Site Issues to Be Cleared

1
ISSUES TO BE SOLVED THIS WEEK ISSUES SOLUTION REMARKS GC-21 PACKAGE HOLD BECAUSE OF COATING REPORT (ONE SPOOL) DISCUSS W/ PMC AND CHECK IN THE SITE CLEARED GC-20 PACKAGE PREPARATION PREPARE IN URGENT BASIS AND HAND OVER TO QC0 CLEARED 3L-PE COATING REPAIR IN SITE – NCC DO NOT SUPPLY THE MANPOWER FOR REPAIR ACTIVITY TRAINING AND APPROVAL OF IMCO PERSONNEL TRAINING AND APPROVAL OF NCC PERSONNEL ON-GOING A1-1 SITE WORK FOR SAND BLASTING – SHBC DO NOT WANT TO DO IN THE SITE CHECK WITH PMC AND ASK FOR THE ADVISE OTHERWISE SUBMIT TQ TO KOC ON-GOING WMS PREPARATION FOR URGENT LOCATIONS 1. STF-A32A 2. GC-20 3. GC-22 4. BS-150 WMS PREPARATION UNTIL 14 APRIL AND DISCUSS TO MICU ON-GOING HBP COATING EXPIRATION AFTER 10 MONTHS OF COATED SPOOL CHECK THE SPOOL STATUS

description

Site issues

Transcript of Site Issues to Be Cleared

ISSUES TO BE SOLVED THIS WEEK

ISSUESSOLUTIONREMARKS

GC-21 PACKAGE HOLD BECAUSE OF COATING REPORT (ONE SPOOL)DISCUSS W/ PMC AND CHECK IN THE SITECLEARED

GC-20 PACKAGE PREPARATIONPREPARE IN URGENT BASIS AND HAND OVER TO QC0CLEARED

3L-PE COATING REPAIR IN SITE NCC DO NOT SUPPLY THE MANPOWER FOR REPAIR ACTIVITY TRAINING AND APPROVAL OF IMCO PERSONNEL TRAINING AND APPROVAL OF NCC PERSONNEL

ON-GOING

A1-1 SITE WORK FOR SAND BLASTING SHBC DO NOT WANT TO DO IN THE SITECHECK WITH PMC AND ASK FOR THE ADVISE OTHERWISE SUBMIT TQ TO KOCON-GOING

WMS PREPARATION FOR URGENT LOCATIONS1. STF-A32A2. GC-203. GC-224. BS-150WMS PREPARATION UNTIL 14 APRIL AND DISCUSS TO MICUON-GOING

HBP COATING EXPIRATION AFTER 10 MONTHS OF COATED SPOOLCHECK THE SPOOL STATUS