SINTAKOTE STEEL PIPELINE SYSTEMS
PROJECT EXPERIENCE
Steel Mains and its antecedents have participated in most of the major water supply
pipelines constructed in Australia since the early 1900’s. A summary of some of those
Steel Mains SINTAKOTE Steel Pipeline Systems projects undertaken in recent years
is given below.
Principal Project Year/s Length
(km)
Diameters
(mm)
Variations* Time*
Extensions
1
Woleebee Creek to
Glebe Weir Pipeline
Project
2013
120
914/960/
1067/1404
None
None
2
Queensland Curtis
LNG Project - Water
Trunklines
2012/2013
140
406/508/
559/660/
762/960
None
None
3
Melbourne
Desalination Plant-
Transfer Pipeline
2009/2010
84
1930
None
None
4
Adelaide
Desalination Plant-
Transfer Pipeline
2009
12
1575
None
None
5
Sugarloaf
Interconnector
Pipeline
2008/2009
70
1404/1750
None
None
6
Wimmera-Mallee
Pipeline Project
2007/2008/
2009
94
711/1016
None
None
7
South East
Queensland
Water Grid
2006/2007/
2008
334
813/
960/1085/
1290/1451
None
None
8
Bayswater Power
Station
2008
4
1451
None
None
9
Ballarat Link of the
Goldfields Superpipe
2007/2008
47
800
None
None
10
Goulburn to
Campaspe Link
Superpipe Project
2007
47
1124
None
None
SOLUTIUONS FOR LIFE Page 2
* There were no variations or time extensions attributable to Tyco Water’s failure to perform.
1. Project Name: Woleebee Creek to Glebe Weir Pipeline Project
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure pipeline from Woleebee Creel to Glebe Weir.
120km of 914/960/1067/1404mm SINTAKOTE RRJ MSCL pipe.
April 2013 to September 2013.
SunWater
None to date.
Pipe deliveries completed to date on time with no problems.
Referee:
Mr Russell Paton
SunWater
Tel: (07) 3120 0201
11
Torrens System
Upgrade Project
2007
3.4
1829
None
None
12
Liverpool to Ashfield
Pipeline
2006/2007
20
988/1067/
1124
None
None
13
Burdekin to
Moranbah Pipeline
2006
172
813
None
None
14
Kwinana
Desalination
Connection
2005/2006
23
1200/1400
None
None
15
Stag Creek Pipeline
2005
15
800/960
None
None
16
Clarence Valley
RWSS – Stage 1B
2003/2004
16
960
None
None
17
Mt Miller Pipeline
2003
17
900
None
None
18
Clarence Valley
RWSS – Stage 1A
2002
35
660
None
None
19
Stirling Trunk Main
2000/2001
106
1400
None
None
SOLUTIUONS FOR LIFE Page 3
2. Project Name: Queensland Curtis LNG Project - Water Trunklines
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure pipeline for the QCLNG Upstream Project.
140km of 406/508/559/660/762/960mm SINTAKOTE RRJ MSCL pipe.
April 2012 to June 2013.
Queensland Gas Company (QGC)
None.
Pipe deliveries completed on time with no problems.
Referee:
Henro Van Wyk
EPcm Contract Manager)
Tel: +61 408 338 682
3. Project Name: Victorian Desalination Project-Transfer Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure pipeline from Wonthaggi Desalination Plant Wonthaggi to
Cardinia Reservoir.
84km of 1930mm SINTAKOTE Ball & Socket Joint MSCL pipe.
December 2009 to December 2010.
Aquasure Consortium (Thiess, Degremont (Suez Environment) and Macquarie
Capital)
None to date (May 2011).
Pipe deliveries completed on time with no problems.
Referee:
Jason Spears
(Project Director Aquasure Pipeline Joint Venture)
Tel: +61 418 534 483
SOLUTIUONS FOR LIFE Page 4
4. Project Name: Adelaide Desalination Plant-Transfer Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure pipeline from Port Stanvac S.A. to Happy Valley Water
Treatment Plant and Reservoir.
12km of 1575mm SINTAJOINT RRJ MSCL pipe.
February 2009 to November 2009.
SA Water.
None
Pipe deliveries all on time with no problems.
Referee:
Andrew Gambling
(Project Director McConnell Dowell-Built Environs Joint Venture)
Tel: 0407 046 504
5. Project Name: Sugarloaf Interconnector Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure pipeline from Eildon Reservoir to Sugarloaf Reservoir.
50km of 1750mm and 20km of 1404mm “SINTAKOTE” Ball and Socket Joint
MSCL pipe.
May 2008 to August 2009.
Melbourne Water.
None.
Pipe deliveries were on or before time with no problems.
Referee:
Rod Clifford (Project Director Sugarloaf Interconnector Project-Melbourne Water)
Tel: (03) 92352561
Mob: 0407 884 088
SOLUTIUONS FOR LIFE Page 5
6. Project Name: Wimmera-Mallee Pipeline Project
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a new pressurised pipeline water supply system to replace the existing
channel delivery system.
64km of 1016 outside diameter SINTAJOINT RRJ and Welded steel pipe and 30km
of 711 outside diameter SINTAJOINT RRJ and Welded steel pipe.
December 2007 to October 2009.
Grampians Wimmera-Mallee Water.
None.
Pipe deliveries were on time with no problems.
Referee:
Mr Jeff Rigby (Managing Director)
GWMWater
Tel: (03) 5382 4611
SOLUTIUONS FOR LIFE Page 6
7. Project Name: South East Queensland Water Grid
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
The South East Queensland Water Grid consists of the Northern Interconnector
Pipeline, the Southern Regional Water Pipeline, the Eastern Interconnector Pipeline
and the Western Corridor Recycled Water Scheme.
334km of SINTAKOTE steel pipe in sizes ranging from 800 to 1451 outside
diameter.
November 2006 to July 2008.
The Queensland Government.
None.
Tyco Water met all supply deadlines for each of these significant projects.
Referee:
Mr Nigel Deacon
Infrastructure Delivery Group
Department of Infrastructure and Planning
Tel: (07) 3898 0474
8. Project Name: Bayswater Power Station
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Constructed by Eire Contractors at Bayswater Power Station Muswellbrook in order
to supply additional water to the Power Station.
Approximately 4km of 1451 outside diameter SINTAJOINT RRJ steel pipe and
fittings.
Period of 8 weeks from February 2008 to May 2008.
Macquarie Generation.
None.
All pipe deliveries were on time.
Referee:
Mr Gavin Heydon (Project Manager)
Macquarie Generation
Mob: 0427 702 204
SOLUTIUONS FOR LIFE Page 7
10. Project Name: Goulburn to Campaspe Link Superpipe Project
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure transfer pipeline from the Waranga Western Channel near
Colbinabbin to connect with Coliban Water’s system at Lake Eppalock.
47km of 1124 outside diameter SINTAJOINT RRJ steel pipe.
February 2007 to July 2007.
Coliban Water.
None.
Pipe deliveries were supplied from Melbourne and Perth on time with no problems.
Referee:
Mr Rick Jackel (Project Director Infrastructure Services)
Coliban Water
Tel: (03) 5434 1222
9. Project Name: Ballarat Link of the Goldfields Superpipe
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pressure pipeline from Sandhurst Reservoir (approx. 10km SW of
Bendigo) to the White Swan Reservoir (approx. 10km NE of Ballarat).
47km of 800 outside diameter SINTAJOINT RRJ steel pipe.
March 2007 to December 2008.
Central Highlands Water.
None.
Pipe deliveries were on time with no problems.
Referee:
Mr Tony Wright (Project Director)
Central Highlands Water
Tel: (03) 5320 3100
SOLUTIUONS FOR LIFE Page 8
11. Project Name: Torrens System Upgrade Project
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Supply of a pipeline within the Torrens Linear Park, between the Torrens Gorge
Weir (off Gorge Road, Athelstone) and Gallery Road Highbury. The sites are located
in Adelaide’s north-eastern suburbs, South Australia.
3.4km of 1829 outside diameter SINTAJOINT RRJ and Welded steel pipe.
May 2007 to September 2007.
South Australian Water Corporation.
None.
First ever supply of 1800 nominal bore SINTAJOINT RRJ steel pipe into South
Australia.
Referee:
Mr Milind Kumar (General Manager Engineering and Projects)
SA Water
Tel: (08) 8204 1000
12. Project Name: Liverpool to Ashfield Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Recycled water main to provide irrigation to local parks and industry. Also used as a
diversion from the George’s River sub-main while renewals took place.
20km of 988/1067/1124 outside diameter SINTAKOTE steel pipe and fittings.
October 2006 to August 2007.
Sydney Water.
None.
Tyco Water Services were able to slip line 6km of 980 internal diameter
SINTAKOTE steel pipe for this project.
Referee:
Mr Adam Binning (Project Manager)
Leighton Contractors
Tel: (02) 9414 3922
SOLUTIUONS FOR LIFE Page 9
13. Project Name: Burdekin to Moranbah Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Water supply pipeline from Burdekin to Moranbah.
172km of 813 outside diameter SINTAJOINT RRJ and Spherical Slip-In welded
joint steel pipe.
Over 10 months finishing October 2006.
SunWater.
None.
Tyco Water was able to supply 5.5km of pipe per week.
Referee:
Mr Tim Donaghy (Senior Project Manager)
SunWater
Tel: (07) 3120 0196
14. Project Name: Kwinana Desalination Connection
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Pipework connecting the Desalination plant into the IWSS.
23km of DN1200/DN1400 outside diameter SINTAJOINT RRJ and Spherical
Slip-In welded joint steel pipe.
October 2005 to March 2006.
Western Australia Water Corporation.
None.
No project problems, completed on time.
Referee:
Mr Mark Oliver
Western Australia Water Corporation
Tel: (08) 9420 2420
SOLUTIUONS FOR LIFE Page 10
15. Project Name: Stag Creek Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Raw Water supply pipeline for Callide Power Station.
8km of 800 outside diameter and 7km of 960 outside diameter SINTAKOTE steel
pipe.
April 2005 to July 2005.
SunWater.
None.
Pipe delivered on time with no issues.
Referee:
Mr Russell Paton
SunWater
Tel: (07) 3120 0201
SOLUTIUONS FOR LIFE Page 11
16. Project Name: Clarence Valley & Coffs Harbour Regional Water Supply Scheme – Stage 1B
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Water supply pipeline for Clarence Valley & Coffs Harbour NSW.
15.6km of 960 outside diameter SINTAKOTE steel pipe.
November 2003 to July 2004.
Clarence Valley Council.
None.
Pipe delivered on time with no issues.
Referees:
Mr Jim Fear
North Coast Water
Tel: (02) 6645 3300
Mr David Tarrant
Dept. of Commerce
Tel: (02) 6648 5901
17. Project Name: Mt Miller Pipeline
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Gladstone Area Water Board Raw Water supply pipeline.
17km of DN900 SINTAKOTE steel pipe.
July 2003 to September 2003.
Gladstone Area Water Board.
None.
Pipe delivered on time with no issues.
Referee:
Mr Alan Edgerton
Tel: (07) 4976 3000
\
SOLUTIUONS FOR LIFE Page 12
18. Project Name: Clarence Valley & Coffs Harbour Regional Water Supply Scheme – Stage 1A
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Water supply pipeline from Clarence Valley to Coffs Harbour NSW.
34.5km of 660 outside diameter SINTAKOTE steel pipe.
April 2002 to September 2002.
Clarence Valley Council.
None.
Contract period was only 21 weeks and Tyco Water supplied all pipes within the
specified period with no time extensions required.
Referees:
Mr Jim Fear
North Coast Water
Tel: (02) 6645 3300
Mr David Tarrant
Dept. of Commerce
Tel: (02) 6648 5901
19. Project Name: Stirling Trunk Main
Description and Location:
Quantity, Size and Type:
Supply Period:
Principal:
Contract Problems:
Remarks:
Water supply pipeline from Stirling Dam to Tamworth Reservoir.
106km of DN1400 SINTAJOINT RRJ and Spherical Slip-In welded joint steel pipe.
Over 18 months finishing January 2001.
Western Australia Water Corporation.
None.
A jointly funded investigation was conducted into the friction effects on buried
SINTAKOTE steel pipelines and resulted in a significant reduction in the number of
welded joints required for thrust restraint.
Referee:
Mr John Wallis
Western Australian Water Corporation
Tel: (08) 9420 2420