SMA Team2.2 Implementation Plan V0.1 17Sep10
Transcript of SMA Team2.2 Implementation Plan V0.1 17Sep10
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 1/26
Practical Softwar
SMA-Course Imple
Document Control information
Faculty Faculty of Information Technology
Issue Date: 14-Sep-10
Author: Duc Le
Document Revision History
Date Version Description
16-Sep-10 0.1 Initial version
17-Sep-10 0.2Update assign tasks and rolesUpdate new membersUpdate assign roles
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 2/26
Engineering Series
entation Plan
Version : 1.0
Revised by
Duc Le
Duc Le
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 3/26
Week# Content Date Time Room
1
15-Sep-10 13:00-15:00
16-Sep-10 15:30-17:00
18-Sep-10 13:00-16:00
2
21-Sep-10 9:00-11:55
23-Sep-10 15:30-17:00
25-Sep-10 13:00-16:00
28-Sep-10 9:00-11:55
Team Assignment#1
Hoa HướngDương
7th Floor
7th Floor
Team Assignment#2
7th Floor
7th Floor
7th Floor
7th Floor
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 4/26
330-Sep-10 15:30-17:00
2-Oct-10 13:00-16:00
4
5-Oct-10 9:00-11:55
7-Oct-10 15:30-17:00
9-Oct-10 13:00-16:00
5
12-Oct-10 9:00-11:55
14-Oct-10 15:30-17:00
Team Assignment#3
7th Floor
7th Floor
Team Assignment#4
7th Floor
7th Floor
7th Floor
Team Assignment
#5
7th Floor
7th Floor
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 5/26
16-Oct-10 13:00-16:00
6
19-Oct-10 9:00-11:55
21-Oct-10 15:30-17:00
23-Oct-10 13:00-16:00
7
26-Oct-10 9:00-11:55
28-Oct-10 15:30-17:00
30-Oct-10 13:00-16:00
2-Nov-10 9:00-11:55
7th Floor
Team Assignment#6
7th Floor
7th Floor
7th Floor
Team Assignment#7
7th Floor
7th Floor
7th Floor
7th Floor
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 6/26
8
4-Nov-10 15:30-17:00
6-Nov-10 13:00-16:00
9-Nov-10 9:00-11:55
11-Nov-10 15:30-17:00
13-Nov-10 13:00-16:00
10
16-Nov-10 9:00-11:55
18-Nov-10 15:30-17:00
Team Assignment#8
7th Floor
7th Floor
9(Mid-term
exam)
Team Assignment#9
7th Floor
7th Floor
7th Floor
Team Assignment#10
7th Floor
7th Floor
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 7/26
20-Nov-10 13:00-16:00
11
23-Nov-10 9:00-11:55
25-Nov-10 15:30-17:00
27-Nov-10 13:00-16:00
12
30-Nov-10 9:00-11:55
2-Dec-10 15:30-17:00
4-Dec-10 13:00-16:00
7th Floor
Team Assignment
#11
7th Floor
7th Floor
7th Floor
Team Assignment#12
7th Floor
7th Floor
7th Floor
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 8/26
13
7-Dec-10 9:00-11:55
9-Dec-10 15:30-17:00
11-Dec-10 13:00-16:00
14
14-Dec-10 9:00-11:55
16-Dec-10 15:30-17:00
18-Dec-10 13:00-16:00
15
21-Dec-10 9:00-11:55
23-Dec-10 15:30-17:00
Team Assignment#13
7th Floor
7th Floor
7th Floor
Team Assignment#14
7th Floor
7th Floor
7th Floor
Team Assignment#15
7th Floor
7th Floor
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 9/26
Activities In MeetingsSubmit TeamAssignment
- Greeting- Prepare Team Operation Process.- Assign responsibilities.- Assign Role in Team.- Prepare EffortLog and Weekly Report.- Reading document to prepare for next team meeting.- Dicuss about Team Assigment's week 1.
- Update some team’s rules- Update SMA Team Assingment 1st.- Discuss SMA Team Assingment 2rd.
+ Assign roles
- Review Requirement Engineer’s report about the Viking project
should measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 2- Discuss Reading: week 1
- Developer report about Implement Team Assignment andDocument Team assignment 2- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#1 DraftTeam Assignment#2 Draft(0:00am 9/22/2010)
- Update Team Assignment 2 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 3
+ Assign roles- Remark about members
Team Assignment#1 FinalTeam Assignment#2 Final(0:00am 9/24/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 3- Discuss Reading: week 2
- Developer report about Implement Team Assignment andDocument Team assignment 3- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#3 Draft(00:00am 09/29/2010)
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 10/26
- Update Team Assignment 3 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 4&5
+ Assign roles- Remark about members
Team Assignment#3 Final(00:00 10/01/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 4&5- Discuss Reading: week 3
- Developer report about Implement Team Assignment andDocument Team assignment 4&5- Tester start check spelling, requirement, submit report on time,and Team Assignment Content
- Prepare slide to presentation
Team Assignment#4 DraftTeam Assignment#5 Draft(00:00am 10/06/2010)
- Update Team Assignment 4&5 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 6
+ Assign roles- Remark about members
Team Assignment#4 FinalTeam Assignment#5 Final(00:00am 10/08/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 6
- Discuss Reading: week 4
- Developer report about Implement Team Assignment andDocument Team assignment 6- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#6 Draft(00:00am 10/13/2010)
- Update Team Assignment 6 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 7
+ Assign roles
- Remark about members
Team Assignment#6 Final(00:00am 10/15/2010)
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 11/26
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 7- Discuss Reading: week 5
- Developer report about Implement Team Assignment andDocument Team assignment 7- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#7 Draft(00:00am 10/20/2010)
- Update Team Assignment 7 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 8&9
+ Assign roles- Remark about members
Team Assignment#7 Final(00:00am 10/22/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 8&9- Discuss Reading: week 6
- Developer report about Implement Team Assignment andDocument Team assignment 8&9- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#8 DraftTeam Assignment#9 Draft(00:00am 10/27/2010)
- Update Team Assignment 8&9 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 10
+ Assign roles- Remark about members
Team Assignment#8 FinalTeam Assignment#9 Final(00:00am 10/28/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 10
- Discuss Reading: week 7
- Developer report about Implement Team Assignment andDocument Team assignment 10- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#10 Draft(00:00am 11/3/2010)
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 12/26
- Update Team Assignment 10 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 11
+ Assign roles- Remark about members
Team Assignment#10 Final(00:00am 11/5/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 11- Discuss Reading: week 8
- Developer report about Implement Team Assignment andDocument Team assignment 11- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#11 Draft(00:00am 11/10/2010)
- Update Team Assignment 11 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 12
+ Assign roles- Remark about members
Team Assignment#11 Final(00:00am 11/12/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 12- Discuss Reading: week 9
- Developer report about Implement Team Assignment andDocument Team assignment 12- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#12 Draft(00:00am 11/17/2010)
- Update Team Assignment 12 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 13
+ Assign roles
- Remark about members
Team Assignment#12 Final(00:00am 11/19/2010)
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 13/26
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 13- Discuss Reading: week 10
- Developer report about Implement Team Assignment andDocument Team assignment 13- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#13 Draft(0:00am 11/24/2010)
- Update Team Assignment 13 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 14
+ Assign roles- Remark about members
Team Assignment#13 Final(0:00am 11/26/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 14- Discuss Reading: week 11
- Developer report about Implement Team Assignment andDocument Team assignment 14
- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#14 Draft(0:00am 12/1/2010)
- Update Team Assignment 14 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 15
+ Assign roles- Remark about members
Team Assignment#14 Final(0:00am 12/3/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members
- Developer start implement Team Assignment and DocumentTeam Assignment 15- Discuss Reading: week 12
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 14/26
- Developer report about Implement Team Assignment andDocument Team assignment 15- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#15 Draft(0:00am 12/8/2010)
- Update Team Assignment 15 about feedback of Teacher
- Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 16
+ Assign roles- Remark about members
Team Assignment#15 Final(0:00am 12/10/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 16- Discuss Reading: week 13
- Developer report about Implement Team Assignment andDocument Team assignment 16- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#16 Draft(0:00am 12/15/2010)
- Update Team Assignment 16 about feedback of Teacher - Prepare slide presentation- Presentation draft- Discuss SMA Team Assignment 17
+ Assign roles- Remark about members
Team Assignment#16 Final(0:00am 12/17/2010)
- Review Requirement Engineer’s report about the Viking projectshould measure to ensure business value to ABC Systems- Overview tasks of members- Developer start implement Team Assignment and DocumentTeam Assignment 17- Discuss Reading: week 14
- Developer report about Implement Team Assignment andDocument Team assignment 17- Tester start check spelling, requirement, submit report on time,and Team Assignment Content- Prepare slide to presentation
Team Assignment#17 Draft(0:00am 12/22/2010)
- Update Team Assignment 17 about feedback of Teacher - Prepare slide presentation- Presentation draft
Team Assignment#17 Final(0:00am 12/24/2010)
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 15/26
Roles
Requirement Engineer: ThuongHuynhDeveloper: Phuoc Nguyen,
Phuc Dang, Thang LeTester: Duc Le, Lam Y
Requirement Engineer: ThuongHuynhDeveloper: Phuc Dang, Lam Y,
Thang LeTester: Phuoc Nguyen, Duc Le
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 16/26
Requirement Engineer: Lam Y.Developer: Thuong Huynh,
Phuc Dang, Duc LeTester: Phuoc Nguyen, Thang
Le
Requirement Engineer: Lam Y.Developer: Thang Le, Phuoc
Nguyen, Phuc DangTester: Thuong Huynh, Duc Le
Requirement Engineer: PhucDang.Developer: Lam Y, Phuoc
Nguyen, Duc Le
Tester: Thuong Huynh, ThangLe
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 17/26
Requirement Engineer: PhucDang.Developer:Phuoc Nguyen, Lam
Y, Duc LeTester: Thuong Huynh, Thang
Le
Requirement Engineer: Duc LeDeveloper: Phuoc Nguyen,
Phuc Dang, Thang LeTester: Thuong Huynh, Lam Y
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 18/26
Requirement Engineer: PhuocNguyenDeveloper: Phuc Dang, Lam Y,
Thang LeTester: Thuong Huynh, Duc Le
Requirement Engineer: PhuocNguyen.Developer: Thuong Huynh,
Phuc Dang, Duc LeTester: Lam Y, Thang Le
Requirement Engineer: ThangLe.Developer: Lam Y, Phuoc
Nguyen, Phuc Dang
Tester: Thuong Huynh, Duc Le
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 19/26
Requirement Engineer: ThangLe.Developer: Lam Y, Phuoc
Nguyen, Duc LeTester: Thuong Huynh, Phuoc
Nguyen
Requirement Engineer: ThangLe.Developer:Phuc Dang, Lam Y,
Duc LeTester: Thuong Huynh, Thang
Le
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 20/26
Requirement Engineer: ThuongHuynhDeveloper: Phuoc Nguyen,
Phuc Dang, Thang LeTester: Duc Le, Lam Y
Requirement Engineer: ThuongHuynhDeveloper: Phuc Dang, Lam Y,
Thang LeTester: Phuoc Nguyen, Duc Le
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 21/26
Homework # Description
1
2
3
• List and briefly describe (2 pages or less) the metrics that you would proposethat ABC Systems collect for the Viking project.
•Ask 30 classmates to collect data about their favorite sport. Then choosing achart type to graph the collected data and using that chart to answer followingquestions:- Which sport is the most popular?- Which sport is the least popular?- What percentage of students like the most popular sport?
• Sally walks everywhere. Here is how far she has walked the past few months.What chart type should Sally use to show how far she walks per month and toknow if Sally’s working is increasing or decreasing?Sally’s WalkingJanuary 60 KmFebruary 48 Km
March 46 KmApril 50 KmMay 44 KmJune 42 Km
• Research to collect data about the amount of sugar in one serving (you get todecide what “one serving” means) for each of the following: milk, cola, water,orange juice, tea and coffee. Then choosing a chart type to graph the collecteddata and using that chart to answer following questions:
- Which drink has the most sugar?- Which drink has the least sugar?
• Summarize (≤ 3 pages) the challenges you’ve faced collecting and usingmetrics, what lessons you’ve learned, and what you would do differently if youwere able to start this course over again.
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 22/26
Comments
3
5
18
Completebefore lecture#
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 23/26
Description
1 3
2 4
3 5
4 7
5 7
6 8
7 9
8 • Each team creates a budget for the Viking project. 11
9 11
10 12
11 13
Teamassignment #
Completebefore lecture#
• Brief description (≤ 3 pages) of project team roles, responsibilitiesand schedule (which team member plays which roles when).• Reporting of planned and actual individual effort log data (use
provided effort log spreadsheet) to Director by team, along withbrief analysis
• Write a paper (≤ 2 pages) describing what the Viking projectshould measure to ensure business value to ABC Systems.• Reporting of actual individual effort log data to Director by team,along with brief analysis
• Reporting of actual individual effort log data to Director by team,along with brief analysis
• Each team presents a GQM chart for one assigned Viking projectgoal:
- Reduce product schedule by 10%- Improve productivity by 10%- Reduce project costs by 10%- Improve product quality by 10%- Reduce project risk by 10%- Reduce product change by 10%- Improve customer satisfaction by 10%- Increase team morale by 10%- Reduce defects found by system test by 10%- Increase project schedule predictability by 10%
• Reporting of actual individual effort log data to Director by team,along with brief analysis
• A paper (≤ 2 pages) briefly describing how a softwaredevelopment methodology impacts the team’s GQM definitions.• Reporting of actual individual effort log data to Director by team,along with brief analysis
• Each team creates a high level network diagram, high level wbsand high level schedule for the Viking project.
• Each team presents on the productivity of their own team basedon their effort log data collected to date, along with supporting data
and recommendations for productivity improvement.
• Each team analyzes the Viking project’s earned value data andsubmits a report (<2 pages) on their findings.
• Each team analyzes provided Viking product bug data andsubmits a report (<2 pages) on their findings
• Each team documents their top ten risks for the Viking project,including a management plan for each risk.
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 24/26
12 14
13 15
14 16
15 17
16 18
17 18 End
• Each team analyzes provided Viking product change data andsubmits a report (<2 pages) on their findings
• Each team analyzes provided Viking customer satisfaction dataand submits a report (<2 pages) on their findings
• Each team analyzes provided Viking team morale data andsubmits a report (<2 pages) on their findings
• Each team generates schedule, budget and resource estimatesfor the Viking project and presents their estimates to the VPEngineering.
• Create a dashboard (paper or real) for ABC Systems to use for managing their projects, and present your dashboard to the VPEngineering.
• Each team reports on their team’s productivity, and theeffectiveness of the improvements, based on their effort log datacollected to date. < 2 page report and spreadsheet containing raweffort log data and pivot table.• Update the GQM models and data management mechanismsfrom homework #3 & 4.
• Summarize (≤ 5 pages) the strengths and weaknesses of theViking project’s metrics
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 25/26
Comments
8/8/2019 SMA Team2.2 Implementation Plan V0.1 17Sep10
http://slidepdf.com/reader/full/sma-team22-implementation-plan-v01-17sep10 26/26