with 100 MVA capacity was
commissioned on 05.11.2016 by APTRANSCO
220 kV SS Parchur in Prakasam Dist of Existing 2 x 100 MVA was commissioned on
05.11.2016 by APTRANSCO with augmented capacity of 3 x 100 MVA.
220 kV SS Gunadala in Guntur Dist of Existing 3 x 100 MVA was commissioned on
11.11.2016 by APTRANSCO with augmented capacity of 2 x 100 + 1 x 160 MVA.
220 kV Line NTPC-IV feeder to Malayalapally 220 kV SS (Ramagundam) circuit -1
with one Ckm was commissioned on 23.11.2016 by TSTRANSCO.
220/132/33 kV Miyapur SS in Hyderabad Dist was commissioned on 11.11.2016 by
TSTRANSCO with augmented capacity of 160 MVA.
400 kV Urvukonda-Veltoor-2 was commissioned on 18.11.2016 at 14:32 hrs by
TSTRANSCO.
Additional capacity of 100 MVA 3rd
Auto Transformer was commissioned at 230/110
kV Cuddalore SS by TANTRANSCO on 19.11.2016.
SR II, Power grid vide letter dated 18.12.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “System
strengthening in Southern region - XXIII” have been put under Commercial Operation
w.e.f 00:00 hrs of 18th
December 2016 in terms of Clause 4 of CERC (Terms and
Conditions of Tariff Regulations 2014).
1 x 125 MVAR 400 kV Bus reactor along with associated bay and equipments
at Hassan 400/220 kV Sub station
60.5 Grid Events/Highlights during December 2016
Wind Mills of 2 MW capacity (Private sector) was added in Tamil Nadu during
December 2016.
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 113
Wind Mills of 42 MW & 40 MW Capacity was added in Andhra Pradesh during
November 2016 & December 2016 respectively.
Solar Capacity of 10.20 MW was added in Andhra Pradesh during November 2016
Wind Mills of 38 MW Wind Capacity were added in Karnataka during December 2016
Solar capacity of 52 MW was added in Karnataka during December 2016
220 kV UG Cable from Ghanapur – Malkaram DC line to Moulali Substation in
Rangareddy Dist of 17.694 ckm was commissioned on 01.12.2016 by TSTRANSCO.
220 kV D/C line from 220/132 kV Durshed SS to 220/132 kV Sircilla SS of 134 ckm
was commissioned on 15.12.2016 by TSTRANSCO
220 kV LILO line from Chillakallu – Narketpally to 400kV Suryapet S/S in Nalgonda
Dist of 24 ckm was commissioned on 21.12.2016 by TSTRANSCO.
100 MVA, 220/132 kV ICT at Sircilla SS (1 No.100MVA PTR charged in Sircilla Dist)
was commissioned on 15.12.2016 by TSTRANSCO.
2nd Ckt stringing on existing 220 kV RSS – Nirmal DC/SC line in Adilabad Dist of 140
ckm was commissioned on 30.12.2016 by TSTRANSCO
125 MVAR Bus reactors at Kudgi II, Uravakonda, & Trivandrum was commissioned
during December 2016.
LILO of 400kV Vijayawada-Gazuwaka at Vemagiri was commissioned on 29.12.2016
at 20:55 Hrs by APTRANSCO
Kamuthi ICT V was commissioned on 30.12.2016 at 17:14 Hrs by TANTRANSCO
Ramagundam ICT II which was under prolonged outage since 30.06.2016 was
commissioned on 30.12.2016 at 17:24 Hrs by TSTRANSCO.
SR II, Power grid vide letter dated 23.12.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Transmission
System associated with Kudankulam Atomic Power Project (2x1000MW) in Southern
Region” have been put under Commercial Operation w.e.f 00:00 hrs of 23rd
December
2016 in terms of Clause 4 of CERC (Terms and Conditions of Tariff Regulations 2014):
Bunching of Tirunelveli – Edamon section of the Tirunelveli – Muvathapuza
(Cochin) 400 kV quad D/c line initially (and temporarily) at 220 kV with
existing Tirunelvelli – Edamon 400 kV twin D/c line (400 kV line charged at
220kV).
Transmission charges for the above assets are payable with effect from 23rd
December 2016
SR II, Power grid vide letter dated 30.12.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “System
strengthening in Southern region - XXIII” have been put under Commercial Operation
w.e.f 00:00 hrs of 30th
December 2016 in terms of Clause 4 of CERC (Terms and
Conditions of Tariff Regulations 2014):
1 x125 MVAR 400 kV Bus reactor along with associated bay and equipments at
Narendra (New, Kudgi) Substation.
Transmission charges for the above assets are payable with effect from 30th
December 2016
SR II, Power grid vide letter dated 31.12.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “System
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 114
strengthening in Southern region - XXIII” have been put under Commercial Operation
w.e.f 00:00 hrs of 31st
December 2016 in terms of Clause 4 of CERC (Terms and
Conditions of Tariff Regulations 2014).
400/220 kV,1 x 500 MVA transformer along with associated bay and equipments
at Madurai Substation
Transmission charges for the above assets are payable with effect from 31st
December 2016
SR II, Power grid vide letter dated 25.01.2017 had informed that consequent to the
successful completion of Trial Operation, the following asset under “System
strengthening in Southern region - XXIII” have been put under Commercial Operation
w.e.f 00:00 hrs of 25th
January 2017 in terms of Clause 4 of CERC (Terms and
Conditions of Tariff Regulations 2014).
Replacement of 1 x 50 MVAR bus reactor with 1 x 125 MVAR bus reactor at
400/220 kV Narendra Substation. (The replaced bus reactor shall be maintained
as a regional spare)
Transmission charges for the above assets are payable with effect from 25th
January 2017
60.6 Grid Events/Highlights during January 2017
Wind Mills of 48 MW was added in Andhra Pradesh during December 2016
Wind Mills of 16.8 MW was added in Andhra Pradesh during January 2017.
220 kV D/C line from 400 kV Uravakonda SS to 220 kV Borampalli SS in Ananthapur
district of 134 ckm was commissioned on 07.01.2017 by APTRANSCO.
220 kV SS at Borampalli in Ananthapur district of 100 MVA capacity was
commissioned on 06.01.2017 by APTRANSCO.
220 kV XLPE UG Cable from Chandrayanagutta SS to Imliban GIS Substation in
Hyderabad district of 9.5 ckm was commissioned on 23.01.2017 by TSTRANSCO.
220/132 kV Imliban GIS SS (PTR – II) in Hyderabad District of 160 MVA capacity
was commissioned on 31.01.2017 by TSTRANSCO.
220 kV Vemunuru LIS in Karimnagar Dist of 1 x 50 MVA existing Capacity was
augmented to a capacity of 2 x 50 MVA and was commissioned on 07.01.2017 by
TSTRANSCO.
400 kV S/C Line from Tirunelvelli 400kV SS (Abishekapatty- PGCIL) to Kanarpatty
400 kV SS was commissioned on 09.01.2017 by TANTRANSCO
400/230 kV Kanarpatty SS of 2 x 500 MVA capacity (1000 MVA) was commissioned
on 09.01.2017 at 18:05 hrs by TANTRANSCO
400/110 kV Kanarpatty SS 3 x 200 MVA capacity (600 MVA) was commissioned on at
18:05 hrs 09.01.2017 by TANTRANSCO
4th Autotransformer of 100 MVA capacity at 230/110 kV Palladam was commissioned
on 09.01.2017 by TANTRANSCO
2nd Auto transformer of 80 MVA capacity at 230 /110 kV Nallamanaickenpartty SS was
commissioned on 11.01.2017 by TANTRANSCO
4th Auto transformer of 100 MVA capacity at 230/110 kV at Thiruvalam SS was
commissioned on 23.01.2017 by TANTRANSCO
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 115
2nd Auto transformer of 100 MVA capacity at 230/110 kV Aliyar SS was commissioned
on 27.01.2017 by TANTRANSCO
SGPL vide letter dated 20.02.2017 had informed that Trial run of 72 hours full load
operation of Unit II of 660 MW of SGPL had completed and the unit is declared COD
on 21st February 2017.
Capacity building workshop for NPCIL Stations was conducted at MAPS on
23.01.2017.
S3 Bid area was operationalized w.e.f 24.01.2017.
125 MVAR B/R at Trivandrum was commissioned on 24.01.2017 at 16:35 hrs by
PGCIL.
400 kV K V Kota - Suryapet-I (was commissioned on 25.01.2017 at 12:54 hrs by
TSTRANSCO
400 kV K V Kota - Suryapet-II was commissioned on 25.01.2017 at 16:58 hrs by
TSTRANSCO.
SR I, Power grid vide letter dated 31.01.2017 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Substation works
associated with system strengthening in Southern Region for import of power from
Eastern Region” shall be put under Commercial Operation wef 00:00 hrs of 01.02.2017
in terms of clause 4 of CERC (Terms and Conditions of Tariff) Regulations, 2014:
LILO of Gazuwaka-Vijayawada 400 kV S/c line at Vemagiri Pooling Station
along with associated bays.
765/400 kV GIS Pooling Station at Vemagiri with 1 x 1500 MVA 765/400 kV
Transformer.
2 nos. 765 kV bays each at Vemagiri Pooling Station and Srikakulam Pooling
Station
2 nos. 240 MVAR 765 kV Bus Reactor at Vemagiri Pooling Station
1 no. 80 MVAR 400 kV Bus Reactor at Vemagiri Pooling Station
1 no. 240 MVAR switchable line Reactor each at Vemagiri and Srikakulam
Pooling Stations each for both circuits of Srikakulam PS-Vemagiri PS 765 kV
D/c line.
Transmission charges of the above assets are payable wef 01.02.2017.
Powergrid SR I vide letter dated 31.01.2017 had informed the following
Consequent to successful completion of Trial Operation, the following assets
under “Common System associated with East Coast Energy Pvt Limited &
NCC power projects LTOA generation projects in Srikakulam area Part A &
Part C” shall be put under Commercial Operation wef 00:00 hrs of 01.02.2017
in terms of clause 4 of CERC (Terms and Conditions of Tariff) Regulations,
2014.
765/400 kV Sub Station at Srikakulam
765 kV Bay extensions at Angul and Srikakulam Substations along with 2 x 240
MVAR switchable line reactors each at Angul S/S and Srikakulam S/S
1 x 330 MVAR 765 kV Bus Reactor at Srikakulam Sub Station
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 116
60.7 Installation of Shunt Capacitors
Progress of installation of capacitors by the constituents during the year
2016-17 is furnished in the Table below:
(Figures in MVAR)
State Requirement
for 2016-17
Installed during the year
2016-17
Andhra Pradesh 549 147.6
Telangana 535.8 0
Karnataka 56.31 0
Kerala 10.00 0
Tamil Nadu 120 19.2
Puducherry 45.8 0
60.8 Demand Variation (Peak Vs Off-peak)
Issue regarding large variation between minimum and maximum demands has been under
the consideration of TCC/SRPC. Issue is also being discussed in the monthly Meetings of
OCC. Following was observed with regard to the period from August 2016 to January
2017:
Descript
ion
Minimum to Maximum Demand Variation %
Andhra
Pradesh Telangana Karnataka Kerala
Tamil
Nadu Puducherry
Southern
Region
August 2016 Highest 30.66 36.70 36.53 41.42 29.90 56.07 27.66
Date (Day) 31.08.2016
(Wednesday)
02.08.2016
(Tuesday)
02.08.2016
(Tuesday)
08.08.2016
(Monday)
01.08.2016
(Monday)
13.08.2016
(Saturday)
03.08.2016
(Wednesday)
Lowest 13.33 17.39 16.21 31.67 11.31 22.81 7.50
Date (Day) 30.08.2016
(Tuesday)
20.08.2016
(Saturday)
19.08.2016
(Friday)
14.08.2016
(Sunday)
07.08.2016
(Sunday)
28.08.2016
(Sunday)
21.08.2016
(Sunday)
Average 20.55 24.14 24.54 37.26 20.11 31.08 14.87
September 2016 Highest 21.01 38.83 27.73 44.05 29.30 54.79 24.39
Date (Day) 08.09.2016
(Thursday)
18.09.2016
(Sunday)
26.09.2016
(Monday)
03.09.2016
(Saturday)
12.09.2016
(Monday)
28.09.2016
(Wednesday)
26.09.2016
(Monday)
Lowest 11.16 18.33 15.32 30.59 12.14 22.52 9.26
Date (Day) 25.09.2016
(Sunday)
02.09.2016
(Friday)
18.09.2016
(Sunday)
14.09.2016
(Wednesday)
11.09.2016
(Sunday)
25.09.2016
(Sunday)
11.09.2016
(Sunday)
Average 14.96 27.65 20.59 37.76 22.26 31.30 17.66
October 2016 Highest 23.05 34.98 27.24 43.39 31.63 61.66 23.80
Date (Day) 31.10.2016
(Monday)
07.10.2016
(Friday)
12.10.2016
(Wednesday)
31.10.2016
(Monday)
31.10.2016
(Monday)
13.10.2016
(Thursday)
03.10.2016
(Monday)
Lowest 10.50 21.80 9.45 29.49 11.28 16.70 7.43
Date (Day) 11.10.2016
(Tuesday)
11.10.2016
(Tuesday)
27.10.2016
(Thursday)
30.10.2016
(Sunday)
29.10.2016
(Saturday)
15.10.2016
(Saturday)
09.10.2016
(Sunday)
Average 14.94 28.78 18.20 36.58 20.08 29.33 15.85
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 117
November 2016 Highest 24.35 40.19 22.33 43.18 30.53 69.69 25.25
Date (Day) 28.11.2016
(Monday)
28.11.2016
(Monday)
28.11.2016
(Monday)
15.11.2016
(Tuesday)
21.11.2016
(Monday)
25.11.2016
(Friday)
28.11.2016
(Monday)
Lowest 11.26 29.58 7.69 31.05 10.34 24.20 10.06
Date (Day) 02.11.2016
(Wednesday)
17.11.2016(
Thursday)
04.11.2016
(Friday)
27.11.2016
(Sunday)
13.11.2016
(Sunday)
13.11.2016
(Sunday)
13.11.2016
(Sunday)
Average 18.45 34.07 16.98 37.33 21.60 32.68 17.63
December 2016 Highest 32.28 41.93 33.58 43.74 44.89 48.99 30.64
Date
(Day)
26.12.2016
(Thursday)
22.12.2016
(Sunday)
12.12.2016
(Thursday)
14.12.2016
(Saturday)
12.12.2016
(Thursday)
12.12.2016
(Thursday)
13.12.2016
(Friday)
Lowest 16.43 32.92 15.35 28.69 16.72 26.59 15.04
Date
(Day)
04.12.2016
(Wednesday)
04.12.2016
(Wednesday)
04.12.2016
(Wednesday)
25.12.2016
(Wednesday)
25.12.2016
(Wednesday)
18.12.2016
(Wednesday)
04.12.2016
(Wednesday)
Average 25.08 37.55 22.13 37.91 25.69 37.27 23.35
January 2017 Highest 35.76 44.49 29.39 41.88 32.26 47.14 29.43
Date
(Day)
20.01.2017
(Friday)
01.01.2017
(Sunday)
27.01.2017
(Friday)
02.01.2017
(Monday)
17.01.2017
(Tuesday)
17.01.2017
(Tuesday)
27.01.2017
(Friday)
Lowest 21.75 31.70 14.82 32.37 19.53 20.57 15.31
Date
(Day)
15.01.2017
(Sunday)
29.01.2017
(Sunday)
11.01.2017
(Wednesday)
08.01.2017
(Sunday)
26.01.2017
(Thursday)
01.01.2017
(Sunday)
27.01.2017
(Friday)
Note: Highest &lowest figures for the month have been computed based on the daily values.
60.9 Frequency of Operation of Southern Grid
Frequency of operation of the Southern Grid for the period under review is furnished below
please:
Month
Percentage of time when frequency (Hz) was Month
Avg.
freq.
Less
than
49.5
49.5
to
49.7
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
Aug 2016 0.00 0.02 6.69 42.41 30.28 20.54 0.06 72.69 50.00
Sep 2016 0.00 0.00 6.74 44.33 30.33 18.58 0.02 74.66 50.00
Oct 2016 0.00 0.00 7.31 46.85 28.58 17.21 0.05 75.43 50.00
Nov 2016 0.00 0.08 10.90 46.76 25.78 16.43 0.05 72.54 49.99
Dec 2016 0.00 0.00 13.24 45.12 24.10 17.44 0.10 69.22 49.99
Jan 2017 0.00 0.00 7.54 43.44 27.73 21.02 0.27 71.17 50.00
During the period under review, caution / violation messages (Annexure- LVII) were
issued to the constituents by SRLDC. Matter regarding overdrawal at low frequency by
some constituents is being regularly deliberated in the OCC forum. Utilities were
requested to kindly adhere to Regulations in this regard.
Issue of caution/violation messages in line with IEGC/Operating Procedure was taken up
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 118
by SRPC Secretariat with SRLDC vide letters dated 05.10.2016 and 18.11.2016
(Annexure-LVIII)
60.10 Reasons for demand -supply gap and its variation:
60.10.1 In 4th
Meeting of NPC held on 10.12.2015 (MoM dated 1.1.2016) the following had been
noted:
Reason for demand-supply gap needed to be clearly mentioned to reflect true picture
of power supply position in different states and also to invite attention of various
agencies including policy makers to the specific problem areas in the power sector for
suitable solution. It was requested to RPCs to advise the states in their respective
regions to intimate broad break-up of demand-supply gap due to various reasons, or
at least, the main reason(s) for demand-supply gap in each month. It was suggested
that this matter could be discussed in the OCC forum of RPCs on regular basis and
the reasons for demand-supply gap ascertained from the States therein and
communicated to CEA.
RPCs agreed to take action accordingly and furnish above information to CEA along
with the power supply position related data every month.
60.10.2 In earlier Meetings, the following had been noted:
SRPC had stated that the information was being sought by MoP/CEA. Though Surplus
power was available, reasons for deficits such as transmission constraints, distribution
constraints, financial constraints etc needed to be elucidated.
CEA had stated that the data being furnished by SRPC for SR constituents was very
reliable. However during shortage conditions at times, MoP desired exact reason of
shortages like transmission constraint or some other financial reason etc. In certain
states, power was not being supplied due to financial limitations. Vidhyuth Pravaah
App showed power availability in different areas and consumers were raising several
questions in social media to MoP.
60.10.3 For the month of December 2016, the following was noted:
In SRLDC PSP report, load shedding was reported by KPTCL while in the monthly
figure, it was reported as Nil. SRPC letter dated 04.01.2017 in this regard is at
Annexure-LIX.
TANTRANSCO had reported load shedding as Nil though loads had been affected
during Vardha Cyclone. SRPC letter dated 04.01.2017 in this regard is enclosed.
(Annexure-LX).
60.10.4 SRPC noted the above.
60.11 Renewable Integration issues
The following issues were deliberated in the TCC:
PCKL stated that weather inputs were very much necessary for RE and demand
forecasting.
KPTCL informed that during this wind season (from May onwards), entire
Karnataka load could be met through wind, solar and CGS drawals. It would be
difficult to manage the LGB.
It was noted that Procedure on Technical Minimum/Compensation for CGS was
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 119
likely to be notified shortly. Similar Procedure for intra-state thermal stations may be
required to facilitate RE integration. UD/OD limits were as per the Regulations of
CERC and issues, if any, needed to be taken up appropriately.
60.12 SRPC noted the above.
61 RELIABLE COMMUNIACTION SCHEME UNDER CENTRAL SECTOR FOR
SOUTHERN REGION
61.1 PGCIL vide letter dated 14.02.2017 (Annexure-LXI) had stated that as desired by Ministry of
Power, DPR for OPGW based Reliable Communication scheme for substations of 132 KV
and above had been prepared by POWERGRID for all the regions. Further, as per directives
of MoP, State Sector Scheme was to be taken up by respective states for their portion and
Central Sector portion by POWERGRID. Accordingly, Fiber Optic connectivity along with
Communication Equipment and associated items from certain stations under Central Sector
scheme are required to be established for data and voice communication to SRLDC for
efficient grid management. OPGW Network of the total of 1,527 Kms (1,084Kms + 443Kms)
has been proposed to be implemented as a part of Reliable Communication Scheme.
Estimated cost of the scheme with OPGW, communication equipment and DCPS (as
required) is 38.17Cr. Tariff for the investment made is to be shared by all constituents in
Southern Region as per CERC notification. The scheme shall become part of existing
Commercial Agreement signed for ULDC Project.
61.2 TCC deliberations
TCC recommended the scheme for approval of SRPC and also for it to become part of
existing Commercial Agreement signed for ULDC project.
61.3 SRPC approved the recommendation of TCC.
62 OPGW LINKS ON LINES CONSIDERING LILO IN FUTURE
62.1 PGCIL vide letter dated 14.02.2017 (refer Annexure-LXI) had stated that for providing
reliable communication from LILO stations, OPGW connectivity is being established on
LILO portion along with transmission line construction. The required OPGW for upcoming
lines had been deliberated in a Meeting taken by Secretary (Power) on 24.07.15 in presence
of CEA and POWERGRID wherein it was decided that upcoming lines may be provided
with OPGW in place of one of the earth-wire. Accordingly, all upcoming lines including
LILO portion is being considered with OPGW. In order to achieve seamless connection of
LILO stations, it is essential to provide OPGW on main line also. Accordingly to ensure
seamless connection of LILO stations it has been proposed to consider OPGW on existing
lines. There are around 20 nos. existing transmission lines which are not having OPGW.
Considering the possibility of LILO of these lines in future, it has been proposed to
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 120
implement OPGW on all these lines. Total requirement of OPGW comes out to be 3,879
kms. List of the lines is as per Annexure enclosed. Estimated cost of OPGW, communication
equipment and DCPS (as required) on account of the same comes to 96.97 Cr.
62.2 TCC deliberations
TANTRANSCO had stated that they had requested for inclusion of NCTPS-Almathy line
in the above proposal. PGCIL had agreed to include the above line for OPGW stringing.
KSEBL had enquired about the OPGW stringing in the state lines. PGCIL had clarified
that the state sector OPGW stringing was to be carried out by states with 30% PSDF
funding.
TCC had recommended the proposal and the scheme for approval of SRPC.
62.3 SRPC approved the recommendation of TCC.
63 ALLOCATION OF 6 FIBRES FROM THE 18 FIBRES AVAILABLE AS SPARE
63.1 TANTRANSCO vide letter dated 14.02.2017 (Annexure-LXII) had requested SRPC for
allocation of 6 fibres from the 18 fibres available as per spare, in all F.O links established in
TN through F.O Expansion Project under ULDC scheme. This is subject to condition that
TANTRANSCO shall avail not more than the maximum fibre kms for which eligible for
alternate path provision for their existing F.O links.
63.2 TCC deliberations
TANTRANSCO had stated that PGCIL was laying 5,700 km of OPGW (of 24 fibres)
under ULDC scheme. The cost is being shared by all the constituents. TANTRANSCO
had requested 6 fibres for alternate paths of its network. This provision could be extended
to all the states on fibre km basis.
PGCIL had informed that in most of the FO, there were no spare fibres available. Six
fibres are available for grid management purposes. The balance 18 fibres in the state or
central sector are left to the entities on how to utilize. As for Central sector, 18 fibres are
being leased out to M/s Powertel as per CERC formula which covered issues like sparing
of fibres, cost sharing (50% being shared by M/s Powertel), ROW compensation
(Rs.3000/km) etc. For grid operation purpose, bandwidth on 6 fibres could be given to
the states. M/s Powertel may not take all the 18 fibres in some of the lines but those fibres
are being leased out anywhere.
Keeping in view the non availability of spare fibres in most of FO links and the approved
MoU with M/s Powertel the scheme of allocation the fibres was dropped.
63.3 SRPC noted the above.
64 FINAL LIST OF OPGW LINKS UNDER FIBRE EXPANSION PROJECT OF
SOUTHERN REGION
64.1 PGCIL vide letter dated 21.02.2017(Annexure-LXIII) had informed that the modified and
final network of 5,735.85 kM OPGW links and 2,287.59 kM of POWERGRID Telecom
network sharing along with final list of links was put up for SRPC approval.
64.2 TCC deliberations
TCC had recommended for approval of the above links
Minutes of the 31st SRPC Meeting held on 25.02.2017 Page 121
64.3 SRPC approved the recommendation of TCC.
65 OPGW STRINGING ON KPTCL LINES
65.1 PGCIL vide letter dated 21.02.2017 (refer Annexure-LXIII) had referred to the minutes of
31st WRPC/TCC Meeting held on 30
th & 31
st March 2016, where in WRPC recommended for
installation of OPGW 220 kV Xeldom-Ambewadi & 220 kV Ambewadi-Narendra KPTCL
lines as part of Master Communication Plan for OPGW network of Western Region for
extending fibre connectivity to GEDC (Goa Electricity Department) network. Copy of
extracts of WRPC Meeting is enclosed as Annexure-II.
It was proposed that KPTCL consent may be obtained by SRPC for laying OPGW on 220 kV
Xeldom-Ambewadi & 220 kV Ambewadi-Narendra KPTCL lines.
65.2 TCC deliberations
KPTCL agreed for laying on OPGW on 220 kV Xeldom-Ambewadi & 2220 kV
Ambewadi-Narendra lines by PGCIL.
65.3 SRPC noted the above.
66 REIMBURSEMENT OF SRPC EXPENDITURE
Statement showing net amount payable by Member Utilities of SRPC for the year 2016 -17,
after adjustment of surplus/deficit for the previous period is furnished in Annexure-LXIV.
Members were kindly requested to ensure payment, wherever due.
67 APPOINTMENT OF CONSULTANTS
67.1 MS, SRPC informed about the staff shortage in SRPC Secretariat and stated that approval for
appointment of Consultants would be sought from Chairperson, SRPC in line with the
procedure.
67.2 SRPC agreed for the same.
68 DATE & VENUE OF THE NEXT SRPC MEETING
UPCL kindly agreed to host the 32nd
Meeting of SRPC. Date and venue would be
communicated in due course.
69 CONCLUSION
Chairperson, SRPC stated that issues had been deliberated at length in TCC & SRPC forum.
He thanked all Members for making the Meeting successful.
*******