Southern California Edison - Clean Hydrogen Power ... · Southern California Edison - Clean...
Transcript of Southern California Edison - Clean Hydrogen Power ... · Southern California Edison - Clean...
909 GASIF0601-1 SCE CHPG Project
Southern California Edison -Clean Hydrogen Power Generation (CHPG)
Project Status & Technology Overview
Satish GaddeJenifer Hedrick
Gasification Technologies Conference, Colorado Springs
Oct 4 – 7, 2009
GTC Oct 6, 2009 Page 2
Discussion Outline
Project Status Southern California Edison
Reasons for the CHPG Project
CHPG Project Status
Next Steps
Technology Overview Conceptual Design
Plant Configuration
Technology Selection Process
Estimated Plant Performance & Cost
GTC Oct 6, 2009 Page 3
Southern CaliforniaEdison is: an investor owned
electric utility (EIX) regulated by the
California PublicUtilities Commission
SCE has 4.8 millioncustomer accounts andserves about 13 millionpeople
Southern California Edison
SCE had provided electricity for more than 120 years
50,000 square mile service area
23,303 MW peak demand
GTC Oct 6, 2009 Page 4
16% of SCE’sgeneration comesfrom renewableforms ofgeneration
The goal is 20%renewablegeneration by 2010
51% natural gas
Generation Mix
GTC Oct 6, 2009 Page 5
California Assembly Bill 32
EPRI “PRISM” Analysis
Senate Bill 1368 -Restricts GHG emissions
1100 lb CO2/MW-hr
Generationtechnology options
to meet climatechange legislation
CA path to Reduced GHG Emissions
GTC Oct 6, 2009 Page 6
Overall Outcome
Requirements
Meet GHG Emissions
Meet obligation to serve
Conclusion
Evaluate options for cost effective technology that meetsrequirements – IGCC
SCE experience with IGCC – CoolWater, Daggat CA, mid-1980’s
Coal relatively stable price, vast domestic sources
Technology can be built at Utility scale,
Baseload generation
With carbon capture and storage, can exceed CA GHG requirements
GTC Oct 6, 2009 Page 7
Sources of Project Funding
California Public Utilities Commission (CPUC)
~$50m conditionally authorized by the CPUC to conduct a
feasibility study of the Clean Hydrogen Power Generation plant:
− Sequestration Testing
− Plant Feasibility
Conditions
− Seek co-funding for Sequestration
− Seek and obtain co-funding for Plant Feasibility
Co-Funding
EPRI Demonstration Project
Southwest Regional Partnership
Application to DOE for ARRA: CCPI Round 3 – results pending
GTC Oct 6, 2009 Page 8
Project Overview
• 500 MWnet
• Western Coal
• 5000’ elevation
• Carbon Capture & Storage in deep salineaquifer
Regulatory
Funding
TechnicalPlant DesignSequestrationTransmission
Permitting
Siting
AuthorizedFeasibilityStudies
Co-fundingRequirements
CentralEasternUtah
PreliminaryAssessments
Complete
Graphic by Colorado Geological Survey
GTC Oct 6, 2009 Page 9
CHPG Project Status – Activities Completedor in Progress
Concept & Site Screening
Feasibility Design
Generation site selection
CO2 storage site selection
Generation Technology screening
Technology selection for IGCC
Technology evaluation
Preliminary specification
Feasibility cost estimate
Preliminary project schedule
Begin vendor participation majorcomponents
Gasifier
Combustion turbine
Major processes
Short-list of acceptable majorcomponent candidates for later selection
GTC Oct 6, 2009 Page 10
Next Steps
Overall Project Schedule
3 Years
2 Years
2 Years
1 Year
Project Definition
Detailed Design
Construction
Demonstration
Jan 1
2010
Jan 1
2011
Jan 1
2012
Jan 1
2013
Jan 1
2014
Jan 1
2015
Jan 1
2016
Jan 1
2017
Jan 1
2009
Jan 1
2018
FEED, Permitting,Sequestration Testing
Detailed Design,
Procurement
Procurement,Construction,
Commissioning
Year 1CommercialOperation
Evaluate technicalfeasibility and
financialreasonableness
909 GASIF0601-11 SCE CHPG Project
CHPG Project Technology Overview
GTC Oct 6, 2009 Page 12
Technical Tasks Completed
Ultra Supercritical PC with 90% CO2 Capture
Conceptual Design
Plant Performance
Plant Emissions
Plant Cost Estimates & Economics
IGCC with 80 – 90% CO2 Capture
Conceptual Design
Gasification Technology Screening
Plant Performance (multiple gasification technologies)
Plant Emissions
Plant Cost Estimates & Economics (multiple gasificationtechnologies)
GTC Oct 6, 2009 Page 13
CHPG Project – Conceptual Design(Simplified Block Flow Diagram)
Coal Handling Scrubber
Shift Reactor Hg Removal Two Stage AcidGas Removal
CO2
Compressor
HRSG
STG
Sulfur Recovery
CryogenicASU
Gas Turbine
Air To ASU
Stack
CO2Acid Gas
CO2 (2200 psig)
O2
N2
from ASU
Gasification Island ParticulateRemoval
Coal Feed& Prep
Heat Sink Cond
Steam Cycleand
Air side Integration
GTC Oct 6, 2009 Page 14
CHPG Base Plant Configuration
Plant Configuration
Output - 500 MWe Nominal
Arrangement - 2 x 2 x 1
Primary Feedstock – Utah Bituminous Coal
Gasifier: Evaluated Five Technologies
Gas Turbine: Evaluated Three Models
HRSG: Two & Three Pressure (LP Induction)
HRSG Natural Gas Supplemental Firing
Steam Turbine: 1800 psig/ 1040oF/1040oF
Wet Cooling System
CO2 Separation: Dual Stage Selexol
CO Shift Reactor: 2- Stage using
Typical Catalyst
GTC Oct 6, 2009 Page 15
80% - 90% CO2 Capture Technology Chosen:Process Flow Diagram (with 2 Stage Shift)
CO2
compression anddrying
H2S
Ab
sorb
er
CO
2
Ab
sorb
er
So
lven
tS
trip
per
Aci
dG
asK
no
cko
ut
Dru
m
H2S FlashDrums
Acid GasEnrichment
CompressedCO2 Product
Wat
er-G
asS
hif
tR
eact
or
1
CO2 FlashDrums
Treated Syngas toCombustion Turbine
Sour Syngasfrom Gasifier
Acid Gas to SulfurRecovery Unit
Steam
MakeupWater
ExportWater
Wat
er-G
asS
hif
tR
eact
or
2
Two Stage Shift required to meet the CHPG Project Requirement
Two Stage Acid Gas &CO2 Separation Unit
GTC Oct 6, 2009 Page 16
Altitude effects on Plant
0.6
0.8
1
1.2
1.4
0 1000 2000 3000 4000 5000 6000 7000
Altitude (ft.)
Po
wer
Ou
tpu
t
NG Operation
IGCC Operation (80% CO2 capture)
Site altitude impacts IGCC design. A sea level design must bemodified to work best at altitude
~18% drop in ambient pressure at the CHPG site ~15% drop in air density
Gas Turbine Output reduces 10-15%compared to Mean Sea Level
Three Gas Turbine ModelsEvaluated
GTC Oct 6, 2009 Page 17
Conceptual Design
Selecting technology that is flexible inhandling western grade blend feedstocks
Customizing the process, selectingequipment and designing to high altitudesite specific conditions
Optimizing the design to reduce upfront andoperating costs
Incorporating lessons learned fromprevious IGCC projects
Selecting equipment that maximizes thePerformance and Capacity Factor as muchas practical
GTC Oct 6, 2009 Page 18
Gasification Technology Selection- Stage 1 (Preliminary Screening)
Comprehensive and Systematic process developed using the Pugh Matrix Approach for variousPlant Attributes. Analysis comprised of Commercial and Technical Variables
WorleyParsons & EPRI In-House expertise and databases utilized to screen the technologies
Started with Nine Gasification suppliers with widely varying technologies
Filtered to Five technologies for detailed assessment
Detailed & Methodical Process followed at all stages of the screening process with independentreviews by all project members and reviewers to isolate any possible discrepancies
7) Score each of the projectdrivers for all the Technology
Suppliers relative to eachother
1) Determine SCEproject drivers
2) Determine theTechnology Suppliers
screening list
3) Define Weighting criteriafor the CHPG project drivers
4) Assign weights to theproject drivers per the CHPG
requirements using theweighting criteria
5) Create a project driversmatrix for each of theTechnology Suppliers
6) Fill in the matrix withthe data received from
the Technology Supplier
8) Estimate the results bymultiplying the Weights and Scores
for all the Technology Suppliers
9) Rank theSuppliers
10) Complete a detailed assessmentof the top five (5) suppliers throughvendor interaction and independent
evaluations
11) Downselect to two (2) gasifiersfor the Pre-FEED phase
12) Select one (1) gasifierprior to the FEED Phase
(future)
Attributes and Drivers are created based onSCE’s goals & CHPG project requirements
GTC Oct 6, 2009 Page 19
Gasification Technology Screening- Stage 2 (Detailed Screening)
Directly interacted with all five (5) Technology Suppliers to obtain the Technical Data for the Avg.Design Case
Detailed Process modelling (in Aspen PlusTM) and Steam Cycle modelling (in GateCycleTM) byWorleyParsons, reviewed by EPRI & SCE
Plant Performance, Capital Cost, O&M and other results estimated for all five (5) technologies
Data developed from the Evaluations was used in the Screening Matrix for final downselection
Four way Confidentiality Agreements executed with all 5 suppliers
GTC Oct 6, 2009 Page 20
Representative CHPG Plant Performance
* coal only** coal plus natural gas
8086Percent% CO2 Captured, as a percent of
carbon in the plant coal feedwhich could have been CO2
425325lbs/MWh
-netTotal CO2 Emissions,
CO2 Emissions
10,800 **11,000 *Btu/kWhNet Plant Heat Rate, HHV
31.5 **31.0 *PercentNet Plant Efficiency, HHV
6,000 **5,350 *MMBtu/hTotal Fuel Consumption, HHV
554486MWNet Plant Power Output
737666MWGross Plant Output
Utah BituminousUtah BituminousFuel
ONOFFNatural Gas Duct Firing
GTC Oct 6, 2009 Page 21
CO2 Produced and Avoided
Plant Carbon Capture Level
CHPG Intensity – 325 lb/MWhr-net
Sequestered Flow rate – 3.5 million tons/yr
0 500 1,000 1,500 2,000 2,500
Natural Gas No Capture
IGCC 2-Stage Shift
IGCC Max Single Shift
IGCC Single Shift
IGCC Min Single Shift
IGCC Skimming
IGCC No Capture
CO2, lb/net MWh
0 200 400 600 800 1,000
CO2, g/net kWh
CO2 Emissions
CO2 Captured
CO2 Avoided vs Natural Gas With No Capture
CO2 Avoided vs
IGCC With No Capture
#V
ALU
E!
0 500 1,000 1,500 2,000 2,500
Natural Gas No Capture
IGCC 2-Stage Shift
IGCC Max Single Shift
IGCC Single Shift
IGCC Min Single Shift
IGCC Skimming
IGCC No Capture
CO2, lb/net MWh
0 200 400 600 800 1,000
CO2, g/net kWh
CO2 Emissions
CO2 Captured
CO2 Avoided vs Natural Gas With No Capture
CO2 Avoided vs
IGCC With No Capture
#V
ALU
E!
GTC Oct 6, 2009 Page 22
Project Costs
Project Preliminary Cost Estimates Completed March 2009 forall five evaluated gasification technologies Gasification Technology Suppliers provided the Costs for their respective
Gasification Island
WorleyParsons estimated Rest of the Plant Costs
Plant Capital and O&M costs comparable to other industrypublications
Plant Cost of Electricity commensurate to the levels publishedby DOE in the Market Based Study
GTC Oct 6, 2009 Page 23
Project Technical Synopsis
IGCC Technology with CCS selected for CHPG Project
CHPG project currently being designed for CO2 Capture levelsof 80 – 90%
Technology Selection Process Established – Screening ofGasification Technology Suppliers Completed
Plant Feasibility Study & Conceptual Design Complete;Preliminary Plant Performance and Costs Estimated
Project proceeding into FEED A Phase (TechnologyOptimization, Process & Equipment Selections, Detailed CostEstimate)
909 GASIF0601-24 SCE CHPG Project
Thank You for your time and attention
Gasification Technologies Conference, Colorado Springs
Oct 4 – 7, 2009