MRac Solar Carport System
Installation Guide
Content 1 Product Introduction ------------------------------------------P2
2 Installation Tool & Components-------------------------------P3
3 Installation Procedure -----------------------------------------P4
4 Warranty--------------------------------------------------------P8
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
2
1. Product Introduction
MRac Carport System is uniquely designed applying to large scale
commercial and utility system, offering shades to your cars while much
environment-friendly.
Please read this Installation Guide thoroughly before installing the MRac
Carport system. This Guide offers the planning and installation
instruction for MRac Carport.
MRac Carport products, when installed in accordance with this guide,
will be structurally adequate and will meet the local standards. During
installation, especially when working on the roof, be sure to observe the
appropriate safety regulations and please pay attention to the relevant
regulations of your local region. Please check that you are using the
current version of the installation manual by contact Mibet Energy by
mail on [email protected], or your local representative.
The installer is solely responsible for:
Complying with all applicable local or national building codes,
including any that may supersede this manual;
Ensuring that MRac and other products are appropriate for the
particular installation and the installation environment;
Using only MRac parts and installers-supplied parted as specified by
MRac (Substitution of parts may void the warranty and invalidate the
letter of certification on page 2);
How to recycle: according to the local relative statute;
How to disassemble: countermove with installation;
Ensure that there are no less than two professional workers in panel
installation;
Ensure the installation of relative electrical equipment is
performance by professional electrician.
Ensure safe installation of all electrical aspects of the PV array.
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
3
2. Installation Tool & Components
2.1 Installation Tool
L-Inner Hexagon
Spanner
Monkey Spanner Socket Wrench Electric Tool
Nylon Wire Tape Square Marker
2.2 Components List
Components List
Full-edge End Clamp Kit
U27 Inter Clamp Kit Rail 115 Rail 115 Connector
Beam 100 Beam 100 Connector C Clamp Kit Carport T-shape Jointer Kit
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
4
Carport Basement 80*80 Square Tube
2.3 Carport System Overview
(1)Full-edge End Clamp Kit (2)U27 Inter Clamp Kit
(3)Rail 115 (4)C Clamp Kit (5)Beam 100
(6) Carport T-shape Jointer Kit
(7)Carport Basement (8)80*40 Square Tube
②
①
③
④
⑤
⑥
⑦
⑧
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
5
3. Installation Guide
3.1 Install Each Unit
3.1.1
Fix the Carport
Basements onto the
pre-made concrete
bases according to the
technical drawing
provided, place the
nuts without fastened;
make sure all the
Carport Basements are
in a line both vertical
and landscape by a
Nylon Wire.
Showed as Drawing 1,
2, 3, and 4.
Nylon Wire
All basements have to be in
a line vertically
Nylon Wire
All basements have to
be in a line landscape
Drawing 1 Drawing 2
Drawing 3
Drawing 4
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
6
3.1.2
(1). Pre-assemble the
C Clamp Kit 150 onto
the T-shape Carport
Jointer by M8*25
bolts, as Drawing 5.
(Don’t fasten the
bolts tightly for the
convenience of next
step)
(2). Slide the
pre-assembled
T-shape Carport
Jointer to the
planned position on
the Beam 100, then
fasten the bolts
tightly now. Showed
as Drawing 6&7.
(3). Assemble the 80
Square Tube onto
the T-shape Carport
Jointer by M20*130
bolts.
Showing as Drawing
8&9.
Drawing 5
Drawing 6
Drawing 7
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
7
(4). Connect the
pre-assembled
Beam 100 Support
with the Carport
Basements, which
have already been
installed onto the
concretes, by
M20*130. 3 to 4
experienced worker
need to cooperate
to finish this step as
Drawing 10&11
showed.
Note: Make sure all
the bolts in this
system are
assembled from the
same direction as
showing in Drawing
12.
Drawing 8
Drawing 9
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
8
Drawing 10
Drawing 11
Keep all the nut in the same
direction for the whole system
Drawing 12
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
9
(5). Repeat above step
as per the technical
drawing suggested till
the whole system
finished.
Note: Make sure all
the bolts should be
fastened tightly.
3.2 Install Rail
3.2.1
The drawings
shows how the
Cross Module
being installed,
which is the main
component in C
Clamp Kit, Inter
Clamp Kit and End
Clamp Kit.
3.2.2
Check the length
of Rail 115, using
the Rail 115
Connector to
extend it
according to the
technical drawing
before assembled
onto the Beam.
8pcs of bolts are
required for each
side, totally 16pcs
bolts for one Rail
115 Connector.
Note: Not
recommend
extending the Rail
Rail
115
Rail 115
Connector
Drawing 13
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
10
115 after
assemble the Rail
115 onto the
Beam.
3.2.3
Assemble Rail 115
onto the Beam
according to the
technical drawing,
a marker can be
used to mark the
right position, as
Drawing showed.
3.2.4
Assemble all the
Rail 115 as
planned.
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
11
3.2.5
Fix the Rail 115
onto the Beam by
C Clamp Kits,
fasten all M8
inner hexagon
bolts.
Note: 2 sets of C
Clamp Kits need
to be used in
each side as
showed.
3.2.6
Repeat above step
and get all Rail 115
assembled as
technical drawing
planned, make
sure the end of all
rails in a line.
Note: All bolts
have to be
fastened tightly.
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
12
3.3 Install Panels
3.3.1
a. Place the
panels according
to technical
drawing (Drawing
1: Section view),
fix the panel by
Full-edge End
Clamp Kit and
U27 Inter Clamp
Kit.
b. Repeat above
step, and make
sure all the
panels are being
installed
properly.
Drawing 1: Section view
Installation of End
Clamp Kit
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
13
3.3.2
Installation
completed, check
all the bolts have
been fastened.
Installation of Inter Clamp Kit
No slot should be
remained between two
rows
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
14
4.Warranty Declaration 15 year limited Product Warranty, 5 year limited Finish Warranty
Mibet (Xiamen) New Energy Co., Ltd. (hereinafter as “Mibet Energy”) warrants to
the original purchaser (“NSEW Trading Pty Ltd.”) of products that it manufactures
(“Solar PV Mounting Systems”) at the original installation site that the Product shall
be free from defects in material and workmanship for a period of fifteen (15) years,
except for the under normal atmospheric conditions for a period of five (5) years,
from the earlier of 1). The date the installation of the Product is completed, or 2). 30
days after the purchase of Product by the original Purchaser (“Finish Warranty”).
The Finish Warranty does not apply to any foreign residue deposited on the finish. All
installations in corrosive atmospheric conditions are excluded. The Finish Warranty is
VOID if the practices specified by AAMA 609 & 610-02 –“Cleaning and
Maintenance for Architecturally Finished Aluminum” (www.aamanet.org) are not
followed by Purchaser. This Warranty does not cover damage to the Product that
occurs during its shipment, storage, or installation.
This Warranty shall be VOID if installation of the Product is not performed in
accordance with Mibet’s written installation instructions, or if the Product has been
modified, repaired, or reworked in a manner not previously authorized by Mibet IN
WRITING, or if the Product is installed in an environment for which it was not
designed. Mibet shall not be liable for consequential, contingent or incidental
damages arising out of the use of the Product by Purchaser under any circumstances.
If within the specified Warranty periods the Product shall be reasonably proven to be
defective, then Mibet shall repair or replace the defective Product, or any part thereof,
in Mibet’s sole discretion. Such repair or replacement shall completely satisfy and
discharge all of Mibet’s liability with respect to this limited Warranty. Under no
circumstances shall Mibet be liable for special, indirect or consequential damages
arising out of or related to use by Purchaser of the Product.
In addition to our Warranty against Defects, the Frame also comes with guarantees
that cannot be excluded under the Australian Consumer Law (Consumer Guarantees).
In the event that the Frame fails to satisfy a Consumer Guarantee, you are entitled to a
replacement or refund for a major failure and compensation for any other reasonably
foreseeable loss or damage. You are also entitled to have the Frame repaired or
replaced if the Frame fails to be of acceptable quality and the failure does not amount
Mibet (Xiamen) New Energy Co., Ltd.
No 69, Xintian Rd., Jimei District, Tel: +86592 3754999
Xiamen, China 361022 Fax: +86 592 6771575
www.mbt-energy.com Email: [email protected]
15
to a major failure. Please note that in addition to the rights and remedies set out in this
document, you may also have other rights and remedies available to you under the
law.
*Manufacturers of related items, such as PV modules and flashings, may provide
written warranties of their own. Mibet’s limited Warranty covers only its Product, and
not any related items.
Making a claim
If you believe that the Frame is defective and you are an End-User, you may either
make a claim against the installer or builder from whom you purchased the Frame or
you may make a claim against us directly. In order to make a claim against us, you
must post, fax or email us a notice, using the contact details set out below.
In your notice you must provide: details of why you believe the Frame is defective; a
copy of your invoice, receipt or any other document which provides proof of
purchase;
Details of any expenses you have incurred in making your claim; and details of how
we should contact you.
Within a reasonable time after receipt of your claim we will contact you to arrange a
time to attend the premises at which the Frame is located.
Jurisdiction
Our Warranty against Defects is to be construed in accordance with the laws of
Victoria and any disputes will be determined by the exclusive jurisdiction of the
courts of Victoria.
Contact Details
NSEW Trading Pty Ltd
Level 5, 24 Albert Road
South Melbourne Vic 3205
Tel: 0417 387673
Email: [email protected]