Slides.project Management Professional (Pmi) Study Guide

download Slides.project Management Professional (Pmi) Study Guide

of 270

description

PMP

Transcript of Slides.project Management Professional (Pmi) Study Guide

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    1/270

    Project Management

    Professional (PMP)Certification Study Guide

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    2/270

    PMI Certification Materials

    To assist PMI candidates for completing the PMIcertification exam administered by the ProjectManagement Institute

    Content is from A Guide To The ProjectManagement Body Of Knowledge (PMBOK)

    www.pmi.org

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    3/270

    Recurring Themes

    Historical Recordsneed to collect and use forplanning, estimating and risk

    Kickoff meetings are important

    Work Breakdown Structures

    Do not introduce benefits that are not stated inrequirements

    Needs of all stakeholders should be taken into accountduring all projects

    Team Members must be involved in project planning Project Mangers must be pro-active

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    4/270

    Chapter 1Introduction

    Projecttemporary endeavor undertaken tocreate a unique product or service

    Has a definite beginning and end and

    interrelated activities Programs adopt new set of objectives and

    continueto work; projects cease when declaredobjectives have been attained

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    5/270

    Chapter 1Introduction

    Projects are uniquecharacteristics areprogressively elaborated

    Progressively: proceeding in steps

    Elaborated: worked with care and detail

    Scope of project should remain constanteven as characteristics are progressively

    elaborated

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    6/270

    Chapter 1- Introduction

    Project Management:the application ofknowledge, skills, tools and techniques to projectactivities in order to meet or exceed stakeholder

    needs and expectations from a defined projectbalancing the following:

    Scope, time, cost, and quality

    Stakeholders expectations

    Requirements (needs) vs. unidentified requirements(expectations)

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    7/270

    Chapter 1- Introduction

    Programs are groups of projects managed in acoordinated way to obtain benefits not availablefrom managing the projects individually

    Most programs have elements of ongoingoperations Series of repetitive or cyclical undertakings

    Projects are often divided into subprojects for

    more manageability Often contracted out to external organizations

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    8/270

    Chapter 2Project ManagementContext

    Project Phases are marked by thecompletion of a deliverable Tangible, verifiable work product

    Review of deliverables and approval/denialare phase exits, stage gates, or kill points

    Phases are collected into the Project LifeCycle Set of defined work procedures to establish

    management control

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    9/270

    Chapter 2Project ManagementContext

    Project Life Cycle defines:

    Technical work performed in each phase

    Who is involved in each phase

    Project Phases can overlapFast Tracking

    Common Characteristics of Project Life Cycles: Cost and Staffing levels are low at start and move higher

    towards the end

    Probability of successfully completing project is low at beginning,higher towards the end as project continues

    Stakeholder influence is high at the beginning and progressivelylowers as project continues

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    10/270

    Chapter 2Project ManagementContext

    Stakeholders:individuals and organizationswho are actively involved in the project

    Often have conflicting expectations and objectives

    In general, differences should be resolved in favor ofthe customerindividual(s) or organization(s) that willuse the outcome of the project

    Stakeholder management is a proactive task

    Project Mangers must determine all stakeholders andincorporate their needs into the project

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    11/270

    Chapter 2Project ManagementContext

    Stakeholders are: Project Managers

    Customers

    Performing Organizations, owners Sponsor

    Team

    Internal/External

    End User Society, citizens

    Others: owner, funders, supplier, contractor

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    12/270

    Chapter 2Project ManagementContext

    Organizational Systems: Project based vs.Non-Project Based Project Basedderive revenues from performing

    projects for others (consultants,contractors),management by projects

    Non-Project Basedseldom have managementsystems designed to support project needs

    (manufacturing, financial services)

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    13/270

    Chapter 2Project ManagementContext

    Organizational Cultures and Styles:

    Entrepreneurial firms more likely to adopthighly participative Project Manageraccept

    higher risk/reward Hierarchical firms less likely to adopt

    participative Project Managertake fewer

    risks

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    14/270

    Chapter 2Project ManagementContext

    Organizational Structures Functional (classical) marked by identifiable

    superiors. Staff grouped by specialty .

    Perceived scope of project limited by function(Engineering, HR). Typically have part-timeProject Manager

    Projectized Organizationblend functional

    and projectized characteristics. Mix cross-department personnel with full-time ProjectManger

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    15/270

    Chapter 2Project ManagementContext

    Project Management Skills General Business Management (consistently

    producing results expected by stakeholders) Leading (establishing direction, aligning resources,

    motivating) Communicating (clear, unambiguous, and complete) Negotiating (conferring with others to reach an

    agreement) Problem Solving (definition and decision making)

    Distinguish causes and symptoms Identify viable solutions

    Influencing Organization (understanding power andpolitics)

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    16/270

    Chapter 2Project ManagementContext

    Socioeconomic Influences Standardsdocument approved that provides

    common, repeated use, rules and guidelines

    Compliance is not mandatory

    Regulationsdocument that identifies products,services or characteristics

    Compliance is mandatory

    Standards often become de facto regulations

    Internationalization Cultural Influences

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    17/270

    Chapter 2Project ManagementContext

    Organization Structure Pros and Cons Projectized

    Efficient OrganizationNo home

    LoyaltyLack of Professionalism

    Effective CommunicationDuplication of functions, lessefficient resource usage

    Matrix Visible Objectivesnot cost effective

    PM ControlMore than 1 boss

    More supportMore complex to control

    Utilize scarce resourcesTough resource allocation

    Information distributionCompetition of priorities

    CoordinationPolicies & Procedures

    Home basedPotential for conflict

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    18/270

    Chapter 2Project ManagementContext

    Functional Organization SpecialistsMore emphasis on functions

    1 supervisorNo career path in PM

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    19/270

    Chapter 3Project ManagementProcesses

    Project Management requires active

    management of Project Processes

    Series of actions that achieve a result

    Project Management Processes Describing and organizing the work

    Product-Oriented Processes

    Specifying and creating the product

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    20/270

    Chapter 3Project ManagementProcesses

    Process Groups: Initiating processes:recognizing a project or phase

    should begin

    Planning processes:devising and maintaining a

    workable plan Executing processes:coordinating resources to

    execute the plan

    Controlling processes:ensuring project objectives

    are met; monitoring, correcting and measuringprogress

    Closing processes:formalized acceptance

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    21/270

    Chapter 3Project ManagementProcesses

    Process Groups are linked by the results eachproduces

    Process Groups are overlapping activities withvarious levels of intensity

    Process Group interactions cross phasesrolling wave planning Provides details of work to complete current phase

    and provide preliminary description of work forsubsequent phases

    Individual processes have inputs, tools andtechniques, and outputs (deliverables)

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    22/270

    Chapter 3Project ManagementProcesses

    Initiating and Planning Processes Committing the organization to begin

    Initiation, High-level planning, Charter

    Amount of planning proportional to the scope ofthe projectCore Planning Scope Planningwritten statement Scope Definitionsubdividing major deliverables

    into more manageable units

    Activity Definitiondetermine specific tasks neededto produce project deliverables Activity Sequencingplotting dependencies

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    23/270

    Chapter 3Project ManagementProcesses

    Core Planning (continued) Activity Duration Estimatingdetermine amount of work

    needed to complete the activities

    Schedule Developmentanalyze activity sequences, duration,and resource requirements

    Resource Planning identify what and how many resourcesare needed to perform the activities

    Cost Estimatingdevelop resource and total project costs

    Cost Budgetingallocating project estimates to individual workitems

    Project Plan Developmenttaking results from other planningprocesses into a collective document

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    24/270

    Chapter 3Project ManagementProcesses

    Planning/Facilitating Processesmanage theinteraction among the planning processes

    Quality Planningstandards that are relevant to the

    project and determining how to meet standards Organizational Planningidentify, document, and

    assigning project roles and responsibilities

    Staff Acquisitionobtaining the human resources

    Communications Planningdetermining rules andreporting methods to stakeholders

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    25/270

    Chapter 3Project ManagementProcesses

    Planning/Facilitating Processes (continued) Risk Identificationdetermining what is likely to

    affect the project and documenting these risks

    Risk Quantificationevaluating risks and

    interactions to access the possible project outcomes Risk Response Developmentdefining

    enhancement steps and change control measures

    Procurement Planningdetermining what to buy

    and when Solicitation Planningdocumenting product

    requirements and identifying possible sources

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    26/270

    Chapter 3Project ManagementProcesses

    Planning/Facilitating Processes (continued) Order of events:

    Scope Statement

    Create Project Team

    Work Breakdown Structure

    WBS dictionary

    Finalize the team Network Diagram

    Estimate Time and Cost

    Critical Path

    Schedule

    Budget

    Procurement Plan

    Quality Plan Risk Identification, quantification and response development

    Change Control Plan

    Communication Plan

    Management Plan

    Final Project Plan

    Project Plan Approval

    Kick off

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    27/270

    Chapter 3Project ManagementProcesses

    Executing Processes Project Plan Executionperforming the activities Complete Tasks/Work Packages Information Distribution

    Scope Verificationacceptance of project scope Quality Assuranceevaluating overall project

    performance on a regular basis; meeting standards Team Developmentdeveloping team and

    individual skill sets to enhance the project

    Progress Meetings

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    28/270

    Chapter 3Project ManagementProcesses

    Executing Processes (continued)

    Information Distributionmaking projectinformation available in a timely manner

    Solicitationobtaining quotes, bids,proposals as appropriate

    Source Selectiondeciding on appropriatesuppliers

    Contract Administrationmanaging vendorrelationships

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    29/270

    Chapter 3Project ManagementProcesses

    Controlling Processesneeded to regularlymeasure project performance and to adjustproject plan

    Take preventive actions in anticipation ofpossible problems Change Controlcoordinating changes across the

    entire project plan

    Scope Change Controlcontrolling scope creep

    Schedule Controladjusting time and projectschedule of activities

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    30/270

    Chapter 3Project ManagementProcesses

    Controlling Processes (continued) Cost Controlmanaging project budget

    Quality Controlmonitoring standards and

    specific project results; eliminating causes ofunsatisfactory performance

    Performance Reportingstatus,forecasting, and progress reporting schedule

    Risk Response Controlresponding tochanges in risk during the duration of theproject

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    31/270

    Chapter 3Project ManagementProcesses

    Closing Processes Administrative Closuregenerating necessary

    information to formally recognize phase or projectcompletion

    Contract Close-outcompletion and delivery ofproject deliverables and resolving open issues Procurement Audits Product Verification Formal Acceptance Lessons Learned Update Records Archive Records Release Team

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    32/270

    Chapter 3Project ManagementProcesses

    Overall Processes

    Influencing the organization

    Leading

    Problem Solving

    Negotiating

    Communicating

    Meetings

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    33/270

    Chapter 3Project ManagementProcesses

    Project Selection Techniques

    Comparative Approach (similar projects)

    Benefit measurement method

    Constrained Optimization (mathematicalapproach)

    Key aspect of scope verification is

    customer acceptance Only 26 % of projects succeed

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    34/270

    Chapter 4Project IntegrationManagement

    Project Integration Management Ensures that the project processes are properly coordinated Tradeoffs between competing objectives and alternatives in

    order to meet stakeholder approval Project Plan Development

    Project Plan Execution Overall Change Control

    These processes may occur repeatedly over the project duration Historical Records are needed to perform project management

    well, they are inputs to continuous improvement Files Lessons Learned Actual Costs Time Estimates WBS Benchmarks Risks

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    35/270

    Chapter 4Project IntegrationManagement

    Project Plan Development Uses outputs from other planning processes to create

    consistent document to guide project execution andcontrol

    Iterated several times Documents planning assumptions

    Documents planning decisions that are chosen

    Facilitates communication

    Defines key management reviews Provides a baseline to track progress measurement

    and project control

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    36/270

    Chapter 4Project IntegrationManagement

    Project Plan Development Inputs Other planning outputs: primarily the planning

    process outputs (WBS, base documents, applicationarea inputs)

    Historical informationverify assumptions, records ofpast project performance

    Organizational policiesquality management,personnel administration, Financial controls

    Constraintsfactors that limit performance,contractual provisions, budget

    Assumptionsrisk factors

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    37/270

    Chapter 4Project IntegrationManagement

    Tools & Techniques for Plan Development

    Project Planning Methodologyany structuredapproach (software, templates, forms, start-upmeetings

    Stakeholder Skills & Knowledgetap into plandevelopment; use expertise for reasonableness

    PMISOut of the box approach to support all projectaspects through closure

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    38/270

    Chapter 4Project IntegrationManagement

    Project Plan Development Outputs Project Plan is a collection that changes over time as more

    information about the project becomes available

    Baseline will change only in response to approved scope change

    Project Plan includes some or all of the following: Project Charter

    Project Management approach or strategy

    Scope statement

    Work Breakdown Structure (WBS)

    Budget, schedule, risks

    Key Staff, Major Milestones Change Control Plan, Management and Communications Plan

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    39/270

    Chapter 4Project IntegrationManagement

    Project Plan Components (continued) Cost Estimates, scheduled start dates and responsibility

    assignments

    Performance measurement baselines

    Major milestones and target dates Required Staff

    Risks, constraints and assumptions

    Subsidiary management plans (scope, schedule)

    Open Issues Pending Decisions

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    40/270

    Chapter 4Project IntegrationManagement

    Supporting Details to the Project Plan

    Outputs from planning processes

    Technical documentation

    Business requirements, specifications, anddesigns

    Relevant standards

    Additional information not previously known

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    41/270

    Chapter 4Project IntegrationManagement

    Project Plan Execution

    Primary process for carrying out the projectplan

    Most costly aspect of project management

    Direction of organizational resources andinterfaces

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    42/270

    Chapter 4Project IntegrationManagement

    Project Plan Execution Inputs:

    Project Plan

    Supporting Detail

    Organizational Policies

    Corrective Actionanything to bring expectedperformance in line with the project plan

    C

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    43/270

    Chapter 4Project IntegrationManagement

    Tools & Techniques for Plan Execution General Management Skills

    Product Skills and Knowledgedefined as part ofplanning, provided by staffing

    Work Authorization Systemformal procedure forsanctioning work to ensure completionwritten orverbal authorization

    Status review meetingsregular exchanges of

    information Project Management Information System

    Organizational Procedures

    Ch 4

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    44/270

    Chapter 4Project IntegrationManagement

    Project Plan Execution Outputs

    Work resultsthe outcome of activitiesperformed is fed into the performance

    reporting process Change Requestsexpand/shrink project

    scope, modify costs and schedule estimates

    Ch t 4

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    45/270

    Chapter 4Project IntegrationManagement

    Overall Change Control Influencing factors that create change to ensure beneficial

    results; ensure that change is beneficial Determining that change has occurred Managing actual changes as they occur

    Evaluate impact of change Meet with team to discuss alternatives Meet with management to present decision

    Change control requires Maintaining integrity of performance measurement baselines

    (project plan) Ensuring changes to scope are accurately recorded Coordinating changes across knowledge areas (scheduling, risk,

    cost, quality, etc.) Determine all factors that control change and pro-actively

    preventing the occurrence; evaluate the impact of change

    Ch t 4

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    46/270

    Chapter 4Project IntegrationManagement

    Inputs to Change Control

    Project Planbaseline performance

    Performance Reportsissue tracking, risk

    management Change Requestsorally or written,

    externally or internally initiates, legally

    mandated or optional

    Ch t 4

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    47/270

    Chapter 4Project IntegrationManagement

    Change Control Tools & Techniques All Changes must be evaluated before a decision can

    be reached

    Change Control Systemcollection of formal

    procedures, paperwork, tracking systems, approvallevels

    Change Control Boarddecision making authority

    Configuration Managementdocumented procedure

    to apply technical and administrative direction ID and document functional and physical characteristics Control changes to these characteristics

    Record and report change and implementation status

    Audit items and system to verify requirements

    Ch t 4 P j I i

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    48/270

    Chapter 4Project IntegrationManagement

    Change Control Tools & Techniques Performance Measurementearned value, plan

    variance analysis Additional Planningrevised cost estimates, modify

    activity sequences, plan adjustments Project Management Information System

    Change Control Systemmay have Change Control Plan Change Control Board

    Change Control Procedures, Corrective Action plans Performance Statistics, Reports, Change forms Specification reviews, Demonstrations, Testing, Meetings

    Configuration Management

    Ch t 4 P j t I t ti

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    49/270

    Chapter 4Project IntegrationManagement

    Change Control Outputs

    Project Plan Updates

    Corrective Actions

    Lessons Learnedvariance causes andreasoning documented for historical purposes

    Ch t 4 P j t I t ti

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    50/270

    Chapter 4Project IntegrationManagement

    Configuration Management

    Rigorous Change Management as it relates to scope Subset of the change control system

    Work Authorization System Controls gold plating; defines what task is/is not

    Meetings

    Most are inefficient; keep minutes

    Status can be determined without meeting

    Ch t 4 P j t I t ti

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    51/270

    Chapter 4Project IntegrationManagement

    Lessons Learned

    Project is not complete until a Lessons Learned iscompleted

    What have we done, how can we do it better Technical Aspects of the project Project Management (WBS, plans, etc.)

    Overall Management (communications, leadership)

    Best to have whole team complete and made available

    Also called Post Mortem

    Ch t 4 P j t I t ti

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    52/270

    Chapter 4Project IntegrationManagement

    Integration is a result of need for communicationwithin a project

    Primary responsibility to decide what changesare necessary is Management

    Project Managers must pro-actively define andsolve problems before reporting to superiors

    Ch t 5 P j t S

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    53/270

    Chapter 5Project ScopeManagement

    Project Scope Management

    Processes required to ensure that the project includesall, and only, work required

    Defining what is/is not included in the project

    Project scopework that must be donemeasuredagainst project plan

    Product scopefeatures and functions included in

    the product or servicemeasured againstrequirements

    Ch t 5 P j t S

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    54/270

    Chapter 5Project ScopeManagement

    Initiationprocess of formally recognizing thata new project exists, or an existing projectcontinue to next phase

    Involves feasibility study, preliminary plan, orequivalent analysis

    Authorized as a result of: Market Demand

    Business Need Customer Request

    Technological Advance

    Legal Requirement

    Ch t 5 P j t S

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    55/270

    Chapter 5Project ScopeManagement

    Initiation Inputs:

    Product Descriptioncharacteristics of theproduct/service that the project was to create

    Less detail in early phases, more comprehensive in latter

    Relationship between product/service and business need

    Should support later project planning

    Initial product description is usually provided by the buyer

    Strategic Plansupportive of the organization'sgoals

    Chapter 5 P j t S

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    56/270

    Chapter 5Project ScopeManagement

    Initiation Inputs (continued)

    Project Selection Criteriadefined in terms of the

    product and covers range of management concerns(finance, market)

    Historical Informationresults of previous project

    decisions and performance should be considered

    Chapter 5 P j t S

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    57/270

    Chapter 5Project ScopeManagement

    Tools & Techniques for Initiation Project Selection Methods:

    Benefit measurement modelscomparative approaches,scoring models, economic models

    Murder Boards Peer Review

    Scoring Models

    Economic Models

    Benefits compared to costs

    Constrained operation modelsprogramming mathematical Linear Programming

    Integer Programming

    Dynamic Programming

    Multi-objective programming

    Chapter 5 P j t S

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    58/270

    Chapter 5Project ScopeManagement

    Tools & Techniques for Initiation Project Selection Methods:

    Decision modelsgeneralized and sophisticated techniques

    Expert judgment

    Business Units with specialized skills Consultant

    Professional and Technical Associations

    Industry Groups

    Delphi Techniqueobtain expert opinions on technical

    issues, scope of work and risks Keep experts identities anonymous

    Build consensus

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    59/270

    Chapter 5Project ScopeManagement

    Outputs from Initiation: Project Charterformally recognizes project,

    created by senior manager, includes: Business need/Business Case Product description & title Signed contract Project Manager Identification & Authority level Senior Management approval Projects Goals and Objectives - Constraintsfactors that limit project management teams

    options Assumptionsfactors that are considered true for planning

    purposes. Involve a degree of risk

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    60/270

    Chapter 5Project ScopeManagement

    Scope Planningprocess of developing awritten statement as basis for future decisions

    Criteria to determine if the project or phase issuccessful

    Scope Planning Inputs:

    Product description

    Project Charter

    Constraints Assumptions

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    61/270

    Chapter 5Project ScopeManagement

    Scope Planning Tools & Techniques

    Product Analysis- developing a betterunderstanding of the product of the project

    Cost/Benefit Analysisestimatingtangible/intangible costs and returns of various projectalternatives and using financial measures (R.O.I.) toassess desirability

    Alternatives Identificationgenerate differentapproaches to the project; brainstorming

    Expert Judgment

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    62/270

    Chapter 5Project ScopeManagement

    Scope Planning Outputs Scope Statementdocumented basis for making

    project decisions and confirming understandingamong stakeholders. Includes:

    Project justificationbusiness need, evaluating futuretrade-offs

    Project Productsummary of project description

    Project Deliverableslist of summary of delivery itemsmarking completion of the project

    Project Objectivesquantifiable criteria met for success.Addresses cost, schedule and metricsunqualifiedobjectives indicate high risk (customer satisfaction)

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    63/270

    Chapter 5Project ScopeManagement

    Scope Planning Outputs (continued) Supporting detailincludes documentation

    of all assumptions and constraints

    Scope Management Planhow projectscope is managed, change control procedure,expected stability, change identification andclassification

    Control what is/is not in the project; preventsdelivering extra benefits to the customer thatwere not specified/required

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    64/270

    Chapter 5Project ScopeManagement

    Scope Definitionsubdividing majordeliverables into smaller, manageablecomponents Improve accuracy of cost, time, and resource

    estimates Define a baseline for performance measurement Clear responsibility assignments Critical to project successreduces risk of higher

    cost, redundancy, time delays, and poor productivity

    Defines what you are doing; WBS is the tool

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    65/270

    Chapter 5Project ScopeManagement

    Scope Definition Inputs:

    Scope Statement

    Constraintsconsider contractual provisions

    Assumptions

    Other Planning Outputs

    Historical Information

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    66/270

    Chapter 5Project ScopeManagement

    Scope Definition Tools & Techniques Work Breakdown Structuretemplates from

    previous projects

    Decompositionsubdividing major deliverables into

    manageable components: Major elementsproject deliverables and project management

    approach

    Decide cost and duration estimates are appropriate at level of detail

    Constituent elementstangible verifiable results to enableperformance management, how the work will be accomplished

    Verify correctness of decomposition All items necessary and sufficient?

    Clearly and completely defined?

    Appropriately scheduled, budgeted, assigned?

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    67/270

    Chapter 5Project ScopeManagement

    Scope Definition Outputs Work Breakdown Structure (WBS)a deliverable-

    oriented grouping of project assignments thatorganizes and defines the scope of the project

    Each descending level represents further detail; smaller and moremanageable pieces

    Each item is assigned a unique identifier collectively known ascode of accounts

    Work element descriptions included in a WBS dictionary (work,schedule and planning information)

    Other formats: Contractual WBSseller provides the buyer

    Organizational (OBS)work elements to specific org. units

    Resource (RBS)work elements to individuals

    Bill of Materials (BOM)hierarchical view of physical resources

    Project (PBS)similar to WBS

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    68/270

    Chapter 5Project ScopeManagement

    Scope Definition Outputs Work Breakdown Structure (WBS)

    First Level is commonly the same at the Project Life Cycle(requirements, design, coding, testing, conversion and operation)

    First level is completed before the project is broken down further

    Each level of the WBS is a smaller segment of level above

    Work toward the project deliverables

    Break down project into tasks that Are realistically and confidently estimable

    Cannot be logically divided further

    Can be completed quickly (under 80 hours rule of thumb) Have a meaningful conclusion and deliverable

    Can be completed without interruption

    Provides foundation for all project planning and control

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    69/270

    Chapter 5Project ScopeManagement

    Scope Definition Outputs Work Breakdown Structure (WBS) - Benefits

    Prevent work slippage

    Project team understands how their tasks fit into the overall projectand their impact upon the project

    Facilitates communication and cooperation between project teamand stakeholders

    Helps prevent changes

    Focuses team experience into what needs to be doneresults inhigher quality

    Basis and proof for estimating staff, cost and time Gets team buy-in, role identification

    Graphical picture of the project hierarchy

    Identifies all tasks, project foundation

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    70/270

    Chapter 5Project ScopeManagement

    WBS phrases Graphical hierarchy of the project

    Identifies all tasks

    Foundation of the project

    Very important

    Forces thought of all aspects of the project

    Can be re-used for other projects

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    71/270

    Chapter 5Project ScopeManagement

    Scope Definition Outputs Work Breakdown Structure (WBS)Dictionary

    Designed to control what work is done and when

    Also known as a task description

    Puts boundary on what is included in a task and what is notincluded

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    72/270

    Chapter 5Project ScopeManagement

    Scope Verification Inputs Work resultspartially/completed deliverables,

    costs to date

    Product documentationdescription available for

    review (requirements) Scope Verification Tools & Techniques

    Inspectionmeasuring, examining, testing todetermine if results conform to requirements

    Scope Verification Outputs Formal acceptancedocumentation identifying

    client and stakeholder approval, customer acceptanceof efforts

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    73/270

    Chapter 5Project ScopeManagement

    Scope Change Control:

    Influencing factors to ensure that changes arebeneficial

    Determining scope change has occurred Managing changes when they occur

    Thoroughly integrated with other control

    processes

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    74/270

    Chapter 5Project ScopeManagement

    Scope Change Control Inputs: Work Breakdown Structure

    Performance Reports- issues reported

    Change Requestsexpansion/shrink ofscope derived from : External events (government regulations)

    Scope definition errors of product or project

    Value adding changenew technology Scope Management Plan

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    75/270

    Chapter 5Project ScopeManagement

    Scope Change Control Tools& Techniques

    Scope Change Control Systemdefinesprocedures how scope change can occur

    All paperwork, tracking systems, approval levels Integrated with overall change control procedures

    Performance Measurementdetermine what iscausing variances and corrective actions

    Additional Planning

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    76/270

    Chapter 5Project ScopeManagement

    Scope Change Control Outputs:

    Scope Changesfed back through planningprocesses, revised WBS

    Corrective Actions Lessons Learnedcause and reasoning for

    variances documented for historical purposes

    Chapter 5 Project Scope

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    77/270

    Chapter 5 Project ScopeManagement

    Management By Objectives (MBO)

    Philosophy that has 3 steps:

    Establish unambiguous and realistic objectives

    Periodically evaluate if objectives are being met Take corrective action

    Project Manager must know that if project is not alignedor support corporate objectives, the project is likely tolose resources, assistance and attention.

    MBO only works if management supports it

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    78/270

    Chapter 6 Project TimeManagement

    Project Time Management Processes required to ensure timely

    completion of the project

    No consensus concerning differencesbetween activities and tasks

    Activities seen as composed of tasksmostcommon usage

    Other disciplines have tasks composed ofactivities

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    79/270

    Chapter 6 Project TimeManagement

    Activity Definition:identifying anddocumenting specific activities to produceproject deliverables identified in the WBS

    Must be defined to meet the project objectives

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    80/270

    Chapter 6 Project TimeManagement

    Activity Definition Inputs

    WBSprimary input

    Scope Statementproject justification &

    project objectives Historical Information

    Constraints

    Assumptions

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    81/270

    Chapter 6 Project TimeManagement

    Activity Definition Tools & Techniques

    Decompositionoutputs are expressed asactivities rather than deliverables

    Templatesreuse from previous projects

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    82/270

    Chapter 6 Project TimeManagement

    Activity Definition Outputs Activity Listall to be performed; extension to the

    WBS and includes description to ensure teammembers understand work to be performed

    Supporting Detailorganized as needed andinclude all assumptions and constraints

    WBS Updatesidentify missing deliverables andclarify deliverable descriptions. WBS updates often

    called refinements; more likely using newtechnologies in project

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    83/270

    Chapter 6 Project TimeManagement

    Activity Sequencingidentifying anddocumenting interactive dependenciesamong activities. Support later

    development of a realistic schedule Project Management software often used

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    84/270

    Chapter 6 Project TimeManagement

    Activity Sequencing Inputs: Activity List

    Product Descriptionproduct characteristics often affectactivity sequencing

    Mandatory Sequencingphysical limitations, hard logic,

    prototypes needed; inherent in nature of work being done Discretionary Dependenciesdefined by project management

    team; best practices or unusual aspects of project soft logic,preferred logic, preferential logic

    External Dependenciesrelationship between project activities

    and non-project activities (company policies, procurement, etc.) Constraints

    Assumptions

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    85/270

    Chapter 6 Project TimeManagement

    Network Diagrams Shows how the project tasks will flow from

    beginning to end

    Proves how long the project will take tocomplete

    Takes project tasks from low levels of WBSand placing them into their order of

    completion (beginning to end)

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    86/270

    Chapter 6 Project TimeManagement

    Activity Sequencing Tools & Techniques Precedence Diagramming Method (PDM)

    constructing network diagram using nodes torepresent activities and arrows to indicate

    dependencies; also called Activity On Node (AON) Most project management software uses

    Includes 4 types of dependencies: Finish to Startfrom activity must finish before to activity can begin;

    most commonly used

    Finish to Finishfrom activity must finish before the next may finish

    Start to Startfrom activity must start before next to activity can start

    Start to Finishtask must start before next activity can finish

    Use caution with last 3 techniques- logical relationships often notconsistently implemented with project management software

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    87/270

    Chapter 6 Project TimeManagement

    Activity Sequencing Tools& Techniques(continued)

    Arrow Diagramming Method (ADM)uses

    arrows to represent activities and connecting atnodes to illustrate dependencies

    Also called Activity On Arrow (AOA)

    Only uses finish to start dependencies

    PERT and CPM only can be drawn using AOA

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    88/270

    Chapter 6 Project TimeManagement

    Activity Sequencing Tools& Techniques(continued)

    Conditional diagramming methods

    GERT (Graphical Evaluation and ReviewTechnique)

    System Dynamic Models

    Allow for non-sequential activities (loops) or

    conditional branchesnot provided by PDM orADM methods

    Chapter 6 Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    89/270

    Chapter 6 Project TimeManagement

    Activity Sequencing Tools& Techniques(continued)

    Network Templatesstandardized networkscan be used. Composed of subnets, or fragnets

    Subnets are several nearly identical portions of anetwork (floors on a building, clinical trials, programmodules)

    Useful for several identical processes (clinical trials,

    programming modules).

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    90/270

    C ap e 6 ojec eManagement

    Activity Sequencing Outputs:

    Project Network Diagramschematicdisplay of project activities and relationships

    (dependencies). Should be accompanied by asummary narrative that describes the diagramapproach

    Activity List Updates

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    91/270

    p jManagement

    Activity Duration Estimating

    Involves assessing number of work periodsneeded to complete identified activities

    Requires consideration of elapsed time,calendars, weekends, and day of week workstarts

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    92/270

    p jManagement

    Activity Duration Estimating Inputs: Activity Lists

    Constraints

    Assumptions

    Resource Requirementsamount of labor assignedto activity

    Resource Capabilitieshuman and materialresources, expertise

    Historical Information Project Files, or records of previous project results

    Commercial Duration Estimatesuseful when durations are notdriven by actual work (approval periods, material resources)

    Project Team Knowledge

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    93/270

    p jManagement

    Activity Duration Estimating Tools& Techniques Expert Judgmentguided by historical information

    should be used whenever possible; high risk withoutexpertise avail.

    Simulationusing different sets of assumptions (MonteCarlo Analysis) to drive multiple durations

    Analogous Estimatingtop down estimating useactual, similar, previous known durations as basis forfuture activity duration. Used when limited knowledge

    is available. Form of expert judgment

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    94/270

    p jManagement

    Activity Duration Outputs: Activity Duration Estimatesquantitative

    assessments of work periods to complete an

    activity. Should indicate a range +/- ofpossible results

    Basis of Estimatesall assumptions shouldbe documented

    Activity List Updates

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    95/270

    p jManagement

    Schedule Development Determining start and finish dates for project

    activities

    Without realistic dates, project unlikely to befinished as scheduled

    Schedule development process often iteratesas more information becomes available(process inputs)

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    96/270

    p jManagement

    Schedule Development Inputs: Project Network Diagram

    Activity Duration Estimates

    Resource Requirements Resource Pool Descriptionavailability

    patterns; shared resources are highly variable

    Calendarsdefine eligible work periods Project Calendars affect all resources

    Resource Calendarsaffect specific resource pools orindividuals

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    97/270

    p jManagement

    Schedule Development Inputs (continued): Constraints

    Imposed Datesmay be required

    Key events or milestonesare initially requested and

    become expected during project

    Assumptions

    Lead and Lag Timedependencies may specifytime in order to satisfy relationship (example2

    weeks to receive order)

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    98/270

    p jManagement

    Schedule Development Tools & Techniques Mathematical Analysiscalculating theoretical

    early/late finish and start dates without regard forresource pool limitations; indicate time periods which

    activity should be scheduled given resource limits andother constraints: Critical Path Method (CPM)single early/late start and finish date for all

    activities. Based on specified, sequential network and single durationestimate. Calculates float to determine flexibility

    Graphical Evaluation and Review Technique (GERT)probabilistictreatment of network and activity duration estimates

    Program Evaluation and Review Technique (PERT)- sequential networkand weighted average duration to calculate project durationdiffers fromCPM by using mean (expected value) instead of most-likely estimate in CPM

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    99/270

    p jManagement

    Schedule Development Tools & Techniques Critical Path Method:refers to estimating based on one time

    estimate per activity One time estimate per task (Most Likely)

    Emphasis on controlling cost and leaving schedule flexible

    Drawn using AOA diagrams Can have dummy task

    PERT(Program Review and Estimating Technique) 3 Time estimates per activity

    Optimistic

    Pessimistic Most Likely

    Emphasis on meeting schedule, flexibility with costs

    Drawn on AOA diagrams

    Can have dummy tasks

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    100/270

    p jManagement

    Schedule Development Tools & Techniques Monte Carlo Analysis

    Uses a computer with PERT values and network diagram

    Tells Probability of completing a project on any specific day

    Probability of completing a project for any specific amount ofcost

    Probability of any task actually being on the critical path

    Overall Project Risk

    Suggests that Monte Carlo simulation will create a project

    duration that is closer to reality than CPM or PERT

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    101/270

    p jManagement

    Schedule Development Tools & Techniques(continued)

    Duration Compressionlook to shorten projectschedule without affecting scope

    Crashingcost and schedule trade-offs to determinegreatest amount of compression for least incremental costoften results in higher costs

    Fast Trackingperforming activities in parallel that normallywould be sequencedoften results in re-work and usually

    increases risk

    Simulation

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    102/270

    pManagement

    Schedule Development Tools & Techniques(continued)

    Resource Leveling Heuristicsleveling resourcesthat apply to critical path activities a.k.a. resource

    constrained scheduling when limitation on quantityof available resources; sometimes called Resource

    Based Method often increases project duration

    Project Management Software

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    103/270

    Management

    Schedule Development Tools & Techniques(continued) Project Mangers role

    Provide the team with the necessary information to properly

    estimate the task Complete a sanity check of the estimate

    Formulate a reserve

    Project Team should be involved; determine taskestimates

    Historical Records Guesses

    Actual Costs

    Benchmarks

    CPM and PERT

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    104/270

    Management

    Schedule Development Tools &Techniques

    Critical Path Method:longest path through a

    network diagram and determines the earliestcompletion of the project

    Proves how long the project will take

    Indicates tasks that need most monitoring

    Almost always have no slack

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    105/270

    Management

    Schedule Development Outputs: Project Scheduleincludes planned start

    and finish dates for each activity; remainspreliminary until resources assignments are

    approved. Usually in following formats: Project Network Diagrams(with date informationadded)show logical and critical path activities

    Bar or Gantt chartsactivity start and end dates,expected durations

    Milestone Chartsidentifies key deliverables andinterfaces Time-scaled network diagramsblend of project

    network and bar charts

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    106/270

    Management

    Schedule Development Outputs (continued): Supporting Detailall assumptions and constraints.

    May also include: Resource requirement by time period (resource histogram)

    Alternative schedules (best/worst case) Schedule reserve/risk assessments

    Schedule Management Planhow updates aremanaged

    Resource requirement updatesleveling and

    activity impact

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    107/270

    Management

    Schedule Control: Influencing factors which create schedule changes to

    ensure changes are beneficial

    Determining that schedule has changed

    Managing actual changes as they occur Inputs to Schedule Control:

    Project Schedulebaseline approved, measureagainst project performance

    Performance Reportsplanned dates met, issues Change Requests

    Schedule Management Plan

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    108/270

    Management

    Schedule Control Tools & Techniques Schedule Change Control Systemdefines

    procedures for schedule changes, paperwork,approval, tracking systems

    Performance Measurementassessmagnitude of variations to baseline; determineif corrective action is needed

    Additional Planning

    Project Management Software

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    109/270

    Management

    Schedule Control Outputs: Schedule Updatesany modifications,

    stakeholder notification Revisions change scheduled start and finish datesgenerally in response to scope changes. Re-baselining may be needed in drastic situations

    Corrective Actionre-align performancewith project plan

    Lessons Learned

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    110/270

    Management

    Key knowledge points not in PMBOK Need to know manual calculations of network

    diagrams Created after project charter and WBS (task

    estimates and dependencies are determined) Mandatory dependencies (Hard Logic)inherent in

    nature of work

    Discretionary dependencies (Soft Logic)based onexperience, desire or results

    External dependenciesbased on needs and desiresof organizations outside the project

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    111/270

    Management

    Methods to draw network diagrams Activity on Node (AON) or Precedence Diagramming

    Method (PDM) Boxes represent tasks

    Arrows show task dependencies 4 types of task relationships

    Finish to Start (task must finish before next can start)

    Finish to Finish (task must finish before next can finish)

    Start to Start (task must start before next can start)

    Start to Finish (task must start before the next can finish)

    No dummy tasks used

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    112/270

    Management

    Methods to draw network diagrams Activity on Arrow (AOA or Arrow

    Diagramming Method (ADM) Arrows used to represent tasks

    Only Finish to Start relationships are used May use dummy tasks (show dependencies) PERT and CPM estimating techniques can only be

    drawn using AOA CPM (Critical Path Method)estimating based on one time

    estimate per activity (the most likely time estimate) Emphasizes controlling cost and allowing schedule flexibility Can have dummy tasks

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    113/270

    Management

    Methods to draw network diagrams Activity on Arrow (AOA or Arrow

    Diagramming Method (ADM) continued:

    PERT(Program Evaluation and Review technique) 3 time estimates per activity: Optimistic (O), Most Likely

    (M), Pessimistic (P)

    Emphasizes meeting schedule, flexibility with cost

    Can have dummy tasks

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    114/270

    Management

    Methods to draw network diagrams PERT(Program Evaluation and Review technique) Estimating based on 3 formulas:

    PERT Duration: (P + 4M + O)/6 Standard Task Deviation: (PO)/6

    Task Variance: Total project estimate:

    Add up all Optimistic, Most Likely and Pessimistic values of the criticalpath tasks and apply P + 4M + O/6

    Total project variance (+/-): Add up the individual task variances and take the square root of the

    value. Use the value as a +/- figure to compute the Optimistic andPessimistic values. The total project estimate will serve as the basis.

    [PO]26

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    115/270

    Management

    Monte Carlo Simulation: Uses a computer with PERT values (P, M, O) and a

    network diagram but does not use the PERT formula

    Indicates Probability of completing project on a specific day

    Probability of completing project for any specific amount ofcost

    Probability of any task actually being on critical path

    Overall project risk

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    116/270

    Management

    Estimating techniques in general: Should be performed by entire project team

    Project manager needs to provide information to allow teamto create estimates; sanity check; formulate reserve

    Estimates are: Guesses, Historical Records, Actual Costs, Benchmarks,

    CPM, PERT

    Critical paths determines the earliest completion date andidentifies tasks that need monitoring

    Can be obtained by CPM, PERT and Monte Carlo estimatingtechniques

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    117/270

    Management

    Key Definitions: Slack (Float):the amount of time a task can be

    delayed without delaying the entire project. Tasks oncritical path have no slack.

    Slack is calculated by the difference between Early Start andLate Start of a task

    Free Slack (Float): the amount of time a task can be delayedwithout delaying the early start date of its successor

    Total Slack (Float): the amount of time a task can be delayedwithout delaying the project completion date

    Lag:inserted waiting time between tasks

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    118/270

    Management

    General Comments: Projects can have more than 1 critical path (increases

    risk) and can involve dummy tasks Negative float indicates that you are behind Resource Leveling involves possibly letting schedule

    and cost slip Heuristicsjust means rule of thumb e.g. 80/20 rule Schedules are calendar basedmakes this different

    than a time estimate Bar Chart a.k.a. Gantt chart (track progress, report to entire team

    including stakeholders, control tool) Network Diagram (to show task inter-dependencies, show project

    organization, basis for project control) Milestone chart (report to Senior management, shows major events)

    Chapter 6Project Time

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    119/270

    Management

    General Comments: To shorten project schedule examine the

    critical path Crashingadd more resources to the critical path

    tasks Usually results in increased cost Fast Trackingperforming tasks in parallel

    Can result in re-work and increased risk

    Best to select method that has least impact on

    the project (is the importance on cost, risk orschedule?)

    Chapter 6Project TimeM

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    120/270

    Management

    General Comments: Bar (Gantt) Charts

    Weak Planning Tool, effective progress and reporting tool Does not show interdependencies of tasks Does not help organize the project more effectively

    Network Diagrams (PERT, CPM, PDM) Shows task interdependencies Aids in effectively planning and organizing work Provides a basis for project control

    Milestone Charts Only shows major events Good for reporting to management and customer

    Flow Charts Depicts workflow and not commonly used for project management

    Chapter 6Project TimeM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    121/270

    Management

    General Comments: Free Slack (Float)amount of time a task can be delayed

    without delaying the early start date of its successor Total Slack (Float)amount of time a task can be delayed

    without delaying the project completion date

    Laginserted waiting time between tasks Resource Levelinglevel peaks of resource usage;

    stable number of resourcesallows schedule and costslip in favor of leveling resources

    Heuristicrule of thumb (80/20 rule)

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    122/270

    Management

    Project Cost Management Ensure that the project is completed within budget

    Concerned with cost of resources needed to completeactivities; consider effect of project decisions on cost

    of using product life-cycle costing Most prospective financial impact of using the productis outside the project scope

    Consider information needs of stakeholders,controllable and uncontrollable costs (budget

    separately for reward and recognition systems)

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    123/270

    Management

    Project Cost Management Estimating should be based on WBS to improve

    accuracy Estimating should be done by the person performing the

    work

    Having historical records is key to improving estimates Costs (schedule, scope, resources) should be managed

    to estimates A cost (schedule, scope, baseline) should be kept and

    not changed Plans should be revised as necessary during completion

    of work Corrective action should be taken when cost problems

    (schedule, scope and resources) occur.

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    124/270

    Management

    Resource Planning: Determining what physical resources and quantities

    are needed to perform work

    Inputs to Resource Planning:

    Work Breakdown Structure Historical Information

    Scope Statementjustification & objectives

    Resource Pool Descriptionwhat resources are

    potentially available for resource planning Organizational Policiesstaffing, procurement

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    125/270

    Management

    Inputs to Resource Planning: Work Breakdown Structure

    Network Diagram

    Schedule

    Risks Historical Information

    Scope Statementjustification & objectives

    Resource Pool Descriptionwhat resources are

    potentially available for resource planning Organizational Policiesstaffing, procurement

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    126/270

    Management

    Resource Planning Tools & Techniques Expert Judgment

    Alternatives Identification

    Resource Planning Outputs: Resource Requirementswhat type & how

    many resources are needed for each activity

    in the Work Breakdown Structure

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    127/270

    Management

    Cost Estimating: Develop approximate costs of resources

    Distinguish estimating from pricing

    Estimatinglikely amount Pricingbusiness decision

    Identify alternatives and consider realigningcosts in phases to their expected savings

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    128/270

    Management

    Cost Estimating Inputs: Work Breakdown Structure

    Resource Requirements

    Resource Rates (if known)

    Activity Duration Estimates

    Historical Information(project files, commercialcost databases, team knowledge

    Chart Of Accountscoding structure for accounting;general ledger reporting

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    129/270

    Management

    Cost Estimating Tools & Techniques Analogous Estimatingtop down; using actual costs

    from previous project as basis for estimate Reliable when previous projects are similar and individuals have

    expertiseform of expert judgment

    Parametric Modelinguses project characteristics inmathematical models to predict costs (e.g.building houses)

    Reliable when historical information is accurate, parameters arequantifiable, and model is scalable

    2 types: Regression analysis, Learning Curve

    Bottom Up Estimatingrolling up individual activities intoproject totalsmaller work activities have more accuracy

    Computerized toolsspreadsheets, software

    Chapter 7Project CostM t

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    130/270

    Management

    Cost Estimating Tools & Techniques Pros and Cons

    Analogous Estimating Quick - Less Accurate

    Tasks dont need to be identifiedEstimates preparedwith little detail and understanding of project

    Less costlyRequires considerable experience to do well

    Gives PM idea of management expectationsInfighting athigh levels of organization

    Overall project costs are cappedDifficult for projects withuncertainty

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    131/270

    Management

    Cost Estimating Tools & Techniques Pros and Cons

    Bottom Up Estimating More AccurateTakes time and expense

    Gains buy-in from the teamTendency for team to padestimates

    Based on detailed analysis of projectRequires thatproject be defined and understood

    Provides a basis for monitoring and controlTeaminfighting to get biggest piece of pie

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    132/270

    Management

    Outputs from Cost Estimating Cost estimatesquantitative assessments of likely costs ofresources required to complete tasks

    For all resources of the project (labor, materials, supplies, inflationallowance, reserve)

    Expressed in units of currency

    Supporting Detail Description of scope (reference to the WBS) Documentation how estimate was developed Indication of range of possible results Assumptions

    Cost Management Planhow cost variances will be managed

    Cost Risk:associated to seller for Fixed Price; associated tobuyer for Time and Materials budget

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    133/270

    Management

    Cost Budgeting Involves allocation of total estimate to individual work

    to establish a cost baseline to measure performance

    Cost Budgeting Inputs

    Cost Estimate Work Breakdown Structure

    Project Scheduleincludes planned start and finishdates for items costs are allocated to

    Needed to assign costs during the time period when theactual cost will be incurred

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    134/270

    Management

    Cost Budgeting Tools & Techniques Same as Cost Estimating Tools and Techniques

    Outputs from Cost Budgeting

    Cost Baselinetime phased budget to measure andmonitor cost performance

    Developed by summing estimated costs by period (S curve ofvalues vs. time)

    Larger projects have multiple baselines to measure different

    aspects of cost performance

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    135/270

    Management

    Cost Control Concerned with influencing factors that create

    changes to the cost baseline that are beneficial

    Determining that the cost baseline has changed

    Managing actual changes as they occur Monitor cost performance to detect variances Record all appropriate changes accurately in the cost baseline

    Preventing incorrect, unauthorized changes being included in thecost baseline

    Informing stakeholders of authorized changes Determine the whys of positive and negative variances

    Integrated will all other control processes (scope, change, schedule,quality)

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    136/270

    Management

    Inputs to Cost Control Cost Baseline Performance Reportsmeet, exceed budget

    50/50 Ruletask is considered 50% complete when it begins and gets credit forremainder 50% only when completed

    20/80 Rule- task is considered 20% complete when it begins and gets credit forremainder 80% only when completed

    0/100 Ruletask only credited when fully completed

    Change Requests Cost Management Plan

    Tools & Techniques of Cost Control Cost Change Control Systemdefines the procedures by which the cost

    baseline may be changed Performance Measurementassess magnitude of cost variations (Earned

    Value Analysis) and what is causing the variance Additional Planningexamine alternatives Computerized Toolsforecast planned costs, track actual costs, forecast effect

    of cost changes

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    137/270

    Management

    Cost Control Outputs Revised Cost Estimate Modifications to cost information; require stakeholder approval and

    adjustments to other project areas

    Budget Updateschanges to approved cost baseline; revised inresponse to scope changes

    Corrective Action Estimate at completion(EAC)forecast of total expenditures Actual to date plus remaining budget modified by a factor (cost performance

    index) Current variances are seen to apply to future variances

    Actual to date plus new estimate for remaining work Original estimates are flawed, or no longer relevant

    Actual to date plus remaining budget Current variances are typical and similar variances will not occur in the future

    Lessons Learned

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    138/270

    Management

    Earned Value Analysis Integrates cost, schedule and scope

    Better that comparing projected vs. actual becausetime and cost are analyzed separately

    Terms: BCWSBudgeted Cost of Work Scheduled (how much work

    should be done)

    BCWPBudgeted Cost of Work Performed a.k.a. EarnedValue (how much work is budgeted, how much did webudget)

    ACWPActual Cost of Work Performed (how much did thecompleted work cost)

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    139/270

    Management

    Earned Value Analysis Terms:

    BACBudget at Completion (how much did youbudget for the total job)

    EACEstimate at Completion (what do we expectthe total project to cost)

    ETCEstimate to Completion (how much more dowe expect to spend to finish the job)

    VACVariance at Completion (how muchover/under budget do we expect to be)

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    140/270

    Management

    Earned Value Analysis Formulas

    Variance(PlanActual)

    Cost Variance (CV):BCWPACWP; negative is

    over budget Schedule Variance (SV):BCWPBCWS;

    negative is behind schedule

    Cost Performance Index (CPI): BCWP

    ACWP

    I am only getting x out of every $

    BCWPACWP

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    141/270

    Management

    Earned Value Analysis Formulas Schedule Performance Index (SPI): BCWP

    BCWS

    I am only progressing x % of the planned rate Estimate at Completion (EAC): BACCPI

    As of now we expect the total project to cost x$

    Estimate to Complete (ETC):EACACWP; how much will

    it cost from now to completion Variance at Completion:BACEAC; when the project is

    over how much more or less did we spend (most commonway of calculating EVA

    BCWP

    BCWS

    BAC

    CPI

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    142/270

    Management

    Earned Value Analysis BCWP comes first in most formulas

    If it is a variance, BCWP comes first

    If it is an index, BCWP is divided by

    If the formula relates to cost, use AWCP

    If the formula related to schedule, use BWCP

    Negative is bad; positive results are good

    ETC refers to this point on; EAC refers to when jobis completed

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    143/270

    Management

    Accuracy of Estimates Order of Magnitude Estimate:-25% - 75%;

    usually made during Initiation Phase

    Budget Estimate:-10% - 25%; usually madeduring the Planning phase

    Definitive Estimate:-5% - 10%; usuallymade during the Planning phase

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    144/270

    Management

    Accounting Standards Not usually part of the exam

    Present Value (value today of future cash

    flows): PV = FV

    (1 + r) N

    FV = Future Value

    R = Interest RateN = Number of time periods

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    145/270

    Management

    Accounting Standards Net Present Value:total benefits (income or revenue) less thecosts. NPV is the sum of each present value of eachincome/revenue item

    Internal Rate of Return (IRR):company may select projectbased on highest IRR

    Payback Period: number of time periods it takes to recover theinvestment in the project before generating revenues Benefit Cost Ratio (BCR):compares costs to the benefits of

    different projects Greater than 1 means benefits are greater than costs Less than 1 means costs are greater than benefits

    Opportunity Cost:opportunity given up by selecting one projectover another

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    146/270

    Management

    Accounting Standards Sunk Costs:expended costs. Sunk costs should not beconsidered when determining to continue with a troubled project

    Law of Diminishing Returns:the more that is put in the less ofan outcome is received

    Working Capital:current assetscurrent liabilities

    Variable Cost:costs that change with the amount of productionor the amount of work (materials, wages)

    Fixed Cost:non-recurring costs that do not change Direct Cost:directly attributable to project work (travel, wages,

    materials) Indirect Cost:overhead items or costs for the benefit of more

    than one project (taxes, fringe benefits)

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    147/270

    Management

    Accounting Standards Depreciation:assets lose value over time

    Straight Line depreciation: same amount is taken each year

    Accelerated Depreciation: 2 forms Double Declining Balance

    Sum of the Years Digits

    Life Cycle Costing:includes operations and maintenancephases

    Value Analysis:find a less costly way to do same work

    Make or Buy decisionsat Development (Planning)phase, not conceptual phase

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    148/270

    Management

    Accounting Standards Project Objectivesare not necessarily needed to fund project Project Definitionfocus on end product initially; costs and benefits

    will be evaluated later

    25% of project lifecycle expended at end of planning No guarantees; only most likely results Line of Balance charts are used for manufacturing Negative Floatthe late start date is earlier than the early start

    date Value Engineering/analysisdoes not trade performance for

    cost

    Prospectusprofitability and technical feasibility used to solicitfunding

    Chapter 7Project CostManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    149/270

    Management

    Accounting Standards Definitive Estimatemost precise/accurate estimate for

    determining project costs

    Management Reserveover time PM wants no change toreserve; customers wants $ back

    Cost and Schedule Datapredicts future performance ROI, Nest Present Value and Discounted Cash Flowall can

    be used to measure total income vs. total $ expended

    Undistributed budgetbudget that contains approved scopechanges but are not planned yet

    Depreciationis not a measurement of profitability Pay Back Period- # of periods required to recover the initialinvestment

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    150/270

    Management

    Project Quality Management Processes required to ensure that the project will

    satisfy the needs for which it was designed

    Includes all activities of the overall management

    function that determine the quality policy, objectives,and responsibilities. These are implemented byquality planning, quality control, quality assurance,and quality improvement.

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    151/270

    Management

    3 major processes: Quality Planningidentifying quality standards that arerelevant to the project (Plan); Project Manager, Project Owner

    Quality Assuranceevaluating overall project performanceto provide confidence that project will satisfy relevant qualitystandards (Implement or Execution); Project Team

    Quality Controlmonitoring specific results to comply withquality standards and eliminating unsatisfactory performancecauses (Check or Control); Project Manager, Project Team

    Compatible with ISO 9000 and 10000 series Proprietary and non-proprietary approaches (total quality

    management Must address the management of the project and the product of the

    project

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    152/270

    Management

    Qualitythe totality of characteristics of an entity thatbear on its ability to satisfy stated or implied needs Critical aspect is to turn implied needs into stated needs through

    project scope management Do not confuse with gradecategory or rank given to entities

    having the same functional use but different requirements for

    quality Customer satisfactionconformance to specifications (mustproduce what is stated) and fitness for use (must satisfy realneeds)

    Preventionavoid mistakes vs. cost of correction Management responsibilityrequires participation of team;

    responsibility of management to provide resources Processes within phasesplan-do-check-act cycle

    Recognize that the investment in product quality improvements may beborne by the performing organization since the project may not last longenough to reap reward

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    153/270

    Management

    Quality Planning Identify quality standards are relevant and how to satisfy

    Inputs to Quality Planning Quality Policythe overall intentions and direction of an

    organization with regard to quality as expressed by management

    Scope Statement Product Description

    Standards and Regulations

    Other Process Outputsprocesses from other knowledgeareas (procurement planning)

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    154/270

    Management

    Tools &Techniques for Quality Planning Benefit/Cost Analysisconsider trade-offs, benefit is lessrework; cost is expense of project management activities

    Benchmarkingcomparing actual or planned practices tothose of other projects

    Flowcharting

    Cause and effect diagramming (Ishikawa or fishbone diagrams)illustrate how causes relate to potential problems or effects System or Process flowchartsshow how various elements of the

    system interrelate Helps anticipation of what and where quality problems may occur

    Design of Experimentsanalytical technique which defineswhat variables have most influence of the overall outcome

    Cost and schedule tradeoffs

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    155/270

    Management

    Outputs from Quality Planning Quality Management Plandescribes how team will implementits quality policy; describes the project quality systemorganizational structures, responsibilities, procedures, processesand resources needed to implement quality management

    Operational Definitionsdefines how an item is measured bythe quality control process. Also known as Metrics.

    Checklistsstructured tool used to verify that a set of requiredsteps has been performed

    Inputs to other processesmay identify a need for furtheractivity in another area

    Quality Assurance

    All planned and systematic activities implemented within the qualitysystem to provide confidence that the project will satisfy qualitystandards

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    156/270

    Management

    Inputs to Quality Assurance Quality Management Plan

    Results of quality control measurements (testing)

    Operational definitions

    Tools & Techniques for Quality Assurance

    Quality planning tools & techniques

    Quality Auditsstructured review of quality management activities toidentify lessons learned

    Outputs from Quality Assurance

    Quality improvementstaking action to increase the effectivenessand efficiency of the project to provide added benefits to thestakeholders

    Most likely will involve change control

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    157/270

    Management

    Quality Controlmonitoring specific results todetermine if they comply with quality standards andidentifying ways to eliminate causes of unsatisfactoryresults Includes project (deliverables) and management (cost and

    schedule performance) results Awareness of statistical quality control

    Prevention (keep errors out of process) and inspection (keep errorsfrom customers)

    Attribute sampling (result conforms) and variable sampling

    Special Causes (unusual events) and random causes

    Tolerances (acceptable range) and control limits (result falls withinrange)

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    158/270

    Management Inputs to Quality Control

    Work resultsinclude process and product results Quality Management Plan Operational Definitions Checklists

    Tools & Techniques for Quality Control

    Inspectionactivities such as testing to determine if results complywith requirements Control Chartsplot results over time Pareto diagramsfrequency of occurrence that identifies type or

    category of result (80/20 rule)guides corrective action Statistical samplingselect population of interest for inspection Flowcharting

    Trend Analysisforecast future outcomes based on historical results Technical performance (# of errors identified; # of errors that remain) Cost and Schedule performance (activities per period with significant variances)

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    159/270

    Management

    Outputs from Quality Control Quality Improvement

    Acceptance Decisions (accept/reject)

    Reworkaction to bring defective item into compliance

    Frequent cause of project overruns

    Completed checklists

    Process Adjustmentsimmediate corrective/preventiveactions

    Most likely involves change control

    Chapter 8Project QualityManagement

  • 5/21/2018 Slides.project Management Professional (Pmi) Study Guide

    160/270

    Management

    Tips from the Review Guide Philosophy:definition of quality, avoidance of gold plating giving customer extras, prevention over inspection

    Conformance to requirements, specifications and fitness of use Quality Managementprocesses required to ensure that the

    project will satisfy the needs for which it was undertaken

    Continuous Improvement