SOLFEX CPC INOX & OEM Planning, Installation, Maintenance and ...

download SOLFEX CPC INOX & OEM Planning, Installation, Maintenance and ...

If you can't read please download the document

Transcript of SOLFEX CPC INOX & OEM Planning, Installation, Maintenance and ...

  • Evacuated tube collectors

    CPC 6 OEM / INOX

    CPC 12 OEM / INOX

    CPC 18 OEM / INOXWith aluminium / stainless steel installation systems

    Operating Guide

    Maintenance and

    Planning, Installation,

  • Table of contents

    Table of contents

    Collector technical data

    Standards and regulations

    Table of contents

    Design and connection of the pipework

    Sizing of the expansion tank

    Location and installation of the expansion tank

    Collector connection options

    2

    3

    4

    Page

    General safety instructions

    General collector information 5

    6-9

    10

    11-12

    13

    14

    Basic hydraulic and electrical layouts

    Delivery of the collector

    Installation on pitched roofs - Tile

    Installation on pitched roofs - Slate

    Installation on pitched roofs - Corrugated sheet

    Installation on flat roofs

    Installation on a facade / Vertical installation

    Installation on a facade / Angle frame installation

    Installing the collector

    Collector pipe work connections

    Commissioning the system - Filling

    Commissioning the system - Adjusting flow rates

    Collector maintenance and repair

    Collector component parts list

    17

    62

    Publication details

    2

    15-16

    18Installation on pitched roofs - Collector Space Requirements

    19-25

    26-32

    33-39

    45-44

    45-52

    53-56

    57

    58-59

    60-61

    Commissioning / Maintenance of the system / System Owner Information 63-64

    65Commissioning / Maintenance check list / Service Record

    66-68

    69

    70-73Tyfocor LS data sheet

    74

  • General safety instructions

    used to record routine servicing.

    This document must be left with the system upon completion and must be

    perform repairs or modifications to the system.

    Instruction must be given to the end-user that only a competent person can

    system must be provided to the end-user.

    Notification on the workings of the system and training on operation of the

    Customer handover

    used.

    In the case of any maintenance requirements, only original spare parts must be

    contract with a competent person.

    general up-keeping of the system

    It is the end-users responsibility for the arrangement of maintenance and

    System functionality checks

    collectors and mountings are securely fastened.

    Completion of the installation should be verified be checking that the

    Do not subject the collectors to any un-necessary loads at a single point or

    the warranty.

    Modification of any system components is strictly forbidden and will nullify

    Adhere to the installation instructions at all times.

    competent person.

    All aspects of installation, maintenance and servicing must be carried out by a

    System installation

    high temperatures that can be generated.

    Necessary care must be taken when working on the collector due to possible

    periods will become hot.

    Uncovered collectors and their components left exposed in sunlight for long

    Heat generated at the collector

    the danger of possible falling glass causing injury.

    Appropriate action must be taken to avoid installations in public areas due to

    Damaged vacuum tubes or flat plate collector glass poses the threat of injury.

    Take extra care when handling the solar collectors to prevent any damage.

    Working with glass

    regulations.

    Particular observation must be made to the current health and safety

    the possibilities of accidents occurring.

    prevention of falling.

    clothing must be worn, especially if there are no guards to aid in the

    Suitable safety equipment must be used and appropriate personal protective

    Whilst working on the roof, maximum prevention must be in place to avoid

    Safety Information

    bearing capacity. If in doubt then seek advice from a structural engineer.

    Working at heights

    over the whole surface area.

    Attention must be taken to ensure that the roof structure has sufficient load-

    It is a recommendation that the end user arranges a maintenance and servicing

    3

  • Standards and regulations

    water services (domestic scale)

    Code of practice for hot and cold

    on building sites.

    BS 8000-15: 1990: Workmanship

    design heat load

    Methods for calculation of the

    in buildings.

    BSEN 12831:2003: Heating systems

    effect on the quality of water

    consumption with regards to their

    water intended for human

    products for use in contact with

    BS 6920: Suitability of non-metallic

    (bespoke systems).

    system and their components

    ENV 12977: Thermal solar heating

    exceeding 70 kW.

    appliances of rated input not

    domestic purposes, using gas-fired

    installation of hot water supplies for

    BS5546: 2000 Specification for

    pool.

    swimming pools for swimming

    for solar heating systems for

    BS 6795:1986 Code of practice

    1998.

    equipment regulations (PUWER)

    Provision and uses of work

    Electricity at work regulations 1989.

    work regulations 1992.

    Personal protective equipment at

    Confined spaces regulations 1997.

    regulations (RIDDOR) 1995.

    or dangerous occurrences

    Reporting of injuries, diseases

    1999.

    Equipment Regulations (LOLER)

    The Lifting Operations and Lifting

    Regulations 1992.

    Manual Handling Operations

    domestic hot water.

    installation of DSHW systems for

    BS5918: A code of practice for the

    2007.

    Management) Regulation (CDM)

    Construction (Design and

    buildings and their curtilages.

    water for domestic use within

    maintenance, of servicing supplying

    design, installation, testing and

    BS6700: 2006 Specification for

    1999.

    The pressure equipment regulations

    health regulations (COSHH) 1994.

    Control of substances hazardous to

    (prefabricated systems).

    system and their components

    EN 12976: Thermal solar heating

    2005.

    The Work at Height Regulations

    1974.

    The Health and Safety at Work Act

    4

  • Carefully read through these installation instructions. Failure to follow these instructions will void any

    manufacturers or legal guarantee claims.

    completely pre-assembled in a collector module:

    Evacuated tubes

    CPC reflector

    Manifold with heat transfer units

    The incident solar radiation is reflected by the CPC reflector onto the absorber surface of the evacuated tubes

    where it is converted into heat. The high vacuum in the tubes combined with the highly selective coating on the

    absorber prevents the heat from escaping into the environment. The heat is transported away from the collector

    using a suitable heat transfer medium and by means of so-called heat exchangers inside the vacuum tubes and

    the tube register connected to them.

    2

    Deviations of 25% are permissible.

    Storage tank capacity: approx. 80 l per m2 collector area for domestic water heating

    and/or partial solar heating.

    expansion tank.

    The type plate is attached to the collector manifold. It contains all the important manufacturer's data in the form

    of symbols. The following table gives the meaning of the individual symbols.

    Symbol Meaning Explanation

    A g area gross gross area

    Vf volume fluid Collector content

    m mass weight

    stg temperature stagnation stagnation temperature, max.

    pmax pressure maximum Operating overpressure, max. permissible

    yprod year production production year

    The CPC OEM/INOX evacuated tube collector consists of 3 main components, which are

    The CPC OEM/INOX and may be used solely for water heating as well as in partial solar heating applications.

    The CPC OEM/INOX should only be used in conjunction with suitable solar controllers and only in

    completely safe and sealed solar heating systems that are fitted with a suitable and sufficiently sized membrane

    General Information

    Structure and function of CPC OEM/INOX

    Applications and design of CPC OEM/INOX

    General collector Information

    Notes on the type plate

    225 litres of storage volume per m of collector area.

    Solar simulation software is recommended for the correct sizing of each individual project.

    l x w length x width length x width

    Further guidance can be found within the Domestic Heating Compiance Guide which stipulates a minimum of

    2

    2

    Aperture surface for domestic water heating = 1 [m ] of apeture area per person + 1 [m ]

    Aperture surface for partial solar heating = 2 [m ] of apeture area per person + 1 [m ]2

    5

  • Number of evacuated tubes 6 12 18

    0 (aperture), DIN 4757-4 or EN 12975 % 64.2 64.2 64.2

    c1 with wind, in relation to aperture W/(m2k) 0.89 0.89 0.89

    c2 with wind, in relation to aperture W/(m2k2) 0.001 0.001 0.001

    K ,trans (50), in relation to aperture 1 1 1

    K ,long (50), in relation to aperture 0.9 0.9 0.9

    Yield forecast kWh/m2a 589 589 589

    Grid dimensions

    (length x height x depth) m 0.70 x 1.64 x 0.1 1.39 x 1.64 x 0.1 2.08 x 1.64 x 0.1

    Gross surface area m2 1.14 2.28 3.41

    Aperture area m2 1.0 2.0 3.0

    Collector contents - OEM I 0.8 1.6 2.4

    Collector contents - INOX I 0.9 1.8 2.6

    Weight - OEM kg 19 37 54

    Weight - INOX kg 19 35 52

    Max. permitted operating overpressure bar 10 10 10

    Max. stagnation temperature C 272 272 272

    Connection width, flow/return mm 15 15 15

    Collector material - OEM Al / Cu / glass / silicone / PBT / EPDM / TE

    Collector material - INOX Al / stainless steel / glass / silicone / PBT / EPDM / TE

    Glass tube material borosilicate glass 3.3

    Selective absorber coating material aluminium nitrite

    Glass tube,

    ( ext./ int./wall thickn./tube lgth.) mm 47/37/1.6/1500

    OEM colour

    (aluminium frame profile, anodised) aluminium grey

    INOX colour

    (aluminium frame profile, powder-coated) RAL 7015

    Colour (plastic parts) black

    Heat transfer medium Tyfocor LS

    Series CPC 6 OEM / INOX CPC 12 OEM / INOX CPC 18 OEM / INOX

    DIN CERTCO registration number 011-7S495-R

    Technical data

    Technical specifications for CPC 6/12/18 OEM / INOX

    Collector technical data

    Thermal shock test ITW test number 06COL513/3OEM08/1

    6

  • Pressure loss of the tube collectors CPC 6/12/18 OEM

    Heat transfer medium: Tyfocor LS; medium temperature medium: 40C

    Pressure loss of the tube collectors CPC 6/12/18 INOX

    Heat transfer medium: Tyfocor LS; medium temperature medium: 40C

    Flow rate [l/min]

    Pressure loss [mbar]

    0

    20

    40

    60

    80

    100

    120

    0 0,25 0,5 0,75 1 1,25 1,5 1,75 2 2,25 2,5 2,75 3 3,25 3,5 3,75 4 4,25 4,5 4,75 5

    CPC 18 OEM

    CPC 12 OEM

    CPC 6 OEM

    Flow rate [l/min]

    Pressure loss [mbar]

    0

    20

    40

    60

    80

    100

    120

    0 0,25 0,5 0,75 1 1,25 1,5 1,75 2 2,25 2,5 2,75 3 3,25 3,5 3,75 4 4,25 4,5 4,75 5

    CPC 18 INOX

    CPC 12 INOX

    CPC 6 INOX

    Pressure loss

    Collector technical data

    7

  • The collector output is calculated based on the collector efficiency ( ) depending on the strength of the

    irradiation (G*) and the aperture area per collector unit (A). It provides information on the thermal output of

    the collector at a specific irradiation strength. The following equation is used to calculate the collector output:

    with:

    If the difference between the collector temperature and the ambient temperature ( ) is zero,

    the collector has zero heat loss to the surrounding air and the efficiency is maximum;

    this is known as optical efficiency .

    Part of the solar irradiation (G*) which strikes the collectors is lost due to reflection and absorption.

    The optical efficiency takes these losses into consideration.

    When the collectors heat up, they dissipate heat to the surrounding area via conduction,

    radiation and convection. The heat transmission coefficient a1 and a2 incorporate these losses.

    The almost horizontal power curves mean that CPC collectors generate high outputs even at great temperature

    differences between the collector temperature and the ambient temperature, in contrast to flat plate collectors.

    Power curve of the CPC 6 /12 /18 OEM / INOX tube collectors

    at an irradiation G* of 1000 W/m2

    Power output per collector unit[W

    ]

    Power curve (G* = 1000 W/m )

    0

    500

    1.000

    1.500

    2.000

    2.500

    3.000

    0 20 40 60 80 100

    CPC 18 INOX

    CPC 12 INOX

    CPC 6 INOX

    ][ K)(am

    Heat output

    Collector technical data

    8

  • In general, less solar irradiation is available for use as solar energy (for water heating and heating support) in the

    six winter months and in transitional periods (e.g. 400 W/m2). The temperature differences between the collector

    temperature and the ambient temperature are also very high due to the low temperatures outside.

    The following tables (source: ITW test report number 06COL513) give an exact overview of how the collector

    output changes depending on the radiation strength and temperature difference. The values specified are for

    vertical irradiation.

    Power output per collector unit [W] for CPC 6 OEM / INOX

    Irradiance

    400 W/m2 700 W/m2 1000 W/m2

    0 257 449 642

    10 248 440 633

    30 229 422 615

    50 210 403 595

    Power output per collector unit [W] for CPC 12 OEM / INOX

    Irradiance

    400 W/m2 700 W/m2 1000 W/m2

    0 514 899 1284

    10 496 881 1266

    30 459 844 1229

    50 420 805 1191

    Power output per collector unit [W] for CPC 18 OEM / INOX

    Irradiance

    400 W/m2 700 W/m2 1000 W/m2

    0 768 1344 1920

    10 741 1317 1893

    30 686 1262 1838

    50 628 1204 1780

    Collector technical data

    9

  • An average throughput of 30 40 l/h per m2 of aperture area (approx. 0.5 0.7 l/min per m2) can be assumed

    when selecting the piping dimensions. We recommend low-flow operation for large-scale solar energy systems,

    as the specific flow rate can be reduced to 12 18 l/h m2 (approx. 0.2 0.3 l/min per m2). In order to keep piping

    work to a minimum, we recommend that you connect max. 9.0 m2 (high-flow) and 15 m2 (low-flow) of collector

    aperture area in series. In order to minimise the pressure loss due to the solar energy system piping, the flow

    speed in the copper piping should not exceed 1 m/s. We recommend flow speeds of between 0.3 and 0.5 m/s.

    The cross sections should be dimensioned in accordance with throughput and speed as in a standard heating

    system. We recommend that you use standard copper piping and gunmetal fittings when installing the collectors.

    The connection points of the pipes should be brazed or connected using olive connections due to the high

    stagnation temperatures. No galvanised pipes, galvanised fittings or graphite seals may be used. Hemp may

    only be used in conjunction with pressure and temperature resistant sealant. The components used must be

    resistant to the heat transfer medium. The thermal insulation of pipes outdoors must be temperature and UV

    Guidelines for selecting pipe diameter dimensions

    High-flow

    Aperture area m2 2 3 4 5 6 7 8 9

    Flow rate litres/min 1.5 2.5 3 3.5 3.5 4 4 4.5

    Low-flow

    Aperture area m2 5 6 7 8 9 10 11 12

    Flow rate litres/min 1.5 1.5 1.5 2 2 2.5 2.5 2.5

    Aperture area m2 13 14 15

    Flow rate litres/min 3 3 3.5

    The pipe diameter dimensions refer to a max. total pipe length of 2 x 20 m of copper piping and an average

    pressure loss of the heat exchanger in the storage tank.

    The values are reference values which must be determined precisely on a case-by-case basis.

    For series connection of CPC 6/12/18 OEM / INOX collectors and a pump with a head height of max. 6 m.

    radiation-resistant and resistant to bird damage. Under no circumstances can plastic pipe work or fittings be

    installed within the solar system.

    Design and connection of the pipe work

    Design and connection of the pipework

    (ID)

    (ID)

    (ID)

    Copper pipe dimensions 12mm 12mm 12mm 12mm 15mm 15mm 15mm 18mm

    Copper pipe dimensions 12mm 12mm 12mm 12mm 15mm 15mm 15mm 18mm

    Copper pipe dimensions 12mm 12mm 15mm

    10

  • Calculation basis for determining the expansion tank size

    The formulae specified below assume that a 6 bar safety valve is used. For precise calculation of the expansion

    tank volume, the content volumes of the following system components must first be determined, in order to

    then calculate the tank volume using the formula below.

    Formula: Vnom ( Vsystem 0.1 + Vvapour 1.25 ) 4.8

    Vnom = nominal volume of the expansion tank

    Vsystem = content of the entire solar circuit

    Vvapour = content of the collectors and pipes which are in the vapour zone

    Example: determining the individual volumes:

    Based on: 2 CPC 12 OEM / INOX collectors

    Pipework: Cu 15 mm, 2 x 15 m in length

    Static height H: 9 m

    Contents of the storage tank heat exchanger and the solar station: e.g. 6.4 l

    Pipelines in the vapour zone: 15 mm Cu pipes, 2 x 2 m

    The individual capacities of the system components can be ascertained from the respective data tables in

    the product description. The sizes of the standard Cu pipes and the contents of the CPC tube collectors are

    specified on the following page.

    Vsystem = Contents of: heat exchanger of the storage tank + pipelines + collectors

    = 6.4 l + 30 m 0.133 l/m + 2 1.6 l = 13.59 l

    Pipes above or at the same height as the collector manifold (or the lowest manifold if there are several collectors

    above each other) can be filled with vapour if the solar energy system comes to a standstill. Thus, the contents

    of the affected pipes and the collectors are included in the vapour volume Vvapour.

    Vvapour = 2 1.6 l + 4 m 0.133 l/m = 3.73 l

    (Contents of 2 x CPC 12 OEM / INOX + 4 m Cu 15 mm piping)

    Calculation of the expansion tank size:

    Vnom ( Vsystem 0.1 + Vvapour 1.25 ) 4.8

    Vnom (13.59 l 0.1 + 3.73 l 1.25 ) 4.8 = 28.90 l

    Selected expansion tank: 35 l

    Sizing the expansion tank

    Sizing the expansion tank

    All expansion tanks within SOLFEX Energy Systems Prestige Solar Thermal Packs are sized based

    on a pipe work length of a maximum 25m and pipe work diameter DN16.

    please refer to the below guidlines or consult the SOLFEX Energy Systems technical team.

    For systems requiring pipe work lengths greater than 25m or pipe work diameters greater than DN16,

    11

  • Required volume of solar fluid Vtot:

    Vtot = Vsystem + Vprimary = 13.59 l + 4.4 l = 17.99 l

    Result:

    35 l expansion tank is sufficient, initial pressure 2.5 bar, operating pressure 3.0 bar, solar fluid capacity 17.99 l.

    Static height H Primary content Initial pressure Operating pressure

    between the highest in expansion

    point of the system and tank in % of TV tanks

    expansion tank nominal volume

    5...10 m 12.5% 2.5 bar 3.0 bar

    10...15 m 11.0% 3.0 bar 3.5 bar

    15...20 m 10.0% 3.5 bar 4.0 bar

    Solar component contents

    Copper pipe

    Model Cu12 Cu15 Cu18 Cu22 Cu28

    Contents (l/m) 0.079 0.133 0.201 0.314 0.491

    Collectors

    H

    Sizing the expansion tank

    primary nomV = V 12.5% = 35 l 0.125 = 4.4 l

    The following applies at a static height of 9 m (see table on the following page):

    can be ascertained from the table below.

    The primary content, as a percentage of the selected tanks nominal volume, as well as pressure data,

    pressure and the operating pressure (depending on the static height H).

    The primary content in the expansion tank arises during filling of the solar energy system due to the initial

    tank must be added to the system volume.

    In order to determine the required volume of solar fluid, the primary content of the corresponding expansion

    Determining system contents, initial pressure and operating pressure:

    Contents (l) 0.8 1.6 2.4 0.9 1.8 2.6

    Model CPC 6 OEM CPC 12 OEM CPC 18 OEM CPC 6 INOX CPC 12 INOX CPC 18 INOX

    12

    2.0 bar0...5 m 14.0% 2.5 bar

  • Fig 1.

    connection port on the pump group.

    this product code you will also receive a female brass cap which will be used to blank off the original

    station (Fig 1 Dimension A), the pre-cooling vessel & expansion vessel will be connected at this position, within

    This product is a brass tee piece which is to be installed into the return line at least 300mm above the pump

    )*&+,(

    !

    !&'%(

    !"#!!$%

    Further Guidelines for pipe work layout.

    Location and installation of the expansion tank

    ES PrestigeSTP

    called a CPC expansion vessel connection port fitting pack, Product Code - CPC-EX-CPFP.

    13

  • Legend

    Corrugated hose return (cold)

    Corrugated hose flow (hot) with collector sensor

    Connection options for 1 collector

    Caution: Sensor is positioned on the flow side (hot).

    Connection options for 2 or more adjacent collectors

    Caution: Sensor is positioned on the flow side (hot).

    Reverse connection of the

    flow direction is possible.

    Connection options for 2 or more collectors

    above one another

    Caution: Sensor is positioned on the flow side.

    arrays, one shut-off ball valve

    and equalise the collector

    In order to facilitate bleeding

    Note!

    Connection options for 1 or 2 adjacent collectors

    and 2 or 3 collectors above one another

    Caution: Sensor is positioned on the flow side (hot).

    Connection options

    Collector connection options

    should be built into each outlet.

    SOLFEX product code: VAL-08-5378

    14

  • Example system for solar water heating

    Example system for solar water heating with heating support

    Basic hydraulic and electrical layout

    Basic hydraulic and electrical layout

    Please refer to other pages of this manual for system dimensioning and minimum

    pipework layout requirements.

    15

  • Basic hydraulic and electrical layout

    Basic hydraulic and electrical layout

    Please refer to other pages of this manual for system dimensioning and minimum

    pipework layout requirements.

    Example system for east / west solar water heating

    Example system for solar water heating with two stores

    16

  • Delivery of the collector

    Delivery of the collector

    sioning.

    the sun protection sheet after commis-

    commissioning impossible. Remove

    medium being vaporised, rendering

    sunlight. It prevents the heat transfer

    the solar energy system even in strong

    tates trouble-free commissioning of

    by a sun protection sheet. This facili-

    Upon delivery, the collector is covered

    a suitable sun protection tarpaulin must be applied.

    filled, however it must not be exposed to the weather for longer than 4 weeks. For longer periods,

    The sun protection sheet must be left on the collector until the collector has been flushed and

    Caution!

    that the hooks encompass the lower frame. Insert the upper mounting hook into the groove in the manifold, and

    allow the collector to slide downwards into the lower hooks. If necessary, lift the collector upwards slightly, so

    Carefully lift the collector (with packaging) over the installed lower mounting hooks. Open the packaging and

    with the help of leaning ladders or planks, which serve as slide ramps.

    prevent swinging or lateral tilting. In the absence of motor-powered aids, the collector is hoisted onto the roof

    able, an inclined hoist can be used. In either case, the collector must, in addition, be guided by ropes, which

    Transport onto the roof is made easier with a construction crane or mobile crane. If such a device is not avail-

    be inserted here. In so doing, it must be ensured that fastenings (knots) are secure.

    On the reverse side of the collector, strap loops are found above and below, left and right. Hooks or straps can

    collector. Attention is to be paid to the strength of the wind.

    The collector is transported onto the roof inside the packaging. This prevents damage to the reverse side of the

    Transporting the collector onto the roof

    Installing the collector

    screw tight onto the bearing rail using a raised torx head screw.

    Note!

    17

  • Dim. A

    Dim. B

    Dim. C

    corresponds to the roof overhang including the thickness of the end wall. The adjoining 0.30 m distance from the

    collector is required for hydraulic connection below the roof.

    Dim. D

    represents a minimum of 3 pan tile rows to the ridge. If this is not observed, there arises a risk of damage to the

    roof cladding at the ridge, especially on wet-laid pan tiles.

    B

    A

    D

    C

    C

    Number of adjacent collectors CPC OEM/INOX

    6 12 18

    (m) (m) (m)

    1 0.70 1.40 2.10

    2 1.40 2.80 4.20

    3 2.15 4.20 6.30

    4 2.85 5.60 8.35

    5 3.55 7.00 10.45

    6 4.25 8.40 12.55

    Number of collectors above one another CPC 6/12/18 OEM/INOX

    (m)

    1 1.64

    2 3.43

    3 5.22

    Installation on pitched roofs

    Installation on pitched roofs

    Space requirement for pitched roofs

    18

  • Installation on pitched roofs / roof tiles

    Pos. 1 Bearing rail, pre-assembled, aluminium, L = 1647 mm 2 3 2 2

    Not shown Bearing rail, pre-assembled,

    Pos. 1 Middle bearing rail, aluminium, L = 1507 mm 1

    Pos. 2 Retaining clamp for pan tile

    1-2 ventilation tiles depending on number of roof penetrations.

    Cordless electric screwdriver or cordless drill, angle grinder with stone disc, 5 mm Allen screwdriver bit,

    T 30 screwdriver bit, hammer.

    OEM/INOX

    List of parts for CPC 12 18 2x6 3x6

    Not shown Bearing rail, aluminium, L = 1355 mm 2

    aluminium, L = 2062 mm 2

    with raised cheese-head screw 4 6

    Pos. 7 Upper retaining hook 2 3 4 6

    Pos. 8 Lower retaining hook, pre-assembled 2 3 4 6

    Pos. 9 Wood screw 6x140 mm 12 18 12 18

    Not shown Slot nut, 20x30x10 4 6

    Pos. 3 Adjustable retaining clamp

    Pos. 6 Spacing board (height adjustment) 12 18 12 1

    Pan tile and plain tile roof cladding

    Component overview and delivery contents

    Necessary accessories

    Tool list

    Pos. 10 Raised torx head screw M8x20 2 3 8 12

    with raised torx head screw 4 6 4 6

    19

  • ca. 2,83 m

    0,8 - 1,2 m 0,8 - 1,2 m

    BA

    0,8 - 1,2 m

    1,4 - 1,9 m

    ca. 2,12 m

    BA

    For the installation of either 2 or 3 CPC 6 collectors, either 2 or 3 vertical bearing rails and 2 horizontal bearing

    rails are provided.

    2 bearing rails are used per collector when installing CPC 12/18 collectors.

    Install the retaining clamps on the rafters with spacing as shown in the diagram below.

    Positioning the retaining clamps for 2 adjacent CPC 6 collectors

    Positioning the retaining clamps for 3 CPC 6 or 1 CPC 6 and 1 CPC 12 arranged adjacently

    Positioning the retaining clamps for 4 adjacent CPC 6 collectors

    Installation on pitched roofs / roof tiles

    B

    A

    ca. 1,40 m

    0,8 - 1,2 m

    CPC 6/12/18 OEM/INOX

    Dim. A 1.64 m

    Dim. B approx. 1.0 m

    Positioning the retaining clamps

    20

  • Installation on pitched roofs / roof tiles

    Positioning the retaining clamps for 5 CPC 6 or 1 CPC 6 and 2 CPC 12 arranged adjacently

    Positioning the retaining clamps for 6 adjacent CPC 6 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 12 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 18 collectors

    0,8 - 1,2 m0,8 - 1,2 m0,8 - 1,2 m

    B

    ca. 4,24 m

    A

    2,08 m 2,08 m 2,08 m

    0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m

    BA

    ca. 1,39 m ca. 1,39 m ca. 1,39 m

    0,8 - 1,2 m 0,8 - 1,2 m 0,8 - 1,2 m

    BA

    BA

    0,8 - 1,2 m0,8 - 1,2 m0,8 - 1,2 m0,8 - 1,2 m

    ca. 3,53 m

    21

  • Installation on pitched roofs / roof tiles

    1. Locate the position of the

    rafters, and remove 2 - 3 pan

    tiles from one row for installation

    of the retaining clamps.

    Note!

    The retaining clamp

    must be positioned in

    the pan tiles trough.

    2. If necessary, insert the spacing

    boards underneath (pos.3) to fix

    the height of the retaining clamp

    (pos.2) so that it protrudes on

    the level of the pan tile beneath,

    and runs just above the pan tile

    in the trough, without resting on

    the pan tile.

    Note!

    In the area of the retain-

    ing clamps, the protrud-

    ing tile edges (pos.B)

    and profiles (pos.A) must

    be removed from the

    pan tiles.

    3. Position the retaining clamp and

    spacing board and screw tightly

    onto the rafter using the 6x140

    mm wood screws (pos. 1).

    4. Ensure that they are securely

    in place.

    5. Re-install the pan tiles.

    Additional installation step when

    height-adjustable retaining

    clamps are used:

    screw on the height-adjustable

    retaining clamp (pos.4). Adjust

    the level to that of the other

    retaining clamps by means of a

    taut line guide . This is achieved

    by moving the bracket up or

    down. Afterwards, fasten the

    more.

    B

    A

    Installing the retaining clamps or the height-adjustable retaining clamps for pan tiles

    Loosen the raised torx head

    raised torx head screw once

    22

  • Installation on pitched roofs / roof tiles

    Installation kit for 2 CPC 6 collectors

    screws (pos.1) for the retaining

    clamps through the elongated

    holes in the bearing rails (pos.2)

    and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment of

    the bearing rails with the use of

    a line guide.

    screws and check that they are

    securely fastened.

    4. Screw the horizontal bearing

    rails (pos.4) onto the vertical

    bearing rails (pos.6) with the

    (pos.5) and the slot nuts and

    fasten tightly.

    5. The lower retaining hooks

    (pos.7) are already pre-

    assembled.

    6. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    7. Ensure that they are securely

    in place.

    Installing the bearing rails and retaining hooks for the CPC 6 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    raised torx head screws

    raised torx head screw per

    23

  • Installation on pitched roofs / roof tiles

    1. Screw the horizontal bearing

    rails (pos.1) onto the vertical

    bearing rails (pos.4) with the

    (pos.2) and the slot nuts and

    fasten tightly.

    2. The lower retaining hooks

    (pos.5) are already pre-

    assembled.

    3. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    4. Ensure that they are securely

    in place.

    Installation kit for 3 CPC 6 collectors

    raised torx head screws

    raised torx head screw per

    24

  • Installation on pitched roofs / roof tiles

    screws (pos.1) for the retaining

    clamps through the elongated

    holes in the bearing rails (pos.2)

    and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment

    of the bearing rails with the

    use of a line guide.

    screws and check that they are

    securely fastened.

    4. Do not attach the upper retain-

    ing hooks (pos.3) until after the

    collectors have been installed.

    Installing the bearing rails and retaining hooks for the CPC 12 and CPC 18 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    25

  • Installation on pitched roofs / slate roofs

    Pos. 1 Bearing rail, pre-assembled, aluminium, L = 1647 mm 2 3 2 2

    Not shown Bearing rail, pre-assembled,

    Pos. 1 Middle bearing rail, aluminium, L = 1507 mm 1

    Make roof penetrations on site (e.g. using metal ventilation elements).

    Cordless electric screwdriver or cordless drill, 5 mm Allen screwdriver bit, T 30 screwdriver bit, hammer.

    OEM/INOX

    List of parts for CPC 12 18 2x6 3x6

    aluminium, L = 2062 mm 2

    Not shown Bearing rail, aluminium, L = 1355 mm 2

    Pos. 2 Slate roof retaining clamp 4 6 4 6

    Pos. 3 6x140 wood screw 12 18 12 18

    Pos. 4 Upper retaining hook 2 3 4 6

    Pos. 5 Lower retaining hook, pre-assembled 2 3 4 6

    Not shown Slot nut, 20x30x10 4 6

    Slate roof cladding

    Component overview and delivery contents

    Necessary accessories

    Tool list

    Pos. 6 Raised torx head screw M8x20 2 3 8 12

    26

  • Installation on pitched roofs / slate roofs

    For the installation of either 2 or 3 CPC 6 collectors, either 2 or 3 vertical bearing rails and 2 horizontal bearing

    rails are provided.

    2 bearing rails are used per collector when installing CPC 12/18 INOX collectors.

    Install the retaining clamps on the rafters with spacing as shown in the diagram below.

    Positioning the retaining clamps for 2 adjacent CPC 6 collectors

    Positioning the retaining clamps for 3 CPC 6 or 1 CPC 6 and 1 CPC 12 arranged adjacently

    Positioning the retaining clamps for 4 adjacent CPC 6 collectors

    ca. 1,40 m

    0,8 - 1,2 m

    A

    B

    ca. 2,12 m

    AB

    1,4 - 1,9 m

    0,8 -1,2 m

    ca. 2,83 m

    A

    0,8 - 1,2 m 0,8 - 1,2 m

    B

    CPC 6/12/18 OEM/INOX

    Dim. A 1.64 m

    Dim. B approx. 1.0 m

    Positioning the retaining clamps

    27

  • Installation on pitched roofs / slate roofs

    Positioning the retaining clamps for 5 CPC 6 or 1 CPC 6 and 2 CPC 12 arranged adjacently

    Positioning the retaining clamps for 6 adjacent CPC 6 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 12 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 18 collectors

    ca. 4,24 m

    A B

    1,4 - 1,9 m 1,4 - 1,9 m

    0,8 - 1,2 m0,8 - 1,2 m

    ca. 1,39 mca. 1,39 mca. 1,39 m

    0,8 - 1,2 m 0,8 - 1,2 m 0,8 - 1,2 m

    A B

    BA

    2,08 m 2,08 m 2,08 m

    0,7 - 1,0 m0,7 - 1,0 m0,7 - 1,0 m0,7 - 1,0 m0,7 - 1,0 m0,7 - 1,0 m

    ca. 3,52 m

    AB

    0,8 - 1,2 m

    1,4 - 1,9 m

    0,8 - 1,2 m

    28

  • Installation on pitched roofs / slate roofs

    1. Locate the position of the

    rafters. Remove slates from

    the area where the retaining

    clamps are to be installed.

    Ensure that each respective

    position is directly over a rafter.

    2. By screwing the wood screws

    (pos.2) through the boarding,

    screw each retaining clamp

    (pos.1) onto the rafter which lies

    beneath. If necessary , use a

    metal underlay (not provided).

    3. Replace the removed slates,

    ensuring that they overlap

    sufficiently. To this end, it may

    be necessary to use a slate

    repair kit (not provided).

    Installing the retaining clamps

    29

  • Installation on pitched roofs / slate roofs

    screws (pos.1) for the retaining

    clamps through the elongated

    holes in the bearing rails (pos.2)

    and tighten slightly.

    In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal.

    2. Assess the alignment of the

    bearing rails with the use of

    a line guide.

    screws and check that they are

    securely fastened.

    4. Screw the horizontal bearing

    rails (pos.4) onto the vertical

    bearing rails (pos.6) with the

    (pos.5) and the slot nuts and

    fasten tightly.

    5. The lower retaining hooks

    (pos.7) are already pre-

    assembled.

    6. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    7. Ensure that they are securely

    in place.

    Installation kit for 2 CPC 6 collectors

    Installing the bearing rails and retaining hooks for the CPC 6 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    raised torx head screws

    raised torx head screw per

    30

  • Installation on pitched roofs / slate roofs

    1. Screw the horizontal bearing

    rails (pos.1) onto the vertical

    bearing rails (pos.4) with the

    (pos.2) and the slot nuts and

    fasten tightly.

    2. The lower retaining hooks

    (pos.5) are already pre-

    assembled.

    3. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    4. Ensure that they are securely

    in place.

    Installation kit for 3 CPC 6 collectors

    raised torx head screws

    raised torx head screw per

    31

  • Installation on pitched roofs / slate roofs

    screws (pos.1) for the retaining

    clamps through the elongated

    holes in the bearing rails (pos.2)

    and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment

    of the bearing rails with the use

    of a line guide.

    screws and check that they are

    securely fastened.

    4. Do not attach the upper retain-

    ing hooks (pos.3) until after the

    collectors have been installed.

    Installing the bearing rails and retaining hooks for the CPC 12 and CPC 18 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    32

  • Pos. 1 Bearing rail, pre-assembled, aluminium, L = 1647 mm 2 3 2 2

    Not shown Bearing rail, pre-assembled,

    Pos. 1 Middle bearing rail, aluminium, L = 1507 mm 1

    1-2 ventilation plates depending on number of roof penetrations.

    Dust mask, cordless electrical screwdriver or cordless drill, 16 mm bit for fibre cement, 17 mm spanner set,

    SWS Allen screwdriver bit.

    Not shown Bearing rail, aluminium, L = 1355 mm 2

    aluminium, L = 2062 mm 2

    Pos. 3 Seal washer 4 6 4 6

    Pos. 4 Upper retaining hook 2 3 4 6

    Pos. 5 Lower retaining hook, pre-assembled 2 3 4 6

    Not shown Slot nut, 20x30x10 4 6

    List of parts for CPC 12 18 2x6 3x6

    OEM/INOX

    Installation on pitched roofs / hanger bolts

    Corrugated roof cladding

    Component overview and delivery contents

    Necessary accessories

    Tool list

    Pos. 6 Raised torx head screw M8x20 2 3 8 12

    Pos. 2 Hanger bolt with raised torx head screw 4 6 4 6

    33

  • For the installation of either 2 or 3 CPC 6 collectors, either 2 or 3 vertical bearing rails and 2 horizontal bearing

    rails are provided.

    2 bearing rails are used per collector when installing CPC 12/18 collectors.

    Install the hanger bolts on the rafters with spacing as shown in the diagram below.

    Positioning the hanger bolts for 2 adjacent CPC 6 collectors

    Positioning the hanger bolts for 3 CPC 6 or

    1 CPC 6 and 1 CPC 12 arranged adjacently

    Positioning the hanger bolts for 4 adjacent CPC 6 collectors

    0,8 - 1,2 m0,8 - 1,2 m

    ca. 2,83 m

    BA

    ca. 2,12 m

    0,8 - 1,2 m

    1,4 - 1,9 m

    BA

    ca. 1,40 m

    0,8 - 1,2 m

    BA

    CPC 6/12/18 OEM/INOX

    Dim. A 1.64 m

    Dim. B approx. 1.0 m

    Installation on pitched roofs / hanger bolts

    Positioning the hanger bolts

    34

  • Positioning the hanger bolts for 5 CPC 6 or

    1 CPC 6 and 2 CPC 12 arranged adjacently

    Positioning the hanger bolts for 6 adjacent CPC 6 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 12 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 18 collectors

    ca. 4,24 m

    0,8 - 1,2 m

    1,4 - 1,9 m

    0,8 - 1,2 m

    1,4 - 1,9 m

    BA

    ca. 1,39 m ca. 1,39 m ca. 1,39 m

    0,8 - 1,2 m 0,8 - 1,2 m 0,8 - 1,2 m

    BA

    2,08 m 2,08 m 2,08 m

    0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m

    BA

    ca. 3,53 m

    0,8 - 1,2 m 0,8 - 1,2 m

    1,4 - 1,9 m

    BA

    Installation on pitched roofs / hanger bolts

    35

  • 1. Locate the position of the

    rafters. If the rafter width is

    less than 60 mm, an auxiliary

    rafter must be added.

    2. Drill through the corrugated

    sheet with a 16 mm drill bit,

    and through the rafter with a

    13 mm drill bit.

    3. Screw the hanger bolt (pos. 1)

    at least 80 mm deep into the

    rafter, but far enough so that the

    black EPDM rubber seal ring

    (pos.2) lies flat and compressed

    between the ridge of the corru-

    gated sheet, and the welded

    washer on the hanger bolt

    (pos.3). The drilled holes in the

    corrugated sheet must be com-

    pletely sealed.

    Installation on pitched roofs / hanger bolts

    Installing the hanger bolts

    36

  • screws (pos.1) for the hanger

    bolts through the elongated

    holes in the bearing rails (pos.2)

    and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment of

    the bearing rails with the use of

    a line guide.

    screws and check that they are

    securely fastened.

    4. Screw the horizontal bearing

    rails (pos.4) onto the vertical

    bearing rails (pos.6) with the

    (pos.5) and the slot nuts and

    fasten tightly.

    5. The lower retaining hooks

    (pos.7) are already pre-

    assembled.

    6. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    7. Ensure that they are securely

    in place.

    Installation kit for 2 CPC 6 collectors

    Installation on pitched roofs / hanger bolts

    Installing the bearing rails and retaining hooks for the CPC 6 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    raised torx head screws

    raised torx head screw per

    37

  • 1. Screw the horizontal bearing

    rails (pos.1) onto the vertical

    bearing rails (pos.4) with the

    (pos.2) and the slot nuts and

    fasten tightly.

    2. The lower retaining hooks

    (pos.5) are already pre-

    assembled.

    3. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    4. Ensure that they are securely

    in place.

    Installation kit for 3 CPC 6 collectors

    Installation on pitched roofs / hanger bolts

    raised torx head screws

    raised torx head screw per

    38

  • screws (pos.1) for the hanger

    bolts through the elongated

    holes in the bearing rails (pos.2)

    and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment of

    the bearing rails with the use of

    a line guide.

    screws and check that they are

    securely fastened.

    4. Do not attach the upper retain-

    ing hooks until after the collec-

    tors have been installed.

    and CPC 18 model

    Installation on pitched roofs / hanger bolts

    Installing the bearing rails and retaining hooks for the CPC 12

    1. Feed the raised torx head

    3. Tighten all raised torx head

    39

  • Space requirements for a single-row collector array:

    Dimension A according to number of collectors

    Dim. B and C according to installation angle

    A

    The CPC OEM/INOX evacuated tube collector can be installed on flat roofs, on slightly sloping roofs

    (up to 20) or in gardens. The spacing between the angle frames must also be adhered to on sloping

    on the substructure.

    roofs. It may be necessary to add auxiliary rafters. If applicable, a stress analysis is to be carried out

    Number of collectors CPC OEM/INOX

    6 12 18

    (m) (m) (m)

    1 0.70 1.40 2.10

    2 1.40 2.80 4.20

    3 2.15 4.20 6.30

    4 2.85 5.60 8.35

    5 3.55 7.00 10.45

    6 4.25 8.40 12.55

    CPC 6/12/18 OEM/INOX

    Installation angle (m)

    Dim. B 30 1.44

    Dim. B 45 1.20

    Dim. C 30 1.04

    Dim. C 45 1.35

    B

    C

    Installation on flat roofs

    Space requirement for flat roofs

    40

  • Free space between the collectors, for double-row or multi-row collector arrays.

    Free space, = 30 (m) Free space, = 45 (m)

    Free space

    August recommended

    September recommended

    and heating October recommended

    and heating recommended

    Type of use Main usage period CPC 6/12/18 CPC 6/12/18

    OEM/INOX OEM/INOX

    Domestic water May to 2.60 not

    Domestic water April to not 3.10

    Domestic water March to not 4.00

    Domestic water all year not 5.00

    Installation on flat roofs

    41

  • Building height of up to 8 m

    Collector type Number Angle Required weight Required weight

    of the angle of the of the front of the rear

    frames frame concrete slab concrete slab

    CPC 6/12/18 OEM/INOX 2 30 75 kg 75 kg

    CPC 6/12/18 OEM/INOX 2 45 75 kg 75 kg

    Building height of up to 20 m

    Collector type Number Angle Required weight Required weight

    of the angle of the of the front of the rear

    frames frame concrete slab concrete slab

    CPC 6/12/18 OEM/INOX 2 30 112 kg 112 kg

    CPC 6/12/18 OEM/INOX 2 45 112 kg 112 kg

    Note!

    Flat roofs covered with gravel :

    clear gravel from the area where

    the concrete slabs are to be

    placed.

    Flat roofs with plastic roof sheet-

    ing: place the concrete slabs on

    protective overlays (building

    protection mats, pos.1).

    Arrange the concrete slabs as

    shown in the figure to the left.A BC

    C

    Dim. A (m) 0.55 1.10 1.40

    6 12 18

    CPC OEM/INOX

    Dim. B 30 (m) 1.05 1.05 1.05

    Dim. B 45 (m) 0.81 0.81 0.81

    Dim. C 30 (m) 0.35 0.35 0.35

    Dim. C 45 (m) 0.27 0.27 0.27

    Installation on flat roofs

    Weight and positioning of the concrete slabs

    42

  • Installation on flat roofs

    Pos. 1 Bearing rail, pre-assembled, aluminium, L = 1647 mm 2 2 2

    2 concrete slabs, minimum weight per slab: 75 kg (if installing on concrete slabs)

    1 building protection mat (if installing on concrete slabs)

    4 wood screws (if installing on wood substructure)

    Drill, cordless electric screwdriver, TX 30 screwdriver bit, masonry drill bit for wall plug or threaded bolt,

    13 mm hex screwdriver bit or 13 mm spanner.

    List of parts for CPC 6 12 18

    OEM/INOX

    Pos. 2 Square tube, straight 2 2 2

    Pos. 3 Square tube, angled 2 2 2

    Pos. 4 Upper retaining hook 2 2 2

    Pos. 7 Lower retaining hook, pre-assembled 2 2 2

    Pos. 8 Hex bolt with wall plug 8 8 8

    Component overview and delivery contents

    Necessary accessories per angle frame

    Tool list

    Pos. 5 Raised torx head screw M8x20 10 10 10

    Pos. 6 Raised torx head screw M8x50 2 2 2

    43

  • Installation on flat roofs

    1. Connect the straight square

    tube (pos.1) and the angled

    square tube (pos.2) using long

    2. Connect the bearing rail (pos.3)

    to the square tubes (pos.1 and

    head screws. Use the lowest

    drilled hole of each bearing rail.

    3. Lay the building protection mat

    between the concrete slabs

    (pos.4) and the flat roof seal.

    Align and, if necessary, underlay

    the concrete slabs.

    4. Drill holes in the concrete slabs

    (pos.4). Bolt the angle frames

    onto the concrete slabs using

    the wall plugs (pos. 5) and the

    hex bolts provided (pos. 6).

    5. Only after the collector has been

    installed, are the upper retaining

    hooks (pos.7) attached to the

    6. Ensure that they are securely

    in place.

    Installing the angle frames and retaining hooks

    raised torx head screws.

    2) using short raised torx

    bearing rails, using 1 raised

    torx head screw per hook.

    44

  • Facade installation / vertical

    B

    A

    A specific clearance of the pipe length must be maintained beneath the array.

    Dim. A

    Dim. B

    Number of adjacent CPC OEM/INOX

    collectors 6 12 18

    (m) (m) (m)

    1 0,70 1,40 2,10

    2 1,40 2,80 4,20

    3 2,15 4,20 6,30

    4 2,85 5,60 8,35

    5 3,55 7,00 10,45

    6 4,25 8,40 12,55

    Number of stacked collectors CPC 6/12/18 OEM/INOX

    (m)

    1 1,64

    2 3,43

    3 5,22

    Facade installation / vertical

    Space requirements

    The CPC INOX / OEM can also be installed vertically on a wall by means of the retaining clamps for pan tiles.

    45

  • Facade installation / vertical

    Pos. 1 Bearing rail, pre-assembled, aluminium, L = 1647 mm 2 3 2 2

    Not shown Bearing rail, pre-assembled,

    Pos. 1 Middle bearing rail, aluminium, L = 1507 mm 1

    Pos. 2 Retaining clamp with raised

    Suitable bolts or screws and wall plugs for fastening onto the wall.

    Cordless electric screwdriver or cordless drill, TX 30 screwdriver bit, hammer.

    OEM/INOX

    List of parts for CPC 12 18 2x6 3x6

    Not shown Bearing rail, aluminium, L = 1355 mm 2

    Pos. 3 Spacing board (height adjustment) 12 18 12 1

    Pos. 4 Upper retaining hook 2 3 4 6

    Pos. 5 Lower retaining hook, pre-assembled 2 3 4 6

    aluminium, L = 2062 mm 2

    Not shown Slot nut, 20x30x10 4 6

    Component overview and delivery contents

    Necessary accessories

    Tool list

    Pos. 7 Raised torx head screw M8x20 2 3 8 12

    torx head screw 4 6 4 6

    46

  • Facade installation / vertical

    For the installation of either 2 or 3 CPC 6 collectors, either 2 or 3 vertical bearing rails and 2 horizontal bearing

    rails are provided.

    2 bearing rails are used per collector when installing CPC 12/18 collectors.

    Install the retaining clamps on the wall with spacing as shown in the diagram below.

    Positioning the retaining clamps for 2 adjacent CPC 6 collectors

    Positioning the retaining clamps for 3 CPC 6 or 1 CPC 6 and 1 CPC 12 arranged adjacently

    Positioning the retaining clamps for 4 adjacent CPC 6 collectors

    ca. 2,83 m

    0,8 - 1,2 m 0,8 - 1,2 m

    BA

    0,8 - 1,2 m

    1,4 - 1,9 m

    ca. 2,12 m

    BA

    B

    A

    ca. 1,40 m

    0,8 - 1,2 m

    CPC 6/12/18 OEM/INOX

    Dim. A 1.64 m

    Dim. B approx. 1.0 m

    Positioning the retaining clamps

    47

  • Facade installation / vertical

    Positioning the retaining clamps for 6 adjacent CPC 6 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 12 collectors

    Positioning the retaining clamps for 1 or more adjacent CPC 18 collectors

    0,8 - 1,2 m0,8 - 1,2 m0,8 - 1,2 m

    B

    ca. 4,24 m

    A

    2,08 m 2,08 m 2,08 m

    0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m 0,7 - 1,0 m

    BA

    ca. 1,39 m ca. 1,39 m ca. 1,39 m

    0,8 - 1,2 m 0,8 - 1,2 m 0,8 - 1,2 m

    BA

    BA

    0,8 - 1,2 m0,8 - 1,2 m0,8 - 1,2 m0,8 - 1,2 m

    ca. 3,53 m

    Positioning the retaining clamps for 5 CPC 6

    48

  • 7Facade installation / vertical

    Note

    When installing on a

    facade, use the correct

    screws or bolts and wall

    plugs.

    1. Drill holes and insert wall plugs

    (pos.1).

    2. Secure the retaining clamps

    (pos.2) to the facade using

    the screws (pos.3).

    Installing the retaining clamps

    49

  • Facade installation / vertical

    screws (pos.1) for the retaining

    clamps (pos.7) through the elon-

    gated holes in the bearing rails

    (pos.2) and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment

    of the bearing rails with the

    use of a line guide.

    screws and check that they are

    securely fastened.

    4. Screw the horizontal bearing

    rails (pos.4) onto the vertical

    bearing rails (pos.6) with the

    (pos.5) and the slot nuts and

    fasten tightly.

    5. The lower retaining hooks

    (pos.7) are already pre-

    assembled.

    6. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    7. Ensure that they are securely

    in place.

    Installation kit for 2 CPC 6 collectors

    Installing the bearing rails and retaining hooks for the CPC 6 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    raised torx head screws

    raised torx head screw per

    50

  • Facade installation / vertical

    1. Screw the horizontal bearing

    rails (pos.1) onto the vertical

    bearing rails (pos.4) with the

    (pos.2) and the slot nuts and

    fasten tightly.

    2. The lower retaining hooks

    (pos.5) are already pre-

    assembled.

    3. Attach the upper retaining hooks

    (pos.3) to the bearing rails once

    the collector has been installed,

    and not beforehand, using one

    hook.

    4. Ensure that they are securely

    in place.

    Installation kit for 3 CPC 6 collectors

    raised torx head screws

    raised torx head screw per

    51

  • Facade installation / vertical

    screws (pos.1) for the retaining

    clamps (pos.2) through the elon-

    gated holes in the bearing rails

    (pos.4) and tighten slightly.

    2. In so doing, align the bearing

    rails so that the overhangs at

    each end are approximately

    equal. Assess the alignment of

    the bearing rails with the use of

    a line guide.

    screws and check that they are

    securely fastened.

    4. Do not attach the upper retain-

    ing hooks (pos.3) until after the

    collectors have been installed.

    Installing the bearing rails and retaining hooks for the CPC 12 and CPC 18 model

    1. Feed the raised torx head

    3. Tighten all raised torx head

    52

  • Facade installation / angle frames

    slopes. For a 60slope, 0.9 m space must be kept free beneath the collector.

    Dimension A according to number of collectors

    Dim. B and C according to installation angle

    AB

    C

    The CPC OEM/INOX can be installed on a wall by means of the angle frames for 45 or 60

    CPC OEM/INOX

    6 12 18

    Number of collectors (m) (m) (m)

    1 0,70 1,40 2,10

    2 1,40 2,80 4,20

    3 2,15 4,20 6,30

    4 2,85 5,60 8,35

    5 3,55 7,00 10,45

    6 4,25 8,40 12,55

    CPC 6/12/18 OEM/INOX

    Installation angle (m)

    Dim. B 45 1,35

    Dim. B 60 1,01

    Dim. C 45 1,20

    Dim. C 60 1,48

    Facade installation / angle frame 45 or 60

    Space requirements

    53

  • Facade installation / angle frames

    Pos. 1 Bearing rail, pre-assembled, aluminium, L = 1647 mm 2 2 2

    Use suitable screws and wall plugs, or threaded bolts and bolting material for the respective surface.

    Drill, cordless electric screwdriver, TX 30 screwdriver bit, masonry drill bit for wall plug or threaded bolt,

    13 mm hex screwdriver bit or 13 mm spanner.

    OEM/INOX

    List of parts for CPC 6 12 18

    Pos. 2 Square tube, straight 2 2 2

    Pos. 3 Square tube, angled 2 2 2

    Pos. 4 Upper retaining hook 2 2 2

    Pos. 7 Lower retaining hook, pre-assembled 2 2 2

    Pos. 8 Hex bolt with wall plug 8 8 8

    Component overview and delivery contents

    Necessary accessories per angle frame

    Tool list

    Pos. 5 Raised torx head screw M8x20 10 10 10

    Pos. 6 Raised torx head screw M8x50 2 2 2

    54

  • Facade installation / angle frames

    slopes. For a 60slope, 0.9 m space must be kept free beneath the collector.

    A

    B

    C

    C

    The CPC OEM/INOX can be installed on a wall by means of the angle frames for 45 or 60

    CPC OEM/INOX

    6 12 18

    Dim. A (m) 0,55 1,10 1,40

    Dim. B 30 (m) 1,05 1,05 1,05

    Dim. B 45 (m) 0,81 0,81 0,81

    Dim. C 30 (m) 0,35 0,35 0,35

    Dim. C 45 (m) 0,27 0,27 0,27

    Positioning the angle frames

    55

  • Facade installation / angle frames

    For wall installations, 4 suitable

    bolts or screws of sufficient length

    and thickness are to be used for

    each angle frame. Here, the com-

    bined weight of the collector and

    angle frames, as well as stress

    from snow and wind must be

    taken into account. The offset

    corner of each angle frame is to

    point upwards.

    On cavity wall masonry, the wall

    plugs are to be inserted in the

    load-bearing wall, or threaded

    bolts are to be used.

    If the angle frame is mounted on

    a facing skin which is not very

    stable, it should be underlaid with

    suitable slabs, which transfer the

    exerted forces onto the masonry

    in such a manner that they are

    distributed over a large area.

    1. Connect the square tubes,

    straight (pos.1) and angled

    (pos.2), using M8x50 raised

    2. Connect the bearing rail (pos.3)

    to the square tubes (pos.1 and

    head screws. Use the upper

    drilled hole on each bearing rail.

    3. Drill holes into the facade.

    Attach the wall plugs (pos.4)

    and angle frames (pos.2) to the

    facade using the provided hex

    bolts (pos.5) or other suitable

    bolts or screws. The alignment

    of the angle frames is to be

    assessed with the use of a

    line guide on the lower edges

    of the frames.

    4. Only after the collector has been

    installed, are the upper retaining

    hooks (pos.6) attached to the

    bearing rails, using 1 raised

    5. Ensure that they are securely

    in place.

    Installing the angle frames and retaining hooks

    torx head screws.

    2) using M8x20 raised torx

    torx head screw per hook.

    56

  • Caution!

    The sun protection sheet

    must be left on the col-

    lector until the collector

    has been flushed and

    filled, however it must

    not be exposed to the

    weather for longer than

    4 weeks. For longer

    periods, a suitable sun

    protection tarpaulin

    must be applied.

    1. Rest the collector on the bearing

    rails in its packaging, open the

    packaging and let the collector

    slide into the lower retainers

    (pos.1). Each lower retainer

    must completely encompass

    the lower frame of the collector.

    2. Position the collector on the

    bearing rails so that there is

    equal overlap on each side.

    3. Screw the upper mounting

    hooks (pos.2) tightly onto the

    bearing rails, using one raised

    hook.

    4. Check that all screw fittings

    are securely fastened.

    Installing the collector

    Installing the collector

    torx head screw for each

    57

  • The flow or return pipe can be con-

    nected to the collector on the left

    or on the right, as selected.

    The connection is made using pre-

    One integrated sensor immersion

    sleeve is available on each collector

    connection side. The sensor is always

    Upon delivery, the collector is covered

    by a sun protection sheet. This facili-

    tates trouble-free commissioning of

    the solar energy system even in strong

    sunlight. It prevents the heat transfer

    medium being vaporised, rendering

    commissioning impossible. Remove

    the sun protection sheet after commis-

    sioning.

    The collector must be commis-

    sioned 4 weeks after installation

    at the latest .

    Installing the collector

    Specifications

    mounted 15 mm olive connections.

    Within SOLFEX Energy Systems Prestige

    Solar Thermal Packs, a first fix connection

    set containg 2x 15mm x 1m lengths of

    flexible stainless steel pipe with insulation

    is available as an optional extra.

    located on the hot flow side.

    Silicone coated high temperature PT1000

    protection box to avoid over-voltage

    sensors (black in colour) can only be used

    The sensor cable can be extended by up to

    15m using 2x 0.5mm cross-section cable and

    up to 50m using 2x 0.75mm cross-section

    cable.

    Note:

    damage caused by lightning storms.

    and must be connected through an over-voltage

    58

  • Note!

    The flow or return pipe

    can be connected to the

    collector on the left or on

    the right, as selected.

    1. Attach the connecting pipes

    with an olive connection as

    shown in the figure to the left.

    Note!

    When tightening or

    loosening the fittings,

    always grip the body

    of the fitting to counter

    the force.

    leak-tight.

    Note!

    If, during commission-

    ing, a motor-driven

    flushing pump is used

    for flushing, bleeding

    and filling the solar

    energy system (for the

    prerequisites please

    refer to the service

    instructions, section

    Commissioning),

    bleeding at the highest

    point of the system is

    unnecessary.

    collector to the pipes, flexible

    metal connection hoses are

    2. Check that the connection is

    available.

    3. For flexible connection of the

    Collector pipe work connections

    Connecting the flow and return pipes to the collector

    59

  • Caution!

    Due to the plastic film for sun protection on the collector, the solar system can be filled also

    during sunshine or strong diffused radiation.

    The system may not be filled if the collectors were previously or are currently exposed to direct

    sun radiation.

    For flushing and filling the solar system the antifreeze Tyfocor LS is exclusively certified.

    In case of neglect, all warranty claims expire.

    1. Before filling the system, check the admission pressure of the expansion tank and correct, if necessary.

    2. Check whether all slide valves, flow control valves, check valves, or

    gravity brakes are in their opened position.

    3. Fill the system through the filling armature with antifreeze Tyfocor LS

    (finished mixture).

    Note!

    The compression test and flushing of the system should not

    be per formed with water, since emptying of the collector is

    not possible. Filling should take place with a motor operated

    pump. This pump should have a minimum flow rate of 5 l/min.

    at 6 bar in order to be able to sufficiently rinse the collectors

    air-free.

    Static height between Admission pressure Operating

    highest point of the system of the expansion tank pressure

    and the expansion tank

    5.......10 m 2,5 bar 3,0 bar

    10.......15 m 3,0 bar 3,5 bar

    15.......20 m 3,5 bar 4,0 bar

    Figure 1

    Flushing, venting, and filling of the solar system

    0........ 5 m 2,5 bar 3,0 bar

    Filling of the system

    Commissioning the system

    60

  • Note!

    Check the system for tightness. Observe the permissible operating pressure.

    The pressure must not drop for half an hour.

    Note!

    In order to make the expansion tank air-free, the system is brought up to the maximum

    We recommend flushing in as well as against the flow direction of the solar pump.

    (See figure1)

    operating position.

    the drain tap.

    With parallel connection of collectors, all collector strands are to be rinsed individually.

    back from the system stays clear.

    Continue the rinsing procedure so long until the Tyfocor that flows

    a slight milky foam.

    During the rinsing procedure, Tyfocor LS tends to generate

    disposed of.

    to be drained into a separate collecting basin and to be

    2 litres which rinse the rough dirt from the solar circuit are

    Note!

    4. The flushing of the system should be performed until no more air exits at

    If parts of the solar system are brazed, then the first

    5. Flush the system a second time to completely remove any remaining air.

    6. Bring the system up to the appropriate operating pressure.

    7. Close the filling armature and bring slide valves, flow control valves, check valves, or gravity brakes into

    Commissioning the system

    permissible pressure. The air is vented out from the expansion tank by quickly opening the

    pipe work connection on the expansion tank or by openeing the drain tap if fitted.

    Repeat this procedure until no more air exits from the expansion tank.

    61

  • Adjust the flow rate on the basis the following table:

    Note!

    Adjust the rough flow rate by means of the choice of the pump stage,

    Settings with high flow systems: approx. 0,5-0,7 l/(min x m2), collectors connected in series:

    Approx. flow rate l/min. (inlet temperature 20C)

    Settings with low flow systems: approx. 0,2-0,3 l/(min x m2), collectors connected in series:

    Approx. flow rate l/min. (inlet temperature 20C)

    Number of CPC 6 CPC 12 CPC 18

    collectors OEM / INOX OEM / INOX OEM / INOX

    1 - 1,5 2,5

    2 1,5 3 3,5

    3 2,5 3,5 4,5

    4 3 4 -

    5 3,5 - -

    6 3,5 - -

    7 4 - -

    8 4 - -

    9 4,5 - -

    Number of CPC 6 CPC 12 CPC 18

    collectors OEM / INOX OEM / INOX OEM / INOX

    1 - 0,5 1

    2 0,5 1 1,5

    3 1 1,5 2

    4 1 2 2,5

    5 1,5 2,5 3,5

    6 1,5 2,5 -

    7 1,5 3 -

    8 2 - -

    9 2 - -

    10 2,5 - -

    11 2,5 - -

    12 2,5 - -

    13 3 - -

    14 3 - -

    - - - -

    and micro-adjust at the flow control valve.

    Adjustments are not required when using pump speed control via the solar controller.

    Adjustment of the flow rate

    Commissioning the system

    62

  • 1. Check freeze protection temperature of the heat distribution medium Tyfocor LS with the suitable freeze

    protec tion checker.

    2. Check electrical connections.

    In case of losses by leakage, Tyfocor LS must be refilled undiluted. In case of doubt the freeze protection

    The freeze protection mixture Tyfocor LS must be replaced immediately. The pH value can be determined

    If this value falls under pH = 7, then corrosion protection of the system is not ensured anymore.

    1. Examination of the freeze protection.

    Commissioning / maintenance of the system

    2. Fluid leakage of the system.

    3.

    4.

    5. Check safety devices for function.

    Check system operating pressure and pre-charge pressure of the expansion vessel.

    CPC INOX / OEM evacuated tube collectors require no maintenance or cleaning.

    changed into a white film due to air penetration.

    A defective tube can be identified in that the silver-coloured vacuum coating at the base of the tube has

    refer to controller handbook for further details.

    4. Activate the solar thermal controller and ensure the correct system parameters are set,

    5. Check circulation pump and flow rate.

    6. Check safety devices for function.

    7. Pull the plastic film for sun protection off the collector.

    Commissioning guide

    We recommend examining the freeze protection by means of a refractometer.

    with litmus paper .

    6. The collector needs not to be cleaned if the roof pitch is > 15.

    A further criteria is the condition of the heat transfer medium pH value.

    3. Check pipe work is correctly insulated with high temperature insulation to current Building Codes of Practice.

    must be determined by means of a refractometer.

    Check solar controller parameters have not been adjusted since commissioning and are set accordingly.

    However, the evacuated tubes can be visually inspected from ground level only by the system owner,

    and defective tubes must be replaced immediately by an approved and competent person only.

    63

    Maintenance / System owner information

  • Commissioning / maintenance of the system

    Do not delay any required repair work as this will cause further damage and will become

    increasingly expensive to repair.

    Do not delay any required repair work as this will cause further damage and will become

    increasingly expensive to repair.

    controller operating manual.

    Further operating instructions can be found within the solar thermal

    64

    Maintenance / System owner information

  • Name:

    Company:

    Date:

    Collector No. of System System ChargeModel Collectors Flow Rate Pressure Charge Pressure

    Expansion Vessel TransferFluid PH Size

    Storage Store MaxTemperature

    DT OffDT On

    Name Company

    20

    19

    18

    17

    16

    15

    14

    13

    12

    11

    10

    9

    8

    7

    6

    5

    4

    3

    2

    1

    SettingsSystem Operating Pressure Expansion Vessel Pre-Charge

    system

    of the whole

    Inspection Controller

    Visual

    Fluid PH

    Transfer

    20

    19

    18

    17

    16

    15

    14

    13

    12

    11

    10

    9

    8

    7

    6

    5

    4

    3

    2

    1

    DateService

    Service

    65

    Commissioning / maintenance

    Commissioning / check list

    Maintenance Log / Check list / Service record

  • A defective tube can be identified in that the silver-coloured vacuum coating at the base of the tube has changed

    into a white film due to air penetration.

    Danger!

    Whenever replacing defective or damaged tubes, gloves and safety glasses

    must be worn.

    1. Carefully remove glass shards, without damaging the CPC reflector surface.

    2. Remove residual glass from the manifold.

    3. Then remove the tube retainer.

    Caution: a risk of cracking arises if the tube is bent by more than 20.

    by up to approximately 20 upwards from the collector level (pos.3).

    space to pull the tube completely out in a downwards direction, the 8 mm stainless steel tube can be bent

    down to the ground, then guide the end of the tube along the ground in a straight line. If there is insufficient

    remove it. For installations on flat roofs, protect the end of the tube by grasping it with a glove, and pull it

    2. Raise the tube a little, and while rotating it slightly around the longitudinal axis, pull it straight downwards and

    of the manifold.

    levers (pos. 2) downwards with thumb and forefinger, and remove the tube retainer by lifting it in the direction

    the manifold (pos. 1) to release the tube retainer. Grip the tube retainer by hand, while pushing the two release

    1. Remove the tube retainer at the lower end. To achieve this, push the tube approximately 5 mm upwards into

    Maintenance and repair

    Maintenance

    Replacing individual tubes

    Removing mechanically damaged tubes

    Removing tubes which are not mechanically damaged

    Collector maintenance and repair

    CPC INOX / OEM evacuated tube collectors require no maintenance or cleaning.

    immediately.

    However, upon servicing, the evacuated tubes must be visually inspected, and defective tubes must be replaced

    66

  • 1. Ensure that the location of the silicone ring (pos.4) in the manifold is clean.

    2. Coat the upper tube end with grease paste or soap, so that the tube can be easily pushed through the

    silicone ring in the manifold.

    3. Install the new tube in a manner corresponding to the manner in which the defective tube was removed.

    While rotating the tube slightly, push it through the silicone ring into the manifold.

    4. Place the tube retainer on the end of the tube. Grip the end of the reflector contour with the tube retainer

    raised, push the tube retainer between the two notches on the aluminium frame, push downwards and into

    the groove in the frame.

    5. Pull the tube downwards into the tube retainer as far as it will go.

    Maintenance and repair

    Installing individual tubes

    67

  • Using the correct replacement part.

    Name / description CPC 6 CPC 12 CPC 18

    CPC OEM reflector plate, 3-fold, for 3 tubes, Al 2 x 4 x 6 x

    If one of the collectors reflector plates is damaged, it can easily be replaced.

    Danger!

    Wear gloves and safety glasses whenever mounting or dismounting tubes.

    Caution!

    Wear gloves and safety glasses when exchanging reflector plates.

    Injuries through reflector edges and hot collector parts are thus to be avoided.

    1. Dismount the tubes above the reflector plate that is to be replaced, as described in point 5.4. Store the tubes

    safely while the reflector is being replaced so as to avoid damaging them.

    2. Pull down on and remove the damaged reflector under the tubes.

    3. Carefully lift up all meander tubes that are present above the reflector that is to be replaced. A batten or

    something similar can be used as an aid when lifting up the meander tubes. Slide the batten diagonally

    under the meander tubes.

    4. Slide the new reflector under the meander tubes with the notches facing the manifold. The notches must be

    clamped onto the top of the manifold.

    5. Mount the tubes again, as described in point 5.5.

    Maintenance and repair

    Replacing damaged reflector plates

    68

  • Position Designation Order no.

    01 Collecting tank cover profile CPC 6 OEM, Al 08-9113

    01 Collecting tank cover profile CPC 12 OEM, Al 08-9125

    01 Collecting tank cover profile CPC 18 OEM, Al 08-9139

    01 Collecting tank cover profile CPC 6 INOX, Al 08-9110

    01 Collecting tank cover profile CPC 12 INOX, Al 08-9122

    01 Collecting tank cover profile CPC 18 INOX, Al 08-9136

    02 Sealing ring tube rubber black, EPDM 55 88-9001

    03 Screws 3.5 x 16, stainless steel 08-9238

    04 Tube holder black, PBT 40 88-8001

    05 Rubber plug for side profile left, TPE 90 08-9220

    06 Rubber plug for side profile right, TPE 90 08-9221

    07 Mirror sheet metal CPC OEM, triple, for 3 tubes, aluminium 88-2011

    08 Evacuated tube, L = 1500 mm, borosilicate glass 08-1916

    09 Spare part set heat guide plate, aluminium 88-2522

    10 Straight screw connection, 15 mm, brass 08-6059

    No picture Screwed angle fitting, 90, 15 mm, brass 08-6064

    No picture Reduction 15 x 12 mm, for clamping ring connector, brass 08-9209

    No picture Support sleeve 12 mm, brass 08-6046

    No picture Support sleeve 15 mm, brass 08-6047

    Component parts list

    Component parts for tube collector CPC 6/12/18 OEM / INOX

    Collector component parts list

    69

  • Tyfocor LS safety data

    must be disposed of in accordance with official regulations. and the fire conditions. Contaminated extinguishing water Further information: The degree of risk is governed by the burning substance

    Special protective equipment: In case of fire, wear a self contained breathing apparatus.

    mentioned can be released in case of fire.Specific hazards: Evolution of fumes/fog. The substances/groups of substances

    for extinguishing environmental fire.2 foam, dry extinguishers, and carbon dioxide (CO ) are suitable

    Suitable extinguishing media: The product is non-flammable. Water spray, alcohol-resistant

    5. Fire fighting measures

    no known specific antidote. Note to physician: Symptomatic treatment (decontamination, vital functions),

    On ingestion: Rinse mouth and then drink plenty of water.

    water with eyelids held open. On contact with eyes: Wash affected eyes for at least 15 minutes under running

    On skin contact: Wash thoroughly with soap and water.

    remove to fresh air and seek medical attention. If inhaled: If difficulties occur after vapour/aerosol has been inhaled,

    General advice: Remove contaminated clothing.

    4. First aid measures

    ingredients are mentioned. The wording of the hazard symbols and R-phrases is specified in Chapter 16 if dangerous

    INDEX No: 603-083-00-7 R-phrases: 36 EC No: 203-820-9 Hazard symbol: Xi 1,1-Iminodipropan-2-ol Content (w/w): > 1 % - < 3 % CAS No: 110-97-4

    Hazardous Compounds:

    Aqueous solution of propane-1.2-diol (CAS-No.: 57-55-6) with corrosion inhibitors.Chemical nature:

    3. Composition/information