SM 18 infrastructure focused on SPL cavity tests
description
Transcript of SM 18 infrastructure focused on SPL cavity tests
SM 18 infrastructurefocused on SPL cavity tests
V. Benda, O. Pirotte, B. Vullierme
SPL cryomodule CRG/VB
SM 18 layout, current status
19.10.2010 2
6 kW Linde
RF cavity
Magnet test benches CFBs
Bloc 4 + FCM + SC Link
GReC
SM 18 cryogenic simplified flow scheme
Compressors
6 kW cold box
WPU 1
WPU 2
CFB 10x
Bloc4, Fresca 2,CL test
Cavity 4x v & 2 x h
Dryerfull flow
Precooler/adsorberSC link
/FCM
Strin
g 3
25 000 l LHedewar
Heater
SC helium
Shield
HP LP
LHe
LHe
1.9 K pumping
CCU 2 & heater 1
CCU 3 & heater 5
19.10.2010 SPL cryomodule CRG/VB 3
SPL cryomodule CRG/VB 4
Main inputs of SM 18 cryogenic infrastructure
• The 6 kW Linde cold box– Capacity: 25 g/s (700 l/h) of LHe
• The 1.8 K pumping capacity– 2 warm pumping units (WPU), each one of a following pumping speed:
• 6 g/s @ 10 mbar• 12 g/s @ 20 mbar• 18 g/s @ 30 mbar
– To each pumping unit is dedicated one very low pressure heater of 32 kW (20g/s)
– The cold compressor (CCU) & one WPU in series: 18 g/s @10 mbar– One WPU is dedicated to CFBs and Bloc 4 including CCU if necessary– Second WPU will be dedicated to cavity tests– Both WPUs can work in parallel
• New clients– Bloc 4, FCM, SC Link: LHe & pumping capacity– Cavity: Pumping capacity will required one WPU
19.10.2010
SPL cryomodule CRG/VB 5
Individual tests compatible with SM18 test capacity… L. Tavian
0
5
10
15
20
25
He co
nsum
ption
[g/s
]
LHeVLP
WPU + CCU
2 WPU
6 kW cryoplant
19.10.2010
SPL cryomodule CRG/VB 6
0
10
20
30
40
50
60
70
80
90
100
LHe VLP
He co
nsum
ption
[g/s
]
SPL RF moduleSPL RF cavityISOLDE RF moduleFCM, SC linksISOLDE cavityLHC RF cavityLHC RF moduleRF TLFresca 2Block 4CFB 3CFB 2CFB 1OSQAR
… but not all together ! Coordination and … L. Tavian
19.10.2010
SPL cryomodule CRG/VB
LHe distribution & 1.9 K pumping, current status
19.10.2010 7
SPL cryomodule CRG/VB 8
SM 18 upgrade,new cavity pumping lineand Bloc 4 distribution
simplified scheme
19.10.2010
SPL cryomodule CRG/VB
2 K RF service module
19.10.2010 9
R01
SV135
SV125
SV105
SV130 SV160
DN25
DN80
DN50
DN32
CV100
CV130
FV170
FV173
FV172
FV168 FV171
FV166 FV160
P-01
GHe LP
GHe Recovery
LHe 1.5 bar
GHe Pumping
GHe return
GHe < 80 K (Thermal schield)
Exhaust
HV100
To helium guards: valves, RF cryostat...
HX01
LT105
LT100
PT105
TT120
TT130
PT130
DN
15
DN
32
DN
25
DN
15
DN
10
DN
10
DN
32
DN
15
RD100
FV140
FV135
FV115
FV125
CV105
FV165
FV167
HV130HV115
HV140HV135
HV140
DN15
PT160
PT170
CV120
TMP
HV135 To RD100To LT100
To RF
SPL cryomodule CRG/VB
Cryo module in the bunker – simulation
19.10.2010 10
Service module Jumper
Cryo module
Interface of a cryo moduleTo be defined!
SPL cryomodule CRG/VB
Clarification of the required cryogenic power @ 2 K
19.10.2010 11
Operating condition Value(nominal/”ultimate”)
cryo duty cycle 4.11%/8.22%
quality factor 10/5 x 109
accelerating field 25 MV/m
Source of Heat Load Heat Load @ 2K(nominal/”ultimate”)
dynamic heat load per cavity 5.1/20.4 W
static losses <1 W (tbc)
power coupler loss at 2 K <0.2/<0.2 W
HOM loss in cavity at 2 K <1/<3 W
HOM coupler loss at 2 K (per coupl.) <0.2/<0.2 W
beam loss 1 W
Total @ 2 K 8.5/25.8 W
Ultimate heat load @ 2 K for 8 cavities is:8 x 25.8 = 208 W
What is the maximum required cryogenic power @ 2 K for a module of 8 cavities: 208 W or 75W?
SPL cavity and SPL module cannot be tested simultaneously.
12
Some questions1)Cryo module interface to be defined (welded sleeve, 4 x flexibles), as well as allocated volume in the bunker for Cryo equipment.2)Required cryogenic power @ 2 K to be clarified.3)Is there any limit of dT during cool down/warm up?4)Required speed of warm up; procedure?5) What is a heat inleak to the thermal shield.6) Point A in the table ??7) Point B: Safety valve adjustment?8) Point C: Available temperature of GHe is 5 K.9) Point D: Available pressure is 0.13 MPa.
19.10.2010 SPL cryomodule CRG/VB
A B
CD