South Hook CHP Plant Herbrandston, Pembrokeshire · · 2016-05-04South Hook CHP Plant...
Transcript of South Hook CHP Plant Herbrandston, Pembrokeshire · · 2016-05-04South Hook CHP Plant...
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 1 17 February 2014
Document 2.12
South Hook CHP Plant
Herbrandston, Pembrokeshire
Applicant’s Response to Examining Authority’s second Round of Written Questions and Request for Information
The Planning Act 2008 Planning Inspectorate Reference: EN 010054
17th
February 2014
Applicant: QPI Global Ventures Limited
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 17 February 2014
South Hook CHP Plant
Applicant’s Response to Examining Authority’s Second Round of Questions
and Requests for Information
Document History
TITLE: Applicant’s Response to Examining Authority’s Second Round of Questions and Requests for Information
DOCUMENT REF: Document 2.12
Version Status/Purpose/ Description
Originator Checked Authorised Date
Final Final for Submission
SHCHP Team
LP/PE/CZ/JT/DI
PE 17-02-14
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 3 17 February 2014
Contents 1 Introduction and Purpose of Document ............................................................................. 4
1.1 Background ........................................................................................................... 4 2 Applicant’s Comments on Written Summaries of Oral Cases put at the Issue Specific
Hearing ............................................................................................................................. 5 2.1 NRW Oral Case ..................................................................................................... 5 2.2 PCNPA & PCC Oral Case – Affordable Housing ................................................... 5
3 Applicant’s Response to Examining Authority’s Second Round of Written Questions and Requests for Information ............................................................................................ 9 3.1 Development Consent Order (DCO) (Q1.1 to 1.6) ................................................. 9 3.2 Questions arising from the applicants response to first round questions on
DCO drafting........................................................................................................ 12 3.3 Statements of Common Ground (SoCG) (Q2.1) .................................................. 16 3.4 Habitats Regulation Assessment (Q3.1 to Q3.4) .................................................. 16 3.5 Other Information (Q4.1 to Q4.4) ......................................................................... 19
APPENDICES Appendix 1 Transportation Technical Note Appendix 2 Revised DCO Appendix 3 Revised Document 1.22 Design Principles Statement Appendix 4 Document 2.13 Draft Landscape Proposals Plan Appendix 5 Document 1.10A Works Plan A,
Document 1.10B Works Plan B and Document 1.9 Section Drawing Plan
Appendix 6 Document 2.14 Limits of Deviation Requirement for Stack Appendix 7 Document 2.8 – SoCG in respect of Seascape, Landscape and Visual
Impact Appendix 8 Figure 1 - Existing Services Drawing for RWE Land
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 4 17 February 2014
1 Introduction and Purpose of Document
1.1 Background
1.1.1 This document summarises the Applicant’s response to the Examining Authority’s second round of written questions and request for information as set out in the Examining Authority’s letter of 27th January 2014.
1.1.2 The format of the Applicant’s response is as follows:
Applicant’s comments on written summaries of oral cases put at the issue Specific hearing held on 15th January 2014.
Applicant’s response to Examining Authority’s second round of written questions and requests for information relating to :
o Development Consent Order (DCO) (Q1.1 to Q1.6)
o Questions arising from the applicant’s response to first round questions on DCO drafting
o Statements of Common Ground (SoCG) (Q2.1)
o Habitats Regulation Assessment (Q3.1 to Q3.4)
o Other Information (Q4.1 to Q4.4)
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 5 17 February 2014
2 Applicant’s Comments on Written Summaries of Oral Cases put at the Issue Specific Hearing
2.1 NRW Oral Case
2.1.1 The Applicant has no comments on NRWs oral representation other than where matters are raised directly by the Examining Authority’s questions.
2.2 PCNPA & PCC Oral Case – Affordable Housing
2.2.1 The Applicant considers that the question of affordable housing remains not relevant and not important for the purposes of the proposed development subject to this DCO application and section 104(2)(d), Planning Act 2008, notwithstanding that the matter is raised in the LIRs.
2.2.2 PCNPA and PCC’s oral submissions indicated that discussions are on-going between the Applicant, PCNPA and PCC and Appendix A of their further written submissions comprises a note of a telephone conference that took place on 10 January 2014 with regard to the matter. However, there is not the potential ‘convergence’ orally suggested by these authorities at the ISH.
2.2.3 Against that context the Applicant sought improved understanding of the question of permanent affordable housing raised by PCNPA and PCC by ascertaining the quantum of the requests.
2.2.4 An email from PCNPA (Martina Dunne) dated 24 January 2014 confirmed that both PCNPA/PCC consider that ‘to prevent homelessness the Authorities ask that 30% of that travelling demand – 57 workers (189/100*30) be provided with accommodation by the project.’ That is, 57 temporary construction period workers.
2.2.5 A subsequent email from PCNPA (Martina Dunne) dated 7 February 2014 confirmed that PCNPA/PCC are seeking 49 units (41 1-bed, 7 2-bed and 1 3-bed) which would cost a total of £4,166,000. That is, 49 permanent units.
2.2.6 No particular site has been identified by PCNPA/PCC on which such permanent housing could be delivered and there is no certainty at present that any site exists that benefits from the necessary planning permission or is genuinely available to provide such housing within the timescale set by the two Authorities (i.e. in readiness for the start of construction due to commence in early 2015 (subject to the granting of the DCO and the efficient discharge thereafter of the relevant pre-commencement requirements)).
2.2.7 Further meetings have taken place between the Applicant, PCNPA and PCC on 10 and 11 February 2014 during which the question of affordable housing was discussed. No agreement has been reached on that question.
2.2.8 The Applicant concludes that no evidence has been provided by the two Authorities to satisfy the guidance tests of EN-1, paragraph 4.1.8 for a development consent planning obligation under section 106 of the Town and Country Planning Act 1990
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 6 17 February 2014
(as amended): (“relevant to planning”; “necessary to make the development acceptable in planning terms”: “directly related to the proposed development”; and “fairly and reasonably related in scale and kind to the proposed development, and reasonable in all other respects”) in summary as follows:
EN-1 paragraph 5.12.4 states that Applicant’s should ‘… refer to how the development’s socio-economic impacts correlate with local planning policies’. Paragraph 5.12.6 states that the IPC should have regard to potential socio-economic impacts that it ‘…considers to be both relevant and important to its decision’, paragraph 5.12.7 states that ‘The IPC may conclude that limited weight is to be given to assertions of socio-economic impacts that are not supported by evidence (particularly in view of the need for energy infrastructure as set out in this NPS)’ with paragraph 5.12.9 stating that ‘The IPC should consider whether mitigation measures are necessary…’. Here, there is no correlation nor relevance between the proposed development and the question of affordable housing. In terms of local planning policies PCNPA and PCC did not set out in their LIRs any correlation between the proposed SHCHP Plant, local planning policy and their request for permanent affordable housing.
Subsequently, upon request of the Applicant for some further explanation, the Authorities raised orally the PCC Local Development Plan Policy GN 3 - Infrastructure and New Development which states that ‘Where development generates a directly related need for new or improved infrastructure, services or community facilities and this is not already programmed by a service or infrastructure company, then this must be funded by the development, and: related in scale and kind to the development;…’ and the PCNPA Local Development Plan Policy 48 that relates to Community Facilities and Infrastructure and states that ‘c) planning permission will be granted for proposals that have made suitable arrangements for the improvement or provision of infrastructure, services and community facilities made necessary by the development.’ Neither of these policies were referred to by the Authorities in their LIRs nor can they be interpreted so as to cover the circumstances of this application and the Applicant concludes that there is no correlation or relevance between the policies and the Authorities’ requests for permanent affordable housing due to the temporary presence of construction workers.
Subsequently, the Authorities have not in their further written representations referred to these two policies again. The Applicant concludes that these two policies are not relevant. The Applicant respectfully submits that the question of permanent affordable housing is neither relevant nor important to this application, despite the reference to that question in the Authorities’ LIRs.
The requested development consent planning obligation is not necessary to make the development acceptable in planning / DCO terms. There is no evidence that the accommodation of temporary construction workers will generate a permanent need that is necessary to be mitigated against by the provision of permanent housing such that the SHCHP development is acceptable in Planning Act 2008 terms.
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 7 17 February 2014
The requested contribution is not “directly related to the proposed development”. There is no evidence to show a direct link between the temporary accommodation for construction period workers and permanent housing loss.
The requested contribution is not fairly and reasonably related in scale and kind to the development. There is no evidential basis to show that 49 permanent housing accommodation units relates to a temporary construction period or to a permanent (non-residential) power station development in which people will work but not live.
The requests are not reasonable in all other respects.
2.2.9 The Applicant therefore concludes that the construction of the proposed CHP Plant will not have any impact upon local housing such that there is any justification for a development consent planning obligation to secure any contribution towards permanent provision of 49 units of affordable housing. As such the Applicant’s position with regard to housing remains as set out in Appendix 2 of its Second Response (Document 2.7), subject to the substitution by EN-1 paragraph 4.1.8 (the guidance tests for development consent planning obligations) for the references to Regulation 122 in Appendix 2, paragraphs 1 and 23. The Applicant considers that the question of affordable housing is not relevant and not important to the ExA’s determination of this application.
Pembrokeshire County Council - Transportation
2.2.10 The Applicant considers that the question of transportation remains not important for the purposes of the proposed development subject to this DCO application for the purposes of section 104(2)(d), Planning Act 2008, and notwithstanding that this matter was raised in an LIR.
2.2.11 Following on from the comments of PCC, in particular at the ISH, a further assessment has been undertaken by RPS and is attached as Appendix 1 to this document and helps to establish :
The precise detail and locations of the various highway improvements and road works recently proposed by the Council in its LIR (as amplified at the ISH);
The justification or otherwise for the works proposed
with a view to establishing if any such works justify a development consent planning obligation under s106 contribution in line with the guidance terms of EN-1, paragraph 4.1.8 (see above). In particular consideration has been given to whether it is “necessary” for the proposed s106 development consent planning obligation contributions to be made in order to make the DCO application proposal acceptable in planning DCO terms. Further to that assessment, the Applicant’s position otherwise remains that as expressed in its Appendix 3 to its Second Response (Document 2.7), subject to the substitution by EN-1 paragraph 4.1.8 (the guidance tests for development consent planning obligations) for the references to Regulation 122 in Appendix 3, paragraphs 2, 8, and 22. The Applicant considers that the
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 8 17 February 2014
question of transportation improvements remains not relevant and not important.
2.2.12 The items listed by the PCC are as follows and addressed further below:
Improvements along the carriageway between Tiers Cross and the Robeston West junction.
New bus laybys and a crossing island at Meadow View.
Visibility improvements at Thornton Cross.
A Shared Use Path (SUP) from Tiers Cross to “Neeston Junction”
Signage and marking improvements.
Improvements between Tiers Cross and the Robeston West Junction
2.2.13 A Swept Path Analysis (SPA) has been undertaken along this length of highway. Two vehicle types have been shown:
Extendible Platform Vehicle with Casings (38.47m long and 2.60m wide) (1);
Truck and 20 Axle Trailer (42.141m long and 2.591m wide) (2)
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 9 17 February 2014
3 Applicant’s Response to Examining Authority’s Second Round of Written Questions and Requests for Information
3.1 Development Consent Order (DCO) (Q1.1 to 1.6)
3.1.1 Detailed below are the Applicant’s responses to Q1.1 to 1.6.
Q1.1 Please would the applicant consider and, as appropriate,
draft a requirement to be included in the DCO that the grid
connection for the power station should be by means of
underground cable.
Applicant’s
Response
Please see new requirement 22 in the attached draft of the DCO
Appendix 2 of this document.
The proposed requirement is:
22. — (1) The electricity cables required to export electricity from the Authorised Development to the Pembroke 400kV sub-station owned by National Grid Electricity Transmission plc (the “Grid Connection”) shall, subject to paragraph (2) below, comprise sub-surface cables and associated infrastructure on land and a crossing beneath the Milford Haven Waterway.
(2) Above ground elements of the Grid Connection may be required in limited circumstances including for example: structures required as part of the underground grid connection (such as tunnel head houses (if required) and other access points); electricity sub-stations; cabling and structures required to connect underground cables together and connect with above ground infrastructure (including termination points); cabling and structures required to cross features such as streams or ditches; cable racks or supports within the Order limits; cable pillar boxes; or any necessary temporary above ground works or cables required during the testing, repair and maintenance of the Grid Connection.
(3) Electricity shall not be exported from the Authorised Development to the Pembroke 400kV sub-station otherwise than by the Grid Connection.
Q1.2 Please would the applicant consider and, as appropriate,
draft a requirement in the DCO to ensure that the design
principles that would apply to the development of the CHP
plant would also apply to future development of carbon
capture and storage plant.
Applicant’s
Response
Please see new requirement 23 in the attached draft of the DCO
(Appendix 2).
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 10 17 February 2014
The proposed requirement is:
23. In the event the undertaker is required to implement the
CCS proposal (as defined in Article 14) then the undertaker shall,
subject to any applicable statutory obligations and consenting
requirements, seek to implement the CCS proposal, where
technically feasible and so far as is reasonably practicable, in
accordance with the principles set out in the design principles
statement.
Q1.3 Please would the applicant consider and, as appropriate,
draft a requirement in the DCO to ensure that the CHP plant
operates primarily in CHP mode.
Applicant’s
Response
Please see the amendment to article 6 in the attached draft of the
DCO (Appendix 2). The proposed amendment is:
“6.— (1) The undertaker is hereby authorised to operate the generating station comprised in the authorised development for the purpose of generating electricity and heat and which shall operate primarily as a combined heat and power plant.
(2) This article does not relieve the undertaker of any obligation to obtain any permit or licence under any other legislation that may be required from time to time to authorise the operation of a generating station.”
In addition the Applicant has included the suggested wording
from NRW in requirement 8 to satisfy its concerns regarding the
impact to the Haven. It was this concern from NRW that was the
reason for requesting assurance regarding operating modes and
we understand from discussions with NRW that the new
requirement 8 now satisfies their concerns. The new sub clause
in requirement 8 is:
“(4) The contribution of the process waste water discharge along
with the aerial emissions from the Authorised Development, in
combination with the process waste water discharges and
emissions from the South Hook LNG Terminal operating as
consented as at the date of this Order, must not increase overall
nitrate loads into the Pembrokeshire Marine SAC and must
ensure no adverse effect on the integrity of the Pembrokeshire
Marine SAC as a result of other contaminants emitted or
discharged by the Authorised Development.”
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 11 17 February 2014
Q1.4 The applicant has been in discussion with interested parties
on a number of other revisions to the application draft of the
DCO. These include (but are not limited to) provisions
relating to design and landscaping, lighting and noise. The
applicant has also proposed a number of amendments to
this version of the DCO in response to my question 5.6 of 30
October 2013.
Please will the applicant submit a revised DCO with
proposed changes from the application draft of the DCO
shown in track change mode. This should include changes
in response to my first round of questions. Please provide
explanations for proposed changes.
Applicant’s
Response
Please see the attached draft of the DCO (Appendix 2). The
draft DCO reflects comments received from the ExA in his first
and second rounds of written questions and reflects drafting that
has been discussed with NRW and PCNPA in response to the
specific drafting suggestions they raised in the PCNPA LIR and
the NRW response dated 20 November 2013. Reasons for the
proposed changes are given in comments attached to the draft.
The Applicant is confident that there are no outstanding issues of
major concern following its discussions to date, and it will
continue to discuss and refine the detailed terms of the DCO with
PNCPA, PCC and NRW. The Applicant intends to circulate a
further draft of the draft DCO by the end of February 2014 that
will indicate where these authorities are in agreement with the
proposed text and highlight if agreement on any particular text
remains outstanding.
Q1.5 If changes to the draft DCO are linked to changes in
supporting documents that are referred to but not included
in the DCO, the applicant should provide revised versions of
those documents with changes show in track change mode.
Applicant’s
Response
Please also find attached an amended draft of the Design
Principles Statement (Document 1.22) (Appendix 3 to this
document) following discussions with PCNPA and PCC and
reflecting drafting proposals submitted by these authorities.
Please also find attached a new document to reflect the progress
in landscape discussions that have taken place between PCNPA,
PCC and NRW. This is the draft landscaping plan (Document
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 12 17 February 2014
2.13) (Appendix 4 to this document) that is now referred to in
requirement 6.
Please also find attached in Appendix 5 the amended Works Plan
A (Document 1.10A), Works Plan B (Document 1.10B) and
Section Drawing Plan (Document 1.9) reflecting drafting
amendments and proposed stack deviation requirements.
Q1.6 Please will Pembrokeshire Coast National Park Authority
(PCNPA), Pembrokeshire County Council (PCC), National
Resources Wales (NRW) and any other interested party
please set out any proposed changes to the DCO that have
not been agreed with the applicant.
Applicant’s
Response
Not applicable – please see however the response to Q1.4.
3.2 Questions arising from the applicants response to first round questions on DCO drafting
3.2.1 Detailed below is the Applicant’s response to Q1.7.1 to Q1.7.6 concerning further questions relating to the DCO drafting.
Q1.7.1 Noted. However, s156(2) provides that s156(1) (order has
effect for benefit of land) is subject to any contrary
provision in the order.
In the interests of clarity, should it be made clear that A7 is
without prejudice to operation of s156?
Applicant’s
Response
Agreed. Please see attached draft of the DCO (Appendix 2).
Q1.7.2 Is the reference to ‘lines’ necessary (and perhaps confusing)
as no lines are shown on Works plan A, only ‘situations’ for
the various numbered works?
Would wording such as the following be clearer: “Each
numbered work comprised in the authorised development
must be constructed within the correspondingly numbered
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 13 17 February 2014
area shown on the works plan (part A) and…”?
Applicant’s
Response
Agreed. Please see attached draft of the DCO (Appendix 2).
Q1.7.3 This question was intended to relate specifically to the
Electrical Sub-station referred to in A3(4), whereas the
response does not address this.
Table 4.1 of the Design Principles statement provides the
parameters of the sub-station as Height – 7m, Length 79m
and Width 47m. Rather than refer to another document
outside the DCO, is it not more straightforward to provide
these parameters in A3(4).
Applicant’s
Response
Agreed. Please see attached draft of the DCO (Appendix 2).
Please note that following feedback from engineering contractors,
the Applicant will (in consultation with PNCPA, PCC and NRW)
seek to adopt a limits of deviation approach for the stack (key
building 9) to allow a limited lateral movement along an east west
axis of up to 15 meters. This is reflected in the draft DCO and is
more particularly detailed in Document 2.14 (Appendix 6 to this
document). This limited flexibility in stack location will allow
greater potential for reducing the mass of the other key buildings
(namely the gas/steam turbine generator building and/or the heat
recovery steam generator building). The Applicant will notify the
public of this intended change and invite comments by way of a
newsletter which it intends to circulate shortly. As noted in
Document 2.14, the Applicant has considered the environmental
impact of the proposed variation in stack location and has
concluded that this will have no material effect on emissions from
the CHP Plant or on its visual impact.
Q1.7.4 Model provision 12 makes provision for a Schedule of
identified accesses to be made or improved, merely adding
the paragraph on which this DCO article is based as a
backstop provision.
Where no specific proposals are yet identified, would it be
clearer and more appropriate to require submission and
approval of details before such accesses are made or
improved?
Applicant’s The Applicant is of the view that the use of a schedule as referred
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 14 17 February 2014
Response to in model provision 12(a) was a mechanism to list those access
works for which no approval from the local planning authority was
required as they were sufficiently detailed to allow an Examining
Authority to assess them prior to the grant of the DCO. Where
such detail does not exist, model provision 12(b) allowed for a
more general right to conduct access works but subject to local
authority approval. As the applicant has not finalised its designs
to the extent it can provide a schedule to the ExA, it is only
seeking the more general right of approval as set out in
paragraph (b). As set out in article 9:
“The undertaker may, for the purposes of the authorised
development, with the approval of the relevant planning
authorities, form and lay out such means of access or improve
existing means of access, at such locations within the Order
limits as the undertaker reasonably requires for the purposes of
the authorised development.”
[Emphasis Added]
This Article follows model provision paragraph (b) save that it
does not refer to a highways authority as the order limits to do not
extend to any public highways. The Applicant therefore remains
of the view that sufficient control is given to the relevant planning
authority as provided for in the form of the model provision. If the
ExA disagrees with this view, the Applicant is willing to clarify
article 9 as follows:
“The undertaker may, for the purposes of the authorised
development, following submission of appropriate details to and
with the approval of the relevant planning authorities, form and
lay out such means of access or improve existing means of
access, at such locations within the Order limits as the
undertaker reasonably requires for the purposes of the
authorised development.”
Q1.7.5 In the Hinkley Point C DCO, the designated body was the
President of the Institute of Civil Engineers. In the King’s
Lynn B Connector DCO and Brechfa Forest DCO it was the
Secretary of State. Why does the applicant consider that the
International Chamber of Commerce would be in a position
to provide a suitably qualified arbitrator for this type of
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 15 17 February 2014
project?
Applicant’s
Response
Is the Examining Authority concerned by the use of the ICC
Rules as the mechanism by which any disputes are resolved, or
simply with the appointment of the arbitrator(s) by the ICC? The
Applicant sees no reason why the ICC would be unable to
appoint a suitably qualified arbitrator. The ICC is a well-
established neutral and independent non-governmental
organization with a strong reputation, and its selection reflects the
international nature of the Applicant’s business. Further details
are available by accessing the link below.
http://www.iccwbo.org/Products-and-Services/Arbitration-and-
ADR/Arbitration/Introduction-to-ICC-Arbitration/Ten-good-reasons-to-
choose-ICC-arbitration/
If it would help to address any concerns the Examining Authority
has, the Applicant would be willing to consider setting out a more
detailed mechanism for the appointment of the arbitrators in the
DCO by which the parties would appoint the tribunal (without
recourse to the ICC), and in the event that the tribunal could not
be agreed, or the parties failed to nominate an arbitrator within
the specified timeframe, the appointment could then be referred
to the ICC or another body such as the Institute of Civil
Engineers as the appointing body.
In response to concerns raised by PCNPA the Applicant is willing
for arbitration proceedings, if so requested, to be conducted with
simultaneous Welsh translation and for the award to be
translated into Welsh. This is reflected in the modification to
article 16, which relates to arbitration, in the attached draft of the
DCO.
Q1.7.6 Are the relevant planning authorities content that they will
be able to enforce any breach of this requirement as
proposed to be redrafted by the applicant?-?
Applicant’s
Response
No response required as directed at PCNPA and PCC
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 16 17 February 2014
3.3 Statements of Common Ground (SoCG) (Q2.1)
3.3.1 Statements of Common Ground between the Applicant and the PCNPA, PCC and NRW have already been submitted to the examining authority.
3.3.2 At present there are no amendments to those documents although final amendments may be submitted prior to the close of the examination as matters currently under discussion between the parties are further discussed and resolved.
3.3.3 However, as agreed at the ISH on 15th January 2014 an additional SoCG, specific to the Seascape, Landscape and Visual Impact of the proposal has been drafted and the latest draft of that Document 2.8 is attached in Appendix 7 of this document. Further drafts may emerge over the next few weeks which will be forwarded to the Examining Authority as necessary.
3.4 Habitats Regulation Assessment (Q3.1 to Q3.4)
3.4.1 Detailed below is the Applicant’s response to questions raised by the ExA on Habitats Regulation Assessment.
Q3.1 In the applicants extended summary of Habitats Regulation
Assessment (HRA) there are several references to
‘restoration and recovery aspirations’.
Please will the applicant provide a further description of
these aspirations and their relevance to the HRA.
Applicant’s
Response
This specific wording was recommended by NRW for the
extended HRA summary.
The relevance of this wording is that there are currently issues
within the Milford Haven catchment with regard to elevated levels
of nitrates and an overall aim to reduce the current levels which
would serve to benefit the surrounding environment, including the
designated sites and associated habitat and species features.
Many of the designated sites include conservation objectives
which make reference to nutrient levels remaining at or reducing
levels in order to maintain or restore environmental quality
conditions (e.g. water quality) in order to support species and
habitat features.
Thus, operation of the CHP Plant, as designed, in integrated
mode, will lead to a reduction of nitrogen inputs into the
catchment from aqueous and aerial emissions, in comparison to
the LNG Terminal alone, which will make a positive contribution
towards: a) the conservation objectives; and, therefore towards:
b) the recovery and restoration aspiration of improving current
nitrate levels in the catchment. This reduction has the potential to
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 17 17 February 2014
enhance the health of habitat and species features, which may
be adversely affected by the current levels present in the
catchment. It should be noted, however, that the maximum
consented emissions of N into the catchment from the LNG
Terminal alone (i.e. without the reduction provided by the CHP
Plant), are less than 1% of the total estimated input of N into the
catchment, and therefore the control of other sources would lead
to a greater reduction of N in the catchment and thereby also
contribute to recovery and restoration aspirations.
Q3.2 Please will NRW confirm that all relevant sites have been
considered in the HRA and if they agree that the correct
sites and features have been screened in and taken forward
to the integrity stage.
Applicant’s
Response
None required as directed to NRW.
Q3.3 In its response to my first round of questions NRW stated
that the Habitats Directive requires that any plan or project
likely to have a significant effect, either individually or in-
combination with other plans or projects, shall be subject to
an appropriate assessment. It subsequently stated that NRW
is required to look at the implications of the grid connection
and the CHP Plant together and that there is the potential for
adverse impacts on site integrity depending on the grid
connection option taken forward.
However, the applicant’s Extended HRA Summary
(submitted in response to the my first round of questions)
stated that there is no construction in the waterway for the
proposed CHP Plant, as such there will be no in-combination
effects with the trenched option.
Please can NRW clarify how they consider there to be in-
combination impacts arising from interactions of the grid
connection with the CHP plant (as opposed to the potential
subsequent effects of the grid connection which would be a
separate planning application)?
Applicant’s
Response
None required as directed to NRW.
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 18 17 February 2014
Q3.4 At the issue specific hearing and in its written summary of
its oral case dated 24 January NRW pointed out that in order
to complete his habitats assessment the Secretary of State
would need some degree of legal certainty about the
absence of adverse effects from water discharges from the
proposed development. This might be achieved through a
legal agreement with South Hook LNG and/or a variation in
the existing South Hook LNG environmental permit, neither
of which are available at present.
Please will the applicant comment on NRW’s view on the
requirements for certainty in carrying out the habitats
assessment and suggest how the Secretary of State’s
requirements could be met; if necessary by inclusion of a
provision in the DCO.
Applicant’s
Response
In the Applicant’s view, this point appears to have arisen
because, at this stage, the Environmental Permit has not been
determined and in NRW’s view, it cannot be certain that the CHP
Plant would operate as a CHP plant pending its determination of
the Permit application. The Applicant has worked hard with NRW
to ensure that NRW was provided with all the information it
required to enable it to provide its opinion on the HRA to inform
the ExA.
In order to address the point raised in oral evidence, the
Applicant has revised DCO requirement 8 in consultation with
NRW, which serves to provide NRW with the reassurance it is
seeking, in advance of its determination of the Environmental
Permit, that there will be no annual increase in nitrate emissions
to the Milford Haven Waterway, as a result of the CHP Plant (in
combination with the LNG Terminal), consistent with the
application.
The Applicant’s understanding is that NRW considers any
increase in nitrate emissions, no matter how small, to be at odds
with the conservation objective to reduce contaminant levels
when compared with the date at which the site was designated.
The Applicant considers that the approach adopted via
requirement 8 avoids the need to consider the degree of conflict
with the relevant objective and therefore the question of the
degree of increase in such emissions does not arise.
On this basis, the certainty that NRW was seeking is now
provided by requirement 8 and the point raised by NRW is now
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 19 17 February 2014
academic . Should the Examining Authority or the Secretary of
State disagree with the approach of the Applicant, the Applicant
further submits that the evidence submitted to inform the HRA is
contained within the Habitats Regulations Assessment Report
(Document 1.8), its extended summary and the updated
matrices. The Applicant understands that NRW agrees with the
HRA, together with the extended summary. Furthermore, by the
time the Secretary of State makes his decision, NRW will have
concluded its determination of the Environmental Permit
application.
NRW has orally indicated at the ISH that it would both seek to
conclude its initial considerations and have issued a draft
decision for consultation during the Examination Period and
before its conclusion and/or otherwise consider providing the ExA
with a ‘letter of no impediment’ during this Period. In the
Applicant’s view, whilst this may remain desirable in accordance
with the general requirement to work closely with the relevant
planning authority, it is now unnecessary, given the agreed
wording of requirement 8.
3.5 Other Information (Q4.1 to Q4.4)
3.5.1 Detailed below is the Applicant’s response to questions raised by the ExA on other information.
Q4.1 In its response to my first questions (question 1.4), the
applicant stated that “There is currently no government
guidance or policy that recommends or requires community
funding for a CHP generating station. Despite this, however,
the Applicant would point out that it intends to implement a
programme of community projects and engagement similar
to the schemes or activities adopted by other energy
companies in and around the Haven.”
Please will the applicant provide details of its proposed
programme of community projects and engagement.
Applicant’s
Response
The undertaker, South Hook CHP Limited, recognises its role as
a responsible corporate citizen and such a role is consistent with
that of other energy companies operating infrastructure along the
Haven.
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 20 17 February 2014
South Hook CHP Limited is engaged in discussions with the
Pembrokeshire Coast National Park Authority and
Pembrokeshire County Council, as well as with the neighbouring
community of Herbrandston, in providing support to community
projects that are consistent with the corporate values of the
project’s sponsors and the joint venture company itself.
Though no specific projects have been identified or agreed to, the
project’s sponsors have agreed to fund community benefits
projects that meet defined criteria. The level of funding during the
operational phase will be up to £200,000 per annum, but is
expected to vary year to year and will be determined via
benchmarking of other regional industry programmes.
It was intended to begin such a community benefits programme
on start-up of operations, but recognising the concerns of the
local community with regard to construction, South Hook CHP
Limited has extended its corporate social responsibility
programme and brought it forward to include the construction
phase of the project. Thus, as the planned construction period is
forecast to be 30 months, an additional £500,000 (£200,000 per
annum) is earmarked for application to community projects during
the construction phase, a portion of which will be secured by an
agreement with PCNPA and PCC.
It is expected that the construction phase funding will be applied
to support specific projects or programmes that provide
community, safety or environmental benefits or work to improve
community communication. South Hook CHP Limited has
requested suggestions of projects from PCNPA and PCC that it
can support in this regard.
The programme during the CHP Plant’s operational phase and its
parameters will be determined in consultation with the community
liaison group(s).
In aggregate, assuming a minimum operating life of 25 years, the
total potential contribution to community benefits from the project
is reasonably expected to approach £5,500,000, including the
construction phase. Any such commitments are dependent on
the project acquiring necessary consents, permits, and project
funding, and prevailing commercial conditions.
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 21 17 February 2014
Q4.2 At the issue specific hearing on 15 January 2014 there was
discussion about the availability of land at RWE Npower’s
Pembroke site which would be required for the proposed
grid connection.
Please will the applicant and RWE Npower, either separately
or in a SoCG, provide an update on their discussions on this
issue and give their latest view on the feasibility of the
proposed grid connection at the Pembroke sub-station.
Applicant’s
Response
RWE’s professional advisor’s comments at the ISH were noted.
In particular, the suggestion by them that RWE wished to
effectively place an embargo on making a connection across its
land to National Grid’s substation on the grounds that this
(combined with proposals from other generators in the area)
would unduly interfere with its requirement to reserve land for the
potential future instalment of carbon capture equipment. The
land that RWE has decided to reserve for such carbon capture is
currently expressed to be its entire land holding and effectively
encircles the substation (the only grid access point for this part of
Wales) However, the history of the current relationship set out
below demonstrates the actual feasibility of such a connection.
South Hook CHP Limited initially met with RWE on 18 December
2012 to discuss the project and options available in routing the
project’s grid connection through RWE’s land to National Grid’s
Pembroke Sub-station.
Subsequent to this meeting, South Hook CHP Limited identified a
preferred grid connection corridor within RWE’s land ownership
to facilitate the connection to Pembroke Sub-station. This
preferred connection corridor was presented to RWE at a
meeting on 14 August 2013, where initial discussions were also
held regarding the possible structure of any future land
agreement.
RWE also conveyed at the August 2013 meeting their intention to
co-ordinate the routings of all other grid connections to the
Pembroke Sub-station, to minimise disruption to their on-going
and future operations and to ensure that no connection was
prevented by virtue of the routing adopted for another. At no point
did RWE convey that it would need to embargo routing by the
Applicant or those other third parties. Rather, the opposite. RWE
appeared to be proactively facilitating grid connections and was
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 22 17 February 2014
keen to properly plan and aggregate a connection route within a
single corridor.
Subsequent to the meeting, South Hook CHP Limited has, in
close coordination with RWE's Estates Department and
management on site, undertaken extensive ecological surveys
along the preferred corridor boundary and surrounding area,
including habitat surveys; bat surveys; dormouse surveys;
breeding bird surveys; wintering bird surveys; otter surveys;
water vole surveys; badger surveys; and invertebrate surveys.
Topographic surveys and ground penetrating radar surveys have
also been undertaken along the preferred corridor boundary and
surrounding area.
Actual access to RWE’s land to facilitate these surveys has been
granted by RWE under an access licence obtained on a monthly
basis from RWE’s estates department. The access licence
ensures that RWE is fully aware when and where third parties are
on their land. The application for an access licence included risk
assessments and method statements for each activity being
undertaken, and a plan identifying the areas to be surveyed (in
this case, identifying the survey which encompasses the
preferred grid connection corridor).
The surveys undertaken to date demonstrate that the preferred
grid connection corridor will be environmentally acceptable and is
technically both viable and feasible.
South Hook CHP Limited and RWE are currently finalising a
confidentiality agreement which will facilitate further discussions
on the grid connection corridor and the structure of a future land
agreement.
As noted within the confidentiality agreement, South Hook CHP
Limited and RWE wish to enter into discussions concerning the
granting of necessary consents (i.e. land agreement) for the
SHCHP Project’s grid connection with the objective of ensuring
that all parties holding a connection agreement to Pembroke
Sub-station can develop a connection, and confirming that
RWE’s ability to develop any future CCR plant is not
compromised by South Hook CHP Limited's corridor.
As required by Pembroke Power Station’s Section 36 consent,
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 23 17 February 2014
RWE must retain a defined area to allow for the future installation
of CCR plant (and RWE has decided to set aside the land shown
by the blue dashed line in Figure 1, Appendix 8 to this
document).
RWE’s requirement to maintain the ability to develop future CCR
plant has been highlighted by RWE throughout our discussions,
and has been taken into account by South Hook CHP Limited
when developing the preferred grid connection corridor.
Rather than access the Pembroke Sub-station from the northern
coastline and route through open areas marked as reserved for
future CCR plant installation, the preferred South Hook CHP
Limited grid connection (shown in yellow on Figure 1, Appendix
8) is routed to the south of Pembroke Sub-station through RWE’s
land which, in the main, is not reserved for future carbon capture
or could not be used for a future CCR plant. As Figure 1 shows,
most of the cable corridor does not enter the CCR area which is
an important point, but where it does, this area would not be
suitable.
Furthermore, where the preferred South Hook CHP Limited grid
connection enters RWE’s land marked as reserved for future
CCR plant installation, it does so along an already highly
congested services corridor which includes two National Grid
400kV double circuit overhead lines from Pembroke Sub-station
and a number of Western Power Distribution (WPD) 132kV
overhead and underground lines from the WPD 132kV substation
(as shown on Figure 1, as above). South Hook CHP Limited
therefore considers this area to be unsuitable for RWE’s future
CCR plant installation given the extensive number of utility
services within this small area.
The area marked as reserved for future CCR plant does not
actually require the sterilisation of that entire area from
development (indeed the existing Pembroke Sub-station and
existing Pembroke Power Station are located within the reserved
area). Rather the obligation exists on RWE to retain sufficient
capacity within the overall defined area to develop future CCR
plant.
Given that South Hook CHP Limited’s preferred grid connection
corridor enters RWE’s future CCR plant area along an existing
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 24 17 February 2014
utilities corridor, the defined area reserved for RWE’s CCR plant
would therefore not be compromised in any way by the South
Hook CHP Limited’s preferred grid connection route to Pembroke
Sub-station.
Therefore, the Applicant’s preferred grid connection remains
technically and actually feasible.
As stated in the applicant’s response to the Examining Authority’s
first questions, in addition to the continuing discussions on grid
connection routing described above, RWE has been a key
consultee throughout the pre-application period for the South
Hook CHP Plant and has received all consultation material
provided to all Section 47 consultees.
Q4.3 In relation to the carbon capture readiness (CCR)
assessment:
Please will the applicant provide comments on NRW’s
assessment of the feasibility of the CCR proposals.
Applicant’s
Response
The Applicant accepts the conclusions drawn by NRW that there
are ‘no foreseeable barriers’ to CC/CCR with regards to space, or
technical feasibility of CO2 capture.
We also understand that their advice does not extend to the
economic feasibility of the applicants assessment, or the
feasibility to transport captured CO2 to storage sites, which would
be the responsibility of the Department of Energy and Climate
Change.
Q4.4 Please will the applicant provide (as discussed at the issue
specific hearing) its assessment of the possible timing of a
requirement to implement carbon capture and storage.
Applicant’s
Response
The November 2009 Guidance Note (URN 09D/810) on CCR for
section 36 consents states:
“5. Many of the power stations consented and built from
now on could still be operating for at least the next 30
years, possibly into the 2040's and beyond. Given the
challenge of the UK’s 80% target for reduction of
greenhouse gases by 2050 as compared to 1990 levels, it
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 25 17 February 2014
is reasonable to assume such plants will need to fit carbon
abatement technology at some point in their lifetime. For
this reason, the Government decided that all new power
stations with electrical outputs at or over 300 MWe and of
a type covered by the LCPD should only be consented if
they can be considered CCR ready.”
No timing has been given as to what mandatory CCR and
storage (CCS) may be required however the matter was debated
in the context of the Emissions Performance Standard (EPS)
contained in sections 57 to 61 of the Energy Act 2013 and as
considered in a specific Energy Act Policy Brief . The Energy Act
imposes an EPS of 450g/kWh at baseload that makes CCS
effectively mandatory for new coal powered generation.
The Government has, however, introduced a grandfathering
policy to reassure investors in the energy sector that new build
power stations will not be subject to retrospective changes in the
EPS.
As stated in the Policy Brief:
“The EPS is set at a level that will not impact on the new
gas generation capacity needed to replace older, retiring
capacity as we make the transition to a low carbon
electricity system. ‘Grandfathering’2 the level until 2045,
will provide long-term regulatory certainty to investors in
new gas generation. 2’Grandfathering’ is a term used to describe a new
feature of the EPS that provides a guarantee to
developers that the EPS limit under which a new fossil-
fuel power plant is consented will be maintained for that
plant until end of 2044.”
As noted in Section 57(2) of the Energy Act 2013:
“Until (and including) 2044, the statutory rate of emissions
is 450 g/kWh.”
The fine detail of the EPS is to be resolved in regulations to be
made under the Energy Act 2013. Section 57(8) states:
“Provision that may be made by virtue of subsection (7)(d)
includes provision for treating emissions attributable to the
supply of heat to customers from combined heat and
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 26 17 February 2014
power plant as not being attributable to the use of fossil
fuel.”
As the anticipated rate of emissions for the natural gas fuelled
CHP Plant will be 300 g/kWh when operating in conventional
power mode, and lower still when operating in CHP mode, we
therefore do not anticipate the South Hook CHP Plant to be at
risk of exceeding the EPS limits it will benefit from the
grandfathering policy under the Energy Act 2013.
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 27 17 February 2014
APPENDIX 1
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 28 17 February 2014
APPENDIX 2
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 29 17 February 2014
APPENDIX 3
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 30 17 February 2014
APPENDIX 4
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 31 17 February 2014
APPENDIX 5
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 32 17 February 2014
APPENDIX 6
South Hook CHP Applicant’s Response to ExA 2nd Questions Document 2.12 33 17 February 2014
APPENDIX 7