8/2/2019 Social Hub Test Plan
1/24
1
Social Hub Release 1.0
Software Test Plan
Version TP 1.0
March 19, 2012
Submitted By:
-
8/2/2019 Social Hub Test Plan
2/24
2
Revision History
Date Version Description Author
-
8/2/2019 Social Hub Test Plan
3/24
3
Table of Content
1. Test Plan Identifier ..5
2.
Introduction .....52.1Team Interaction ...5
3. Objective and Scope ....53.1Objective...5
3.1.1 Primary Objective..5
3.1.2 Secondary Objective. .63.2 Scope ....6
4. Risk ...6
4.1Schedule ....6
4.2Technical ...64.3Management ..6
4.4
Personnel ...74.5Requirements .7
5. Features and Functions to Test76. Features and Functions not to Test..7
7. Process Overview 8
8. Testing Process 99. Testing Strategy ...9
9.1Usability Testing .11
9.2Unit Testing.11
9.2.1 White Box Testing ...119.2.2 Black Box Testing ...11
9.3
Iteration/Regression Testing...119.4System Testing129.4.1 Performance Testing12
9.5Final Release Testing ..12
9.6Testing completeness Criteria.13
-
8/2/2019 Social Hub Test Plan
4/24
4
10. Test Levels ...13
10.1 Build Tests .1310.1.1 Level 1 - Build Acceptance Tests13
10.1.2 Level 2 - Smoke Tests.13
10.1.3 Level 2a - Bug Regression Testing13
10.2 Milestone Tests ..1410.1.4 Level 3 - Critical Path Tests...14
10.3 Release Tests.. 14
10.3.1 Level 4 - Standard Tests.1410.3.2 Level 5 - Suggested Test.14
11. Suspension / Exit Criteria.14
12. Resumption Criteria .1513. Bug Tracking/ Bug Process. .15
13.1 Various Roles in Bug Resolution ...15
14. Test Deliverables ...16
14.1
Deliverables Matrix ...1614.2Documents .17
14.2.1 Test Approach Document1714.2.2 Test Plan ..17
14.2.3 Test Schedule ..18
14.2.4 Test Specifications Requirements Traceability Matrix...1815. Remaining Test Tasks ..18
16. Resource & Environment Needs ..19
16.1Data Entry workstations .19
16.2Main Frame1917. Staffing and Training Needs.19
18. Roles and Responsibilities20
19.
Schedule ...21
20. Planning Risks and Contingencies ...2121. Approvals .22
22. Glossary 23
23. References 23
-
8/2/2019 Social Hub Test Plan
5/24
5
1. Test Plan IdentifierSocial Hub Release 1.0 TP 1.0
Note, the structure of this document is primarily based on the IEEE 829-2008 Standardfor Software Test Documentation.
2. IntroductionThis document is a high-level overview defining testing strategy for the Social Hub(Release 1.0) Project. Its objective is to communicate project-wide quality standards and
procedures. It represents a snapshot of the project as of the end of the planning phase.
This document will address the different standards that will apply to the unit, integration
and system testing of the specified application. We will utilize testing criteria under thewhite box, black box, and system-testing paradigm. This paradigm will include, but is
not limited to, the testing criteria, methods, and test cases of the overall design.Throughout the testing process we will be applying the test documentation specificationsdescribed in the IEEE Standard 829 for Software Test Documentation.
2.1Team InteractionThe following describes the level of team interaction necessary to have a successful
product.
The Test Team will work closely with the Development Team to achieve a highquality design and user interface specifications based on customer requirements.
The Test Team is responsible for visualizing test cases and raising quality issuesand concerns during meetings to address issues early enough in the development
cycle.
The Test Team will work closely with Development Team to determine whetheror not the application meets standards for completeness. If an area is not
acceptable for testing, the code complete date will be pushed out, giving thedevelopers additional time to stabilize the area.
-
8/2/2019 Social Hub Test Plan
6/24
6
3 Objective and Scope3.1Objective
3.1.1
Primary Objective
A primary objective of testing application systems is to: assure that the system meets the
full requirements, including quality requirements (AKA: Non-functional requirements)
and fit metrics for each quality requirement and satisfies the use case scenarios and
maintain the quality of the product. At the end of the project development cycle, the usershould find that the project has met or exceeded all of their expectations as detailed in the
requirements.
Any changes, additions, or deletions to the requirements document, FunctionalSpecification, or Design Specification will be documented and tested at the highest level
of quality allowed within the remaining time of the project and within the ability of thetest team.
3.1.2 Secondary Objective
The secondary objective of testing application systems will be to: identify and expose allissues and associated risks, communicate all known issues to the project team, and ensure
that all issues are addressed in an appropriate matter before release. As an objective, this
requires careful and methodical testing of the application to first ensure all areas of the
system are scrutinized and, consequently, all issues (bugs) found are dealt with
appropriately.
3.2ScopeThe Social Hub (Release 1) Test Plan defines the unit, integration, system, regression,
and Client Acceptance testing approach. The test scope includes the following:
Testing of all functional, application performance, security and usecases requirements listed in the Use Casedocument.
Quality requirements and fit metricsto the project.
End-to-end testing and testing of interfaces of all systems that interact
with the project.
4 Risks4.1Schedule
-
8/2/2019 Social Hub Test Plan
7/24
7
The schedule for each phase is very aggressive and could affect testing. A slip in the
schedule in one of the other phases could result in a subsequent slip in the test phase.Close project management is crucial to meeting the forecasted completion date.
4.2TechnicalSince this is a new system to assist the public. In the event of a failure there is no
option of old system which can be used. We will run our test on new application not
depend on existing system.
4.3ManagementManagementsupport is required so when the project falls behind, the test schedule
does not get squeezed to make up for the delay. Management can reduce the risk ofdelays by supporting the test team throughout the testing phase and assigning
people to this project with the required skills set.
4.4PersonnelDue to the aggressive schedule, it is very important to have experienced testers on
this project. Unexpected turnovers can impact the schedule. If attrition does happen,
all efforts must be made to replace the experienced individual.
4.5RequirementsThe test plan and test schedule are based on the current Requirements Document. Any
changes to the requirements could affect the test schedule and will need to beapproved.
5 Features and Functions to TestTesting will consist of several phase each phase may or may not include testing of
anyone or more of the following aspects of the Social Hub (Release 1.0) (listed
alphabetically):
Accessibility
Audit
Availability
Coding standards Compatibility
Content
Functional
Legal
Marketing
Navigation
-
8/2/2019 Social Hub Test Plan
8/24
8
Performance
Reliability
Scalability
Security
Site recognition
Usability
6 Features and Functions Not to TestIt is the intent that all of the individual test cases contained in each test plan will be
performed.
However, if time does not permit, some of the low priority test cases may be dropped.
7 Process OverviewThe following represents the overall flow of the testing process:
1. Identify the requirements to be tested. All test cases shall be derived using the
current Program Specification.
2. Identify which particular test(s) will be used to test each module.
3. Review the test data and test cases to ensure that the unit has been thoroughly
verified and that the test data and test cases are adequate to verify proper
operation of the unit.
4.
Identify the expected results for each test.
5. Document the test case configuration, test data, and expected results.
6. Perform the test(s).
7. Document the test data, test cases, and test configuration used during the testing
process. This information shall be submitted via the Unit/System Test Report
(STR).
8. Successful unit testing is required before the unit is eligible for component
integration/system testing.
9. Unsuccessful testing requires a Bug Report Form to be generated. This documentshall describe the test case, the problem encountered, its possible cause, and the
sequence of events that led to the problem. It shall be used as a basis for later
technical analysis.
-
8/2/2019 Social Hub Test Plan
9/24
9
10.Test documents and reports shall be submitted. Any specifications to be reviewed,
revised, or updated shall be handled immediately.
8 Testing Process
Figure 1: Test Process Flow
The diagram above outlines the Test Process approach that will be followed.
a. Organize Project involves creating a System Test Plan, Schedule & Test
Approach, and assigning responsibilities.
b. Design/Build System Test involves identifying Test Cycles, Test Cases, Entrance& Exit Criteria, Expected Results, etc. In general, test conditions/expected results
will be identified by the Test Team in conjunction with the Development Team.
The Test Team will then identify Test Cases and the Data required. The Testconditions are derived from the Program Specifications Document.
c. Design/Build Test Procedures includes setting up procedures such as Error
Management systems and Status reporting.
d. Build Test Environment includes requesting/building hardware, software and
data set-ups.
e. Execute System Tests The tests identified in the Design/Build Test Procedures
will be executed. All results will be documented and Bug Report Forms filled outand given to the Development Team as necessary.
f. Signoff- Signoff happens when all pre-defined exit criteria have been achieved.
9 Testing StrategyThe following outlines the types of testing that will be done for unit, integration, and
system testing. While it includes what will be tested, the specific use cases thatdetermine how the testing is done will be detailed in the Test Design Document. The
template that will be used for designing use cases is shown in Figure 2.
a. Organize
Project
b. Design SystemTest
c. Design/Build
Test Proc.
d. Build TestEnvironment
e. Execute
system Test.f. Signoff
-
8/2/2019 Social Hub Test Plan
10/24
10
Tested By:
Test Type
Test Case NumberTest Case Name
Test Case Description
Item(s) to be tested
1
2
Specifications
Input
ExpectedOutput/Result
Procedural Steps
1
2
3
4
5
6
7
Figure 2: Test Case Template
-
8/2/2019 Social Hub Test Plan
11/24
11
9.1Usability TestingThe purpose of usability testing is to ensure that the new components and features will
function in a manner that is acceptable to the customer.Development will typically create a non-functioning prototype of the UI components to
evaluate the proposed design. Usability testing can be coordinated by testing, but actual
testing must be performed by non-testers (as close to end-users as possible). Testing
will review the findings and provide the project team with its evaluation of the impactthese changes will have on the testing process and to the project as a whole.
9.2Unit Testing (Multiple)Unit Testing is conducted by the Developer during code development process to ensurethat proper functionality, language-specific programming errors such as bad syntax, logic
errors and code coverage have been achieved by each developer both during coding and
in preparation for acceptance into iterations testing. The unit test cases shall be designedto test the validity of the programs correctness.
The following are the example areas of the project must be unit-tested and signed-offbefore being passed on to regression Testing:
Databases, Stored Procedures, Triggers, Tables, and Indexes
NT Services
Database conversion
.OCX, .DLL, .EXE and other binary formatted executable.
9.2.1
White Box Testing
In white box testing, the UI is bypassed. Inputs and outputs are tested directly at the code
level and the results are compared against specifications. This form of testing ignores thefunction of the program under test and will focus only on its code and the structure of that
code. Test case designers shall generate cases that not only cause each condition to take
on all possible values at least once, but that cause each such condition to be executed atleast once. To ensure this happens, we will be applying Branch Testing. Because the
functionality of the program is relatively simple, this method will be feasible to apply.
9.2.2 Black Box TestingBlack box testing typically involves running through every possible input to verify that it
results in the right outputs using the software as an end-user would. It includes
performing Equivalence Partitioning and Boundary Value Analysis testing.
9.3Iteration/Regression Testing
-
8/2/2019 Social Hub Test Plan
12/24
12
During the repeated cycles of identifying bugs and taking receipt of new builds
(containing bug fix code changes), there are several processes which are common to thisphase across all projects. These include the various types of tests: functionality,
performance, stress, configuration, etc. There is also the process of communicating
results from testing and ensuring that new drops/iterations contain stable fixes
(regression). The project should plan for a minimum of 2-3 cycles of testing(drops/iterations of new builds).
At each iteration, a debriefing should be held. Specifically, the report must show that tothe best degree achievable during the iteration testing phase, all identified severity 1 and
severity 2 bugs have been communicated and addressed. At a minimum, all priority 1
and priority 2 bugs should be resolved prior to entering the beta phase.
9.4System TestingThe goals of system testing are to detect faults that can only be exposed by testing the
entire integrated system or some major part of it. Generally, system testing is mainlyconcerned with areas such as performance, security, validation, load/stress, and
configuration sensitivity. But in our case well focus only on function validation andperformance. And in both cases we will use the black-box method of testing.
9.4.1 Performance TestingThis test will be conducted to evaluate the fulfillment of a system with specified
performance requirements. It will be done using black-box testing method. And this will
be performed by:
Storing the maximum data in the file and trying to insert, and observe how the
application will perform when it is out of boundary. Deleting data and check if it follows the right sorting algorithm to sort the
resulting data or output.
Trying to store new data and check if it over writes the existing once.
Trying to load the data while they are already loaded
9.5Final Release TestingTesting team with end-users participates in this milestone process as well by providingconfirmation feedback on new issues uncovered, and input based on identical or similar
issues detected earlier. The intention is to verify that the product is ready for distribution,
acceptable to the customer and iron out potential operational issues.
Assuming critical bugs are resolved during previous iterations testing- Throughout the
Final Release test cycle, bug fixes will be focused on minor and trivial bugs (severity 3
and 4). Testing will continue its process of verifying the stability of the application
through regression testing (existing known bugs, as well as existing test cases).
-
8/2/2019 Social Hub Test Plan
13/24
13
9.6Testing completeness CriteriaRelease for production can occur only after the successful completion of the applicationunder test throughout all of the phases and milestones previously discussed above.
The milestone target is to place the release/app (build) into production after it has beenshown that the app has reached a level of stability that meets or exceeds the client
expectations as defined in the Requirements, Functional Specifications.
10Test LevelsTesting of an application can be broken down into three primary categories and several
sub-levels. The three primary categories include tests conducted every build (Build
Tests), tests conducted every major milestone (Milestone Tests), and tests conducted atleast once every project release cycle (Release Tests). The test categories and test levels
are defined below:
10.1 Build Tests10.1.1 Level 1 - Build Acceptance Tests
Build Acceptance Tests should take less than 2-3 hours to complete (15 minutes is
typical). These test cases simply ensure that the application can be built and installedsuccessfully. Other related test cases ensure that adopters received the proper
Development Release Document plus other build related information (drop point, etc.).
The objective is to determine if further testing is possible. If any Level 1 test case fails,the build is returned to developers un-tested.
10.1.2 Level 2 - Smoke Tests
Smoke Tests should be automated and take less than 2-3 hours (20 minutes is typical).These tests cases verify the major functionality a high level.
The objective is to determine if further testing is possible. These test cases should
emphasize breadth more than depth. All components should be touched, and every majorfeature should be tested briefly by the Smoke Test. If any Level 2 test case fails, the build
is returned to developers un-tested.
10.1.3 Level 2a - Bug Regression Testing
Every bug that was Open during the previous build, but marked as Fixed, Needs Re-
Testing for the current build under test, will need to be regressed, or re-tested. Once the
smoke test is completed, all resolved bugs need to be regressed. It should take between 5
minutes to 1 hour to regress most bugs.
-
8/2/2019 Social Hub Test Plan
14/24
14
10.2 Milestone Tests10.2.1 Level 3 - Critical Path Tests
Critical Path test cases are targeted on features and functionality that the user will see anduse every day.
Critical Path test cases must pass by the end of every 2-3 Build Test Cycles. They do notneed to be tested every drop, but must be tested at least once per milestone. Thus, the
Critical Path test cases must all be executed at least once during the Iteration cycle, and
once during the Final Release cycle.
10.3 Release Tests10.3.1 Level 4 - Standard Tests
Test Cases that need to be run at least once during the entire test cycle for this release.
These cases are run once, not repeated as are the test cases in previous levels. FunctionalTesting and Detailed Design Testing (Functional Spec and Design Spec Test Cases,
respectively). These can be tested multiple times for each Milestone Test Cycle
(Iteration, Final Release, etc.).Standard test cases usually include Installation, Data, GUI, and other test areas.
10.3.2 Level 5 - Suggested Test
These are Test Cases that would be nice to execute, but may be omitted due to timeconstraints.
Most Performance and Stress Test Cases are classic examples of Suggested test cases
(although some should be considered standard test cases). Other examples of suggestedtest cases include WAN, LAN, Network, and Load testing.
11Suspension / Exit CriteriaIf any defects are found which seriously impact the test progress, the QA manager may
choose toSuspend testing. Criteria that will justify test suspension are:
Hardware/software is not available at the times indicated in the project schedule.
Source code contains one or more critical defects, which seriously prevents or limitstesting progress.
Assigned test resources are not available when needed by the test team.
12Resumption Criteria
-
8/2/2019 Social Hub Test Plan
15/24
15
If testing is suspended, resumption will only occur when the problem(s) that caused the
suspension has been resolved. When a critical defect is the cause of the suspension, the
FIX must be verified by the test department before testing is resumed.
13Bug Tracking/ Bug ProcessDuring testing, the testing team members normally encounter behavior that goes against a
specified or implied design requirement in the product. When this happens, we will
document and reproduce the bugs for the developers.
Expectation of a bug:
Keep track of what version of the application the bug is found
Determine if bug has already been written up
Indicate the steps to reproduce the bugwrite enough details for others looking atthe bug to be able to duplicate it; exclude unnecessary steps (i.e. If access point is
irrelevant, be more general in your steps). Actual resultsbe specific on your findings.
Expected resultshow the product should behave based on the specified orimplied requirements.
ImplicationsHow does the defect affect the quality of the product?
The following chart defines the impact levels to be used when entering bugs.
Impact Definitions
1Fatal Test Stopper: If you cant access a function and need the bug to be fixed
immediately. The defect prevents QA from testing the feature area, sub-
area or functionality of the feature.2Serious Beta Stopper: This is a bug that users would experience such as: data
corruption, calculation errors, incorrect data, UEs and system crash oncommon user scenarios, significant QA risk, and major UI defects.
3Minor Live Release: A bug that must be fixed before the product is officiallycompleted, UEs or crashes, content, and UI and graphic changes required
for release.
13.1 Various Roles in Bug Resolution AuthorThe person who wrote the bug; this will be someone on the QA team
Resolver
Normally an Engineer assigned to a specific area of the application. VerifierNormally a QA Engineer responsible for testing the fix and closing the
bug.
14Test Deliverables
-
8/2/2019 Social Hub Test Plan
16/24
16
Testing will provide specific deliverables during the project. These deliverables fall into
three basic categories: Documents, Test Cases / Bug Write-ups, and Reports. Here is adiagram indicating the dependencies of the various deliverables:
As the diagram above shows, there is a progression from one deliverable to the next.Each deliverable has its own dependencies, without which it is not possible to fullycomplete the deliverable.
Program function specifications
Program source code
Test plan document - this document should address testing objectives, criteria,standards, schedule and assignments, and testing tools.
Unit Testing Plan
Integration Plan
System Testing Plan
Test Design Document
Unit white-box test designcovers white testing criteria, methods and testcases
Require-ments [PM]
Project Plan
[PM]
Functional
Spec [PM]
Test Plan Test Spec.
/ Outline
Detailed
Design[Dev]
Test
Cases
Bugs
Bug
Results
TC CoverageReports
Bug Reports
Weekly
Status
Reports
Test Case
Results
-
8/2/2019 Social Hub Test Plan
17/24
17
Unit black-box test designcovers black-box testing criteria, methods andtest cases
System test designcovers system test criteria, methods, and test cases,scripts.
Test report document Unit white-box test reportcovers unit white box test results, problems,
summary and analysis
Unit black-box test reportcovers unit black box test results, problems,summary and analysis
System Test reportcovers system test results, problems, summary andanalysis
15Remaining Test TaskTask Assigned To Status
Create Acceptance Test Plan TM, PM, Client
Create System/Integration Test
Plan
TM, PM, Dev.
Define Unit Test rules and
Procedures
TM, PM, Dev.
Define Turnover procedures for
each level
TM, Dev
Verify prototypes of Screens Dev, Client, TM
Verify prototypes of Reports Dev, Client, TM
16 Test EnvironmentsThere are essentially two parts to the Social Hub application in production: the client-side, which because the application is going to accessed over the Internet by members of
the general public, Social Hub has little control over. And the server-side which (initially)
will be comprised of a single cluster of servers residing at Social Hubs corporate center.
Available Client-side Environment
Social Hub will utilize set of desktop and laptop machines, which currently consists ofthe following machine specifications:
Low-end PC
Processor: Pentium4 (2.4 GHz)
-
8/2/2019 Social Hub Test Plan
18/24
18
RAM: 512 MB
Hard Disk Drive: 40 GBMonitor: 17 Color Screen (default 1024 x 76816 bit color)
56.6kps Modem or 100MB Ethernet Internet connection typically running
Windows XP or Windows 2000 Professional
The following Windows based Browsers are readily available for installation on any of
the client platforms:
Internet Explorer ofMicrosoft CorporationFirefox (also called Mozilla Firefox) ofMozilla Corporation
Chrome ofGoogle
Opera ofOpera Software ASANetscape Navigator ofNetscape Communications Corporation (now part of AOL)
SeaMonkey ofMozilla Foundation
Maxthon Browser ofMaxthon
Browser settings (cache size, # of connections, font selection etc.) where possible wereleft unchanged
i.e. the installation defaults were used for all testing. No optional Plug Ins will beinstalled.
Available Server-side Environments
In addition to the cluster of servers used for production, two functionally exact replicas of
the serverside production environment will be created and maintained. The development
team will use one replica for unit and integration testing, while the second replica will bereserved for system testing by the testing team. Prior to a new release being put into
production, the Web application will be moved to a staging area on the production system
where a final series of acceptance tests can be performed.
While the replica systems will be functionally the same as the production environmente.g. same system software installed in the same order, with the same installation options
selected etc. Due to budget constraints, the replicas will be scaled down versions of the
production system (e.g. instead of several Web servers, there will only be one) and in thecase of the unit/integration replica, the hardware specifications may not be exactly the
same.
In addition, several network file and print servers will be made available (on a limitedbasis) for the testing team to use as load generators during performance tests.
Available Testing Tools
The following 3rd party free tools were available to scan the Web site and providefeedback:
Bobby (accessibility, performance & html syntax)cast.org
Freeappraisal (performance from 35 different cities)keynote.com Scrubby (meta tag analyzer)scrubtheweb.com
Site analysis (search engine ratings)site-see.com
Stylet (style sheet validation)microsoft.com
http://windows.microsoft.com/en-US/internet-explorer/products/ie/homehttp://windows.microsoft.com/en-US/internet-explorer/products/ie/homehttp://www.mozilla.com/en-US/firefox/new/http://www.google.com/chrome/intl/en/landing_chrome.html?hl=enhttp://www.google.com/chrome/intl/en/landing_chrome.html?hl=enhttp://www.opera.com/http://www.opera.com/http://isp.netscape.com/http://isp.netscape.com/http://www.seamonkey-project.org/http://www.seamonkey-project.org/http://www.maxthon.com/http://www.maxthon.com/http://www.seamonkey-project.org/http://isp.netscape.com/http://www.opera.com/http://www.google.com/chrome/intl/en/landing_chrome.html?hl=enhttp://www.mozilla.com/en-US/firefox/new/http://windows.microsoft.com/en-US/internet-explorer/products/ie/home -
8/2/2019 Social Hub Test Plan
19/24
19
Tune up (performance & style checker) & gif lube (gif analyzer)websitegarage.com
Websat (usability)nist.gov Web metasearch (search engine ratings)dogpile.com
Webstone (performance benchmarking tool) - mindcraft.com
Windiff (file comparison)microsoft.com
W3C validation service (html and css syntax)w3c.org
In addition the following commercial tools were available:
Aetgweb (pair-wise combinations) from Telcordia/Argreenhouse Astra Site Manager (linkage) from Mercury Interactive
eTester suite (capture/reply, linkage & performance) from RSW 100 virtual user
license FrontPage (spell checking) from Microsoft
Ghost (software configuration) from Symatec
KeyReadiness (large scale performance testing) from Keynote systems
LinkBot Enterprise (link checking, HTML compliance and performance estimates) from
Watchfire Prophecy (large scale performance testing) from Envive
WebLoad (performance) from Radview1000 virtual user license Word (readability estimates) from Microsoft
A manual digital stopwatch was also available.
17 Staffing and Training NeedsIf a separate test person is not available the project manager/test manager will assume this
role.In order to provide complete and proper testing the following areas need to be addressed
in terms of training if not experienced: General development & testing techniques
Web site development lifecycle methodology
All development and automated testing tools that they may be required to use
The administration staff will require training on the new screens and reports.
18 Roles and ResponsibilitiesTesting Team
Test Manager
Ensure Phase 1 is delivered to schedule and quality
Produce high level and detailed test conditions
Produce expected results
Report progress at regular status reporting meetings
Co-ordinate review and signoff of test conditions
Manage individual test cycles and resolve tester queries/problems.
-
8/2/2019 Social Hub Test Plan
20/24
20
Tester
Identify test data
Execute test conditions and mark-off results
Prepare software error reports
Administrate error measurement system Ensure test systems outages/problems are reported immediately and followed up.
Ensure entrance criteria are achieved prior to system test start.
Ensure exit criteria are achieved prior to system test signoff.
19ScheduleThe section contains the overall project schedule. It discusses the phases and key
milestones as they relate to quality assurance. It discusses the testing goals and standards
that wed like to achieve for each phase of testing that will be deployed, e.g ., Usability
Testing, Code Complete Acceptance, Beta Testing, Integration Testing, Regression
Testing, System Testing.The key dates for overall development and Testing are outlined below.
Milestones End Date Notes QA Deliverables/Roles
Planning Phase 00/00/00 At this Milestone, the high level
planning should be completed. Some
of the deliverables are: Project Plan,
Program function specifications.
High-level test planning activities,
which include preliminary
development of Master QA Plan (this
document, QA schedule.
Design Phase This is a feature-driven milestone
where the requirements and initiatives
are further defined and solutions arefinalized. The deliverables for this
phase are Program source code and
other design related documents.
Development and Test engineers
participate actively in feature design
by inspecting and reviewing therequirements and design documents.
As the design documents are
completed, the test engineers are
encouraged to start working on the
Test Plan document and test design
planning.
Code Complete
-Infrastructure
This milestone is when all
infrastructure development and
functions should be complete. The
testing team should have performed
unit & integration testing before
checking the code into any build.
The Test Engineers should have
completed or in the final stages of
their preliminary Infrastructure Test
Plan, test cases and other QA
documents related to test execution
for each feature or component such
as test scenarios, expected results,
data sets, test procedures, scripts and
applicable testing tools.
Code Complete
-Function
This milestone includes unit testing and
code review of each function
component prior to checking the code
The Test Engineers should have
provided Code Complete Assessment
Test to Development Engineer one
-
8/2/2019 Social Hub Test Plan
21/24
21
Milestones End Date Notes QA Deliverables/Roles
into the test phase. The deliverables
include system-testing specification,
Unit testing specifications, Integration
plan.
week prior to Code Complete Review
date. The Test Engineers should also
have completed or in the final stages
of their preliminary White Box TestPlan, test cases and other QA
documents related to test execution
for each feature or component such
as test scenarios, expected results,
data sets, test procedures, scripts and
applicable testing tools.
Beta Ready This milestone represents that all
features are ready for Beta release
shutdown.
2 Weeks regression of Binary Tree
features to Beta and preparation for
Beta Shutdown.
Feature
Complete
This phase allows for feature clean up
to verify remaining bug fixes andregression testing around the bug fixes.
This milestone indicates that the
feature is ready for Beta regression.
All bugs verified and QA
documentation is finalized. The testEngineers should assess that Binary
Tree features are ready for Beta
regression and have started their
preliminary Test Summary Reports.
Regression Test This milestone represents that project
is ready for Regression Testing.
Complete regression test execution of
complete system and update Test
Summary Reports for regression.
Ship/Live 04/03/03 Product is out. Any unfinished Testing documents
should be complete.
.
20Planning Risks and ContingenciesThe following seeks to identify some of the more likely project risks and propose
possible
Contingencies:
Web site becomes unavailable Testing will be delayed until this situation isrectified - May need to recruit more staff to do the testing or reduce the number of
test cases.
Web testing software is not available/does not work (e.g. Web site uses cookiesand tool cannot handle cookies) - This will delay the introduction of automated
testing and result in more manual testing - May need to recruit more staff to dothe testing or reduce the number of test cases.
Testing staff shortages/unavailability, many of the test staff are part-time and haveother higher priorities, in addition no slack time is allocated for illness or vacation- May need to recruit more staff to do the testing or reduce the number of test
cases.
A large number of defects/incidents make it functionally impossible to run all ofthe test cases.
-
8/2/2019 Social Hub Test Plan
22/24
22
Not enough time to complete all test cases. If time cannot be extended, individualtest cases will be skipped, starting with the lowest priority
21ApprovalsName (Print) Signature Date
1.
2.
3.
4.
5.
-
8/2/2019 Social Hub Test Plan
23/24
23
22GlossaryTERM/ACRONM DEFINITION
API Application Program Interface
BCP Business Continuity Plan
Branch testing A white box test design technique in which test cases are
designed to execute branches.
CAT Client Acceptance Testing
Coverage The degree, expressed as a percentage, to which a specifiedcoverage item has been exercised by a test suite.
End-to End Testing Tests user scenarios and various path conditions by verifying
that the system runs and performs tasks accurately with the sameset of data from beginning to end, as intended.
N/A Not Applicable
QA Quality Assurance
Severity The degree of impact that a defect has on the development or
operation of a component or system.
SME Subject Matter Expert
SOP Standard Operating Procedure
STR System Test Report
TBD To Be DeterminedTSR Test Summary Report
23ReferencesPressman, Roger S. Software Engineering - A Practitioner's Approach. Fifth edition. The
McGraw-Hill companies, Inc.
Kaner, C., Falk, J., Nguyen, H.-Q. Testing Computer Software. Wiley Computer Publishing,
1999.
-