Site Improvement and Deep Foundations - …courses.washington.edu/cm510/Lecture4.pdfSite Improvement...

35
1 Advanced Construction Techniques Deep Foundations Professor Kamran M. Nemati Autumn Quarter 2016 1 CM 510 Advanced Construction Techniques Site Improvement and Deep Foundations 2 Foundation Construction Shallow Foundations: consisting of footings or rafts foundation sized to control settlement and provide adequate margin of safety against shear failure in the foundation soil Deep Foundations: piles and piers used to bypass unsatisfactory soils and transfer structure loads to a suitable bearing stratum

Transcript of Site Improvement and Deep Foundations - …courses.washington.edu/cm510/Lecture4.pdfSite Improvement...

1

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

1

CM 510

Advanced Construction Techniques

Site

Improvement

and Deep

Foundations

2

Foundation Construction

Shallow Foundations:

consisting of footings or rafts

foundation sized to control settlement and provide adequate margin of safety against shear failure in the foundation soil

Deep Foundations:

piles and piers

used to bypass unsatisfactory soils and transfer structure loads to a suitable bearing stratum

2

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

3

What is a Foundation?

The element of a structure that transfers loads to the underlying ground with performance consistent with the design of the structure.

Loads are a combination of:

Static

Dynamic

Horizontal

Vertical

4

What is a Foundation?

Transcona Grain ElevatorWinnipeg, ManitobaOctober 18, 1913

Tilt: 27°

Bridge Abutment on Piles- 30 inches of Settlement

over 10 years

3

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

5

Reasons for Deep Foundations

Source: FHWA NHI-05-042 Design and Construction of Driven Pile Foundations - Volume I.

End Bearing Friction

(b) Uplift(a) Upper Strata Weak

or Compressible(c) Lateral

Loading

6

Reasons for Deep Foundations

Source: FHWA NHI-05-042 Design and Construction of Driven Pile Foundations - Volume I.

(d) Combined Uplift andLateral Loading

BridgeBent

Highway Signs orNoise Barriers

(e) Scour (f) Liquefaction

4

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

7

Reasons for Deep Foundations

Source. FHWA NHI-05-042 Design and Construction of Driven Pile Foundations - Volume I.

(h) Underpinning (i) Swelling(g) Fender Systems Soils

8

Reasons for Deep Foundations

Example of Forces on a Bridge (Lateral – Ice and River, Vertical – Vehicle)

Photograph courtesy of FHWA-NHI-132012 Soils and Foundations Workshop Participants Workbook

5

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

9

Reasons for Deep Foundations

Bridge Abutment ScourPhotograph courtesy of FHWA-NHI-132012 Soils and Foundations Workshop Participants Workbook

10

Reasons for Deep Foundations

Scour at Bridge AbutmentPhotograph courtesy of FHWA-NHI-132012 Soils and Foundations Workshop Participants Workbook

6

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

11

Excavations and Excavation Supports

In many construction jobs deep excavations must be made before the structure can be built.

When excavations have the potential to endanger lives or adjacent properties, bracing to support the soil must be designed.

The Occupational Safety and Health Act (OSHA) requires that all trenches exceeding 5 ft in depth be shored.

In large construction areas, excavation walls may be sloped, instead of providing structural support.

12

Slope Failure Mechanisms

Rotational slump in homogeneous clay

Translational slice in cohesionless sand or gravel

Slip along plane of weakness

7

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

13

Slope Stability

Driving forces: the component of soil weight downslope (forces causing instability).

Resisting forces: the soil strength acting in the opposite direction (resisting forces).

Mechanism of failure: When driving forces exceed the resisting forces.

14

Slope Stability

Factor of safety (FS): the ratio of resisting forces (or moments) to the driving forces (or moments).

Forces Driving

Forces ResistingFS

If FS 1, the slope will fail

If FS 1, the slope is theoretically stable.

The usual FS required is between 1.3 and 1.5

8

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

15

Slope Stability (Cont’d)

To estimate the factor of safety for a slope, the following information is required:

1. The soil and water profile

2. The kinematics of potential slope failure

3. The strength and weight of soils, and

4. The proposed slope geometry.

This estimate is for homogeneous materials.

16

Slope Stability (Cont’d)

Stability number is defined as:c

HN c

S

where:

= unit weight of

soil,

Hc = critical height,

and

c = cohesion.

(For clay soil f 0)

9

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

17

Example 1

For clay soil, the stability number of a slope cut at 65°, with f = 0 is 5, if the upslope angle a = 0,

565°

ft 5.29110

5650

s

c

cNH

48.120

5.29FS

psf 4405

20110

s

cc

N

HC

48.1440

650

dReq'c

c FS

Ns = 5

If = 110 pcf and c = 650 psf,

and slope height = 20 ft

Alternatively, the critical cohesion for the slope

and

18

Example 2

4.55

ft 9.26110

55.4650

s

c

cNH

A cut slope is to be made in a soft clay with its sides rising an angle of 75° to the horizontal. Given c =

650 psf and = 110 pcf, determine

the maximum depth up to which the excavation can be carried out.

7.28.241

650 FS

cc

c

psf 8.24155.4

10110

S

cc

c

cS

N

Hc

c

HN

From the graph Ns = 4.55

If the cut described above is made to only 10 feet, what is the factor of safety of the slope against sliding?

10

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

19

Theoretical Safe Heights for Homogeneous Clay Cut Slope with Vertical Sides

Soil

Consistency

Unconfined

Compressive

Strength,

qu (psf)

Cohesion, c

(psf)

Safe Height, H

(ft)

Very soft < 500 < 250 < 5

Soft 500 – 1000 250 – 500 5 –10

Medium 1000 – 2000 500 – 1000 10 – 20

Stiff 2000 – 4000 1000 – 2000 20 – 40

Very stiff 4000 – 8000 2000 – 4000 40 – 80

Hard > 8000 > 4000 > 80

The slope failures are probable in shallow excavations only for very soft to medium homogeneous clays.By flattening the slope angle from 90° to 45°, significant improvement in the factor of safety for a slope of a given height can be achieved.

Slope Stability (Cont’d)

20

Slope Protection

Temporary slope protection should be provided to prevent sloughing of soil materials into the excavation, such as coating or other impervious material applied to the slope.

To prevent slope erosion in rainstorms, spray-on product are used on silty soil materials to bind the soil particles on the surface.

11

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

21

Slope Protection (Cont’d)

Plastic covering can be used to prevent changes in moisture content on the surface of the slope to maintain stability.

Chain link fence can be draped over a slope surface, when the slope contains significant amount of loose large rocks.

22

Shallow Trenches

Cross-trench bracing are used in utility trench excavations.

Intermittent sheeting and bracing

Continuous sheeting and bracing

Trench shielding

12

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

23

Deep Cuts

Excavation depths exceeding 10 to 20 ft, require specialized planning for support.

Lateral earth pressure is proportional to the vertical pressure.

As a cut is made, the soil at the face tend to expand and move into the cut area.

If a support is placed against the excavation surface to prevent the soil movement, then the pre-excavation stress is maintained.

24

Excavation Support Methods

Soldier beam and lagging

Pairs of soldier beams are driven to a depth slightly below the final excavation.

Their spacing is in the order of 6 to 12 ft so that available timber can be used for lagging.

The lagging timber, which is slightly shorter than the spacing but on the order of 2 to 4 in. thick, are installed behind the front flange to retain the soil as excavation proceeds. Some hand excavation is usually required to get the lagging into the place.

13

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

25

Soldier beam and lagging

The soldier pile and lagging method is inappropriate for perfectly cohesionless soil.

For cohesionless soils sheeting must be used.

26

Soil Nailing

Soil Nailing is an insitu reinforcing of the soil while it is excavated from the top down.

An array of soil nails which are passive inclusions are installed in a grid that functions to create a stable mass of soil.

This mass of reinforced soil functions to retain the less stable material behind it.

In the right soil conditions, soil nailing is a rapid and economical means of constructing excavation support systems and retaining walls.

14

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

27

Soil Nailing

In many applications soil nailing can be the least disruptive way to construct a retaining wall.

Soil nailing requires an unusual amount of hand work, craftsmanship and geotechnical knowledge to construct.

The typical construction sequence begins with the excavation of a shallow cut. Then shotcrete is applied to the face of the cut and soil nails are drilled and grouted. This sequence is then repeated until subgrade is reached.

28

Soil Nailing Examples

NorthWest Animal Facility, UC Berkeley, Cal

Construction of an underground laboratory at the UC Berkeley, required temporary shoring on all four sides of the excavation. The tolerances for the shoring was specified to be no more than plus or minus one inch. The excavation depth varied from 15 to 37 feet, and was constructed in colluvial soils, consisting of stiff sandy clays and dense clayey sands with gravel and some cobbles. Approximately 14,000 square feet of area was soil nailed.

15

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

29

Soil Nailing Examples

Chemistry Building, WSU, Pullman, WA

The 40-ft deep excavation at this site was made in stiff to hard, slightly clayey silt, with standard penetration resistances ranging from 15 to 45. The silt had a cohesion of 200 psf and a friction angle of 28 degrees. At one corner of the site, a two story brick auditorium was located ten feet behind the soil nailed wall. The movement was less than 0.3 inches at the face of the wall, less than 0.2 inches at 18 feet behind the wall, and less than 0.1 inches at 36 feet behind the wall. Eight rows of soil nails were designed to support the excavation.

30

Soil Nailing Examples

The Beckman Center, UC San Diego, Cal

Construction of the New Chemical Science Building at the Scripps Research Institute required an excavation of up to 57 feet deep. The job consisted of 75% soil nailing and shotcrete and 25% of soldier beam and tieback shoring - a total of 24,080 sq ft. The soldier beams and tiebacks were utilized where soil nails would have interfered with existing buildings and new or existing utilities. The deepest section was shored with 10 lifts of permanent soil nails. A permanent shotcrete facing was installed in front of the shoring system which was completed in ten weeks.

16

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

31

Soldier Pile - Tremie Concrete

SPTC is used for very difficult conditions in soft ground with a high water table.

Soldier piles are set in predrilled holes, and the space between flanges of adjacent soldier piles is excavated and filled with bentonite slurry.

Reinforcement is lowered into the trenches and tremie concrete is placed. As tremie concrete displaces the slurry, it is collected and recycled for future use.

The final product is a continuous concrete wall beneath the ground surface prior to excavation. After completion of the wall, excavation and interior bracing can begin.

32

Soldier Pile - Tremie Concrete

17

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

33

Soldier Pile - Tremie Concrete

Typical free-hanging mechanical clamshell for slurry trench excavation

34

Soldier Pile - Tremie Concrete

free-hanging mechanical clamshell

18

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

35

Slurry Trench Method (Cont’d)

Used in cases of troublesome dewatering and excavation support problems.

It involves constructing an impervious barrier beneath the ground surface.

The excavated material is replaced with heavy clay slurry (the lateral pressure from the slurry will keep the trench open)

36

After the excavation is completed, concrete placement follows using tremie concrete method, from bottom to the top of excavation.

As tremie concrete displaces the slurry, it is collected and recycled for future use.

When the concrete is cured, the construction site is enclosed within a rigid, impervious barrier.

This method has been employed to depths exceeding 200 feet.

Slurry Trench Method (Cont’d)

19

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

37

Tremie Concrete

Underwater concrete plays an important role in the construction of offshore structures.

It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).

38

Tremie Concrete Mix

Special mix with plasticizer

High slump concrete with set retarders

Smaller aggregate sizes

Four-hour workability

Designed for placement under water via tremie pipe

20

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

39

Tremie Concrete

Underwater Concrete Mixes:

Structural concrete Coarse Aggregate: Gravel of 3/4” max. size.

Use 50-55 % of the total aggregate by weight.

Fine Aggregate: Sand, 45-50% of the total

aggregate by weight.

Cement: Type II ASTM (moderate heat of hydration),

600 lbs/yd3.

Pozzolans: ASTM 616 Type N or F, 100 lbs/ yd3.

40

Tremie Concrete

Water/Cement Ratio: 0.42 (0.45 Maximum).

Water-Reducing Admixture (preferably it is also plasticizer): Do not use superplasticizers.

Air-Entrainment Admixtures: To give 6% total air.

Retarding Admixture: To increase setting time to 4-24 hours, as required.

Slump: 6 1/2 in. ± 1 in.

This mix will develop compressive strength in the range of 5,600 – 7,000 psi at 28 days.

It will flow out on a slope of 6:1 to 8:1 horizontal/ vertical and, if properly placed, should give nominal segregation and laitance.

21

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

41

Tremie Pipe

Breaking Tremie Tube - In this operation the contractor is removing a 20' section from the 140' + tremie tube to continue the first full depth placement in the UR pylon. Concrete placed will be about 400 CYs.

42

Tremie Pipe

Transition of the pipeline from vertical to horizontal.

22

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

43

Placement of Tremie Concrete

The placement of tremie concrete is carried out through a tube, usually 10-to 12-in. pipe.

The pipe may be sectional but joints should be flanged and bolted, with soft rubber gasket, so as to prevent any in-leakage of water.

The tremie pipe must have sufficient wall thickness so that it negatively buoyant when empty.

44

Placement of Tremie Concrete

Install a steel plate on the bottom end with a soft rubber gasket. The plate is tied with twine to the pipe.

23

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

45

Placement of Tremie Concrete

The placement is started by placing the sealed pipe on the bottom and then partially filling it with the tremie concrete mix.

When tremie has been filled to a reasonable distance (distance required to overcome the frictional head 1-2 m) above the balancing head of fresh concrete versus surrounding liquid, the pipe is raised 150 mm, allowing the concrete to flow out.

The lower end of the pipe is kept embedded in fresh concrete, but no deeper than where the concrete has taken the initial set (with retarder to prevent the initial set, the depth of embedment becomes less sensitive).

46

Placement of Tremie Concrete

The tip of the tremie pipe should always be immersed about 1 m as a minimum so as to prevent water inflow into the pipe.

The flow of concrete should be smooth, consistent with the rate at which concrete can be delivered into the hopper at the top.

The method of delivery should provide relatively even feed to the hopper rather than large batches being suddenly dumped.

When large areas are to be covered, multiple tremie pipes should be used.

The distance tremie can flow without excessive segregation is between 6 and 20 m.

24

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

47

Placement of Tremie Concrete

48

Tremie concrete procedures was used to repair damage to a reef in the Florida Keys caused by vessel impact.

The impact site was located in six to ten feet of water off Miami, in a region of the reef frequented by sight-seeing boats and recreational divers. The ship impact destroyed the living surface of the reef over an area of approximately 50-ft by 70-ft, forming a shallow crater in the reef.

Diver Places underwater tremie concrete between reef units and bottom. Bottom of the barge can been seen just a few feet above the diver's head.

Tremie Concrete - Application

25

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

49

Excavation Bracing

For narrow excavations, internal struts are most appropriate.

Before struts are installed, a horizontal member called waler is placed against the soil support.

Intermediate struts are then installed from waler to waler across the excavation.

Cross-lot struts are not feasible for very wide excavations.

50

Excavation Bracing

Design of excavation bracing for a pump station adjacent to an active spring.

26

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

51

Excavation Bracing

Design of excavation bracing for a detention basin and related piping.

52

Excavation Bracing (Cont’d)

For very wide excavations, raker bracingis used.

The support for the rakers (driven piles or footings) are installed at the bottom of the excavation.

27

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

53

Excavation Bracing (Cont’d)

Construction of the soil support and removal of the remainder of the excavation then begins.

Compared to cross-lot bracing, in raker bracing system the central portion of the work area is relatively uncluttered.

54

Tiebacks

Anchors or tiebacks eliminate obstructions in the excavation inherent in rakers or struts.

28

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

55

Tiebacks

They consist of rods that extend well beyond any potential failure surface into firm undisturbed soil or rock.

Some tiebacks are made with high tensile cables grouted into rock and pre-stressed against a wale, and others utilizing ordinary steel rod or reinforcing steel.

56

Tiebacks (Cont’d)

Tieback systems are generally very successful in preventing movements of the excavation walls.

Usually, the excavation wall is left in place after the permanent construction inside the braced excavation is complete. Its is often used as the back form for the permanent basement of the structure.

29

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

57

Tiebacks (Cont’d)

Tiebacks, if left in place, are always cut to relieve tension when the permanent structure can safely carry the load.

58

Void Forms

In case of expansive soils, carton/void forms can be specified to be placed under the slab on grade.

30

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

59

Void Forms

If there is no void space between the foundation and the expansive soil.

60

Void Forms

If there is no void space between the foundation and the expansive soil

31

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

61

Void Forms

If there is no void space between the foundation and the expansive soil

62

Void Forms

Isolating the structure from the expansive soil

32

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

63

Void Forms

Isolating the structure from the expansive soil

64

Void Forms

Isolating the structure from the expansive soil

33

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

65

Movement limits associated with

braced excavation supports

The opposite figure was developed from data gathered on a number of braced excavation projects.

It can be used to estimate settlement induced adjacent to an excavation.

66

Movement limits associated with

braced excavation supports

Example:

You want to estimate the settlement 15 ft from the bracing wall of a 30-ft-deep excavation in soft clay.

5.030

15

depth Excavation

excavation from Distance

0.5

0.6

%6.0depth Excavation

Settlement

Expected settlement = 0.006 30 = 0.18 ft

34

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

67

GLOSSARY OF TERMS

Waler: Horizontal timber used to hold close sheeting in position.

Lagging: Lengths of sawn hardwood timber planks used to support the sides, walls or roof as necessary of shafts and drives and to prevent material from those faces falling into the excavation. The term is also sometimes used when referring to the layer of poling boards doing the same duty in trenches. The lagging is supported in turn by walkings, legs, caps, sets or frames, as applicable. (See also "lathes" below).

Lathes: Short lengths of hardwood timber usually split and about 1.25 to 1.5 meters long used to support the side walls (and roof in drives) and supported in turn by walings, legs or caps as applicable.

Strut: Hardwood timber (usually horizontal) in compression resisting thrust or pressure from the face or faces of an excavation.

Soldier: Vertical upright hardwood timber used for supporting a trench wall, taking the thrust from horizontal walers and supported by struts.

68

Slurry Trench / Diaphragm Walls

In recent years, the slurry trench method has been successfully developed to deal with particularly troublesome dewatering and excavation support problems.

These methods involve constructing an impervious barrier beneath the ground surface.

35

Advanced Construction Techniques

Deep Foundations

Professor Kamran M. NematiAutumn Quarter 2016

69

Slurry Trench / Diaphragm Walls