Snowtown Wind Farm Stage 2 Investor and Analyst Briefing 2626 … · 2012. 8. 27. · • 47 Suzlon...
Transcript of Snowtown Wind Farm Stage 2 Investor and Analyst Briefing 2626 … · 2012. 8. 27. · • 47 Suzlon...
Snowtown Wind Farm Stage 2 Snowtown Wind Farm Stage 2
Investor and Analyst BriefingInvestor and Analyst Briefing
2626 July 2012July 2012
Disclaimer
The information set out below relates to future matters, that are subject to a number of risks and uncertainties (many of which are beyond the control ofnumber of risks and uncertainties (many of which are beyond the control of TrustPower, which may cause the actual results, performance or achievements of TrustPower or the TrustPower Group to be materially different from the future results set out below The inclusion of the forwarddifferent from the future results set out below. The inclusion of the forward-looking information below should not be regarded as a representation or warranty by TrustPower, the directors of TrustPower or any other person that th f d l ki t t t ill b hi d th t th tithose forward-looking statements will be achieved or that the assumptions underlying any forward-looking statements will in fact be correct.
2Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Outline
• Key project information• Wind farm contract suite• Construction timetable• Approvals and regulatory framework• Project economics• Project economics• Financing• Sale of Snowtown 2 South – update
3Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Project summary
• Site located 140 km north of Adelaide
Project summary
• 100 MW Stage 1 commissioned in 2008 – 44% long-term capacity factor, prior to Stage 2g p y , p g
• Stage 2: 270 MW, split into two separate wind farms– 90 × 3 MW turbines– 48 turbines for Snowtown 2 North (144 MW) – 42 turbines for Snowtown 2 South (126 MW)
• Total expected project cost ≤ A$439m• Capacity factor for Stage 2≈ 42% (40% North and 44% South)p y g ( )
• PPAs cover 100% of Stage 2 output
4Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Site location and turbine layoutSite location and turbine layout
Direction of construction
Snowtown
5Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Key contracts• EPC Agreement – Siemens Ltd
Key contracts
– Siemens SWT-3.0-101/108 Direct Drive WTG– Covers full installation, to commissioning and handover
• Warranty and O&M Agreement (WOM) – Siemens Ltd– Comprehensive availability warranty and full service O&M coverage
for 15 years from first turbine handovery
• Power purchase agreements – Origin Energy Electricity Limited– Separate agreements for Snowtown 2 North and South with identical– Separate agreements for Snowtown 2 North and South, with identical
commercial terms– Agreements cover 100% of the energy and RECs– Expiry date 31 December 2030 with options to extend the energy– Expiry date 31 December 2030, with options to extend the energy
portion for a further five years at either a put or call price
6Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Key contracts cont.• Transmission Connection Agreement – ElectraNet Pty Ltd
Key contracts cont.
– 25-year agreement finalised
• Land– 25-year agreements in place with all 24 landowners– TrustPower will have the ability to repower the site at the end of these
agreementsg– Strong community and council support of the project
• Transmission line – Downer EDI Pty LtdTransmission line Downer EDI Pty Ltd– 28km transmission line (275 kV) to be constructed between wind
farms and the market connection point, a new substation on the Para-Bungama lineu ga a e
– Line and substation will be owned by Snowtown 2 North and shared by both wind farms
7Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Construction timetable
2012 2013 2014
Construction timetable
Financial Close and
2012 2013 2014
Q1 Q2 Q3 Q4 Q3 Q4 Q1 Q2 Q3 Q4
Notice to Proceed
Wind farm construction
Wind farm completion and handover
Transmission line and connection
KeyDesign, delivery and construction
Commissioning and reliability testing
Major milestoneand construction reliability testing
First h i ti
Snowtown S th l t
Snowtown N th l t
8Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
synchronisation South complete North complete
Approvals secured
D l t Pl i A l W k fi ld R CDevelopment Planning Approval Wakefield R.C.
Foreign Investment Approval FIRBForeign Investment Approval FIRB
Generation Licence ESCOSA
9Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Supporting regulatorySupporting regulatory framework
• Emission Reduction Target– Australia has committed to reducing greenhouse gas emissions to 5% g g g %
below 2000 levels by 2020
• Renewable Energy Target (RET)Renewable Energy Target (RET)– Australia’s Large-scale RET legislation is a key driver of renewable
investment– The Government is targeting 20% renewable electricity generation byThe Government is targeting 20% renewable electricity generation by
2020 (41,000 GWh)– Wind is likely to make up c. 75% of this total (≈ 9,700 MW, an
increase of 6,600 MW on current levels), )– The LRET scheme runs to 2030, which supports long-term PPAs
10Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Project economics
Turbine price PPA Currency Wind resource / technology matchtechnology match
Star alignment++
Swift execution=
Shareholder value
11Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Project economics cont.Project economics cont.Snowtown 2
SouthSnowtown 2
North
TotalSnowtown South North Stage 2
Capacity (A$m) 126 MW 144 MW 270 MW
Long term expected annualLong term expected annual yield(at market connection point)
481 GWh 504 GWh 985 GWh
C it f t 44% 40% 42%Capacity factor 44% 40% 42%
CAPEX (A$) 182m 257m 439m
(A$m/MW) 1.44 1.78 1.63
Assumed mid-life ref rbishment $400 000 $400 000 $400 000refurbishment (A$ per WTG, years 16-20)
$400,000 $400,000 $400,000
Ungeared Project IRR >15.0% >13.0% >13.5%
12Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefingRefer significant assumptions slide 21 and 22
Snowtown Stage 1Snowtown Stage 1A successful investment
• 47 Suzlon S88 turbines (98.7MW) plus prototype 2.1MW turbine
389 GWh long term• 389 GWh long term expected annual output
• Commissioned 2008
• 44% long term expected capacity factor before commissioning of Stage 2
13Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
commissioning of Stage 2
Snowtown Stage 1Snowtown Stage 1A successful investment
60%
Wind Farm Capacity Factors (SCADA Data)
30%
40%
50%
y Factor %
10%
20%
Capacity
0%
Aug‐09 Nov‐09 Feb‐10 May‐10 Aug‐10 Nov‐10 Feb‐11 May‐11 Aug‐11 Nov‐11 Feb‐12 May‐12
Snowtown Stage 1 Avg NEM WF CF (Excl Snowtown Stage 1)
• Snowtown forecast long term output expected to reduce by 19 GWh once Snowtown North constructed due to wind shading
• Capacity factor will reduce from 44% to just under 42%14Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
• Capacity factor will reduce from 44% to just under 42%
Financing – CommittedFinancing – Committed Sources of Funding
• TrustPower Group has committed debt facilities of
TrustPower Group Funding Sources (NZD millions) committed debt facilities of
close to NZ$ equivalent 1.5 billion
40118
238 NZD Bank238
674
NZD Bank
ECA Facility
Sub Bonds
Senior Bonds
240
AUD Bank
Unutilised Bank
186
15Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Financing – DebtFinancing – Debt Maturity
Debt Maturity (Including Commitment to Fund Snowtown II)
NZD/AUD 0 80
• Over the next 12 months long term $A f di ill b ht
500
600
700 NZD/AUD 0.80 funding will be sought
to refinance AUD bank facilities used for Snowtown Stage 2
300
400
500
NZD
million
Snowtown Stage 2
100
200
‐0‐1 1‐2 2‐3 3‐4 4‐5 5+
Years to Maturity
Subordinated Senior ‐ Drawn Senior ‐ Committed for Snowtown II Senior ‐ Undrawn
16Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Financing –Financing Group Gearing Ratio
Debt:Debt+EquitySell South post construction Hold South Long Term
35%
40%
45%
50%
quity
10%
15%
20%
25%
30%
Deb
t:Deb
t+Eq
0%
5%
10%
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Financial Year Ended March
Refer significant assumptions slide 21 and 22
Financial Year Ended March
17Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Financing – Group GearingFinancing Group Gearing
4.5
Debt/EBITDAFSell South post construction Hold South Long Term
2 5
3.0
3.5
4.0
TDAF
1.0
1.5
2.0
2.5
Deb
t/EBIT
‐
0.5
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Financial Year Ended March
Refer significant assumptions slide 21 and 22
18Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Impact on theImpact on the TrustPower Group
Snowtown 2 Snowtown 2 Total Snowtown
First full year of operation of Snowtown 2 project – FY16
Snowtown 2North**
Snowtown 2 South
Total Snowtown Stage 2
CAPEX(A$m) 257 182 439
EBITDA (A$m) 41.2 36.7 77.9
NPAT (A$m) 8.6 11.3 19.9
Operating Free Cash Flow (after tax and debt service) (A$m) 21.5 20.4 41.9
Earnings per share (NZ cps)* 3 4 4 5 7 9Earnings per share (NZ cps)* 3.4 4.5 7.9
* Exchange rate of NZD/AUD 0.8000 assumed** Includes impact of wind shading on Snowtown Stage 1
19Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
Snowtown 2 SouthSnowtown 2 South sales process update
TrustPower has two potential avenues to sell Snowtown 2 South:Snowtown 2 South:
1. Sale completed soon after financial closeExclusive process commenced with a potential co-investor that was p pshort listed but unable to provide binding bid by targeted financial close.
2 Sell at commissioning (2014)2. Sell at commissioning (2014)Potential to offer pre-committed long term funding package.Large pool of potential co-investors interested once construction risk
d i l di f fi i l i t i t t d iremoved including range of financial investors interested in renewable infrastructure assets.
20Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
TrustPower’sTrustPower s Australian vision
• Snowtown Stage 2 will be the first of several wind f d d d i h ifarms constructed and managed with co-investors
• By 2022:– TrustPower will own 600MW of sustainable generation– It will have built another 600MW for its development p
partners, for which it continues to play a management role• Our Australian pipeline currently consists of p p y
approximately 1,280 MW of potential wind options
21Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
SignificantSignificant AssumptionsProject related assumptions
Capex• Based on pricing under fixed price contracts with Siemens Ltd (“Siemens”), Downers EDI Engineering Power Pty Ltd and ElectraNet Pty Ltd• Portions in foreign currencies converted to A$ using rates set by forward exchange contracts. 100% of foreign currency exposure is covered by o t o s o e g cu e c es co e ted to $ us g ates set by o a d e c a ge co t acts 00% o o e g cu e cy e posu e s co e ed by
forward contractsEBITDAF • Revenue based on fixed price contract with Origin Energy Electricity Limited (“Origin”) and long term expected average wind volumes• Maintenance costs based on maintenance contract with Siemens• Landowner royalties based on land rental agreements• Other costs estimated based on existing wind farm costsOther costs estimated based on existing wind farm costs• Fair value movements on financial instruments will be zero as hedge accounting is used for foreign exchange cover.NPAT• EBITDAF less interest (based on expected average TrustPower Group Australian funding cost), depreciation (at 5%) and tax (at 30%)Free cash flows• NPAT plus depreciation and less capex (assumed to be nil in first year of operation i.e. the first full year post commissioning)EPSEPS• Based on expected $A NPAT converted to NZD at 0.8000 divided by number of TrustPower shares on issue (less treasury stock held by TrustPower)Wind volume/capacity factors • Based on independent expert assessmentUngeared Project IRR• Based on project cash flows (being EBITDAF less cash tax and capex) p j ( g p )• Revenue post fixed price contract with Origin based on estimated price path• Maintenance costs post contract with Siemens based on cost in last year of contract• Project life assumed to be 25 years, after 25 years value assumed to be book value of roads, substation and electricity reticulation system• Inflation assumed at 2%
22Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing
SignificantSignificant AssumptionsGroup Funding AssumptionsDebt:Debt+Equity• Snowtown Stage 2 capex funded entirely through debt. • No other major items of capital expenditure over and above normal operating capex.j p p p g p• Equity increased by profits less dividend and an inflation driven revaluation of generation assets.• Profits are defined as EBITDAF less interest (based on expected average TrustPower Group funding cost), depreciation (at existing rates as per note
2.6 of the 31 March 2012 financial statements) and tax (at 28% in New Zealand and 30% in Australia)• EBITDAF on existing business growing in line with electricity wholesale prices (flat over first three years then lifting)• Snowtown Stage 2 EBITDAF in accordance with above assumptions Under the scenario where Snowtown 2 South is sold post construction the saleSnowtown Stage 2 EBITDAF in accordance with above assumptions Under the scenario where Snowtown 2 South is sold post construction the sale
proceeds reflect the capital expenditure plus an estimate of the expected net present value of future earnings less tax (capital gains tax and stamp duty)
• Dividends held flat at current cents per share• Free cash flows after dividends used to retire debt.Debt/EBITDAFDebt/EBITDAF• Based on same assumptions as debt:debt+equity
23Date: 26-Jul-12 Snowtown Wind Farm Stage 2: Investor and analyst briefing