SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

41
TUAS WRP DTSS 2 Design and Implementation of TWRP Design and Implementation of TWRP Scott Trusler Scott Trusler Scott Trusler Scott Trusler Tuas WRP Project Director, CH2M (now Jacobs) Tuas WRP Project Director, CH2M (now Jacobs) Tuas WRP Project Director, CH2M (now Jacobs) Tuas WRP Project Director, CH2M (now Jacobs) 11 July 2018 11 July 2018 11 July 2018 11 July 2018 SAFETY ●SCHEDULE ●BUDGET ●QUALITY now a Jacobs company

Transcript of SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Page 1: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

TUAS WRPDTSS 2

Design and Implementation of TWRPDesign and Implementation of TWRP

Scott TruslerScott TruslerScott TruslerScott Trusler

Tuas WRP Project Director, CH2M (now Jacobs)Tuas WRP Project Director, CH2M (now Jacobs)Tuas WRP Project Director, CH2M (now Jacobs)Tuas WRP Project Director, CH2M (now Jacobs)

11 July 201811 July 201811 July 201811 July 2018

SAFETY ● SCHEDULE ● BUDGET ● QUALITY now a Jacobs company

Page 2: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

AgendaAgenda

Raising the Bar» Safety

» Innovation

» Working with Others

Delivery of TWRP» Project Overview

» Major TWRP Components

» Tendering and Construction Timeline

» Contract Packages

» Tendering Requirements & Scope

» Key Project Delivery Requirements

» Progress and Ongoing Preparation Works

» Project Challenges

Summary and Next Steps

2SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 3: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Raising the BarRaising the Bar

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 3

Page 4: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

TWRP Safety MissionTWRP Safety Mission

To fully implement PUB’s DTSS 2 Safety Mission

To team with the Contractors to create a collaborative safety culture committed to PUB’s Mission of ZERO HARM

We will not compromise on safety for any reason

We will recognise and reward safe performance

We will continuously learn and improve our approach to the safety and health of everyone involved in the delivery of TWRP

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 4

Page 5: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Workplace Safety and HealthWorkplace Safety and Health

No fatalities or life-changing incidents

Full compliance with all statutory regulations

Implementation of PUB’s safety requirements and life-saving rules

Don’t know, don’t care –eliminate both

5SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 6: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Workplace Safety and HealthWorkplace Safety and Health

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 6

Raise the bar for Personal Protective Equipment (PPE)

Safety Training Facility with hazard simulators

Incentive & Disincentive Scheme

» Rewards for commitment and demonstrable actions leading to exemplary performance in safety

» Deductions for poor safety performance, including inadequate supervision of sub-contractors

» Monthly assessment and scoring of KPIs in line with safety targets

» Progressive incentive payments during delivery

Helmet

Glasses Ear Plug/Muff

Glasses

Glasses

Long Sleeves

Long Pants

Page 7: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Plant Design FeaturesPlant Design Features

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 7

TWRP will include many advanced treatment processes including:

» Biosorption

» Membrane bioreactors

» Production of NEWater (NW) and Industrial Water (IW) for use by industry

» Hydrolysis of biosolids prior to anaerobic digestion

» Co-digestion of biosolids and imported food waste and greasy waste

First large-scale applications of Industrial ecology

» Waste or byproduct of one industry/process is used as an input into an adjacent process

» Move from a linear to a cyclical or closed-loop system

Page 8: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

SMART InnovationsSMART Innovations

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 8

SMART Personnel

» Wearable technologies: high visibility, real-time tracking, vital tracker, H2S sensor and body camera

SMART Operations and Maintenance

» Use of autonomous vehicle, deploying drones and autonomous robots

SMART Assets

» Use of Augmented Reality (AR) coupled with a Building Information Modelling (BIM) software

Page 9: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Collaborative Multi-Agency ImplementationCollaborative Multi-Agency Implementation

9SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Working with the National Environment Agency on the IWMF design and synergies

Security by Design – Ministry of Home Affairs (MHA)

Expanded and Integrated BIM Usage – Building and Construction Authority (BCA)

Green Mark Programme – BCA

Landscape Replacement Area + Solar Power – Urban Redevelopment Authority (URA)

Liaising and approvals with many other agencies

Page 10: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Delivery of TWRPDelivery of TWRP

10SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 11: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project LocationProject Location

11SAFETY ● SCHEDULE ● BUDGET ● QUALITY

68 hectares of reclaimed land

Limited development

Site bounded by sea water intake canal and Tuas Power

~54Ha

~14Ha

Page 12: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 12

1. Influent Pumping Stations

Page 13: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 13

2. Liquids (Domestic and Industrial Used Water) Treatment Facilities

Page 14: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 14

3. Biosolids Treatment Facility

Page 15: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 15

4. NW and IW Storage & Pumping

Page 16: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 16

5. Wet Weather Treatment Facility

Page 17: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 17

6. Admin/O&M with Visitor Gallery

Page 18: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project OverviewProject Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 18

1. Influent Pumping Stations

2. Liquids (Domestic and Industrial Used Water) Treatment Facilities

3. Biosolids Treatment Facility

4. NW and IW Storage & Pumping

5. Wet Weather Treatment

6. Admin/O&M with Visitor Gallery

Page 19: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Major TWRP ComponentsMajor TWRP Components

19SAFETY ● SCHEDULE ● BUDGET ● QUALITY

An illustration of the process flow

Page 20: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Industrial LiquidsIndustrial Liquids

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 20

Page 21: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Domestic LiquidsDomestic Liquids

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 21

Page 22: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

BiosolidsBiosolids

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 22

Page 23: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Tendering and Construction TimelineTendering and Construction Timeline

Milestone 1 – June 2023» Industrial used water influent pump station and treatment stream

commissioned and into production

Milestone 2 – August 2024» Domestic used water influent pump station and one-half of liquid treatment

stream commissioned and into production

» NEWater plant commissioned and into production

Milestone 3 – December 2025» Completion and commissioning of whole of Tuas WRP (Phase 1)

23SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 24: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Contract Packages (11 nos.)Contract Packages (11 nos.)

24SAFETY ● SCHEDULE ● BUDGET ● QUALITY

No. Name Description

C1A Site Development Works • Temporary site wide support infrastructures and services

• Permanent yard piping, utilities, 22 kV, port sewer, near-shore outfall

C2A Influent Pumping Stations • Two coarse screen shafts, three pumping stations, rising mains

• Two 66 kV substations

C3A Industrial Liquids Modules • Headworks, primary treatment, secondary treatment, tertiary

treatment to produce Industrial Water

C3B Domestic Liquids Modules – Primary • Headworks and primary treatment

C3C Domestic Liquids Modules – Secondary

and NEWater

• Secondary treatment including MBR, and NEWater production

C3D Product Water Storage and Pumping • Storage and pumping of NEWater and Industrial Water

C4A Biosolids and Digesters • THP, digestion, thickening, dewatering, solids conveyance

C5A Plant Monitoring and Control System • SCADA/PLC system with progressive buildout

C6A Administration and Operations Buildings • Two separate buildings

C6B Site Completion • Scope to be defined, includes roads, CCTV, main entrance and etc.

C6C Wet Weather Treatment Facility • Domestic used water overflow treatment and discharge

Page 25: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

25SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Milestone 3Completion of

Testing and

Commissioning of

TWRP

Tendering and Construction TimelinesTendering and Construction Timelines

Milestone 2Domestic Used

Water &

NEWater

Commissioned

NOTE:

The dates are indicative.

Milestone 1Industrial Used

Water

Commissioned

Dec 2018 / Jan 2019

Today

May 2018

Sep / Oct 2018

C1A – Site Development Works

C2A – Influent Pumping Stations

C3A – Industrial Liquids Modules

C3B – Domestic Liquids Module - Primary

C4A – Biosolids and Digesters

C5A – Plant Monitoring and Control System

C6A – Administration and Operations Bldgs

Construct/Operate

Extended Commissioning

Construct/Operate

Construct/Operate

C3C – Domestic Liquids Module - Secondary and NEWater

C3D – Product Water Storage and Pumping

C6B – Site Completion

C6C –Wet Weather Treatment Facility

Construct/Operate

Construct/Operate

Page 26: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

C2A - Influent Pumping StationsC2A - Influent Pumping Stations

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 26

Tunnels

IPS adjacent to

incoming two

tunnels under

DTSS2 Contract T-08

Scope includes:» 2 coarse screen shafts and 3 pump station

shafts with mined connections from T-08

» Shaft diameters from 20 m to 48 m ID; depths at 60 m and 80 m

» Domestic IPS – 16 pumps with total pumping capacity of 1,950 MLD

» Industrial IPS – 10 pumps with total pumping capacity of 450 MLD

» 6 rising mains underground to liquids modules headworks

» Centralised odour control facility

Page 27: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

C3A - Industrial Liquids ModulesC3A - Industrial Liquids Modules

Scope includes:» Two liquid treatment modules

» Headworks, primary treatment tanks, secondary bioreactor and membrane tanks

» Ceramic and polymeric membranes

» Industrial Water production

» Odour control facility

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 27

Industrial Liquids

Modules

Page 28: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Tendering Requirements:Contract 2A BCA RegistrationsTendering Requirements:Contract 2A BCA Registrations

28SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 29: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Tendering Requirements:Contract 3A BCA RegistrationsTendering Requirements:Contract 3A BCA Registrations

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 29

*Min. paid-up capital and minimum net worth of $15 million (equivalent to Civil Engineering A1 financial grade)

Page 30: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

C3B & C3C - Domestic LiquidsModulesC3B & C3C - Domestic LiquidsModules

Scope includes:» Two liquid treatment modules

» Headworks, primary treatment tanks, secondary bioreactor and membranes tanks

» Polymeric membranes

» NEWater production

» Odour control facilities

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 30

Domestic Liquids

Modules

Page 31: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

C4A - Biosolids TreatmentC4A - Biosolids Treatment

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 31

Biosolids

Facilities

Scope includes:» Biosolids building with space for future

equipment

» Thermal hydrolysis pre-digestion, centrifuges for pre-dewatering and thickening

» 10 silo digesters – potential construction with post-tensioned precast panels

» Majority of the IWMF interfaces

» Food waste and greasy waste receiving and treatment

» To IWMF > biosolids, biogas, odorous air

» From IWMF > electricity, steam, food waste

Page 32: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

6D BIM6D BIM

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 32

Design provided in BIM model with limited 2D drawings

Bentley Microstation platform with Navisworks

Contractors to update model; MEICA design completion and construction as-builts

Aligned to Singapore’s BIM Guide (BCA)

Contractors to deliver updated as-built model with COBie data embedded for all managed assets

3D

4D

5D6D

Quantity take-offs for

BQ and payment

Page 33: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Document ControlDocument Control

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 33

Supervision team will use a single TWRP document system (Aconex) for all document and workflow control – Common Data Environment/Project Management Information System

Contractors can choose their own system but must use S.O. system for communications & submissions

Contractors to be provided with an Aconex license for access to S.O. TWRP system

Page 34: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Primavera P6 ProgrammePrimavera P6 Programme

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 34

Integrated project programme built on P6

All contractors will be required to plan and report in P6

Programmes to be resource-loaded

Programmes linked to 3D Model in BIM for time-phasing

Page 35: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Summary of Key Project Delivery RequirementsSummary of Key Project Delivery Requirements

35SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Key Project

Requirements

for Tuas Water

Reclamation

Plant

Document Control

6D BIM

Safety Training Facilities

Primavera P6

Programme

Smart Innovations

Page 36: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Ongoing Preparation WorksOngoing Preparation Works

Ground Improvement Work to complete Q3 2018

Soil Investigation complete Q4 2018

Access Bridges» Route 2 in service

» Route 3 Q4 2018

Other» C1A Site Development

Contract tendering in process; award by year end 2018

» Sitewide Instrumentation & Monitoring Contract tendering in process; award Q4 18

36SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 37: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Project Challenges Project Challenges

Tight site» Thousands of workers at peak

» Thousands of vehicle movements on site

Restricted Access» Two land routes

» Limited site road network

Several tall structures» 38.5 m digester tanks

Interfaces» Between contracts and with incoming tunnels, IWMF

» With site-wide roads, utilities

Competition with other major infrastructure programmes in Singapore

Meeting first milestone by June 2023; concurrent construction & operations thereafter

37SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 38: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Summary and Next StepsSummary and Next Steps

38SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 39: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Key TakeawaysKey Takeaways

39SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Safety is a MUST

Timely completion of project

Value for Money

Industry’s Collaboration needed to succeed

Productivity and Innovations

Page 40: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

UpcomingUpcoming

Tenders rolling out in 2018:

» Contract 2A – September / October 2018

» Contract 3A – December 2018 / January 2019

Use [email protected] mailbox for general queries

40SAFETY ● SCHEDULE ● BUDGET ● QUALITY

Page 41: SIWW 2018 Tuas Nexus Forum TWRP Delivery revFINAL

Thank YouThank You

41SAFETY ● SCHEDULE ● BUDGET ● QUALITY