THESOLAR STATIONTeam:Victor Y. Liao, BEMichael McDonald, ECETrev Comstock, ECE
Advisor:Dr. Rajendra Singh, ECE
INTRODUCTION Green efforts exist at
Clemson Visibility of these
projects is not readily apparent
Sustainability is a 21st century issue
CLEMSON UNIVERSITY ENERGY AWARENESS*
20% by 2020: Reduce energy usage 20% by 2020 “In an effort to further reduce greenhouse gas emissions,
Clemson also has a long range goal to increase its energy sourcing from renewable resources by 10% by fiscal year 2025.”
100% by 2030: Net zero emissions by 2030 “Transform the main campus into a model for energy
sustainability: a “net-zero,” carbon-neutral campus.” “As Clemson continues to innovate to reach for it's 2020
and 2030 goals, solar installations will play a major role in meeting our energy needs.”
*https://www.clemson.edu/facilities/energy-awareness/
PROBLEM & SOLUTION Clemson needs to demonstrate its commitment
to sustainability Students need to be better connected to green
energy Laptops/phones always need to be recharged Lack of outdoor charging if you want to be
outside
VISION Our project aims to create a solar charging table
for personal electronics These tables could be installed around campus for
students to work at outdoors They provide enough power to charge 2-4
laptops, phones, tablets, or other personal electronics
The battery ensures a steady supply of energy even in cloudy conditions
DESIGN
DESIGN
DESIGNSolar Panels
BatteryInverter
Outlet
BENEFITS Attractive, high visibility installation demonstrates
Clemson’s commitment to sustainability Allows students to interact with renewable energy
in a personal way, while providing a useful service About 1/5 of the cost of commercial versions Table built for students, by students Mobile installations can be moved around campus Could save Clemson up to 200 kWh/table each
semester
PROGRESS Completed a design for our concept and
determined the components necessary for its construction
Acquired the electrical components, including the solar panels
Received approval to install our first table on campus
SCHEDULESpring 2015 Fall 2015 – Spring 2016January Finalize selection of table, buy
mounting pole and electrical box
February Construct first table and test
operationMarch Place at Lee Hall courtyard and
have grand unveilingApril Survey usage and make notes
for future improvements
August – December 2015 Build 2 tablesJanuary – April 2016 Build last 2 tables
PROPOSED LOCATIONS
BUDGET4 Solar Stations @ $2,542 each =
$10,168
QUESTIONS?