SOUTHERN REGIONAL LOAD DESPATCH CENTER POSOCO,POWERGRID, BANGALORE
-
Upload
leila-marsh -
Category
Documents
-
view
34 -
download
1
description
Transcript of SOUTHERN REGIONAL LOAD DESPATCH CENTER POSOCO,POWERGRID, BANGALORE
SOUTHERN REGIONAL LOAD DESPATCH CENTERPOSOCO,POWERGRID, BANGALORE
UI regulations,ATC,
congestion regulations
and experiences in SRBy
P.Bhaskara Rao, Addl G M, Shamreena Verghese , Mgr
16 May 2011
Overview• Ui_regulations• Transfer Capability• Relevance of transfer capability in Indian
electricity market• Reliability Margin• Difference between transfer capability and
Transmission Capacity• Assessment of Transfer capability• Ratio of transfer capability to transmission
capacity• Congestion regulations• overview of constraints and hotspots in SR
Transfer Capability - Definition
North American Electricity Reliability Corporation’s definition of TTC(Total Transfer
Capability )• “TTC is the amount of electric power that can
be transferred over the interconnected transmission network in a reliable manner based on all of the following conditions– all facility loadings in pre-contingency are within
normal ratings and all voltages are within normal limits
– systems stable and capable of absorbing the dynamic power swings
– before any post-contingency operator-initiated system adjustments are implemented, all transmission facility loadings are within emergency ratings and all voltages are within emergency limits”
06th Oct 2009 4NRLDC, POWERGRID
06th Oct 2009 NRLDC, POWERGRID 5
European Network of Transmission System Operators’ definition of Total Transfer Capability
(TTC)• “TTC is that maximum exchange programme
between two areas compatible with operational security standards’ applicable at each system if future network conditions, generation and load patterns were perfectly known in advance.”
• “TTC value may vary (i.e. increase or decrease) when approaching the time of programme execution as a result of a more accurate knowledge of generating unit schedules, load pattern, network topology and tie-line availability”
Transfer Capability as defined in the Indian Electricity Grid Code (IEGC)
‘Transfer Capability’ of a transmission network is the ability to transfer electric power when operated as part of the interconnected power system and may be limited by the physical and electrical characteristics of the system considering security aspects of the grid.
Total Transfer Capability as defined in the Congestion charge regulations
• “Total Transfer Capability (TTC)” means the amount of electric power that can be transferred reliably over the inter-control area transmission system under a given set of operating conditions considering the effect of occurrence of the worst credible contingency.
Available Transfer Capability as defined in the Congestion charge regulations
• “Available Transfer Capability (ATC)” means the transfer capability of the inter-control area transmission system available for scheduling commercial transactions (through long term access, medium term open access and short term open access) in a specific direction, taking into account the network security. Mathematically ATC is the Total Transfer Capability less Transmission Reliability Margin.
06th Oct 2009 NRLDC, POWERGRID 9
Simultaneous TTC
Area A Area B
Area C
2000 MW 4000 MW
5000 MW
Relevance of Transfer Capability in
Indian Electricity Market
CERC Open Access Regulations 2004
5. Criteria for allowing transmission access:
ii) The short term access shall be allowed, if request can be accommodated by utilising:(a) Inherent design margins(b) Margins available due to variation in power flows(c) Margins available due to in-built spare transmission capacity created to cater to future load growth
Tariff Policy Jan 2006
7.3 Other issues in transmission
(2) All available information should be shared with the intending users by the CTU/STU and the load dispatch centres, particularly information on available transmission capacity and load flow studies.
Open Access Theory & PracticeForum of Regulators report, Nov-08
“For successful implementation of OA, the assessment of available transfer capability (ATC) is very important. A pessimistic approach in assessing the ATC will lead to under utilisation of the transmission system. Similarly, over assessment of ATC will place the grid security in danger.”
13th October 2009 13POWERGRID
Declaration of Security Limits
• “In order to prevent the violation of security limits, System Operator SO must define the limits on commercially available transfer capacity between zones.” CIGRE_WG_5.04_TB_301
• “System Operators try to avoid such unforeseen congestion by carefully assessing the commercially available capacities and reliability margins.” CIGRE_WG_5.04_TB_301
13th October 2009 14POWERGRID
Reliability Margin
06th Oct 2009 NRLDC, POWERGRID 16
NERC definition of Reliability Margin (RM)
• Transmission Reliability Margin (TRM)– Amount of transfer capability necessary to ensure reliable
service under a reasonable range of uncertainties in system conditions
• Capacity Benefit Margin (CBM)– Amount of transmission transfer capability reserved to ensure
access to generation from inter connected system
• Reliability Margin is time dependent• In the Indian context
– Overdrawal / Underdrawal by constituents resulting from demand forecast error
– Sudden outage of a large generator in a control area
06th Oct 2009 NRLDC, POWERGRID 17
Quote on Reliability Margin from NERC document
• “The beneficiary of this margin is the “larger community” with no single, identifiable group of users as the beneficiary.”
• “The benefits of reliability margin extend over a large geographical area.”
• “They are the result of uncertainties that cannot reasonably be mitigated unilaterally by a single Regional entity”
Reliability margin as defined in Congestion charge regulations
• “Transmission Reliability Margin (TRM)” means the amount of margin kept in the total transfer capability necessary to ensure that the interconnected transmission network is secure under a reasonable range of uncertainties in system conditions;
August 08, 2007 GSIOAR-2007, IT-BHU, Varanasi 19
Distinguishing features of Indian grid
• Haulage of power over long distances• Resource inadequacy leading to high uncertainty in
adhering to maintenance schedules • Pressure to meet demand even in the face of acute
shortages and freedom to deviate from the drawal schedules.
• A statutorily permitted floating frequency band of 49.5Hz to 50.2 Hz
• Non-enforcement of mandated primary response, absence of secondary response by design and inadequate tertiary response.
• No explicit ancillary services market• Inadequate safety net and defense mechanism
April 20, 2023 NRLDC, POWERGRID 20
Reliability Margins- Inference• Grid Operators’ perspective
– Reliability of the integrated system– Cushion for dynamic changes in real time– Operational flexibility
• Consumers’ perspective– Continuity of supply– Common transmission reserve to take care of contingencies– Available for use by all the transmission users in real time
• Legitimacy of RMs well documented in literature• Reliability Margins are non-negotiable• The actual power flow only demonstrates the utilization
of these margins during real-time and therefore should not be a reason for complain
Difference between Transfer Capability and Transmission
Capacity
06th Oct 2009 NRLDC, POWERGRID
Transmission Capacity Vis-à-vis Transfer Capability
Transmission Capacity Transfer Capability
1 Declared by designer/ manufacturer Declared by the Grid Operator
2 Is a physical property in isolation Is a collective behaviour of a system
3 Depends on design only Depends on design, topology, system conditions, accuracy of assumptions
4 Deterministic Probabilistic
5 Constant under a set of conditions Always varying
6 Time independent Time dependent
7 Non-directional (Scalar) Directional (Vector)
8 Determined directly by design Estimated indirectly using simulation models
9 Independent of Parallel flow Dependent on flow on the parallel path
Transfer Capability is less than transmission capacity because
• Power flow is determined by location of injection, drawal and the impedance between them
• Transfer Capability is dependent on– Network topology– Location of generator and its dispatch– Pont if connection of the customer and the quantum of demand – Other transactions through the area– Parallel flow in the network
• Transmission Capacity independent on all of the above
• When electric power is transferred between two areas such the entire network responds to the transaction
77% of electric power transfers from
Area A to Area F will flow on the transmission path
between Area A & Area C
Assume that in the initial condition, the power flow from
Area A to Area C is 160 MW on account of a generation dispatch
and the location of customer demand on the modelled
network.
When a 500 MW transfer is scheduled from Area A to Area
F, an additional 385 MW (77% of
500 MW) flows on the transmission path from
Area A to Area C, resulting in a 545 MW power flow from
Area A to Area C.
Cross border capacity available for trade
• “Physical capacity connecting zones A and B is sum of 1-3 and 2-3 physical line capacities. However, the cross border capacity available for commercial trade would be less or at most equal to the sum of capacities of cross border lines individually.” CIGRE_WG_5.04_TB_301
1
2
3
A B
13th October 2009 25POWERGRID
Assessment of Transfer Capability
Transfer Capability Calculations must
• Give a reasonable and dependable indication of transfer capabilities,
• Recognize time variant conditions, simultaneous transfers, and parallel flows
• Recognize the dependence on points of injection/extraction
• Reflect regional coordination to include the interconnected network.
• Confirm to reliability criteria and guides.
• Accommodate reasonable uncertainties in system conditions and provide flexibility.
13th October 2009 POWERGRID 27
Courtesy: Transmission Transfer Capability Task Force, "Available Transfer Capability Definitions and Determination", North American Electric Reliability Council, Princeton, New Jersey, June 1996 NERC
April 20, 2023 NRLDC, POWERGRID 28
Total Transfer Capability: TTC
Voltage Limit
Thermal Limit
Stability Limit
Total Transfer Capability
Total Transfer Capability is the minimum of the Thermal Limit, Voltage Limit and the Stability Limit
Time
Power Flow
29
Transfer Capability assessment
AnticipatedNetwork topology +Capacity additions
Anticipated Substation Load
Anticipated Ex bus
Thermal Generation
Anticipated Ex busHydro generation
LGBR
Last Year
Reports
WeatherForecast
Trans.Plan +
approv.S/D
Last Year
patternOperator
experience
Planning criteria
Operating limits
Credible contingencies
Simulation
Analysis
Brainstorming
Transfer Capability
ReliabilityMargin
less
AvailableTransfer
Capability
equals
Planning Criteria is strictly followed during simulations06th Oct 2009 29NRLDC, POWERGRID
30
Steady State Voltage Limits
Voltage (kV rms)
Nominal Maximum Minimum
765 800 728
400 420 380
220 245 198
132 145 122
From Section 5 of Transmission Planning Criteria
31
Credible contingencies
• From Section 3.5 of IEGC– Outage of a 132 kV D/C line or– Outage of a 220 kV D/C line or– Outage of a 400 kV S/C line or– Outage of a single ICT or– Outage of one pole of HVDC bi pole or– Outage of 765 kV S/C line
without necessitating load shedding or rescheduling of generation during steady state operation
Input Data and Source
06th Oct 2009 32
S No. Input Data Suggested Source
1 Planning Criteria Manual on Transmission Planning Criteria issued by CEA
2 Network Topology Existing network with full elements available
Planned outages during the entire assessment period
New transmission elements expected
3 Transmission line limits Minimum of thermal limit, stability limit and voltage limit
4 Thermal unit availability Load Generation Balance report, Maintenance schedule
Anticipated new generating units
5 Thermal despatch Ex bus after deducting the normative auxiliary consumption
Output could be further discounted by the performance index of generating units of a particular size as compiled by CEA
6 Gas based thermal despatch
Past trend
7 Hydro despatch Peak and off peak actual hydro generation on median consumption day of same month last year
The current inflow pattern to be duly accounted
8 Load Anticipated load
9 Credible contingencies Planning criteria + Operator experience
NRLDC, POWERGRID
Process for assessment
• Base case construction (The biggest challenge) – Anticipated network representation– Anticipated load generation– Anticipated trades
• Simulations– Increase generation in exporting area with
corresponding decrease in importing area till network constraint observed
06th Oct 2009 33NRLDC, POWERGRID
Concerns-1• Wide range of permissible frequency band
– Significant interplay of frequency and voltage in a large grid
• ‘UI’ considered as an infinite source / sink
• Limited voluntary participation by utilities for congestion management in real-time– Primary response, Reactive Support
• Availability norm falling short of ensuring Dependability– Outage of complete power station– Outage of complete EHV substation
Concerns-2 • Changes in long-term allocations
• Uncertainties in planned outages of shared resources
• Medium-term inadequacies in transmission/generation – Open Loops, Switching arrangement
• Safety net– Relay settings/ behavior: – Credible N-1 contingency getting converted into simultaneous
multiple outages in real-time
• Frequent large scale contingencies– Fog, Widespread rains, Cyclone, Silt– Limited support from online tools in case of fast events
13th October 2009 POWERGRID 36
Intra-day STOA
Day-ahead STOA
Collective (PX) STOA
First Come First Served STOA
Advance Short Term Open Access (STOA)
Medium Term Open Access (MTOA)
Long Term Open Access (LTOA)
Reliability Margin (RM)
Available Transfer Capability is
Total Transfer Capability less Reliability Margin
TTC ATC
RM
Ratio of transfer capability to transmission capacity
13th October 2009 POWERGRID 38
Congestion
Congestion in Power System
“Congestion is a situation where the demand for transmission capacity exceeds the transmission network capabilities, which
might lead to violation of network security limits, being thermal, voltage stability limits
or a (N-1) contingency condition.”
CIGRE_WG_5.04_TB_301
13th October 2009 40POWERGRID
Visibility of congestion
• Visible to the market players– “If for a given interconnection, there is more demand
for cross border capacity than commercially available, the interconnection is also treated as congested, meaning no additional power can be transferred. This congestion is visible for market players as a limit on their cross-border transactions.”- CIGRE_WG_5.04_TB_301
• Invisible to the market players– “It is possible that even though the available
commercial interconnection capacity is not fully allocated to market players, some lines, being internal or cross-border, become overloaded. This physical congestion is a problem of the System Operator and has to be dealt with by this entity.” CIGRE_WG_5.04_TB_301
13th October 2009 41POWERGRID
To be handled before-the fact
To be handled in real-time
Congestion visible to the market• “The more transactions and the more
meshed the network, the higher the chance for mismatch between commercial exchange and physical flows.” CIGRE_WG_5.04_TB_301 Congestion
Sign of growth and vibrant market Natural corollary to Open Access
Existing transmission system was not planned with short-term open access in mind
Security margins have been squeezed ‘Pseudo congestion’ needs to be checked
13th October 2009 42POWERGRID
Congestion in real-time is a security threat
• Phenomenon common to large meshed grids
• Coupling between voltage and frequency accentuates the problem in a large grid
13th October 2009 POWERGRID 43
Real-time Congestion types
• Internal congestion (Intra-zonal)– Within a single System Operator’s control area
• Cross-border (Inter zonal)– Also called seams issue– Several System Operators involved
Was not experienced -Regional grids were small
-Trades were limited
13th October 2009 44POWERGRID
Experienced occasionally under- Grid Contingencies
- Skewed conditions in gridAggressive Open Access trades
Types of congestion in Indian context
• 3 / 2 / 1 month (s) ahead – advance
• First come first served
• Day ahead PX
• Day ahead bilateral
• Contingency transaction
• Real time
Reasons for congestion in India
• Fuel / resources related constraints– Long haulage of power• Physical network limitations– Fast growing network, transition, mismatch• Inadequate compliance to reliability
standards– Inadequacy in Safety net • Market Design/Interplay and behavior of
players13th October 2009 46POWERGRID
Causes of congestion• Inadequate transmission – including outages
• Inadequate reactive support
• Weather diversity, seasonal demand variation
• Skewed generation availability – monsoon, planned / forced outages
• Uneven purchasing power of utilities in a shortage scenario
• Compulsion to meet load at all costs (agriculture, festival, election etc.) – Aggressive buying
• Economy (cheaper generation to replace costlier generation)
• Inflated sale / purchase requirement – Pseudo congestion
• Inter play with UI mechanism – Bids based on anticipated UI price
Regulatory initiatives• Modifications in Grid Code & other regulations
– Frequency band tightening – Cap on UI volume, Additional UI charge– Inclusion of new definitions (TTC, ATC, Congestion)
• Congestion Charge Regulation– Congestion Charge Value, Geographical
discrimination – Procedure for Assessment of Transfer Capability– Procedure for Implementation of Congestion Charge
13th October 2009 POWERGRID 48
Suggestions for improving transfer capability-1
• installation of shunt capacitors in pockets prone to high reactive drawal & low voltage
• strengthening of intra-state transmission and distribution system
• improving generation at load centre based generating stations by R&M and better O & M practices
• avoiding prolonged outage of generation/transmission elements
• reduction in outage time of transmission system particularly those owned by utilities where system availability norms are not available
Suggestions for improving transfer capability-1
• minimising outage of existing transmission system for facilitating construction of new lines
• expediting commissioning of transmission system-planned but delayed execution
• enhance transmission system reliability by stregthening of protection system
• strengthening the safety net- Under voltage load shedding schemes, system protection schemes
AN OVERVIEW CONSTRAINTS AND HOTSPOTS in
SR
ELECTRICITY, n. The power that causes all natural phenomena not known to be caused by something else. Ambrose Bierce, The Devil’s Dictionary, 1881–1906
SALIENT FEATURES OF SOUTHERN REGIONAL GRID
• BEST HYDRO-THERMAL MIX 30-70 %• HYDRO GENERATION TO MEET THE BASE LOAD• CONSIDERABLE IPP CONTRIBUTION • PUMPED STORAGE SCHEMES IN SRISAILAM-AP (900 MW) &
KADAMPARAI-TN (400 MW)– FAST RAMPS– SKEWED FLOWS
• HIGHEST WIND GENERATION AMONGST ALL THE REGIONS(>3500 MW WITH 1500 MW VARIATION)
• HEAVILY DEPENDENT ON MONSOON• VOLTAGES CHANGE FROM 370 KV TO 425 KV AT SOME
BUSES OVER THE YEAR.• 1000 MW NUCLEAR UNITS EXPECTED AT KUDANKULAM (TN)-
RELIABILITY IMPACT
• CONGESTION RELATIVELY NEW CONCEPT FOR SR IN RECENT YEARS.
NORTH EAST MONSOON
(WINTER MONSOON)
SOUTH WEST MONSOON
(SUMMER MONSOON)
IMPORT FROM CENTRAL GRIDCONTINGENCY CONDITIONS
• SR HAS BEEN ABLE TO ACCOMMODATE IMPORTS FROM
OTHER REGIONS TO..
– RELIEVE LINE LOADINGS IN THAT REGION (EXAMPLE SR IMPORTED
POWER TO RELIEVE LOADING OF FARRAKA-MALDA AND TALCHER –
ROURKELA ON MANY OCCASIONS)
– NATURAL CALAMITIES : SMOG PROBLEM CAUSING UNFORSEEN TRIPPINGS
IN NR IN DEC-JAN EVERY YEAR – SR IMPORTS POWER TO THE MAXIMUM
TO ASSURE SAFETY OF INDIAN GRID
– CORRIDOR INSUFFICIENCY : SR HAS WHEELED POWER FROM ER TO WR
ON MANY OCCASSIONS
– MAJOR L/C’S IN NEW GRID
– SYSTEM DISTURBANCES IN NEW GRID
THE SOUTHERN REGION GRID
ATC ISSUES AND HOTSPOTS
SOUTHERN REGION
WESTERNREGION
EASTERN REGION
NORTHERN REGION
NORTH-EASTERN REGION
1
2
TWO ELECTRICAL REGIONS w.e.f Aug. 2006
‘NEW’ GRID
HVDC INTERCONNECTS
AC INTERCONNECTS
MAJOR INTERCONNECTIONS
2X500 MW BACK TO BACK STATION AT
GAZUWAKA(SR)
1000 MW BACK TO BACK STATION AT
BHADRAWATI(WR)
TALCHER
KOLAR
TALCHER-II TO KOLAR
2000 MW BIPOLE LINK
INTER REGIONAL TRANSFER CAPACITY SR WITH OTHER REGIONS
• WITH ER• JEYPORE-GAZUWAKA 1000 MW• TALCHER-KOLAR 2000 MW
• WITH WR• RAMAGUNDAM-CHANDRAPUR 1000 MW
TOTAL CAPACITY IS 4000 MW
220 KV LINKS ARE IGNORED BECAUSE THEY ARE NOT IN ACTIVE USE
OVERLOAD CAPACITY AT KOLAR IS NOT CONSIDERED EXCEPT IN AN EMERGENCY
ALLOCATIONS OF SR PEAK
SR ISGS/ SR BENIFICIARY
RSTPS STAGE-1&2
RSTPS STAGE-3
TALCHER
STAGE-2
NLC TSII
STAGE-1
NLCTSII
STAGE-2
NLC TS1 EXP
MAPS KGS KGS3
FARAKKA
KAHALGAON
TALCHER-1
Installed Capacity @
2100 500 2000 630 840 420 440 440 2201600 840 1000
APTRANSCO 34.00 35.73 21.29 21.16 27.08 0.00 10.42 32.67 34.48 2.48 2.45 2.48
KPTCL 19.19 20.22 18.57 22.35 22.16 26.45 7.36 27.37 29.87
KSEB 11.66 12.20 21.00 10.86 11.39 14.00 5.23 8.64 7.96
TNEB 26.50 27.82 25.46 33.20 36.30 55.32 75.47 28.08 24.90 1.46 1.44 1.46
PONDY 3.78 4.03 3.48 12.43 3.07 4.23 1.52 3.24 2.79 0.73 0.72 0.73
GOA 4.76
NLC MINES
HVDC 0.11 0.20
ORISSA 10.00
TOTAL 100.00 100.00 100.00100.0
0 100.00 100.00 100.00 100.00 100.00 4.67 4.61 4.67
APTRANSCO SYSTEM
KPTCL SYSTEM
KSEB SYSTEM
Ramagundam2480 MW
ER ISGS143 MW
MAPS Nuclear 265 MW
TALCHER STG II1640 MW
KAIGA Nuclear 450 MW
NEYVELI IINEY EXP1642 MW
GAZUWAKA HVDCBHADRAWATI HVDC
TALCHER-KOLAR HVDC
SCHEDULE OF INTER STATE FLOWS AT PEAK HOUR WHEN ISGS DESPATCH IS FULL
895 MW
Pondy262 MW
585 MW
940 MW
1480MW
25 MW
TNEB SYSTEM
3 Nos. 400 kV lines &2 Nos 220 kV lines
Goa
95 MW
4 Nos. 400 kV lines &3 Nos 230 kV line
6 Nos. 400 kV lines &2 Nos 220 kV lines
*WITHOUT POOL LOSSES
4 Nos. 400 kV lines &1 Nos 220 kV line
ENT: 1728 MW
ENT: 2185 MWENT: 1385 MW
ENT: 965 MW
HYDERABAD URBAN AREA
YEDUMAILARAM
MAMIDAPALLI
MALKARAM
MOULALI
GHANAPUR GHANAPUR
MAMIDAPALLI
SIVARAMPALLI C.H.GUTTA
G BOWLI
245 MW X2
262 MWX3
66 MW
98 MW80 MW
127 MW 80 MWX2
162 MWX2
45 MWX2
COIMBATOREHEAVILY LOADED DURING LOW HYDRO
WILL BE SOLVED WITH COMMISSIONING OF ARASUR 400 Kv
TTPS
SR PUDUR
TTP AUTO
PARAMAKUDY
THENI
PASUMALAI
MADURAI
A-KULAM
K-KURUCHI
VEERANAM
KAYATHAR
SANGANERI
STERLITE
SIPCOT
TO EDAMON
TO SABARIFIRI
WIND ENERGY IN S. TAMILNADU- LINE LOADINGS
BASE CASE
1. 5 UNITS AT TTPS
2. WIND 1000 MW APPROX
3. KSEB NORMAL DRAWAL
4. WITHOUT STEPPING UP AT ICT’s AT TIRUNELVELI
5. REG. LOSSES 853 mw
137
146110
111
189
87
110
OPEN
180
6977 8
46
174
180
17
7
174
121
17
16
MAJOR WIND INJECTION POINTS
UDAYATHURKANARPATTY
THIRUNELVELI
9
141
55
TRIVANDRUM
113
223
128
26
AMUTHAPURAM
290
152
212
WIND
KODI KORICHI : 100
VEERANAM : 260
UDAYATHUR : 140
AMUTHAPURAM : 138
SANGANERI : 130
140
276
OPEN
EVOLUTION OF A CONSTRAINT
S1-S2 BID AREA SPLIT
EVOLUTION OF S1-S2 BID AREA CONSTRAINTS
• SR APPROACHING PEAK LOADS
• TN+KERALA SHORT OF POWER– PARTICIPATE AGGRESSIVELY IN STOA
AND PX– TN ISGS ENTITLEMENT IS AROUND 2000
MW– TRADES 2300 MW AT A POINT!
Congestion Management in SR: Between S1, S2 bid areaSnapshot of 400kV Hosur-Salem flow 725MW and the Drawl by S2 area constituents on 19-01-2010 at18:52Hrs
Congestion Management in SR: Between S1, S2 bid area
Snapshot of 400kV Hosur-Salem flow 725MW on 19-Jan-2010 18:52 Hrs
Congestion Management in SR: Between S1, S2 bid area
• During the period 18-22Hrs the schedules of TN and Kerala was around 4200 MW and 950 MW respectively.
• At this levels, 400kV Hosur-Salem flow is greater than 750 with no N-1 reliability.
• In case of tripping of 400kV Hosur-Salem or 400kV Somanahalli-Salem, other circuit get severely loaded.
• Worsens with low generation in TN-Kerala area
Congestion Management in SR: Between S1, S2 bid area
Congestion Management in SR: Between S1, S2 bid area
• In N-1 condition, 400kV Hosur-Salem and 400kV Somanahalli-Salem getting severely loaded.
• To limit the flow below 800MW, it was decided to put limit on schedule.
• After conducting load flow study, Schedule decided for S2 area constituents was 5000MW.
Congestion Management in SR: Between S1, S2 bid area
• Schedule breakup margin for individual constituents(approx.):
TNEB- 3700 MWKSEB- 900 MWPONDY-270 MW
• In case all NeyveliTS2 and TS1Exp units are there the limit increases to 5000MW as 60% counter flow towards S1 area will be there.
• The limit=flow sum(400kV SMN-Salem,400kV Kolar-Hosur,400kV Kolar-KVPattu,400kV Chittur-SRPD,400kV Nellore-Almatti)+Generation at NeyveliTS2+Generation at Neyveli TS1Exp
Congestion Management in SR: Between S1, S2 bid area
Sample Calculation of limit between S1,S2 bid area PX margin
A=S1,S2 bid area limit set (MW)
B= ISGS Entitlements after loss (MW)
C= STOA bilaterals approved after loss (MW)
D=available Px Margin for S2 area constituents
::D=A-B-C
Congestion Management in SR: Between S1, S2 bid area
IMPROVING THE TRANSFER CAPABILITY• SPS TO LIMIT POST CONTINGENCY
VIOLATION– SUGGESTED FOR S1-S2
• SPS TO RE-ARRANGE NETWORK IN KERALA TO LIMIT LOADS BEYOND A THRESHOLD– BEING WORKED OUT FOR KERALA
• SPS ARMING AND DISARMING BASED ON PRE-CONTINGENCY EVALUATION– Ex: SPS 450/1000
• SPLITTING THE NETWORK– NEYVELI-MADRAS CASE- 230 KV PARALLEL IS
KEPT OPEN WHEN FLOW EXCEEDS 350 MW
CLOSING THE 220 KV KADKOLA-KANIYAMPETTA LINE
SHIFTING OF CONGESTION!
Base Case
1.Sharavathi Gen-Full2. Varahi-3 Units3.400kV Nelamangala-Talaguppa-one ckt-out4.220kV Kadakola-Kanyampet-out
108MWx2
256 MW137MWx4
62MWx2
66MWx2
45MWx2
129MWx2
108MW
60MW
50MWx2
61MW
159MWx2
10MW
Talguppa
Sharavathi
STRP
Varahi
Nelamangala
Huyyaganahalli
Mysor
Hootgalli
Kadakola
Kaniyampet
105MW
Mysore ICT flow 129MWx2
Case-1
1.Sharavathi Gen-Full2. Varahi-3 Units3.400kV Nelamangala-Talaguppa-one ckt-out4.220kV Kadakola-Kanyampet-in with flow 193MW
123MWx2
252 MW140MWx4
60MWx2
66MWx2
45MWx2
129MWx2
121MW
75MW
122MWx2
22MW
164MWx2
40MW
Talguppa
Sharavathi
STRP
Varahi
Nelamangala
Huyyaganahalli
Mysor
Hootgalli
Kadakola
Kaniyampet
122MW
193MW
After closing 220kV Kadakola KaniyampetThe line flow shared by following:1.Mysore ICTs- 120MW (62%)2.From shimoga-30 MW (16%)3.220kV TkHalli-Hootgalli-40 MW(21%)
Mysore ICT flow 189MWx2
77MWx2
149x2 MW146MWx4
84MWx2
66MWx2
114MWx2
152MWx2
74MW
30MW
49MWx2
48MW
152MWx2
9MW
Talguppa
Sharavathi
STRP
Varahi
Nelamangala
Huyyaganahalli
Mysor
Hootgalli
Kadakola
Kaniyampet
75MW
Case-2
1.Sharavathi Gen-Full2. Varahi-zero Generation3.220kV Kadakola-Kanyampet-out
Mysore ICT flow 152MWx2
91MWx2
147x2 MW149MWx4
81MWx2
66MWx2
114MWx2
204MWx2
89MW
45MW
112MWx2
14MW
157MWx2
35MW
Talguppa
Sharavathi
STRP
Varahi
Nelamangala
Huyyaganahalli
Mysor
Hootgalli
Kadakola
Kaniyampet
90MW
Case-3
1.Sharavathi Gen-Full2. Varahi-zero Generation3.220kV Kadakola-Kanyampet-out
Mysore ICT flow 204MWx2
168 MW
Conclusion
• It is impossible to plan / design a large congestion-free system
• Mild / occasional congestion indicates optimum investment in transmission
• Regular congestion indicates inadequacy– Generation– Transmission– Reactive compensation
The balance needs to be restored !
06th Oct 2009 NRLDC, POWERGRID
Grid SecurityMarket
References• Central Electricity Authority
– Manual on Transmission Planning Criteria, Jun-94• Central Bureau for Irrigation and Power
– Thermal limits of various conductors used in transmission system, Technical Report no. 77, May 1991
• North American Electric Reliability Corporation– ‘Transmission Transfer Capability A Reference Document for Calculating and
Reporting the Electric Power Transfer Capability of Interconnected Electric Systems ’ –May 1995
– ‘Available Transfer Capability Definitions and Determination’ -June 1996– ‘Transmission Capability Margins and their use in ATC determination –White
Paper’, 17th June 1999– ‘Reliability Criteria and Operating Limits Concepts’, Version 4 Draft 8, 2nd May
2007
• Power System Engineering Research Centre– ‘Electric Power Transfer Capability: Concepts, Applications, Sensitivity and
Uncertainty’, PSERC publication 01-34, November 2001, http://www.pserc.wisc.edu
• European Network of Transmission System Operators for Electricity– NTC and ATC in the internal market of Electricity in Europe, Mar 2000– Definitions of Transfer Capacities- Final Report, April 2001– Procedures for Cross border transmission capacity asssessments, Oct 2001 8406th Oct 2009 NRLDC, POWERGRID