Social Monitoring Report Project Number: 37231-033 December 2015 PAK: Punjab Irrigation Agriculture Investment Project New Khanki Barrage Project Loan 2841 Internal Resettlement Monitoring Report Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department, Punjab for the Asian Development Bank (ADB). The social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation...

Page 1: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

Social Monitoring Report

Project Number: 37231-033

December 2015

PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841

Internal Resettlement Monitoring Report

Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department,

Punjab for the Asian Development Bank (ADB).

The social monitoring report is a document of the borrower. The views expressed herein do not

necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgments as to the legal or other status

of any territory or area.

Page 2: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

GOVERNMENT OF THE PUNJAB

IRRIGATION DEPARTMENT

New Khanki Barrage Project (NKBP)

ADB Loan No. 2841-PAK

Internal Resettlement Monitoring Report

For

Quarter October - December 2015

PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES

IRRIGATION DEPARTMENT CANAL BANK MUSTAFABAD,

LAHORE

Page 3: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

New Khanki Barrage Project (NKBP)

Internal Resettlement Monitoring Report for the Quarter October - December 2015

1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)

The project is category B for i volu tary resettle e t a d category C for i dige ous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was prepared and

submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012. LARP was revised/

updated and cleared by ADB in Feb 2014. Land Acquisition is in progress according to requirement

of Land Acquisition Act 1894. A total of 8.6 acres of land was required for construction of Head

Regulator and Head Reach of the new LCC. Section 4 and section 5 of Land Acquisition Act for 8.6

acres of land were notified and published in the Punjab Gazette on August 07, 2012 and January 21,

2013 respectively. Land price was assessed, and the EA released the total amount Rs. 9.925 million

to the Revenue Department, Government of the Punjab.

However, due to change in engineering design it was found that only 4.58 acres out of 8.6 acres of

land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5 Sarsai. Due to

this change, process of land acquisition was re-initiated. The section 4 & 5 of land Acquisition Act

1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

29, 2015 respectively.

Again due to change in engineering design of LCC Lead Channel, the procedure for acquiring 5 kanal,

10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in process.

Compensation rates have been re-calculated to reflect current values and procedures. The

landowner has received full payment for crop losses trees and structures.

The five affected families which are residing at the Dera of land owner, now they are shifted in their

new accommodation built by the landowner on his remaining land. Their livelihoods remain

unaffected. These households have received their relocation allowance (Pak Rupees

5,000/household) and cash assistance for vulnerable households (Pak Rupees72, 000/-household).

Alternative accommodation for the 15 no. of the affected families of Irrigation staff is also being

constructed and out of 15 AFs, 8 are shifted in new buildings. Funds for the remaining compensation

activities are available. All compensation payment of 6.625 acres land and relocation of the 07

affected households will be completed by Feb 2016.

LARP implementation activities for Tranche-2 relates to LCC Lead Channel (component) of New

Khanki Barrage Project. Internal Resettlement Monitoring of all relevant activities is the

responsibility of PMO (Environment and Social Unit (ESU). Internal Monitoring Reports in the shape

of QPR are being regularly submitted to the Bank. The PMO is in the process of engaging an

independent resettlement monitor (IM) to cover all tranches of the MFF. The IM will be mobilized

Page 4: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

by Feb 2016 and is expected to submit its first external resettlement monitoring report by end of

Feb 2016.

ESU / PMO for Punjab Barrages in busy in Implementation of LARP since 2012.

The Implementation Schedule of LARP is given below:

Sr.

No.

Action Time Line Responsibility To date Status

1 Establishment of PMO - PID PMO is already in place at

Lahore.

2 Setting-up the ESU. In place

PMO ESU is already in place.

3 Setting-up the LIU at Khanki 30 June, 2012

PMO Notified

4 Establish Grievance Redress Cell. 30 Sep, 2012 PMO Notified.

5 Submission of draft LARP to ADB 30 June, 2012 PMO Submitted

6 Approval of LARP 15 June, 2012 ADB Cleared

7 Urdu translation and disclosure of

LARP

05 July, 2012 PD/ ESU Also paste at website

8 Formation of DPs Consultation

Committees (2 Nos.)

30 Jun 2012 LIU Formed and notified.

9 Deployment of Supervisory

Consultants

30 Sep. 2012 PMO Deployed

10 Deployment of Social & Environment 31 Dec 2012 PMO Deployed

11 Employment to DPs/ locals (age of

economic group)

June 2013 to

March 2017

Contractor/

Consultants/PMO

A list of willing and

potential DPs/ locals is

included in LARP. Also

given to DESCON

(Contractor) for action.

12 IMR submission before handing over

Barrage site for construction

31 Oct, 2012 PMO Done

13 NTP for Barrage - ADB Done

14 Construction of Link LCC 30 Jun. 2016 Contractor/ PMO To be completed upto 30

Page 5: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Jun, 2016.

Land Acquisition

15 Section-4 Notification Dec. 2015 LAC Due to new / revised

drawing of LCC in

September 2015

16 Section-5 Notification January-2016 LAC --

17 Land Acquisition Process through

Private Negotiation

-- -- Not Applicable

18 LARP Updation Oct. 2015 Consultant Discussed with ADB

representatives on

October 07, 2015.

19 Payment to DPs (Partial Payment) July 2015 Land owner/ PMO 100% payment has

released to land owner,

labourers are shifted in

alternate location at

nearby place.

20 Relocation of Farming labourers Dec., 2015 Land owner/Agri.

Labourers PMO

-

21 Final payment to land owner after

confirmation by IM that labourers

have been relocated and paid as in

LARP.

May 2016 PMO -

22 Possession/ Transfer of Land May 2016 LAC/ PMO -

23 Relocation/ Construction of Staff

Colony

Dec. 2015 PMO -

24 Relocation/ shifting of PID staff Dec. 2015 Residents/ PMO -

25 Construction of Community Lined

Watercourses

30 Jun 2016 Contractor/ PMO -

26 Construction of Lined Public

Watercourse

30 Jun 2016 Contractor/ PMO -

27 Construction of High Level Channel 30 June 2016 Contractor/ PMO -

28 Date of contract award (expected) 30 Sept.,

2012

PMO -

29 Full Implementation of LARP Dec. 2016 PMO -

Page 6: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

30 IMR confirming LARP implementation Dec. 2016 IM Specialist/

PMO

-

31 Commencement of civil works Subject to

ADB approval

for NTP.

ADB Subject to ADB approval

on the satisfactory

implementation of LARP.

32 Redress of Community Complaints Continuous

activity

GRC/ PMO Ongoing activity till

project completion.

Total amount under LARP is Rs. 18.05 Million. Out of which, Rs. 9.925 Million has already been paid

to the Revenue Department for land Acquisition. Rupees 3.987 million have been paid to the 19 no.

of affected families as compensation amount for their structures, vulnerability allowance & shifting

allowance. The detail is given in Annex-A.

2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP

The LARP of New Khanki Barrage was approved in 2012. Again, it was updated and approved in 2014. The

adjustment was made in compensation rates of the land after certification by the Revenue Department,

Government of Punjab.

The rates are still applicable up till now. The adjustment made in the compensation is given

in Annex-B.

3. EMPLOYMENT FOR THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS

Two types of affected families are residing at LCC Lead Channel. First are Irrigation Department Employees

and they are already serving in Irrigation Department. Second are the land owner and his agriculture

laborers, those are cultivating crops. They remained busy in construction and shifting in newly built houses.

The Contractor is ready to accommodate the affected families for jobs as and when they demand. ESU, PMO

Punjab Barrages requested to the Consultants to ask the Contractor to provide jobs under the project. As per

recommendation of the Engineer, the Contractor trace each of the person included in the list, the list of the

potential persons of affected families requiring jobs under the project. The Contractor offered them an

appropriate employment. Out of 16 affected persons, only 3 residents of Irrigation Colony were willing for

jobs with the Contractor and the Contractor hired their services. The status of employment of affected

families is given in Annex-C. The Contractor also offered jobs to the family members of employees of

Irrigation Department of Khanki Division. Out of 26 applications, 20 family members of Irrigation staff were

Page 7: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

offered jobs and the Contractor hired their services under the Project. The detail is given in Annex-D

Regarding employment to the unskilled labor of the local area, the status of skilled and un-skilled labor

employment for the month of October, November and December, 2015 is given in Annex-E, which is

59%, 59% and 61 % respectively for the unskilled labor for the project area.

4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING

CONDITION

Total Twenty One (21) affected families (AFs) are to be dislocated from LCC Lead Channel component of New

Khanki Barrage Project. In first phase, land owner and his five (05) Agri-laborers are relocated and an amount

of Pak Rupees 3.927 million has been paid to the six (06) no. of affected families as the compensation amount

for their structure and other assets. During the above mention quarter the shifting allowance amounting to

PKR 60,000/- has been paid to 12 No of irrigation staff. Crop compensation for 2.125 acre (remaining land)

and private trees (100%) paid to Mr. Farooq Akbar Cheema vide cheque No. 44598144 dated 07-12-2015. Out

of Fifteen (15) No. of affected families of Irrigation Department Employees 08 no. of families have shifted to

the newly constructed residences. The remaining 07 no. of families shall be shifted in the month of February

2016.

The owner of the land has built the new dera along with the residences for the labourers 05

No. of Agri. Labourers have been shifted in their new residences. Before and after

comparison of residences shall be presented in next quarterly report.

Case No.1

Mr. Farooq Akbar Cheema is the only land owner fall in category of affected household. His land,

trees and residential structures were affected due to NKBP. A compensation payment of amounting

Pak Rs. 1,570,362 was given for crops, tube well, hand pump and structures. Current status of land

and structure can be viewed as under:

Page 8: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Mr. Farooq Akbar Cheema (Land owner) is standing on his land and structures in the back ground.

Case No.2

Mr. Muhammad Anwar is the farm laborer of Mr. Farooq Akbar Cheema. He was residing in the

house that will be relocated to the new constructed house by the land owner. He has collected an

amount of Rs. 77,000/- as compensation /poverty allowance and relocation allowance current status

is as under:

Mr. Muhammad Anwar standing in front of his residence. Picture of new residence shall be furnished in next

quarterly report.

Case No.3

Mr. Amanat Ali is the farm laborer of Mr. Farooq Akbar Cheema. He was residing in the house that

will be relocated to the new constructed house by the land owner. He has collected an amount of Rs.

77,000/- as compensation /poverty allowance and relocation allowance current status is as under:

Page 9: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Mr. Amanat Ali standing in front of his residence. Picture of new residence shall be furnished in next

quarterly report.

Case No.4

Mr. Manzoor Hussain is the farm laborer of the Mr. Farooq Akbar Cheema. He built the residential

structure in the land of land owner. He has been paid an amount of Rs. 986,100/- as compensation

for structure, 1 no. hand pump, poverty allowance and relocation allowance.

Mr. Manzoor Hussain standing in front of his residence. Picture of new residence shall be furnished in next

quarterly report.

Page 10: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No.5

Mr. Anayat Muhammad is the farm laborer of Mr. Farooq Akbar Cheema. He was residing in the

house that will be relocated to the new constructed house by the land owner. He has collected an

amount of Rs. 77,000/- as compensation /poverty allowance and relocation allowance current status

is as under:

Mr. Anayat Muhammad standing in front of his residence. Picture of new residence shall be furnished in next

quarterly report.

Case No.6

Mr. Muhammad Ramzan is the farm laborer of Mr. Farooq Akbar Cheema. He was residing in the

house that will be relocated to the new constructed house by the land owner. He has collected an

amount of Rs. 77,000/- as compensation /poverty allowance and relocation allowance current status

is as under:

Page 11: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Mr. Muhammad Ramzan standing in front of his residence. Picture of new residence shall be furnished in

next quarterly report.

The 08 No. of Irrigation Department employees have been shifted to their new residences constructed under

New Khanki Barrage Project. The status of previous and current residences is as below.

Case No. 7. Mr. Abdul Hameed (Guage Reader) with his family at current residence.

Page 12: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No.8. Mr. Muhammad Mansha (Beldar) with his family at his current residence.

Case No. 9. Mr. Ghulam Abbas (Chowkidar) with family at his current residence.

Page 13: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No. 10. Mr. Faisal Mehmood (Naib Qasid) at his current residence.

Case No. 11. Mr. Muhammad Akram (Regulation Beldar) with family at his current residence.

Page 14: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No. 12. Mr. Muhammad Riaz (Boatman) with family at his current residence.

Case No.13. Mr. Liaqat Ali (Regulation Beldar) with family at his current residence.

Page 15: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No. 14. Mr. Walayat Hussain (Head Boatman) with family at his current residence.

The remaining 07 No. of Irrigation employees (case No. 15 to 21) shall be shifted to their new residences in

the month of February 2016.

Case No.15

Mr. Muhammad Shabbir (Beldar) is living in Government residence that needs to be relocated at the

earliest. Under NKBP new residence is near completion. He will be relocated to new allocated

building and get relocation allowance of Rs. 5,000/-.

Case No. 15. Mr. Muhammad Shabbir (Beldar) standing in front of his current residence

Page 16: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No.16

Mr. Muhammad Mushtaq (Beldar) is living in Government residence that needs to be relocated at the

earliest. Under NKBP new residence is near completion. He will be relocated to new allocated

building and get relocation allowance of Rs. 5,000/-.

Case No. 16. Mr. Muhammad Mushtaq(Beldar) standing in front of his current residence

Case No.17

Mr. Ashraf Masih (Sweeper) is living in Government residence that needs to be relocated at the

earliest. Under NKBP new residence is near completion. He will be relocated to new allocated

building and get relocation allowance of Rs. 5,000/-.

Case No. 17. Mr. Ashraf Masih(Sweeper), standing in front of his current residence.

Page 17: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No.18

Mr. Amanat Ali (Painter) is living in Government residence that needs to be relocated at the earliest.

Under NKBP new residence is near completion. He will be relocated to new allocated building and

get relocation allowance of Rs. 5,000/-.

Case No. 18. Amanat Ali (Painter) standing in front of his current residence.

Case No.19

Mr. Sibt Ul Hassan (Sub Engineer) is living in Government residence that needs to be relocated at

the earliest. Under NKBP new residence is near completion. He will be relocated to new allocated

building and get relocation allowance of Rs. 5,000/-.

Case No. 19. Sibt Ul Hassan (Sub Engineer) standing in front of his current residence

Page 18: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Case No.20

Mr. Rana Ayub ((Sub Engineer)) is living in Government residence that needs to be relocated at the

earliest. Under NKBP new residence is near completion. He will be relocated to new allocated

building and get relocation allowance of Rs. 5,000/-.

Case No. 20. Rana Ayub (Sub Engineer) standing in front of his current residence

Case No.21

Mr. Muhammad Shabir (Sub Engineer) is living in Government residence that needs to be relocated

at the earliest. Under NKBP new residence is near completion. He will be relocated to new allocated

building and get relocation allowance of Rs. 5,000/-.

Case No. 21. Muhammad Shabir (Sub Engineer) standing in front of his current residence

Page 19: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

5. GRIEVENCE REDRESSAL MECHANISM

Tranche-2 also has an operational Grievance Redressal Mechanism that covers all types of

grievances of NKBP, including resettlement. Complaint register is also being maintained by the

Consultants to record community concerns and their solutions. Out of 27 complaints, 17 complaints

have been resolved while 12 complaints are yet to be resolved. The detail of complaints is given in

Annex-F.

Page 20: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Status of Settlement of Complaints

Annex –A

Sr# Date Complainant Location Sort of Complain Status

1 10/2/14 Imtiaz Ahmed

Lundpur

/complete

address

Demand for Culverts at

Chanawan Road Resolved

2 1/1/15 Zubair Ahmad BurjCheema

Demand for

Culverts/186+36 and

192+32 /Chanawan Road

Resolved

3 10/1/15 MansoorWarraich ThatthiBaloch

Demand for

Culverts134+71/Chanawan

Road

Resolved

4 5/1/14 Khizar Hayat ThatthiBaloch

Demand for

Culverts/115+70Chanawan

Road

Resolved

5 10/12/14 NaseemHussain ThatthiBaloch

Demand for

Culverts/84+93/Chanawan

Road

Resolved

6 15/12/14 Master Shafqat Ali Faqiranwali

Demand for

Culverts/56+37/Chanawana

Road

Resolved

7 14/10/14 Farooq Akbar Cheema LCC Increase the rate of land

/LCC In Process

8 26/12/14 Dr. AzharIqbalCheema KotJaffar Small Bridge /Gunayanwala

to KotJaffar Road Resolved

9 1/12/14 Rana Muhammad Khan BurjDhalla

Demand for

Culverts/19+200/ Chanawan

Road 21+150

Resolved

10 Repeated

App Dr. AzharIqbalCheema KotJaffar No 8 Applicaton Repeated. Resolved

11 12/4/15 GhulamSarwarCheema BurjCheema Demand for

Culverts/Chanawan Road Resolved

12 21/05/15 Head Mistress Girls

School Khanki Play Ground/ Khanki In Process

13 16/5/15 GhulamRasool Ratowali /Jamil

Town

Cemented Ramp & Soling

/LMB Road In Process

14 21/5/15 Farooq Akbar Cheema Kot Imam Bux Drainage of flood

water/Chanawan Road In Process

15 14/5/15 Umer Hayat BurjDhalla Demand for

Culverts/Chanawan Road Solved

16 8/6/15 Hafiz SaifUllahChatta KotRatta Speed Breaker/ Footpath

/Chanawan Road In Process

17 9/6/15 Muhammad

AslamRandhawa KorRatta Outlet /Chanawan Road In Process

18 8/6/15 Haji

AmjadPervaizRandhawa KorRatta

Repair the old bridge

/Chanawan Road In Process

19 7/6/15 PervaizIqbalBhatti KotRatta Repair the old In Process

Page 21: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

bridge/Chanawan Road

20 9/6/15 XEN Irrigation Khanki Boundary wall / Play

Ground/Irrigation Colony

Approved by

PMO

21 6/4/15 Master NasirMahmood KotRatta Change the location of

culvert/Chanawan Road Resolved

22 11/4/15 WaqasChatta Advocate Lundpur Court Case /Chanawan Road Resolved

23 9/7/15 SDO Headworks Khanki Breakage of High Level

Channel Resolved

24 7/7/15 Umer Hayat BurjDhalla Hurdle on Chanawan Road In Process

25 14/7/15 Farooq Akbar Cheema Khanki Drainage of Rain water from

crops Resolved

26 22/7/15 Amanat Ali Khanki Standing Rain Water in

Colony Resolved

27 28/7/15 SDO Headworks Khanki Breakage of High Level

Channel Resolved

28 19/11/2015 Sibt-Ul-Hassan Khanki Boundary Wall of New

Irrigation Colony In Process

Page 22: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Annex –B

Implementation of LARP for New Khanki Barrage as of September 2015

Contract No. 2841-PAK

Sr.

No

Contract

No.

Status of

Preparation,

vetting and

approval of

RP

No.

of

AFs

Payment

Due

(PKR in

million)

Total

AFs

paid

Amount

Paid

(PKR in

million)

%

Implementation

%

Amount

Paid Remarks

1 2841-PAK

LARP for

LCC Lead

Channel

Component

(under

NKBP)

Draft LARP

of LCC Lead

Channel was

prepared

and

approved in

2012. Later

on LARP was

revised,

updated and

cleared by

ADB in Feb,

2014

21 13.446 19 3.987 90.47% 29.65 Cost of

6.625 @

1,200,000 is

amounting

to Rs.

7,950,000

while PMO

has

deposited

Rs. 9.925

(million) to

the

Revenue

Department

for

payment to

the land

owner

Page 23: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Adjustment made in Compensation Rates in LARP July, 2014

Annex - C

Sr. No.

Description Unit Unit Rate of LARP 2012

Unit Rate of updated LARP 2014

Remarks

A) Mouza -Wise Acquisition of Private Land I) Khanki Acres 0.474(Rs.Million) 1.2(Rs. Million)

The rates of 2012 were not applicable in

2014 so, after Consultation with

Revenue and Agriculture

Department, rate for land and crop

compensation were updated, while rates for structures and,

other i.e. Tree

compensation and livelihood assistance are

still applicable in 2015-16.

Therefore, there is no much changes

recognized for D, E, F and G up till

now.

B) Land Acquisition Compulsory Surcharge (15%)

- - -

C) Crop Compensation

Rabi Acres 32,236 42,000

Kharif Acres 54,373 82,000

D) Residential Structures (Houses)

Sq. ft. Rs.675/sqft Rs.675/sqft

- i) Pacca structure Sq. ft. - - - ii) Semi-Pacca structures - Sq. ft. - - - iii) Katcha/ thatched shed - Sq. ft. - -

E) Others - - - i) Cattle Yard Sq. ft. Rs.675/sqft Rs.675/sqft

ii) Borehole of a tube well / drilling

No 148000/ bore 148000/ bore

iii) Hand pump No 0.01 0.01

Cost of W/C 1 community ,Private

Meters 1445/m 1445/m

F) Tree Compensation

Fruit Trees

No 4208.33 4208.33

Timber wood trees

No 1663.16 1663.16

G) Livelihood Assistance - -

- Livelihood assistance to vulnerable families

- - -

a) impassion cash assistance /allowance equivalent to 6 months OPL adjustment amount , i.e.(Rs. 12000)

DFs 0.072 0.072

b) Relocation assistance Rs. 5000/- to be paid all the DPs requiring to move out of the ROW or Land acquired for the Project

DFs 0.005 0.005

Page 24: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

Annex-D

New Khanki Barrage Project (NKBP)

District Wise Skilled / Unskilled Labour for the Month of October 2015

Sr #

Districts

DESCON

Total

Sub Contractor TOTAL

Total

Remarks

Skilled Unskilled Skilled Unskilled Skilled Unskilled

Th

ree n

um

be

r o

f em

plo

ye

es f

rom

aff

ecte

d f

am

ilie

s a

re w

ork

ing

wit

h t

he

co

ntr

acto

rs

1 GUJRANWALA 140 125 265 48 37 188 162 350

2 HAFIZABAD 25 8 33 38 28 63 36 99

3 CHINIOT 3 0 3 3 0 3

4 SHEIKHUPURA 18 10 28 18 10 28

5 NANKANA 18 0 18 18 0 18

6 FAISALABAD 40 12 52 40 12 52

7 JHANG 21 9 30 21 9 30

8 TOBA TEK SINGH 9 4 13 9 4 13

9 Gujrat (Barrage

Adjoining Villages 138 56 194 42 32 180 88 268

Total 412 224 636 128 97 540 321 861

%age 68.10% 53.85% 62.29% 51.41% 75.19% 63% 59% 62%

Other Districts 193 192 385 121 32 314 224 538

Total Districts 605 416 1021 249 129 854 545 1399

59% is used during the month of October 2015

Page 25: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

New Khanki Barrage Project (NKBP) District Wise Skilled / Unskilled Labour for the Month of November 2015

Sr #

Districts

DESCON

Total

Sub Contractor

TOTAL Total

Remarks

Skilled Unskilled Skilled Unskilled Skilled Unskilled

1 GUJRANWALA 157 173 330 51 38 208

211 419

Th

ree n

um

be

r o

f em

plo

ye

es f

rom

aff

ecte

d f

am

ilie

s a

re w

ork

ing

wit

h

the c

on

tracto

rs

2 HAFIZABAD 31 12 43 40 31 71

43 114

3 CHINIOT 3 0 3 3 0

3

4 SHEIKHUPURA 18 10 28 18

10 28

5 NANKANA 22 0 22 22 0

22

6 FAISALABAD 44 12 56 44

12 56

7 JHANG 24 20 44 24

20 44

8 TOBA TEK

SINGH 11 4 15 11

4

15

9 Gujrat (Barrage

Adjoining Villages

188 71 259 38 28 226

99 325

Total 498 302 800 129 97 627

399

1026

%age 65.44% 54.51% 60.84% 53.09% 78.86% 62%

59%

61%

10 Other Districts 263 252 515 114 28 377

278 655

Total Districts 761 554 13515 243 123 1004

677

1681

59% is used during the month of November 2015

Page 26: Social Monitoring Report PAK: Punjab Irrigation ...€¦ · December 2015 PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841 Internal Resettlement

NKBP Internal Resettlement Monitoring Report

PMO For Punjab Barrages

New Khanki Barrage Project (NKBP)

District Wise Skilled / Unskilled Labour for the Month of December 2015

Sr #

Districts DESCON

Total Sub Contractor TOTAL

Total

Remarks

Skilled Unskilled Skilled Unskilled Skilled Unskilled

Th

ree n

um

be

r o

f em

plo

ye

es f

rom

aff

ecte

d f

am

ilie

s a

re w

ork

ing

wit

h t

he

co

ntr

acto

rs

1 GUJRANWALA 207 178 385 51 38 258 216 474

2 HAFIZABAD 41 16 57 40 31 81 47 128

3 CHINIOT 9 0 9 9 0 9

4 SHEIKHUPURA 30 14 44 30 14 44

5 NANKANA 24 0 24 24 0 24

6 FAISALABAD 68 12 80 68 12 80

7 JHANG 36 33 69 36 33 69

8 TOBA TEK

SINGH 29 8 37 29 8 37

9

Gujrat (Barrage Adjoining Villages 292 101 393 38 28 330 129 459

Total 736 362 1098 129 97 865 459 1324

%age 68.21% 58.96% 64.86% 42.57% 70.80% 63% 61% 62%

10 Other Districts 343 252 595 174 40 517 292 809

Total Districts 1079 614 1693 303 137 1382 751 2133

59% is used during the month of December 2015