Situational Awareness UPDEA - Workshop. Awareness of the Situation 25,623 Alarms in 8 Hours 53...
-
Upload
jasper-booth -
Category
Documents
-
view
212 -
download
0
Transcript of Situational Awareness UPDEA - Workshop. Awareness of the Situation 25,623 Alarms in 8 Hours 53...
Situational AwarenessSituational Awareness
UPDEA - Workshop UPDEA - Workshop
Awareness of the Situation
19 Feb 2006 - 00h00 - 08h00 am
0
100
200
300
400
500
600
700
800
900
1000
00
:00
00
:34
00
:59
01
:25
01
:50
02
:15
02
:40
03
:05
03
:31
03
:57
04
:23
04
:48
05
:13
05
:38
06
:03
06
:28
06
:53
07
:18
07
:43
DEVICE
AMP
HZ
KV
MVA
MW
TAP
PANEL
• 25,623 Alarms in 8 Hours• 53 Alarms / min (average)• 80% Are consequential
Things to keep in mind during a disturbance -• Analog data is not reported in time with the state data• Controls are issued but the feedback is very slow• Control staff are no longer aware of the situation.
• Communications protocol (IEC60870-5-101)• SCADA data base design
State Alarming to Process Alarming
27 / 16:00:22 ARNOT SIMPL2 MVA HIGH ++ 450 440 ALARM
400 kVArnot
Customer
132 kV400 kVSimplon
220 kV
27 / 15:30:00 ARNOT SIMPL2 MVA HIGH 425 420 ALARM
Customer
Items to keep in mind that will cause a blackout:• The trip limit is 50% above the 90 degree limit.• Don’t have predictive analysis tools• No Rate-of-change alarm processing.• No consequential analysis warning• No warnings of when it could trip.
30 MVA in 30 min.
90
70
Alarm Questions
Customer
• How much knowledge do Control Staff have of the situation?• Address of a state change – there is no context.• No information - only data! • Why 2 separate messages?
Why not 1 message with all the event Information e.g.27 / 15:30:00 ARNOT_SIMPL1 - Trip - ARC - Trip, - Main 1, Zone 1, White phase, - Impedance Earth Fault - 35 km from
Arnot- Tripped 3 phase - Locked out –
Permanent Fault - 320 MVA Loss at 402 kV- DR indicates lightning strike on White
phase
Windhoek
Gaborone
Pretoria
Johannesburg
Cape Town
MaputoMbabane
South Africa Swaziland
Lesotho
Namibia
BotswanaZimbabwe
H
H
H
H
P
H
H
T
T
ET
ET
ET ETET
ETETET
ET ET
ET
T
P
N
ET
Transmission transports the electricity to Distribution
Generation makes the electricity
Distribution then sells the electricity to the customer
Electricity Production
Electricity production is a continuous process but we do not monitor it as such.
SCADA Master data base
Substn (Network Model)
CB
Line
Bus
KV
XF
Un
Power ApplicationSCADASubstation
Device
Point
Point
Analog
Analog
Counter
Device TypePAS Prediction tools State Estimation Short-circuit analysis Contingency analysis Voltage VAr dispatch
Violation alarming is
kept on this side
Real Time alarming is
done on this side
X
Problems :
Load / Truck
Processes are never static - they are always changing
Monitoring Problems
Result : We do not predict the future but we can
Limit Exceeded1d ad t
2 Rate-of-change
a
a’
b
b’
Hands up who recognise this.
Adding Situational Awareness
• Add Consequential Analysis - (New)• Combine PAS tool outputs• Add predictive warnings to SCADA
Monitor the Rate-of-Change of the Process Variables.
Reactive Proactive
1. Temperature 2. Megawatts 3. Megavars 4. Kilo Volts
Trip LimitHigh ++High
5 – 60 minutes
Customer
Customer
1
234
3
4
1
1 200
012
400
320
160012
0
0
Venus
VT
Designing for a Disturbance (1)
SCADA Master
Containerise substation data
Bay State
Substation State
Bay states
Station Bay
In classical systems each point is reported
individually to the SCADA master.
SCADA Master Philosophy• Front Ends use the bay and station state to filter the alarms• Messages are automatically suppressed based on bay state• Event data from both ends of a line is combined
Substation Philosophy• Bays report their state to the station bay following a change• The station state is a function of the bay and busbar states• The station bay decides what is sent to the SCADA Master• Update messages are sent to all bays on the same busbar
• A Dead Bus automatically sets the alarm suppression flag. • 1 message is sent to the control staff for dead busses
• Include the protection, analog data and what happened
Summary
• Change the: – Substation data base to Object Oriented structure– Master station data base to support Object Orientation– Communications protocol to allow for containerisation
• Allow – Ad hoc messages from RTU– Dynamic alarm suppression at Master based on bay state
• Provide– Situations Awareness identification areas using colour– Consequential Analysis tool to SCADA tool box
SCADA Database
Protocol Conversion
Dual Front EndComputers
EMSBack End Computers
1 200
012
400
320
160012
0
0
VT
Designing for a Disturbance (2)
X.21
RTU
Host I/O
Station Level 2
Bay Level 1
Bay Level 1
Station Level 2
Network Level 3
Bay Level 1
Bay Level 1
Primary Plant input via the RTU
SCADA – Substation philosophy :• Each status and analog values is reported individually to the
SCADA master• The physical bay structure is modelled in SCADA
SCADA Bay model
Level 1:Bay Modelling
BayDeviceElementSub - Element
BayDeviceElementSub - Element
BayDeviceElementSub - Element
Region Level 3
Level 3 :Network and region
Modelling
Master Station Philosophy• Each physical Bay is modelled in SCADA
including the substation and region bays.
• All tele-metered state changes are defined as log only.
• No messages are sent directly to the control staff from the station.
• All incoming status and analog value are used to update the bay state only.
• The station state is a function of the bays and busbar states.
• The bays send messages to update the Station bay state.
• The station object updates the bay states based on the overall station state.
Station Level 2
Level 2 :Sub-station
Modelling Station Level 2Station Level 2
Designing for a Disturbance (3)
Alarming
• The station bay sets flags that decides what alarm data is sent to the control staff by
the bays. See example on next slide.
• The station bay generates and sends messages that are common to the station.
• For local bay events the bay generates and sends bay related messages
• For line events the alarm data is combined from both bays to create a single line
alarm message
• A Dead Bus automatically sets the alarm suppression flag.
• All alarm messages include the protection, analog data and explain what happened
Station Level 2
Bay Level 1
Bay Level 1
Station Level 2
Network Level 3
Bay Level 1
Bay Level 1
Primary versus Consequential
Bay 1
Battery Charger
Bay 2
Bay 3
Bay DC Fail indication (Consequential)
Battery Fail Alarm (Primary)
Alarm Log
13H14 Bay 1 DC Fail Alarm13H14 Bay 2 DC Fail Alarm13H14 Bay 3 DC Fail Alarm
Battery DC Fail condition
Alarm Log
13h14 Battery DC output fail alarm
System Activity Log
13H14 Bay 1 DC Fail Alarm 13H14 Bay 2 DC Fail Alarm13H14 Bay 3 DC Fail Alarm
80% of alarms are consequential
Summary
• Change the: – Substation data base to Object Oriented structure– Master station data base to support Object Orientation– Containerisation is performed at the Master Station
• Allow – Bays to generate alarm messages– All alarms are defined as log only at Master
• Provide– Situations Awareness identification areas using colour– Consequential Analysis tool to SCADA tool box
Situational Awareness
Problem identification Highlight problem areas in colour on the display
Sequential Analysis Indicate the cause and effect and number of possible incidents in a possible event
Rate of change Identify time to Trip
Contingency Analysis Identify consequences of Trfr 2 trip and reasons for tripping.
VSAT Identify local voltage changes and risks
Consequential Analysis Identify Time to Trip (Trfr 4)
Identify size of Load loss and number of customers affected
Situational AwarenessScenario : • Trfr 2 has reported an oil temperature high alarm – note red line. • Since we measure the actual temperature and can predict, based on the current, when the
transformer will trip, i.e. how much time we have before it will trip.• Contingency Analysis calculated how much load will be carried by transformer 4 if trfr 2 trips.• Contingency Analysis also predicts that trfr4 will also trip on overload.• We can also predict how long it will take before trfr 4 trip based on the new load,• With VSAT we can estimate the resulting voltage collapse risk if both transformers trip.• We can also calculate the total load loss and the number of customers that will be affected.
Adding Situational Awareness
1) Highlight problem area in colour on the display
2) Indicate the cause and effect and number of possible incidents in a possible event
Sequence = 1 of 2Trip Time = + 0 Interruption = 76 + j26Reason = °C Customers = 0 VSAT = No threat
Sequence = 2 of 2Trip Time = + 2Interruption = 150 + j55Reason = AmpsCustomers = 6 VSAT = No threat
3) Highlight second problem area in a different colour. Include time to trip and consequences.
Questions