Solar Photovoltaic Modules

100
Solar Photovoltaic Modules Introduction to Photovoltaics Component Parts Panels Mountings Inverters Ancillary components, cabling etc. Electrical Installation MPPT Strings Grid Connection System design; For Part L For Energy Production

Transcript of Solar Photovoltaic Modules

Page 1: Solar Photovoltaic Modules

Solar Photovoltaic Modules

• Introduction to Photovoltaics • Component Parts

• Panels • Mountings • Inverters • Ancillary components, cabling etc. • Electrical Installation

• MPPT Strings • Grid Connection

• System design; • For Part L • For Energy Production

Page 2: Solar Photovoltaic Modules

Background

Electronic Controllers for Grid tied and off-grid hybrid solar/wind systems.

Page 3: Solar Photovoltaic Modules

Solar PVs

• Photons cause electron flow across junction between two types of silicone

• Process degrades at rate of about 0.7% per annum

• Commercial efficiency typically 16% (compared to 60% thermal)

• Complements wind as part of national renewable energy

• Initially developed for remote power (satellites, then lighthouses) – Over 50 years in use

• Massive price decreases as volume production rises

Page 4: Solar Photovoltaic Modules

Solar PVs Spain

Page 5: Solar Photovoltaic Modules

Charanka Solar Park

550Mw 3km from end to end 2,750,000 Panels

Page 6: Solar Photovoltaic Modules

Charanka Solar Park

550Mw 3km from end to end 2,750,000 Panels

Page 7: Solar Photovoltaic Modules

Potential for hvdc solar distribution

Page 8: Solar Photovoltaic Modules

Economics

• UK - Feed in tariff 16p plus savings or 4p for export

• Germany - Production 12c plus savings

• Ireland - Nil for production, 9c for exports (currently halted)

• 4kw system in UK will earn €1,000 to €1600 per annum

• 4kw system in Ireland will earn up to €700 depending on self-consumption (can use diversion systems)

Stick rather than carrot

Page 9: Solar Photovoltaic Modules

System Design for Part L Technical Guidance Document Part L 2011

- 10 kWh/m2/annum contributing to energy use for domestic hot water heating, space heating or cooling;

or - 4 kWh/m2/annum of electrical energy; or - a combination of these which would have equivalent

effect.

Page 10: Solar Photovoltaic Modules

Component Parts

4-1

1 PV array, 2 PV array combiner/junction box, 3 Grid-tied inverter,

4 Import/export meter, 5 Connection to grid, 6 Loads.

Other configurations are possible Grid-tied photovoltaic systems

Page 11: Solar Photovoltaic Modules

Monocrystalline module

3-11 Photovoltaic effect

Cut from solid silicon rods with round edges removed. Hence appearance

Page 12: Solar Photovoltaic Modules

Polycrystalline module

3-12 Photovoltaic effect

• Tends to have less of the blue tinge in modern production

• Can come on white or black backsheet. White is more efficient due to better heat loss

• Can be black or natural aluminium frame. Black usually more discreet but powder coating pushes up price

Page 13: Solar Photovoltaic Modules

All black (black backsheet)

3-12 Photovoltaic effect

• Black mono so white triangles are not conspicuous

• White is more efficient due to better heat loss, but black more aesthetically acceptable

• Can be black or natural aluminium frame. Black usually more discreet but powder coating pushes up price

Page 14: Solar Photovoltaic Modules

Standards

MCS in UK. • UK Microgeneration Certification Scheme • UK market standard as pre-requisite to feed in tariff • Sets standards for major components and for installation practice TUV tested Standards Required • EN 61215 - Energy Production • EN 61730 - Mechanical Safety • EN 62716 – Ammonia Corrosion Testing • EN61701 – Salt Mist Corrosion Testing

Page 15: Solar Photovoltaic Modules
Page 16: Solar Photovoltaic Modules

Dimensions

• Most common panels are approx 1650mm x 992mm

• Can be mounted in portrait of landscape format

Page 17: Solar Photovoltaic Modules

Electrical Characteristics

Page 18: Solar Photovoltaic Modules

Electrical Characteristics

• At 800W/m2, 73% of 1kw production

• Note Isc at 800W/m2 is less than Imp at 1kw

• Therefore fuse protection on single string is not possible, (nor necessary)

Page 19: Solar Photovoltaic Modules

Effect of temperature on the operation of solar pv modules

3-14 Photovoltaic effect

Typical temp coefficient of pMax: 0.41%/K

• Roof integrated systems will have poorer cooling • Important to calculate Voc at minimum temperature

Page 20: Solar Photovoltaic Modules

Voc (Open Circuit Voltage)

• Must be calculated for the lowest possible temperature in that region (voltage rises with temperature)

• Voc of panels in series must be less than Vmax for inverter

• Voltage at 25OC is 38.4V (STC is 25OC and 1000W/M2)

• Temperature Coefficient is -0.32%/K

• At -20OC coefficient is 45 X 0.32% or 14.4%

• Voc at -20OC is 38.4+14.4% or 43.8V per module

• If inverter V max is 450V, you should have no more than 10 panels in series in a string

MCS Requires • Voltage: Voc(stc) x 1.15 • Current: Isc(stc) x 1.25

Page 21: Solar Photovoltaic Modules

Effect of irradiation levels Unlike thermal, output is almost pro-rata

3-15

UMPP voltage range

Module voltage (V)

Mo

du

le c

urr

en

t (A

)

Photovoltaic effect

Page 22: Solar Photovoltaic Modules
Page 23: Solar Photovoltaic Modules

Cabling Options

Page 24: Solar Photovoltaic Modules

Cabling Options

MCS Standard: Because PV array cables almost exclusively rely on double or reinforced insulation as their means of shock protection they should not be buried in walls or otherwise hidden in the building structure as mechanical damage would be very difficult to detect and may lead to increase instances of shock and fire risk. Where this cannot be avoided conductors should be suitably protected from mechanical damage, suitable methods may include the use of metallic trunking or conduit or the use of steel wire armoured cable in accordance with BS 7671

Page 25: Solar Photovoltaic Modules

Cabling Options

• Cables are to be well supported, especially those cables exposed to the wind.

• Cables must be routed in prescribed zones or within mechanical protection, fully supported / cable tied (using UV stabilised ties)

• Cables must also be protected from sharp edges

• Observe procedures for dealing with live cables and prevent this where possible

• Be aware of potential capacitor discharge delay on inverter

Page 26: Solar Photovoltaic Modules

DC Layout – typical 4 panel array

Page 27: Solar Photovoltaic Modules

Layout 8 panel dual-tracking system for partial shading or East/West

Page 28: Solar Photovoltaic Modules

DC Isolator

• Disconnects panels from

inverter • No other connections should

be broken or made while this connector is closed

Page 29: Solar Photovoltaic Modules

Inverter

• Injects DC from panels into grid • Must conform to EN50438 • Unique Irish variants • Usually under-sized slightly for

improved efficiency • May include DC isolator • Most also offer wifi connectivity as

optional extra

• Micro-inverters –vs- Wall mounted

MCS on Power ratio - It is common practice for an inverter power to be less than the PV array rating. In the UK, inverters are typically sized in the range of 100 - 80% of array capacity.

Page 30: Solar Photovoltaic Modules

Inverter Specs

Page 31: Solar Photovoltaic Modules

Inverter Specs

Note: Higher Vin mad, Multi string, current per string,

Page 32: Solar Photovoltaic Modules

Inverter Specs

Lower efficiency at low power- hence tendency to slightly under-size inverter.

Page 33: Solar Photovoltaic Modules
Page 34: Solar Photovoltaic Modules

Inverter Micro-inverters –vs- Wall mounted

Page 35: Solar Photovoltaic Modules
Page 36: Solar Photovoltaic Modules

Inverter – Irish Standards

Page 37: Solar Photovoltaic Modules

AC Isolator

• Provides clear instructions on how to isolate system in event of fire or other hazard

• Labelling also standardised under MCS process

MCB in consumer unit • Usually an MCB in the consumer unit • Generally no RCD required.

Page 38: Solar Photovoltaic Modules

Labelling Requirements

Page 39: Solar Photovoltaic Modules

Labelling Requirements

Page 40: Solar Photovoltaic Modules

Labelling Requirements

Page 41: Solar Photovoltaic Modules

850W

Nothing on

850W

Page 42: Solar Photovoltaic Modules

600W

2000W

1400W

Page 43: Solar Photovoltaic Modules

600W

100W

500W

Page 44: Solar Photovoltaic Modules

ZZZzzz…

400W

400W

Page 45: Solar Photovoltaic Modules

ZZZzzz…

400W

400W

Residential Import Price: 22c approx Export Price: Was 9c. Now zero

Currently not available

Page 46: Solar Photovoltaic Modules

Immersion Diversion

Units

Page 47: Solar Photovoltaic Modules

Immersion Diversion Units

• Solic uses triac to switch on load in mid-cycle in the same way that a dimmer switch works

• This causes spike on the grid at the moment of switch on as seen on oscilloscope reading

Page 48: Solar Photovoltaic Modules

Immersion Diversion Units

• Products like EMMA ™ and Immersun™ use high frequency switching using IGBTs or mosfets which do not require zero-crossing switch-off

• Sine wave is unaffected • Some loss in the switching circuit due to

voltage drop across IGBT/mosfet. • Much more expensive units.

Page 49: Solar Photovoltaic Modules

Immersion Diversion Units

• Typical solar thermal system will delivery 1800 KwHrs of hot water per annum • Typical solar PV 2kw system will deliver 1900 KwHrs of POWER per day • If 33% of this is used as electricity, saving is 19c per KwHr on that portion • Remaining 66% diverted to heating water will save approx 9c per KwHr.

• Immersion diversion would cause de-rating of the system under DEAP so

should be a retrofit • Viable alternative to export tariff until this returns • Only really viable for systems above about 1.5kw • Low cost units generally not adequately certified.

Page 50: Solar Photovoltaic Modules

Applying for Grid Connection

• Complete form NC6 or for new dwelling, inform ESB of the size of inverter which will be used

• Provide EN50438 certificate for inverter (with Irish Variants) • Industrial systems (over 6kw) require Mainspro or similar relay http://www.esb.ie/esbnetworks/en/commercial-downloads/NC6.pdf

Systems above 25A (6kw) single phase or 16A (11kw) 3 phase

• Complete form NC5 • Will require use of Mainspro or similar relay to isolate system • Fee of €700 for desktop survey • You can ignore most of the requirements on the form for sub 50kw Systems.

Above that, it will cost yer! (will require G10 relay and site testing by ESB) • http://www.esb.ie/esbnetworks/en/commercial-downloads/NC5.pdf

Page 51: Solar Photovoltaic Modules

Roof Mounting

Page 52: Solar Photovoltaic Modules

Roof Mounting

Page 53: Solar Photovoltaic Modules

Spacing Roof Hooks

• Max space between roof hooks – 800mm • Max over-run from (A) to end of rail – 200mm • Rails may be joined (C)

Page 54: Solar Photovoltaic Modules

Roof Hooks Pantile Tiles

Wider base plate so that hook can be in tile dip. Usually one every 60cm to 80cm

Best practice to notch pantiles at roof hook

Page 55: Solar Photovoltaic Modules

Roof Hook Flashing

Page 56: Solar Photovoltaic Modules

Roof Hook Flashing

Page 57: Solar Photovoltaic Modules

Rail Spacing

Page 58: Solar Photovoltaic Modules

Roof Hook Spacing

Page 59: Solar Photovoltaic Modules

Roof Integrated Benefits • Less visual impact • Lower wind exposure Disadvantages • Higher installation time

& cost (partly offset by reduced slates)

- e.g. 2kw system • €2520 on-roof • €2870 in-roof

- 1kw System • €1460 on-roof • €1690 in-roof

• Reduced output due to higher temperature

Page 60: Solar Photovoltaic Modules

Trapezoidal Steel

Corrugated Steel Trapezoidal Steel

• Very low-cost industrial systems

• As little as 4c per watt

• Very quick to fit

• Mounting screws self—drilling

Page 61: Solar Photovoltaic Modules

Standing Seams

Various fittings to attach rails to standing seams

Page 62: Solar Photovoltaic Modules

Industrial Systems

• Often better payback as displacing all power at retail price

• Use monitoring in advance to assess baseload

Potential Use • Super-valu and similar supermarkets • Hotels • Industry • Anywhere with environmental

credentials to maintain

Page 63: Solar Photovoltaic Modules

Industrial Systems East/West

• South facing 30O pitch optimal for yearly production • South facing 65O pitch optional for winter production (road signs) • Wind loading, especially ballasted roof systems, makes mounting expensive • Self consumption power available over a longer period with some facing

east and west. However, winter production reduced. • Lower pitch is often used to reduce wind load

• South facing 4kw system at 30O slope produces 3976 KwHrs per year • South facing 4kw system at 15O slope produces 3751 KwHrs per year • East-west facing 4kw system at 10O slope produces 3319 KwHrs per year • Loss of 16.5% production can be compensated with additional panels

Page 64: Solar Photovoltaic Modules

Industrial Systems East/West

• Quick assembly, low wind loading, ready ballasted • Faces east and west at 10O pitch • Full wind load data available

Page 65: Solar Photovoltaic Modules

Industrial Systems Consol

Page 66: Solar Photovoltaic Modules

Industrial Systems Consol

Page 67: Solar Photovoltaic Modules

Industrial Systems Consol

Page 68: Solar Photovoltaic Modules

Industrial Systems Consol

Page 69: Solar Photovoltaic Modules

Industrial Systems Consol

Page 70: Solar Photovoltaic Modules

Industrial Systems Consol

Page 71: Solar Photovoltaic Modules

Industrial Systems

Page 72: Solar Photovoltaic Modules

Industrial Systems

Page 73: Solar Photovoltaic Modules

Industrial Systems

Page 74: Solar Photovoltaic Modules

Industrial Systems Energy provided over longer period

0

500

1000

1500

2000

2500

3000

3500

4000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

16S/15d

8EW/10d

16S/30d

Page 75: Solar Photovoltaic Modules

Industrial Systems But diminished in mid-winter

0

500

1000

1500

2000

2500

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

16S/15d

8EW/10d

16S/30d

Page 76: Solar Photovoltaic Modules

Industrial Systems Lightning Protection

Generally not required except on tall buildings • Consult lightning specialists • If isolated air termination

system fitted, maintain separation distance and place modules within protected area

Page 77: Solar Photovoltaic Modules

Industrial Systems Lightning Protection

• No air termination • Use type 2 surge

protectors on both AC and DC sides

Page 78: Solar Photovoltaic Modules

Industrial Systems String Combiners / Fuses

Multiple Strings can produce higher current in short circuit

In > 1.5 x Isc stc In ≤ 2.4 x Isc stc In ≤ Maximum series fuse value Fuse both +ve and -ve

Page 79: Solar Photovoltaic Modules

Industrial Systems String Combiners / Fuses

Can use string combiner boxes to implement double pole fuse

Page 80: Solar Photovoltaic Modules

Industrial Systems String Combiners / Fuses

Can use string combiner boxes to implement double pole fuse

Page 81: Solar Photovoltaic Modules

Industrial Systems String Combiners / Fuses

Can use string combiner boxes to implement double pole fuse

Page 82: Solar Photovoltaic Modules

Industrial Systems Mainspro Relay

• Required if exceeding

6kw single ~ or 11kw 3~

• Over 50Kw becomes “Embedded Generation” requiring G10

Page 83: Solar Photovoltaic Modules

Commissioning

Commissioning the system The grid should be connected to the inverter first, then the DC isolator closed. The inverter will then power up and can have its country settings set. If there is a need to disconnect the system, it is generally preferred to isolate the grid from the inverter first, and then open the DC isolator.

Page 84: Solar Photovoltaic Modules

Commissioning

• Should provide handover documents detailing the system

• Will require online certification of inverter installation

Page 85: Solar Photovoltaic Modules

System Design – for Part L

• Renewable Energy equivalent to 10KwHrs thermal or 4KwHrs Electricity per m2 per annum

• Also must meet CPC and EPC targets (usually with building envelope, but small excesses can sometimes be remedied with PV)

• For example, house 150m2 will need to produce 600KwHrs electricity. Need to consider; • Roof orientation • Roof pitch • Shading factor

Page 86: Solar Photovoltaic Modules

System Design Part L

• Apendix M of DEAP Manual; The electricity produced by the PV module in kWh/year is 0.80 x kWp x S x ZPV where S is the annual solar radiation from Table H2 (depending on orientation and pitch), and ZPV is the overshading factor from Table H3. • Take a system with three off 250W panels. Total panels = 750W or 0.75Kwp • Lets assume house has pitch 30 degrees and roof facing SE.

Page 87: Solar Photovoltaic Modules

Orientation & Pitch

0.80 x kWp x S x ZPV • KwP = 0.75 • Roof pitch 30 degrees facing SE has S (solar radiation) = 1021 (KwHrs/m2/yr)

Page 88: Solar Photovoltaic Modules

Shading Factor

0.80 x kWp x S x ZPV • KwP = 0.75 • Roof pitch 30 degrees facing SE has S (solar radiation) = 1021 (KwHrs/m2/yr) • Assume shading from Table H3 is “none or very little”. ZPV = 1

Page 89: Solar Photovoltaic Modules

Calculation

0.80 x kWp x S x ZPV • KwP = 0.75 • Roof pitch 30 degrees facing SE has S (solar radiation) = 1021 (KwHrs/m2/yr) • Assume shading from Table H3 is “none or very little”. Zpv = 1

• Output is • 0.8 x 0.75Kwp X 1021 X 1 = 612.6KwHrs/Yr.

• System meets renewables obligation of Part L for house 150m2

• PvSyst suggests this system in Dublin would produce 675 KwHrs.

Page 90: Solar Photovoltaic Modules

Calculation

0.80 x kWp x S x ZPV • KwP = 0.75 • Roof pitch 30 degrees facing SE has S (solar radiation) = 1021 (KwHrs/m2/yr) • Assume shading from Table H3 is “none or very little”. Zpv = 1

• Output is • 0.8 x 0.75Kwp X 1021 X 1 = 612.6KwHrs/Yr.

• System meets renewables obligation of Part L for house 150m2

Another formula

Panel size in Peak Watts = 4 x area in m2 / (S x Zpv x 0.8)

Page 91: Solar Photovoltaic Modules

Online Part L Calculator

Page 92: Solar Photovoltaic Modules

Online Energy Production Calculator

Page 93: Solar Photovoltaic Modules

Entering in DEAP

Page 94: Solar Photovoltaic Modules

Entering in DEAP

• Enter calculated production for both Part L contribution and Delivered Energy. • Look up current value for Primary Energy Conversion Factor on SEAI website

(currently 2.37) • Look up CO2 Emission Factor for electricity on SEAI website (currently 0.522)

• http://www.seai.ie/Your_Building/BER/BER_FAQ/FAQ_DEAP/Results/What_are_the

_electricity_factors_used_in_the_latest_version_of_DEAP.html

Page 95: Solar Photovoltaic Modules

Combining Thermal and PV

• Clients for one-off houses may prefer to use solar thermal. • For large one-off houses, (over 200m2), it is economically difficult to meet Part L with

solar thermal alone • In such cases, design an optimal solar thermal system to meet the clients’

requirements • See what percentage of renewable energy component has been met • Calculate remaining energy required and meet this with PV.

Page 96: Solar Photovoltaic Modules

Combining Thermal and PV

Example • House 300m2 requires modest 300L solar thermal system. • Would need 3,000 KwHrs/yr thermal • 4m2 solar thermal panel and 300L cylinder produces 1700KwHrs/yr • 1700/3000 = 56.67% • Need to produce 43.33% of requirement using PV • 300 x 4 x 43.33% = 396Kw Hrs. • On south facing roof at 30O pitch, 2 off 250w panels would produce

430KwHrs/yr. • Likely price €1,000 for hardware.

Page 97: Solar Photovoltaic Modules

Other ways of achieving Part L

• There is no “one size fits all” • Some households use large amounts of hot water in summer, others use

showers, dishwashers and washing machines. • Maintenance of solar thermal required.

• Heat dump strategy required;

• To cope with excess summer production / holidays • Lack of heat dumps has given industry bad reputation

• Stagnation

• Puts pressure on component parts • Degrades glycol

• Heat Pump

• May be justified if large amount of space heating required • In well insulated envelope, or near-passive, savings negligible and would

not be recouped in the lifetime of the system

Page 98: Solar Photovoltaic Modules

Planning Exemptions

Solar Thermal or PV panel in a domestic setting • Total panel area must not exceed 12 sq. m or 50% of the total roof area including

existing panels • The distance between the plane of the wall or pitched roof and the panel must not

be more than 15cm. • The distance between the plane of a flat roof and the panel must not exceed 50cm. • The panel must be a minimum of 50cm from the edge of the wall or roof on which

it is mounted. • A free standing array’s height must not exceed 2m above ground level. • The erection of a free standing array must not reduce the area of private space to

the rear or side of the house to less than 25 sq. m. All assumes not in a visually sensitive area.

Page 99: Solar Photovoltaic Modules

Planning Exemptions

Solar Thermal within a light industrial or business setting • Can not be erected on a wall. • Total panel area must not exceed 50 sq. m or 50% of the total roof area including

existing panels. • The distance between the plane of the pitched roof and the panel must not exceed

50cm in a light industrial building and 15cm in a business premises. • The distance between the plane of a flat roof and a panel must not exceed 2m in a

light industrial setting and 1m in a business premises. • The panel must be a minimum of 50cm from the edge of the roof on which it is

mounted or 2m on a flat roof. • Any associated equipment or storage must be within the roof space of the building. • A free standing array’s height must not exceed 2m above ground level. • The total aperture area of a free standing array must not exceed 25 sq. m. • No advertising can be placed on the panel and a free standing panel must not be

placed to the front of the premises.

Page 100: Solar Photovoltaic Modules