SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be...

36

Transcript of SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be...

Page 1: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 2: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

Record Notes of the Meeting on AP & Telangana Scheduling & Operational issues held on 18th December 2015

A Meeting on AP & Telangana Scheduling & Operational issues was held at

TSTRANSCO office at Hyderabad on 18th December 2015. List of participants is at

Annexure-I.

TSTRANSCO vide letters dated 06.08.2015 and 02.11.2015 (Annexure-II) had

requested to convene a coordination meeting between Telangana SLDC & APSLDC along

with all State generating stations to discuss scheduling issues of shared projects and

other modalities.

SE, SLDC, TSTRANSCO welcomed representatives from power utilities of Andhra

Pradesh & Telangana and SRPC & SRLDC.

SRPC & SRLDC stated that scheduling of shared projects would be in the interest

of both States. A common agreed methodology in respect of ramp up, ramp down,

technical minimum, backing down etc. would be helpful and a consensus may be arrived

at.

SRLDC presentation on the practices of scheduling of ISG Stations is at

Annexure-III.

Scheduling of shared projects

TSTRANSCO suggested that scheduling of the shared projects could be taken up

including ramp-up / ramp-down, backing down, revision of schedule etc., as is

being carried out for ISG Stations.

APTRANSCO stated that presently scheduling of shared projects could only be

done on net of schedule on day ahead basis and it was revised only during tripping

/ synchronization of units. All other provisions could be considered after

scheduling software is in place in both the SLDCs. Only around 1,000 – 1,200

MW margin is available to manage the variations in the demand and integration of

Page 3: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

renewables . In the coming years, huge renewable generation is likely to be added

to AP grid and there could be need of taking out the shared project units and

stations also. How power from such units under reserve shut down could be

shared with the other State needs to be deliberated?

The following was agreed / noted after deliberations:

Scheduling of shared projects would continue as per existing methodology of net of

schedule between AP & TS. Day to day shares would be ensured. The schedules to

other State would be revised under unit outage/synchronization.

In emergency conditions, the other State may consider modification in the

schedules of the shared projects only at the request of SE/CE of the SLDC.

During reserve shut down, the other State would continue to get deemed schedule

from the unit/stage/station. Both APSLDC & TSSLDC agreed to it operationally on

interim basis. This assumes significance since huge renewable integration is

planned in both the States. Backing down/reserve shutdown gets complex with

multiple variable charges of energy even for different stages in the same station.

Both the States would follow merit order backing down/reserve shut down. The

other State’s request of surrender of power from the reserve shut down unit could

be considered.

Since this issue has significant commercial / operational implications, the same

was recommended to flag for discussion in higher forum. However both

AP & TS would also refer and get the provisional methodology vetted through their

commercial division/management for the interim period.

It was agreed that for revision of Simhadri Stage I schedules, 6 time blocks would

be given to APSLDC by TSSLDC due to non-availability of web based scheduling

SW at APSLDC.

Revisions of schedules of IPPs in AP by TSSLDC would be considered by APSLDC.

Page 4: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

Only net of scheduling of shared projects would be continued by SRLDC. The

revision in net schedule would be carried out in the 4th time block, after receiving

the revised schedule from the respective SLDC (first time block being the request

for revision). All the previous time block’s net schedule details would be frozen by

SRLDC. In view of software limitations, the source file would not be available at

SRLDC and both States need to reconcile the revisions mutually.

It was agreed that both the SLDCs would reconcile the implemented schedule on

daily basis to avoid any ambiguity.

APSLDC & TSSLDC agreed to take immediate steps to put in place a full fledged

scheduling software (State generators, shared projects, Discoms, renewables, URS

etc.) by December 2016. A simple module of scheduling the shared projects could

be put in place by 31st March 2016 for scheduling the shared projects only. SRLDC

assured assistance, if required on technical specifications and sharing other

relevant information for the scheduling software.

TSSLDC stated that scheduling of shared projects could be carried out in line with

ISG Stations. APSLDC stated that the scheduling of shared projects in line with

ISG Stations would be put to management only after scheduling software is in

place.

The following ramp up/ramp down rates and technical minimum were noted

(Generators were requested to revert back in case of any discrepancy) as tabled

below:

APGENCO

Unit installed

capacity

Ramp up Ramp down Technical

minimum

Remarks

500 MW 30 MW/Block 30 MW/Block 330 MW

210 MW 10 MW/Block 10 MW/Block 134 MW

Page 5: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

TSGENCO

Station/Stage

Installed capacity

Ramp up Ramp down Technical minimum (Ex-bus)

Remarks

Kakatiya TPP I

500 MW

30 MW/Block 30 MW/Block 330 MW

KTPS – O & M (Units 1-8)

720 MW

45-60 MW/Block

45-60 MW/Block

450 MW Unit-wise details would be furnished separately

KTPS – V (Unit 9)

250 MW

15 MW/Block 15 MW/Block 162 MW

KTPS – V (Unit 10)

250 MW

15 MW/Block 15 MW/Block 162 MW

KTPS – Unit 11

500 MW

30 MW/Block 30 MW/Block 330 MW

RTS –B

62.5 MW

Will be informed separately

AP -IPPs

It was noted that the stations ramp up and ramp down rates were generally around

9 MW/minute (upto around 350 MW). Unit ramp up and ramp down rates were

around 2-2.5 MW/minute. Technical minimum was generally around 60% of DC.

Other operational issues

SRPC presentation on operational issues is at Annexure-IV.

LGBR for the year 2016-17

APSLDC agreed to furnish the power purchase details and LGBR at the earliest.

Page 6: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

TSSLDC stated that the requirement figures were being reworked due to changes in

agriculture supply. Tentative purchases along with LGBR would be furnished.

Pollution Mapping

APTRANSCO & TSTRANSCO agreed to follow up with the concerned.

VC facility at SLDCs

AP SLDC stated that VC facility would be taken up at Vijayawada SLDC as and when

it is ready. At present building construction is in progress.

TSSLDC informed that equipment was in place and final connectivity to be made in

coordination with M/s. Alstom & PGCI. It will be ensured shortly.

Pump mode & Condenser mode operation

Srisailam LB units: Unit V not possible in pump mode due to technical problem.

SRLDC/SRPC requested TSGENCO/TSSLDC to revert back with the details of the

problem and the action plan for revival.

Nagarjunasagar units: TS informed that the pumping capability was to be tested by

the OEM (M/s BHEL) and it was also linked with minimum water availability in the

downstream tail pond reservoir.

TSSLDC confirmed that the SCADA issues with respect to Srisailam LB and

Nagarjunasagar were resolved. On a query, it was confirmed that all the units at

Srisailam LB and Nagarjunasagar were being run on condenser mode as per SLDC

instructions.

GT tap changes

APGENCO informed that GT taps for Upper Sileru units could not be changed as they

were stuck. SRLDC/SRPC suggested APGENCO to revert back with action plan for

rectification. GMR confirmed that the taps had been changed to 400 kV. Spectrum

confirmed that the GT taps had been changed to 220 kV. Other IPPs were suggested

Page 7: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

to change the GT taps as recommended (400 kV & 220 kV levels). APSLDC assured

of follow up.

TSGENCO informed that in respect of Kothagudem units, PO for DVR had been

placed and was expected within two months. Subsequent to commissioning, they

would examine the possibility of bringing all the units GT taps to 220 kV level.

Regarding Nagarjunasagar units they would revert back.

Status of Reactor at Srisailam

TSTRANSCO informed that they had sent a reminder to CEA. SRPC/SRLDC

suggested that the issue could also be referred to the Standing Committee by

TSTRANSCO.

Reactive power management

APTRANSCO informed that Tenders had been finalized for the 32 x 7.5 MVAR and 4

x 14.4 MVA capacitors at 33 kV level.

TSNPDCL informed that 81 x 1 MVAR and 80 x 2 MVAR capacitor banks had been

commissioned at 11 kV level of 33/11 kV SS. Orders for 248 x 2 MVAR capacitor

banks had been placed and which were planned to be commissioned before March

2016.

SRPC informed that the issue was being followed up in the NPC and requested all to

furnish timely details.

Status of implementation of protection audit recommendations

SRPC / SRLDC emphasized that the time line allowed by Hon’ble CERC is getting

over by Dec’15 for phase – I & Phase – II activities but many items are yet to be

completed.

AP & TS utilities noted the dates for completion of Phase-I and Phase-II activities.

They stated that they would approach Hon’ble Commission.

Page 8: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

RGMO/FGMO

APGENCO informed that Krishnapatnam unit II was under shut down and it would

come back with RGMO in place.

APSLDC confirmed that Hinduja TPP Unit-I was equipped with RGMO and the

details would be furnished to SRLDC/SRPC.

TSSLDC confirmed that the RGMO status points for thermal units were available at

SLDC. Details in regard of Hydro units would be furnished.

SRLDC requested that the consolidated table of RGMO status could be made

available to SRLDC through ICCP.

SCADA mapping of AUFR & df/dt feeders

APSLDC informed that 135 RTUs were required with an estimated cost of around

Rs.250 Crores. ( with systems etc) 20 RTUs were being purchased presently.

TSSLDC informed that 35 RTUs were required. 75% of mapping was over.

SRLDC/SRPC stated that as per Hon’ble CERC Order on KSEBL petition (dated

27.11.2015 on Petition No. 60/MP/2014) all the SR States were to complete 100%

mapping. Status was to be furnished to the Commission by 31st January 2016 by

SRPC/SRLDC and therefore the status/schedule for achieving 100% SCADA mapping

needs to be furnished by 31st December 2015. SRLDC would verify it with SCADA in

first week of January 2016 and consolidated report would be furnished.

ADMS

APSLDC informed that the revised logic had been implemented. Presently, 150 MW

of feeders had been put under the Scheme and they were planning to add additional

feeders.

TSSLDC informed that remote tripping of the feeders had been tested and they were

taking up with M/s. Alstom for making the Scheme operational. On a query, TSSLDC

Page 9: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

informed that they had identified 500-600 MW of radial loads for this Scheme which

would be shed as per O/D in a cyclic manner.

LVRT

APSLDC informed that they are taking affidavits/certificates from the wind

generators in respect to implementation of LVRT.

SRLDC/SRPC suggested taking up with their SERCs for bringing out of specific

guidelines to enable the wind/Solar developers for mandatory implementation of

LVRT and enabling SLDCs for ensuring compliance.

On a query about LVRT / HVRT feature for Solar Generators, SRLDC clarified that

the Solar Generators also should ensure for implementation of LVRT / HVRT feature

as noted during the hearing of petition no. 420 / MP / 2014.

PSS tuning of generators

APGENCO informed that Order has been placed for PSS Tuning of Rayalaseema TPP

units and would be completed by August 2016. In respect of VTPS, PSS Tuning of

Units 3 and 4 had been completed by M/s BHEL and the reports had been furnished .

For Unit 5 and 6 replacement with DAVR along with PSS tuning would be completed

by August 2016. For Units 1, 2 and 7 PSS tuning was planned. SRT reports for

Krishnapatnam units would be furnished in the specified format.

TSGENCO: Nagarjunasagar units SRT reports would be furnished.

SRPC/SRLDC stated that Test Reports/graphs were to be furnished in legible specific

formats (in soft copy) clearly indicating the parameters and scales. SRT report and

PSS tuning details for Hinduja unit to be furnished. It was pointed out that all the

units above 50 MW(including IPPs) were required to carry out PSS tuning and SLDC

needed to ensure compliance. Schedule agreed in the 30th October 2015 meeting was

to be followed.

Upcoming generating stations

Page 10: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective

Special Meeting on AP & Telangana scheduling and operational issues on 18.12.2015

TSGENCO informed that Kakatiya Stage-II unit was likely to come up within 10-15

days. Singareni Unit-1 and 2 were planned to be synchronized by December 2015 and

January 2016 respectively.

APSLDC informed that Hinduja unit-1 was test synchronized.

Implementation of additional loads for SPS by TS

SRPC/SRLDC informed that the DTPCs had been installed by PGCIL at Veltoor,

Gajwel, Budidampadu and RSS. TSTRANSCO was requested to complete their scope

of work and necessary instructions could be passed on to the respective sub-stations.

TSTRANSCO assured of necessary action in this regard.

************************************

Page 11: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 12: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 13: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 14: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 15: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 16: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 17: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 18: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 19: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 20: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 21: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 22: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 23: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 24: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 25: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 26: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 27: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 28: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 29: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 30: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 31: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 32: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 33: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 34: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 35: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective
Page 36: SOUTHERN REGIONAL POWER COMMITTEE - KarnatakaDec 18, 2015  · revision in net schedule would be carried out in the 4th time block, after receiving the revised schedule from the respective