South End Rock Tunnel Update€¦ · zTender Review Greg Clausen zFinancial Cheryl Mahaffy...
Transcript of South End Rock Tunnel Update€¦ · zTender Review Greg Clausen zFinancial Cheryl Mahaffy...
Introduction Alan Stephen
Background Greg Clausen
Technical Information Shawn Scott
Tender Review Greg Clausen
Financial Cheryl Mahaffy
Recommendation of Award of Tender Alan Stephen
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
CONTENTS:
Slide 2 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Dennis Consultants (A Division of R.V. Anderson Associates Ltd.)
Shawn Scott, P. Eng.Project Manager
Alex Sorensen, C.E.T.Design Manager
Armand Therrien, C.E.T.Project Director
Slide 3 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
CITY STAFF
Cheryl MahaffyManager of Financial Planning and Policy
Al Sweetman, P. Eng.Water and Wastewater Engineer
Greg Clausen, P. Eng.City Engineer
Slide 4 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
BACKGROUND:Summary of three earlier reports to Council
November 29, 2001April 16, 2003February 16, 2005
By late 1990’s, sanitary sewer system had exceeded it’s capacity
Class Environmental Assessment initiated in 2000Four Alternatives Considered:
1) Upgrade Existing System2) Expand Existing System3) Rock Tunnel Collector4) Do Nothing
November 29, 2001, Council approved the preferred Alternative No. 3, Rock Tunnel Collector, subject to securing funding
Slide 5 of 26
Existing TunnelProposed Tunnel
Existing and Proposed Rock Tunnel SystemExisting and Proposed Rock Tunnel System
Slide 6 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
2001 – 2003, $8.4 million Provincial funding secured
April 16, 2003, Council Approved Rock Tunnel Project with recommended funding formula
If the project had not been approved, all new development would have been immediately frozen and all existing approved projects retroactively rescinded where legally possible
Slide 7 of 26
Nepahwin Lake
Regent Street
Paris
Stre
et
South End Tunnel
Three main components
Access ShaftsDrop Shafts
Tunnel Segments
Slide 8 of 26
Nepahwin Lake
Regent Street
Paris
Stre
et
- Lo-Ellen Tunnel: 1.42km
Lo-Ellen Tunnel
Walford Tunnel
- Walford Tunnel: 0.51km
Tunnel Segments
Green Tunnel
- Green Tunnel: 2.39km
- Main Tunnel to Burwash: 1.97km
Main SE Tunnel
Existing Tunnel
- Paris Tunnel: 0.18km
Paris Tunnel
Slide 9 of 26
Nepahwin Lake
Regent Street
Paris
Stre
et
Access Shafts/Drop Shafts
Lo-Ellen Tunnel
Walford Tunnel
Green Tunnel
Main SE Tunnel
Existing Tunnel
Paris Tunnel
Sewage Drop Shafts
Access Shafts
Burwash DS
Stewart DS
Service Road DS
Algonquin DS
Walford DS
Paris DS
Oriole DS
Access Road DS
Green DS
Three Access Shafts:
YALE SHAFT
Yale
BURWASH SHAFT
Burwash
GREEN SHAFT
GreenNine Drop Shafts:
Walford, Paris, Oriole, Stewart, Service, Burwash, Algonquin, Access, and Green.
Existing Shaft
Sustainable - sections of the existing tunnel are 40 plus years oldTotal length of the South End Tunnel - 6.5 kmAverage depth below ground - 25 meters (75 feet)Tunnel dimensions - 1.5m (5’) wide by 2.1m (7’) high ( minimum size based on current drill and blast tunneling technology)Access shafts dimensions- 3.0m (10’) by 3.5m (12’)Tunnel is lined with a concrete invert (improves flow and reduces build-up of solids in tunnel)Tunnel construction eliminates existing six sewage lift stations- Walford Lift Station- Paris Lift Station- Burwash Lift Station- Green Lift Station- Stewart Lift Station- Oriole Lift StationExcavated rock will be used to start construction of the Laurentian University Alternate Access RoadEstimated construction time: 3 Years
UNIQUE FEATURES:
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
TENDER PROCESS:
March 21, 2005, tenders called for the preferred Rock Tunnel Collector option
Tenders closed on May 3, 2005
Tenders only valid until July 2, 2005
2001 EA COST ESTIMATES WERE UPDATED TOINCLUDE:
1) 2005 Construction Prices for both Upgrade and Expansion Alternatives
2) Current Tender Results for Rock Tunnel AlternativeSlide 12 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Slide 13 of 26
The 2005 Cost Estimates are shown on same format as original 2001 EA Report
The 2001 EA Report included Total Costs for entire service area for both 20 year and 60 year periods for all three Alternatives, as follows:
Slide 14 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
ALTERNATIVES 20 YEAR TOTAL 60 YEAR TOTALUpgrading $46.3 M $81.4 MExpansion $45.4 M $77.0 MRock Tunnel $39.3 M $54.1 M
2005 COST ESTIMATES (EA Format)
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Slide 15 of 26
For comparative purposes, staff also created a combined option which included both Rock Tunnel and Conventional Construction methods
COMBINED Alternative 2005 Cost EstimateSection Tunnel Upgrade Expansion Combination Rock Tunnel and
Conventional Sewer System
Main Tunnel to Burwash $10.30 M $18.50 M $11.56 M Tunnel $14.70 M
Walford Road $ 3.55 M $ 1.35 M $ 1.44 M Conventional $ 2.43 M
Paris Street $ .83 M $ 1.60 M $ 1.60 M Tunnel $ 1.17 M
Lo Ellen $ 5.46 M $ 5.20 M $ 6.67 M Conventional $ 4.85 M
Green Avenue $ 8.90 M $ 7.14 M $ 8.08 M Conventional $ 7.13 M
Total Estimates $29.04 M $33.79 M $29.35 M Total Estimate $30.28 M (1)
Annual Operating and Maintenance Costs – Year 1
$ 10 K $ 255 K $ 340 K $ 210 K
Note (1) It should be noted that the project cannot be done piecemeal (i.e. Rock Tunnel for Main andParis Street and Conventional for balance) at the prices shown in the Rock Tunnel Option. Splitting the project between construction types increases the costs, as shown.
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
COST COMPARISON RESULTS:20 Year Total
7.1 Rock Tunnel Alternative $39.3 M5.2 Expansion Alternative $45.4 M
Combination Alternative $45.4 M5.1 Upgrade Alternative $46.3 M
The Rock Tunnel Collector Alternative is the least expensive alternative using both EA Costing Format and Combined Format
Slide 16 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Economic impact – both on existing businesses and new development
Public disruption during construction
Engineering fees for other alternatives
Additional EA study / fee studies for other alternatives
Re-tendering process and price increases
Future growth
Service life
OTHER FACTORS:Numerous other factors that make the Tunnel the preferred option:
Slide 17 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
EXPLANATION OF PROJECT PRICE INCREASE:
Slide 18 of 26
2005 Project Estimate $31.1 M2001 Project Estimate $22.7 MIncrease $ 8.4 M
Inflation (12.1%) (2001 – 2005) $2.53 MAdditional Engineering Design $0.50 MInsurance $1.00 MProperty Acquisition $0.50 MIncrease in Scope of Contract / Work $3.39 MAccess Road to University $0.34 MMiscellaneous $0.14 M
$ 8.4 M
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
ROCK TUNNEL TOTAL COSTS:$28,275,000 Recommended Contract
$ 3,200,000 Engineering
$ 500,000 Property Acquisition
$ 1,000,000 Construction Insurance (3 years)
$32,975,000
$ 1,900,000 Less GST Rebate
$31,075,000 Total Costs
FINANCIAL
Slide 19 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
PRESENT FUNDING:$14,248,300 CGS funding committed to project
$ 965,000 CGS funding for Marcel / Bouchard & Oriole Lift Stations
$ 8,400,000 Committed funding from Province
$23,613,300 Available Funding
Slide 20 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
FUNDING SHORTFALL:$31,075,000 Total Project Estimate
$23,613,300 Available Funding
$ 7,461,700 Funding Shortfall
Slide 21 of 26
PROPOSED ADDITIONAL FUNDING:$ 340,000 Culvert work to be funded from 2006 Roads
Envelope
$ 106,700 Sewer and Water Payments Reserve FundActually collected for Green Lift Improvements
$4,000,000 External Borrowing
$1,000,000 2006 Wastewater Envelope
$1,000,000 2007 Wastewater Envelope
$1,015,000 2008 Wastewater Envelope
$7,461,700
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Slide 22 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
EXTERNAL FINANCING:$4,000,000 External Borrowing
Annual repayments @ 6.5 % over 20 years = $363,000
Slide 23 of 26
POSSIBLE FUNDING SOURCES:
1) Fund totally from Capital Financing Reserve Fund- Wastewater (present balance $4.5 million)- Not recommended as reserve fund would be depleted
2) Implement a fee by-law under Section 391 of Municipal Act- Applied only to all new development benefiting from the project
continued
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Slide 24 of 26
POSSIBLE FUNDING SOURCES: (continued)
3) Undertake a Mini Development Charges Study to implement a development charge to partially fund this project.A development charge could be applied either city-wide or area specific.
4) Increase user fees (water / wastewater rates) to finance repayments
5) Possibly impose Local Improvement Charges
6) Federal Gas Tax ??
South End Rock Tunnel UpdateSouth End Rock Tunnel Update
Slide 25 of 26
South End Rock Tunnel UpdateSouth End Rock Tunnel UpdateRESOLUTION:THAT the tender for this Rock Tunnel Project be awarded to McNally Construction Inc. in the tendered amount of $28,274,558.78, which includes a reduction of $750,000 in the contingency allowance in the contract, being the lowest tender received meeting all terms and conditions of the tender, and,
THAT the total overall cost of the project, estimated to be $31.075 million, including engineering, property acquisition and construction insurance costs, and after the GST rebate, be funded as follows:
$14,248,300 Approved for this project$ 965,000 Approved for Marcel / Bouchard and Oriole Lift Stations Projects$ 8,400,000 Commitment from Province$23,613,300 Previously committed / approved funding
$ 340,000 Culvert work from the 2006 Roads Capital Envelope$ 106,700 From the Sewer and Water Payments Reserve Fund$ 4,000,000 External Borrowing$ 1,000,000 Additional contribution from the 2006 Waste Water Capital Envelope$ 1,000,000 From the 2007 Waste Water Capital Envelope$ 1,015,000 From the 2008 Waste Water Capital Envelope$31,075,000 and,
THAT staff be directed to come back with a report outlining financing options for the repayment of the loan in accordance with the report from the General Manager of Infrastructure and Emergency Services, dated June 8th, 2005.